Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 1
Corrigendum & Addendum No. 6
S.
No. Clause reference Corrigendum & Addendum
1. Volume 1, Section I,
ITB, Cl. no-11.2 (a),
Page no. 10.
Form of Letter of Technical Bid is attached herewith as Annexure-1
2. Volume 1, Section II,
BDS, Clause no. 11.2
(d), page no. 31.
Form of Joint Venture agreement is attached herewith as Annexure-2
3. Volume 1, Section III,
page no. 35.
Evaluation Criteria is attached herewith as Annexure-3
4. Volume 1, Part A,
Clause no. 1.1.3.3(ii),
page no. 46
The words “letter of acceptance” in fourth line under heading „Interim
Operation and Maintenance‟ under Clause 1.1.3.3(ii), may be read as
“effective date of contract”.
5. Volume 1, Part A,
Clause no. 1.1.4.2(c),
page no. 47.
The second sentence under Clause 1.1.4.2(c), "The O&M Contract Price............
Defect Liability Period", stands deleted.
The revised sentence is as under:
“The O&M Contract Price will be the total amount for operation and
maintenance during the 10 Years of O&M period plus amount for payment to be
made in the One Year Defect Liability Period, as set out in Volume 3, Section XII,
Schedule of Payment.”
The words “Section XIV” in the last line of second paragraph under Clause
1.1.4.2(c) O&M Contract Price, may be read as “Section XII”
6. Volume 1, Part A,
Section VIII, Sub-Clause
no. 4.19, page no. 53.
The Paragraph under heading During Defect Liability Period and Operation
& Maintenance "During the 1 year…………. Electricity Supply Agency", stands
deleted.
The revised paragraph is as under :
"During the 1 year DLP and 10 years O&M period, DJB shall pay the electricity
charges to the Electricity Supply Agency directly but this shall be lesser of the
following:
(i) the actual power consumed during the period
(ii) the power charges calculated on the basis of net power consumption
guaranteed by the Contractor. The net power consumption shall be adjusted
for the quantity and quality of the raw sewage treated at the WWTP, as per
Technical Schedule, Part-9, Section XI, Volume 2 of the Bid documents.
Any additional electricity charges on account of the actual power consumption
exceeding the net power consumption guaranteed shall be borne by the
Contractor and the Employer shall recover such additional charges from the
contractor.
No payment is admissible to contractor for rendering O&M services during
Defect Liability Period except for manpower, chemicals & sludge disposal.
Payment of electricity charges shall be made by the employer directly.
Further during extended period of DLP of the Plant all costs of operation &
maintenance including electricity charges shall be borne by the Contractor.
Any penalties due to higher demand charges, if any, imposed by the Electricity
Supply Agency will be borne by the contractor."
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 2
S.
No. Clause reference Corrigendum & Addendum
7. Volume 1, Part-A,
Section VIII, Sub-Clause
no. 22.4, Page no. 85
The word '(b)' in heading "Delays or interruptions caused by the
Contractor", may be read as "(a)".
8. Volume – 1, Part-A,
Section VIII, Sub-Clause
no. 22.7, Page no. 87
The word '22.8' in first line under heading Sub-Clause 22.7 Operating
License, may be read as "22.7".
9. Volume 1, Part-A,
Section VIII, Sub-Clause
no. 22.8, Page no. 88
The word '22.9' in first line under heading Sub-Clause 22.8 Non-Availability
of Raw Sewage, may be read as "22.8".
The point no. i) under Sub-Clause 22.8, "the employer shall be liable ............
bid documents" stands deleted.
The revised point is as under:
"i) the Employer shall be liable to pay to the Contractor the Fixed Operation &
Maintenance Charges as specified by the bidder at the time of bidding in „Price
Schedule B-1, A.- Fixed Part, sl. no.-2, Section XII, Volume 3 of Bid documents‟"
10. Volume 1, Part-A,
Section VIII, Sub-Clause
no. 22.9, Page no. 88
The word '22.10' in first line under heading Sub-Clause 22.9 Adverse
Operating Conditions, may be read as "22.9".
11. Volume 1, Part B,
Section IIIA, Eligibility
and Qualification
Criteria, Clause no.
4.2(a), Page no. 108
The first paragraph under the heading „Requirement‟ in the table of
„Experience‟ at Clause no. 4.2(a), “The Bidder should have experience of
Design, Construction……………………… as BOD ≤ 10 mg/l, TSS ≤ 10 mg/l”,
stands deleted.
The revised paragraph is as under :
“The Bidder should have experience of Design, Construction, Testing &
Commissioning of at least one Waste Water Treatment plant (WWTP) of minimum
50 MLD capacity based on aerobic growth process designed to meet effluent
standards as BOD ≤ 10 mg/l, TSS ≤ 10 mg/l.”
12. Volume 1, Part B,
Section III A, Note iii,
Page no. 111.
The Note at Sl. No. iii) mentioned at the bottom of Eligibility and
Qualification Criteria, "the experience of the bidder ........... full experience,
Stands deleted.
The revised Note is as under :
"iii) The experience of the bidder in a project executed in JV, shall be considered
only if the firm has completed the work as a Lead member with maximum share in
the JV in that particular project. However, in case of JV with 50:50 share, both
the partners will qualify for full experience.”
13. Volume 2, Section XI,
Part 1, Clause no. 1.7
(2), Page no. 137
The point no. (n) (i) under Sl. No. xiv) Other contingent works, "Soft three
dimensional model: Contractor .........equipment", stands deleted.
The revised point no. (n) (i) is as under :
"Soft Three Dimensional Model :Contractor shall provide three dimensional
graphical working model of the plant with the help of standard software such as
Bentley etc. which will be viewable on the screen of not less than of 80 cm (32
inches). The model shall be rendered to allow outlook of the plant from various
viewpoints to show all structures, interconnecting pipe work and equipment. The
contractor shall also provide an HD LED TV of 40" size of reputed make such as
Sony, Samsung etc. As approved by the Engineer "
14. Volume 2, Section XI,
Part 1, Clause no. 1.7
(4), Page no. 138
The words “fuel & electricity etc.” in second line of fourth paragraph under
heading „Operation of Plant during Defect Liability Period of one year‟
under Clause 1.7 Brief Scope of Work, may be read as “fuel etc.”
15. Volume 2, Section XI, The word “electricity” in fourth line of first paragraph under heading
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 3
S.
No. Clause reference Corrigendum & Addendum
Part 1, Clause no. 1.7
(5), Page no. 138 „Operation & Maintenance of the Plant for a period of 10 years‟ under
Clause 1.7 Brief Scope of Work, stands deleted.
The words “4 years” in fourth line of second last paragraph under heading
„Operation & Maintenance of the Plant for a period of 10 years‟ under
Clause 1.7 Brief Scope of Work, may be read as “2 years”.
16. Volume 2, Section XI,
Part 1, Clause no. 1.7
(5)(iv), Page no. 139.
The point no. (iv) at Sl. No. 5 under Clause no. 1.7 Brief Scope of work,
"Guarantee for automation system", stands deleted.
The revised point no. (iv) is as under :
"Guarantee for auto operation of plant."
17. Volume 2, Section: XI,
Part 2, Clause no. 2.3,
Page no.170
Add "Sl. No. 9" after "Sl. No. 8" in the table as under clause no. 2.3
Demolition of Interfaces and Tie-Ins with Existing Facilities:
S.
No.
Unit/Structure
Description
Quantity Indicative
Dimension
9. Existing Digesters
Control MCC Room
1 11.2 m x 4.7 m
x 3.4 m
18. Volume 2, Section XI,
Part 2, Clause no. 2.4,
Page no. 170
Add at the end of first paragraph under Clause no. 2.4 Sewage Treatment
Process, "The existing plant ............ tender document or not", the following :
"Contractor to incorporate necessary chemical dosing system to achieve the
guaranteed phosphorus parameters in treated effluent."
19. Volume – 2, Section
XI, Part-2 Clause no.
2.5, Page no. 173.
The first bullet point at top of page under Clause no. 2.5 General Design
Requirements, for liquid and sludge.................. more than 15.0 m/s". Stands
deleted.
The revised bullet point is as under:
“For liquids and sludge, the velocity of full flow in pipes or conduits shall be
maintained as specified under Part-4, cl. no. 4.2.19.1 at page 339. Piping Sizing
& Material. All mixed liquor and sludge pipes shall have minimum 200 mm
diameter and shall be provided with appropriate cleanouts and flushing
arrangements for safe and easy flushing using high-pressure water.”
20. Volume – 2, Section
XI, Part-2 Clause no.
2.5, Page no. 174
The words “measurement and” in third line of the last bullet point under
Clause no. 2.5 General Design Requirements, stands deleted.
21. Volume – 2, Section
XI, Part-2, Clause no.
2.8, Page no. 178
In the table at Sl. No. v) under Clause 2.8 Common Inlet Chamber for Phase
I & II WWTPs, the size of the rising main "750 mm dia" may be read as "900
mm dia".
22. Volume – 2, Section
XI, Part-2, Clause 2.8,
Page no. 178
Add at the end of 1st paragraph "All the above incoming .............. maximum
TWL" under the 1st table under Clause no. 2.8, the following :
“Bidders are advised to verify the size of existing pipe lines at the site and no
claim on account of any variation in this regard shall be entertained”.
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 4
S.
No. Clause reference Corrigendum & Addendum
23. Volume 2, Section XI,
Part 2, Clause 2.10, Page
no. 179 & 180
The heading of Clause 2.10, "Fine Screen Channels" may be read as "Coarse
and Fine Screens Channels".
The first paragraph under Clause 2.10 Fine Screen Channels, "the raw
sewage ............... SS 316 construction". Stands deleted.
The revised paragraph is as under:
"The raw sewage from the inlet chamber shall flow by gravity to Coarse and Fine
Screen Channels & flow shall be distributed equally to each screen channel.
Screening shall be done in two stages and Contractor shall have to provide
automatic mechanical coarse screens to remove particles larger than 20 mm size
and in second stage there shall be fully automatic mechanical fine screens to
remove particles larger than 6mm. The screen shall be supplied with shaftless
screw conveyor to convey the screenings to the automatic screening press and
discharge system that compacts, dewater and discharges the screenings through
chute to the screenings storage system. The screens and shaftless screw conveyor
shall be in SS 316 construction. The screen shall be movable bars / perforated
band having a design life of 15 – 20 years. A straight line channel before the
screen is mandatory. Minimum length of the channel shall be 5 times the width of
the screen chamber. A similar channel after the screen channel shall also be
provided."
The last sentence “The design criteria for Fine Screen Channel given below:”at
the end of page no. 179 under Clause 2.10 Fine Screen Channels may be read
as "The design criteria for Coarse and Fine Screens Channels given below:”
The requirements mentioned against Sl. Nos. iii., v., vi. & x. in the table at
page no. 180 under Clause 2.10 Fine Screen Channels, stands deleted.
The revised requirements against Sl. Nos. iii., v., vi. & x. are as under :
Sr.
No
Description Requirements
iii. No. of Screen
Channels
Coarse Screen - 6 nos. (4W + 2S)
Fine Screen - 6 nos. (4W + 2S)
Each screen designed for 25% of the peak flow i.e.
91 MLD (20 MGD) + recycle or other flow (if any)
v. Clear spacing of bars
- Coarse Screen
- Fine Screen
20 mm (maximum) and thickness of bar shall be 10
mm (minimum).
6 mm (maximum) and thickness of bar shall be 3
mm (minimum).
vi. Velocity through
screen opening 1.2 m/sec (max)
x. Angle of Inclination of
screen to horizontal
For fine screens angle between 45º to 55º and for
coarse screens angle between 60º to 75º shall be
considered.
24. Volume 2, Section XI,
Part 2, Clause 2.11, Page
no. 181
The description & requirement mentioned against Sl. Nos. vi. in the table at
page no. 181 under Clause 2.11 Grit Chambers, stands deleted.
The revised description & requirement against Sl. Nos. vi. is as under :
Sr. No Description Requirements
vi. HRT of Grit Chamber at peak flow As per manufacturer‟s design
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 5
S.
No. Clause reference Corrigendum & Addendum
25. Volume – 2, Section
XI, Part-2, Clause no.
2.16, Page no. 184
The last sentence of „Note‟ under Clause no. 2.16 Bio Reactor "The minimum
sewage .............maximum as 270C", stands deleted.
The revised sentence in the Note is as under:
“The minimum sewage temperature used for design may be considered as 17.80C
and maximum as 290C”
26. Volume – 2, Section
XI, Part-2, Clause
2.16.1, Anoxic Zones,
Page no. 185
The parameter “6.0 m (maximum)” at Sr. no. vi.) Liquid Depth of table under
clause 2.16.1 Anoxic Zones may be read as “10.0 m (maximum)”
27. Volume – 2, Section
XI, Part-2, Clause
2.16.1, Aerobic Zones,
Page no. 186
The parameter “6.0 m (maximum)” at Sr. no. xii) Liquid Depth of table under
clause 2.16.2 Aerobic Zones may be read as “10.0 m (maximum)”
28. Volume – 2, Section
XI, Part-2, Clause
2.16.2, Aerobic Zones,
Page no. 187
The requirements mentioned against Sl. Nos. ix), x), xiii) & xiv) of Point 'B.
Aeration Requirements' in the table under Clause no. 2.16.2, stands deleted.
The revised requirements against Sl. Nos. ix), x), xiii) & xiv) are as under:
Sl.
No. Description Requirements
ix) Fouling Factor for
Diffuser
0.70
x) Minimum Sewage
Temperature 17.8 deg C
xiii) Type of diffuser Fine bubble membrane disc type/ tubular type
grid diffusers, fixed type (non retrievable type)
xiv) Diffuser membrane
MOC
Silicone Membrane with laser drilled holes
29. Volume – 2, Section
XI, Part-2, Clause 2.18,
Page no. 189
The parameter “0.75% (minimum)” at Sr. no. ix „Solid Concentration in
Waste Activated Sludge‟ of table under clause 2.18 Secondary Clarifier may
be read as “0.75% (maximum)”
30. Volume-2, Section-XI,
Part-2, Cl. No. 2.21.1,
Page no. 191
The word “four nos.” in first sentence under Clause 2.21.1 Travelling Bridge
Filters, may be read as "six nos."
The parameter “4 nos. (minimum)” at Sl. No. (iii) of table under clause 2.21.1
may be read as “6 nos. (minimum). The over load to other filter should not be
more than 20% in N-1 condition”
31. Volume-2, Section-XI,
Part-2, Cl. No. 2.21.2,
Page no. 192
The word “four nos.” in first sentence under Clause 2.21.2 Cloth Media Disk
Filters, may be read as "six nos."
The parameter “4 nos. (minimum)” at Sl. No. (iii) of table under clause 2.21.2
may be read as “6 nos. (minimum). The over load to other filter should not be
more than 20% in N-1 condition”
32. Volume-2, Section-XI,
Part-2, Cl. No. 2.21.3
Page no. 192
The parameter “4 nos. (minimum)” against Number of units of table under
clause 2.21.3 may be read as “6 nos. (minimum)”
33. Volume-2, Section-XI,
Part-2, Cl. No. 2.22,
Page no. 193
The parameter "45 minutes (minimum)" under the head 'Requirements' at S.
No. (iv) in the table under the Cl. No. 2.22 Chorine Contact Tanks, may be
read as "30 minutes (minimum)"
34. Volume – 2, Section XI,
Part-2, Clause 2.23,
page no. 194.
The parameter "12 Nos. (minimum)" at S. No. iii) Chlorine Tonner Online in
the table of Vacuum Chlorinator under the Cl. No. 2.23 Chlorination
Building, may be read as "4 Nos. (minimum)"
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 6
S.
No. Clause reference Corrigendum & Addendum
35. Volume-2, Section-XI,
Part-2, Cl. No. 2.24,
Page no. 194
Add after Sr. No. iv. in the table under the heading "De-chlorination System"
of Clause no. 2.24, the following:
Sr. No. Description Requirements
v Residual Chlorine at outlet 0.2 mg/l (Minimum)
36. Volume-2, Section-XI,
Part-2, Cl. No. 2.26,
Page no. 195
The parameter "60 Kg /m2-d (Maximum)" at S. No. iv) „Design Sludge
Loading Rate‟ in the table of Gravity Sludge Thickener under the Cl. No.
2.26, may be read as "100 Kg /m2-d (Maximum)".
37. Volume-2, Section-XI,
Part-2, Cl. No. 2.34.1,
Page no. 203
Add at the end of 2nd
paragraph under Clause no. 2.34.1 Power Generation
Building, the following :
“The biogas Engine should have features of black start with the help of clean gas
from clean gas holder.”
Add at the end of last paragraph under Clause no. 2.34.1 Power Generation
Building, the following :
"Central cooling system along with cooling towers all associated ducts, grilles,
etc. for cooling of major buildings such as Power Generation Building, Air
Blower Building and Sub-Station Building. The water softening plant of the
required capacity for use of treated effluent required for cooling system shall also
be supplied. Water from DJB water supply system or ground water is not to be
utilized for any cooling system purpose."
38. Volume-2, Section XI,
Part-2, Clause 2.36,
Page no. 205
The parameter in the table under point B. Polymer Dosing System "2.5 kg/ton
dry solids (Minimum)" at S. No. ii under the Cl. No. 2.26, may be read as "5
kg/ton dry solids (Minimum)".
And the parameter in the table under point B. Polymer Dosing System "As
per requirement with a installed 100% standby" at S. No. vi under the Cl. No.
2.26, may be read as "8 Nos. (4 Working + 4 Standby).”
39. Volume-2, Section-XI,
Part-2, Cl. No. 2.38.5,
Page no. 210
Add at the end of Paragraph under Cl. No. 2.38.5 :
“Sufficient space for filling of three no. tankers simultaneously at each filing
station shall be provided. Operator room etc shall be as per contractor‟s design
subject to approval of Engineer. The capacity of each pump shall be 100m3/hr.”
40. Volume – 2, Section
XI, Part-2, Clause 2.41,
Page no. 212.
Add at the end of 1st Paragraph under Cl. No. 2.41, the following:
“The system shall be provided at minimum three locations.”
41. Volume – 2, Section
XI, Part-3, Clause
3.2.4, Page no. 225.
The point no. viii. under Clause no. 3.2.4 Design Conditions for Foundations,
"Pressure release ……………. not permitted", stands deleted.
The revised point no. viii. is as under :
"Pressure release valves (PRVs) shall be provided in base slab of tanks wherever
is required to minimise the effect of sub-soil water. Pressure release valves will be
permitted wherever it does not affect the process or the system. Pressure release
valves shall be of Gun Metal, 100 mm dia. to be provided with inverted filter
media depth (min depth-750 mm) at bottom. PRVs shall be interconnected through
channels (min 300 mm depth X 300 mm width), filled up with filter media. PRVs
shall be provided @ 50 sqm area of base slab for one valve. No PRV will be
allowed in Gasholders."
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 7
S.
No. Clause reference Corrigendum & Addendum
42. Volume – 2, Section
XI, Part-4, Clause
4.2.2, Page no. 271
The parameter “4 nos. (2W+2S)” in the last sentence of 1st
paragraph under
Clause no. 4.2.2 Grit Removal System (Cyclonic / Vortex type), may be read
as "3 nos. (2W+1S).”
43. Volume – 2, Section
XI, Part-4, Clause
4.2.6, Page no. 285
The first bullet point at Sl. No. (e) ii) Fouling Factor under Clause no. 4.2.6
Diffuser “For retrieval diffusers…………….. of emptying tank”, stands deleted.
44. Volume – 2, Section XI,
Part-4, Clause 4.2.7.1,
Page no. 291
The first word “four” against S.No. a) under heading Description under
clause 4.2.7.1 may be read as “Six”
45. Volume – 2, Section
XI, Part-4, Clause
4.2.8.1, page no. 292
The 4th
paragraph under Clause no. 4.2.8.1 Chlorination System “Bidder shall
design ……………….. 15 days chlorine requirement”, stands deleted.
The revised paragraph is as under :
“Bidder shall design the complete chlorine dosing system (with 50% standby)
including service water supply, safety equipment, leakage detection equipment,
chlorine toners, chlorine storage shed (15 days storage capacity plus on line
connected cylinders). Chlorine toners shall be supplied to fulfil 15 days chlorine
requirement at the minimum design dosing rate of 15 mg/l.”
46. Volume – 2, Section XI,
Part-4, Clause 4.2.8.6,
Page no. 295
The parameter in 2nd
sentence of first paragraph under Clause no. 4.2.8.6
Motive Water Booster Pumps, “4 pumps (2 duty + 2 standby)”, may be read
as “6 pumps (4 duty + 2 standby)”.
47. Volume – 2, Section XI,
Part-4, Clause 4.2.17.1,
Page no. 315
The parameter “1.0% to 3.0%” in 2nd
line of second paragraph under Sl. No.
1 General Requirements under Clause no. 4.2.17.1 Bio-Gas Engines, may be
read as “1.0% to 2.0%”.
48. Volume – 2, Section XI,
Part-4, Clause 4.2.17.1,
Page no. 316
The words “special cast iron with four valves” in 1st sentence of fifth
paragraph under heading „Cylinder Head‟ at Sl. No. 4 Main Components
under Clause no. 4.2.17.1 Bio-Gas Engines, may be read as “special cast iron
with two/four valves”
49. Volume – 2, Section XI,
Part-4, Clause 4.2.17.1,
Page no. 318
The 6th
bullet point “Anchor bolts” at top of page 318 of Sl. No. 5 Alternator
under Clause no. 4.2.17.1 Bio-Gas Engines, stands deleted.
50. Volume – 2, Section XI,
Part-4, Clause 4.2.17.1,
Page no. 322
The word “3 nos.” in 1st sentence at Sl. No. 18 Electrical Requirements for
Gas Engine Generators, may be read as “2 nos.”
51. Volume – 2, Section XI,
Part-4, Clause 4.2.17.6,
Page no. 325
The word “10 meters (minimum)” in 1st line of second paragraph under Clause
no. 4.2.17.6 Flare System, may be read as “6 meters (minimum)”
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 8
S.
No. Clause reference Corrigendum & Addendum
52. Volume – 2, Section
XI, Part-4, Clause
4.2.19.1, Page no. 339.
The 1st sentence under Clause no. 4.2.19.1 Material of Pipes, Sizing & Design
Basis, “Unless otherwise specified…………………… working range, stands
deleted.
The revised sentence is as under :
“Unless otherwise specified, the water velocity in the suction branches of a pump
shall not exceed 1.5m/s and in the discharge branch shall not exceed 2.0 m/s when
the pump is operating within its specified working range.”
The table under heading “Piping Sizing & Material” under Clause no. 4.2.19.1
Material of Pipes, Sizing & Design Basis, stands deleted.
The revised table is as under :
Service / Flow Basis MOC
Gravity Lines for Sewage,
Water & Waste Water
Velocity between 0.6 to 1.2
m/s & designed as pipe line
flowing full.
DI Class K 9
Pressure/pumping line for
Sewage, Water & Waste
Water
Velocity between 1.2 to 2
m/sec
DI Class K 9/MS
Cement Mortar
lined for sizes
above 1200 mm
Sludge line Gravity – 1.0 m/sec (max)
Pumping – 1.5 m/sec (max)
(Minimum size of pipe shall
be 200 mm)
DI Class K 9
Air (Pressurized Lines) for
Aeration Tank, Grit
Chamber, Gas Mixing
System etc. except common
header pipe line from Air
Blower to Aeration tank.
