37
ReliabilityFirst 3/6/08 RC Meeting 1 Reliability Standards Update ReliabilityFirst Corporation RFC Compliance Workshop Columbus, Ohio September 29 & 30, 2008 Presented By: Bob Millard

Reliability Standards Update Reliability First Corporation RFC Compliance Workshop Columbus, Ohio

  • Upload
    minh

  • View
    41

  • Download
    2

Embed Size (px)

DESCRIPTION

Reliability Standards Update Reliability First Corporation RFC Compliance Workshop Columbus, Ohio September 29 & 30, 2008 Presented By: Bob Millard. What’s Up at the Board. The following will be discussed at the RFC Board meeting in Chicago 10/8/08 - PowerPoint PPT Presentation

Citation preview

Page 1: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 1

Reliability Standards Update

ReliabilityFirst Corporation

RFC Compliance Workshop

Columbus, Ohio

September 29 & 30, 2008

Presented By: Bob Millard

Page 2: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 2

What’s Up at the Board

The following will be discussed at the RFC Board meeting in Chicago 10/8/08

• Automatic Reserve Sharing (BAL-501-RFC-01)

– Day One standard approved 12/12/05

– SAR stated “standard” no longer needed for reliability

– Map to RTO documents showed complete overlap

– Unanimous vote to retirement

Page 3: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 3

What’s Up at the Board

• Operating Reserve (BAL-002-RFC-02)

– Day One standard approved 12/12/05 & revised 5/9/07

– Establish optional methodology per NERC BAL-002

– Submitted for NERC/FERC approval process

– NERC comments focused on % of spinning fulfilled by interruptible

– Recommend reclassify as regional CRITERION until NERC makes a final decision on whether revised BAL-002 needs support by regional standard

Page 4: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 4

What’s Up at the Board

• Disturbance Monitoring (PRC-002-RFC-01)

– Regional standard support shown in NERC Standards Work Plan

– Referenced in NERC Board approved PRC-002 (a Fill-in-the-Blank standard)

– Referenced in FERC approved PRC-018

– Used as a starting point by NERC drafting team

– NERC 1st draft still to be posted

– RFC standard will replace legacy documents

Page 5: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 5

What’s Up at the Board

• Disturbance Monitoring (continued)

– Did not pass 1st or 2nd ballot after 7 comment postings

– Major issue: Joint responsibility (TO and GO) for DME installations at generating facility interface

– Drafting team proposes to have RFC Board remand back to team to remedy major issue

– Drafting team remedy - monitoring provided by owner of monitored equipment (arrangements can still be made as to who owns DME)

– Informal survey by team suggests additional posting and ballot would be successful

Page 6: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 6

RFC Standards

• Resource Adequacy (BAL-502-RFC-02)

– Day Two standard approved by RFC Board 3/9/06

– ACTION PLAN to revise standard approved by RFC Board 8/9/07

• Based on legal advise

– Remove enforcement of requirement to secure resources

– Limit enforcement to reserve requirement analysis and assignment

Page 7: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 7

RFC Standards

• Resource Adequacy (continued)

– ACTION PLAN included:

• Addition of significant improvements from RFC experience & MRO development through MRO Board approval

• Modifications to conform to current RFC Standards Procedure (such as Violation Risk Factors)

– Supplemental SAR approved after 1st comment posting of proposed revision to revise applicability

Page 8: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 8

RFC Standards

• Resource Adequacy (continued)

– 2nd comment posting completed 9/16/08 and included:

• Removal of reference to LSE or PRSG due to removal of enforcement of securing reserves

• Addition of PC to reflect new focus of standard toward analysis

– Revised standard ready for balloting and preparation for action by RFC Board at December meeting

Page 9: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 9

RFC Standards

• Gen MW verification (MOD-024-RFC-01)

– Based on 3/10/06 SAR by Day Two team

– Replace legacy documents per intent of By-laws

– Comply with NERC “fill-in-the-blank” NERC MOD-024-1

– FERC confirmed “warrant continued monitoring”

– Provide verification for “planning reserve” analysis

– NERC drafting underway but no posting yet

– Fill gap until NERC complete (possible 2 years)

– Used as starting point for NERC drafting team

Page 10: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 10

RFC Standards

• Gen MW verification (continued)

– 4th comment posting completed 9/11/08

– Major applicability issue removed by defaulting to unit size values specifically listed in NERC Compliance Registry Guidelines

– SDT reviewing comments to determine next move

– Comments now range from “requirements are too detailed” to “not detailed enough”

– ULTIMATELY when NERC standard is approved, RFC requirements will be retired or become a variance in the NERC standard

Page 11: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 11

RFC Standards

• Gen MVAR verification (MOD-025-RFC-01)

– Based on 3/10/06 SAR by Day Two team

– Replace legacy documents per intent of By-laws

– Comply with NERC “fill-in-the-blank” NERC MOD-025-1

– FERC confirmed “warrant continued monitoring”

