68
A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical Mechanical pWLPY Civil SIGNA c Protection & Control ______ Z2L LAND Transmission & Distribution _______________ Telecontro I System Planning REPLACE FUEL OIL HEAT TRACING Holyrood Thermal Generating Station Ju'y 2011 newfoundland labrador hydro a nakor energy company

REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

A REPORT TO

THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES

Electrical

Mechanical

pWLPYCivil

SIGNAc Protection & Control______Z2L

LAND Transmission & Distribution_______________

Telecontro I

System Planning

REPLACE FUEL OIL HEAT TRACING

Holyrood Thermal Generating Station

Ju'y 2011

newfoundland labrador

hydroa nakor energy company

Page 2: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro i

Table of Contents

1 INTRODUCTION ................................................................................................................ 1

2 PROJECT DESCRIPTION ..................................................................................................... 4

3 EXISTING SYSTEM ............................................................................................................. 6

3.1 Age of Equipment or System ............................................................................. 10

3.2 Major Work and/or Upgrades ........................................................................... 10

3.3 Anticipated Useful life ........................................................................................ 12

3.4 Maintenance History ......................................................................................... 12

3.5 Outage Statistics ................................................................................................ 13

3.6 Industry Experience ........................................................................................... 13

3.7 Maintenance or Support Arrangements ............................................................ 13

3.8 Vendor Recommendations ................................................................................ 13

3.9 Availability of Replacement Parts ...................................................................... 13

3.10 Safety Performance ........................................................................................... 14

3.11 Environmental Performance .............................................................................. 14

3.12 Operating Regime .............................................................................................. 17

4 JUSTIFICATION ............................................................................................................... 18

4.1 Net Present Value .............................................................................................. 19

4.2 Levelized Cost of Energy .................................................................................... 20

4.3 Cost Benefit Analysis .......................................................................................... 20

4.4 Legislative or Regulatory Requirements ............................................................ 20

4.5 Historical Information ........................................................................................ 20

4.6 Forecast Customer Growth ................................................................................ 20

4.7 Energy Efficiency Benefits .................................................................................. 21

4.8 Losses during Construction ................................................................................ 22

4.9 Status Quo .......................................................................................................... 22

4.10 Alternatives ........................................................................................................ 22

5 CONCLUSION .................................................................................................................. 23

5.1 Budget Estimate ................................................................................................. 23

5.2 Project Schedule ................................................................................................ 24

APPENDIX A ............................................................................................................................. A1

APPENDIX B ............................................................................................................................. B1

APPENDIX C ............................................................................................................................. C1

APPENDIX D ............................................................................................................................. D1

APPENDIX E ............................................................................................................................. E1

APPENDIX F ............................................................................................................................. F1

Page 3: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 1

1 INTRODUCTION

The Holyrood Thermal Generating Station (Holyrood) is an essential part of Newfoundland

and Labrador’s generating system, delivering electrical energy to retail, industrial, and

residential customers. This plant has three generating units producing a total capacity of

490 MW. The plant was constructed in two stages. Stage 1 was commissioned in 1971

bringing on line generating Units 1 and 2, each rated at 150 MW. Stage 2 was commissioned

in 1979 bringing on line generating Unit 3 also rated at 150 MW. In 1988 and 1989, the

generation capacity of Units 1 and 2 was increased to 175 MW each. Holyrood has the

capacity of generating over 3,000,000 MWh of energy annually which is approximately 40

percent of the Island Interconnected System’s energy requirement.

Figure 1: Holyrood Thermal Generating Station

At this plant, Bunker C fuel oil is burned in large oil burning furnaces, converting water to

steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe,

equipped with electric heat tracing was installed as part of the original construction and is

used to transport Bunker C Fuel Oil from the marine terminal to the facility’s fuel storage

Page 4: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 2

tanks approximately 1200 m away. The 455 mm diameter pipeline is divided into two

subsections at approximately the midpoint of the pipeline. Each subsection of pipeline

consists of separate heat tracing circuits, designated as North Section and South Section. In

addition, there is a section of 100 mm diameter pipeline, approximately 100 m in length,

which also requires replacement of heat tracing cable.

During the period from September to April, shuttle tankers arrive at the marine terminal

and Bunker C fuel oil is pumped through the 455 mm diameter insulated pipeline to the

tank farm. Before the shuttle tanker attempts to pump oil into the pipeline, the oil is heated

to approximately 60OC onboard the tanker. Because of the thick nature of this oil, to

successfully transport oil through the pipe the oil temperature must be maintained at a

minimum of 30OC throughout its path of flow. To maintain an oil temperature of 30OC

throughout the pipe, an oil heating system known as electric heat tracing (EHT) is installed

along the full length of the pipe. The main component of EHT is the copper conductor which

is heated by the flow of electric current produced by three phase 600 volt power supply.