At velocities between 8 – 10
m/sec (desirable) with a
maximum of 15 m/sec in
small sections
SS – 316
Air (Pressurized Lines)
common header pipe line
from Air Blower to
Aeration tank.
At velocities between 8 – 10
m/sec (desirable) with a
maximum of 15 m/sec
DI Class K9
Gas Mixing System
complete
At velocities between 3.5 –
4.5 m/sec.
SS 316
Bio Gas piping At velocities between 3.5 –
4.5 m/sec.
SS 316
Service Water Velocity between 1.4 to 2.0
m/sec
GI Class B
Chemical Feed Lines Velocity between 0.6 to 1.5
m/sec
PVC / PP /
HDPE / SS
53. Volume – 2, Section
XI, Part-4, Clause
4.2.19.2(4), Page no.
345.
The 3rd
paragraph at Sl. No. 4 Butterfly Valves under Clause no. 4.2.19.2,
“Valve of diameter 600 mm ……………. electric actuator”, stands deleted.
The revised paragraph is as under :
“The actuator arrangement for Butterfly valves shall be provided as per the
Automation requirement, however valves of diameter 600 mm and above shall be
provided with electric actuator only.”
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 9
S.
No. Clause reference Corrigendum & Addendum
54. Volume – 2, Section
XI, Part-4, Clause
4.2.20, Page no. 349.
The type of parameter at 1st row of the table under Clause no. 4.2.20 Lifting
Arrangement, “Lesser than 3 Ton………….. EOT (Double Rail), may be read as
“If not specifically mentioned against any unit, type for less than 1 Ton capacity –
HOT (Double Rail) and for more than 1 Ton - EOT (Double Rail) shall be
provided.”
55. Volume – 2, Section
XI, Part-5, Cl. No.5.1
Page no. 364
The 4th
paragraph under Clause no. 5.1 General, “The Contractor shall possess
……………….. rules and regulations”, stands deleted.
The revised paragraph is as under :
“The Contractor or hired subcontractor shall possess the valid electrical
contractor‟s license of appropriate class from the concerned statutory bodies
governing the area of work place.”
56. Volume – 2, Section
XI, Part-5, Cl. No.-
5.1.3 Page no. 368
The last sentence of 2nd
paragraph under Clause no. 5.1.3 System Description
and Scope, “Sufficient details by way ……….……………….. have been
furnished”, stands deleted.
The revised sentence is as under :
“Sufficient details for dismantling and installation items such as cables, lighting
fixtures, lighting DBs, cable trays etc. have been furnished under clause 5.2.”
The first sentence of 4th
paragraph under Clause no. 5.1.3 System Description
and Scope, “The scope also includes ………………. three phases of the plant”,
stands deleted.
The revised sentence is as under :
“The scope also includes cabling, lighting, earthing and lightning protection
installation of the plant.”
57. Volume – 2, Section
XI, Part-5, Cl. No.
5.1.3 Page no. 369
The heading “Dismantled Equipment/installation” along with its paragraph “All
the dismantled equipment…………………. designated store” under Clause no.
5.1.3 System Description and Scope, stands deleted.
58. Volume – 2, Section
XI, Part-5, Cl. No.
5.2.5 Page no. 371
The last words “Digester Control Panel” of point at Sl. No. 7 under Clause
5.2.5 415V, LV Switchboards, may be read as “Panel”.
59. Volume – 2, Section
XI, Part-5, Cl. No.
5.2.6 Page no. 371
The first sentence of the last paragraph under Clause 5.2.6 Starters,
“Installation, Testing, Commissioning ………………….. proposed motors”, stands
deleted.
Add at the end of Clause no. 5.2.6 Starters, the following :
“5.2.6.1 Local Push Button Stations
The specifications of LPBS shall be as per attached Annexure E-2.”
60. Volume – 2, Section
XI, Part-5, Cl. No.
5.3.2,Page no. 382
The parameter “Frame–2” against „Minimum thickness of sheet steel in mm
Cold rolled (Frame/Enclosure/Covers)‟ at 1st row of table under heading
„Constructional Requirements‟ at Clause no. 5.3.2 MV (11 KV) Indoor
Switchboard, , may be read as “Frame – 2.5”
61. Volume – 2, Section
XI, Part-5, Cl. No.-
5.3.2.2(h) Page no. 384
The point at Sl. No. h) under Clause no. 5.3.2.2 Operating Mechanism
Control, “Provision for remote …………….future SCADA”, stands deleted.
The revised point is as under:
“h) Provision for remote control shall be provided.”
62. Volume – 2, Section
XI, Part-5, Heading- I.
Motors, Page no. 397
The word “Motors shall have space heaters” in first sentence of 6th
paragraph
at page no. 397 under heading „I. Motors‟, may be read as “Motors rated 30
kW and above shall have space heaters”.
Add at the end of the 6th
paragraph at page no. 397 under heading „I.
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 10
S.
No. Clause reference Corrigendum & Addendum
Motors‟, “Motors shall have space heaters…………… temperature measuring
device”, the following :
“Thermistor shall be provided for flame proof motors.”
63. Volume – 2, Section
XI, Part-5, Heading-II.
1. b), Page no. 398
The point “shorting (bypass) arrangement” at Sl. No. b) at page no. 398 under
heading „II. 1. Constructional and Performance Features‟, may be read as
“DOL By pass arrangement”
64. Volume – 2, Section
XI, Part-5, Heading-V,
Page no.- 405
Add at the end of table under „Motor Starters and Contactors‟ at page 405
under heading „V. LV Indoor Switchboard‟, the following :
Description Unit Particulars
Type of Starter - Draw Out type
65. Volume – 2, Section
XI, Part-5, Heading-
VIII, Page no. 412
The word “33%” in the last sentence of paragraph under heading „VIII.
Lighting System Equipment‟ at page no. 412, may be read as “50%”.
66. Volume – 2, Section
XI, Part-5, Heading-IX.
2, Page no. 421
The word “metallic” in the 1st sentence of last paragraph of point no. 2 Buried
Cables at page no. 421 under heading „IX. Cabling System Installation‟, may
be read as “non-metallic”
67. Volume – 2, Section
XI, Part-5, Heading-XI.
1., Page no. 428
The word “copper TPN” in the 2nd
sentence at point no. 1 Specifications at
page no. 428 under heading „XI. Non-segregated Phase Bus Duct‟, may be
read as “Aluminium TPN”.
68. Volume – 2, Section
XI, Part-5, Heading-
XII, Page no. 431
The parameter “4.0 meters (approx.)” in the 1st bullet at point no. 1. General
under sub-heading „Technical Specifications-Hydro Turbines‟ at page no.
431, may be read as “2.5 meters (approx.)”.
69. Volume – 2, Section
XI, Part-5, Heading-
XII, Page no. 436
The 1st sentence under sub-heading „Output & Efficiency Guarantees for
Turbine Generator Set‟ at point no. 8 Neutral Grounding at page no. 436
under heading „XII. Micro-Hydro Power Plant‟, “the efficiency of the
generator…………….shall be guaranteed”, stands deleted.
The revised sentence is as under :
“The efficiency of the generator & turbine at rated head at 100 % & 50% shall be
guaranteed”
70. Volume – 2, Section
XI, Part-5, Heading-
XII, Page no. 440
The heading “Synchronisation Panel” along with its paragraph “One swing
type …………………. in future” at page no. 440 under heading „XII. Micro-
Hydro Power Plant‟, stands deleted.
71. Volume – 2, Section
XI, Part-5, Heading-
XIV, 5.3.15.1, Page no.
442
The point at Sl. No. 2 of Clause no. 5.3.15.1 General under Heading „XIV.
Specific Specification-Electrical & Instrumentation Work, “Incomer rating of
LT Panels…………………………..calculated capacity”, stands deleted.
The revised point is as under :
“Incomer rating of PMCC/PCC panel will be selected based on transformer
secondary current; however incomer rating of MCC panels will be sized
considering (Total running load+50% standby+10% spare feeder‟s load) X 1.15.
(15% extra will be considered for safety margin). 20% spare feeders or minimum
one no. of each type shall be considered as spare for all panels”
72. Volume – 2, Section
XI, Part-6, Cl. No. 6.1,
Page no. 445
The word “water” in the sentence in fifth line of 1st Paragraph under Clause
no. 6.1 General, may be read as “effluent”.
The words “various statutory bodies / locations” in the last sentence of 1st
Paragraph under Clause no. 6.1 General, may be read as “DJB”.
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 11
S.
No. Clause reference Corrigendum & Addendum
73. Volume – 2, Section
XI, Part-6, Cl. No.
6.5.1 Page no. 452, 453
The parameter “Inlet of Gravity Thickener” in „Location‟ column at Sl. No. 11
in the table at page no. 453 under Clause no. 6.5.1 Instrument Design
Criteria, may be read as “Inlet to digesters”.
Add at the end of the table at page no. 453 under Clause no. 6.5.1 Instrument
Design Criteria, the following :
Sr. No. Location On Line Instrument
15. Discharge of centrifuge feed pump Electro Magnetic Flow meter
74. Volume – 2, Section
XI, Part-6, Cl. No. 6.9,
Page no. 471
The words “die-cast aluminium;” in the 2nd
sentence under Clause no. 6.9,
may be read as “die-cast aluminium/FRP;”
75. Volume – 2, Section
XI, Part-6, Cl. No.
6.12.1, Page no. 484
The words “through wireless technology” in the 2nd
sentence in the last
paragraph under Clause no. 6.12.1 General of SCADA System, may be read
as “through Optical Fiber cable communication”.
76. Volume – 2, Section
XI, Part-6, Cl. No.
6.12.6.2, Page no. 487
The parameters in „Remarks‟ column of the first item of table UPS under
Clause no. 6.12.6.2 Peripheral Subsystem, may be read as under :
Qty Hardware
Component
Remarks
1 10 KVA UPS for
Control room
Hardware
“The UPS is designed for 10 KVA with
two hours backup. However, adequacy
of capacity of UPS should meet the
bidder‟s system design requirement”.
77. Volume – 2, Section
XI, Part-6, Cl. No.
6.12.7.12 (5), Page no.
497
The 4th
paragraph of Sl. No. 5. Input/Output Devices under Clause no.
6.12.7.12 PLC (1 No.) “All the I/O modules………………………one HZ
minimum”, stands deleted.
The revised paragraph is as under :
“All the I/O modules shall have minimum 8 channels for the Analog and
minimum 16 channels for the Digital modules. Special modules like Counter
inputs shall monitor dry contact pulses with an input resolution of one HZ
minimum. However, nos. of channels shall be selected to meet the system
requirement.”
78. Volume – 2, Section
XI, Part-7, Clause 7.19,
Page no. 555
Add at the end of last paragraph under Clause 7.19 Performance Test, the
following :
“Performance tests shall be conducted for continuous 72 hour”
79. Volume – 2, Section
XI, Part-8, Clause 8.1,
Page no. 559
The word “DJB” in 2nd
sentence of 1st paragraph under Clause no. 8.1 Scope
of Works, may be read as “The Contractor”.
80. Volume – 2, Section
XI, Part-8, Clause
8.2.3, Page no. 573
The fifth paragraph under Clause no. 8.2.3, Sub-head no. 2 Staffing “The staff
strength ……………..days in a week”, stands deleted.
81. Volume – 2, Section
XI, Part-8, Clause
8.2.5, Page no. 575
The Clause no. 8.2.5 “Plant and Mobile Plant” along with its paragraphs i) to
iv), stands deleted.
82. Volume – 2, Section XI,
Part-10, Clause no.
10.1, Page no. 683
Add in the list of Approved Makes at S. No. 4 'Bar Screen', the following :
- HDO
- EIMCO
83. Volume – 2, Section XI, Add in the list of Approved Makes at S. No. 36 'Submersible Pumps', the
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 12
S.
No. Clause reference Corrigendum & Addendum
Part-10, Clause no.
10.1, Page no. 687 following :
- Aqua Machineries Pvt. Ltd. (Aqua)
84. Volume – 3, Section
XII, Page no. 707, 708
& 711
The quantity “1 Nos.” against S. no. 5(c) at Point no. A. Demolition Works
under Price Schedule : A3-Breakup of Cost for Rehabilitation of Existing
Civil Units, may be read as “3 Nos.”
The parameter “500 microns” at 2nd
line in S. no. 19 under „Description‟
column at Point no. B. Rehabilitation Works under Price Schedule : A3-
Breakup of Cost for Rehabilitation of Existing Civil Units, may be read as
“250 microns.”
85. Volume – 3, Section
XII, Page no. 719
Add parameter “NA” under column „DLP‟ in heading „A. Fixed Part‟ against
S. No. 3, 4 & 5 under „Price Schedule : B1, Operation and Maintenance‟.
86. Volume – 3, Section
XII, Page no. 720
The words “Rs. 6.30 (Rupees Six and Paise Thirty only)” in point no. (ii) of the
NOTE under the table of „Price Schedule:B1, Operation and Maintenance‟,
may be read as “Rs. 7.20 (Rupees Seven and Paise Twenty only)”
87. Volume – 3, Section
XII, Page no. 720 The point no. (iv) of the NOTE under the table of „Price Schedule:B1,
Operation and Maintenance‟, “For evaluation purpose the unit rate of
…………….. net electrical consumption”, stands deleted.
The revised point is as under:
“For evaluation purpose, the NPV of O&M cost will be calculated using the
values in row 15 above and electricity cost will be added to the same.”
88. Vol. 3, Section XV,
Service Level
Agreement during O &
M period of 10 yrs and
during Defect Liability
Period, Page no. 732 &
733
The * point “An event …………… system reliability” under the table of
„Liquidated Damages for Non Compliance of Treated Effluent Standards‟,
stands deleted.
The revised * point is as under :
“* An event is defined as online reporting duration within 3minutes. Cumulative
event shall be of maximum of total 30 minutes a day i.e. 98% system
reliability.”
The first paragraph under „Condition-B: Breakdown of Equipment‟, “In case
of breakdown………………… mentioned below”, stands deleted.
The revised paragraph is as under :
“In normal practice it is expected that there would not be any breakdown of
equipment with proper preventive maintenance. However, in an eventuality under
exceptional conditions and with the approval of Employer, the Contractor shall be
penalized as mentioned below :”
The parameters “2% & 1%” under the column „Penalty Imposed‟ against
„Semi-Critical Equipment and Non Critical Equipment‟, may be read as “5%
& 6%”.
89. Volume-4, Section
XVI, drawing list
The drawing no. “YAP-III/R2/E/SLD/001(T) R0”, stands deleted.
The revised drawing no. YAP-III/R2/E/SLD/001(T) REV.-01 is attached as
Annexure E-1.
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 13
ANNEXURE- 1
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 14
Section – IV: Bidding Forms (Technical Evaluation) & Bidders Technical
Proposal for Rehabilitation
Letter of Technical Bid
Date: [insert date of Bid submission]
Loan Agreement No.: ID-P215
IFB No.:
To:
EXECUTIVE ENGINEER (C) DR. XI
DELHI JAL BOARD
Govt. of NCT of Delhi
Room No. 308, Varunalaya, Phase – I
Karol Bagh, New Delhi - 110005
We, the undersigned, declare that:
(a) We have examined and have no reservations to the Bidding Documents, including addenda
issued in accordance with Instructions to Bidders (ITB 8). [Insert the number and issuing date of
each addendum];
(b) We, including subcontractors meet the eligibility requirements in accordance with ITB 4 and ITB
5;
(c) We, including subcontractors have no conflict of interest in accordance with ITB 4;
(d) We offer to execute in conformity with the Bidding Documents the following Works:
“Rehabilitation and Up-Gradation of Rithala Phase - I Wastewater Treatment Plant (WWTP)
182 MLD with Effluent Standards of BOD – 10 mg/l, TSS – 10 mg/l or better under YAP (III)”.
(e) Our Bid shall be valid for a period of 180 days from the date fixed for the Bid submission
deadline in accordance with the Bidding Documents, and it shall remain binding upon us and
may be accepted at any time before the expiration of that period;
(f) We are not participating, as a Bidder or as a subcontractor, in more than one Bid in this bidding
process in accordance with ITB 4.2(c), other than alternative Bids submitted in accordance with
ITB 13; and
(g) We hereby certify that we have taken steps to ensure that no person acting for us or on our behalf
will engage in any type of fraud and corruption.
Name of the Bidder*[insert complete name of person signing the Bid]
Name of the person duly authorized to sign the Bid on behalf of the Bidder** [insert complete name
of person duly authorized to sign the Bid]
Title of the person signing the Bid [insert complete title of the person signing the Bid]
Signature of the person named above [insert signature of person whose name and capacity are shown
above]
Date signed [insert date of signing] day of[insert month], [insert year]
*: In the case of the Bid submitted by joint venture specify the name of the Joint Venture as Bidder
**: Person signing the Bid shall have the power of attorney given by the Bidder to be attached with
the Bid.
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 15
ANNEXURE - 2
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 16
Joint Venture Agreement for Consortium
(On Non – judicial stamp paper of Rs 100 duly attested by notary public)
This Joint Venture Agreement (Agreement) entered / intend to enter into this day of 201__
at__________________________________________________________________
Among
_______________(hereinafter referred as” ---------------”) and having office at ________________
Party of the First Part
_______________(hereinafter referred as” ---------------”) and having office at ________________
Party of the Second Part
_______________(hereinafter referred as” ---------------”) and having office at _________________
Party of the Third Part
The parties are individually referred to as Party and collectively as Parties.
Whereas DELHI JAL BOARD (the “Employer”) has invited Proposals from interested Firms
and/or Consortiums for Appointment of Private operator for Project[s].
AND WHEREAS the Parties have had discussions for formation of a Consortium for bidding for the
said Project and have reached an understanding on the following points with respect to the Parties
rights and obligations towards each other and their working relationship.
IT IS HEREBY AS MUTUAL UNDERSTANDING OF THE PARTIES AGREED AND
DECLARED AS FOLLOWS:
1. That M/s ________________ who is the Lead Members of the Consortium commits to hold a
minimum stake equal to __% of the Consortium at all times during the Contract Period.
2. That any dilution of participation interest by the Parties in the consortium shall be as per the
provisions of the Contract.
3. That the Parties shall carry out all responsibilities as per terms of the Contract.
4. That the roles and the responsibilities of each Party at each stage of the Bidding shall be as
follows:
Name of Consortium
Member
Role (Lead Member
or Member)
Percentage
Share in
Consortium
Responsibilities
No changes in the percentage share in consortium shall be allowed thereof, except in accordance with
the provisions of the Contract document.
5. That the Parties affirm that they shall implement the Project in good faith and shall take all
necessary steps to see the Project through expeditiously. They shall not negotiate with any other
party for this Project.
6. That the parties shall be jointly and severally liable for execution of the project.
7. In case of default of member(s) the following recourse shall be applicable:
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 17
8. That this Agreement shall be governed in accordance with the laws of India and courts in Delhi
shall have exclusive jurisdiction to adjudicate disputes arising from the terms herein.
In witness whereof the Parties affirm that the information provided is accurate and true and have
caused this Agreement to be duly executed on the date and year above mentioned.
Name, Designation and Signature of
Authorized signatory of Party of the first part:
Authorized signatory of Party of the second part:
Authorized signatory of Party of the third part:
Witness 1
Witness 2
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 18
ANNEXURE - 3
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 19
Section - III: Evaluation Criteria
1.1 Evaluation of Technical Bids
1.1.1 Assessment of Adequacy of Technical Proposal with Requirements
1.1.2 Personnel
The Bidder must demonstrate that it has the personnel for the key positions to be posted at site that meet
the requirements in the Table: List of Key Personnel.
The Bidder shall provide details of the proposed personnel and their experience records in the relevant
Information Forms included in Section IV, Bidding Forms.
TABLE : LIST OF KEY PERSONNEL
S.
No. Position
Desirable
Qualification
Total
Experience
(Years)
Experience
in Similar
Works
(years)
Minimum
number
Required
1 Construction
Project Manager
Graduate in Civil
Engineering with
experience in Project
Management
15 10 1
2 Construction
Project Engineer
(Civil)
Graduate in Civil
Engineering
10 5 1
3 Construction
Project Engineer
(Mechanical /
Electrical)
Graduate in Mechanical /
Electrical Engineering
10 5 1
4 Quality
Assurance /
Quality Control
Engineer
Graduate in Civil
Engineering
10 5 1
5 Safety Engineer Diploma in Safety
Engineering
5 3 1
Note:
The above staff and number are the minimum to be available at site, as per site requirement, during
execution of contract. However, the successful bidder shall deploy additional staff of required
qualification in sufficient numbers, as required at site for successful completion of the contract. The
Project Manager should be responsible for timely execution of work and he should have an authority of
work in administrative and financial deals/decisions for the project.
The Bidder shall provide details of the proposed personnel and their experience records in Form PER-1
and Form PER-2 in Section IV: Bidding Forms.
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 20
1.1.3 Equipment
a. The Bidder must demonstrate that it has all the key construction equipment and specifically the
equipment listed below:
Table-Key Items of Equipment
S. No. Equipment Type and Characteristics
1 Excavators
2 Mobile Crane (10 ton capacity)
3 Bar bending and cutting machines
4 Concrete pump
5 Concrete Batch Mixing Plant
6 Concrete mixers Machines(Electrical/Diesel)
7 Concrete vibrator of various types
8 Dewatering pump sets
9 Tippers/trucks (3 Ton / 12 Ton capacity)
10 Cube testing machines
11 Diesel Generator set (62.5 kVA capacity)
12 Welding Machinery
13 Water Tankers (10,000 Litre capacity)
b. The above is a partial list and number of equipment/machinery/plant specified herein may vary as
per actual requirement at site.
c. The Bidder shall provide further details of proposed items of equipment using Form EQU in
Section IV: Bidding Forms.
d. The bidder shall arrange all machinery, tools, plants, equipments, etc required during construction
as per the site requirements.
e. The number and capacity of the equipment/machinery/plant to be engaged in the work are to be
compatible with nature and magnitude of works so as to complete the work on schedule.
f. All the equipment/machinery/plant operators shall be skilled and experienced in using the
equipment/machinery/plant to deliver the necessary output.
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 21
1.2 Evaluation of Price Bids
In addition to the criteria listed in ITB 36.2 (a) – (d) the following criteria shall apply:
For plant and equipment, the comparison shall be of the ex-factory price of plant and equipment offered
from within the Employer's country, (such price to include all costs as well as duties and taxes paid or
payable on components and raw material incorporated or to be incorporated in the plant and equipment)
and of the CIF-named port of destination price offered from outside the Employer's country; plus the cost
of local transportation, civil works, installation and other services required under the contract.
The following evaluation methods for bid evaluated the “Lowest Evaluated Substantially Responsive
Bid” shall be followed:
(a) Time Schedule: The plant and equipment covered by this bidding process are required to be
shipped, installed and the facilities completed within the period specified. Bidders submitting bids
that deviate from the specified time schedule will be rejected.
