27
0 CIV498 – Group Design Project CIBC Bank College and Spadina Authors: Brett Sagert 997233845 and Shuliang (Peter) Sun 996007440

Report - Building Science Capstone Project - CIBC Bank Retrofit

Embed Size (px)

DESCRIPTION

Report of CIBC energy retrofit project. Evaulated range of design alternatives to lower building's energy and water consumption. Used LCA to evaluate sustainability of various proposals in addition to economic analysis.

Citation preview

  • 0

    CIV498 Group Design Project CIBC Bank College and Spadina

    Authors: Brett Sagert 997233845 and Shuliang (Peter) Sun 996007440

  • 1

    Contents Project Description........................................................................................................................................ 2

    Site Context ............................................................................................................................................... 2

    Climate ...................................................................................................................................................... 2

    Local Considerations ................................................................................................................................. 3

    Current Condition ..................................................................................................................................... 3

    HVAC ......................................................................................................................................................... 3

    Business Objective .................................................................................................................................... 4

    Final Condition .......................................................................................................................................... 4

    Sustainability Measures ................................................................................................................................ 5

    Energy, Cost and Emissions ....................................................................................................................... 5

    Photovoltaics ......................................................................................................................................... 5

    Passive Solar Lighting and Heating ....................................................................................................... 6

    Non-Passive Lighting ............................................................................................................................. 8

    Water Management .................................................................................................................................. 9

    Green Roofs .............................................................................................................................................. 9

    Rainwater Capture .............................................................................................................................. 10

    Energy Efficient Water Fixtures .......................................................................................................... 10

    Embodied Energy of Retrofits ................................................................................................................. 11

    General Embodied Energy and Life Cycle Analysis ............................................................................. 11

    Window Retrofits ................................................................................................................................ 12

    Energy and Economic Analysis .................................................................................................................... 14

    Base Load Summary ................................................................................................................................ 14

    Photovoltaics........................................................................................................................................... 16

    Passive Lighting and Light Shelves .......................................................................................................... 17

    Internal Lighting ...................................................................................................................................... 18

    Cisterns, Toilets and Faucets................................................................................................................... 18

    Green Roofs ............................................................................................................................................ 21

    Argon Filled Windows ............................................................................................................................. 21

    Economic Payback for All Retrofits ......................................................................................................... 22

    References .................................................................................................................................................. 25

  • 2

    Project Description

    Site Context

    The main objective for this

    project is to do a retrofit on a retail

    store or establishment and determine

    the effectiveness of the retrofit based

    on sustainability measures discussed

    later. Our group has decided to do a

    retrofit of the CIBC bank located on the

    North West corner of College and

    Spadina at 268 College Street.

    Figure 1 CIBC Location1

    Climate

    The intersection of College and Spadina can

    be considered to just be on the outskirts of

    Torontos core downtown area. The average

    summer temperature is 15C and the average

    winter is 0C. The daily sunlight hours average five

    hours per day over a given year see Figure 22.

    Monthly average rainfall is 60 mm with a peak

    average in August and September of 80 mm per

    month. Toronto also receives a small amount of

    snow during the winter months, with an average of

    30 mm per month.

    Figure 2 Torontos Climate2

  • 3

    Local Considerations

    This site is located on one of the busiest intersections in the downtown Toronto area, due to the

    locations of Chinatown to the south, University of Toronto St. George Campus to the north and east and

    Little Italy to the west. The chosen site makes this bank prime real estate for walking traffic from all

    directions. The site is also adjacent to two of the main streetcar lines that run through Toronto, the

    Spadina 510 line which runs North-South3 and the College 506 line that runs East-West4. This makes

    access to the site through public transportation easy and accessible. The bank also provides its

    customers with temporary parking spots in the parking lot located behind the bank as well as bicycle

    parking in front of the east entrance.

    Current Condition

    Based on the location and the aesthetic look of the building we concluded that it was built

    sometime in the early 1980s. The building has a total of three entrances: two glass entrances, located

    on the south and east faades, for customers and one opaque metal entrance, on the west faade, for

    the employees. The exterior of the building is stucco and concrete tiles with the two customer entrances

    having a high percentage of glass (around 40% glass and framing). The northern faade is shared with

    the building to the north. The roof is a typical concrete roof with a simple stormwater management

    drainage system that drains to the sewers.

    During the summer months the southern faade and parking lot are shaded partially by the

    trees planted along the sidewalk along College St. A small percentage of the roof is shaded due to the

    cover of the trees from the neighbouring building to the north. During the winter months these trees

    lose their leaves and allow for solar heat gain through windows. The bank currently has no lighting

    schedule and all of the lights are either on when the bank is in operation or off when closed, except a

    few outdoor lights for security reasons.

    HVAC

    The heating is controlled by a furnace with thermostat set temperatures of

    and indoor design temperatures of

    ( . The cooling is controlled by DX coils with cooling with thermostat temperatures of ( )

    to ( with design temperatures indoor of to supply of . The cooling

    unit size was estimated at 5.5-7.5 tons with air flow set to 0.5 cfm/sqf.

