Release Control with PowerCenter Release Control with PowerCenter at UBS / Switzerlandat UBS / Switzerland
Friedrich LehnFriedrich LehnConfiguration & Release ManagerConfiguration & Release ManagerOctober 2000October 2000
AgendaAgenda
Project Overview PowerCenter Configuration Configuration Management Deployment Process Release Process Summary
Project OverviewProject Overview
Global, integrated investment services firm offering- the full range of wealth management, asset management, investment banking and securities services- to the full spectrum of clients
World’s largest private bank
Top ten financial services firm by market capitalization- $62 billion dollars
Total client assets of US$1 trillion
UBSUBS
Project OverviewProject Overview
System EnvironmentsSystem Environments
DevelopmentDevelopment ProductionProductionTestTest
IBM AIX SP2 cluster DB2 UDB EEE PowerCenter 1.6
Project OverviewProject Overview
Load ProcessLoad ProcessFile
Preprocessing
Conditioning
AutoLoader
PowerCenter
SQL Apply
AutoLoader
System of Records
Common Data Warehouse
Project OverviewProject Overview
Main organizational element
Three letter acronym as base for naming standards
Each delivery stream gets the same infrastructure:UNIX directories, meta data area, PowerCenter folders
Each delivery stream has business responsible, data modeler, database administrator, delivery stream manager
Team size typically between 1 and 5
Delivery streams release independently from each other
Delivery StreamDelivery Stream
Project OverviewProject Overview
Application StructureApplication Structure
Delivery streams:
RCL release control toolsMDR meta data repositoryDSF DWP sourcing frameworkFDS feed specific data processing<SDA> subject data area<MAR> data mart
<MAR> <MAR>......
RCL MDR FDS
System of Records
DSFDSF
DWP Sourcing Framework
<SDA> <SDA>...
Common Data Warehouse
Project OverviewProject Overview
Two areas:/dwp_root UNIX based files, version controlled/dwp_data dynamic data, archival on demand
Additional directory level for the environment in order to support more than one environment on one system
/dwp_root is organized by delivery streams
Directory StructureDirectory Structure
Project OverviewProject Overview
/dwp_data is organized by logical processing stepsand by delivery streams
Symbolic links from PowerCenter program areato /dwp_data
Tool support for generation of directories(delta processing, integration with release procedures)
Directory Structure (continued)Directory Structure (continued)
PowerCenter ConfigurationPowerCenter Configuration
Start with one single (local) repository
Support different, clearly separated environments with different responsibilities
All environments have identical structure (products, databases, PowerCenter server configurations)
All program changes (UNIX, PowerCenter) are done on the development system
All changes on test and production systems go through the release process and are clearly tracked
Design PrinciplesDesign Principles
PowerCenter ConfigurationPowerCenter Configuration
Repository StructureRepository Structure
D S V S A S P
Server Server Server
D developmentS stagingV versioningA integration / user acceptance testP production
PowerCenter ConfigurationPowerCenter Configuration
Folder StructureFolder Structure
Release area is identical in all environments.
user area
(avoid shortcuts)
team area
release area
PowerCenter ConfigurationPowerCenter Configuration
developer development, unit and integration testing
delivery stream manager manager, release planning
release manager deployment, tracking, configuration controlPowerCenter administration
session manager session management for testand production systems
Roles and ResponsibilitiesRoles and Responsibilities
Role Responsibility
Configuration ManagementConfiguration Management
External tool for software configuration management (Rational Corporation)
Powerful version control, work space andbuild management
Same directory structure as in development environment
Fully automated access layer
ClearCaseClearCase
Configuration ManagementConfiguration Management
Integrate all release specific data:sourcing framework, DDL, documentation, scripts & SQL
Avoid problems with current PowerCenter version mechanism (shortcuts, sessions)
Enable automation of release process
Different responsibilities for different environments
Enforce change tracking
Why external version control?Why external version control?
