39
The Study for Development of the Rural Electrification Master Plan 08-004 J R E D No. in Zambia Final Report Summary Report January 2008 Japan International Cooperation Agency (JICA)

REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

  • Upload
    others

  • View
    10

  • Download
    0

Embed Size (px)

Citation preview

Page 1: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

The Study for

Development of

the Rural Electrification Master Plan

08-004

J R

E D

No.

in Zambia

Final Report

Summary Report

January 2008

Japan International Cooperation Agency (JICA)

Page 2: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

The Study for

Development of

the Rural Electrification Master Plan in

Zambia

Final Report Summary Report

Table of Contents

Page

Acronyms

1. Background .....................................................................................................................1

2. Principles and Purpose of Master Plan Development ..................................................1

3. Master Plan Development Process ................................................................................2

4. Results of Master Plan Development.............................................................................4

5. Recommendation ..........................................................................................................24 5.1. Practical Use of Master Plan ............................................................................................... 24

5.2. Management of Rural Electrification Fund ......................................................................... 24

5.3. Increase of Electricity Access Rate ..................................................................................... 24

5.4. Supporting Sustainable Electrification Business in Rural Area ........................................... 25

Page 3: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Acronyms ACSR Aluminium Conductor Steel Reinforced

AfDB African Development Bank

CA Catchment Area

CBR Crude Birth Rate

CEC Copperbelt Energy Corporation

CHESCO Chipata Energy Service Company

CSAA Client Service Accounts Assistants

CSO Central Statistics Office

DDACC Direct Debit and Credit Clearing

DoE Department of Energy

DWA Department of Water Affairs

ECZ Environmental Council of Zambia

EIA Environmental Impact Assessment

EIRR Economic Internal Rate of Margin

EIS Environmental Impact Statement

EPB Environmental Project Brief

EPPCA Environmental Protection and Pollution Control Act

ERB Energy Regulation Board

ESCO Energy Service Company

ESU Environment and Social Affairs Unit of ZESCO

FIRR Financial Internal Rate of Return

FNDP The Fifth National Development Plan

FY Fiscal Year

GEF Global Environmental Facility

GIS Geographical Information System

GNI Gross National Income

GRZ Government of the Republic of Zambia

IEE Initial Environmental Examination

IMR Infant Mortality Rate

IPP Independent Power Producer

JBIC Japan Bank for International Corporation

JICA Japan International Corporation Agency

K (Zambia) Kwacha

KG-PS Kafue Gorge Power Station

KNB-PS Kariba North Bank Power Station

KPLC Kenya Power & Lighting Company

KSh Kenya Shilling

kW, MW kilowatt, megawatt

kWh, MWh, GWh kilowatthour, megawatthour, gigawatthour

LDC Least Developed Countries

LEB Life Expectancy at Birth

Page 4: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

LESCO Lundazi Energy Service Company

Mc-HP Micro-hydropower plant

MEWD Ministry of Energy and Water Development

MFNP Ministry of Finance and National Planning

MTENR Ministry of Tourism, Environment and Natural Resources

NEP National Energy Policy

NESCO Nyimba Energy Service Company

NRSE New and Renewable Source of Energy

PRP Power Rehabilitation Project

REA Rural Electrification Authority

REF Rural Electrification Fund

REMP Rural Electrification Master Plan

REP Rural Electrification Programme

RGC Rural Growth Centre

ROA Return on Assets

SAPP Southern African Power Pool

SEA Strategic Environmental Assessment

TEPCO Tokyo Electric Power Company, Inc.

TFR Total Fertility Rate

Tr Transformer

UNIDO United Nations Industrial Development Organization

UTM Universal Transverse Mercator

VF-PS Victoria Falls Power Station

WB World Bank

ZAMSIF Zambia Social Investment Fund

ZCCM Zambia Consolidated Copper Mines

ZESCO Zambia Electricity Supply Corporation (Currently “ZESCO Ltd.” is the company’s official name)

ZMD Zambia Meteorological Department

Page 5: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating the rural economy in the Republic of Zambia. In 1994, the Government of the Republic of Zambia (GRZ) established the Rural Electrification Fund (REF) by committing the sales tax on electricity, and has been trying to increase the electrification rate in rural area by executing projects funded by REF. The household electrification rate, however, still remains at approximately 20% countrywide, and only 2 –3% in rural area. As a mid-term target, achieving 35% of household electrification rate (50% in urban area and 15% in rural area) by 2010 was set in the Poverty Reduction Strategy Paper published in 2002. For aiming to achieve this goal, GRZ has been strengthening policies and institutions related to rural electrification. In December 2003, the Rural Electrification Act was enacted to establish Rural Electrification Authority (REA) and to improve the management of REF.