  • 4

    Figure 3 Graphical Representation of HVAC System.

    Business Objective

    The main objective of CIBC is to focus on providing its clients with banking and wealth

    management strategies. While these clients are visiting the bank they need to feel comfortable and

    welcome. CIBC is also committed to helping make a difference on a community level by investing

    millions in projects all across Canada5. Sustainalytics and MacLeans have both ranked CIBC among the

    50 most socially responsible corporations in Canada. By showing an interest in helping to protect the

    environment by retrofitting their buildings, they can help to attract more customers and investors who

    share similar goals6.

    Final Condition

    The final design will showcase three major areas of retrofication: the roof, the washroom

    facilities and the windows. On the roof we will mount a solar voltaic system that will help generate

    electricity for the building. Additionally, the roof will be used to collect rainwater and provide the site

    with 100% self-reliance in terms of water consumption. All of the collected rainwater will be filtered and

    used in the new washroom facilities. Lastly improvements will be made to the existing windows which

    will help to allow more natural lighting and reduce electrical consumption.

  • 5

    Sustainability Measures

    For this project we have decided to focus on three main measures of sustainability to determine

    the effectiveness of our potential retrofits. The measures are as follows: cost, water usage, and

    embodied energy. Cost in any project is often the key driving factor to the owner; if the project is not

    economically sustainable it will likely be rejected. Typically the project would be accepted if the costs

    can be recouped by the savings over a defined period of time, as set by the owner of the building. The

    team wanted to help the bank achieve self-sufficiency in water usage by utilizing the rainwater falling on

    the rooftop. To help with the management of the new source of water, efficient fixtures would be added

    to the sites facilities to reduce overall consumption. An additional benefit would be seen by Torontos

    storm sewers, as the rooftop runoff from the bank will be captured and consumed, saving energy spent

    on waste water treatment. When trying to achieve a sustainable building retrofit, the team felt it

    necessary to analyze the retrofits from a life cycle perspective. By quantifying the energy that goes into

    the material, construction, operation, maintenance, renovation, demolition and disposal, we would be

    able to make an informed decision. Also this will allow the team to empirically compare one retrofit

    versus another and gauge the sustainability of the different options.

    The final decisions for the retrofit projects will be chosen if and only if they can reasonably and

    measurably show that they are energy saving and cost beneficial. Additionally, we will look into retrofits

    that will positively impact the way in which water management or waste water management is handled.

    In order to promote the life cycle sustainability of the site, we also want to consider the impacts of the

    embodied energy that these projects have on the environment.

    Energy, Cost and Emissions

    Photovoltaics

    Photovoltaics can be used to reduce the peak energy demand of the building consumption, due

    to the fact that the time of energy consumption aligns with the power generation. Figure 5 on the next

    page depicts a study done on photovoltaic demonstrating this effect. In Ontario, electricity users are

    paying a premium of 1.5 billion dollars a year (1 cent/kWh) to make sure there is electricity for peak

    demand7. By lowering the consumption from the grid at the time when electrical prices are high, we will

    be able to save on energy costs.

  • 6

    Figure 5 - Power Generation vs. Time of Day

    Note: Location , comparable to Toronto (Yoo, Seung (2011), Han Yang University )

    The photovoltaic setup considered in this retrofit is made by Siemens Solar Industries. The

    average cost of an installed solar panel is approximately 5000 $/kW. The energy output of the solar

    system will depend on annual insolation. In Toronto this number comes out to be about 1200 kWh/ (kW

    installed capacity)8. When looking at the embodied energy of crystalline silicon, we see it takes about

    5598 kWh equivalent of energy to manufacture 1 kW of silicon panels9.

    Passive Solar Lighting and Heating

    Passive Solar is a term referring to heat gain from natural radiation from the sun, without the

    use of mechanical or electrical processes. There are two main ways in which the thermal energy stored

    in the suns rays can be transferred into the building. The sunlight can directly enter the building through

    surfaces that are transparent such as windows, glass doors and skylights, or the sunlight can be used to

    heat up a thermal mass which then radiates energy into the building through long wave radiation10.

    One of the prominent features of the CIBC bank is that it has large windows on the east and

    south faade of the building. These windows allow significant amounts of insolation into the interior

    during the heating season and, if not prevented, allow heat into the building during the cooling season.

    The windows act as significant source of lighting for building throughout the year. According to the solar

    isolation design tool, assuming a solar heat gain factor of 0.75, the annual solar isolation entering the

    windows at the bank is estimated to be about 95,000 ekWh. Below is a table estimating monthly solar

    gain from windows.

  • 7

    Figure 6 Monthly Solar Heat Gains from Windows

    Given the project is located in Toronto, it is important to note that our climate consists of two

    distinct and diverse seasons: a heating season during the winter months, where we require as much

    solar heat gain as possible, and conversely, a cooling season during the summer months, where the

    need is to minimize the heat gain.