(b) Operating & Maintenance Costs:
i. Since the full-operation and maintenance costs (i.e., once all the facility construction is
complete and the entire phases are brought under operation to achieve the desired effluent
quality) of the facilities being procured form a major part of the life cycle cost of the
facilities, these costs will be evaluated for 15 years and based on the performance
characteristics of the plant and equipment proposed to be furnished by the Bidder as well as
on past experience of the Employer or other employers similarly placed. Such costs shall be
added to the bid price for evaluation.
ii. In addition to this, Operation and Maintenance cost as quoted by the bidder for the interim
operation and maintenance period(s), i.e., during interim period when only partial phase or
phases are complete in construction (works contract) and/or portions of the phases are under
construction rehabilitation, shall also be considered as part of evaluation.
Factors which will be used in calculating include:
i. Operation of the Plant and facilities during 1 year DLP plus 10 years of O&M Period at its
rated capacity/output following completion of commissioning and the trial operation period;
ii. The estimated total cost of the electricity required at and consumed by the Plant and
equipment during the 1 year DLP plus 10 years of O&M Period, including:
a. The power consumed by the equipment supplied as a part of the facilities, based on
calculations of the operating efficiencies and power consumption of all electrically-
operated Plant and equipment under working condition.
b. The guaranteed Power generated from Bio-gas and Micro-hydro Plant;
iii. The Evaluation shall further be considered as:
Based on the equipment selected, the bidder shall provide net guaranteed power
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 22
consumption (Total power requirement – Power generated) during operation and
maintenance. This net guaranteed power consumption shall be multiplied by the current
rate of electricity charges of Rs. 7.20 per KWh and shall be added to the overall operation
and maintenance cost provided by the bidder; which then will be used to determine Present
Value (PV) (O&M) for each year and for the total duration of O&M + DLP period.
iv. The rate at ten (10) percent per annum will be used to discount the present value of all
annual future costs calculated under (ii) above for the period specified in (i).
v. Land cost shall not be accounted for evaluation.
The O&M cost as quoted by the Bidder for the 10th Year will be used to calculate the cost for 11
th
Year onwards till 15th Year. For calculating Routine Operational Cost for Manpower, Electricity,
Consumables, Preventive/Periodic Maintenance Cost and Replacement Cost, an average escalation
factor of 8% shall be used for calculating the rate for each of the mentioned operational heads from
11th Year onwards till 15
th Year.
The O&M NPV cost inclusive of power cost calculated as per the procedure stipulated above will
be added to the Bid Price (capital costs plus Interim O&M cost) to obtain the Evaluated Bid Price
upon which the decision for award of contract will be based.
(c) Functional Guarantee of the facilities: Bidders shall state the functional guarantees in a format
indicated in Schedule XI, Section XII: Technical Schedules, Volume - 2 of Bid Document (e.g.
performance, efficiency, consumption) of the proposed facilities in response to the Technical
Requirements. Plant and equipment offered shall have a minimum (or a maximum, as the case may
be) level of functional guarantees specified in the Technical Requirements to be considered
responsive. Bids offering plant and equipment with functional guarantees less (or more) than the
minimum (or maximum) specified will be rejected.
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 23
Form PER-1: Proposed Personnel
[insert day, month, year]
Bidder‟s Legal Name: [insert full name]
IFB No.[insert number]
Page [insert page number] of [insert total number] page
[The Bidder shall provide the names of suitably qualified personnel to meet the specified requirements
stated in Section III: Evaluation and Qualification Criteria, Clause 1.1.2.]
1. Title of position*
Name
2. Title of position*
Name
3. Title of position*
Name
4. Title of position*
Name
*As listed in Section III.
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 24
Form PER-2: Resume of Proposed Personnel [insert day, month, year]
Bidder‟s Legal Name: [insert full name]
Joint Venture Party Legal Name:[insert full name]
IFB No.[insert number]
Page [insert page number] of [insert total number] page
[The Bidder shall provide the data on the experience of the personnel indicated in Form PER-1, in the
form below:]
Name of Bidder
Position
Personnel
information
Name Date of birth
Professional qualifications
Present
employment
Name of employer
Address of employer
Telephone Contact (manager / personnel officer)
Fax E-mail
Job title Years with present employer
[Summarize professional experience over the last 20 years, in reverse chronological order. Indicate
particular technical and managerial experience relevant to the project.]
From To Company / Project / Position / Relevant technical and management
experience
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III)
Delhi Jal Board
Corrigendum & Addendum No. 6 25
Form EQU: Equipment
[insert day, month, year]
Bidder‟s Legal Name: [insert full name]
Joint Venture Party Legal Name:[insert full name]
IFB No.[insert number]
Page [insert page number] of [insert total number] page
[The Bidder shall provide adequate information to demonstrate clearly that it has the capability to meet the
requirements for the key equipment listed in Section III: Evaluation and Qualification Criteria, Clause
1.1.3. A separate Form shall be prepared for each item of equipment listed, or for alternative equipment
proposed by the Bidder.]
Item of equipment
Equipment
information
Name of manufacturer
Model and power rating
Capacity
Year of manufacture
Current
status
Current location
Details of current commitments
Source Indicate source of the equipment
Owned Rented Leased Specially manufactured
Omit the following information for equipment owned by the Bidder.
Owner Name of owner
Address of owner
Telephone Contact name and title
Fax Telex
Agreements Details of rental / lease / manufacture agreements specific to the project
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III) Delhi
Jal Board
Corrigendum & Addendum No. 6 26
ANNEXURE
E-1
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III) Delhi Jal Board
Corrigendum & Addendum No. 6
27
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III) Delhi
Jal Board
Corrigendum & Addendum No. 6
28
ANNEXURE
E-2
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III) Delhi
Jal Board
Corrigendum & Addendum No. 6
29
FIELD PUSH BUTTON STATIONS
1. The design, manufacture and performance of the equipment to be supplied under the scope of this
specification shall comply with latest revisions of relevant Indian Standards and rules.
The design and workmanship shall be in accordance with best engineering practices as applicable
to industrial electrical enclosure.
2. CONS TRUCTION
Industrial Local Control Station enclosure shall be Cast Aluminium LM6 alloy enclosure having
minimum 3 mm thickness.
The enclosure shall be weather proof, IP-55 suitable for outdoor installation. Local control
stations for use in hazardous areas shall be Ex-d protection, suitable for gases such as methane
(CH4), CO, CO2 and H2S and shall be suitable for zone-1 application. These shall be CMRS
certified. All mating surfaces of industrial LCS shall be with continuous non-deteriorating type
special rubber gasket/neoprene gaskets. An additional 2mm thick Aluminium canopy shall be
provided to give adequate protection against weather.
3. CABLE ENTRIES
Two threaded entries shall be of 20 mm shall be provided on each Local Control Stations at the
bottom for fixing the cable glands. Metallic/rubber plug shall be provided for sealing one of the
cable entry.
4. EARTHING
The enclosure shall be provided with two(2) nos. of external earthing terminals and one (1) no.
internal earthing terminal each of 2.5 mm diameter complete with nut, spring washers for
termination.
5. WIRING
All internal wiring up to the terminal block in the Local Control Station shall be carried out with
1.5 sq.mm stranded copper conductors. Wires shall be PVC insulated type 650/1100V grade. The
wire shall be terminated with crimping type lugs only and shall be provided with ferrules at both
the ends.
6. PAINTING
The Local Control Stations shall be treated with two coats of epoxy primer after thorough
cleaning and treating of the surfaces and shall be finally provided with two coats of epoxy paint.
Shade of final paint shall be 631 of IS5.
7. NAME PLATE
Each LCS shall be provided with name plate. Name Plate shall be made from rear engraved,
Perspex with letters of size minimum 6 mm on black background. All name plates shall be
identical in size and shall be fixed with screws on the cover.
8. COMPONENT SPECIFICATIONS
PUSH BUTTON
Each push button shall be provided with 1NO+1NC contacts, each rated to carry, make and break
10A at 240 V AC.
Colour of the actuators of “STOP” push button shall be RED and that of “START” push button
shall be GREEN. Stop push button actuator shall be mushroom head type and shall have stay-put
feature i.e. once the STOP push button is pressed, it remains in pressed position until its actuator
is turned in either direction. START push button shall be totally shrouded type to prevent
accidental start of the motor.
Rehabilitation and Up-gradation of 182 MLD Phase-I WWTP at Rithala under YAP (III)
JICA funded Yamuna Action Plan Project (III) Delhi
Jal Board
Corrigendum & Addendum No. 6
30
TERMINAL BLOCK
Voltage grade of terminal block shall be 660V. Current rating, their size and make shall be as per
the requirement specified. Two nos. spare terminals shall be provided in each local control
station.
9. DRAWING DATA AND MANUALS
The various drawing and documents to be submitted with offer and after placement of order shall
be as per attached schedule. Before starting manufacture of the equipment, the manufacturer shall
take the approval of design drawings from the engineer.
10. INSPECTION & TESTING
The LCS shall be routine tested at manufacturer‟s works in the presence of purchaser/his
representative before dispatch to site.
11. SPECIFIC TECHNICAL PARTICULARS
S.NO. DESCRIPTIONS DETAILS
1 Material of Enclosure Die Cast Aluminium alloy LM6
2 PUSH BUTTONS Make
3 Actuator GREEN for START and RED for STOP
4 TYPE Spring return for START and mushroom
headed stay put for STOP
5 Standard to which equipments
confirm
IS 8623 & IS 4237
6 Terminal Block
6.1 Type Clip-on
6.2 Size 2.5 sq.mm
6.3 Voltage Grade 660V
6.4 Current Rating 10A
7 Internal Wiring
7.1 Size 1.5 sq. mm Stranded copper conductor.
31
Name of work :- Rehabilitation and Up-Gradation of Rithala Phase - I Wastewater Treatment Plant (WWTP) of 182 MLD with Effluent Standards of BOD < 10 mg/l, TSS < 10 mg/l or better under YAP (III) Project (on
DBO basis) with 10 years Operation & Maintenance (Package R2).
Reply to Prebid Queries
S. No. Volume Page Clause Particulars as per Bid Document Bidder‟s Queries Reply
1) Vol 1, Part A
Sec 1
3 2.3
Section - I
Japanese ODA Loan The loan received from JICA would be applied for portion of works to be carried under
this project.
We understand that complete scope of work falling under Part-A “Works Contract” is
funded by JICA.
Kindly confirm our understanding is correct.
Further specify the source of funding for Operation & Maintenance part and confirm
the agency involved, would be part of Contract agreement signed with selected bidder
post award.
Part A: Capex by JICA
Part B: O&M by DJB
2) Vol 1, Part A
Sec 1
3 2.3 The above Loan Agreement will cover only a part of the project cost.
As for the remaining portion, the Borrower will take appropriate
measures for finance
Please indicate the Funding structure of Project by JICA for Design and Build and
O&M
As above
3) Vol 1, Part A
Sec 1
6 Clause 4.2 I A firm (including its affiliate), if acting in the capacity of a
subcontractor in one Bid, may participate in other Bids, only in that
capacity.
We feel that this is an indirect conflict of interest, as the arrangement could impact the
financial bid of bidders involved with such subcontractor, and should be disallowed.
Kindly accept and confirm.
As per bid document
4) Vol 1, Part A
Sec 1
6 Section I
Clause 5
Materials, Equipment and Services
Please mention the list of eligible source countries
As per bid document
5) Vol 1, Part A
Sec 1
14 18.3
Section I
Contract Price Adjustment Please elaborate.
Considering fluctuating prices of materials and labour and prevailing practice of
contract price adjustment is governed by price prevailing 28 days prior to the date of
bid submission. Accordingly request to confirm reduce the bid validity to 120 days
followed by 30 days for applicability of bid price adjustment factor.
As per bid document
6) Vol 1, Part A
Sec 1
15 Clause 19.4, ITB The Bid Security of unsuccessful Bidders shall be returned as
promptly as possible upon the successful Bidder‟s signing the
Contract and furnishing the Performance Security pursuant to ITB 42.
This is a risk for the Bidders:
a) The returning of Bid Security of unsuccessful Bidders should not be linked to the
successful Bidder‟s actions such as signing of Contract or furnishing of
Performance Security. The Employer may, if consider appropriate, forfeit
successful Bidder‟s Bid Security in accordance with Clause 19.6 (b), if he fails in
his obligations, but the same should not be a reason to hold back unsuccessful
Bidder‟s Bid Security; and
b) The returning of Bid Security of unsuccessful Bidders should be time bound
activity, say within 10 days of declaring as unsuccessful Bidder
Kindly accept and confirm.
As per bid document
7) Vol 1, Part A
Sec 1
17 22.1 Bid Submission Date Being a major tender/project and lot of work involved in preparation of Technical
Study, Process calculations, Dealing with nos. of vendors/agencies, obtaining a techno-
commercial quotes and preparation of technical cum financial bid, we feel the time
provided is less, therefore we request you to please extend the date of submission of
the tender for 8 weeks after receipt of Pre-Bid Clarification Report.
Please accept and Confirm.
Refer C&A No. 5
8) Vol 1, Part A
Sec 1
25 Clause 36
Evaluation of Price bids
Power consumption is not specified as evaluation criteria. Please confirm the same.
Refer C&A No. 6, Sl. No. 3
9) Vol 1, Part A
Sec 1
27 Clause 41, Signing of Contract: “Within twenty-eight (28) days of receipt of the
Contract Agreement, the successful Bidder shall sign, date, and return
it to the Employer.”
Against the subject clause we please clarify ....If the Successful Bidder can sign the
contract through any of its SPVs [existing or by incorporating a new SPV (company or
LLP, as desired by the bidder)] instead of signing of the contract itself. Further the
period of 28 days seems very short and propose at least 45 days‟ time for signing of the
contract by such SPV.
Please confirm.
As per bid document
10) Vol 1, Part A 29 Condition of ITB 2.1. The amount of Japanese ODA Loan is JPY 32,571 million. Please kindly indicate the share of this amount that is allocated for the current As per bid document
32
Sec II Contract, Part A –
Section II : BDS
Package-R2 which is the Scope of Works for this Tender.
11) General
Volume - 1
-
29
-
Bid Data Sheet (BDS) The clause descriptions/ conditions mentioned in the Bid Data Sheet (BDS) for the
package shall amend and/or supplement the provisions in the Instructions to Bidders
(ITB). Wherever there is a conflict, the provisions of BDS shall prevail over those in
the ITB. Kindly confirm.
As per bid document
12) Vol 1, Part A
Sec II
31 11.2
Section II
Hard Copy Submission Submission of Original set + 3 Copies of complete bid along with original tender
documents in 3 sets is desired. Usual practice is returning original ONE set of tender
documents dully signed & stamped on each page, confirm our understanding is correct.
Confirmed
13) Vol 1, Part A
Sec II
31 11.2,
Section II
Joint Venture Agreement Kindly provide the format or confirm bidder can submit per his own format. Refer C&A No. 6, Sl. No. 2
14) Vol 1, Part A
Sec II
31 Ref. Cl. ITB 11.2
(a) to (g)
Statement from the Bidder (and each member of a Joint Venture) in
accordance with Clause 4 Section I: Instructions to Bidders;
In the absence of any specific format bidders are allowed to submit statement with
requisite declaration in their own format. Kindly confirm or provide the specific
format/ form of declaration
Refer C&A No. 6, Sl. No. 2
15) Vol 1, Part A
Sec II
31 Ref. Cl. ITB 15.1
(ii)
For those inputs to the Works that the Bidder expects to supply from
outside the Employer‟s country (referred to as “the foreign currency
requirements”), in Japanese Yen, Euro and/or USD.
We understand from the clause that the supplies from outside the Employer‟s country
can be quoted in more than one (1) foreign currency
As per bid document
16) Vol 1, Part A
Sec II
31 BDS, ITB 11.2 We presume that signed tender document is not to be submitted along with the bid.
Please confirm.
Duly signed & stamped
original tender document is to
be submitted along with bid 17) Vol 1, Part A
Sec II
32 Bid Security ,
Validity &
Release
We understand that in case of Joint Venture (not being legally incorporated at the time
of bidding) the lead partner can submit the Bid Security in the form of Bank Guarantee
in its own name.
Kindly confirm our understanding
As per bid document
18) Vol 1, Part A
Sec II & Vol-
3, Sec-XII
32, 25
& 720
ITB : 32.3, 36.1
36.2, 34.1 & Price
–B1
Evaluation Criteria The evaluation criteria specified at the different places in the document is not clear and
is not giving the feel of actual methodology of evaluation. Hence, We request you to
kindly provide us the detailed evaluation criteria for this project.
Refer C&A No. 6, Sl. No. 3
19) Vol 1, Part A
Sec II
32 20.2
Section II
Power of Attorney Legally valid Power of attorney is envisaged for authorized signatory of bid.
Notarized power of attorney is submitted with all bids as legalized document, please
confirm is ok.
As per bid document
20) Vol 1, Part A
Sec II
32 Ref. Cl. ITB 20.2 The written confirmation of authorization to sign on behalf of the
Bidder shall consist of: Original Power of Attorney (legally valid) for
authorised signatory of the Bid.
Power of Attorney by nature is one original document issued in the name of the
authorized signatory. We request you to accept a Notarised copy of Power of Attorney
instead of Original.
As per bid document
21) Volume – 1 ,
Part A, Section
– II
33 Bid Data Sheet: Date of Submission This bid is quite complex since require proper design work and coordination with EPC
and O&M interface, especially during the Interim Period. Please kindly provide an
extension of ten weeks.
Refer C&A No. 5
22) Vol 1, Part A
Sec II
34 42.2
Section II
Performance Security Bank issues bank guarantee for in favour of company transacting with them in lieu of
assurances available and not in name of JV formed.
Thus accept the Performance security from Lead partner of JV for performance of
contract.
As per bid document
23) Vol 1, Part A
Sec II:
34 Condition of
Contract, Part A –
Section II : BDS
ITB 42.2. In the case of Joint Venture (JV), each partner shall submit
the Performance Security in the name of joint venture from his own
bank account and in the same proportion of their JV.
Please kindly confirm that this requirement only applies to the Performance Security
and not to any other bank security, e.g. such as the Bid Security
Confirmed
24) Volume–1 ,
Part A,
Section–III
35 Evaluation of price bid The Criteria of Evaluation of price bids for lowest bidder is not detailed in the tender
documents, However factors like “net electrical consumption”, NPV calculation on
total O&M cost etc. are provided in the Volume – 3, Section : XII ( page No. 720).
We request DJB to kindly reconfirm the criteria of arriving the lowest evaluated bid
price.
Refer C&A No. 6, Sl. No. 3
25) Volume 1 Part
A, Section–I
45 Clause 1.1.3.3
(ii):
O&M Period EPC period finishes upon receipt of Take-Over Certificate and O&M period starts
upon completion of Works, i.e. upon issuance of Take-over Certificate. However
clause 1.1.3.7, clause 4.19 and 10.5 confirms that Bidder shall bear all O&M cost
during the DLP period. Further clause 1.1.4.2(c) confirms that the O&M period is 10
years. However Clause 8.1 confirms that the Contractor shall commence the Operation
and Maintenance services immediately after successful commissioning of the entire
As per bid document
33
Works and issuance of the Taking-Over Certificate. Similarly Clause 8.2 and 10.5 refer
to Section X which allows for 1+10 years of Operation and Maintenance.
26) Vol 1, Part A
Sec VIII &
Vol 2, Sec XI,
Part 1
46
&
135
1.1 Interim operation & Maintenance &
Brief Scope of work.
It is mentioned that Interim operation shall start from the 28 days from the Letter of
Acceptance which is contradicting with the clause 1.7. Point -1 where it is specified
that the contractor shall take over the existing plant within 28days from the effective
date of contract. Kindly Clarify.
Refer C&A No. 6, Sl. No. 4
27) Vol 1, Part A
Sec VIII
47 - Contract Value We understand that this project is JICA funded. We hope that funds would be available
for this Project.
As per bid document
28) Vol 1, Part A
Sec VIII
48 Particular
Conditions,
Clause 1.5
Priority of Documents We request you to re-arrange the priority of documents as suggested below:
(a) The Contract Agreement;
(b) The Letter of Acceptance;
(c) The Letter of Tender;
(d) Corrigendum & Addendum and Reply to Pre-Bid Queries issued
(e) The Particular Conditions;
(f) The General Conditions of Contract;
(g) The Employer‟s Requirement;
(h) The Schedules (if any)
(i) Contractor‟s Proposal and post Bid-opening correspondence;
Internal Note: We have shift the priority of the document mentioned at Pt. (h)
Corrigendum & Addendum and Reply to Pre-Bid Queries issued of Particular
Conditions of the Contract document to make it as Pt. (d).
As how the conditions as mentioned in the Particular Conditions or in General
Conditions of Contract supersedes the Conditions revised in Corrigendum or agreed in
replies to pre-bid queries.
As per bid document
29) Vol 1, Part A
Sec VIII
48 1.5 Priority of documents We wish to submit that a contract agreement is finalized with bidder, with following
sequence of events :-
Negotiation of prices, if required.
Any non-material clarifications in contractors bid.
Evaluation of contractor‟s bid document.
Tender addendums, which may or may not be result of bidder technical / commercial
queries.
Pre-bid replies to pre bid queries.
Bid documents – The particular requirements, GCC, Employer requirements, various
schedules.
The tender specified Priority of documents is not in sequence of actual progress of a
Tender being converted into Contract Agreement. In its present form, it leaves room
for ambiguity and flawed interpretation. In order to eliminate these discrepancies, we
propose the priority as – (a), (b), (c), (i), (h), (d), I, (f), (g).
As per bid document
30) Vol 1, Part A
Sec VIII
49 Sub- Clause 1.16 If required, the Contractor shall have to remove all
defects/deficiencies pointed out by the I/CTE/Employer and/or
Employer‟s Personnel. Recoveries, if any, proposed by the
DJB/CTE/Employer and/or Employer‟s Personnel, will be
enforceable from the Contractor‟s payment.”
From the word recoveries we mean that any applicable Liquidated Damages. If not, we
request you to remove the clause of recoveries as the contractor is already liable to
remove all defects/ deficiencies
As per bid document
31) Vol 1, Part A
Sec VIII
49 Section VIII
Clause 1.13
Compliance with Laws
Please specify the extent and names of the Permits/Licenses/Approvals which
contractor needs to obtain. Also, please confirm if the same will be paid by the
Employer
As per bid document
32) Volume 1 Part
A, Section–I
49 Clause 1.13:
Compliance with Laws It is noted that Contractor shall obtain all permits, however it would be expected that
government atleast obtain initial and most important permits like planning permission
upon approval of the Environmental Impact Statement. Please confirm.
As per bid document
33) Vol 1, Part A
Sec VIII
50 Particular
Conditions,
Clause 4.2,
Performance Security If the Contract is extended beyond the original date of Completion of the Project not
due to the reasons attributable to Contractor then in such case whether Employer will
pay the commission charges for extending the validity of the Performance Security.
Please confirm.
As per bid document
34
34) Volume 1 Part
A, Section–I
50 Clause 4.1: Contractor‟s General Obligations
Kindly note that “fit for purpose” obligations are not market standard. The obligations
of the Contractor shall be to comply with the contract, whereas this clause could go
beyond. Please kindly delete reference to “fit for purpose”.
As per bid document
35) Vol 1, Part A
Sec VIII
50
& 85
Sub Clause 4.1
and 22.3
Sub- Clause 4.1 – Contractor‟s General Obligations
Sub-Clause 22.3 – Delivery of Raw Material
We request you to remove the clause of “Fit for Purpose” from the contract. As per bid document
36) Vol 1, Part A
Sec VIII
52 PCC, Clause 4.2 “No payment on account of manpower, consumables & preventive
maintenance /replacement is admissible to the Contractor during Trial
run & commissioning period of the WWTP”
This is a risk to the Contractor. Kindly amend this in line with arrangement for power/
electricity to the certain extent, this cost to be borne by the Employer, and beyond this
the Contractor.