Figure 2 shows a picture of the existing 455 mm fuel oil pipeline equipped with electric heat

tracing in Holyrood.

Page 5: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 3

Figure 2: Electric Heat Tracing

Page 6: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 4

2 PROJECT DESCRIPTION

This project is required to replace the electric heat tracing (EHT) on the fuel oil pipeline at

the Holyrood Thermal Generating Station. The existing heat tracing cables have

deteriorated and have resulted in various problems with the performance of the existing

application, including failed sections of heat tracing due to open circuits and ground faults.

This two year project also includes the replacement of fiberglass insulation and metal

cladding for the entire pipeline. The scope of work includes:

• Erection of scaffolding for the shore arm and three expansion joints on the 455 mm

diameter line

• Removal of existing insulation, metal cladding and mineral insulated heating cables

• Testing of 455 mm diameter pipe thickness at prescribed intervals

• Coating of 455 mm diameter pipe for corrosion protection

• Installation of the new electric heat tracing system

• Installation of new insulation and cladding

• Installation of programmable controller with self diagnostics

• Construction Management

• Commissioning of the new system

• Disposal of existing metal cladding, insulation, and heat tracing cable

An external contractor will be required to install the new system. Based on discussions with

the original equipment manufacturer (OEM), Tyco Thermals Controls, of the existing heat

tracing system, it is anticipated that the existing copper heat tracing cable will need to be

replaced with a stainless steel heat tracing cable. Stainless steel heat tracing cables offer

better corrosion resistance than copper heat tracing, making it more suitable for this

application.

Page 7: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 5

It will take approximately four to six months to complete replacement of the entire heat

tracing system. Hydro proposes to complete the work in two sections – the South Section

and 100 mm diameter pipeline to be completed in the summer of 2012 and the North

Section to be completed in the summer of 2013. Each section takes approximately two to

three months to complete.

Page 8: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 6

3 EXISTING SYSTEM

The electric heat tracing equipped on the fuel oil pipeline consists of a High Density

Polyethylene (HDPE), copper sheathed, mineral insulated (MI) electric heat tracing cable.

These cables are strapped to the fuel oil pipe line every three to five linear feet intervals.

They are then insulated with two inches of fiberglass insulation and then wrapped with

metal cladding as shown in Figure 3.

Figure 3: Cross Section of 18” (455 mm) Pipeline

The 455 mm diameter fuel oil pipeline heat tracing consists of two main electric circuits,

North Section and South Section, both of which are approximately 600 meters in length.

Each section of pipeline is then subdivided by heat tracing cable lengths of approximately 50

meters. The North Section runs from the facility tank farm to the midpoint of the pipeline,

and the South Section runs from the marine terminal to the midpoint of the pipeline.

The 100 mm diameter pipeline runs from the marine terminal to approximately three

meters past the control valve located near the base of the shore arm. The shore arm is a

cement structure extending approximately 100 m from the shoreline into the ocean to

support a marine terminal at water depths which allow shuttle tankers to dock and un-load

fuel oil. The purpose of this pipeline is to drain a section of 455 mm diameter pipeline from

the marine terminal to the control valve. This is done so that if ice were to damage the 455

mm diameter pipeline on the shore arm, the pipeline would be empty of fuel and no oil

Page 9: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 7

would be released into the environment. The shore arm is shown in Figure 4.

Figure 4: Shore Arm

Please refer to Appendix A for a layout drawing of the existing fuel oil pipeline.

From 2004 to 2011, repetitive failures of the existing heat tracing cables have occurred due

to ground faults and open circuits. As a result, attempts to pump oil through the pipeline

have failed because the oil could not be maintained at the required temperature for oil

flow.

Page 10: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 8

The existing heat tracing system was newly installed in 2002 to replace the original bare

copper mineral insulated electric heat tracing. Since 2002, the high density polyethylene

jacket has melted off and the cable is failing prematurely.

Over time, moisture has accumulated within the insulation, and has caused corrosion of the

copper sheath of the cable. The moisture seeps through the outer copper sheath and

causes system failure by creating open electric circuits and ground faults. As a result, in

2009, the original three phase system was modified into a two phase system in order for

the system to remain operational. This system operates on a continuous basis due to the

lack of confidence that the system will re-energize once turned off.

Figures 5 and 6 show pictures of the deteriorated heat tracing cables.

Figure 5: Deteriorated Heat Tracing Cable

Page 11: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 9

Figure 6: Deteriorated Heat Tracing Cable

Also, the existing heat tracing application on the 100 mm diameter pipeline has experienced

similar problems as the main pipeline. It consists of bare copper mineral insulated heat

tracing cables which were installed during original construction and has exceeded its useful

service life. Over the years moisture has accumulated within the insulation and corroded

the copper sheath, resulting in open electric circuits and ground faults and thus, failure to

heat the oil.

Figure 7 shows a picture of the existing electric heat tracing cable on the 100 mm diameter

fuel oil pipeline.

