17
1 August 14, 2003 Blackout Summary based on NERC reports, Power System Engineering Research Center Report, and DOE Reports 2 Overview Overview of power system and reliability Pre-outage conditions on August 14 Trigger events and start of cascade Wide area cascade Root causes Canada Restoration Activities 3 Reliability Overview Balance generation and demand Balance reactive power supply and demand Monitor flows and observe thermal limits Observe power and voltage stability limits Operate for unplanned contingencies Plan, design and maintain a reliable system Prepare for emergencies Reliably operate the system you have! 4 3 Interconnections / 10 NERC Regions 5 NERC Control Areas 6 NERC Reliability Coordinators

Reliability Overview 3 Interconnections / 10 NERC Regions · 1 August 14, 2003 Blackout Summary based on NERC reports, Power System Engineering Research Center Report, and DOE Reports

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

1

August 14, 2003 Blackout

Summary based on NERC reports, Power System Engineering

Research Center Report, and DOE Reports

2

Overview

● Overview of power system and reliability● Pre-outage conditions on August 14● Trigger events and start of cascade● Wide area cascade● Root causes● Canada Restoration Activities

3

Reliability Overview

● Balance generation and demand● Balance reactive power supply and demand● Monitor flows and observe thermal limits● Observe power and voltage stability limits● Operate for unplanned contingencies● Plan, design and maintain a reliable system● Prepare for emergencies

Reliably operate the system you have!

4

3 Interconnections / 10 NERC Regions

5

NERC Control Areas

6

NERC Reliability Coordinators

2

7

Footprints of Reliability Coordinators in Midwest

8

Blackout Statistics60 Million people in 8 states and 2

provincesAlmost 62,000 Mw of load

PJM Interconnection – 4,000 MwMidwest ISO – 18,500 MwHydro Quebec – 100 MwOntario IMO – 21,000 MwISO New England – 2,500 MwNew York ISO – 24,400 Mw

34,000 Miles of Transmission290+ Generating Units

9

August 14 Conditions Prior to Blackout● Planned outages

Cook 2, Davis Besse nuclear plantsEast Lake 4, and Monroe 1

● Transfers high to northeast U.S. + OntarioNot unusually so and not above transfer limits

● Critical voltage dayVoltages within limitsOperators taking action to boost voltages

● FrequencyTypical for a summer day

● System was within limits prior to 15:05, on both actual and contingency basis

10

Warm But Not Unusual for August

11

August 14 Imports to Northeast-Central Compared to 6/1 to 8/13/2003

-8000

-6000

-4000

-2000

0

2000

4000

6000

0:00

2:00

4:00

6:00

8:00

10:00

12:00

14:00

16:00

18:00

20:00

22:00

Hour (EDT)

MW

Max ImportsMax ExportsAverage14-Aug

Impo

rtsEx

ports

16:00

12

Pre-Blackout Loads, Generation and Interchange

3

13

Voltages Prior to 15:05 EDT August 14

14

Frequency Typical for Summer Day

15

Blackout Sequence of Events

16

Characteristics of a Disturbance● Frequency excursions

Generation > Load = Frequency RiseGeneration < Load = Frequency Decline

● Voltage Excursions (in the blackout region)

Declines, leading to voltage collapse in some areas− Insufficient reactive power (VARs) is the

principal reason for voltage decline and collapse

Overvoltages after load trips

17

Frequency in Chattanooga, TN

18

Frequency excursions in the Midwest

4

19

Frequency in Ann Arbor, MI

20

Unusual Voltage Problems

21

“Softswitching Technologies – I-grid Monitors”

22

“Softswitching Technologies – I-grid Monitors”

23

“Softswitching Technologies – I-grid Monitors”

24

Voltage Collapse on Staten Island

5

25

Blackout was NOT Caused by

● Heavy wide-area transfers● Low voltages, voltage collapse● Lack of IPP voltage/reactive support● Frequency anomalies● Cinergy outages starting at 12:08● East Lake 5 trip at 13:31

Contributing factor to later events, but not by itself causal to the blackout

● DPL Stuart-Atlanta trip at 14:02Contributing factor to loss of MISO real-time monitoring, but not electrically significant 26

Blackout Sequence – Phase 1

27

Outage Sequence of EventsTransmission Map Key

ONTARIO

Transmission Lines

765 kV500 kV345 kV230 kV

Transmission Lines

765 kV500 kV345 kV230 kV

28

East Lake 5 Trip: 1:31:34 PM

ONTARIO

2

1

ONTARIO

29

East Lake 5 Exciter Failure Causes Trip

30

Stuart Atlanta Trip: 2:02 PM

ONTARIO

6

31

System Operator Comments

● Phone call from Cinergy operator to MISO Operator at 2:36pm:

“I hate to worry you, but I think we’re a trip away from … setting a little history.”