In order to enhance rural electrification efficiently, preparation of the Rural Electrification Master Plan in Zambia (REMP) was considered as an urgent issue, and GRZ requested the Government of Japan to assist the development of Master Plan in 2004. Accordingly, Japan International Cooperation Agency (JICA), an official agency responsible for the implementation of the technical cooperation program on behalf of the Government of Japan, sent a study team to Zambia for project formulation in September 2005, followed by the preliminary study team in January 2006. The study team held discussion with GRZ on the Scope of Work of the Master Plan Study, and execution of the study was approved.

JICA selected the Tokyo Electric Power Company, Inc. (TEPCO) as consultant to execute this Master Plan Study. The Study Team of TEPCO commenced the study in May 2006, and accomplished the study in January 2008.

2 Principles and Purpose of Master Plan Development To execute rural electrification projects in Zambia, a systematic implementation plan that indicates electrification targets, electrification order, electrification method, time schedule, and required budget was necessary. Therefore, a systematic implementation plan was developed as the REMP targeting 2030 along the following principles:

Develop logical, objective, numerical/quantitative, and convincing Master Plan

Adopt decentralized planning process

Provide realistic financial plan to be implemented

The objective of the REMP Development was to formulate the Master Plan for rural electrification in Zambia up to the year 2030 and to bring about technology transfer to counterparts so that they could continue updating and implementing the Master plan by themselves.

The Master Plan consisted of the following items:

1) Rural Electrification Plan up to 2030

(a) Development of selection criteria for rural electrification projects (b) Selection of candidate site for rural electrification considering socio-economic and

technical aspects (c) Selection of electrification methods

Extension of existing grid Isolated mini-grid with renewable energy, such as mini- and micro-hydro power generation Solar home system (SHS) Mini-grid with diesel power generation, if none of the above is feasible

(d) Case study executions

1

Page 6: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

2) Financial Plan for Rural Electrification (a) Study on financing strategy (b) Cost estimation of implementing the Master Plan at each phase (c) Evaluation of the validity of rural electrification projects (EIRR / FIRR)

3) Policy Recommendations for Acceleration and Dissemination of Rural Electrification

(a) Organization structure for promoting rural electrification (b) Operational management of Rural Electrification Fund (c) Framework of promoting the participation of private sector (IPP and ESCO) (d) Affordable initial connection fee and sustainable electricity tariff (e) Policy on curbing the negative impact of electrification on society and environment

4) Development of Comprehensive Rural Electrification Program

(a) Implementation procedure of long-term rural electrification plan (b) Prioritisation of execution plans (c) Consensus-oriented rural electrification plan with donors; ex. Japanese Bank for

International Cooperation (JBIC), African Development Bank (AfDB) and World Bank (WB)

3 Master Plan Development Process The development flow of the REMP is shown in Figure 1.

Making Long List of Unelectrified RGCs(Decentralized Planning Process)

Making Long List of Unelectrified RGCs(Decentralized Planning Process)

Forecast of Potential Demandfor each of Unelectrified RGCsForecast of Potential DemandForecast of Potential Demandfor each of for each of UnelectrifiedUnelectrified RGCsRGCs

Setting Temporary Electrification Priority of RGCs Based on Potential Demand

(Application of Demand Criteria)

Setting Temporary Electrification Priority Setting Temporary Electrification Priority of of RGCsRGCs Based on Potential DemandBased on Potential Demand

(Application of Demand Criteria)(Application of Demand Criteria)

Calculation of Financial Indicators (FIRR and EIRR) for each of Project Packages

(Financial Analysis)

Calculation of Financial Indicators Calculation of Financial Indicators (FIRR and EIRR) for each of Project Packages(FIRR and EIRR) for each of Project Packages

(Financial Analysis)(Financial Analysis)

Selection of Optimal Electrification Method for each RGC by the Least Life Time Cost

(Application of Supply Criteria)

Selection of Optimal Selection of Optimal Electrification MethodElectrification Method for for each RGC by each RGC by the Least Life Time Costthe Least Life Time Cost

(Application of Supply Criteria)(Application of Supply Criteria)

Creation of Project Packages(Grouping or Making Cluster of RGCs)

Creation of Project PackagesCreation of Project Packages(Grouping or Making Cluster of (Grouping or Making Cluster of RGCsRGCs))

Finalization of Electrification Priority of Project Package by Financial Indicators

Finalization of Electrification Priority Finalization of Electrification Priority of Project Package by Financial Indicatorsof Project Package by Financial Indicators