    In order to prevent gaining heat in the summer months, there are numerous successful methods

    in which we can prevent heat entering the building when we do not want it. We will review the

    efficiency of overhangs, deciduous trees, window blinds, light shelves, and tinted window panes.

    Overhangs are an effective way in which we can use the angle of the sun to our advantage.

    During the summer months, when we want to avoid heat entering into the building, the sun is at its

    highest point and during the winter months it is at its lowest point. By adding an overhang above the

    windows, we are able to block the incoming solar rays during the summer, and allow them in during the

    winter.

    A second efficient method is provided by nature itself. Deciduous trees offer an opportunity to

    use different seasons our advantage. During the summer months, the trees leaves block the incoming

    solar radiation and absorb the heat gain, providing a noticeably cooler effect. During the winter when

    the trees have shed their leaves, light is allowed to pass into the building11.

    0 2000 4000 6000 8000 10000 12000

    Jan

    Feb

    mar

    Apr

    May

    Jun

    Jul

    Aug

    Sep

    Oct

    Nov

    Dec

    Jan Feb mar Apr May Jun Jul Aug Sep Oct Nov Dec

    Series1 4636 5442 8131 9403 9717 7724 10542 9583 9915 8384 6323 4866

    Monthly Solar Gains from Windows

  • 8

    Window blinds, either manual or sensor operated, also provide the building with the ability to

    prevent light and direct solar radiation to enter into the building. A main disadvantage of a conventional

    blind system is that only two options are available: when blinds are closed, you have solar heat gain or

    when blinds are open, light enters into the building. Exterior blinds can be used to provide shading, but

    they do not allow as much long wave radiation into the building. Interior blinds, if highly reflective, can

    reduce the internal heat gain through the windows by 45%12. Blinds can also be designed to allow for

    the top half of the window to reflect the light up back into the celling while still blocking the lower part

    of the window from receiving solar energy.

    Light shelves can be a useful means for allowing natural light to be dispersed through the

    building. These shelves work by reflecting the incoming solar rays onto the celling of the building, thus

    lighting up more area. Unfortunately, these shelves do not reduce the amount of solar heat gain for the

    building, as they only disperse the light. Depending on the given angle of the sunlight and the light shelf,

    we can see illumination from 20 up to 100 times the unit area of the shelf itself. Not only does this help

    to spread the light around, it also help to reduce the concentrated effects of the suns radiation13.

    Tinted window glass provides another way in which you can adjust the amount of sunlight

    entering the building through windows. By tinting the glass surface using a sensor, you are able to allow

    block the incoming solar radiation reducing the incoming solar radiation significantly. This can be a very

    useful process during the summer time when we are aiming to reduce the incoming solar radiation14.

    All of these methods are simple and viable option for reducing the energy consumption for the

    building in a year. In order to determine which of these options or combination of these options we

    would choose, we utilized a decision matrix tree. The decision matrix tree took into account the cost of

    the retrofit, the amount of light provided during the summer and winter months, as well as the heat

    gain from the sun during the summer and winter months.

    Non-Passive Lighting

    Currently the building has rows of fluorescent tubing to provide lighting for the interior of the

    building as well as task lighting at the bank tills and individual office spaces. The two customer entrances

    of the building use incandescent bulbs to provide light 24 hours a day for safety purposes. In order to

    reduce the electrical consumption of the building, we plan to replace the existing interior lights and

    exterior with LED lights. This will reduce the electrical consumption of the interior area by half and the

    exterior area by ten times the current consumption. The reason for this large reduction in electrical

  • 9

    consumption is the fact that for the same amount of light LEDs require 50% less energy than CFLs and

    require 90% less energy than incandescent light bulbs.15 It is important to note that LED lights produce

    slightly less heat than CFLs, so there are minor savings in the summer and conversely, in the winter,

    there would be a slight increase in heating cost. The average life span of a LED bulb is six times more

    than CFLs, meaning the bank will have to replace them less often.

    To further lower the amount of energy consumed by the building, installing sensors on the

    reaming non-passive light sources will effectively maximize natural lighting, and deliver significant

    savings. Using the sensors, we will provide the minimal necessary light required for the bank at any one

    given time, with the option to turn on more lights if needed.

    Water Management

    Green Roofs

    Green roofs provide numerous amounts of benefits for a building other than just an

    aesthetically pleasing site. Toronto is the first North American city to have a bylaw requiring the

    construction of green roofs on new development erected after 2009. Although the retrofit for the CIBC

    bank will not be considered a new development and therefore would not force a green roof, we felt it

    necessary to still consider it to be a potential retrofit.

    Figure 7 Layer Breakdown of a Green Roof

    The numerous benefits of green roofs include an increased R value of the rooftop, as well as a

    noticeable reduction of urban heat island effect. Green roofs can be divided into two categories:

  • 10

    extensive and intensive green roof. Extensive green roof have a thin layer of vegetation on top of the

    rooftop and can be easily installed in modules. Intensive green roofs on the other hand have a thicker

    layer of vegetation that can act like a park. This installation type usually requires structural modification

    in order to support the new load; considering this factor, the team will only analyze the potential of

    implementing an extensive green roof.