32

MISO State Estimator and Reliability Analysis

● MISO state estimator and contingency analysis ineffective from 12:37 to 16:04

State estimator not solving due to missing information on lines out in Cinergy then DPLHuman error in not resetting SE automatic trigger

● Using Flowgate Monitoring tool to monitor conditions on previously identified critical flowgates

33

FirstEnergy Computer Failures

● 14:14 Alarm processing subsystem fails and operators are not aware

No further status changes or alarms to FE operatorsReal-time displays no longer show current information

● 14:20 Several remote consoles fail● 14:41 EMS server hosting alarm processor and other

functions fails to backup● 14:54 Backup server fails

EMS continues to function but with very degraded performance (59 second refresh)FE system data passed normally to others: MISO and AEPAGC function degraded and strip charts flat-lined

● 15:08 IT warm reboot of EMS appears to work but alarm process not tested and still in failed condition

● No contingency analysis of events during the day including loss of East Lake 5 and subsequent line trips

34

Phone Calls between MISO and First Energy

● 3:36pm – MISO asks “… what is going on over there?”

● First Energy says they are unsure.● MISO replies, “I wonder what is

going on here. Something strange is happening.”

35

Phone Calls to FirstEnergy

● FE received calls from MISO, AEP, and PJM indicating problems on the FE system but did not recognize evolving emergency

14:32 AEP calls regarding trip and reclose of Star-S. Canton15:19 AEP calls again confirming Star-S. Canton trip and reclose15:35 Calls received about “spikes” seen on system15:36 MISO calls FE regarding contingency overload on Star-Juniper for loss of Hanna-Juniper15:45 FE tree trimming crew calls in regarding Hanna-Juniper flashover to a treePJM called MISO at 15:48 and FE at 15:56 regarding overloads on FE system

36

Phone Calls to FirstEnergy

● First Energy told MISO that the voltage on a major line was dangerously low. “Do you have any idea what is going on?”

● MISO replied that the Hanna-Juniper line was out, adding “I am wondering if it is still out.”

● “We have no clue” First Energy replied. “Our computer is giving us fits too. We don’t even know the status of some of the stuff around us.”

● MISO comments: “I can’t get the big picture of what’s going on. Strange things are all happening at the same time.”

7

37

“You’re On the Air!”

38

“You’re On The Air!”

39

Blackout Sequence – Phase 2

40

Chamberlin-Harding (3:05:41)

41

Chamberlin-Harding Indication of Ground Fault Due to Tree Contact as Measured by DFR at Juniper

42

(3:05:41) Hanna-Juniper(3:32:03)

8

43

Hanna Juniper Confirmed as Tree Contact atLess than Emergency Ratings of Line

44

“LEGAL” RESTRICTIONS ON VEGETATION MANAGEMENT--BEFORE

45

“LEGAL” RESTRICTIONS ON VEGETATION MANAGEMENT--AFTER

46

Effects of Ambient Conditions on Ratings

47

(3:05:41)(3:32:03)

Star- S. Canton (3:41:35)

48

Situation after Initial Trips 3:05:41 – 3:41:35

ONTARIO

9

49

Canton Central – Tidd(3:45:41)

50

138 kV Lines Overload and Cascade Near Akron

Simulated 138 kV Line Loadings

0

20

40

60

80

100

120

140

160

180

200

Outages

% o

f Nor

mal

Rat

ings

(Am

ps)

Dale-W.Can138 kV

W.Ak-PVQ22 138 kV

Cham-W.Ak138 kV

E.Lima-N.Fin 138 kV

CantC Xfmr

W.Ak-PVQ21 138 kV

Babb-W.Ak138 kV

E.Lima-N.Lib 138 kV

Clov-Torrey138 kV

Dale-W

.Can

138 kV

W.A

k 138 kVB

kr Failure

E.Lima-N

.Fi n138 kV

CantC

Xfmr

W.A

k-PV Q21

138 kV

Babb-W

.Ak

138 kV

E.Lima-N

.Li b138 kV

Clov-Torre y

138 kV

Star-S.Cant

345 kV

Hanna-Jun

345 kV

Hard-C

hamb

345 kV

Cham

-W.A

k138 kV

5115:05:41 ED

T

15:32:03 EDT

15:41:35 EDT

15:51:41 EDT

16:05:55 EDT

0

20

40

60

80

100

120

140

% o

f Nor

mal

Rat

ings

Canton C

entral Transformer

Babb-W

.Akron 138 kV H

arding-C

hamberlin

Hanna-

Juniper

Star-S.Canton

Cloverdale-Torrey 138 kV

E.Lima-N

ew Liberty 138 kV

W.Akron-Pleasant Valley 138 kV

E.Lima-N

.Finlay 138 kV

Cham

berlin-W.A

kron 138 kV

W.A

kron 138 kV Breaker

Dale-W

.Canton 138 kV

Sammis-Star

138 kV Cascade Contributes Furtherto Overload of Sammis-Star

52

Sammis-Star(4:05:57.5)