Allocation of Project Package into Project Phase from 2008 to 2030

Allocation of Project Package Allocation of Project Package into Project Phase from 2008 to 2030into Project Phase from 2008 to 2030

[Assumption]1) PF, BE, HH Growth Rate:

2.9%/year or 1.986 times from 2006 to 2030

2) A Hammer Mill Service Ratio:174 Households/Hammer Mill

3) 100% Electrification Rate for PF, BE, and HH in 1,217 RGC by 2030

[Assumption]1) PF, BE, HH Growth Rate:

2.9%/year or 1.986 times from 2006 to 2030

2) A Hammer Mill Service Ratio:174 Households/Hammer Mill

3) 100% Electrification Rate for PF, BE, and HH in 1,217 RGC by 2030

[Socio Economic Survey]

[Socio Economic Survey]

19 Electrified RGCs

71 Unelectrified RGCs

[Technical Aspects Analysis]Unitary Daily Load Estimation[Technical Aspects Analysis]Unitary Daily Load Estimation

[Social Aspects Analysis]1) Ability to Pay2) Willingness to Pay3) Prioritized Property for Electrification

[Social Aspects Analysis]1) Ability to Pay2) Willingness to Pay3) Prioritized Property for Electrification

Policy RecommendationPolicy Recommendation

Completion of Rural Electrification Master Planup to 2030

Completion of Rural Electrification Master PlanCompletion of Rural Electrification Master Planup to 2030 up to 2030

Making Long List of Unelectrified RGCs(Decentralized Planning Process)

Making Long List of Unelectrified RGCs(Decentralized Planning Process)

Forecast of Potential Demandfor each of Unelectrified RGCsForecast of Potential DemandForecast of Potential Demandfor each of for each of UnelectrifiedUnelectrified RGCsRGCsForecast of Potential Demandfor each of Unelectrified RGCsForecast of Potential DemandForecast of Potential Demandfor each of for each of UnelectrifiedUnelectrified RGCsRGCs

Setting Temporary Electrification Priority of RGCs Based on Potential Demand

(Application of Demand Criteria)

Setting Temporary Electrification Priority Setting Temporary Electrification Priority of of RGCsRGCs Based on Potential DemandBased on Potential Demand

(Application of Demand Criteria)(Application of Demand Criteria)

Setting Temporary Electrification Priority of RGCs Based on Potential Demand

(Application of Demand Criteria)

Setting Temporary Electrification Priority Setting Temporary Electrification Priority of of RGCsRGCs Based on Potential DemandBased on Potential Demand

(Application of Demand Criteria)(Application of Demand Criteria)

Calculation of Financial Indicators (FIRR and EIRR) for each of Project Packages

(Financial Analysis)

Calculation of Financial Indicators Calculation of Financial Indicators (FIRR and EIRR) for each of Project Packages(FIRR and EIRR) for each of Project Packages

(Financial Analysis)(Financial Analysis)

Calculation of Financial Indicators (FIRR and EIRR) for each of Project Packages

(Financial Analysis)

Calculation of Financial Indicators Calculation of Financial Indicators (FIRR and EIRR) for each of Project Packages(FIRR and EIRR) for each of Project Packages

(Financial Analysis)(Financial Analysis)

Selection of Optimal Electrification Method for each RGC by the Least Life Time Cost

(Application of Supply Criteria)

Selection of Optimal Selection of Optimal Electrification MethodElectrification Method for for each RGC by each RGC by the Least Life Time Costthe Least Life Time Cost

(Application of Supply Criteria)(Application of Supply Criteria)

Selection of Optimal Electrification Method for each RGC by the Least Life Time Cost

(Application of Supply Criteria)

Selection of Optimal Selection of Optimal Electrification MethodElectrification Method for for each RGC by each RGC by the Least Life Time Costthe Least Life Time Cost

(Application of Supply Criteria)(Application of Supply Criteria)

Creation of Project Packages(Grouping or Making Cluster of RGCs)

Creation of Project PackagesCreation of Project Packages(Grouping or Making Cluster of (Grouping or Making Cluster of RGCsRGCs))

Finalization of Electrification Priority of Project Package by Financial Indicators

Finalization of Electrification Priority Finalization of Electrification Priority of Project Package by Financial Indicatorsof Project Package by Financial Indicators

Finalization of Electrification Priority of Project Package by Financial Indicators

Finalization of Electrification Priority Finalization of Electrification Priority of Project Package by Financial Indicatorsof Project Package by Financial Indicators

Allocation of Project Package into Project Phase from 2008 to 2030

Allocation of Project Package Allocation of Project Package into Project Phase from 2008 to 2030into Project Phase from 2008 to 2030