Kindly accept and confirm.
As per bid document
37) Vol 1, Part A
Sec VIII
52 4.19
Section VII
Construction Power & Water Request provide both construction power and water free of cost since essential
component of project execution to support to fasten the execution activity and to
continue during trial run as already confirmed.
As per bid document
38) Vol 1, Part A
Sec VIII
52 4.19
Section VII
Power & water Kindly provide construction power & water free of cost for faster execution. As per bid document
39) Vol 1, Part A
Sec VIII
52 4.19
Section VIII
Excess Power During Trial run period excess power consumption that exceeds guaranteed power
value contractor to pay difference of actual vs guaranteed.
As per bid document
40) Vol 1, Part A
Sec VIII
52 Sub-Clause 4.19 Electric connection Clause no. 4.19 specifies, electricity connection is to be arranged by the contractor.
Since the plant is existing power connection is available for this Rehabilitation and
Up‐gradation work, please confirm.
Please advice for either case of electric connection, the approximate distance from
power source to DJB boundary be advised.
The Contractor is required to keep Generators of adequate capacity as standby
arrangement in case of electricity failure during construction for running of pump sets,
vibrators, mixer, needle sets and electric set and other electrically operated
construction equipment etc. Please confirm.
As per bid document
41) Vol 1, Part A
Sec VIII
52 - The cost of electricity / power supplies shall be paid directly by DJB
to electricity supply company as per the similar provision of O&M
period. During the 1 year DLP and 10 years O&M period, the
Contractor shall pay the electricity charges to the Electricity Supply
Agency.
These statements are contradictory. We understand that the electricity bill during the
O&M & Interim Period. Kindly confirm.
Refer C&A No. 6, Sl. No. 6
42) Vol 1, Part A
Sec VIII
52 Sub Clause 4.19
Electricity, Water and Gas
As per tender “The Contractor shall arrange and provide at his own cost electric
connection of suitable load from Electricity Supply Agency.”
Kindly change as the client shall provide electric connection from Electricity Supply
Agency at a single point within plant premises and the bill for the same shall be paid
by contractor.
As per bid document
43) Vol 1, Part A
Sec VIII
52 Sub-Clause 4.19 Electricity, Water and Gas:
The cost of electricity / power supplies shall be paid directly by I to
electricity supply company as per the similar provision of O&M
period. i.e., minimum of the power consumption guaranteed by the
contractor or actual consumed at site. However any excess power
consumed than the guaranteed power during six months trial run
period then the power charges shall be borne by the Contractor.
We request you to pay bonus if the consumption of grid power is lesser than the net
power consumption guaranteed by the contractor by efficient operation of gas engine.
Please accept and Confirm.
As per bid document
44) Vol 1, Part A
Sec VIII
53 Sub. Cl. 4.19 Electricity, Water & Gas We understand from the clause that electricity charges during construction period shall
be borne by Contractor and during trial run & commissioning by I. For later, the
provisions shall be similar to the O&M period. Kindly confirm
As per bid document
45) Vol 1, Part A
Sec VIII
53 Sub. Cl. 4.19 Trial run and commissioning period is given as 6 month Trail run and commissioning period is given as 6 month. Please specify what is the
trial run period after which start of O&M is considered.
Kindly clearly define the sequential events and periods of Commissioning, Trial Run,
PGTR
As per bid document
46) Vol 1, Part A
Sec VIII
55 Sub- Clause 5.2 Review period for Contractor‟s Documents Considering the stringent project time lines, it is important that the document review
period should be strictly defined in the contract. As per FIDIC yellow book cl. 5.2, the
review period of contractor‟s documents shall not exceed 21 days for acceptance or
As per bid document
35
non-acceptance. We suggest employer to incorporate this clause in the Particular
conditions of contract.
47) Volume 1 Part
A, Section–I
57 Clause 6.11 Disorderly Conduct
Contractor has to perform all the obligations as per the contract and completion risks
are already transferred, so it is unreasonable that the Engineer interferers with the
Contractor‟s labour. That would be a problem of the Contractor exclusively so please
kindly delete the second paragraph:
“In case of any disputes with labourer (skilled or unskilled) and charges are claimed
against the Contractor, the Engineer shall have the full authority to deduct the same
from the bill of the Contractor, so as to enable him to settle the disputes.”
As per bid document
48) Vol 1, Part A
Sec VIII
59 8.7 Mile Stones Please confirm that the Interim Milestones shall be defined and framed in consultation
& agreement with the Contractor.
As per bid document
49) Volume 1 Part
A, Section–
VIII
59
& 85
Clause 8.7 and
Clause 22.4
Delay Damages Compensation for loss of profit and loss of revenue is unreasonable and normally
excluded in similar contracts, including FIDIC, as penalties/damages are already
quantified in the relevant clauses. Please kindly delete points b) and c) in this clause.
As per bid document
50) Vol 1, Part A
Sec VIII
65
& 66
Particular
Conditions,
Clause 13.8,
Adjustment for changes in Cost We presume Contractor needs to provide the weightages for the price adjustment
formula as an annexure in the bid. Please confirm.
As per bid document
51) Vol 1, Part A
Sec VIII
65 13.5
Section VIII
Price Variation O&M period is 11 yr. (including DLP), price variation clause must be applicable both
on chemical & fuel. Confirm & provide formulae.
As per bid document
52) Vol 1, Part A
Sec VIII
65 Sub-Clause 13.7 Adjustments for Changes in Legislation Adjustments for changes in legislation to include GST as well.
Please accept and confirm.
As per bid document
53) Vol 1, Part A
Sec VIII
65 Sub-clause 13.8
Adjustment for
change in cost
Price Variation shall be applicable for Works Contract and Operation
and Maintenance contract
We understand Price variation clause shall be applicable for “Interim O&M contract”
also
As per bid document.
54) Volume 1 Part
A, Section–
VIII
65 Clause 13.8
Adjustment for Changes in Cost This clause is meant to apply to construction projects, however this being a DBO it is
felt that the clause shall be adjusted accordingly since the weightage of Labour and
materials during this two periods is completely different. Otherwise the inflation risk of
the Contract during the O&M is much more than the 15% intended. Please kindly
provide specific relief for O&M period where the labour component is much bigger
than the material.
As per bid document
55) Vol 1, Part A
Sec VIII
66 - The base date shall be taken as 28 days before the last date of
submission of final bid.
We understand this applicable for O&M Contract as well. Kindly confirm. As per bid document.
56) Vol 1, Part A
Sec VIII
68 13.9
Section VIII
Tax Variation Price bid is desired inclusive of all the taxes, Central government is likely to introduce
new taxes like GST etc.
Further contract duration is about 15 years with expectation of change in taxation
structure. Kindly confirm statutory variations shall be reimbursed like recovery being
made on prevailing rates.
As per bid document
57) Vol 1, Part A
Sec VIII
68 13.9 – Taxation Unless explicitly mentioned in the Contract, Employer doesn‟t ensure
any tax benefits (reduced tax rate/tax waivers) under Custom Duty,
VAT, any Cess, etc, during the time of submission of bids. Bidders
are advised to consider the actual tax rates (without considering any
waiver) while estimating the Contract Price. Any benefits received
during the currency of Contract or later shall be passed on to the
Employer by the Contractor. The amount due under the clause shall
be recovered from Contractor‟s Running account bill, final payment
or any other payments due the Contractor under this Contract.
Employer shall also have the right to liquidate the Performance
Security available with it to the extent required to recover such
amount due.
We observed from the tender documents that this DBO Project being invited under
International Competitive Bidding and Funding from Japan International Cooperation
Agency (I) towards the cost DJB Project (111). In view the above, request the
employer to confirm the following :-
(a) Whether Exim Benefit applicable Exim Policy of India shall be considered in the
bid,
(b) Whether employer will issue required Project Authority Certificate, Payment
Certificate/Disclaimer Certificate to avail Deemed Export by the Contractor
I Whether the employer issue relevant certificate under Exim Policy of India to obtain
advance license to the Contractor/nominee
As per bid document
58) Vol 1, Part A
Sec VIII
68 13.9 – Taxation For all items mentioned in Employer‟s Central Sales Tax
Registration, Employer shall issue “Form –C” so as to rationalize its
liability arsing out of Sales Taxes I a project except projects for
construction of residential and administrative blocks for the use by
Please confirm whether the Employer issue “Form C” to the Contractor on “Sale in
transit” sales.
As per CST rules.
36
employer and employees. Accordingly, Employer shall issue “Form
C” for all major materials and supplies/equipment made for Civil,
E&M and O&M works in the project as specified in “Annexure – List
of Items for issue of Form „C‟ , Volume 4 of the Bid documents,. The
bidders shall accordingly quote the price in a manner that transfer of
liability to Employer flowing from Sales Taxes is rationalized.
59) Vol 1, Part A
Sec VIII
68 Sub-Clause 13.9 Form all items mentioned in Employer‟s Central Sales Tax
Registration ……………… The bidders shall accordingly quote the
price in a manner that transfer of liability to Employer flowing from
Sales taxes is rationalized
Request the confirmation for issue Form-C for chemicals and Spares
supplied/Consumed during O&M by contractor which is being supplied on “Sale in
transit” under 6(2) of CST Act based on the contactor transit invoice.
As per CST rules.
60) Vol 1, Part A
Sec VIII
68 Clause 13.9
Taxation
Bidders are advised to consider the actual tax rates (without considering any waiver)
while estimating the Contract Price. Any benefits received during the currency of
Contract or later shall be passed on to the Employer by the Contractor. The amount due
under the clause shall be recovered from Contractor‟s running account bill, final
payment or any other payments due to the Contractor under this Contract. Employer
shall also have the right to liquidate the Performance Security available with it to the
extent required to recover such amount due.
The clause may be modified as “the amount due under the clause shall be recovered on
mutual consent of employer and contractor”
As per bid document
61) Vol 1, Part A
Sec VIII
68 Sub-Clause 13.9 Taxation Employer would be issuing form C for major materials and equipment‟s as specified in
their CST Registration certificate – In case there is any future liability on contractor
from tax authorities the same shall be borne by employer along with all associated
costs. CST Registration copy to be given to contractor/bidder.
Please confirm.
As per bid document
62) Vol 1, Part A
Sec VIII
68 Sub-Clause 13.9 Exemption on Excise Duty Does DJB sent any proposal or has any plan to make representation to Ministry of
Finance in order to allow excise duty and customs duty exemption for the project like
Notification 108/95 CE & 84/97 Cus available to WB/ADB sponsored projects, since
DJB is not an International Organization as per these notifications?
(This is very important since there could be huge savings in excise & customs duties
costs and its cascading effect on VAT/CST etc.)
Please confirm.
As per bid document
63) Vol 1, Part A
Sec VIII
68 Sub-Clause 13.9 Exemption on Service Tax Please confirm the exemption on Service Tax. As per bid document
64) Vol 1, Part A
Sec VIII
68 Sub-Clause 13.9 Taxation Please clarify and confirm whether DJB shall be eligible to issue Form–C for Bought-
out items / Goods supplied by Contractor through sub-suppliers on “Sale in Transit”
U/S6 (2) of CST Act wherein the Contractor‟ s Sales/Tax invoice do not consider CST
Tax separately in the invoice. Please confirm
Replied elsewhere
65) Vol 1, Part A
Sec VIII
68 Sub-Clause 13.9 Taxes and Duties Any increase or new imposition of taxes and duties & other levies shall be reimbursed
at actual Kindly accept and confirm.
As per bid document
66) Vol 1, Part A
Sec VIII
69 13.9 – Taxation The Contractor shall be accordingly required to submit its request for
issuance of “Form C” along with the following documents to the
Employer:
(a) The Contractor‟s Sale invoice specifying the goods, its quantity,
delivery challan, rate, value and tax (tax must be charged at the
concessional rate applicable against Form-C). Invoice should clearly
mention that the sale is against Form C. TIN No. of the parties
involved shall also be indicated.
Please clarify and confirm whether the Employer accepts contractor‟s “Sale Invoice”
which is inclusive CST against “Form C” for bought out plant and Equipments directly
supplied by manufacturer/sub-suppliers of “Contractor/Bidder”.
As per bid document
67) Vol 1, Part A
Sec VIII
69 13.9 – Taxation The above mentioned documents shall need to be submitted within
prescribed time limit of 60 days from the end of the period for which
the Form – C is required, failing with Employer shall not be
responsible for dely/denial of Form – C by the Department of Trade
& taxes, Government of National Capital Territory of Delhi and for
any consequential financial implications.
Please specify the time limit of 60 days is from the date of receipt of good at
Employer‟s site or after the certification of RA bill/invoice.
As per bid document
68) Vol 1, Part A 69 13.9 – Taxation Service tax (if any applicable) shall be reimbursed and shall not be We understand that by virtue of Notification No.25/2012 ST 20.6.2012 as amended As per bid document
37
Sec VIII included in the Tender Cost. time to time for Design and Build and O&M Contract. Pl confirm the required benefit
being considered in the bid
69) Vol 1, Part A
Sec VIII
69 Sub-Clause 13.9 Taxation:
The above mentioned documents shall need to be submitted within
prescribed time limit of 60 days from the end of period for which
Form-C is required, failing which Employer shall not be responsible
for delay/denial of Form-C by the Department of Trade & Taxes,
Government of National Capital Territory of Delhi and for any
consequential financial implications
We request to amend the clause that any delay/denial of Form – C by the Department
of Trade & Taxes, Government of National Capital Territory of Delhi shall be suitably
compensated by the Employer
As per bid document
70) Vol 1, Part A
Sec VIII
69 Sub Clause 13.9 /
Taxation
It is mentioned that “Service Tax (if applicable) shall be reimbursed and shall not be
included in the Tender Cost.”
We presume that the above clause is applicable for EPC as well as O&M scope also.
As per bid document
71) Vol 1, Part A
Sec VIII
71 Sub Cl. 14.4,
Particulars of
contract
Performance Guarantee test We understand that performance guarantee tests (PGTR) shall be for a period of 72
hours. The PGTR shall be performed immediately after 6 months commissioning &
trial run period and the subsequent payment shall be released. Kindly Confirm
As per bid document
72) Volume 1 Part
A, Section–I
71 Clause 14.4 Schedule of Payments The only difference of the Operation and Maintenance payment between the Interim
Period and the DLP Period / O&M Period is that “consumables & chemicals at
actuals”. Please kindly explain what it is meant by “at actuals”.
Please note that ability of the Contractor to properly manage the existing assets is very
limited, almost null. Thus it is very difficult to calculate the maintenance cost and
consumables and chemicals during the Interim Period, so it would be more appropriate
that the Employer reimburse such costs during this period as Employer is already doing
with Electricity, until the Taking-Over Certificate
As per bid document
73) Vol. I 73 - Type of Payment Payments during O&M will be independent of the quantity of sewage received at plant
inlet. Kindly confirm.
As per bid document
74) Vol 1, Part A
Sec VIII
74 14.8
Section VIII
Delayed Payment Interest provision of 10% on delayed payments is given, please provide number of
days beyond which the payment would be considered as delayed. Please confirm.
As per bid document
75) Vol 1, Part A
Sec VIII
74 14.7 Local Bank Account: The concerned Executing Agency (The
Employer) may include provision of payment to local bank account
which may be monitored by the Employer, and the bidder shall
ensure that the funds are utilized only for the intended project failing
which Penal Action may be taken by the Employer.
Request the employer to modify this clause to delete the monitoring of the bank of
account of Contractor is not order
As per bid document
76) Vol 1, Part A
Sec VIII
76 Clause 16.1 &
Clause 16.2
Termination payment Kindly clarify about termination payment under these clauses. As per bid document
77) Vol 1, Part A
Sec VIII
78 Particular
Conditions,
Clause 18
Insurance If the Contract is extended beyond the original date of Completion of the Project not
due to the reasons attributable to Contractor then in such case whether Employer will
pay the Premium charges for maintaining the validity of the required insurances as
mentioned in the Contract which are under the scope of Contractor. Please confirm.
As per bid document
78) Vol 1, Part A
Sec VIII
85 Sub- Clause 22.4 If the need to suspend the Operation and Maintenance by the
Employer is due to any failure of the Contractor or circumstances for
which the Contractor is responsible under the Contract, the provisions
of paragraph (a) of this Sub-Clause shall apply. If the need to suspend
the Operation and Maintenance is not as a result of any failure by the
Contractor or is due to circumstances for which the Contractor is not
responsible under the Contract, the provisions of paragraph (b) of this
Sub-Clause shall apply.
Kindly provide the paragraph (a) & (b) of this clause as the same is not defined in the
tender
Refer C&A No. 6, Sl. No. 7
79) Vol 1, Part A
Sec VIII
88 Clause 22.9, Adverse Operating Conditions Even if the Contractor manages to meet the Output Standards, it would incur additional
O&M cost. The Employer should compensate Contractor for any such additional O&M
cost. Kindly accept and confirm.
As per bid document
80) Vol 1, Part A
Sec VIII
88 22.8 Non-
availability of
Raw Sewage
In the event of non-availability of Raw Sewage to the Facility beyond
a continuous period of 56 working days, after the start of the
Operation Period the responsibilities of the Contractor shall stand
suspended. During such period of suspension, (i) the Employer shall
be liable to pay to the Contractor the Fixed Operation & Maintenance
We hope in the event of non-availability of Raw Sewage beyond 56 days, the charges
for the Day 1 to 56 th day shall be paid as per the Price Schedule A-7. Beyond 56th
day
until the employer resumes the facility the charges shall be paid as per Vol 3, Section
XII, Schedule of Payment and Prices, Schedule A-9.
Refer C&A No. 6, Sl. No. 9
38
Charges as specified by the bidder at the time of bidding in „Schedule
A-9, Section XIV, Volume 3 of Bid documents‟ (ii) in the event of
sustained inability to supply Raw Sewage to the facility for a period
greater than 56 days , the Employer shall be liable to pay inventory
holding charges for chemicals and consumables that may have been
stored by contractor for the purpose of treatment of sewage, that may
otherwise have been required, as per the consumption norms
specified at the time of bidding. Such charges shall be payable for
each day beyond the period of eight weeks mentioned hereinabove,
till such time as the Employer resumes the Facility.
81) Vol 1, Part A
Sec VIII
88 Sub-Clause 22.8 Non-Availability of Raw Sewage
Schedule A – 9 in the Price Schedule is missing. Kindly Provide.
Refer C&A No. 6, Sl. No. 9
82) Vol 1, Part A
Sec VIII
88 Clause 22.8 Non-availability of raw sewage:
In the event of non-availability of Raw Sewage to the Facility beyond
a continuous period of 56 working days, after the start of the
Operation Period the responsibilities of the Contractor Shall stand
suspended.
The 56 days of time period is extremely high, and is a risk for a Contractor. Kindly
reduce the same at 7 days.
Kindly accept and confirm.
As per bid document
83) Volume 1 Part
A, Section–I
88 Clause 22.8 Non-Availability of Raw Sewage It is understood that the 56 days period is intended to limit the inventory charges as per
point (ii). However the modification to the following paragraph is required, otherwise
the Contractor is taking the risk of non-availability of water for the first 56 days, which
is unreasonable and contradictory to point (i) of this clause. For clarity, amendment
requested is as follows:
“In the event of non-availability of Raw Sewage to the Facility beyond a continuous
period of 56 working days, after the start of the Operation Period the responsibilities of
the Contractor shall stand suspended.”
As per bid document
84) General
Volume-1
-
88
-
22.8
In the event of non-availability of Raw Sewage to the Facility beyond
a continuous period of 56 working days, after the start of the
Operation Period the responsibilities of the Contractor shall stand
suspended. During such period of suspension, (i) the Employer shall
be liable to pay to the Contractor the Fixed Operation & Maintenance
Charges as specified by the bidder at the time of bidding in „Schedule
A-9, Section XIV, Volume 3 of Bid documents‟ (ii) in the event of
sustained inability to supply Raw Sewage to the facility for a period
greater than 56 days , the Employer shall be liable to pay inventory
holding charges for chemicals and consumables that may have been
stored by contractor for the purpose of treatment of sewage, that may
otherwise have been required, as per the consumption norms
specified at the time of bidding. Such charges shall be payable for
each day beyond the period of eight weeks mentioned hereinabove,
till such time as the Employer resumes the Facility.
We understand beyond 56th day until the employer resumes the facility the charges
shall be paid as per Vol 3, Section XII, Schedule of Payment and Prices, Schedule A-9.
Refer C&A No. 6, Sl. No. 9
85) Vol 1, Part A
Sec VIII
89 Sub-Clause 22.9
(c )
Adverse Operating Conditions:
The Liquated Damages as specified in „Annexure – Service Level
Agreement, Volume 4 of Bid Document‟ then shall be applicable on
the agreed Alternative Output Standards.”
We understand that in such an event of adverse/lean conditions of raw sewage, the new
LD for alternative agreed standard in terms of output quality shall be mutually
discussed between the contractor & employer and agreed upon. Kindly Confirm
As per bid document
86) Vol 1, Part A
Sec VIII
89 Sub-Clause 22.9
(c )
Adverse Operating Conditions:
The Liquated Damages as specified in „Annexure – Service Level
Agreement, Volume 4 of Bid Document‟ then shall be applicable on
the agreed Alternative Output Standards.”
From sub-clause 4.9, Vol. I, Section VIII, O&M the power charges during O&M
periods have to paid by the employer as per guaranteed power defined in the bid.
However, we understand that in the event of adverse/lean conditions of raw sewage,
the impact on power consumptions and payment thereafter shall be mutually discussed
between the contractor & employer and agreed upon. Kindly confirm
As per bid document
87) Vol. I 95 - Retention Money We understand will be applicable per format provided & governed by performance
security.
As per bid document
88) Vol 1, Part A
Sec X
101 8
Section X
Contract duration 12 months defect liability period will start at the end of 36 months construction period
and 6 months trial run, confirm.
Also confirm total contract duration is 174 months = 36+6+12+120.
The project involves major rehabilitation & upgradation that will entail working
As per bid document
39
running plant repairs/works for which 36 months construction period may be
insufficient as has happened at Keshopur plant of DJB request suitable increase the
period.
89) Vol 1, Part A
Sec X
101 - Appendix to technical Proposal The clause descriptions/ conditions mentioned in Section X Appendix to technical
Proposal for the package shall amend and/or supplement the provisions in Section VII
– General Conditions of Contract and Section VIII – Particular Conditions of Contract.
Wherever there is a conflict, the provisions of Section X Appendix to Technical
Proposal shall prevail over those in the Section VII – General Conditions of Contract
and Section VIII – Particular Conditions of Contract. Kindly confirm.
As per bid document
90) Vol 1, Part A
Sec X
101 1.1.3.3 Section – X : Appendix to Technical Proposal As it is not a Greenfield Project, involves replacement/rehabilitation of the existing
plant in phases, demolition of old units, construction of new units, integration of old
and new units, and operation of the existing plant, all at the same time, the stipulated
36 months period for the construction is very short.
In addition, it is required to complete the Rehabilitation of the 50% of the liquid stream
within 18 to 20 months (ref. Vol-2, pg. 135). This is unrealistic as it is this Phase-1 of
the works which will require the longest duration.
