report he

Embed Size (px)

Citation preview

  • 7/31/2019 report he

    1/12

    HEAT EXCHANGER

    Sample calculation for exchanger E-101

    From the calculation;

    Area, A = 55.371 m2

    Pressure, P = 240 bar

    MOC tube = SS ; MOC=Material of construction, SS= Stainless steel

    MOC shell = SS

    Estimation of Cp and Fp:

    1. From table A-4 (multiple pipe):

    B1 = 1.74

    B2 = 1.55

    2. From table A-2 (for P=240 barg):

    C1 = 13.1467

    C2

    = -12.6574

    C3 = 3.0705

    3. Calculate value Fp using equation below:

    log Fp = C1 + C2 log(P) + C3 [log(P)]2

    log Fp = 13.1467

    12.6574 log (240) + 3.0705 [log (240)]2

    Fp = 2.61

    4. Estimation of purchased cost, Cp0:

  • 7/31/2019 report he

    2/12

    From figure A.5;

    Cp0/A =

    Cp0(2001) = $ 19379.85

    5. Estimation of material factor, FM:

    Since material of construction for both shell and tube is SS and multiple type, therefore:

    From Table A.3: Identification number = 5

    Thus, from figure A-18: Material factor, FM = 2.75

    Therefore,

    CBM = Cp0 (B1 + (B2 x Fp x FM))

    CBM = 19379.85 x (1.74 + (1.55 x 2.6 x 2.75)) = 249324.19

    Bare Module Cost,

    CBM (2012) = CBM (2001) [ I2 (2012) / I1 (2001) ]

    Where:

    I1 = cost index for year 2001 = 397

    I2 = cost index for year 2011 = 643.11

    For $1 = RM 3.1645 (average currency for year 2012)

    So, Bare Module Cost,

    CBM

    (2012) = $249324.19 (643.11/ 397) = $ 403886.35

    Bare Module Cost, CBM (2012) in Malaysia currency = RM1278098.36

  • 7/31/2019 report he

    3/12

    Table: Total price for all heat echanger:

    Equipment Area, m2 Purchase cost,

    Cp0(2001) ($)

    Bare module cost,

    CBM (2012) ($)

    Bare module cost,

    CBM (2012) (RM)

    E-101 55.37 19,379.85 403,886.35 1,278,098.36

    E-102 66.79 22,707.92 473,245.10 1,497,584.11

    E-103 46.26 15,726.70 327,752.77 1,037,173.64

    Total 1,204,884.22 3,812,856.11

    Reactor

    From the chemical and mechanical design calculation;

    Volume, VTotal = 3.534 m3

    Pressure, P = 240 bar

    Materials of Construction = stainless steel

    Estimation of Cp:

    The value for K1 and K2 and K3 are referred to the table A.1 in the Turton (2009) page 910 and

    the value are:

    K1 = 4.7116

    K2 = 0.5521

    K3 = 0.0004

    For V=3.534m3

    log10Cpo = 4.7116 + 0.5521log10(3.5534) + 0.0004[log10(3.534)]

    2

    = 4.7116 + 0.3027 + 0.0004

    = 5.0147

    Cpo = 103,442.7

  • 7/31/2019 report he

    4/12

    Cpo (2011) = 103,442.7(622/397) = $ 162,067.8

    log Fp = C1 + C2 log(P) + C3 [log(P)]2

    For conversion vessel, the operating pressure is 2.2 barg. From Table A.2, C1=C2=C3=0 and

    from equation A.3 (Turton, 2009), then Fp= 1

    Bare Module Cost:

    CBM = 162,067.8 (2.25+ (1.82) (3.1)(1))

    CBM = $ 1,279,039.10

    The currency $ 1 = RM 3.02

    So, the value from Bare Module Cost is in US dollar ($) must be converted into Ringgit Malaysia

    (RM)

    $ 1,279,039.10 = RM 3,862,698.00

    As conclusion, the price for the reactor is RM 3,862,698.00.