Allocation of Project Package into Project Phase from 2008 to 2030

Allocation of Project Package Allocation of Project Package into Project Phase from 2008 to 2030into Project Phase from 2008 to 2030

[Assumption]1) PF, BE, HH Growth Rate:

2.9%/year or 1.986 times from 2006 to 2030

2) A Hammer Mill Service Ratio:174 Households/Hammer Mill

3) 100% Electrification Rate for PF, BE, and HH in 1,217 RGC by 2030

[Assumption]1) PF, BE, HH Growth Rate:

2.9%/year or 1.986 times from 2006 to 2030

2) A Hammer Mill Service Ratio:174 Households/Hammer Mill

3) 100% Electrification Rate for PF, BE, and HH in 1,217 RGC by 2030

[Assumption]1) PF, BE, HH Growth Rate:

2.9%/year or 1.986 times from 2006 to 2030

2) A Hammer Mill Service Ratio:174 Households/Hammer Mill

3) 100% Electrification Rate for PF, BE, and HH in 1,217 RGC by 2030

[Assumption]1) PF, BE, HH Growth Rate:

2.9%/year or 1.986 times from 2006 to 2030

2) A Hammer Mill Service Ratio:174 Households/Hammer Mill

3) 100% Electrification Rate for PF, BE, and HH in 1,217 RGC by 2030

[Socio Economic Survey]

[Socio Economic Survey]

19 Electrified RGCs

71 Unelectrified RGCs

[Socio Economic Survey]

[Socio Economic Survey]

19 Electrified RGCs

71 Unelectrified RGCs

[Technical Aspects Analysis]Unitary Daily Load Estimation[Technical Aspects Analysis]Unitary Daily Load Estimation[Technical Aspects Analysis]Unitary Daily Load Estimation[Technical Aspects Analysis]Unitary Daily Load Estimation

[Social Aspects Analysis]1) Ability to Pay2) Willingness to Pay3) Prioritized Property for Electrification

[Social Aspects Analysis]1) Ability to Pay2) Willingness to Pay3) Prioritized Property for Electrification

[Social Aspects Analysis]1) Ability to Pay2) Willingness to Pay3) Prioritized Property for Electrification

[Social Aspects Analysis]1) Ability to Pay2) Willingness to Pay3) Prioritized Property for Electrification

Policy RecommendationPolicy Recommendation

Completion of Rural Electrification Master Planup to 2030

Completion of Rural Electrification Master PlanCompletion of Rural Electrification Master Planup to 2030 up to 2030

Completion of Rural Electrification Master Planup to 2030

Completion of Rural Electrification Master PlanCompletion of Rural Electrification Master Planup to 2030 up to 2030

Figure 1 Flowchart of Rural Electrification Master Plan Development

2

Page 7: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

3

In the REMP, Rural Growth Center (RGC), a rural locality with a high concentration of residential settlements and the centre of rural economic activities, was selected as the electrification target (refer to Figure 2 regarding the concept of RGC). In the process of “Technical Aspect Analysis”, the “Decentralized Planning Process” was adopted to identify 1,217 RGCs in rural areas as the electrification target. Next, “Demand Criteria (or potential daily maximum demand in each RGC)” and “Supply Criteria (or the “Unit Life Time Cost in Net Present Value”)” were used to cluster (or group) 1,217 RGCs into 180 Project Packages (refer to Figure 3 regarding the concept of Project Package), and to select the optimal electrification mode (among transmission/distribution extension, SHS, mini-hydro, and diesel generator) for each of the 1,217 RGCs. Then, based on the estimated cost for each Project Package, the final electrification priority of 1,217 RGCs in 180 Project Packages was determined by Financial Indicator (FIRR). Finally, these 180 Project Packages were grouped into 22 Annual Project Phases up to 2030, by the uniform annual project cost.

CatchmentCatchment AreaArea of a RGCof a RGC

Rural Growth CentreRural Growth Centre- Public Facilities: School,

Hospital, Post Office etc.- Business Entities: grocery

shop, carpentry workshop, barber/hair saloon, battery charging etc.

- Public Market- Hummer Mill- Households- Local Communities

Rural Village- Households:

farmers, craftsmen etc.

Rural Village

Rural Village

Rural Village

Rural Village

Villagers go to RGC to- Sell their Products at Market- Use Public Services- Purchase Daily Necessities- Mealie Meal, etc.

Villagers bring back from the RGC- Daily Necessities- Mealie Meal- Cash etc.

CatchmentCatchment AreaArea of a RGCof a RGC

Rural Growth CentreRural Growth Centre- Public Facilities: School,

Hospital, Post Office etc.- Business Entities: grocery

shop, carpentry workshop, barber/hair saloon, battery charging etc.