Page 12: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 10

Figure 7: Deteriorated Heat Tracing Cable

The condition of the existing heat tracing cables on the 455 mm diameter and 100 mm

diameter pipes place the environment, worker safety and system reliability at risk.

3.1 Age of Equipment or System

The heat tracing system on both the North and South section of the 455 mm diameter

pipeline replaced the original in 2002. It has been in operation for nine years. The 100 mm

diameter pipeline was installed during original construction and has been in operation for

40 years.

3.2 Major Work and/or Upgrades

In 2002, the original bare copper electric heat tracing cable on the South Section and North

Section was replaced with a new copper sheathed mineral insulated electric heat tracing

cable, equipped with a high density polyethylene jacket.

Page 13: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 11

Tyco Thermal Controls (TTC) is the Original Equipment Manufacturer (OEM) for the electric

heat tracing installed during original construction, and for the new replacement cable

installed in 2002.

From 2004 to 2011, repetitive failures have been experienced with the cables on both the

North and South Sections of EHT cable which was installed new in 2002. As a result, Hydro

operations personnel modified the three phase electric heating system into a two phase

system to mitigate sections of deteriorated heat tracing cable. This modification was

required for the electric heating system to remain operational, and is a temporary measure

until replacement of the entire electric heat tracing system occurs. The procedure of

eliminating an electrical phase, or "making two phases into one" allowed reenergization of

the heat trace during critical operational periods in the winter months. The trade off for this

is essentially double the rated electrical current flowing through sections of the heat trace

system. This shortens the life of the remaining sections of heat trace. Given the total length

of the fuel oil piping a proper design requires three individual electrical phases, each equally

sharing a component of the total heat trace system.

In September 2009, Hydro contracted the OEM of the existing heat tracing cables to provide

an analysis and opinion to determine the cause of the premature failure of the electric heat

tracing cable installed in 2002. TTC discovered that the HDPE jacketed copper MI cables had

been installed in place of bare copper MI cables. The following is a quote from Page 2 from

the TTC Report dated March 31, 2011: “There are two problems associated with using the

jacketed cable for this installation. The first is that the 26.7 watts/ft output of the heater

exceeds our maximum recommendation of 8-9 watts/ft for jacketed copper MI cables on

metal pipes. The second is that the sheath temperature for these heaters would be in

excess of 405oF and this exceeds the recommended maximum continuous operating

temperature for HDPE of 248oF”. Please refer to Appendix B for more information.

Also, early in 2011, an internal root cause failure analysis was completed to determine the

Page 14: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 12

reasoning behind the decision to choose the electric heat tracing cable currently installed

on the North and South section of the fuel oil pipeline. Please refer to Appendix C.

3.3 Anticipated Useful life

The anticipated useful life of copper heat tracing cable is 20 years. However, this may vary

depending on environmental and service conditions.

3.4 Maintenance History

The five year maintenance history for the Holyrood Thermal Generating Station electric

heat tracing system is shown in Table 1.

Table 1: Five Year Maintenance History

Year Corrective

Maintenance

($000)

Corrective Maintenance (CM)

2011 9.0 Three CM work orders on malfunctioning of EHT

2010 0.5 One CM work order on malfunctioning of EHT

2009 32.3 Four CM work orders on malfunctioning of EHT. 3 phase

system modified to a 2 phase system

2008 7.9 Five CM work orders on malfunctioning of EHT

2007 0.5 One CM work order on malfunctioning of EHT

Preventive maintenance of the heat tracing system is a component of the annual

maintenance strategy of the fuel oil delivery system. Hydro does not track heat tracing

preventive maintenance costs separately from the total unit maintenance cost. As a result,

specific preventive maintenance costs for the heat tracing system are not available.

Page 15: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 13

3.5 Outage Statistics

No outages have been attributed to failed electric heat tracing at Holyrood.

3.6 Industry Experience

Curtiss Wright, Scientech, is experiencing similar problems such as ground faults and circuit

failures with bare copper electric heat tracing. The outer copper sheath of the heat tracing

cable reacts to the original pipe insulating material, attacking the outer sheath. Over time,

moisture seeps through the outer sheath and causes electrical ground faults resulting in

failure of the electric heat tracing. Please refer to Appendix D.

3.7 Maintenance or Support Arrangements

All maintenance work is performed by Hydro operations personnel.

3.8 Vendor Recommendations

TTC recommends replacement of the entire existing copper heat tracing system with

stainless steel heat tracing. Copper heat tracing is not suitable for this application because

of the moisture levels and sea salt spray experienced in Holyrood. Please refer to Appendix

E.

3.9 Availability of Replacement Parts

Replacement heat tracing cables are readily available within three to four weeks of an

order.

