Rehoming 3G

Embed Size (px)

DESCRIPTION

Rehoming 3G

Citation preview

  • Rehoming 3G

  • Rehoming 3GStep of Rehoming 3G

    Preparation & Creation site Dbase Verify dbase created in OSS before implementation Alarm collection before rehoming Rehoming Implementation Verify dbase created in OSS after implementation Alarm collection after rehoming Clean up old Dbase

  • 1. Preparation & Creation Dbase

    Use Rehosting Tools Open CM Editor Plan New Rehost

  • 1. Preparation & Creation Dbase

    Put the name and select new RNC

  • 1. Preparation & Creation Dbase

  • 1. Preparation & Creation Dbase

    Copy WBTS config actual from CM Editor

  • 1. Preparation & Creation Dbase

    Paste in the xml rehost plan

  • 1. Preparation & Creation Dbase

    Put the new parameter ( base on data from planning )

  • 1. Preparation & Creation Dbase

    Fill in IPNB, WBTS, WCEL new value needed base on latest Update Datafill & Nodin data

  • 1. Preparation & Creation Dbase

    Provision RNW creation plan , click the green sign in Operation ( Right Above )The status should be with green ticks otherwise please do the troubleshoot

  • 2. Verify the database created in OSS before implementationThe RNP Engineer will check to ensure that the sites prepared will be the same as the old database. Any discrepancies will be sent to the NIC Enginner to be corrected.

  • Alarm collecting will be done before rehome activity. These are necessary to capture any existing alarms before rehome activity. This file will be needed for documentation3. Alarm collection before rehoming

  • This work phase is moving the database to new RNC. The process includes:

    Locking the old site

    Recom / Configure Flexy BTS using WBTS manager Update Adjacencies

    Unlock sites.4. Implentation Rehoming

  • RNP Engineer will check all sites rehomed to the new RNC, verify the database to ensure there is no discrepancies compare to the old database.5. Verify database created in OSS after impelementation

  • Alarm collecting will be done after rehome activity. These will capture all active alarms after rehome activity and this file will be needed for documentation. The pre and post alarm logs are compared to check for any new NODE B/RNC alarms. These are escalated accordingly.6. Alarm collection after rehoming

  • Delete RNW/ WBTS/ DCN and all children through RNC.

    Delete Old site from Database using Network Editor. 7. Clean up old database