- Public Market- Hummer Mill- Households- Local Communities

Rural Village- Households:

farmers, craftsmen etc.

Rural Village

Rural Village

Rural Village

Rural Village

Villagers go to RGC to- Sell their Products at Market- Use Public Services- Purchase Daily Necessities- Mealie Meal, etc.

Villagers bring back from the RGC- Daily Necessities- Mealie Meal- Cash etc.

Rural Growth CentreRural Growth Centre- Public Facilities: School,

Hospital, Post Office etc.- Business Entities: grocery

shop, carpentry workshop, barber/hair saloon, battery charging etc.

- Public Market- Hummer Mill- Households- Local Communities

Rural Village- Households:

farmers, craftsmen etc.

Rural Village

Rural Village

Rural Village

Rural Village

Villagers go to RGC to- Sell their Products at Market- Use Public Services- Purchase Daily Necessities- Mealie Meal, etc.

Villagers bring back from the RGC- Daily Necessities- Mealie Meal- Cash etc.

Figure 2 Concept of Rural Growth Centre

Project PackageProject PackageProject PackageProject Package

Nearest SubstationNearest Substation

11stst Prioritized RGCPrioritized RGC11stst Prioritized RGCPrioritized RGC

Newly ExtendingNewly ExtendingDistribution LineDistribution LineNewly ExtendingNewly ExtendingDistribution LineDistribution Line

RGCsRGCs RGCsRGCs

Extending Extending Branch LinesBranch Lines

Extending Extending Branch LinesBranch Lines

Figure 3 Concept of Project Package

Page 8: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

In addition, Socio Economic Survey was carried out, in the process of “Social Aspect Analysis.” In the Socio Economic Survey, data were collected more than 1,300 interviewees in 90 RGCs: 71 unelectrified and 19 electrified RGCs. Based on the data collected in the Socio Economic Survey, the ability to pay, willingness to pay, and prioritized property for electrification were analyzed, and these results were used as basic information to elaborate policy recommendation with the involvement of Stakeholders.

The outputs from the Technical and the Social Aspect Analysis were combined to develop a Comprehensive Rural Electrification Program.

4 Results of Master Plan Development Initial findings, results and outputs of this Study are as follows:

1) 1,217 Unelectrified RGCs were clustered (or grouped) into 180 Project Packages. The electrification priority order of 180 Project Packages and the optimal electrification mode for each of 1,217 RGCs are shown in Table 1, and 2 respectively. In Figure 4, the locations of 1,217 RGCs are also shown by each of 9 Provinces.

2) Although not many Project Packages’ FIRR are attractive, considerable number of Project Packages show reasonable EIRR.

3) US$ 1,103 million is required to realize all 180 Project Packages (including 1,217 RGCs) by 2030. This means approximately US$ 50 million per year is needed from 2008 to 2030. The prioritized 180 Project Packages are grouped into 22 Annual Project Phases up to 2030, each requiring US$ 50 million, as shown in Table 3.

4) The target household electrification rate is set as 66.0% nation-wide, requiring a rate of 50.6% for the rural areas. This is achievable if DoE, REA and ZESCO success to increase the household electrification rate at 90% in the urban areas, 100% in 1,217 RGCs in the Master Plan, and 20% in the rural areas other than 1,217 RGCs by 2030 (refer to Table 4). The growth of household electrification rates in urban areas, rural areas, and nation-wide during the REMP period are shown in Figure 5. The cumulative number of electrified RGC and rural electrification rate by 2030 are also shown in Figure 6. It is essential that the Zambian Government makes appropriate investment to the rural electrification projects in the Master Plan to meet these targets.

5) Since the annual amount of Rural Electrification Fund (REF) is much less than the required project cost to realize the Master Plan, in addition to making effort to increase the REF, utilization of the low interest loan from the international donors should be necessary.

6) In the nation wide, 241 RGCs are identified as Solar Home System Market. 7) Although a lot of mini-hydro potential sites exist in Zambia, only 3 sites (Mujila Falls Lower,

Upper Zambezi, and West Lunga in North-western Province) were financially feasible. Locations of these mini-hydro potential sites and supplying RGCs are shown in the Map of North-western Province in Figure 4. Brief specification and construction cost of mini-hydro, and potential demand of supplied RGCs are summarized in Table 5.

8) Unelectrified households and business entities pay considerable amount of money to meet their needs using alternative energy sources (K59,141 and K75,315 respectively). In 2006, the estimated ability to pay for electricity monthly bill for households and business entities are K35,485 and K60,252 respectively.

