ACCU A.Rozanov 12.09.2007 1
Report from Accommodation Facilities meeting
Outlook
• Accommodation Facilities meeting 10.09.2007• Patrick Geeraert, Chris Onions, Francesco Navarria, Alexandre Rozanov,
Gerard Fournier, Mauro Nonis, Bertrand Salami, Michael Poehler, Jose Salicio
Diez
• Scope of the meeting is increased from “Hostel
Fund” to include both hostel and office situation of
CERN users• New hostel in building 41 is operational since June
and reimbursement of the loan should be finished in
2008
ACCU A.Rozanov 12.09.2007 2
Report from Accommodation Facilities meeting CERN Hostels (M.Nonis)
Buildings
Single +
washbasin
Single +
washbasin + Toilet
Single +
Bathroom
Double +
washbasin
Double +
Bathroom
Handicapped
FlatTotal beds
38 56 30 60 26 25 2 doubles 1 double 25439 _ _ 92 _ 24 _ _ 140
41 _ _ 91 _ 51 single et 1
double_ 104
Total 56 30 243 26 5 4 1 498
Price
27 CHF Per
room
48 CHF Per
room
58 CHF Per
room
14 CHF Per bed
64 CHF for
1 person
77 CHF for 2
persons
58 CHF Per room
For Single
64 CHF – For double
90 CHF the flat
with lounge, kitchen, bathroo
m
ACCU A.Rozanov 12.09.2007 3
Report from Accommodation Facilities meetingExternal Hostels (M.Nonis)
• CERN has an agreement with a private hostel in St Genis (France). • CERN looks after the reservation; all other activities are not under
Housing Fund’s mandate.
Single + Washbasin
Single + washbasin +
Toilet + shower
Number of beds
60 21
Rate 18.1 euros 26.40 euros
ACCU A.Rozanov 12.09.2007 4
Report from Accommodation Facilities meeting Occupancy rates (M.Nonis)
Buildings 38 and 39 only
ACCU A.Rozanov 12.09.2007 5
Report from Accommodation Facilities meeting
M. NONIS TS/FM – CERN Accommodation Facilities meeting – 10.9.2007
BOOKING REQUESTS PROCESSING TIMES (M.Nonis)
September 2006
December 2006 –
January 2007June 2007
Requests received per day100 400 200
Requests received per day (beginning of the month)
250 780 250
Feed back from Reception2 days 7 days 3 days
Feed back from Reception (beginning of the month)
3 days 15 days 5 days
ACCU A.Rozanov 12.09.2007 6
Report from Accommodation Facilities meeting
Reservation type / categoryMaximum reservation
delay1
Maximum duration for one
single stay
Maximum duration of stay, within
calendar year
Maximum number of beds per
visitorAcceptation
criteria BuildingPriority
over other reservations
Single persons 60 days 60 days 60 days 1 or 2 --- 38, 39, 41
Summer students 60 days 90 days 90 days 1Following list from the HR
Dept.38
Employed members and associates 2 60 days 60 days ----- 1 or 2 Concerned
Department 38, 39, 41
Students (others) 60 days 60 days 60 days 1Request from
CERN University’s responsible
38, 39
Selection board candidates 60 days 1 à 2 days --- 1 Given from the HR Dept. 38, 39, 41
Council members 12 months 60 days 60 days 1 or 2Via the Council
Secretariat39
Visits 60 daysFrom the day before to the day after the
visit---- 1 or 2 List given by
the organiser 38, 39, 41
School groups (official visits) 60 daysFrom the day before to the day after the
visit---- 30 % 3 List given by
the school 38
Experimental weeks 4 / workshops 4 / conferences 4 / VIP visits
12 monthsFrom the day before to the day after the conference
60 days 30 % 3List given by
the secretariat or the organiser
38, 39, 41
1 – before arrival date2 – only at beginning of contract3 – of the total capacity per room type4 – officially organised by CERN
Building 38 : 199 rooms, 250 bedsBuilding 39 : 116 rooms, 140 bedsBuilding 41 : 98 rooms, 104 beds
Draft for discussion of RESERVATION RULES (M.Nonis)
ACCU A.Rozanov 12.09.2007 7
Report from Accommodation Facilities meeting
Possible improvements in hostels
• Sliding window reservations should avoid peaks in delays near 1 of the moth and beginning of the year• Clear written rules for block reservation after discussion with ACCU• Clear written rules for current day (waiting) list• Reducing the block reservations from 30% to 25%???, 20%???,…. • Monitoring of the number of refusals and the number of unsatisfied requests in daily (waiting) lists during two months (October-November 2007)• Request from hostel management to give the estimation of the number of beds needed in the hostel during LHC start-up 2008-2009 from ACCU side• Possibility to increase the number of beds by moving reception, TV rooms, cuisines to building 222 (project to be discussed with ACCU)• Restart efforts to get contract with one more external hotel/hostel• Reducing delays of reservations reply: 48h request from ACCU side, 3 days current estimate from hostel side • WWW booking (next slide)
ACCU A.Rozanov 12.09.2007 8
Report from Accommodation Facilities meeting
WWW based booking
• Agreed that it is technically possible and should be introduced• It can not be on 100% of beds as some visitors do not have credit cards needed in obligatory field of WWW interface and block reservations• Abuses should be limited by credit card guarantee and fees for late cancellations/modifications (details to be discussed)• In case of cancellations forced by official changes of schedule, the facility of payment of cancellation fees by team leader account should be available• WWW reservations will apply to fixed % of beds. Initial % can be determined from experimental number of credit card users in the past. • Ultimately the WWW booking delay should be negligible (at start up ~ 3 days delays are possible)• Old non-WWW booking will still work in parallel for remaining beds
ACCU A.Rozanov 12.09.2007 9
Report from Accommodation Facilities meeting
Office situation
• Request to increase the number of offices by 500 places in 2006 for LHC experiments• 200 places recuperated for LHC experiments in existing buildings in 2006/2007• Discussions of the extension of the building 40 for 300 places with eventual delivery in 2010 . To be discussed with LHC experiments concerned (ATLAS, CMS).• Is there a need for new evaluation of the office space needs in LHC start-up in 2008-2009 ?
ACCU A.Rozanov 12.09.2007 10
Report from Accommodation Facilities meeting
Conclusions
• Feedback for Blocking Reservation rules will be needed• Feedback for WWW reservation rules will be needed• Transparencies of Mauro Nonis will be attached to the Agenda (these are only preliminary material for discussion)• Estimations of the need of beds (offices) in 2008-2009 will be probably needed
ACCU A.Rozanov 12.09.2007 11
Report from Accommodation Facilities meeting