    Vessel

    From the chemical and mechanical design calculation;

    Volume, D = 1.5 m

    Height = 3.0 m

    Pressure, P = 240 bar

    Materials of Construction = stainless steel

    By Using CAPCOST software:

    Cpo (2011) = RM 11,800

    CBM (2011) = 1,530,000

  • 7/31/2019 report he

    5/12

    Compressor

    1) Fluid power = 4850.7 kW

    MOC = SS

    Compressor type = Centrifugal

    Cpo (2011) = RM 1,630,000

    CBM (2011) = 9,390,00

    2) Fluid power = 5393.1 kW

    MOC = SS

    Compressor type = Centrifugal

    Cpo (2011) = RM 1,630,000

    CBM (2011) = 9,390,00

    TOTAL CAPITAL INVESTMENT

    Equipment Specification

    Base Bare

    Module Cost

    (RM)

    Heat Exchanger 1 E -100 712,342

    Heat Exchanger 2 E -101 1,804,200

    Heat Exchanger 3 E -102 58,227

    Heat Exchanger 4 E -103 1,854,825

    Component Splitter 1 X - 100 123,040

    Component Splitter 2 X 101 123,040

    Component Splitter 3 X 102 123,040

    Reactor CRV-100 2,612,383Separator V-100 53,202

    Pump 1 P-101 94,008

    Pump 2 P-102 68,948

    Pump 3 P-103 68,948

    Compressor 1 K-100 154,060

  • 7/31/2019 report he

    6/12

    Contingency and Fee (8%)

    Contingency = Total Bare Module Cost 0.15

    = RM 1,199,439.75

    Fees = Total Bare Module Cost 0.08

    = RM 639,701.2

    Total Module Cost, TMC = Total Bare Module Cost + Contingency + Fees

    = RM 9,835,405.95

    Auxiliary Facilities (10%)

    Site Development = Total Bare Module Cost 0.05

    = RM 399,813.25

    Auxiliary Buildings = Total Module Cost 0.04

    = RM 319,850.6

    Offsite Facilities = Total Module Cost 0.21

    = RM 1,679,215.65

    Auxiliary Facilities = Site Development + Auxiliary Buildings +

    Offsite Facilities

    = RM 2,398,879.5

    Grass-roots capital (GRC) = Total Module Cost + Auxiliary Cost

    = RM 10,395,144.5

    Compressor 2 K-101 146,002

    Total Bare Module Cost (RM) 7,996,265

  • 7/31/2019 report he

    7/12

    Labor Cost

    The operating labor requirement for chemical processing plants is given by:

    NOL = (6.29 + 3.17P2 + 0.23 Nnp)

    0.5

    The value of Nnp is given by:

    Nnp= Equipment

    Where:

    NOL The number of operators per shift

    P The number of processing steps involving the handling of particulate solids.

    Nnp The number of non particulate processing steps handling steps.

    Type of Equipment No. Of Equipment NNP

    Heat Exchanger 4 4

    Reactor 1 1

    Splitter 3 3

    Vessel 1 -

    Pump 3 -

    Compressor 2 2

    Total 10

    NOL = (6.29 + 3.17P2 + 0.23 Nnp)

    0.5

    = 2.93

  • 7/31/2019 report he

    8/12

    Event Cost

    onsite

    Purchased Equipment Installation

    Instrumentation and Control

    (installed)

    Piping (installed)

    Electrical and Material (installed)

    30 % GRC

    15 % GRC

    30 % GRC

    8 % GRC

    RM 3,118,543.75

    RM 1,559,271.70

    RM 3,118,543.75

    RM 831,611.60

    offsite

    Building

    Yard Improvements

    Service Facilities

    Land

    10 % GRC

    1 % GRC

    5 % GRC

    2% GRC

    RM 1,039,514.50

    RM 103,951.40

    RM 519,757.20

    RM 207,902.90

    Total RM 10,499,096.80

    Event Cost

    Engineering and supervision

    Construction Expenses

    Contractors

    Fee

    Contingency

    5 % GRC

    8 % GRC

    1.5 % GRC

    10 % GRC

    RM 519,757.2

    RM 831,611.60

    RM 155,927.20

    RM 1,039,514.50

    Total RM 2,546,810.50

    Cost (RM)