9) The connection fee charged in rural areas by ZESCO (K2,873,000 for 1 Phase and K4,887,000 for 3 Phase) was much higher than the rural households’ ability to pay (average monthly income by K910,757) and willingness to pay (K2,508,483).

10) Duration (usable daily hours of electricity) was the most important factor for unelectrified residents, compared to Urgency (years until electrified), Monthly Fee, and Connection/Initial Fee. Although 24 hours usage per day was the most preferred, unelectrified residents were eager to use electricity even for 5 hours per day (such as by SHS).

4

Page 9: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 1 Final Electrification Priority of Project Packages by 2030 (1/2)

5

Page 10: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 1 Final Electrification Priority of Project Packages by 2030 (2/2)

6

Page 11: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 2 Electrification Priority of Project Packages by Province (1/12) Central Province

7

Page 12: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 2 Electrification Priority of Project Packages by Province (2/12) Copperbelt Province

8

Page 13: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 2 Electrification Priority of Project Packages by Province (3/12) Eastern Province

9

Page 14: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 2 Electrification Priority of Project Packages by Province (4/12) Luapula Province

10

Page 15: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 2 Electrification Priority of Project Packages by Province (5/12) Lusaka Province

11

Page 16: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 2 Electrification Priority of Project Packages by Province (6/12) Northern Province (1/2)

12

Page 17: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 2 Electrification Priority of Project Packages by Province (7/12) Northern Province (2/2)

13

Page 18: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 2 Electrification Priority of Project Packages by Province (8/12) North-western Province

14

Page 19: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 2 Electrification Priority of Project Packages by Province (9/12) Southern Province (1/2)

15

Page 20: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 2 Electrification Priority of Project Packages by Province (10/12) Southern Province (2/2)

16

Page 21: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 2 Electrification Priority of Project Packages by Province (11/12) Western Province (1/2)

17

Page 22: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 2 Electrification Priority of Project Packages by Province (12/12) Western Province (2/2)

18

Page 23: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

19

Figu

re 4

Lo

catio

n M

ap o

f 1,2

17 R

GC

s by

Pro

vinc

e (1

/9)

Cen

tral

Pro

vinc

e

Page 24: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

20

Fi

gure

4

Loca

tion

Map

of 1

,217

RG

Cs

by P

rovi

nce

(2/9

) C

oppe

rbel

t Pro

vinc

e

Page 25: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

21

Figu

re 4

Lo

catio

n M

ap o

f 1,2

17 R

GC

s by

Pro

vinc

e (3

/9)

East

ern

Prov

ince

Page 26: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

22

Figu

re 4

Lo

catio

n M

ap o

f 1,2

17 R

GC

s by

Pro

vinc

e (4

/9)

Luap

ula

Prov

ince

Page 27: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

23

Figu

re 4

Lo

catio

n M

ap o

f 1,2

17 R

GC

s by

Pro

vinc

e (5

/9)

Lusa

ka P

rovi

nce

Page 28: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

24

Fi

gure

4

Loca

tion

Map

of 1

,217

RG

Cs

by P

rovi

nce

(6/9

) N

orth

ern

Prov

ince

Page 29: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

25

Figu

re 4

Lo

catio

n M

ap o

f 1,2

17 R

GC

s by

Pro

vinc

e (7

/9)

Nor

thw

este

rn P

rovi

nce

Page 30: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

26

F

igur

e 4

Loc

atio

n M

ap o

f 1,2

17 R

GC

s by

Pro

vinc

e (8

/9)

Sout

hern

Pro

vinc

e

Page 31: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

27

Fi

gure

4

Loca

tion

Map

of 1

,217

RG

Cs

by P

rovi

nce

(9/9

) W

este

rn P

rovi

nce

Page 32: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 3 Annual Project Phases by 2030 (1/2)

28

Page 33: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 3 Annual Project Phases by 2030 (2/2)

29

Page 34: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 4 Targeting Electrification Rate in 2030

# of HH HH Ratio # of Elec. HH Elec. Rate # of HH # of Elec. HH Elec. Rate896,234 (39.0%) 426,608 47.6% 1,779,880 1,601,892 90.0%

1,403,408 (61.0%) 43,506 3.1% 2,787,102 1,411,604 50.6%a) 1,216RGCs 535,717 (23.4%) 0 - 1,067,729 1,067,729 100.0%b) Others 867,691 (37.6%) 43,506 3.1% 1,719,373 343,875 20.0%

2,299,642 (100.0%) 470,113 20.4% 4,566,982 3,013,496 66.0%

2030

UrbanRural

Total

2006

52.9%54.7%56.4%58.2%60.0%61.7%63.5%65.3%67.0%68.8%70.6%72.3%74.1%75.9%77.6%79.4%81.2%82.9%84.7%86.5%88.2%90.0%