A practical and realistic completion period is 30 months for 50% of the liquid stream,
and overall 46 months for the Construction Works. Kindly review and confirm.
As per bid document
91) Vol 1, Part A,
Section X
101 Appendix to
Technical
Proposal
Sub-Clause 1.1.3.3. Time for Completion of Works Section B
“O&M Contract” totals 1+10=11 years following successful
completion of the Trial Run and Commissioning Period.
Please kindly confirm O&M Period of 11 years. As per bid document
92) Vol 1, Part A,
Section X
102 Appendix to
Technical
Proposal
Sub-Clause 4.2. Amount of Performance for Section B equals 5% of
O&M Contract Price which corresponds to a cost of more than half a
year of O&M.
Please decrease percentage as this exposure is too high to initiate the O&M Works. As per bid document
93) Volume 1 Part
A, Section ‐ X:
102 Amount of
Performance
Security
5% of O&M Contract Price for the performance security is very high considering that
the Employer has other remedies under the contract like damages and termination
rights. Normally it would be expected the security to be 10% of the annual O&M
payment. Please kindly consider.
As per bid document
94) Vol-I Part-B 103 Service Tax Being a DJB, this Project would be exempted from service tax via GOI notification
number 25/2011-12.
Kindly Confirm.
As per latest GOI notification
95) Vol 1, Part A
Sec X
103 Appendix to
technical
proposal, Sr. No.
24
Delay Damages for
Works
Existing Contract Point – 2.0% of accepted Works Contract Price applicable to Section
A, for each month of delay to be computed on per day basis, in the same currency /
currencies in which the Works Contract Price is payable.
Query – Can 2% as mentioned in the Existing Contract Point be changed to 1%. Please
confirm.
As per bid document
96) Vol 1, Part A
Sec X
103 Clause 24, Pg.
103
Maximum amount of Delay Damages for Works: 2.0% of
accepted Works Contract Price applicable to Section A, for each
month of delay to be computed on per day basis
We feel that the delay damages @2% of accepted Works Contract Price is very high,
kindly reduce and restrict it to 1%.
Please accept and confirm.
As per bid document
97) Vol 1, Part B
Sec III-A
105 Qualification
Criteria
General Construction Experience- The Bidder should have successful
experience of Design, Construction, Testing & Commissioning of the
conventional activated sludge process with sludge digestion and
mechanical dewatering in: At least one WWTP 50 MLD (In JV)
We understand that the purpose of a JV is to help businesses combine resources with a
partner to accomplish business goals that neither company is capable of accomplishing
alone. So if one JV partner is not fulfilling the eligibility criteria it can complimented
by others, moreover it is observed that no such condition is observed in any other
projects funded by DJB, The ADB and The World Bank as this also reduce
competition by restricting potential JVs. Hence we request you to please consider and
amend this PQ as “Should be met by all partners” or change it with “Each partner at
least have one WTP of 50 MLD”.
As per bid document
98) Vol 1, Part B
Sec III-A
105 QC, Cl. No.4, General Construction Experience : Each Partner meet at least
WWTP of 50 MLD
Kindly accept Combined qualification in case of Joint Venture, Kindly waive off Each
Partner Experience Criteria.
Please accept and Confirm.
As per bid document
99) Vol 1, Part B
Sec III-A
106 Section III A
Clause 3.1
Financial Performance
Submission of Audited balance sheet.
We presume last 3 years are FY 2015-16, FY 2014-15 & FY 2013-14. Please confirm,
As per bid document
100) Vol 1, Part B 107 Eligibility and The S. No. 3.3 refers to Financial Resources but the explanation is given for Available As per bid document
40
Sec III-A Qualification
Criteria
Bidding Capacity. Please provide the details for Financial Resources. Also, the details
and format for Available Bidding Capacity.
101) Vol 1, Part B
Sec III-A
107 3. Financial
Situation
Financial Resources Please specify how the information provided in this form will be used in bid
evaluation.
As per bid document
102) Vol 1, Part B
Sec III-A
107 Section III A
Clause 3.3
Financial Resources
Kindly specify the value of bid capacity to be satisfied.
As per bid document
103) Vol 1, Part B
Sec III-A
108 4. Experience 4.1General construction Experience :-
The Bidder should have successful experience of Design,
Construction, Testing & Commissioning of the conventional
activated sludge process with sludge digestion and mechanical
dewatering in:
At least 1 (One) Wastewater Treatment Plant (WWTP) of 100 MLD
OR
At least 2 (Two) Waste Water Treatment plant (WWTP) of 70 MLD
each
OR
At least 3 (Three) Waste Water Treatment plant (WWTP) of 50 MLD
each
The above projects should have been commissioned in last 10 years
as on date of submission of Bids. The Bidder is required to submit the
authenticated end-user certificate for successful completion &
commissioning of the project as stipulated in the form 4.1t
Kindly accept construction experience of SBR type STPs in addition to Conventional
ASP; since the treatment processes of both type DJB are very much similar.
Moreover DJB constructed on SBR Technology has delivered treated effluent
parameter BOD < 10 mg/l, TSS < 10 mg/l which are better than conventional ASP
Process.
As per bid document
104) Vol 1, Part B
Sec III-A
108 4. Experience 4.2(a) The Bidder should have experience of Design,
Construction, Testing & Commissioning of at least one Waste Water
Tertiary Treatment plant (WWTTP) of minimum 50 MLD capacity
based on aerobic growth process with effluent standards as BOD ≤ 10
mg/l, TSS ≤ 10 mg/l. The above projects should have been
commissioned in last 10 years as on date of submission of Bid. The
Bidder is required to submit the authenticated end-user certificate for
successful completion& commissioning of the project as stipulated in
the form 4.2.
We have designed, constructed, tested & commissioned many DJB.s deriving outlet
parameter as BOD ≤ 5 mg/l, TSS≤ 10 mg/l at secondary stage. It is requested to
accept the secondary stage experience in lieu of tertiary Treatment Plant (TTP). Please
confirm.
Refer C&A No. 6, Sl. No. 11
105) Vol 1, Part B
Sec III-A
108 4.2 (a)
Section III A
WWTTP Tertiary Treatment Plant are usually build in water scarcity areas. In India tendency of
using the tertiary treated water is not much in existence due to abundance of fresh
water available in major states. Even if they are they are very less both in terms of
number as well as in capacity.
Thus requirement of 50 mld WWTTP would limit the completion to only 3 or 4
bidders. Request to relax the requirement and accept the experience of 20 mld in place
of 30 mld WWTTP.
Refer C&A No. 6, Sl. No. 11
106) Vol 1, Part B
Sec III-A
108 Sr. No. 4 Clause
4.2 (a)
Section III A
Please refer Section-IIIA Eligibility and Qualification Criteria,
Experience
We understand that Waste Water Tertiary Treatment Plant means any Aerobic Growth
Process based Waste Water Treatment Plant designed with effluent standards as BOD
< 10 mg/l, TSS < 10 mg/l. Please confirm.
Confirmed
107) Vol 1, Part B
Sec III-A
108 4.1
Eligibility & Qualification Criteria
General Construction Experience; Compliance Requirement.
The purpose of JV is to meet the financial & technical qualification jointly & severally.
Hence any one partner meeting the criteria of construction of DJB “one plant of 100
MLD or 2 plant of 70 MLD or 3 plant of 50 MLD” will serve the purpose of
qualification.
Hence kindly request you to remove the clause of each partner satisfying the
criteria of commissioning of at least 50 MLD capacity WWTP.
As per bid document
108) Vol 1, Part B
Sec III-A
108 Cl. 4.1 General Experience:
The Bidder should have successful experience of Design,
Construction, Testing & Commissioning of the conventional
activated sludge process with sludge digestion and mechanical
dewatering in:
At least 1 (One) Wastewater Treatment Plant (WWTP) of 100 MLD
OR
Since the proposed technology for the new plant is based on conventional activated
sludge process with primary clarifier and secondary clarifiers along with sludge
digesters, we understand that the aerobic suspended growth process referred in this
criteria are those plants which has both primary and secondary clarifiers and sludge
digesters. Please confirm.
As per bid document
41
At least 2 (Two) Waste Water Treatment plant (WWTP) of 70 MLD
each
OR
At least 3 (Three) Waste Water Treatment plant (WWTP) of 50 MLD
each
109) Vol 1, Part B
Sec III-A
108 Cl. 4.2 (a) The Bidder should have experience of Design, Construction, Testing
& Commissioning of at least one Waste Water Tertiary Treatment
plant (WWTTP) of minimum 50 MLD capacity based on aerobic
growth process with effluent standards as BOD ≤ 10 mg/l, TSS ≤ 10
mg/l.
We have completed a number of plants with suspended aerobic growth process, which
are not contractually designed for BOD < 10 mg/l and TSS < 10 mg/l, however these
plants are consistently producing treated effluent of quality BOD < 10 mg/l and TSS <
10 mg/l during operation. Please clarify whether such plants will be considered for
qualification.
No
110) Vol 1, Part B
Sec III-A
108 Eligibility and
Qualification
Criteria
As we know, that even slight modifications in Conventional ASP plant qualifies it
under Variation of ASP. Similarly, the proposed plant works scope is of Variation of
ASP which includes Biological Reactor for Nitrification/Denitrification. And in plants
of Variation of ASP, separate Sludge Digestion will not be there. Overseas, most of the
clients may not prefer separate sludge digestion if power generation is not a necessity.
Hence to allow more bidders to participate for a competitive bid, we request to modify
the clause:
“The Bidder should have successful experience of Design, Construction, Testing &
Commissioning of the conventional activated sludge process with sludge digestion and
mechanical dewatering in”
May be modified as:
“The Bidder should have successful experience of Design, Construction, Testing &
Commissioning of the Conventional Activated Sludge Process with Mechanical
Dewatering / Variation of ASP with mechanical Dewatering in”
As per bid document
111) Vol 1, Part B
Sec III-A
108
4. Experience Authenticated end user Certificates for successful completion &
commissioning of the projects.
Please confirm if Notary Attestation would be sufficient for the End-user certificates
issued outside India by Foreign Clients / End –users.
As per bid document
112) Vol 1, Part B
Sec III-A
Section III A
108 Clause 4.1 General construction experience:
Conventional Activated sludge process as described in CPHEEO manual chapter 5
clause 5.3.1.1 means – “Aeration followed by secondary clarifier with return activated
sludge”. Hence plants with Step Aeration, Extended Aeration, plug flow etc. also come
under CASP. Kindly confirm.
Since most of the European countries are with abundant power resources, sludge
digestion and power generation is introduced only as per requirement for most of the
plants. Also, as Power generation and rehabilitation work has been already asked
separately as experience criteria.
Therefore under this clause of specific experience in Design, Construction, testing &
commissioning of the conventional activated sludge process with mechanical
dewatering is to be provided.
As per bid document
113) Vol 1, Part B
Sec III-A
108 Section III A
Clause 4.1
General construction experience:
Tender specifies “The Bidder should have successful experience of Design,
Construction, Testing & Commissioning of the conventional activated sludge process
with sludge digestion and mechanical dewatering”
Request to also consider as “ The Bidder should have successful experience of Design,
Construction, Testing & Commissioning of the conventional and variation of activated
sludge process with mechanical dewatering”
As per bid document
114) Vol 1, Part B
Sec III-A
108 Clause 4.2 (a) Referring to the bids invited earlier for “Package –R-2 : Rehabilitation and Up-
gradation of Rithala – Phase I (182 MLD) Waste Water Treatment Plant (WWTP) with
effluent standards of BOD -10 mg/l , TSS – 10 mg/l or better under YAP (III)” invited
via ID No. PQ –YAP (III) {K3/R2/2012-13}, it was clarified that the experience of
Waste Water Treatment plant with secondary treatment facility for a minimum 50
MLD capacity based on aerobic growth process with effluent standards as BOD ≤ 10
mg/l, TSS ≤ 10 mg/l will be considered for qualification under referred clause.
Thus, we understand that the same experience shall be accepted for this tender under
clause 4.2 (a). Kindly confirm.
As per bid document
115) Vol 1, Part B 108 Clause 4.1 In view of competitive bidding and inviting maximum participation of bidders we As per bid document
42
Sec III-A request DJB to kindly remove the required experience of 50 MLD WWTP by each
partner and allow the referred “General Construction Experience” to be met
cumulatively by all partners combined. Kindly confirm
116) Vol 1, Part B
Sec III-A
108 Clause 4.2 (d) In view of competitive bidding and inviting maximum participation of bidders we
request DJB to kindly allow the experience of power generation from duel fuel / co
generation engines in addition to bio gas engines.
Kindly confirm.
As per bid document
117) Vol 1, Part B
Sec III-A
108 Clause 4.2 (a) Specific Construction Experience
The Bidder Should have Experience of Design, Construction, Testing
& Commissioning of at Least one waste water Tertiary Treatment
Plant of (WWTP) of minimum 50 MLD Capacity based on aerobic
growth process with effluent standards as BOD <= 10 mgl,
TSS<=10mgl.
The above project should have been commissioned in last 10 years as
on date of submission of bid. The bidder is required to submit the
authenticated end user Certificate for Successful Completion &
Commissioning of the Project
Due to lack of Priority for Sanitation, maximum STPS which were installed/
constructed in the past were based on Conventional Activated Sludge Process
Technology (CASP) upto Secondary Treatment. And requirement of quality of Treated
Sewage was also not very high so the plant installed earlier was up to secondary
treatment only.
Very few STPs installed in India have Tertiary treatment process, resulting very
limited companies having experience of installation of STPs with tertiary treatment
process. And majority of the Indian companies involved in waste water sector have
experience in Construction of STPs with Secondary Treatment only.
It is therefore suggested not to make mandatory for the companies to have experience
of Tertiary Treatment on aerobic growth process with effluent standards as BOD <= 10
mgl, TSS<=10mgl, for participating in the bidding process.
Else, it should be allowed that qualification may be complied by Specialist
Subcontractors.
Specialist Subcontractor is a specialist enterprise engaged for highly specialized
processes which cannot be provided by the main Contractor.
In this case Indian Companies can bring the expertise of Foreign Companies having
requisite experience, as Specialist Subcontractor. Because of Joint and Several
Liabilities, Foreign Companies are bit reluctant to participate as Joint Venture, so if
Specialist Subcontractor Experience is allowed, then the expertise of Foreign
Companies scan also be taken for successful execution of project.
Such condition has been accepted and allowed in many projects funded by ADB as
well Locally funded Projects.
Refer C&A No. 6, Sl. No. 11
118) Vol 1, Part B
Sec III-A
109 4. Experience 4.2(b) The Bidder should have experience of Rehabilitation or Up
gradation of clarifiers or aeration unit or digesters or gas holders for
at least one Wastewater Treatment Plant (WWTP) of 50 MLD or
above capacity. The above projects should have been commissioned
in last 10 years as on date of submission of Bid. The Bidder is
required to submit the authenticated end-user certificate for
successful completion & commissioning of the project as stipulated
in the form 4.2 b.
It is requested to accept experience of Rehabilitation or up gradation for 2Nos. of
WWTP each of 40 MLD capacity or one WWTP of 50 MLD Capacity. Please confirm
As per bid documents
119) Vol 1, Part B
Sec III-A
109 4.2(a) Eligibility & Qualification Criteria
General Construction Experience; Compliance Requirement
The norms for effluent discharge of BOD ≤10 mg/l, TSS ≤ 10 mg/l has recently been
introduced.
Hence we would request you to consider projects which has been partially
commissioned but meeting the effluent discharge limit of BOD≤10 mg/l, TSS ≤ 10
mg/l.
As per bid document
120) Vol 1, Part B
Sec III-A
109 4.2 (b)
Section III A
Rehabilitation & Up gradation Experience Bigger size projects having capacity more than 100 mld came into existence after 90‟s.
A regular STP usually have a design life of almost 30 years for Civil & 15 years for
electro Mechanical. Thus requirement of Rehabilitation and up gradation reduces to
minimum.
We request to delete the said requirement as it would limit the no. of bidders and
would lead to poor competition against prospective bidders.
As per bid document
121) Vol 1, Part B
Sec III-A
109 Clause 4.2 (b) Specific Construction Experience
The Bidder Should have Experience of Rehabilitation or Upgradation
of clarifiers or aeration Unit or digester or gas holder for at least one
waste Water Treatment Plant (WWTP) of 50 MLD or above
Capacity .
In India, majority of experience is for construction of New STPs only as till date only
new STPs were built. Now the tenders have called for Renovation/ Rehabilitation of
STPs which has been built earlier. So Experienced Companies will find it difficult to
meet such experience of Rehab/Renovation.
Further in the Tender, all the Civil Rehabilitation Works is Item Rate which can be
executed by any Civil Contractor as per the Item Specified and All other remaining
As per bid document
43
The above project should have been commissioned in last 10 years as
on date of submission of bid. The bidder is required to submit the
authenticated end user Certificate for Successful Completion &
Commissioning of the Project
activities like electro Mechanical works will be completely changed and installed new.
So therefore such qualification should not be made mandatory and can be deleted.
Such changes in Qualification will increase the competition and majority of Indian
Companies having expertise in STPs can also participate.
Else following can also be considered:
1. Rehabilitation of Water Treatment Plants should be also be allowed or
2. Can be complied by Specialist Sub Contractor as defined in the previous point.
122) Volume 1 Part
‐ B Section -
III A
109 Qualification
Criteria Clause
4.2 (b)
The experience of construction is as good as rehabilitation, and in fact sometimes it is
difficult to find boundaries between the definitions. Please allow for Construction in
addition to Rehabilitation/Up-gradation experience.
As per bid document
123) Vol 1, Part B
Sec III-A
110 4. Experience 4.2( d) The Bidder should have experience of Design, Construction,
Erection and successful Commissioning of at least one Waste Water
Treatment plant (WWTP) based on conventional activated sludge
process with minimum 0.5 MW/0.65MVA power generation from
biogas produced at the plant using only biogas engines. The above
projects should have been commissioned in last 10 years as on date of
submission of Bid. The Bidder is required to submit the authenticated
end-user certificate for successful completion & commissioning of
the project as stipulated in the form 4.2 d.
It requested to accept experience of design, constricting, erection, and successful
commissioning of at least two WWTP based any technology with minimum 125 KVA
capacity power generation from biogas produced at the plant using biogas engines.
Please accept.
As per bid documents
124) Vol 1, Part B
Sec III-A
110 4. Experience 4.2 (e) The Bidder should have done Operation & Maintenance for at
least 1 year in the last 10 years of one Waste Water Treatment plant
(WWTP) of minimum 50 MLD capacity based.
On conventional activated sludge process which they have designed,
constructed, tested and commissioned. The above projects should
have been commissioned in last 10 years as on date of submission of
Bid. The Bidder is required to submit the authenticated end-user
certificate for successful completion, commissioning and operation &
maintenance of the project as stipulated in the form 4.2 e.
It is requested to accept the O & M experience for at least 1 year in the last 10 years of
one WWTP of min. 50 MLD capacity based on SBR process or 2 years O & M
experience of two WWTP of min. 40 MLD capacity based on ASP/SBR process.
Please accept.
As per bid document
125) Vol 1, Part B
Sec III-A
110 Sr. No. 4 Clause
4.2 (d)
Section III A
Please refer Section-IIIA Eligibility and Qualification Criteria,
Experience,
We request you to consider experience of power generation from bio gas produced at
the plant using only bio gas engine either from Conventional Activated Sludge Process
or from any other biological process having Anaerobic Digester as bio gas producing
unit OR UASB based Waste Water Treatment Plant OR STP. Please confirm that
power generation system with any of the above three options are acceptable.
As per bid document
126) Vol 1, Part B
Sec III-A
110
4.1, 4,2(d). (e) Eligibility & Qualification Criteria
General Construction Experience; Compliance Requirement
The requirement is a refurbishment work of a conventional ASP process to produce a
higher quality effluent.
Hence we request you to consider Conventional/ Modified ASP process for pre
qualification.
As per bid document
127) Vol 1, Part B
Sec III-A
111 Notes (v) For Foreign Bidders/companies, the experience shall only be
considered if the experience exhibited is from outside its home
country
We are unable to understand the rationale behind incorporation of this clause. The
purpose of including an international / foreign company is to bring more expertise
thereby benefiting the project.
Also, for international competitive bidding incorporating such a clause is a virtual
barrier for international companies. Moreover, the rules of JICA clearly states that
companies from all member countries are to be treated as equal and are eligible for
participation however, such clauses are clearly biased and against the basic principles
of international competitive bidding.
We therefore request you to kindly remove this criteria. Please accept and Confirm.
As per bid document
128) Vol 1, Part B
Sec III-A
111
Notes (iii) The experience of the bidder in a project shall be considered as
experience unless the project was constructed under a 50:50 JV,
where in both partners will qualify for full experience
As per our understanding of the clause, if a company has less than 50% share in a
completed project, it will not be considered for evaluation.
We sincerely believe that such criteria are unjustified and uncalled for.
Bidders should be allowed to claim experience of projects completed by them up to
their share in those projects, irrespective of any minimum percentage.
Please accept and Confirm.
Refer C&A No. 6, Sl. No. 12
129) Vol 1, Part B
Sec III-A
111 Eligibility & Qualification criteria
Note-v.
For equality treatment of both type of bidders i.e Foreign and National bidders, we
request that this clause be applicable to them equally.
As per bid document
44
130) Vol 1, Part B
Sec III-A
111 Notes: Experience
of foreign bidders
/ companies
Please note that firms bidding globally at first obtain expertise of executing similar
jobs in their domestic environment/ home country. Thus in view of inviting quality
competition with increased no of qualified participants we request the Delhi Jal Board
(DJB) to kindly allow the foreign bidders/ companies with experience in their home
country as well.
Kindly confirm.
As per bid document
131) Vol 1, Part B
Sec III-A
111 Note V
For Foreign Bidders/companies, the experience shall only be
considered if the experience exhibited is from outside its home
country
The experience is related to the scope and quality of work done and the place of project
execution has no relevance. The international experience of the bidder can be verified
in a different way, so that it is not limited to direct experience of technology,
construction and O & M.
The present tender condition is restrictive in nature and favors limited overseas
companies having office in India. Most of the bids submitted by these companies are in
JV with their parent company as they neither have similar working experience in India
nor their parent company has experience in their own country.
Hence we request you to accept experience of foreign company in their home country
and give an equal level to all bidders.
As per bid document
132) Volume ‐ 1 :
Part ‐ B
Section - III A:
111 Qualification
Criteria
Notes under
Clause 4.0
Notes under Experience
The experience of the bidder in a project shall be considered as
experience unless the project was constructed under a 50:50 JV,
where in both partners will qualify for full experience
Request to please clarify the clause as it seems company having 49% experience will
qualify but with 50% share will not qualify.
The experience of the bidder will be considered of lead member only in case of project
executed in JV. Kindly clarify.
Refer C&A No. 6, Sl. No. 12
133) Volume 1 Part
B Section III
A:
111 Footnotes to Qualification Criteria
Point iii: It is understood that bidders can use their experience as long as they have
50% of more in a JV. Please kindly clarify.
Refer C&A No. 6, Sl. No. 12
134) Volume 1 Part
B Section III
A:
111 Footnotes to Qualification Criteria
Point v: This implies that Indian companies are allowed to use their home country
experience, but foreign companies are not. This is discriminatory to foreign companies,
and it is also unreasonable since home country experience also enriches the knowhow
of a company. Please remove.