    1) 1 operator per month = 1,800

    2) 1 operator per year = 21600

    (including bonus + allowance)

    Direct Cost

    Indirect Cost

  • 7/31/2019 report he

    9/12

    Fixed Capital Investment (FCI)

    Working Capital

    Start Up Cost

    (FCI = GRC + Total)

    12 % FCI

    8 % FCI

    RM 23, 441, 051.80

    RM 2,812,926.20

    RM 1,875,284.10

    Total Capital Investment (TCI) RM 28,129,262.10Total = Direct+Indirect = RM 13,045,907.30

    Assumption

    1) Plant performed: 3 shifts per day

    2) Plant is tunning 24hours per day: 1 day

    3) Maintainace day per year: 30 days

    4) Operation day per year: 335 days

    5) Minimum day for operator rest: 14 days

    6) Week for 1 operator work: 48 weeks

    7) Shift needed for a plant in year: 1005 shift/year

    8) 1 operator can obtained shift: 230 shift/year.operator

    NON :

    Operating labor cost, COL:

    COL = NOL x NON x PO

  • 7/31/2019 report he

    10/12

    Manufacturing Expenses Cost (RM/yr)

    Cost PerProduction(RM/kg)

    Direct Production

    Cost

    Raw Materials

    Utilities & Land

    Water, Electric & Land

    Miscellaneous

    Maintenance andRepairs

    Operating Supplies

    Operating Labor

    Direct Supervision &

    Clerical Labor

    Laboratory Charges

    Patents and Royalties

    Indirect Production

    Cost

    Local Taxes

    Insurance

    Plant Overhead

    2 % FCI

    0.5% of Maintenance

    and Repairs

    0.2% of maintenance

    and repair

    10 % of Operating

    Labour

    15 % of Operating

    Labour

    0.01% FCI

    1 % FCI

    1% FCI

    50 % of Operating

    labor

    259, 290. 000

    32,590,000.00

    468,821.03

    2,344.1

    937.60

    93.76

    140.60

    2344.10

    234,410.5

    234,410.5

    468.8

    3.11

    3,342.60

    48.08

    0.2404

    0.0962

    0.0096

    0.0144

    0.2404

    25.3825

    25.3825

    0.0508

    Total Manufacturing Expenses, AME 292,823,971 30,033.22

  • 7/31/2019 report he

    11/12

    Total Manufacturing Expenses, AME Cost (RM/yr)

    Cost perproduction(RM/kg)

    Administration Cost

    Distribution & Selling

    Expenses

    Research &

    Development

    25 % of PlantOverhead

    10% of FCI

    3% of FCI

    1,049,310.60

    3,497,702.00

    1,049,310.60

    76.1474

    253.8245

    76.1474

    Total General Expenses, AGE 5,596,323.19 406.1192

    Total ProductionCost, APC

    Depreciation, ABD

    APC = AME + AGE

    (excludingdepreciation)

    10 % FCI

    2,141,397,014.99

    3,497,702.00

    155398.9126

    253.8245281

    Total Expenses, ATE ATE = APC + ABD 2,144,894,716.99 155652.7371

    price for product

    Urea RM 21 /kg

    Raw material usage

    Urea 9750 kg/hr

    Annual sales for product RM 204,750 /yr

    Total revenue from

    sales

    Net annual profit,

    ANP

    Product

    Total Revenue

    535,125,100.00

    45,248,845.50

    54,884.62

    4,640.90

  • 7/31/2019 report he

    12/12

    Income taxes

    Net annual Profit,

    ANNP

    Rate of Return

    30% ANP

    ANPIncome Taxes

    (ANNP-ABD)/TCI x

    100%

    13,574,653.65

    31,674,191.85

    125..03%

    1,392.27

    3,248.64

    Cash flow

    Year of construction 3 years

    Plant Life 22 years

    Working Capital RM 2,812,926.20

    TCI

    Total Annual RM 28,129,262.10

    Sales RM 535,125,100.00

    Total Expenses, ATE RM 2,144,894,716.99

    Bank Loans

    1st year = 10% of TCI

    2nd year = 45% of TCI

    3rd year = 45% of TCI