9.2%13.5%

16.8%19.7%

22.7%25.3%

27.9%30.1%

32.3%34.5%

36.4%38.1%40.0%41.4%42.8%44.3%45.4%46.7%47.8%48.8%49.8%50.6%

26.2%29.6%

32.2%34.7%

37.2%39.5%

41.7%43.8%

45.9%47.8%49.7%51.4%53.3%54.9%56.4%58.0%59.3%60.8%62.2%63.5%64.8%66.0%

0.0%

10.0%

20.0%

30.0%

40.0%

50.0%

60.0%

70.0%

80.0%

90.0%

100.0%

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

Year

Ele

ctrif

icat

ion

Rat

e

Urban Elec. RateRural Elec. RateNational Elec. Rate

Figure 5 Transition of Household Electrification Rates by 2030

63149 202

274330

387445

505 552611

677739

807 850 883 929 9631,0271,060

1,1181,1681,217

9.2%

13.5%

16.8%

19.7%

22.7%25.3%

27.9%30.1%

32.3%34.5%

36.4%38.1%

40.0%41.4%

42.8%44.3%45.4%

46.7%47.8%48.8%49.8%50.6%

0.0%

10.0%

20.0%

30.0%

40.0%

50.0%

60.0%

Ru

trific

0

100

200

300

400

500

600

700

800

900

1,000

1,100

1,200

1,300

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

Year

Cum

ulat

ive

Num

ber o

f Ele

c. R

GC

ral E

lec

atio

n R

ate

Cumulative # of Elec. RGCRural Elec. Rate

Figure 6 Transition of Cumulative Number of Electrified RGCs

and Rural Electrification Rate by 2030

30

Page 35: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 5 Brief Specifications of Mini-Hydro Power Plants (1/2)

1. Mujila Falls Lower

[Design Result] [Electrified Area]Province Northwestern Ikelenge RGC 1995 kWDistrict Mwinilunga Nyakaseya RGC 483 kWName of the Site Upper ZambeziName of the River Zambezi River [Project Cost Estimation]Latitude S11:06:18 I. Construction Cost 1,496,720 US$Longitude E24:13:41 i) Temporary Works 224,360 US$Catchment Area 698 km2 ii) Civil Engineering 677,860 US$80% available discharge 6.44 m3/s iii) Turbine, Gen and Main Transform 364,000 US$Design Discharge 6.0 m3/s iv) Distribution Line & Transformer 230,500 US$Gross Head 9.0 m II. Engineering Service Cost 119,738 US$Effective Head 8.0 m III. Overhead Cost 374,180 US$Generation Capacity 380 kW IV. Profit Margine 299,344 US$Volume of Powerhouse 362 m3 Grand Total 2,289,982 US$Volume of Weir 216 m3

Length of Channel 142 mLength of Penstock 47 mLength of Tailrace 30 mLength of Spillway 60 mLength of Distribution Line 4.5 km

[Design Result] [Electrified Area]Province Northwestern Kanyama RGC 598 kWDistrict Mwinilunga Kakoma RGC 350 kWName of the Site Mujila Falls Lower Mujila Village 234 kWName of the River Mujila River Kapundu Village 233 kW

Total 1,415 kWLatitude S11:30:52Longitude E24:46:24 [Project Cost Estimation]Catchment Area 1,146 km2 I. Construction Cost 6,393,200 US$80% available discharge 9.21 m3/s i) Temporary Works 404,070 US$Design Discharge 10.0 m3/s ii) Civil Engineering 1,070,230 US$Gross Head 18.0 m iii) Turbine, Gen and Main Transfor

m 1,158,000 US$Effective Head 17.1 m iv) Distribution Line & Transformer 3,760,900 US$Generation Capacity 1,400 kW II. Engineering Service Cost 511,456 US$Volume of Powerhouse 596 m3 III. Overhead Cost 1,598,300 US$Volume of Weir 450 m3 IV. Profit Margine 1,278,640 US$Length of Channel 210 m Grand Total 9,781,596 US$Length of Penstock 23 mLength of Tailrace 20 mLength of Spillway 36 mLength of Distribution Line 98 km

2. Upper Zambezi

31

Page 36: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Table 5 Brief Specifications of Mini-Hydro Power Plants (2/2)