– NERC drafting underway but no posting yet (scheduled behind NERC MOD-024-1)

– Fill gap until NERC complete ( 2+ years)

– Used as a starting point by the NERC drafting team

Page 12: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 12

RFC Standards

• Gen MVAR verification (continued)

– 2nd comment posting completed 8/31/08

– Variety of comments reflect the technical complexity of the standard

– SDT reviewing comments to determine next move

– ULTIMATELY when NERC standard is approved, RFC requirements will be retired or become a variance in the NERC standard

Page 13: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 13

RFC Standards

• Under Frequency Load Shed (PRC-006-RFC-01)

– RFC Board approved Day Two standard rescinded early 2006 due to generator requirement ambiguity carried over from legacy documents

– Day Two 2/10/06 SAR initiated drafting

– Replace legacy documents per intent of By-laws

– Comply with NERC “fill-in-the-blank” NERC PRC-006-1

– FERC confirmed “warrant continued monitoring”

Page 14: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 14

RFC Standards

• Under Frequency Load Shed (continued)

– NERC initial comment posting completed 8/15/08 stated that regional standard was required

– RFC 4th comment posting ends 10/4/08

– Major issues addressed: Applicability goes beyond Compliance Registry Criteria and issues dealing with areas of credible islanding

– Direction of RFC draft agrees with NERC initial draft

Page 15: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 15

Waiting in the Wings

• RFC SARs & SDT in queue – Sub-Regional Transmission Adequacy

Requirements SAR

• Complements RFC Resource Adequacy standard

• Developed with initial Resource Adequacy effort

• Intended to provide some level of confidence that transmission will be available for delivery

• Considers probability of transmission outage

• Establishes deliverability criteria to achieve a transmission import capability level for each sub-region to achieve an acceptable reliability level

Page 16: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 16

Waiting in the Wings

• RFC SARs & SDT in queue (continued)

– Special Protection System Requirements SDT• In line with NERC “fill-in-the-blank”

NERC PRC-012-0• Regional standard support shown in NERC

Standards Work Plan

• RFC has approved “procedure” today

• Also considers need for conditions on installation and duration (already discussed by NERC TPL SDT for consideration in draft)

Page 17: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 17

Waiting in the Wings

• RFC SARs & SDT in queue (continued)

– Blackstart Capability Plan SAR

• Intended to detail and enhance the system Blackstart Capability Plan (BCP) requirements stated in the NERC EOP standards and RFC EOP-007-RFC-01

• NERC Project 2006-03 well underway covers EOP-005 — System Restoration Plans

EOP-006 — Reliability Coordination - System Restoration

EOP-007 — Establish, Maintain, and Document a Regional

Blackstart Capability Plan

EOP-009 — Documentation of Blackstart Generating Unit Test

Results

Page 18: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 18

Waiting in the Wings

• RFC SARs & SDT in queue (continued)

– Sub-Regional Transmission Adequacy Requirements SAR

• Wait for outcome of Resource Adequacy standard and consider RTO practices

– Special Protection System Requirements SDT

• Wait for TPL & NERC Project 2010-05 activity

– Blackstart Capability Plan SAR

• Since NERC posted 3rd draft Spring 2008, may need to delete & modify related RFC standard

Page 19: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 19

We continue to evolve

Questions ON RFC

“STANDARDS”?

Our Goal

RELIABILITY

Page 20: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 20

Outside RFC Standards

WHAT’S UP AT NERC?

WHAT’S FERC DOING?

WHO’S IN CHARGE?

WHAT DO I WATCH FOR?

CAN I MAKE A DIFFERENCE?

Page 21: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 21

Understanding Standards

Legal

Purist

Out of Box

Folksy

Gut feel

Comfort Zone

Operating Manual

Planning Standards

Version 0

Improvement

Functional Model

Reliable System Customer Needs

Page 22: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 22

Understanding the FM

• Functional Model concept

– Start from clean slate

– Develop a group of “functions” that are needed to make the overall system work

• Realize that there can be more than one set of functions that can work

• Divorce from corporate structure but make sure they will blend

– FM provided basis/guideline for Version 0

Page 23: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 23

Understanding the FM

• FM continues to evolve

• Version 4 completing approval process through Standing Committees and on to NERC Board

• Latest Version 4 as presented to Committees includes original proposed changes, i.e. LSE, DP, GOP, etc but fell back to “planning functions” as stated in Version 3

• “Planning functions” will be major focus of Version 5 for next Spring

• “Planning functions” did not blend with structure across continent

Page 24: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 24

Understanding Compliance Registry Guidelines

• Registry created to administer technically based requirements established for applicable entities as specified in the standards using the FM as a guide

• Registry created to inform entities who will be monitored from a practical stand-point

• Registry does not list monitored facilities – but criteria can be used as default or specified in standard based on technical need