As per bid document
135) Vol 1, Part B
Sec III-B
116 Forms Litigation History Kindly specify the number the past years a bidder is required to mention its litigation
history where the Court / Arbitral award are against the Bidder.
As per bid document
136) Vol 1, Part B
Sec III-B
116 Forms Litigation History Please clarify the selection / rejection criteria for this clause, since the same is not
mentioned in the Bidding Document.
As per bid document
137) Vol 1, Part B
Sec III-B
118 Section III B
Form FIN 3.1
Financial Documents
Kindly allow that wholly owned subsidiaries of foreign firms/ Companies having
registered office in India can quote using parent company‟s Technical & Financial
capabilities and commitments.
As per bid document
138) Vol 1, Part B
Sec III-B
120 Form FIN-3.3 Financial Resources Kindly specify the minimum amount of Financial Resources necessary to be
demonstrated by the Bidder for the Employer to accept his Financial position suitable
for the project.
As per bid document
139) Vol 1, Part B
Sec III-B
121 Part B, Form FIN
3.4 Financial
Performance
Since it has been specified in the Qualification Criteria that all financial documents
need to be certified by Chartered Accountant, then signature of Company Secretary in
Form FIN 3.4 may also be altered to Chartered Accountant.
As per bid document
140) Vol. I Part - B 154 - Pre-Qualification Bid document has asked for Conventional Sludge Process with Sludge Digester.
With of latest technologies quantity of sludge generated has decrease thus making the
sludge Digester unviable for big size project.
Thus request to amend the requirement of same.
As per bid document
141) Vol. I Part - B 155 - Pre-Qualification The no. of biggest size STPs came into existence about 10-15 yrs. The process of
Rehabilitation of bigger Plant has taken place recently. Therefore, it is not possible for
prospective bidders to have experience in rehabilitation for such capacity.
Bid Requirement of 50 MLD Rehabilitated Project would resist the no. of prospective
bidders to participate. Request to amend the said clause to 20 MLD.
As per bid document
142) Vol. I Part - B 156 Pre-Qualification Power generation is only feasible with projects sizes of more than 50 MLD and so.
Since number of such plant are few in number, thus parties having such experience
would also be few.
In order to encourage maximum participation for healthy competition request to amend
As per bid document
45
the requirement and allow sub-contractor experience for Qualification in Power
generation.
143) Volume-1 General Qualification Criteria
Parent/Subsidiary Exp.
We request the department to kindly accept that “Any parent foreign firm having
Indian subsidiary or parent Indian firm having foreign subsidiary showing technical
experience will be considered provided such experience meet the qualifying criteria”.
Kindly confirm our understanding.
As per bid document
144) Volume-1 General Mobilization Advance Please confirm 10% interest free mobilization advance payment against bank guarantee
of equivalent value.
As per bid document
145) Volume-1 General Degree of variation In case inlet parameters vary significantly high leading to non-compliance of
guaranteed parameters then no penalty or any type of recovery should be done from
Contractors during O&M period.
As per bid document
146) Volume-1
General Extend the bid submission period We request you to extend the bid submission period at least FOUR WEEKS from
scheduled bid submission of 27.07.2016 as we have to study the existing plant for its
modification work
Refer C&A No. 5
147) Volume 1
General Since good cash flow is very crucial for the smooth progress of the job, we request you
to change the percentage of retention to 5%
As per bid document
148) Volume 1
General We request for the provision of release of Delay Damages imposed if the next
milestone is achieved as per the project Schedule.
As per bid document
149) Volume-1 General Mode of Payment The tender silent on the mode of payment. We request to accept that all payments shall
be covered through a confirmed, unconditional, irrevocable Letter of Credit (LC)
payable at sight issued in a form acceptable to all nationalized & scheduled banks.
LC of 100% to be opened within 3 months of the signing of the contract.
The Letter of Credit shall be valid up to 3 months from the date of project completion.
All the cost of LC shall be to Employer‟s account. The LC shall allow for partial
shipments and transhipments.
As per bid document
150) Volume-1 General 2nd
Pre-bid Meeting Keeping the technicality and importance of the project, we request you to please
organize 2nd
pre-bid meeting after publishing 1st Pre-bid Meeting clarifications report
and Site Visit of the bidder, this will enable bidder to focus on those queries/
observations which will rise out of site visit and during the tender document study and
calculations.
Please accept and Confirm.
As per bid document
151) Volume-1 General Funding Status & Pattern Kindly confirm us the detailed funding status & pattern for the subject project. It is JICA assisted project.
152) Volume-1 General Joint venture As per our understanding the Number of members in a JV is not limited.
Kindly confirm.
As per bid document
153) Volume-1 General Variation in Taxes Our understanding that there would be provision in contract for any changes in taxation
law in future. Kindly Confirm.
As per bid document
154) Volume-1 General Payment of Contractor‟s Bills Payment against RA bills shall be realized within 28 days of the submission of bills
with all supporting documents. Kindly confirm.
As per bid document
155) Vol-2 131 1.2 Project background – incoming pipe lines upto WWTP. The pipe lines from pumping station 1 – 6 transporting the raw sewage to WWTP.
Additionally 2 nos. rising mains are provided to WWTP, kindly elaborate.
Further these rising mains are let into WWTP common inlet chamber provided by DJB
therefore confirm scope of work starts from common inlet chamber.
Please reconfirm the pumped flow is passed through existing coarse screen to common
chamber, hence coarse screening is not in contactor‟s scope.
Refer C&A No. 6, Sl. No. 22
156) Vol-2,
Section XI,
Part 1
131 1.2 Project Background Kindly provide invert levels of all the incoming sewer pipes mentioned under this
clause as well as in cl 1.7 (ii), pg. 136.
Bidders to verify from site
157) Vol. 2 132 1.4 item 3 Incoming 11KV cable from existing 11KV Metering panel to 11KV
switchboard of Phase-1
Location of TPDDL existing S/S from where 11KV power will be made available for
new WWTP or
11kv cable length from Purchaser 11Kv Metering panel to each in11KV HT Panel
comer of 11KV switchboard of new WWTP.
Bidders to verify from site
158) Volume -2 /
Section:X1,
Part 1
132 1.4 The existing HT electric power, 3 phase 11 KV AC is available at the
existing TPDDL (Tata Power Delhi Distribution Limited) substation.
Kindly indicate the location of existing TPDDL substation in proposed layout. Bidder to verify from site
46
159) Vol. 2 –
Section XI
132 Part 1 / Clause 1.5 The Rehabilitation & Up-gradation of Rithala WWTP for Phase-I,
(182 MLD) is one of the packages under Yamuna Action Plan Project
(III). It will be essentially a Design, Build & Operate (DBO) contract
but for civil units which require rehabilitation; rates shall be quoted
on Item Rate basis in Volume-3. The nomenclature of this package is
as below:
We presume that, the rehabilitation works will be measured as per actual and payment
will be paid accordingly. Please confirm.
As per bid document
160) Vol 2 – Sec X1
Part 1
132 1.5 For this purpose, National Mission for Clean Ganga(NMCG),
Ministry of Water Resources (MOWR), Government of India (GOI),
the borrower, has received Loan from Japan Bank for International
Cooperation Agency (JICA), amounting to JPY 32,571 Million
towards the cost of Yamuna Action Project Plan project (III) YAP
111, for which the loan agreement was signed on 17th February,
2011
Request the employer to specify/notify benefit/exemptions available to this project
based on the Funding from JICA and being considered in the bid price
As per bid document
161) Volume 2 132 Section XI
Part1
Scope of Work
Clause 1.3
As per the mentioned clause, Phase I WWTP (40 MGD) constructed during the year
1989-1990 and some of the major units such as Primary Clarifier, secondary clarifier
and gas holder civil structures has to retained and rehabilitated.
Please clarify whether any structural assessment has to be carried out by the contractor
for the major units before replacement of all electro mechanical equipment.
As per bid document
162) Vol.- 2 133
& 184
1.6 & 2.16 Sewage Temperature A discrepancy is observed WRT min & max sewage temperature i.e.17.8/290C against
18/ 270C respectively.
Please clarify.
Refer C&A No. 6, Sl. No. 25
163) Vol. 2, Section
XI, Part-1
133 Clause 1.6 Incoming Waste water quality & design parameter
Tender Clause states- design BOD3 value given is 225mg/l
We assume that all the BOD terms shall be read as BOD3 at 270C & BOD5 at 20
0C.
Please confirm.
Confirmed
164) Vol-2,
Section XI,
Part 1
133 1.6 Incoming Waste Water Quality and Design Parameter The ratio of design value of Ammonical Nitrogen and TKN is 84%. This is very high
compared to the typical range of 70 – 75%. As the objective of the treatment is to meet
the effluent quality requirement of TN <10 mg/l, this high ratio will result into a
conservative design of the plant. Kindly review and reconfirm the design value of TKN
and Ammonical Nitrogen to consider.
As per bid document
165) Volume –II,
Sec-XI ,Part -2
133 1.6 Effluent Quality Requirement :
COD < 50 mg/l
Please note that there is no specific treatment in the plant for COD reduction. While in
a pure municipal sewage it is likely that the COD in the treated effluent may be less
than 50 mg/l, any trade effluent contamination in the municipal sewage would easily
breach the COD limit in the treated effluent. Hence, we request that the COD should be
excluded from the contractual list of treated effluent guarantee. Kindly review and
confirm.
As per bid document
166) Volume – 2,
Section: XI,
Part 1,
133 Cl. 1.6 Raw sewage parameters Please provide the following parameters of raw sewage for plant design and guarantee
Purpose.
a) Heavy metals (with breakup of each element).
As per bid document
167) Volume-2
Section:X1,
Part 1
Electrical
Specification
134 1.7 Interim Operation of the existing & partly rehabilitated WWTP
during construction & rehabilitation period :
The work of Rehabilitation & Up gradation shall be executed in
phased manner so that the existing facilities can be partially used to
treat the incoming flow.
It is very difficult to execute Rehabilitation & Up gradation in phased manner for
electrical equipment as there may be common electrical equipment which will be
supplying both the sections. Kindly clarify or give the specification about how to
proceed the Rehabilitation & Up gradation of electrical system in phased manner.
As per bid document
168) General, Vol-2
Part-1
134 1.7 – 1) - During interim O&M period for we assume that the equipments from other phase can
be utilised in phase which is under operation to run the plant during interim period. Pls
confirm
As per bid document.
169) General
Volume-2
Part-1
134 1.7 – 1) During Interim operation period, it shall be the responsibility of the
Contractor to maintain all the existing electrical & Mechanical
equipment and instruments in proper working conditions and no extra
payments shall be made for this purpose. If required, with permission
of DJB, Contractor can use the existing equipments, which are
dismantled for the purpose of temporary repair of similar equipments
in another stream under operation, during interim Operation Period
We understand that the DJB shall handover the plant in good working conditions. If
anything in electro-mechanical equipment are not functioning properly same has to be
make it good by DJB before taking over by contractor. Kindly confirm.
As per bid document.
170) Volume 2
Section XI,
134 Clause 1.7-1),
Brief Scope of
We presume that, sludge which are to be collected from existing digester, sludge
drying bed and from any other existing units shall be disposed within the Rithala plant
Confirmed
47
Part 1 Work as discussed in the pre bid meeting.
Please confirm.
171) Volume 2
Sec XI, Part 1
134 Clause 1.7-1), Brief Scope of Work Please provide the quantity of Sludge Generated and Sludge disposal distance during
Interim O&M?
Bidders to verify from site
172) Volume 2
Section XI,
Part 1
134 General
Clause 1.7-1),
Brief Scope of
Work
We presume that the power during the following periods in Interim Operation will be
under the scope of Employer:
1. During first 18 months when 50% is under rehabilitation – For the balance
50% which is under Interim Operation by the Contractor
2. Second Phase of 18 months – When the Rehabilitated 50% comes under the
Interim Operation by the Contractor.
Please confirm.
As per bid document
173) Volume-2
Section:X1,
Part 1
General
Requirements
& Scope of
Work
135 1.7 The Contractor shall continue to operate the first section of the plant
in such a manner that it would be treating the available flow of
wastewater but at the same time also take up the work of
rehabilitation and upgrading the liquid and sludge stream of the
second section of the plant. Once the work for rehabilitation & up-
gradation of second section is completed, the Contractor will take-up
immediately work for rehabilitation & up-gradation of first section
and start operation of second section. This phase of operation (partial
or full) of WWTP until completion of rehabilitation, up-
gradation and new construction of
full plant is termed as “Interim Operation”.
Interim Operation is difficult in electrical equipment in view of the following points.
1. Both first and second section of the plant loads are connected through a common
MCC panel located at respective area of the plant.
2. Cables which are separate for each equipment but laid in same trenches make very
difficult to lay cable above or near the live cables and also excavating and winding the
cables in phased manner.
3. HT Panel & Transformers are common for both the sections
4. Aerator MCC panel for the existing is 2 numbers but the proposed is one number
(not possible for sectioning / phased manner)
Hence we request you to consider the above and kindly provide a solution /
methodology for interim operation of the electrical system.
As per bid document
174) Volume 2 135 Section XI, Part
1, Clause 1.7,
Brief Scope of
Work
As per the clause, Interim operation needs to be done during Rehabilitation and
Upgradation which is of 36 months duration. During this period, only half of the
system will be available for the contractor to operate as balance half will be under
rehabilitation. We presume that the outlet parameters mentioned is not applicable for
this phase as it is very difficult to achieve the same for the available flow of 100% with
a system of 50%. Please confirm.
As per bid document
175) Volume 2 135 Section XI
Part1
Scope of Work
Clause 1.7
We assume that during takeover of plant by contractor all the existing equipment will
be in good working conditions since interim operation has to be carried out and the
same shall be assured by the owner. Please confirm.
We assume that, if any critical equipment not in operation, such as primary sludge
pumps, Aerators, Secondary Sludge pump, etc the same has to be replaced by the
owner before handing over the plant. Please clarify.
As per bid document
176) Volume 2 135 Section XI, Part1,
Scope of Work,
Clause 1.7
We understood from tender that, for the present flow of 20 to 25 MGD and with
existing system (4 Primary Clarifier, 8 Nos – Aeration Tank and 4 Nos. Secondary
clarifier) the treated effluent quality was BOD < 20 mg/l and TSS < 30 mg/l.
During intermittent operation i.e with 50% working stream, the treated effluent quality
will be difficult to guarantee BOD < 20 mg/l and TSS < 30 mg/l. Therefore please
relax the guarantee during intermittent operation.
As per bid document
177) Volume 2 135 Section XI, Part1,
Scope of Work,
Clause 1.7
Please provide the quantity of sludge currently being generated and disposed. We
assume that during intermittent operation the sludge generated can be directly disposed
to sludge drying beds. This may cause odor / nuisance. Please confirm.
Bidders to verify from site
178) Vol. - 2,
Section XI
Part 1
135 1.7 (1) Brief Scope of Work Kindly confirm that design effluent quality parameters of the existing Rithala Phase-1
plant. As it will be necessary for the purpose of Interim Operation of existing and
partially rehabilitated waste water treatment plant during construction and rehabilitated
period.
As per bid document
179) Vol-2,
Section XI,
Part 1
135 1.7 (1) Brief Scope of Work While the existing Aeration Tank is shallow and has surface aerators, the new
Bioreactor will be deeper and will be provided with Fine Bubble Aeration Diffused
System. In addition, the required volume and plan area of the new Bioreactor will be
over 3 to 4 times of the existing Aeration Tank. With the limited space between PST
and SST, it will be practically impossible to carry-out the construction of new
Bioreactor in parts while retaining and operating a part of the existing Aeration Tank.
Hence, we suggest that the operation of the existing plant during the Interim Operation
should be limited to upto Primary Clarification only. Kindly review and confirm.
As per bid document
48
180) Section XI -
Part - 1 :
General
Requirements
136 1.7 Brief Scope of
Work:
vii) Replacement of all E&M equipment including all pumps, motors,
piping, valves & sluice gate etc. and all connected accessories in all
the process and pumping units being rehabilitated
Kindly clarify if replacement of all E&M equipment includes replacement of existing
instrument and control system. If yes, please give details of existing control system -
make, quantity (no. of panels) to be replaced
Bidder to verify from site
181) Volume 2 136 Section XI, Part
1, Clause 1.7, 2,
Brief Scope of Work Please provide the distance between the newly constructed common inlet chamber and
Phase II inlet chamber, which has to be connected under this contract.
Bidders to verify from site
182) Volume 2 136 Section XI, Part
1, Clause 1.7, 2,
Brief Scope of Work Please provide distances between existing pipelines referred under clause 1.2 to newly
constructed inlet chamber for phase 1 and 2.
Bidders to verify from site
183) Volume 2 136 Section XI
Part1
Scope of Work
Clause 1.7 (Point
2. Vii)
Please provide the as built drawing of piping for the following:
– From distribution chamber u/s of Primary Clarifier to individual
clarifier
– From Primary Clarifiers to the sump of Raw Sludge pump house
– From distribution chamber u/s of Final Clarifier to individual clarifier
– From Final Clarifiers to the sump of Return Activated Sludge pump
house
With pipe diameter, MOC and invert levels of the pipe for rehabilitation.
It is mentioned that above pipes only have to be desilted and replacement is not
required. Please confirm.
Bidders to verify from site
As per bid document 184) Vol -2,
Sec-XI, Part -1
136 1.7
Point -2 (xi)
Rehabilitation of Existing Gas Holders Kindly confirm the active storage volume in the existing gas holders which are to be
rehabilitated.
Bidders to verify from site
185) Vol-2
Sec XI-Part 1
136 1.7
Point -2 (vii)
Brief Scope Of Work The following existing piping arrangement are specified to be de-silted:
a) From distribution chamber u/s of Primary Clarifier to individual clarifier;
b) From Primary Clarifiers to the sump of Raw Sludge pump house;
c) From distribution chamber u/s of Final Clarifier to individual clarifier;
d) From Final Clarifiers to the sump of Return Activated Sludge pump house.
As these Pipe are old and buried, either confirm that these pipes are still in good
condition, non-leaking and has residual life to last for the expected life of the
Rehabilitated / Upgraded Plant, or confirm that in case the pipes needs
replacement/rectification, the cost shall be paid by the Employer as per the
requirement.
As per bid document
186) Vol. 2 137 Trial & Run period In general, tenders have trial & run period normally 3 months, which is enough to
judge the performance of plant.
Thus request to amend the requirement of same
As per bid document
187) Volume 2 138 Section XI, Part
1, Clause 1.7, 4,
Brief Scope of
Work
Operation of Plant during DLP of One year: - As per this clause, all the routine
operating cost for manpower, and consumables (like chemicals, laboratory glassware,
oil/lubricants, fuel & electricity etc.), transportation, disposal of treated effluent,
cartage and stacking of sludge within plant are in contractor scope. We presume that,
electricity for operating the plant shall be provided by client. Please confirm.
Refer C&A No. 6, Sl. No. 14
188) Volume 2 138 Section XI, Part
1, Clause 1.7, 5,
Brief Scope of
Work
Operation of Plant during O&M period: - As per this clause, all the routine operating
cost for manpower, and consumables (like chemicals, laboratory glassware,
oil/lubricants, fuel & electricity etc.), transportation, disposal of treated effluent,
cartage and stacking of sludge within plant are in contractor scope. We presume that,
electricity for operating the plant shall be provided by client. Please confirm.
Refer C&A No. 6, Sl. No. 15
189) Volume 2
Section XI,
Part 1
139 The contractor shall, at no extra cost to the DJB, refurbish / repair &
recondition all E&M&I equipment in the concluding year of the
O&M contract to a condition, so that they remain in running
condition with regular preventive and recommended maintenance,
including supply of all necessary spares that may be required to
operate these equipments for another 4 years.
Kindly confirm the handover spares at the end of O&M period is for 2 years or 4 years. Refer C&A No. 6, Sl. No. 15
190) Vol 2 –
Section XI
139 Part 1 / Clause 1.7
Item no 6.
6) Demolition of Structures of Existing WWTP …………
The material obtained after demolition of sludge drying beds and
other structures shall be stacked at site in heaps / stacks as directed by
engineer. The serviceable material shall be issued to the contractor
We presume that, all the debris from the demolition structures shall be disposed within
the Rithala plant.
Please confirm.
Or
As per bid document
49
................... Please indicate the location with lead distance if disposed at any other DJB's land.
191) Vol 2 –
Section XI
139 Part 2 / Clause 2.3 2.3 Demolition of Interfaces and Tie-Ins with Existing Facilities
List of Existing Units / Structure to be Demolished
During our site visit, we have observed a existing control building at the existing
digester area and we presume that, this building also shall be demolished by bidder.
Please confirm.
Refer C&A No. 6, Sl. No. 17
192) Volume 2 139 Section XI, Part
1, Clause 1.7, 6,
Brief Scope of
Work
Demolition of structures of existing WWTP: Please confirm the disposal distance of
the excess malba / debris / unserviceable material obtained during demolition. We
presume that, to dispose the material, site will be provided by client. Please confirm.
As per bid document
193) Volume 2 139 Section: XI, Part
1, 5. O&M of the
plant for a period
of 10 years.
In the referred clause of page 139, it is mentioned that the contractor is to ensure the
guarantee for the “Automation system”. Hence we request client to please clarify the
referred clause regarding the Guarantee of Automation system.
Refer C&A No. 6, Sl. No. 16
194) Volume 2 139 Section XI
Part 1, Scope of
Work, Clause 1.7
– Point No 5
Please provide the level of guarantee for automation system and how it can be
measured for evaluation.
Refer C&A No. 6, Sl. No. 16
195) General
Volume 2
Section XI,
Part 1
139 Clause 6) Surplus Material Kindly confirm us the distance between the site and the place where surplus material is
to be disposed.
Pls confirm whether the disposal site will be made available to the contractor or not.
Bidders to verify from site
196) Vol. 2,
Section XI,
Part-1
151 Clause 1.14 Topographical survey data
Tender Clause states-
The ground level varies from 215.5m to 214.25m i.e. from existing
inlet chamber to filtration beds respectively. FGL of the site should
be maintained as 100mm below the RL of center line of existing
approach road.
Please provide us RL of center line of existing approach road for FGL determination.
However we suggest that, the finished ground level shall be maintained as the Natural
ground level and micro grading will be done all-around the structure.
Please confirm.
Bidder to verify from site
As per bid document
197) Vol- 2,
Section XI,
Part 1
151 1.14 FGL of Existing Road Kindly provide the RL of the existing approach Road so that the tender requirement
that the FGL of the site should be 100 mm below the RL of center line of existing
approach road can be properly complied with.
As per bid document
198) Vol-2, Section
XI, Part 1
152 Clause 1.15 Soil Investigation Report Please mention the FGL of plant to enable us to estimate. As per bid document
199) Vol-2, Section
XI, Part 1
152 Clause 1.15 Soil Investigation Report Soil Investigation report. Please furnish the soil investigation report for ascertain the
Net SBC at different locations
As per bid document
200) Vol. 2 155 Labour placement We understand land for Labour hutment and other activities pertain for execution
would be provided free of cost from DJB with power & water connection.
As per bid document
201) Vol-2, Section
XI, Part 1
155
to
157
Clause 1.23.2.1,
1.23.2.7 & 1.23.3
Space Space for Site office, stores & labor may be provided to the contractor by Client at free
of cost.