Configuration ManagementConfiguration Management
<delivery stream>_<major>.<minor>.<patch>
e. g. ACC_1.0.1
<major> major release number(high level “wave” planning)
<minor> minor release number(delivery stream development plan)
<patch> patch level (bug fixes, emergency releases)
Release NamingRelease Naming
Configuration ManagementConfiguration Management
Versioning Versioning ExampleExample
Labeling Schema:
ACC_x.y.z release labelRLS_A current version in
user acceptance testRLS_P current version in production
/main/1/main/1
/main/2/main/2
/main/4/main/4
/main/5/main/5
ACC_1.0.0
ACC_1.0.1
ACC_1.0.2
ACC_2.0.0
RLS_P
RLS_A
reset_acc.sql
/main/3/main/3
Deployment ProcessDeployment Process
Repository Copy:- via GUI / database backup & restore- trackable (result is a file)- problem: overwrites server configuration
Folder Copy:- only via GUI- and therefore not trackable
Mapping Copy:- only via GUI- used only within development repository
PowerCenter Deployment FacilitiesPowerCenter Deployment Facilities
Deployment ProcessDeployment Process
“Repository Copy” is the only trackable method
Delivery Streams require folder level deployment
ApproachApproach
Introduce staging repositories in all environments
Staging repository is used to separate folder from repository, using the “Folder Copy” method
Staging repository is then deployed using the“Repository Copy” method
Use combination of both methods:
Deployment ProcessDeployment Process
Freeze, Deliver and Receive ProcessesFreeze, Deliver and Receive Processes
D S V S A S P
manual folder copydatabase unload / loadautomated processdelivery package
ClearCase
Freeze
Deliver
Receive
Deployment ProcessDeployment Process
sub unload {system("db2 connect to $repository user $user using $password");
db2select(\@tables, ”SELECT tabname FROM syscat.tablesWHERE tabschema = 'PCSTAGE'and (tabname LIKE 'OPB_%' or tabname LIKE 'REP_%') and type = 'T'ORDER BY tabname");
foreach $table (@tables) {system("db2 export to $table of del modified by coldel0x02 chardel0x03
select \\* from $user.$table”);};
system("tar cvf $tarfile *");}
Repository UnloadRepository Unload
Deployment ProcessDeployment Process
sub load {system("db2 connect to $repository user $user using $password");system("tar xvf $tarfile");
foreach $file (("OPB_REPOSIT", "OPB_REPOSIT_INFO")) {system("sed -e 's/CDW_StagingD/$name/g' $file > tmp.out");system("sed -e 's/DDBPCR/$dbs/g' tmp.out > $file");
}foreach $table (<*>) {
system("db2 delete from $user.$table”);system("db2 import from $table
of del modified by coldel0x02 chardel0x03 delprioritycharinsert into $user.$table”);
};}
Repository LoadRepository Load
Release ProcessRelease Process
Responsible for high level planning and impact analysis
Defines release scope and release numbers on baseof delivery streams
Assigns responsibilities (delivery stream manager, data modeler, database administrator, business responsible)
Result is documented in “wave plan” document
Wave plan is base for all subsequent design, implementation and quality assurance tasks
Change Control BoardChange Control Board
Release ProcessRelease Process
1. Preparation of UNIX and PowerCenter release areas delivery stream manager
2. Issue release request delivery stream manager
3. Create new release (Freeze) release manager- Copy to staging repository, unload- Create / update ClearCase file versions- Create release label and attach to new release
4. Create release package (Deliver) release manager- delta / full processing- lock release in ClearCase
5. Install release (Receive) IT integration / IT operation - Load, copy from staging repository- Post install script
6. Create / update database objects in target environment database administrator
7. Restart PowerCenter server IT integration / IT operation
Release ProcedureRelease Procedure Responsible
Release ProcessRelease Process
Provide easy-to-use information on all releases
Today: ClearCase based
In future: Integration with meta data repository
Release DatabaseRelease Database
DSF_1.1.4 A 27-Jul-00.17:32:27 new config filesDSF_1.1.3 20-Jul-00.13:16:38 fix for single node load problemDSF_1.1.2 P 19-Jul-00.14:05:30 correct JDM, error handlingDSF_1.1.1 18-Jul-00.17:51:19 removed environment dependenciesDSF_1.1.0 17-Jul-00.17:11:47 see release notesDSF_1.0.2 11-Jun-00.14:07:01 changed Gen_EnvironmentDSF_1.0.1 09-Jun-00.13:20:03 see release notesDSF_1.0.0 24-May-00.17:48:42 initial version
Example:
SummarySummary
PowerCenter was successfully introduced at UBS and proved to work well within the sourcing framework
Configuration control with ClearCase is efficient and straight forward
Release process meets the requirements and is efficient(so far ~200 successful releases, effort usually below ½ hour)
Generally little administration overhead although some improvements in PowerCenter would make administrator´sand release manager´s life easier
ExperiencesExperiences
SummarySummary
Copy of sessions
Export / import folders via (UNIX) command linefor further automation of release process
Avoid restart after deployment
Logical backups / restores via command line with result on server side (more flexible than database backup, avoid ODBC overhead)
User administration via command line
Wish ListWish List