• Registry criteria can be driven/changed by technical needs of standards

Page 25: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 25

Understanding Standards

SO NOW YOU KNOW

• Where the terms came from

• All the components there had to be considered in drafting

• How entities are earmarked for compliance initially

• And what you know today may change tomorrow

• This presents a real opportunity to test your understanding and flexibility

Page 26: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 26

What’s Up at NERC

• What is NERC’s GRAND SCHEME ?– Reliability Standards Development Plan

alias Three year (???) Work Plan: 2009-2011

– Updated annually

– Presented by usual e-mail, at Standing Committees, at Standards Workshop

– Presented by WEBEX

• 8/28/08 slides at NERC website under “About Standards: Development Plan”

– Industry comments and suggestions solicited for gaps, priorities, improvement, new items

Page 27: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 27

“Work Plan”

• What is NERC’s GRAND SCHEME ?

– Volume I: Overview

• Plan Description – high level list of “Projects”

• Modifications since last revision

• FERC 15 point review list for approving standards

• General information on the how, why & what of standards

• Industry comments that helped create latest version

Page 28: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 28

“Work Plan”

• What is NERC’s GRAND SCHEME ?

– Volume II: List of “Projects”

• Tabulation listing each standard and indicating what Project it is part of

• Tabulation listing each Project and indicating which standards are included

• A selection is allocated to each Project giving its description, status, schedule and issues to be considered

Page 29: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 29

“Work Plan”

• What is NERC’s GRAND SCHEME ?

– Volume III: Regional Reliability Standards Projects

• Identifies 4 NERC standards anticipated to be supported by regional standards

– Project 2007-01 — Underfrequency Load Shedding (PRC-006)

– Project 2007-05 — Balancing Authority Controls (BAL-002)

– Project 2007-11 — Disturbance Monitoring (PRC-002)

– Project 2010-05 — Protection Systems {SPS} (PRC-003)

Page 30: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 30

“Work Plan”

• What is NERC’s GRAND SCHEME ?

– Volume III: Regional Reliability Standards Projects

• Identifies, by region, the regional reliability standards being developed

• NOTE: The term “standard” means that the requirements being developed are expected to be submitted for the regional/NERC/FERC approval process to received enforcement under law

The term “criterion” means that the requirements only apply to members of the region or other contract agreed to membership

Page 31: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 31

“Work Plan”

• What is NERC’s GRAND SCHEME ?

– How can I find the latest status of any one Project knowing that there are 39 active teams working right now?

– NERC website under “Standards” then under “Standards Under Development”

– Dave Taylor, Manager of Standards, prepares a monthly XCEL worksheet “Project Summary” for the NERC Standards Committee

– Part of NERC SC minutes (soon to have separate link????)

Page 32: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 32

Voluntary to Mandate

• What’s FERC’s involvement ?– Another layer of approval and commenting has been

added.

– FERC approval process is fairly obvious & related to legal and ERO processes

– INDUSTRY PARTICIPANTS MUST BE WATCHFUL FOR COMMENTING ON FERC ORDERS RELATED TO STANDARDS

– IF INDUSTRY DOES NOT FILE WITHIN 30 DAYS NOTICE on Directives in Orders to change “standards” or provide for the same intent are considered, IT IS ASSUMED INDUSTRY AGREES.

Page 33: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 33

Variance

• NERC Rules of Procedure and Standards Development Procedure sites “Variance”

Note: The term “difference” was changed August 2006

• A different or alternative way to meet the intent of a NERC standard requirement

– If it is the same, then there is no variance

– If it is needed not for meeting a NERC requirement, then it’s a local requirement

Page 34: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 34

Variance

• Who may ask for Variances?

– An Interconnection (e.g. WECC in FAC standard)

– A Region (Regional Entity, not the RRO)

– A sub-region

– Any entity that does things differently (e.g. MISO, PJM and SPP in the TLR standard)

• Variance can be added while drafting is underway

• If no drafting in progress, a SAR is needed

Page 35: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 35

Variance

• Example of a Variance?

– NERC standard requires at least 5% of “X” to be compliant

– An entity, let’s say an RE, requires at least 2% of “X”

– Since they both want a % of “X”, the 2% is a Variance

• If RFC drafts a standard on Resource Adequacy that is not covered by a NERC standard, it is a regional standard and not a Variance

• Request for Variance is a routine question for posting

Page 36: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 36

NERC Summary

• So keep an eye on the NERC Work Plan

• Keep an eye on the FERC Orders

• Keep an eye on postings for comment

• Participate on SDTs to help steer the team

• Submit comments, before the ballot, even if you agree, otherwise the draft will go a different way

• The opportunities are endless and challenging but once we get over first pass, we will know what we need to do to keep the lights on.

Page 37: Reliability Standards Update Reliability First  Corporation RFC Compliance Workshop Columbus, Ohio

ReliabilityFirst 3/6/08 RC Meeting 37

We continue to evolve

Questions?

Our Goal

RELIABILITY