As per bid document
202) Volume 2
Section XI,
Part 1,
156 Clause 1.23.2.2 Water Supply during Construction We request you to please provide free of cost Water during Construction period apart
from Operation and Maintenance Period.
Kindly accept and confirm.
As per bid document
203) Volume 2
Section-XI,
Part 1
156 Clause 1.23.2.4 Electricity for Contractor's Use on Site We request you to please provide free of cost Electricity during Construction period
apart from Operation and Maintenance Period.
Kindly accept and confirm.
As per bid document
204) Volume-2
Part-1
157 General Site office / Contractors office provided during execution of contract We request site office / contractor‟s office provided during construction will used
during O & M period without demolishing the same
As per bid document
205) Vol. 2 158 1.24 1.24 Vehicle ;- The Contractor shall provide two numbers of new air
conditioned seven seater road vehicles as approved by the Engineer
for the duration of the Construction Period.
Please specify upper ceiling limit for daily/monthly/ yearly usage of vehicle to be
provided.
3000 Km per month approx.
206) Vol. 2 159 Disposal point Provide the distance from site for damping of Excavated earth. Bidders to verify from site. 207) Volume 2:
Section XI,
Part 1
159 General
Requirements &
Scope of Work
1.28 Inspection of equipments. In case of inspections outside India
and in case there are travelling charges, boarding & lodging charges
etc. of DJB staff/PMC, shall these be borne by DJB or Contractor?
Please kindly confirm. As per bid document
50
208) Volume 2:
Section XI,
Part 1
159 Part 2 – Plant &
Process
Requirements
2.16 Bio Reactor. The minimum sewage temperature used for design
shall be 18°C (page 184) or 15°C (page 187).
Please kindly resolve discrepancy. Refer C&A No. 6, Sl. No. 28
209) Vol. -2 160 1.29 Statutory Approval The Contractor is required to obtain all statutory approvals for /and on behalf of DJB
under the following categories:
i.) Factory Act, ii.) Electricity Act, iii.) Environment Act, iv.) Municipal Act, v.)
Explosives Act, vi.) Any other act
Our understanding plant is in existence and operation with all statutory approvals
already in place with DJB, statutory approvals would be duplicated incurring
unnecessary cost.
As per bid document
210) Vol . 2
Sec X1 Part 1
160 1.29 Statutory Approval : The contractor shall obtain all statutory approval
for/and on behalf of DJB under the following
(1) Factories Act
We request the employer to confirm whether the existing plant being cover the
Factories Act in the State of Delhi. If so, please furnish the registration number issued
under the said Act.
As per rules
211) Vol-2, Section
XI, Part 1
160 Clause 1.29 Clearances We understand that all kind of legal / statutory / Govt. clearances, Land/crop
compensation for the project is in employer scope. Pls confirm.
As per bid document
212) Vol-2, Section
XI, Part 1
160 Clause 1.29 Clearances We request you to kindly forward the requisition to concerned government department
for clearances, required for project work, other Liaoning work will be done by
contractor. Pl. Confirm
As per bid document
213) Vol-2, Section
XI, Part 1
160
Clause 1.29
Approvals & Permissions All PCB approvals & permissions will be in employer‟s scope. All required
permissions & Approval towards respective authority, Institutions shall be in client‟s
(Employer‟s) scope. Please confirm.
As per bid document
214) Vol-2, Section
XI, Part 1
166
&
167
1.36 List of Items for issue Form C Our understanding is that Employer shall issue Form C - for the bought out
materials/equipments supplied by the Contractor on "Sale in Transit" bass U/S (2) of
CST Act. Pl confirm our understanding is in order.
As per CST rules.
215) Vol-2, Section
XI, Part 1
166 Clause 1.36, Brief
Scope of Work
List of Items for issue of form „C‟:- Travelling Bridge Filters / Cloth Media Filter /
Membrane Filtration System / DAF Thickener / Micro Power Turbine / Bio Chemical
Scrubber are not included in the items which is required as per tender document to
supply for the project. Request you to please provide C form for this item. Please
confirm.
As per bid document
216) Vol-2, Section
XI, Part 2
168 Plant & Process,
Clause 2.2.1
Please provide the inlet fecal coliform to be considered for design. Bidders to verify from site
217) Vol-2, Section
XI, Part 2
168 2.2 Waste Water and Sludge Quality Peak Flow value is specified as 80 MGD. However, we understand that it implies that
the Diurnal Hourly Peak Flow of 15,167 m3/hr, and the Total cumulative flow to the
plant shall be limited to the average design flow of 40 MGD only. Please confirm.
As per bid document
218) Vol-2, Section
XI, Part 2
168 2.2 Waste Water and Sludge Quality – Duration of Peak Flow Kindly confirm the typical duration of the Diurnal Peak Flow during the day to the
plant, or provide the Raw Sewage Flow Profile over 24 hours as this information is
very critical for the design of the sensitive Biological Process and Functional
Guarantees.
As per bid document
219) Vol-2, Section
XI, Part 2
169 Plant & Process,
Clause 2.2.2
We presume that treated effluent quality requirement and guarantee specified in 2.2.2
clause is after chlorine contact tank. Please confirm.
Confirmed
220) Vol-2, Section
XI, Part 2
169 Sludge Quality Standards
Sludge Quality Requirements (Dewatered Sludge)
As per Page no. 169 of tender document, it is mentioned that the Minimum Sludge
Consistency after dewatering shall be 25% (+/-) 2 % w/w.
However, in practice dewatering machines offer sludge consistency of about 20- 22%
w/w. Therefore, we request the department to kindly consider the sludge consistency of
dewatered sludge according to the consistency obtained in actual practice and confirm
your acceptance for 20-22% w/w sludge consistency for dewatered sludge at the outlet.
As per bid document
221) Vol-2, Section
XI, Part 2
170 Plant & Process
Clause 2.3
We assume, except primary clarifier, secondary clarifier and gas holder, the bidder is
free to construct new one instead of rehabilitating the existing unit such as distribution
chamber, interconnecting channel etc. Please Confirm.
As per bid document
222) Vol-2, Section
XI, Part 2
170 Plant & Process
Clause 2.3
Please provide the depth from Existing ground level (EGL) for the following unit that
has to be demolished.
1. Aeration Tank
2. Digester
3. Sludge drying beds.
Bidders to verify from site
51
223) Vol-2, Section
XI, Part 2
170 Plant & Process
Clause 2.4
As per NIT, the treated effluent guarantee for phosphorous is provided as 2 mg/l (Inlet
– 6 mg/l), but as per clause 2.4 the existing WWTP shall be rehabilitated and upgraded
to MLE process.
In MLE process only nitrogen can be removed biologically; therefore for Biological
Nutrient Removal process (Nitrogen and Phosphorous) shall we consider A2/O, UCT,
Bradenpho etc. process instead of MLE process to guarantee both nitrogen and
phosphorous removal. Please clarify.
Refer C&A No. 6, Sl. No. 18
224) Vol-2, Section
XI, Part 2
170
&
206
2.3 & 2.37 Existing Drying Beds & New Sludge Drying Beds Since there are already 48 nos. of SDBs in the plant, it would be better to use some of
these SDBs to manage 10 % of Digested sludge /Dewatered sludge, and not build
additional SDBs. Please review and confirm.
As per bid document
225) Vol-2, Section
XI, Part 2
170 2.4 Sewage Treatment Process Kindly provide the HFL of supplementary drain. Refer hydraulic flow diagram
drag no. YAP-
III/R2/P/HFD/002(T).
However, bidders to verify
the levels from site. 226) Vol-2, Section
XI, Part 2
170 Cl. 2.4 Sewage Treatment Plant process
Existing STP shall be rehabilitated and upgraded to achieve treated effluent parameters
as mentioned under cl. 2.2.2 of Volume 02. The main biological liquid treatment
process shall be conventional plug flow activated sludge with initial anoxic zone and
internal mixed liquor recycle (MLR) for denitrification, also known as Modified
Ludzack- Ettinger (MLE process. Bidder can also propose alternative biological
process based on membrane bio reactor (MBR) which shall be able to achieve treated
effluent parameters as mentioned under cl. 2.2.2 of Volume 02.
As per bid document
227) Vol-2, Section
XI, Part 2
171 2.5 Bypasses shall be provided around all flow meters and other in-line
instrumentation such that the instrument can be isolated and removed
for calibration and maintenance without interrupting the flow,
regardless of whether or not such bypasses are shown in any
drawings included in the Tender Document
We assume that, all Magnetic flow meters will be provided with 2 Nos. Isolation Valve
and 1 No. Bypass Valve.
Please confirm.
Confirmed
228) Vol-2, Section
XI, Part 2
171 Part 2 / Clause 2.4 Further the IL of the treated effluent channel at the outfall point shall
be minimum 1 m above the HFL of Nangloi supplementary drain.
We presume that, the HFL of Nangloi drain is 208.85 as indicated in the Hydraulic
profile diagram Drg No : YAP-III/R2/P/ HFD/ 002 (T) Please confirm.
This as per the available
records, however bidders are
also required to also verify
the same from concerned
authority. 229) Vol-2, Section
XI, Part 2
171 New Common
Inlet Chamber
Please provide the distance of Inlet chamber of existing Phase-II plant from the
proposed New common Inlet chamber for Phase-I and Phase-II.
Bidders to verify from site
230) Vol-2, Section
XI, Part 2
171 Plant & Process
Clause 2.4
Please provide the TWL of common inlet chamber in order to find the maximum
available head for designing the hydraulics.
As per bid document
231) Vol-2, Section
XI, Part 2
171 Plant & Process
Clause 2.4
As per Volume 4, Section XVI Drawing – HFD, the TWL of inlet chamber of Phase I
provided as 219.19 m, where screen head loss considered as 50 mm which is very less
when compared to CPHEEO standard. As per CPHEEO a minimum 300 mm head loss
to be considered across the screen at peak flow. Therefore the TWL of the Phase inlet
chamber will be 219.44 mm (250 mm higher). Please clarify.
Please clarify whether the available head at the common inlet chamber is sufficient to
consider 219.44 m as TWL of Phase I Inlet chamber.
As per bid document
232) Vol-2, Section
XI, Part 2
171 2.5 General Design Requirement
We understand that for the Overhead Lifting of Aeration Tank Pumps, Blowers,
Digestor Gas Compressors, etc. the type of lifting equipment (HOT or EOT crane)
shall be as per clause 4.2.20,page 349. Kindly confirm.
Refer C&A No. 6, Sl. No. 54
233) Vol-2, Section
XI, Part 2
172 Clause 2.5 (7th
Point)
Plant & Process We assume all the liquid holding structures shall be drained through gravity or by
pumping through existing pumps.
As per bid document
234) Vol-2, Section
XI, Part 2
173 2.5 The minimum velocity of full flow in pipes or conduits shall not be
less than 0.6 m/s and the maximum shall not be more than 1.2 m/s for
pump suction and not more than 1.5 m/sec for pump discharge.
All the clauses are contradicting with each other for Sewage, Water & Waste Water.
We assume that, we shall design pipe line sizes as per the Velocity Basis provided in
Page No. 339.
Please confirm.
Refer C&A No. 6, Sl. No. 19,
23 & 52
235) Vol-2, Section 173 2.5 The normal pipeline peak flow velocity for gases shall not be more Please note that, the Bio-gas will get condensed, if the line velocity exceeds more than Refer C&A No. 6, Sl. No. 19,
52
XI, Part 2 than 15.0 m/s. 6.0 m/s. We assume that, we shall be design the Bio-gas pipe lines with the velocity of
3.5 to 6.0 m/s. Please confirm.
23 & 52
236) Vol-2, Section
XI, Part 2
173 2.5 Appropriate restrained flexible connections and/or joints shall be
provided for all pipes where they connect to any and all of the
following:
o Equipment such as pumps, blowers, or inline devices
o Valves
We assume that, the type of flexible connections / joints shall be as per Bidder's
design.
Please confirm.
As per bid document
237) Vol-2, Section
XI, Part 2
174 Plant & Process,
Clause 2.6
We assume new bye pass facility has to be provided for common inlet chamber and for
Phase I inlet chamber. Please clarify.
As per bid document
238) Volume 2 174
& 453
Section XI, Part
2, Plant &
Process, Clause
2.5
Section XI
Part 6
Instrumentation
Clause 6.5.1
In Part 2, Plant and Process, Clause 2.5 it is mentioned as – “For clarifiers, the design
shall provide for separate and independent measurement and control of the flow rate of
sludge withdrawal from each individual clarifier unit”.
In Part 6, Instrumentation, Clause 6.5.1 – List of instruments, online flow measurement
is specified only for Primary Sludge Pump Header line and Return Sludge Line.
From above two clauses it is contradicting that whether flow rate of sludge to be
monitored individually from each clarifier or sludge flow to be measured only in the
common header line of Primary sludge and RAS Pumps. Please clarify.
Refer C&A No. 6, Sl. No. 20
239) Vol-2, Section
XI, Part 2
175 Plant & Process
Clause 2.6
As per this clause, for Process Pumps, Blowers and Compressors: If not mentioned
specifically otherwise, provide 100% standby unit.
Please confirm whether bidder can choose no of standby units as per standard
engineering practice.
As per bid document
240) Vol-2, Section
XI, Part 2
176 Plant & Process
Clause 2.7 & 2.10
& 2.11
In Clause 2.7 and in layout, the no of units for the following structures specified as :
Fine Screen Channel – 4 Nos (2 W + 2 S)
Grit Chamber – 4 Nos (2 W+ 2 S)
But in Same volume and section, clause 2.10 & 2.11 the no. of screen and grit chamber
provided as 3 Nos. (2W+1S). Please clarify whether to consider 3(2W+1S) or
4(2W+2S).
Refer C&A No. 6, Sl. No. 23
& 42
241) Vol-2, Section
XI, Part 2
176 Cl 2.7 Rehabilitation Work For the Bidders to reliably assess the nature, complexity and scope of the Demolition
and Rehabilitation works to be carried-out, kindly provide the As-Built / GA Drawings
of all the units in Phase-1 plant. As a minimum, the drawings for the following units
should be provided:
Screen / De-gritting Unit / Distribution Chamber of PST
PST
Aeration Tanks
Secondary Clarifier with distribution Chamber.
Raw Sludge Sump & Pump House
Electric Sub-station
Sludge Digester.
Gas Holders
Bidders to verify from site
242) Vol-2, Section
XI, Part 2
176 Cl. 2.7 Sewage Treatment Process Layout and facilities Description - Indicative list of major
treatment units Existing / proposed
As per Item no. 16 of the table, existing Bioreactor tanks to be demolished and
constructed as new. We request you to allow bidders to use existing bioreactor tank
with necessary modifications if it is meeting the requirements for process requirements
As per bid document
243) Vol-2, Section
XI, Part 2
176 General
Clause 2.7
Please provide the dimensions of distribution chamber of Primary Clarifier &
Secondary Clarifier and the interconnecting Channel width and height.
Bidders to verify from site
244) Vol. 2 177 2.7
S. No. 47
Existing Substation Building-PMCC-1 This S/S Building will also have other
New 11KV HT panel , new Transformers , different MCCs etc.
As per Bid document
245) Vol. 2 177
&
212
2.7
S.no. 51 & 2.40
Micro Hydro Power Generation System Necessary liasoning work / getting permission will be in scope of Purchaser for
hooking up power to grid.
As per bid document
246) Vol-2, Section
XI, Part 2
178 Common Inlet chamber for Phase-I and Phase-II WWTPs The common Inlet chamber will be designed as per the Hydraulics of Phase-I WWTP
and TWL of Inlet chamber for Phase-II WWTP.
As per bid document
53
It is assumed that the pumping head (in the upstream Pumping stations) for all the
incoming raw sewage rising mains (8 nos.) is sufficient for this design.
Otherwise, please provide the maximum TWL feasible in this Common Inlet chamber
for design purposes.
247) Vol-2, Section
XI, Part 2
178 Common Inlet chamber for Phase-I and Phase-II WWTPs- Rising
mains
Please provide any layout indicating the location of all the 8 nos of incoming rising
mains which have to be interconnected to the common Inlet chamber.
Bidders to verify from site
248) Vol-2, Section
XI, Part 2
178 Common Inlet chamber for Phase-I and Phase-II WWTPs- Rising
mains
Please provide approximate lengths for each rising main which have to be extended
and connected to the Common Inlet chamber.
Bidders to verify from site
249) Vol-2, Section
XI, Part 2
178 Common Inlet chamber for Phase-I and Phase-II WWTPs- Rising
mains
Please mention the shut-down time (if any specific requirement), for each incoming
sewage rising main.
Bidders to verify from site
250) Vol-2, Section
XI, Part 2
178 Plant & Process
Clause 2.8
Please provide the invert level of incoming pipes (8 Nos) to common inlet chamber
and the direction of entrance to the common inlet chamber.
Bidders to verify from site
251) Vol-2, Section
XI, Part 2
179 Clause 2.10, Fine
Screen Channels
As per this clause, Electrically operated Inlet & Outlet thimble mounted isolation
sluice gates shall be provided for controlling the flow from common channel to Grit
chambers. We request you to please accept for Open Channel gates instead of thimble
mounted sluice gates. Please confirm.
As per bid document
252) Vol-2, Section
XI, Part 2
179 Clause 2.10, Fine
Screen Channels
We request you to please accept inclination angle of screen to horizontal is 400 to 700
instead of 450 to 700. Please confirm.
Refer C&A No. 6, Sl. No. 23
253) Vol-2, Section
XI, Part 2
179 Common Inlet chamber for Phase-I and Phase-II WWTPs- Existing
Siphon/duct
Please provide the details/drawings of the existing siphon/duct conveying wastewater
to Phase-II WWTP.
Bidders to verify from site
254) Vol-2, Section
XI, Part 2
179 2.10 Fine Screen Channels As per our experience in the O&M of STPs, and the feedback from the Screen
Vendors, a 10 or 20 mm Medium Bar screen should be provided upstream of 6 mm
Fine Screen for its trouble free operation and Manufacturer‟s Warrantee. However, in
the tender there is no mention of a Medium Screen before 6 mm Fine Screen. Kindly
confirm if the raw sewage is already passed through a medium bar screens (opening
not exceeding 20 mm). Otherwise, please make the provision of Medium Screen before
the Fine Screen mandatory for all the Bidders.
Refer C&A No. 6, Sl. No. 23
255) Vol-2, Section
XI, Part 2
179
& 180
Clause 2.10
& 2.11
Mechanical treatment Is it acceptable to use 4 strings of mechanical treatment (4 screen channels + 4 grit
chambers)
Refer C&A No. 6, Sl. No. 23
256) Vol-2, Section
XI, Part 2
Vol-2, Section
XI, Part 4, Para
3
180
181
271
Clause 2.11,
4.2.2.
Grit chambers
Tender Clause states-
“No. of Units shall be 3 Nos. (2W+1S)”.
Grit chambers
Tender Clause states-
“Grit chambers shall be of vortex type with centre drive and
independent washer and or /or classifier as specified in Part -2, Vol-
2, total 4nos(2 W+2S) each designed for a 50% of peak flow of
i.e.182mld. “
We Presume that required quantity shall be 3 Nos. (2W+1S).
Please confirm.
Refer C&A No. 6, Sl. No. 42
257) Vol-2, Section
XI, Part 2
180 Clause 2.11 Mechanical treatment Is it acceptable to use classical, horizontal grit chambers? As per bid document
258) Vol-2, Section
XI, Part 2
181 Plant & Process
Clause 2.11
The vortex grit chambers have a typical detention times at peak design flows 20 to 30
seconds. But as per mentioned clause the minimum HRT of grit chamber at peak flow
provided as 60Sec. Please clarify.
Refer C&A No. 6, Sl. No.24
259) Vol-2, Section
XI, Part 2
181 2.11 Grit Chamber Kindly confirm the maximum design SOR at Peak Flow conditions for the design of
the Vortex Grit Chamber.
As per vendor design subject
approval of Engineer In-
charge 260) Vol-2, Section
XI, Part 2
182
& 189
Clause 2.13 &
2.18
Plant & Process Please provide the diameter and MOC of sludge withdrawal line from primary and
secondary clarifier for the selection of valves and designing.
Bidders to verify from site
261) Vol-2, Section
: XI , Part:2 &
Part:4
182
&
271
2.13
&
4.2.2
Cyclone Grit Chamber Number of grit chambers specified in 2.13 is ( 2W+1S ) which is in variance with
clause 4.2.2 where the number of grit chambers mentioned is 4( 2W+2S). Kindly
Clarify the discrepancy.
Refer C&A No. 6, Sl. No. 42
262) Vol-2, Section
XI, Part 2
183 Plant & Process
Clause 2.13
Please provide the As Built Drawing of Primary Clarifier or provide the following
details
Bidders to verify from site
54
1. Inlet Pipe dia and MOC
2. Influent arrangement
3. Weir arrangement (Single Weir or double Weir)
4. Sludge withdrawal pipe invert level and sludge valve arrangement details.
263) Vol-2, Section
XI, Part 2
183 Plant & Process
Clause 2.13
Please provide the present sludge consistency from primary clarifier which is pumped
to the digester.
Bidders to verify from site
264) Vol-2, Section
XI, Part 2
183 Plant & Process
Clause 2.15
Please provide the dimension of existing raw sludge sump for mixer design and invert
level of incoming sludge pipes from primary clarifier.
We assume that as per bidder design, the pump capacity and head shall be designed
and replace the existing raw sludge pumps with new ones. Please confirm.
Bidders to verify from site
As per bid document
265) Vol-2, Section
XI, Part 2
184 2.16
Bioreactor
While the tender allows the actual HRT as per design, the specified minimum 10 hr
HRT value is very low considering the fact that due to the poor TKN/BOD ratio at the
inlet of bioreactor and low temperature of sewage during winter in Delhi, the actual
design HRT will be much higher. In our view, the long terms interest of the Employer
will be better protected with a more realistic minimum HRT specified that will deter
the Bidders from compromising the design for the sake of bid competitivity We request
this issue to be reviewed and minimum HRT to be re-confirmed.
Refer C&A No. 6, Sl. No. 26
& 27
266) Vol-2, Section
XI, Part 2
184
& 349
2.15
(B-iv)
Raw Sludge Sump & Pump House - Other Allied Works
EOT Crane is specified for Raw Sludge Pump House, whereas HOT (Double Rail)
crane is specified in clause 4.2.20 (page 349) for up to 3 MT lifting requirement. Since
the weight of the Raw Sludge Pumps shall be much less than 3 MT, we understand
HOT (Double Rail) crane shall be acceptable. Kindly confirm.
Refer C&A No. 6, Sl. No. 54
267) Vol-2, Section
XI, Part 2
184
& 187
Clause 2.16.2
Clause no. 2.16
Aerobic Zones
Tender Clause states -
“Minimum Sewage temperature – 15 deg C”.
Aerobic Zones
Tender Clause states -
"The minimum sewage temperature used for design may be
considered as 180C and maximum as 270C. “
There is ambiguity for minimum design temperature for aeration temperature.
We Presume that minimum sewage temperature of 17.80C shall be considered for
design in line with influent water properties specified at Page 133/ Vol. 2, Section XI,
Part-1, Clause 1.6.
Please confirm.