Page 16: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 14

3.10 Safety Performance

The existing heat tracing cables have deteriorated resulting in safety hazards from

potentially failing equipment. Improper functioning of the heat tracing is a serious concern

to the safety of operations personnel when shuttle tankers attempt to pump Bunker C fuel

oil from the marine terminal to Holyrood’s facility tank farm. For successful pumping of oil

through the pipe to the tank farm, the oil must be maintained at a temperature of 30OC.

Improper functioning heat tracing cannot achieve this temperature. As a result, as the

tanker attempts to pump cooled oil (<30OC) through the pipe, there is the possibility for

build-up of excessive back pressure in the pipeline at the marine terminal. Excessive

pressure can result in damaging the pipeline, leading to spillage of hot Bunker C fuel oil,

potentially causing severe burns or a fatality.

3.11 Environmental Performance

The environmental concern present with the condition of the existing heat tracing system is

the potential release of a large volume of bunker C fuel oil into the environment. As

mentioned earlier, a shuttle tanker attempting to pump oil through the pipeline at a

maintained temperature lower than 30OC, can potentially result in excessive back pressure

in the line, bursting the pipe, leading to spillage of Bunker C fuel oil into the Atlantic Ocean.

Page 17: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 15

Figure 8: 455 mm Pipeline

Spillage of Bunker C oil presents serious concern. The release of oil would result in

contamination of the Atlantic Ocean, detrimentally impacting highly populated plant and

marine life. It should also be noted that a nearby public beach would be negatively

impacted as well.

Bunker C oil is very thick and sticky, and has been found to float, sink, or do both in water1.

Bunker C oil properties make it very difficult to treat and clean up when it comes in contact

with the environment.

Clean up of an oil spill of approximately 15,000 barrels would not only require great effort,

but will be very costly as an extensive amount of resources will be required to clean up oil

from the ocean and shoreline. It was estimated that a minimum cost to clean up an oil spill

into the Atlantic Ocean is approximately $1,000,000.

1 - www.buzzardsbay.org/number6oil.htm

Page 18: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 16

Figure 9 shows a picture of the beach and surrounding area near the Holyrood Thermal

Plant.

Figure 9: Holyrood

Image taken from http://sonyald.blogspot.com/2011/02/my-hometown-holyrood-nl.html

Page 19: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 17

Figure 10 below is a picture of a bunker oil spill in San Francisco.

Figure 10: Bunker Oil Spill in San Francisco

Image taken from http://thegreenists.com/date/2007/11/page/4

3.12 Operating Regime

Currently, the remaining two phases of heat tracing is in continuous operation because of

the lack of confidence the system will work again if turned off. Operations personnel believe

the existing system has deteriorated to the point that if they de-energize the cables for any

period of time, they will not re-energize when turned back on. The new proposed

installation will allow for the heat tracing system to be switched off during summer months

through the installation of a programmable controller. Seasonal operation will reduce the

total power consumed by approximately 50% of the total power consumed by the existing

system.

Page 20: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 18

4 JUSTIFICATION

This project is justified on the requirement to replace the deteriorated electric heat tracing

system based on safety, operational reliability, and the environment. Due to the highly

corrosive environment that this heat tracing system is exposed to, an anti-corrosive

material is required. The previous installation used a copper sheathed material with a HDPE

jacket. This jacket did not withstand the temperatures it was exposed to and melted.

Stainless steel is the most economic material that will withstand both corrosion and the

required temperatures.

The project is required based on the following reasons:

1. Failure to Receive Oil

The storage of Bunker C fuel oil has to be maintained at sufficient levels in the tank farm to

ensure continuous operation of the Holyrood Generating Station. Electric heat tracing of the

entire length of piping heats the highly viscous oil to enable pumping from shuttle tankers

to the facility tank farm. The existing electric heat tracing system has deteriorated and is

now temporarily repaired for unloading oil from the tankers. On February 22, 2011, a tanker

could not deliver fuel for three days due to failed electric heat tracing, resulting in three

days of demurrage payments of $18,000 to $25,000 per day.

2. Consultant Recommendations

A consultant, AMEC completed a condition assessment and advised Hydro that the system

should be replaced as indicated in the following quote from Page 1 of their condition

assessment report: “The heavy oil electrical trace heating system on the pipeline from the

dock to the receiving point at the south end of the tank farm was replaced but has recently

experienced failures. The plant has managed to get two phases back in working order, but

the failure of these phases is very likely. This issue needs to be resolved and the system

replaced”. See Appendix F.

Page 21: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 19

3. OEM Recommendations

The OEM, Tyco Thermal Controls, has recommended that the existing copper heat tracing

system be replaced with new stainless steel electric heat tracing.

4. Personnel Safety

The insulation of the cables of the existing heat trace system has become brittle. This

reduces the ability of the insulation to protect from electric ground faults and the insulation

resistance has become lower than the acceptable minimum value. The deterioration of the

insulation indicates that there are places where there are leakage currents which endanger

the safety of personnel.