    Currently, without a green roof during the summer, the building absorbs solar radiation and

    transfers a portion of that heat into the building, thereby increasing the buildings cooling load. With a

    green roof, the evaporative cooling of moisture from soil and shading reduces the temperature of the

    roof. During the winter season the green roofs layers of vegetation and mediums provide additional

    insulation and reduce the buildings heating load. The urban heat island effect is minimized by reducing

    impermeable hardscape footprint and reducing the solar reflectance index (SRI) of the rooftop16.

    Rainwater Capture

    The process of capturing rainwater and reusing it for the sites main water source is an effective

    way to cut down on water costs. By sloping the roof towards a drain, we are able to capture the fallen

    rainwater in a cistern. The water is transferred from the roof through pipes to a cistern located below

    the drainage area. Once in the cistern, the water is then filtered using mechanical and natural processes.

    The now filtered water can be pumped back into the building and consumed by the utilities17.

    The captured rainwater can be reused for the buildings systems that require water. On our

    current site water is consumed in only the one bathroom and break room. If our project was to

    implement green roof technologies, then the captured rainwater could also be used for irrigation of the

    green roof.

    Energy Efficient Water Fixtures

    One of the main goals of this project is to make the site self-sufficient in water usage, so it is

    important to consider energy efficient water fixtures. Even though the site only has one small bathroom

    and one break room, the team feels that it is still important to consider the impact that inefficient water

    fixtures can have on the water consumption. We have decided to replace the existing 13 L/flush toilet

    with a dual flush toilet which will reduce the water consumption to 4.8L /flush18. Another retrofit will be

    to replace the inefficient old faucets with new high-efficiency faucets which will bring the consumption

    from 8 L/min down to 3.2 L/min19.

  • 11

    Embodied Energy of Retrofits

    General Embodied Energy and Life Cycle Analysis

    When looking at embodied energy, we will typically consider carrying out a life cycle analysis

    (LCA) to help users understand the complete energy impacts of a building retrofit.

    Traditional building retrofit products typically focus exclusively on reducing the operational

    energy of the building. The team wanted to get the complete picture of retrofit building products effect

    on sustainability. This way the team would be able to empirically compare the sustainability of two very

    different products, such as rooftop photovoltaic and green roofs. In order to create an LCA of a product,

    the system boundaries and processes need to be known, as well as how much energy is consumed at

    each stage. Level I of LCA includes the direct energy input into the construction, prefabrication,

    maintenance, replacement, demolition, and disposal of the building. Level II of the LCA takes into

    account the energy to produce the materials. Level III takes into account the energy embedded in

    production, delivery and installation of machines that are used in building materials, manufacturing and

    on-site and off-site construction processes. Level IV accounts for the energy involved in the machines

    that are utilized to produce machines as well as (of third level regression) also the consumed energy in

    their main, upstream, and downstream production processes. Figure 8 represents the four levels of LCA

    for the construction, prefabrication, maintenance, replacement, demolition/disposal of building

    products. In our study we will only focus on Level I (direct energy input) of the LCA.

    Figure 8 The Four Levels of LCA18

  • 12

    Within the 1st level of LCA the product looks at the embodied energy and operational energy.

    The embodied energy takes into account the energy involved in the raw material acquisition, processing,

    manufacturing, transportation, decommissioning, and disposal of a product. For a conventional

    buildings LCA the embodied energy accounts for approximately 2-38% of LCA20. Figure 9 illustrates the

    various processes involved in access level I of LCA.

    Figure 9 General Process of LCA

    Window Retrofits

    Currently the way the bank is set up the windows are not utilized to their fullest

    potential, as there are blinds that prevent sunlight from penetrating into the building. These

    windows are all single glazed 1/4 thick panes with a clear tint and aluminum framing. This type

    of window allowed for many different options in terms of ideas for the retrofit. These ideas

    included: double glazed with argon fill, electro-chromic tinted windows, and lastly, keeping the

    current system, making improvements to interior lighting.

    Argon can be used as a fill for double glazed windows to increase the resistance value

    and to lower the energy consumption of the building. This is done by reducing heat loss during

    winter and preventing heat from the exterior exchanging with interior during summer.

  • 13

    Electro-chromic windows utilize an electro-chromic coating that is a thin film of

    switchable material applied to the glass that can change the windows optical transmission by

    applying a small amount of voltage. This technology has the potential to reduce incoming

    insolation and to reduce the solar heat gain coefficient of the window. Research further states

    that this technology has potential to reduce up to 20% of the energy consumed by the building

    during the heating and cooling season. Research states that the payback period for electro-

    chromic windows is only 0.3 years due to the low amount of embodied energy in the product.

