Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

Embed Size (px)

Citation preview

Page 1: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every project

Rehabilitation of Locks on the Kentucky RiverJoshua M. Repp, PEBergmann Associates

Page 2: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Presentation Overview• River System History • Evolution of Lock and Dams Structures• Existing Condition of Structures• Lock No. 3&4 Renovation Plan• Lock Dewatering System

Page 3: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Kentucky River – Inland Waterway Relationships

Rochester, NY

Lower Mississippi

Kentucky River

Upper Mississippi

Ohio River

Page 4: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

River System Structures

• 14 Locks and DamsOwners: Kentucky River Authority (KRA)Corps of Engineers

• Dams– fixed crest

• Locks– Locks 1-4 (open)– Locks 5-14 (closed)– 145’x38’ chamber (Locks 1-5)– 147’x52’ chamber (Locks 6-14)– 8 to18 foot Lifts

Frankfort

Lexington

JacksonL4

L&D 3

Page 5: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

1775 1800 1900 2000 2010

Pre-1775• Native Americans occupied land.

1775• Increase in mining & timbering• First Flat Boats

Kentucky River System History - Timeline1790• Coal Barges

1812• Steam Boats

1836 - 1842• L&D 1-5 Constructed

1836 - 1842• Kentucky Railroad Expansion Begins

1862• Civil War• Damage to Dams

1884 - 1917• L&D 6-14 Constructed

1951Recommended Closure of Locks 8-14

1836 – 1842Commercial Navigation Decline due to Railroad Expansion

2003-2004L&D 6-14 closed due to lack of funding

2007Plan issued to rehabilitate Locks 1-4 for recreational use

Page 6: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Kentucky River Locks 3 & 4 Project

GEST, KYRehabilitate Locks(Additive Alternative Work)

Replace Dam 3(Base Bid)

Lock & Dam No. 4 Lock & Dam No. 3

Page 7: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Evolution of Dam Structures

Page 8: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Evolution of Dam Structures

Page 9: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Evolution of Dam Structures

Page 10: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Evolution of the Kentucky River Dams

Timber Crib Dam - Original 1830’s- Replaced in-kind 1910

Concrete Cap- Original 1910- Repaired 1950

Dam Sheeting & Resurfacing Repair

- 1990’s

Cellular Dam - Ongoing- 2 of 14 dams

Page 11: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Dam History - 1990’s Dam Renovation

Page 12: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Dam Replacement – Cellular Dam No. 9

Page 13: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Existing Conditions - Dam No. 3

p o

Sect o s

MissingApron

Sections Broken Apron

Sections

Page 14: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Lock Structures• Walls

– 220’ long by 30’ high – Locks 1-8 limestone masonry– Locks 9-14 concrete walls

• Miter Gates– Original wooden gates replaced with

horizontally framed steel gates.– Original hand-operated machinery

converted to electric and hydraulic

• Filling/Emptying System– Miter gate valves (filling/emptying)– Wall culverts (filling)

Page 15: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Existing Lock Conditions - Locks 5-14 Closed to Navigation

Lock 5

Upper Miter Gate

Upper Sill

Concrete Bulkhead Wall

Page 16: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Existing Lock Conditions• Miter Gates

– Timber Seals (Quoin, Miter, & Sill)– Gate Valves– Gate Misalignment– Pintle

Weathered Miter & Quoin Post

Weathered Quoin

Gate ValveLeakage

Page 17: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Existing Lock Conditions• Miter Gate Anchorages

Failed Anchor

Pin

2 Anchor Pins

Miter Gate

Page 18: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Existing Conditions - Machinery

Page 19: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Existing Lock Conditions• Preparation of Overtopping

– Secure of miter gates– Removable or collaspable

railing, machineryCollapse

Machinery Stands

TurnbuckleAssembly

Cable Tie-backs

Store Rack in-line with

Gate

Remove/ Collapse Wall &

Gate Railing

Page 20: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

River Levels – Lock and Dam No.3

Top of Lock

T/O Crest EL. 453.7

6 mo. Flood6 mo. Flood

+10’

-7’+1’

1 yr. Flood+16’

+7.5’

10 yr. Flood

+31’ +22’

Page 21: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

MAY 2010

Page 22: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

MAY 2010 Flood – Construction at Dam No. 9

Page 23: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

MAY 2010 Flood – Construction at Dam No. 3

Page 24: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

MAY 2010 Flood – Debris at Lock No. 3 Upper Gate

Page 25: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

MAY 2010 Flood – Debris at Lock No. 4 Upper Gate

Page 26: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Lock Renovation Plan• Rehabilitate Gates

– Gate Valves– Replace Pintle & Bonnet– Steel Repairs– Diagonal Replacement– Quoin, Miter, Sill Seals