3. West Lunga [Design Result] [Electrified Area]Province Northwestern Mwinilunga BOMA 2,093 kWDistrict MwinilungaName of the Site West Lunga [Project Cost Estimation]Name of the River West Lunga I. Construction Cost 5,746,043 US$Latitude S11:47:37 i) Temporary Works 178,524 US$Longitude E24:26:56 ii) Civil Engineering 2,385,271 US$Catchment Area 5,460 km2 iii) Turbine, Gen and Main Transform 3,023,918 US$95% available discharge 35 m3/s iv) Distribution Line & Transformer 158,330 US$Design Discharge 20.0 m3/s II. Engineering Service Cost 498,890 US$Gross Head - III. Others 1,227,703 US$Effective Head 14.5 m Grand Total 7,472,636 US$Generation Capacity 2,500 kWVolume of Powerhouse 1130 m3

Volume of Weir - m3

Length of Channel 1500 mLength of Penstock - mLength of Tailrace - mLength of Spillway - mLength of Distribution Line 6.5 km

32

Page 37: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

5 Recommendation

5.1 Practical Use of Master Plan

Although the final electrification priority of Project Packages were determined by Financial Indicator (FIRR) in the REMP, the priority should be modified in practice and updated by taking into account the opinions of Zambian Government and Financial Organization, such as in the financial coordination with International Development Partners. For example, Zambian Government may wish to pay attention to the balance of development among areas/Provinces. Some of Financial Organizations may also wish to apply some project selection criteria as their loan conditions. Therefore, the staff members of DoE and REA need skills to merge the new criteria with the original Master Plan in a flexible way. Such skills and techniques could be transferred under the JICA Technical Cooperation Project scheduled to commence in 2008.

Since financial evaluation for SHS portion in each Project Package was excluded in the REMP, International Donors may not be willing to provide financial assistance for SHS projects. They may, for instance, wish to finance a Project Package with high priority ranking but excluding RGCs electrified by SHS in a Package. Even in such a case, however, maintaining an electrification priority order of SHS portion according to the priority of a Project Package, by providing subsidy utilising Rural Electrification Fund (REF) for SHS installation to households and business entities, is suggested. Regarding public facilities (such as school and hospital/clinic) in RGCs electrified by SHS, the installation cost is assumed to be provided from the Government Authorities (such as Ministry of Education and Ministry of Health).

5.2 Management of Rural Electrification Fund

The REF as currently funded is not sufficient to implement the REMP, and thus measures are needed to increase REF and methods of efficient and effective utilization of funds need to be considered. Firstly, the Zambian Government should allocate an adequate budget every year toward the REF as it does for other infrastructures, such as health and road sector. Secondly, the Rural Electrification Levy should be charged to the mining sector (which consumes 50% of the national total) and to the export of electricity. At the time of writing, it was uncertain what percentage of levy should be charged to the mining sector, other industries and electricity export, but the Zambian Government was considering 5% electricity levy for them as a measure towards social responsibility, while the levy by the domestic consumers would remain at 3%. Thirdly, the REF needs to be efficient and effective in its management in order to ensure that the program runs smoothly. Such measures are also likely to attract the interest of Development Partners. Therefore, more transparency, accountability and efficiency are required in the process of electrification project selection and utilization of the REF. Fourthly, the electrification levy should be paid directly to REA, not through the Ministry of Finance and National Planning. Otherwise, the possibility remains that the rural electrification levy will be used for other purposes by the Government (such as a general account budget). Finally, electrification facilities funded by the REF (such as mini-hydro, but exclude SHS) should be owned by either REA or ZESCO, and leased to other private companies or local communities for O&M, if necessary.

5.3 Increase of Electricity Access Rate

A high initial connection fee is one of the hindrances to increase electricity access, even in areas where distribution line has been extended. The tariff charged by utility companies should be capital cost reflective and thus reduction of the initial connection fee should be considered. In addition, the payment of initial connection fee by the consumers to the electricity network should be spread over a period of 3 to 5 years.

Setting up a technical standard for appropriate low cost electrification method could also contribute to increase the electrification rate in rural areas. Moreover, exemption of import tax for equipments used for rural electrification gives the advantage of reduced project cost and connection fee.

33

Page 38: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating

Summary Report

Finally, to create a price competitive market, supporting capacity development and formation of new companies to undertake rural electrification business, such as construction and operation & maintenance is recommended.

5.4 Supporting Sustainable Electrification Business in Rural Area

Development of local capacity in simple operation and maintenance of electricity systems, such as SHS and mini-hydro, through a mobile training program provided by DoE and REA could contribute to making the rural electrification business sustainable. Development of the mobile training programs could be supported by JICA Technical Cooperation Project scheduled to commence in 2008.

34

Page 39: REMP for Zambia Final Report Summary · 2008-02-06 · Summary Report 1. Background Rural electrification has long been identified as a vehicle to eradicate poverty by stimulating