53

Sammis-Star Zone 3 Relay Operateson Steady State Overload

54

Actual Loading on Critical Lines

0

400

800

1200

1600

12:00 13:00 14:00 15:00 16:00

Time - EDT

Flow

s (M

W)

Harding - ChamberlinHanna - JuniperStar - South CantonSammis - Star

East Lake 5 Trip

Harding - Chamberlin Line Trip

Hanna - Juniper Line Trip

Sammis - Star Line Trip

Star - South Canton Line Trip

10

55

Actual Voltages Leading to Sammis-Star

250

270

290

310

330

350

370

15:00 16:00Time - EDT

Vol

tage

(kV)

Star

Hanna

Beaver

Perry

100% Voltage

95% Voltage

90% Voltage

Sammis - Star 345 kV Line Trip

Star - South Canton345 kV Line Trip

Hanna - Juniper345 kV Line Trip

Harding - Chamberlin345 kV Line Trip

Gaps in Data Records

56

Cascade Sequence 1

57

Major Path to Cleveland Blocked after Loss of Sammis-Star 4:05:57.5 PM

RemainingPaths

58

Cascade Sequence 2

59

345 kV Lines Trip Across Ohio to West

ONTARIO

60

Generation Trips 4:09:08 – 4:10:27 PM

ONTARIO

11

61

Cascade Sequence 3

62

345 kV Transmission Cascade Moves North into Michigan 4:10:36 – 4:10:37 PM

63

Blackout Sequence – Phase 3

64

Cascade Sequence 4

65

Cascade Sequence 5

66

Northern Ohio and Eastern Michigan Served Only from Ontario after 4:10:37.5 – 4:10:38.6 PM

12

67

Cascade Sequence 6

68

Power Transfers Shift at 4:10:38.6 PM

69

Blackout Sequence – Phase 4

70

Cleveland – Toledo Island 4:10:39 - 4:10:46 PMCleveland Blacks Out

71

Eastern Eastern Michigan (Detroit) UnstableVoltage and Frequency Collapse and Pole Slipping

Ontario – Michigan Interface Flow and Voltages Beginning 16:10:38

72

Generator Trips to 16:10:38

13

73

Generator Trips – Next 7 Seconds

74

Overloads on PJM – NY Ties 4:10:39 PM

75

PJM – NY Separating 4:10:44 PM

76

Northeast Completes Separation from Eastern Interconnection 4:10:43 – 4:10:45 PM

North of LakeSuperior

77

Conditions at Niagara Indicate Progressively Worsening Stability Conditions with Prior Events

78

Island Breaks Up: 4:10:46 – 4:13 PM

14

79

Cascade Sequence 7

80

Frequency in Ontario and New York during BreakupNiagara Generation Stays with Western NY

81

Frequencies in Separated Areas

82

Generator Trips – After 16:10:44

83

Cascade Sequence 8

84

Areas Affected by the BlackoutService maintained

in some area

Some Local Load Interrupted

End of the Cascade

15

85

The August 14th Outage

Before After

86

87

Blackout Root Cause Group 1FE Situational Awareness

● FE did not ensure a reliable system after contingencies occurred because it did not have an effective contingency analysis capability

● FE did not have effective procedures to ensure operators were aware of the status of critical monitoring tools

● FE did not have effective procedures to test monitoring tools after repairs

● FE did not have additional high level monitoring tools after alarm system failed

88

Blackout Out Root Cause Group 2Vegetation Management

● FE did not adequately manage tree growth in its transmission rights of way

89

Blackout Out Report: Vegetation Management

90

Blackout Out Report: Vegetation Management

16

91

Blackout Out Report: Vegetation Management

92

Blackout Out Report: Vegetation Management

93

Blackout Out Report: Vegetation Management

94

Blackout Out Report: Vegetation Management

95

Blackout Out Report: Vegetation Management

Some Reported Problems:

Otter Tail Power: FWS and DNR repeatedly planted trees in ROW

Pacificorp: DOT planted trees in ROW, would not allow them to be pruned

NY Environmental Dept requires filing for a “temporary revocable permit” to trim trees, requires 2 years to process application

96

Blackout Cause Group 3Reliability Coordinator Diagnostics

● MISO’s state estimator failed due to a data error.

● MISO’s flowgate monitoring tool didn’t have real-time line information to detect growing overloads

● MISO operators couldn’t easily link breaker status to line status to understand changing conditions.

● PJM and MISO ineffective procedures and wide grid visibility to coordinate problems affecting their common boundaries

17

97

North America Blackout Characteristics