    Figure 10 Shows the Layers of an Electro-Chromic Window21

  • 14

    Energy and Economic Analysis

    Base Load Summary

    Figure 11 Base Load Summary

  • 15

    From the base load summary table we can see that the building consumes a total of 62,900

    ekWh a year in electrical consumption and 236,000 ekWh in Natural Gas consumption. This brings the

    total energy consumption of the building to around 300,000 ekWh which means the bank consumes an

    average of 652 ekWh/m2 which is an extremely high value. We want to reduce this value significantly

    and will do so using the retrofits explained earlier. The water consumption for the single bathroom and

    sink in a year was calculated to be 281,820 liters based on 50 people using the washroom in a given day.

    Figure 12 Electrical Consumption Breakdown

    Figure 13 Natural Gas Consumption Breakdown

    Space Cool 27%

    Vent. Fans 20%

    Pumps & Aux. 0%

    Misc. Equip. 27%

    Task Lights 4%

    Area Lights 22%

    Electricity Consumption (Total = 62,900 ekwh)

    Space Heat 99%

    Hot Water 1%

    Natural Gas Consumption (Total = 236,000 ekwh)

  • 16

    Photovoltaics The team determined that rooftop photovoltaic panels would be suitable for the site because

    the building has a large area of rooftop without any obstructions. A decision to use a ten kW system was

    make as it would be ideal based on the sites size. The team decided use the company Sanyo because it

    offers a unique HIT technology along with a fair price. Sanyo solar developed a unique technology

    named Heterojunction Intrinsic Thin (HIT) layer. It utilizes amorphous and crystalline silicon layers to

    create high efficiency solar panels. An amorphous layer is less energy intensive to make so the HIT cell

    panels have a lower embodied energy compared to that of conventional solar panels. The panels chosen

    for the site was the HIT 240 panels with rated power of 240 Watts,

    with a rated cell efficiency is 21.6%. With this setup the site will

    require a total of 42 panels grouped into six modules in order to

    obtain the 10 kW capacity. Figure 14 shows a 3-D Sketch-up drawing

    for layout of solar panels which was arranged to maximize solar gain.

    Sanyo HIT 240S

    Rated Power (S.T.C) 240 W

    Cell Efficiency 21.6 %

    Rated Power for 42 panels 10.1 kW

    Panels per module 7 ( 1.68 kW)

    Number of modules 6

    Price per panel 22 $560

    Total price (42 panels) $23,520

    Figure 14- Proposed Photovoltaic System on Roof.

    Sanyo HIT Power 240S

  • 17

    Photovoltaics

    1 kW System 10 kW System

    Embodied Energy (kWh) 5598 55,980

    Space Needed (ft^2) 100 1,000

    Area (m^2) 9.7344 97

    Energy Generated (kWh/year) 1200 12,000

    Payback Period (years)

    5

    Figure 15 Embodied Energy Payback for a Photovoltaics System in Toronto

    We determined that the total cost of the solar project would amount to 50,000$. This cost

    includes the cost of the panels, the racks, the labour for installation and renting a mobile crane for a day

    load the solar panels onto the roof.

    Passive Lighting and Light Shelves As each of the banks three faades with windows had different window sizes and qualities, we

    analyzed the three faades individually and we decided separately which was the best option or options

    for the given faade. For the eastern faade, we decided to use light shelves and blinds in the windows.

    In the morning, the blinds would be open to allow for morning sun to be reflected throughout the

    building, providing heat gain. In the afternoon, the blinds could be closed completely limiting unwanted

    solar heat gain. For the southern faade, we decided to use the existing trees in combination with light

    shelves and blinds. For both the eastern and southern faade the combination of the blinds and the light

    shelves will help to control the amount of light entering into the building. When we reviewed the

    western faade, we felt that no changes were necessary.

    By utilizing the existing windows, blinds and trees, we are able to maximize the amount of light

    entering into the building and control the interior lighting according to the level of lighting required.

    There were several potential retrofits that we could have used to increase the amount of natural lighting

    and we decided to go with adding light shelves to all of the eastern and southern faades. By using the

    light shelves in combination with the existing blinds, we will be able to control the amount of light

    entering into the building.

    In terms of retrofit items, the only addition to the site will be the light shelves along the

    windows on the eastern and southern faade. These light shelves cost 100 $/unit and for the site we

    require a total of 16 light shelves. These light shelves reduce the required lighting in the building by

  • 18

    75W/meter of the perimeter of the building. The reason for this is due to the incoming light being

    reflected onto the ceiling and refracted in a way which increases the amount of light by reducing its

    intensity. The total cost for the light shelves for the retrofit will be 1,600$ but will reduce the daily

    lighting demand by 14% as compared to that of the current blinds system23.

    Internal Lighting In order to calculate the amount of light bulbs required to light the building, it was important to

    determine the acceptable lighting levels for a bank. Based on typical lighting levels required in an office

    work space, 500 lumen/m2 is required24. This means that the banks lighting requirement is 230,000

    lumens translating to roughly 275 LED bulbs at 840 lumens per bulb. At 30$ per LED light bulb the initial

    cost to replace all of the bulbs will be 8250$; however, Energy Star is currently offering a 5$ discount on

    LED light bulbs, so the total cost could be reduced to 6875$25 26. The energy consumption for the

    buildings lighting will be reduced by 50%.