5. Environmental Performance

Release of Bunker C oil into the Atlantic Ocean is a serious environmental concern, and

presents a high risk of severely impacting an environment which is highly populated with

plant and marine life. The pipeline has the capacity to contain approximately 15,000 barrels

of oil. This risk is significantly reduced with the installation of a new heat tracing cable

suitable for this application.

Failure to replace the existing heat tracing cables increases the likelihood of failure to

receive fuel oil and could lead to extensive equipment damage, and poses serious risk to

personnel safety, the environment and operational reliability.

4.1 Net Present Value

A net present value calculation was not performed in this instance as only one viable

alternative exists.

Page 22: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 20

4.2 Levelized Cost of Energy

This project will not affect the levelized cost of energy for the system.

4.3 Cost Benefit Analysis

A cost benefit analysis is not required for this project proposal as there are no quantifiable

benefits.

4.4 Legislative or Regulatory Requirements

There are no legislative or regulatory requirements associated with this project.

4.5 Historical Information

In 2002, the original copper MI heat tracing cables on the fuel oil delivery pipeline was

replaced with new jacketed copper MI heat tracing cables. Please refer to Appendices B and

C.

4.6 Forecast Customer Growth

This project has no effect on forecasted customer growth. Figures 11 and 12 below show

the fuel quantity forecast required to meet the load forecast.

Page 23: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 21

Figure 11: Island Interconnected Peak Demand to be supplied to Holyrood

Figure 12: Holyrood Plant Fuel Forecast

4.7 Energy Efficiency Benefits

There are no energy efficiency benefits associated with replacement of the existing copper

electrical heat tracing system with stainless steel heat tracing.

Page 24: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 22

4.8 Losses during Construction

There are no losses anticipated to occur during construction of this project as the

replacement will be performed during the period from May 1 to August 31 when no oil is

delivered to Holyrood.

4.9 Status Quo

The status quo is not an acceptable alternative because the deteriorated and obsolete

equipment poses safety hazards to Hydro operations personnel and poses risk to the

environment and reliable delivery of service to customers.

4.10 Alternatives

Electric heat tracing is the only viable option to the problems described.

Page 25: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 23

5 CONCLUSION

The replacement of the fuel oil heat tracing system is justified on the basis of the safety and

environmental concerns and the unreliability of the existing equipment to operate properly.

Without the replacement, operating staff, the environment, and system reliability are

exposed to unacceptable risks associated with failure of the heat tracing cable. To eliminate

known safety, reliability and environmental risks, the entire heat tracing system on the fuel

oil pipeline requires replacement.

5.1 Budget Estimate

The budget estimate for this project is shown in Table 2.

Table 2: Budget Estimate

Project Cost:($ x1,000) 2012 2013 Beyond Total

Material Supply 5.0 5.0 0.0 10.0

Labour 234.1 191.0 0.0 425.1

Consultant 0.0 0.0 0.0 0.0

Contract Work 1,027.0 917.0 0.0 1,944.0

Other Direct Costs 0.0 0.0 0.0 0.0

Interest and Escalation 86.9 213.1 0.0 300.0

Contingency 121.3 87.8 0.0 209.1

TOTAL 1,474.3 1,413.9 0.0 2,888.2

Page 26: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 24

5.2 Project Schedule

The work is scheduled over a two year period and will be completed during the period from

May through August when no fuel oil is delivered to site. The anticipated project schedule is

shown in Table 3.

Table 3: Project Schedule

Activity Start Date End Date

Planning Initial Project Planning

Design Transmittal Development

Jan 2012 Mar 2012

Design Equipment Tenders

Placement of Orders

Detailed Design Engineering

Mar 2012 Apr 2012

Procurement Equipment Delivery Apr 2012 May 2012

Construction Equipment Installations – South

Section

Equipment Installations – North

Section

Equipment Retirement

May 2012

May 2013

Aug 2012

Aug 2013

Commissioning Equipment in Service – South Section

Equipment in Service – North Section

Sep 2012

Sep 2013

Sep 2012

Sep 2013

Closeout Project Completion and Closeout Dec 2013 Dec 2013

Page 27: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Newfoundland and Labrador Hydro Page 25

Page 28: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix A

Newfoundland and Labrador Hydro A1

APPENDIX A

Fuel Oil Delivery Line Heat Trace

Page 29: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix A

Newfoundland and Labrador Hydro A2

Page 30: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix B

Newfoundland and Labrador Hydro B1

Appendix B

Tyco Thermal Controls – Holyrood Heat Tracing Background

Information

Page 31: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix B

Newfoundland and Labrador Hydro B2

March 31, 2011

Newfoundland Labrador Hydro

Holyrood, NL

A0A 2R0

Attention: Christian Thangasamy, M.Eng., P. Eng.

Reference: EHT system on the 18 inch Fuel Oil Line

Background Information

Christian,

The following represents a summary of the Tyco Thermal Controls (TTC) electric heat tracing

(EHT) system installed on the 18 inch fuel oil line at the Holyrood Generating Facility.