• Masonry Repointing• Concrete Overlay on Top of Wall• Convert Power Supply from

Electric to Pneumatic• Various Safety Upgrades

Page 27: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Renovation Summary

Pneumatic Supply Conduit

Add Diagonal Strap

Rehabilitate Valves (3)

Replace Anchorages

Replace Pintle & Socket

Replace Seals

Rubber Sill Seal

Reconstruct Sill

Reconstruct Quoin with Quoin Plate

Repoint Masonry

Concrete Overlay (6”)

Page 28: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Renovation Design ChallengesDewatering of the Lock• Wall Stability Analysis Issues

– Geometry unknown• the thickness of the lock walls was

determined by the resident engineer during construction

– No former calculations– Wall not theoretically stable with no

physical signs of instability

Page 29: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Wall Geometry Investigations at Lock 3

Landwall Riverwall

Dam CrestEsplanade

Lock Floor & Rock Line

Interpolated Rock Line

Interpolated Masonry Line

Page 30: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

1

FULL WALL STRUTTING

ANCHOR LANDWALL

Wall StrutNeedle Dam

BulkheadNeedle Dam

Bulkhead

Wall Anchor

Needle Dam Bulkhead

Needle Dam Bulkhead

Page 31: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

PHASE 1 - DEWATERING

PHASE 2 - DEWATERING

Secure Lower Gate

Secure Upper Gate

Wall Strut

Needle Dam Bulkhead

Wall Strut

Needle Dam Bulkhead

Page 32: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Strut System for Dewatering

Struts(7o incline)

Waler

Sliding Plane

Flanged Adjustment Assembly

Page 33: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Bulkhead System for Dewatering @ Lower Gate

Gate Recess

Wall Struts

Sheet Piling

Anchored Precast Sill

Blocks

Bulkhead Beam

Wall Anchors

Page 34: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

Wall Anchors

Wall Anchors

Temporary Survey Marker

Bulkhead Reactions

Wall Struts

Lower Gate

Bulkhead Reactions

Page 35: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

www.bergmannpc.com

our people and our passion in every projectour people and our passion in every project

PDH QuestionsQ: When were the first locks and dams constructed on the Kentucky River?

Q: What were two major factors related to the decline in commercial traffic for the river system?

• 1830’S

Q: What two advantages did vertical walers offer to the strut system?

1. Variable river levels – difficult to navigate2. Unreliability and size of lock and dam structures3. Advancement of railroads for transport of goods

Q: The adjustment assembly in the pipe struts was detailed for what purpose?

1. Improved global stability - Increased the sliding resistance of the lock riverwall by lowering the sliding plane.

2. Better load distribution to the irregular and discontinuous masonry

• To ease removal of the strut between grouted walers after use in dewatering.

Page 36: Rehabilitation of Locks on the Kentucky Rivernewyorkcanals.org/_pdfs/Repp.pdf · Better load distribution to the ... The 260 mile long Kentucky River runs from ... 350 person consulting

The Rehabilitation of Locks on the Kentucky River System, Kentucky, US Joshua M. Repp, P.E., Bergmann Associates, Rochester, NY, USA [email protected] The 260 mile long Kentucky River runs from Eastern Kentucky (south around the City of Lexington) through the City of Frankfort (capital city of the Commonwealth) and flows northwest into the Ohio River. The river is divided into navigation and water supply pools by a series of 14 locks and dams, many originally constructed in the 1830’s with stone masonry walls. Due to a decline in commercial navigation over the past few decades, the locks have been closed by the state. Reinforced concrete weir walls have been constructed at locks 5 through 14 as a more permanent closure. Some of the timber crib and sheet pile dams, originally constructed to retain pool for navigation purposes, have been replaced to secure pool for water supply. Recently the KRA/FAC has been evaluating the rehabilitation of Locks 1 through 4, potentially restarting recreational river navigation from the Ohio River to Frankfort, KY. Bergmann Associates has been contracted to evaluate the lock conditions, structural stability and to develop repair plans. Full rehabilitation documents were developed for Locks 3 and 4 and base repair schemes developed for all four of the 38’ wide by 175’ long locks. The history of this rehabilitation and future repairs plans will be presented. Joshua M. Repp is a Project Engineer and Lead Structural Engineer for Bergmann Associates, a 350 person consulting engineering firm and currently works out of the Buffalo Office. He has been working in the Civil Works Group at Bergmann mostly on waterway structures projects around the eastern US for the past seven years. His roles on the projects for the KRA included Assistant Project Manager, Project Engineer, Structural Designer and Cost Engineer. He is a graduate of the University of Buffalo with a BS in Civil Engineering and a ME in Civil-Structural Engineering. He is a Professional Engineer in New York State.