    In order to ensure that the internal lighting will not be in operation when there is an appropriate

    amount of sunlight, light sensors will be installed in the bank. These light sensors turn the lights on

    automatically when there is not enough sunlight in the room. One light sensor can cover an area of 65

    m2, which means in order to provide proper coverage for the bank, the site will require seven light

    sensors. Each of these sensors cost a total of 63$, bringing the total cost for sensors to 441$27. A

    combined energy savings for lighting sensors will reduce the banks energy consumption by 20% in the

    lighting sector28.

    Cisterns, Toilets and Faucets By having a major objective of completely taking the bank off of city water and being self-

    sufficient in terms of water consumption, it is paramount that the site be able to generate its own

    water. An ideal way to accomplish this task would be to utilize the roof of the bank as a collection

    system for rainwater and storing it in a cistern. Using the rainwater capture tool, designed by Hannah

    Wong for CIV498, we were able to determine the appropriate size for storage we would require in order

    to convert all the water consumption from city water to reused rainwater. The design tool provided an

    output stating that the maximum use of water in a month would be approximately 13.3 m3. For our

    project we decided to go with a storage tank size that was 10.0 m3. The reason behind the smaller tank

    is we will receiving far more water than we will be able to store or consume. Excess water will bypass

    the cistern and enter into the city storm sewers to be treated as if it were runoff water.

  • 19

    Figure 16 Harvested Rainwater Captured by Cistern

    Initial cost of the cistern itself is 2100$ and will result in a 100% reduction in city water

    consumption. The dimensions for the chosen cistern can be found in Figure 17 below29. We chose this

    specific cistern design for two main reasons. Firstly, this cistern met the capacity size we were looking

    for to store the sites water requirements. Secondly, the dimensions of the design were ideal for the two

    potential locations for the cistern. Given that this site is not a new development, it would make things

    difficult if we tried to place the cistern underground near the building. This means that the cistern could

    either be located between the buildings on the north-west side, if the land was owned by the bank, or

    within one of the designated parking spots for the bank, as the space would accommodate the cisterns

    dimensions.

    -5

    0

    5

    10

    15

    20

    25

    30

    35W

    ate

    r V

    olu

    me

    [m

    3]

    Time

    Harvested Water Use Gain (L)Use (L)

    Net (L)

  • 20

    Figure 17 Proposed Cistern for Site

  • 21

    To ensure that the bank consumes less water, we will upgrade the current washroom and break

    room facilities. The existing toilet will be replaced with a dual flush toilet costing 200$ and the faucets

    will also be replaced with a highly efficient faucet costing 65$ each. The savings for these upgrades will

    be seen in an overall reduction of water consumption on the site. Since all of the water will be replaced

    by captured rainwater, all of the cost savings for these three sections will be grouped together as seen in

    Figure 21. The water consumption for the new washroom and break room facilities will be 63% of the

    original consumption. Water captured in the cistern can also be used to clean the solar panels when

    needed.

    Green Roofs Using the study by Katherine Myrans (2009) we calculated the embodied energy of a green roof

    by summing up the embodied energy of the various green roof components. Next we reviewed the

    study done by Ryerson University (2005) which had estimated green roofs save about

    4.15kWh/m^2/year in the Toronto region16. We used this information to calculate the payback period of

    implementing a green roof.

    Figure 18 Embodied Energy of a Green Roof in Toronto

    Using Figure 18 we see that the payback period for a green roof with embodied energy is around

    190 years. When we compared this to the 10 kW photovoltaic system which has an embodied energy

    payback period of 5 years, we decided not to go with a green roof on the building.

    Argon Filled Windows The embodied energy was one of our main concerns in the project, so we wanted to compare

    the two types of windows. We did this by simulating each one separately in the program E-quest to see

    which saved the most energy. Below is the table comparing the embodied energy of double glazed

    clear/tint inch argon with double glazed clear/tint electro-chromic windows.

    Area (m^2) MJ

    Study(K.Myrans) 1 2,850

    Rooftop 478 1,361,588

    Total Savings (MJ/year) 7,170

    Payback Period (years)

    190

  • 22

    Study:

    ( G.Weier & Muneer)

    (E. Syrrakou, S. Papaefthimiou*, N. Skarpentzos and P. Yianoulis)

    Type Argon Electro-Chromic

    Area (m^2) ekWh ekWh

    Windows m^2 199 51

    West 3 656 169

    East 60 11,933 3,067

    South 85 16,905 4,344

    Total = (N,E,S,W) 148 29,494 7,580

    Figure 19 Argon Filled Window Comparison of Embodied Energy

    We determined the embodied energy payback period of double glazed windows and found that

    with only the argon fill the payback was 1.8 years, whereas if we added the electro-chromic property,

    the payback period became 0.3 years. However, when we did the economic analysis on replacing the

    windows, we found that it was not economically feasible, in fact, the cost of argon filled windows and

    electro-chromic windows were around 800 $/m2 without including labour costs or additional

    complexities in replacing the windows themselves. Since the eastern and southern faades have such a

    high percentage of glass the added cost makes replacing the windows uneconomical.