The original installation was done in February 1970. The construction drawings show that

the 4000 foot line was divided into two circuits at approximately the mid-point of the

pipeline. The circuits were designated as North (ccts 1A to 1E) and South (ccts 2A-2D). The

mineral insulated heating cable was Pyrotenax reference R12C: single conductor, 600 volt,

bare copper, 14 watts/linear foot. The system operated as designed for approximately 30

years until 2000 when repair work began.

TTC provided a budget to replace the heat tracing in December 2000 offering 3 options: self-

regulating heating cables, mineral insulated heating cables or STS (skin effect). It was

suggested at this time to change the mineral insulated cables to stainless steel. Alloy 825

heating cables have a higher operating temperature range and offer better corrosion

resistance than copper jacketed cables.

In May 2002 another proposal was submitted offering 2 options: replace all or a part of the

MI heating cable with new MI cables or install a complete new system with self-regulating

heaters. It is our understanding that, for budget considerations, only a few of the heating

cables were replaced on the North circuit. TTC introduced new cable reference numbers

Page 32: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix B

Newfoundland and Labrador Hydro B3

effective March 17, 1997 and the original R12C cable reference was changed to the new

reference 61CC5162. This reference is a copper MI cable.

On May 23, 2002 Tyco sent a letter to Newfoundland Hydro summarizing the existing EHT

system. Over the past number of years many significant changes had been made to the

system.

• Existing circuits 1B, 1D and 1E were not operating.

• Circuit 1B was taken out of service and teck cable was installed as a jumper. This

would reduce the overall resistance in the circuit and increase the power output and

sheath temperature of the remaining cables.

• NL Hydro request made to provide a new design to install 6 each 150 foot MI cables

series connected to the 3 each 366 foot cables of circuit 1A.

• At some time in 2003 Newfoundland Hydro would reconnect ½ of circuit 1D and all

of circuit 1E.

• By connecting the MI cables as detailed above, the copper heating cables would be

operating at 41 volts, producing 26.7 watts/ft and having a sheath temperature of

approximately 407 deg. F. It was noted that TTC normally limits the sheath

temperature of copper cables to 392 deg. F.

TTC was not made aware of whether or not circuit 1D and 1E were ever reconnected. Also, it

is not clear if or when the teck cable was replaced by heating cable.

In September 2009 TTC reviewed this installation again. Insulation was removed to check

the condition of the heater in different sections of the pipe. At this time it was discovered

that HDPE jacketed copper MI (B61CH5162/…) had been installed in place of bare copper

(B61CC5162/…) during the retrofits.There are two problems associated with using the

jacketed cable for this installation. The first is that the 26.7 watts/ft output of the heater

exceeds our maximum recommendation of 8-9 watts/ft for jacketed copper MI cables on

metal pipes. The second is that the sheath temperature for these heaters would be in excess

of 405 deg. F and this exceeds the recommended maximum continuous operating

temperature for HDPE of 248 deg. F. During the visual inspection of the heater it was found

that the jacket had melted off of the copper heating cable which would be expected based

on the calculated sheath temperature. It appears that an incorrect purchase requisition may

have been issued for jacketed copper heating cable. While the HDPE jacket would be

damaged due to temperature, the copper MI cable would still operate. The copper cable,

without the HDPE jacket, may have been subject to increased corrosion.

Later in September TTC sent their field service representative to site to inspect the system

and fault locate many of the cables. Many of the circuits were found to be open or

grounded. A report was submitted outlining the necessary steps to repair some of the

Page 33: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix B

Newfoundland and Labrador Hydro B4

cables. The field service rep returned in October to carry out some of the repairs to the

cables. The system today operates with only 2 of the phases working.

In general, TTC electric heat tracing systems have a 10-year warranty and an expected life in

excess of 20 years. This assumes that the EHT system, which includes not only the heat

tracing cables and controls but also the insulation, cladding and distribution wiring, is

properly maintained.

The existing system appears to have worked for almost 30 years. When repairs were

undertaken it seems that, to meet budget constraints, compromises were made to the

system. As this is a resistance heating system, changes made to some sections of the circuit

design (1A to 1E) caused other heating cables in the circuit to operate at wattages, currents

or temperatures exceeding their recommended design limits.

Please call me if you have any questions concerning this information.

