Activity ID Activity Name OriginalDuration
Start Finish
SWT-CP-1160 Grouting of identified shearkey locations in North Side 18d 26-May-12 14-Jun-12
SWT-CP-1170 Grouting of identified shearkey locations in East Side 10d 17-Jun-12 27-Jun-12SWT-CP-1180 Grouting of identified shearkey locations in South Side 8d 28-Jun-12 07-Jul-12
WALKWAY REPAIRING WWALKWAY REPAIRING WORKS 40d 02-May-12 17-Jun-12
SWT-CP-1190 Sealing by Epoxy injection on cracked surfaces 30d 02-May-12 05-Jun-12
SWT-CP-1200 Saw Cutting and Sealing in Construction joint surfaces 30d 14-May-12 17-Jun-12
HANDINGOVERHANDINGOVER 55d 05-May-12 07-Jul-12
SWT-CP-1205 Removal of debris and cleaning of site 55d 05-May-12 07-Jul-12
SWT-CP-1210 Handing over 0d 07-Jul-12
Apr May Jun Jul
Qtr 2, 2012 Qtr 3, 2012
Grouting of identified shearkey locations in Nor
Grouting of identified
Gr17-Jun-12, WALKWAY REPAIRING WO
Sealing by Epoxy injection on cracked surfaces
Saw Cutting and Sealing in Construction07-
ReHa
DOHA NORTH SEWERAGE TRATMENT PLANT-BIOREACTOR 5 REPAIR WORKS FOR BIOREACTOR -5
SEWERAGE TREATMENT PLANT -DOHA NORTH
05-Apr-12 13:41
Primary Baseline
Actual Work
Remaining Work
Critical Remaining W ork
Milestone
Summary Date Revision Checked Approved 5