    Type Area (m^2) Argon Electro-Chromic

    Total = (N,E,S,W) 148 106,179 27,287

    Total Savings (MJ/year) 60,487 79,690

    Payback Period (years) 1.8 0.3

    Figure 20 Argon Filled Window Comparison Embodied Energy Payback Period

    Economic Payback for All Retrofits In any retrofit project the ability to repay the capital costs of the retrofits is very important.

    There are a few main concerns that need to be considered when taking out money for a project,

    specifically, both how long until the entire loan is paid off and how prices will increase as time goes on.

    For this project we wanted to make sure that all of the retrofits were paid off within in a ten year time

    period. We assumed that the utilities would increase in cost 2% each year and the interest rate on the

    banks loan would be 3% a year30. The total cost for the projects retrofit was around 65,000$ and would

    be repaid within eight years and produce a profit of 24,750$ by the end of the ten year time period.

  • 23

    We have three main figures that help to explain the cost of the retrofits as well as their benefits

    to the bank and when it will be paid off. Firstly we have Figure 21 which represents all of the retrofits

    along with their costs and benefits. Secondly, Figure 22 which represents a cash flow diagram over the

    ten year time period. Lastly, we have Figure 23 shows the breakdown of the savings over each year. In

    conclusion we successfully shown that all of the proposed retrofits not only provide savings in energy or

    water, but are also able to payback their capital costs within the ten year time period.

    Retrofit Material Cost ($)

    Number of Hours

    Labour Cost ($)

    Material and Labor Cost ($)

    Electricity Energy Savings (Kwh)

    Fit Electricity Energy Savings (Kwh)

    Water Savings (m^3)

    Electrical Photovoltaics 38,480 24 11520 50,000 0 12000 0

    LED Lighting 6875 11 880 7755 8805 0 0

    Light Shelves 1600 8 640 2240 1761 0 0

    Light Sensors 441 1 80 521 1233 0 0

    Water Cistern 2100 16 1280 3380 0 0 282

    Toilet 200 4 320 520 0 0 0

    Faucet 130 1 80 210 0 0 0

    Total Savings 49,826 65 14,800 64,626 11,799 12,000 282

    Figure 21 Economic Summary Sheet of Retrofits

    Figure 22 Graphical Representation of Economic Payback

    $(60,000)

    $(50,000)

    $(40,000)

    $(30,000)

    $(20,000)

    $(10,000)

    $-

    $10,000

    $20,000

    $30,000

    1 2 3 4 5 6 7 8 9 10

    Capital Over A 10 Year Time Peroid

  • 24

    Annual Reduction Loan Electricity 11799 ekWh $64,626 Fit Elec 12000 ekWh Loan Repaid Water 282 m3 YES

    Electricity Price Fit Electricity Price Water 0.13 $/kWh 0.54 $/kWh 2.62 $/m3

    Year Electricity Savings Fit Savings

    Water Savings Interest Repayment

    Loan Principal

    1 $1,564.51 $6,609.60 $753.62

    $(1,936.83) $6,990.89

    $(57,570.11)

    2 $1,595.80 $6,741.79 $768.69

    $(1,727.10) $7,379.18

    $(50,190.93)

    3 $1,627.71 $6,876.63 $784.06

    $(1,505.73) $7,782.68

    $(42,408.25)

    4 $1,660.27 $7,014.16 $799.74

    $(1,272.25) $8,201.92

    $(34,206.33)

    5 $1,693.47 $7,154.44 $815.74

    $(1,026.19) $8,637.47

    $(25,568.86)

    6 $1,727.34 $7,297.53 $832.05 $(767.07) $9,089.86

    $(16,479.00)

    7 $1,761.89 $7,443.48 $848.69 $(494.37) $9,559.70 $(6,919.30)

    8 $1,797.13 $7,592.35 $865.67 $(207.58)