Regards,

Pete Inglis

Regional Manager

Tyco Thermal Controls

3 Kingslea Gardens

Toronto, ON

M8Y 2A7

Phone: 416-234-0886

Page 34: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C1

Appendix C

Root Cause Failure Analysis of Electric Heat Tracing

Page 35: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C2

Table of Contents

Root Cause Failure Analysis of Electric Heat Tracing page 1

Appendix 1 Tanker Report

Appendix 2 Acceptance form for offloading oil tankers

Appendix 3 Discharge Pressure Log

Appendix 4 Pumping Log

Appendix 5 Canadian Maritime Agency Statements of Facts

Appendix 6 Tyco’s Inspection Report

Appendix 7 Copy of Cable Tag

Appendix 8 Copy Tyco Specification Sheet for Copper MI Cables

Appendix 9 Copy of Purchase Order Requisition for Copper Sheathed Cable

Appendix 10 Copy of the Quote for 12w/ft copper sheathed cables from vendor with the

words PVC jacket

Appendix 11 Copy of P.O. #40043 OP dated 03/02/17 for R12C

Appendix 12 Copy of the Vendor’s fax dated May 23, 2002 informing delivery time and

price for copper sheathed cables

Page 36: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C3

HOLYROOD THERMAL GENERATING STATION

INCIDENT REPORT

Root Cause Failure Analysis of Electric Heat Tracing

Marine Terminal to Tank Farm 18 inch Bunker C oil Piping

Date of incident: 19 February 2011

Date of start of investigation: 14 March 2011

Date of final report: 31 March 2011

Incident Cost: $ 100,000

Incident Summary:

The Holyrood Thermal Generating Station burns Bunker C oil as fuel in the burners. Bunker C oil is

stored in four tanks on site for its daily use. These tanks are filled by Bunker C oil brought by ocean

going tankers. These tankers berth at the plant’s marine terminal which is at a distance of 4000 feet

from tank # 1 which is the farthest tank. The oil from the tankers is pumped through 18 inch piping.

Bunker C oil being very viscous needs to be maintained at approximately 300 C by means of either

electrical or steam tracing the piping for pumping. At Holyrood the 18 inch pipe is provided with

electrical heat tracing.

Every year the plant receives between five and ten oil tankers. On 14th February a tanker arrived at

St John’s pilot station and it was ready to discharge oil on 19th February. The oil could not be

pumped for three days due the failure of the electric heat tracing on the 18 inch 4000 feet long pipe.

This resulted in a demurrage payment for three days.

Initial Conditions:

The electric heat tracing was on. It had not tripped.

Initiating Event:

When commencing to pump from the tanker the pressure was increasing indicating a block in the

discharge piping. The flow meter in the ship did not show any indication of oil flow.

Incident Description:

On 19th February, mechanics went to the dock to discharge oil from the tank. The loading arms

were connected at 1410 hrs. Mechanics commenced pumping at 1530 hrs. The pump discharge

pressure remained at 400 kpa until 1800 hrs. The flow meter at the tanker did not show any flow

Page 37: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C4

except for the 137 barrels which is the volume of the empty 18 inch piping from the dock to the

block valve at dock gate. This portion of the piping is drained after discharging the oil from tankers

by means of 4 inch drain piping. It was found that the electric heat tracing had malfunctioned.

The Shift Supervisor raised an emergency work order on 20th February for electricians to attend to

the defective electric heat tracing.

The present electric heat tracing was commissioned in 2004. In 2000, Tyco, the manufacturer of the

electric heat tracing submitted a proposal to Hydro for replacement the 30 year old electric heat

tracing system. The original heat tracing cables were copper sheathed with part number R12C150.

The letter ‘C’ is for copper sheathed, the number 150 is for the length of the heating cable in feet

and the number 12 is the size of the cable in wire gauge.

Tyco’s options in 2000 were:

1. Self Regulating Heating Cables $1,122,498.00

2. Mineral Insulated Inconel Sheathed Heating Cables $879,341.00

3. Skin Effect Heat Tracing System $710,388.00

Tyco included the option of stainless steel sheathed cable heaters. However, in 2002, Hydro did not

opt for any of the above when the project for replacement of the Heat Tracing started. Hydro did

not have a budget to afford any of the above options. Hence Hydro planned to replace the defective

copper sheathed heater cables, by the plant forces over a two/four year period to preserve budget.

Tyco carried out the design calculations for copper sheathed heater cables. The sheath temperature

was calculated to be 1380 C. The watts/ft was 12. Hydro contemplated replacing the copper

sheathed mineral insulated heater cables with self regulating cables. Tyco informed Hydro that the

cost of self regulated cables would be $84,000 and that of copper sheathed mineral filled heater

cables as $18,000. Hydro opted for the copper sheathed mineral filled heater cables in view of the

lower cost as well as costs associated with new 208 V step down transformers required for the self

regulating heater cables.

The plant decided to have the copper sheathed heater cables to be jacketed with High Density

Polyethylene to protect the copper sheath from corrosion. Plant electricians began installing High

Density Polyethylene jacketed copper sheathed mineral cables during Oct 2002. The allowable

maximum temperature for High Density Polyethylene is 1100C. The maximum allowable wattage for

High Density Polyethylene jacketed heater cable is 8 watts per foot. Hydro did not change the heater

cable length to suit the lowered wattage loading.