    $10,047.57 $3,128.27

    9 $1,833.07 $7,744.20 $882.98 $93.85

    $10,554.10 $13,682.37

    10 $1,869.73 $7,899.08 $900.64 $410.47

    $11,079.93 $24,762.30

    Figure 23 Energy Savings Breakdown

  • 25

    References 1 CIBC Location. Google Maps. Accessed Apr, 2013. Available at: https://maps.google.ca/maps?q=cibc+college+and+spadina&aq=0&um=1&ie=UTF-8&hl=en&sa=N&tab=wl 2 Toronto Climate. The World Executive. Accessed Apr, 2013. Available at: http://www.worldexecutive.com/locations/north_america/canada/ontario/toronto/weather.html 3 Spadina 510 Line. Toronto Transit Commission. Updated Nov, 2012. Available at: http://www.ttc.ca/Routes/510/RouteDescription.jsp?tabName=map 4 College/Carlton 506 Line. Toronto Transit Commission. Updated Jun, 2010. Available at: http://www.ttc.ca/Routes/506/RouteDescription.jsp?tabName=map 5 CIBC Communities. Canadian Imperial Bank of Commerce. Accessed Apr, 2013. Available at: https://www.cibc.com/ca/inside-cibc/quick-facts.html 6 CIBC Awards and Recognition. Canadian Imperial Bank of Commerce. Accessed Apr, 2013. Available at: https://www.cibc.com/ca/inside-cibc/awards-and-recognition.html 7 Spears, John. Energy: Ontario overpaying to meet peak electricity demand, consultant argues. Business section, The Star, 02-24-2012. http://www.thestar.com/business/2012/02/24/energy_ontario_overpaying_to_meet_peak_electricity_demand_consultant_argues.html 8 Natural Resource Canada, Photovoltaic potential and solar resource maps of Canada. http://pv.nrcan.gc.ca/index.php?m=r 9 K. Knapp, T. Jester. Empirical Investigation of the Energy Payback Time for Photovoltaic Modules. * Energy and Environmental Economics Inc, 353 Sacramento Street, Suite 1700, CA 94111, ** Siemens Solar Industries, 4650 Adohr Lane, Camarillo, CA 93011, US. 17-04-2000. 10 Passive Solar and Wind. Ontario Architecture. Updated 2002. Available at: http://www.ontarioarchitecture.com/passivesolar.htm 11 Deciduous Trees. EcoKids. Accessed Apr, 2013. Available at: http://www.ecokids.ca/pub/eco_info/topics/forests/types_of_trees.cfm 12 Interior Blinds. University of Minnesota. Accessed Apr, 2013. Available at: http://energy.gov/energysaver/articles/energy-efficient-window-treatments 13 Light Shelves. Queens University. Updated 2010. Available at: http://livebuilding.queensu.ca/green_features/smart_lighting/light_shelves 14 Dynamic Windows. SPD Control Systems Corporation. Updated Dec, 2012. Available at: http://www.spdcontrolsystems.com/ 15 LED vs Incandescent vs CFL. Design Recycle Inc. Accessed Apr, 2013. Available at: http://www.designrecycleinc.com/led%20comp%20chart.html 16 Myrans, Katherine (2009). Comparative Energy and Carbon Assessment of Three Green Technologies for a Toronto Roof. Graduate Department of Geography and Centre for Environment, University of Toronto. 17 Applications of Rain Water Storage. Portable Tank Group. Accessed Apr, 2012. Available at: http://www.water-storage-tank.com/rain-water-storage-tanks.html 18 Water-Efficient Toilet. Canada Mortgage and Housing Corporation. Updated, 2010. Available at: http://www.cmhc-schl.gc.ca/en/co/renoho/refash/refash_004.cfm 19 Ontario Guideline for Residential Rainwater Harvesting Systems. Updated, 2010. Available at: http://www.sustainabletechnologies.ca/Portals/_Rainbow/Documents/ONTARIO_RWH_HANDBOOK_2010.pdf

  • 26

    20 Manish K. Dixit, Charles H. Culp, Jose L. Fernandez-soils. System boundary for embodied energy in buildings: A conceptual model for definition. Renewable and Sustainable Energy Reviews 21 (2013) 153-164. 21 E.Syrrakou, S. Papaefthimiou, N. Skarpentzos, and P. Yianoulis (2005). Electro chromic Windows: Physical Characteristics and Environmental Profile. Solar Energy Laboratory, Physics Department, University of Patras, Greece. 22 http://www.simpleray.com/Panasonic-Sanyo-HIT-240-Watt-Solar-Panels-p/1500-019.htm 23 Light Shelves. Energy Books. Updated 1999. Available at: http://www.energybooks.com/pdf/10001005.pdf 24 Common Lighting Levels Indoor. Engineering Tool Box. Accessed April, 2013. Available at: http://www.engineeringtoolbox.com/light-level-rooms-d_708.html 25 LED Light Bulb. Canadian Tire. Accessed April, 2013. Available at: http://www.canadiantire.ca/AST/browse/3/HouseHome/Lighting/CompactFluorescentBulbs/PRDOVR~0525878P/Energizer+Omni+Directional+A19+LED+Light+Bulb%2C+13W.jsp?locale=en 26 ENERGY STAR Discount. Hydro One. Accessed April, 2013. Available at: http://www.hydroone.com/MyHome/SaveEnergy/Pages/Coupons.aspx 27 Light Sensor for Occupancy. ProLighting. Updated 2012. Available at: http://www.prolighting.com/lrf2-ocrb-p-wh.html 28 Light Sensors for Occupancy. Madison Gas and Electric. Updated 2009. Available at: http://www.mge.com/business/saving/madison/PA_10.html 29 Model 2200H 10,000 L Cistern. Tanks-a-Lot. Updated Jun, 2011. Available at: http://www.tanks-a-lot.com/Portals/160863/docs/h2200.pdf 30 CIBC Loans. Canadian Imperial Bank of Commerce. Accessed Apr, 2013. Available at: https://www.cibc.com/ca/loans/cibc-rrsp-maximizer-loan.html