The electric heat tracing project was completed on 12th November 2004 at a cost of $231,698. The

heat tracing began to fail from 2005. It was observed that the HDPE was cracking and melting. The

heater cable was getting overheated and grounding out due to loss of insulation. In Nov 2009, the

heat tracing system had to be modified to a two phase system from 3 phases due to excessive

Page 38: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C5

grounding in one phase. There were 19 corrective maintenance work orders between Nov 2004 and

19th Feb 2011.

Immediate Corrective Action:

The electricians found that the electric heat tracing was ‘ON’ with a section halfway between the

railway crossing and the dock gate, ‘open’ circuited. The terminations of the cold leads to the

defective section had to be drilled as they had fused to their brass terminals at the terminal box. The

defective section was by-passed by energizing an unused section of a phase which had been taken

out of service in 2009.

Causes & Corrective Actions:

The decision by the Plant to go for High Density Polyethylene jacketed heater cables contributed to

the failure of the heat tracing system. As per Tyco, the HDPE jacketed cables are designed and used

as snow melting cables. These cables are used for corrosive embedded applications such as asphalt

or snow melting where the HDPE can dissipate heat over a large area. When the HDPE jacketed

heater cable is wrapped on a pipe, it has only a finite area of contact thus limiting the area for heat

transfer. The wattage loading is 8 watts per foot for the high density polyethylene jacketed cables.

The plant purchased HDPE jacketed heaters for a system which was designed for copper sheathed

cables with a load of 12 watts per foot. The tags on the cables on the 18 inch fuel oil piping show

150 feet and 1800 watts. Thus High Density Polyethylene cable heaters which were designed for a

maximum load of 8 watts/foot were subjected to a load of 12 watt/foot.

The HDPE jacketed cables have therefore been subjected to excessive overheating and broke down.

The copper core burnt out due to higher than design wattage causing the break down of the copper

sheath resulting in cable failure. The resistance measured on the system has repetitively been lower

than the allowable value of 1.6 meg ohm.

The following accelerated the breakdown of the heat tracing system.

1. The moisture ingress through defective sealing in the cladding which provided a source

for grounding.

2. Tech cables which were installed to by pass defective circuits decreased the resistance

in the heater cables and thereby increased the power in the cables resulting in

overheating.

Weekly measuring of the resistance in the circuits has been initiated as a condition monitoring

strategy.

Lessons Learned:

Page 39: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C6

1. When changing the material composition of a component, thorough research has to be

done on the applicability of the new material.

2. When replacing a component in an existing system, the new component must be checked

whether it conforms to the specifications of the existing system.

3. Prior to commissioning a project, the function of the system and components in the system

should be thoroughly understood by calling for meetings and discussions with end

users/vendors.

4. When budget is not available, more Preventive Maintenance needs to be carried out to keep

the system in operation and efforts to expedite the budget approval process should be

made rather than trying to fit the project to the available budget.

Page 40: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C7

Appendix 1

Page 41: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C8

Page 42: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C9

Appendix

2

Page 43: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C10

Appendix 3

Page 44: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C11

Page 45: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C12

Appendix 4

Page 46: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C13

Appendix 5

Page 47: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C14

Page 48: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C15

Appendix 6

Page 49: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C16

Page 50: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C17

Appendix 7

Page 51: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C18

Appendix 8

Page 52: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C19

Appendix 9

Page 53: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C20

Appendix 10

Page 54: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C21

Appendix 11

Page 55: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix C

Newfoundland and Labrador Hydro C22

Appendix 12

Page 56: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix D

Newfoundland and Labrador Hydro D1

Appendix D

Fossil Operations & Maintenance Information Service – Above

Ground Fuel Line Heat Tracing Cable

Page 57: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix D

Newfoundland and Labrador Hydro D2

Page 58: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix D

Newfoundland and Labrador Hydro D3

Page 59: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix E

Newfoundland and Labrador Hydro E1

Appendix E

Fuel Lines Engineering, Procurement and Construction (EPC)

Services

Page 60: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix E

Newfoundland and Labrador Hydro E2

Page 61: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix E

Newfoundland and Labrador Hydro E3

Page 62: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix E

Newfoundland and Labrador Hydro E4

Page 63: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix E

Newfoundland and Labrador Hydro E5

Page 64: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix E

Newfoundland and Labrador Hydro E6

Page 65: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix E

Newfoundland and Labrador Hydro E7

Page 66: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix E

Newfoundland and Labrador Hydro E8

Page 67: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix F

Newfoundland and Labrador Hydro F1

APPENDIX F

AMEC – Condition Assessment & Life Extension Study

Page 68: REPLACE FUEL OIL HEAT TRACING...steam which is then used to propel turbine generators. A 455 mm diameter insulated pipe, equipped with electric heat tracing was installed as part of

Replace Fuel Oil Heat Tracing

Appendix F

Newfoundland and Labrador Hydro F2