Refer C&A No. 6, Sl. No. 28
268) Vol-2, Section
XI, Part 2
185 2.16.1(xiv) Mixing Power for Anoxic Tank
Mixing requirement specified as 8 - 10 Watt/cum in tender document, We request you
to allow bidder‟s to design mixing system as per the criteria specified in CPHEEO
manual. Ref. CHHEEO Manual/ Part A Chapter 5.
As per bid document
269) Vol-2, Section
XI, Part 2,
Plant &
Process
185 Clause 2.16.1 As per this clause minimum mixing requirement of 8-10 Watt/cum to be provided in
the anoxic tank, this is on higher side. As per vendor recommendation the minimum
mixing power requirement is 1-6 Watt/cum for denitrification units.
Therefore shall we consider minimum mixing requirement to 1- 6 Watt/cum. Please
confirm.
As per bid document
270) Vol-2, Section:
XI, Part 2
185
&186
2.16.1 & 2.16.2
Anoxic Zone and Aerobic Zone – Liquid Depth Considering the space constraint and the required very big volume of the Bioreactor,
please allow 7 m (maximum) liquid depth as against 6 m (maximum) specified in the
tender. Kindly review and confirm.
Refer C&A No. 6, Sl. No. 26
& 27
271) Vol-2, Sec-XI ,
Part -2
185
186
2.16 Anoxic Zones & Aerobic Zones – Liquid Depth Due to the large volume of the Bioreactor required, the Tender limiting the “Liquid
Depth 6.0 m (maximum)” shall make it difficult for the new bioreactor to be
accommodated in the available space in the plant. There are plants in India and abroad
where more than 6 m Liquid Depth in Bioreactor has been provided and operated
successfully.
We request the Bidders should be allowed to propose the Bioreactor depth as per his
requirement to fit the plant within the overall available space. Kindly review and
confirm
Refer C&A No. 6, Sl. No. 26
& 27
272) Volume-2 185 Section XI Part 2
Clause 2.16.1
Anoxic zones Mixing requirement
Mixing requirement specified for Anoxic zone is very high (8-10 W/m3).
2-3 W/m3 is sufficient for the purpose. Kindly confirm.
As per bid document
273) Vol. 2, Section
XI, Part-2
187
Clause 2.16.2
Aerobic Zones
Tender Clause states -
“Fouling factor for diffuser – 0.8 ”
Please confirm the fouling factor to be considered for design. Refer C&A No. 6, Sl. No. 28
55
Vol. 2, Section
XI, Part-4, Sub
clause e)
284
&
285
Clause no. 4.2.5
Diffusers
Tender Clause states -
“Fouling Factor
‐ For retrieval diffusers which can be cleaned and serviced at a
frequency of 6 to 8 weeks without the need of emptying tank - 0.90
‐ For fixed ( i.e. non retrievable diffusers ) which cannot be cleaned
or serviced without emptying of tank - 0.70 “
274) Vol. 2, Section
XI, Part-2
187
Clause 2.16.2
Aerobic Zones
Tender Clause states -
“Diffuser Membrane MOC - EPDM or silicon elastomer with UV
protection”.
Please confirm the MOC of Diffuser Refer C&A No. 6, Sl. No. 28
275) Vol. 2, Section
XI, Part-2
187 Clause 2.16.2 Aerobic Zones
Table Point No. C.i - Minimum Air Blower Quantity
Tender Clause states - Minimum one number Blower for each
aeration tank and minimum 50% standby for total numbers.
Please note that bidders should be allowed to choose the Process Air Blower
Configuration as per their process design. Provision on minimum one blower for each
aeration tanks should be relaxed. However, bidders will follow the minimum 50%
standby requirement for total number of blowers.
As per bid document
276) Vol-2, Section
XI, Part 2
187 Clause 2.16.2 Plant & Process We assume that bidder is free to choose the number and configuration of blower as per
bidder design. Please confirm.
As per bid document
277) Vol-2, Section
XI, Part 2
187 Clause 2.16.2 Plant & Process Whether additional safety factor of 20% to be considered for oxygen demand. As per
NIT, already we have considered maximum oxygen demand by considering oxygen
credit (in denitrification process) as 50% for nitrification process. Please Clarify.
As per bid document
278) Vol-2, Section
XI, Part 2
187 2.16.2 Aerobic Zones
Point –C ,
Process Air Blower ( i )
50% Standby (minimum) of Total nos. is specified. It may be noted that specified High
Speed Centrifugal/Turbo Blowers are efficient and robust, but are also very expensive
equipment. Excessive Standby units, complete with mechanical and electrical systems,
will cost a lot of money to the Employer without any real advantage. In addition, the
Building size will also increase adding to the cost. Hence, we suggest 50%standbyof
the total nos. with a max. of 2 nos. Standby should be specified for Process Air
Blower. Kindly review and confirm.
As per bid document
279) Vol-2, Section
XI, Part 2
187 2.16.2, B (x) Minimum Sewage temperature Minimum sewage temperature specified is 15 deg C, whereas at pg. 168 (cl 2.2.1), the
minimum sewage temperature is specified as 17.8 deg C. The minimum temperature
for design will play a major role in the sizing of the Bioreactor for Nitrification and
De-nitrification, and the plant performance. Hence, we request the Employer to specify
the minimum design temperature of the raw sewage to be considered for design by all
the bidders.
Refer C&A No. 6, Sl. No. 28
280) Vol-2, Section
XI, Part 2
187 2.16.2, B (ix) Diffuser Fouling
Factor
Please confirm that the design Fouling Factor shall be as per the criteria and value
specified in vol-2, Section – XI, Part 4, Cl 4.2.5 (e).
Refer C&A No. 6, Sl. No. 28
281) Volume-2 187 Section XI Part 2
Clause 2.16.2
Aeration requirements
Tender specifies “Oxygen Demand safety factor as 20%”
Request to remove the same as standby blowers are provided which can always cater
the additional air requirement for instant.
As per bid document
282) Volume-2 187 Section XI Part 2
Clause 2.16.2
Process Air blowers
Tender specifies “Min. no. of standby air blowers required as 50%”
Min. no. of standby Air blowers shall be 33% as per general practice. Kindly revise the
same.
As per bid document
283) Vol-
2,Section:XI,
Part-2
188
2.16.2
Suitable Air Cooling System shall be provided to reduce the
temperature of compressed Air from discharge of air blower before
entering into the Aeration Tank
We assume that, the type and location of Air cooler is as per Bidder's Design.
Please confirm.
As per bid document
284) Vol-2, Section
XI, Part 2
189 Plant & Process
Clause 2.18
Please provide the As Built drawing of Secondary Clarifier or provide the following
details
1. Inlet Pipe dia and MOC
2. Influent arrangement
3. Weir arrangement (Single Weir or double Weir)
Sludge withdrawal pipe invert level and sludge valve arrangement details.
Bidders to verify from site
56
285) Vol-2, Section
XI, Part 2
189 2.18
A
Secondary Clarifier Minimum SVI value for design is not specified in the tender. Kindly note that SVI
value is one of the most critical parameter in the design of the Secondary Clarifier in
such plants. However, in ASP plants having Primary Clarifiers, and Bioreactor
designed with nitrification and de-nitrification process, typical SVI value is in the
range of 120 - 150. In order to ensure that designs proposed by each Bidder is reliable
and comparable for fair evaluation, we request you to kindly specify the minimum
design SVI value to consider.
As per bid document
286) Vol-2, Section
XI, Part 2
189 2.18
A (ix)
Secondary Clarifier
Solid concentration in waste activated sludge is specified as 0.75%
(minimum).However, in STPs with Primary Clarifiers and Bioreactor designed with
nitrification and de-nitrification process, the typical concentration of waste activated
sludge is in the range of 0.4 to 0.6 %. With unrealistic high concentration as per tender,
the RAS, Bioreactor and Sludge Treatment Units will be undersized, and shall
eventually lead to permanent operational and process performance problems. We
recommend that for the purpose of design, the waste activated sludge concentration
should be specified as 0.5% (maximum). Please review and confirm.
Refer C&A No. 6, Sl. No. 29
287) Vol-2, Section
XI, Part 2
189 Clause 2.19 RAS capacity of existing Secondary Clarifier Sludge Pipe The critical information about the existing RAS Pump capacity, sludge pipe diameter
from each secondary clarifier to the RAS Sump is missing in the tender. During our
site visit on the day of Pre-bid Meeting, it was observed that are 5 (4W+1S) RAS
Pumps, and the pump discharge pipe is of diameter 350 mm. Hence, the actual possible
maximum RAS capacity is estimated to be approximately equivalent to 40 to 50 %
only. It may kindly be noted that for the Rehabilitation and Up-gradation of the plant to
achieve the new standards (esp. for BOD and TN), the RAS capacity required will be
more than 100%. It will be possible only if the sludge pipe of each of the existing
Secondary Clarifier is of 700 - 800 mm dia. Kindly, therefore, confirm the size of the
Secondary Clarifier Sludge Pipe as this is an extremely critical information necessary
for the plant design& viability of the project, and cannot be ascertained by the Bidder
on his own as the pipes are buried under the raft.
Bidders to verify from site
288) Vol-2, Section
XI, Part 2
190 Plant & Process
Clause 2.19
Please provide the dimension of existing RAS sump for mixer design and invert level
of incoming sludge pipes from secondary clarifier.
We assume that as per bidder design, the pump capacity and head shall be designed
and replace the RAS sludge pumps with new ones. Please confirm.
Bidders to verify from site As per bid document
289) Vol-2, Section
XI, Part 2
190 2.19
(B-iv)
RAS Sump and Pump House - Other Allied Works
EOT Crane is specified for RAS Sludge Pump House, whereas HOT (Double Rail)
crane is specified in clause 4.2.20 (page 349) for upto 3 MT lifting requirement. Since
the weight of the RAS Pumps shall be much less than 3 MT, we understand HOT
(Double Rail) crane shall be acceptable. Kindly confirm.
Refer C&A No. 6, Sl. No. 54
290) Vol. II 191 2.21 Tertiary Filtration System
2.21.1 Travelling Bridge Filters
2.21.2 Cloth Media Disk Filters
2.21.3 Membrane Filter System
Tender specifies 3 types of tertiary filtration systems. We understand that bidder has
choice to select any one system among 3 mentioned in tender. Please confirm
Confirmed
291) Vol. -2 191 2.21 Design flow – Tertiary treatment Plant Please reconfirm that the rehabilitation work is designed for 182 MLD raw sewage
flow design capacity accordingly tertiary treatment plant is also to be designed for
average flow 182 MLD, kindly elaborate
As per bid document
292) Vol- 2,
Sec : XI,
Part-2 &
Part-10
191
&
684
2.21
& 10.1
Tertiary Filtration System
&
List of Approved Make
Tertiary Filtration System is as critical a process for the plant and contractual
performance of the Contractor as Biological Process. Irrespective of out-sourcing the
Equipment from the tender List of Approved Vendor, the Bidder remains solely
responsible for the Contractual Performance towards the Employer, including during
11 years long O&M and supply of Spare, Hence, we understand that the Bidder, having
his own Tertiary Filter Technology out of the options specified, is allowed to propose
his design and Technology for the same. Kindly confirm.
As per bid document
293) Vol-2, Section
XI, Part 2
191
& 192
2.21 Tertiary Filtration System For all the Tertiary Filtration Options, 4 nos. (minimum) Units are specified. Kindly
note that in the event one unit is out of Service, the Filtration Units in operation shall
be continuously 33 % over-loaded. During the Peak Flow durations, the overloading
shall be 133%. For robust and consistent performance of the filtration units in such
applications, it is advisable not to allow more than 20% continuous overloading. As the
Secondary Treatment is to be designed with 6 streams, we suggest the Tertiary
Refer C&A No. 6, Sl. No. 30,
31 & 32
57
Filtration Units should also be 6 nos. (minimum). Kindly review and confirm
294) Vol-2, Section
XI, Part 2
191 Clause 2.21 Tertiary filtration system There are three types of filters - should bidder apply all devices or choose the one that
will be assembled? Is it acceptable to use micro-screens?
As per bid document
295) Vol-2, Section
XI, Part 2
191 Plant & Process
Requirements
2.21 Tertiary Filtration System. Please clarify whether Travelling Bridge Filters plus Cloth Media Disk Filters plus
Membrane Filter System are all deemed necessary to achieve the Treated Effluent
Quality Requirement & Guarantee, or whether the Contractor can propose to combine
two out of the three suggested systems.
As per bid document
296) Vol-2, Section
XI, Part 2
192 Clause 2.21.2 Effluent filters
The quantity of Effluent filtration system shall vary depending upon the vendors for
producing the desired flow. Kindly allow contractor to decide numbers of filters to be
installed, in order to have smallest footprints.
As per bid document
297) Vol-2, Section
XI, Part 2
193 Plant & Process
Clause 2.22
As per CPHEEO Manual, the chlorine contact tank to be designed for 30 min HRT at
average flow. But as per tender the HRT at peak flow is provided as 45 minutes which
is on higher side. Please clarify whether chlorine contact tank to be designed for 30 at
average flow as per CPHEEO or 45 min at peak flow.
Refer C&A No. 6, Sl. No. 33
298) Vol-2, Section
XI, Part 2
193 Clause 2.22 Chlorine contact tank
Tender specifies “HRT for CCT shall be 45 min. at peak flow” To achieve the desired
MPN at outlet effluent, 20-30 min. of retention at average flow is sufficient. Kindly
confirm & revise the same.
Refer C&A No. 6, Sl. No. 33
299) Volume 2 193 Clause 2.22 Disinfection We request you to consider UV disinfection that is more Eco-Friendly Technology and
also guarantees highest degree of Bacteria and pathogen removal from wastewater.
As per bid document
300) Vol-2, Section
XI, Part 2
193 HRT of Chlorine Contact Tank
As per Page no. 193 of tender document, it is mentioned that the Hydraulic retention
time of chlorine contact tank shall be minimum 45 minutes at peak flow.
However, as per latest CPHEEO manual, it is mentioned that the detention time in the
chlorine contact tank should be 30 minutes based on average flow. It is therefore
requested to the department to kindly consider the HRT of Chlorine Contact Tank as
per CPHEEO manual.
Refer C&A No. 6, Sl. No. 33
301) Vol-2, Section
XI, Part 2
194 Clause 2.23 Chlorination system
Tender Clause states -
“Vacuum chlorinator – 6 Nos. (4W+2S) (minimum)
Please confirm the chlorination system and booster pump quantity requirement. As per bid document
302) Vol-2, Section
XI, Part 2
194 Plant & Process
Clause 2.23
In Clause 2.22, bidder has to design the chlorine dosing in chlorine contact tank and in
clause 2.23 the capacity of vacuum chlorinator provided as 30 kg/h (4W+2S), which is
contradicting. Please clarify whether to consider 30 kg/h or bidder has to design the
dosage and chlorinator capacity.
As per bid document
303) Vol-2, Section
XI, Part 2
194 Plant & Process
Clause 2.23
As per this clause 12 Nos of chlorine tonners to be kept in online, this is on higher side.
If we consider 30 kg/h as capacity of chlorinator then we required 2880 kg of chlorine
in a day i.e 4 tonners required to be kept in online. Please clarify the number of tonners
to be kept in online
Also please clarify the number of tonners to be kept as storage. (For 15 days storage
and 30 kg/h chlorinator capacity around 48 nos of tonners required)
Refer C&A No. 6, Sl. No. 34
304) Vol-2, Section
XI, Part 2
194 2.23 Chlorinator capacity Please clarify if the specified design Chlorinator Capacity is at Average Flow or at
Peak Flow.
As per bid document
305) Vol-2, Section
XI, Part 2
194 2.24 De-Chlorination system We understand that the residual free chlorine to be maintained at the outlet of the De-
chlorination system is “Below Detection limit (BDL)”. Please confirm.
Refer C&A No. 6, Sl. No. 35
306) Vol-2, Section
XI, Part 2
195 Plant & Process
Clause 2.26
As per this clause the maximum sludge loading rate to be considered for gravity sludge
thickener design is 60 Kg/m3-d which is very low.
In CPHEEO manual (Part A – Engineering , Clause 6.3.1, Page No 6-20), sludge
loading rate for primary sludge is 90-140 kg/day/sqm and in Wastewater Engineering –
Treatment and Reuse - Metcalf and Eddy , (Table 14-19, Page 1492), sludge loading is
100 – 150 kg/m2/d.
Please provide the revised maximum sludge loading rate to be considered for the
design of gravity sludge thickener.
Refer C&A No. 6, Sl. No. 36
307) Vol-2, Section
XI, Part 2
195 Clause 2.26 Gravity sludge thickener
5% thickened sludge concentration from outlet of thickener is difficult to achieve
As per bid document
58
without poly dosing. Kindly allow to consider sludge concentration per standard
practice.
308) Vol-2, Section
XI, Part 2
195
& 196
Clause 2.26 &
2.27
Plant Water Pumps, Sludge thickening Is it acceptable to use belt type or Archimedean screw type mechanical thickeners? As per bid document
309) Vol-2, Section
XI, Part 2
196
204 &
205
Plant & Process
Clause 2.28, 2.35
& 2.36
As per NIT, 100 % standby has to be considered for Digester feed pump 4(2W+2S),
Centrifuge Feed Pump 8(4W+4S) and Centrifuge 8(4W+4S). Since we are providing
Sludge thickener and DAF at upstream of Digester feed pump which act as sludge
holding tank in emergency situation. Therefore shall we consider 50% standby for
Digester feed pump, Centrifuge Feed Pump and Centrifuge.
Please confirm.
As per bid document
310) Volume 2 196 2.27 Dissolved
Air Floatation
(DAF) Thickener
The Tender asks for construction of two round flotation unit used for
mechanical compaction of sediment before fermentation chambers.
We request you to consider use of other better form of mechanical compaction that will
guarantee the same output parameters as the sludge in the specifications or better (e.g.
drum compactor or others of renowned make and quality). Please confirm.
As per bid document
311) Vol-2, Section
XI, Part 2
196 2.27 DAF for Secondary thickening In sludge thickening application, Direct Pressurization DAF Sludge Thickeners, which
do not require separate sludge recirculation, are proven to perform better. This
technology is already implemented by the Employer in a STP in Delhi. Hence, we
understand that Direct Pressurization type DAF Thickener is also acceptable. Kindly
confirm.
As per bid document
312) Vol-2, Section
XI, Part 2
196 2.27 Dissolved Air Flotation (DAF) Thickeners Typically, the Biologically sludge in DAF Thickener can be thickened to a maximum
concentration of 3.5 to 4% (compared to 2% - 2.5% in Gravity Thickeners in warm
waters). The requirement of 4% (minimum) cannot be achieved consistently. A bidder
considering 5% conc. will be compliant with this requirement but the Sludge Digester
will be under-sized. We, therefore, request that this criteria should be changed to 4%
(maximum). Kindly confirm.
As per bid document
313) Vol-2, Section
XI, Part 2
197
&
204
Mechanical
Ventilation
System
As per the document, Mechanical ventilation system has to be provided for Thickened
Sludge Pump house and Digested Sludge Pump house.
We assume only forced extract system and natural supply system will suffice the
requirement of Mechanical ventilation. Please confirm.
As per bid document
314) Vol-2, Section
XI, Part 2
198 2.29
Regarding Anaerobic Digesters You have considered the dome of anaerobic digesters of Mild Steel with Cathodic
protection. We request you to consider Double Membrane type Gas Dome looking to
the better performance and life. The corrosion normally takes place with MS
Structures. This we have observed during our experience of construction of 33 Nos. of
anaerobic digesters more than 30 M dia during last 36 years.
As per bid document
315) Vol. 2 Section
XI, Part-2
198 Clause 2.29 Anaerobic Digesters –Working volume
In the Table given on page no. 200 under sub-clause A-xii to xv,
various requirements towards Bottom slope, SWD of Anaerobic
digesters, Minimum depth of Grit and Scum zones are given
Please advise if bidders are allowed to consider bottom conical portion of Anaerobic
Digesters as part of total working volume for each digester.
As per bid document
316) Vol. 2, Section
XI, Part-2
198 Clause 2.29 Anaerobic Digesters – Mixing
In the Table given on page no. 200 under sub-clause B-i & ii,
Anaerobic Digester mixing system and requirements are defined.
Please advise if bidders are allowed to consider alternate mixing technology in the
form of Top Mounted vertical Agitators. These type of agitators consumes very less
power when compared with Confined gas mixing systems.
As per bid document
317) Volume 2 198 Clause 2.29 The process of fermentation / digestion We wish to draw your attention to the fact that on one hand the tender makes specific,
relatively high demands on the ecological effects of the process and on the other hand
restricts / imposes specific process parameters, requirements and technology.
In this case, the Contractor cannot be held responsible for the final result (effect),
unless the Contracting Authority allows the contractor for possibility of making
changes by the Contractor to the described process requirements (eg. the temperature
of the fermentation process, the mixing method in the fermentation tanks, solid
concentration of the inlet sludge and digested sludge, other detailed parameters etc.),
leading to achievements of results not worse than the required by the Employer.
Please confirm that the Contractor shall be free to run the plant as per the requirement /
prevailing condition and make changes as and when required to achieve the desired
output parameters.
As per bid document
318) Volume 2 198 Clause 2.29 Anaerobic Digester Construction We propose the construction of a closed digester in technology of reinforced concrete
and steel. Foundations and underground part of the tank shall be made of reinforced
As per bid document
59
concrete. The part of the tank that is above ground shall be made of bolted steel plates
enamelled with cobalt glass insulated with mineral wool and protected by galvanized,
trapezoidal, powder coated metal sheets.
The advantage of above construction is, it gives a longer life and better thermal
insulation that in turn helps maintains the temperature which is directly proportional to
the quality of outlet parameter. Please consider and confirm. 319) Volume 2
Sec-XI ,Part -
2
198 2.29 Anaerobic digesters Since the Sludge Digesters are now heated to maintain an optimum temperature of 32
to 37 deg C, the specified 20 day SRT for Digester design is already conservative as
per the CPHEEO Manual which allows 15 days SRT. Also, the Vortex Grit Chamber
to be provided in the plant are much more efficient compared to the conventional
Detritus type Grit Chambers. The Digesters with Gas Mixing System are completely
mixed, and there is no foam/scum accumulation problem. Hence, additional Digester
volume for Grit and Scum storage is no more necessary in modern Digesters. We,
therefore, recommend to delete the requirement of 0.5 m depth for Grit and 0.5 m
depth for Scum accumulation in Digester and optimize the Capex and Opex without
compromising the performance. Kindly review and confirm.
As per bid document
320) Vol-2,
Section –XI,
Part-2
198 2.29 Anaerobic Digester It will be more economical for the Employer to consider only 4 nos. Digesters instead
of 6 nos. specified in the tender. In Rithala Phase-2 Plant of the same capacity, only 4
nos. Digesters are provided. Kindly review and confirm.
As per bid document
321) Vol-2, Section
XI, Part 2
198 Clause 2.29 Anaerobic Digesters Is it acceptable to use chambers made of enamelled steel or steel with anticorrosion
protection?
As per bid document
322) Vol-2, Section
XI, Part 2
198 Plant & Process
Requirements
2.29 Anaerobic Digesters. The Anaerobic digesters shall have facility
for gas mixing and hydraulic pumped mixing, and contents inside the
digester shall be continuously kept under homogenous mixed
condition through these mixing systems (page 198). However, only
the Gas Mixing system is further mentioned and specified throughout
the Technical Specifications. Does the Employer nevertheless require
the combination of both Gas Mixing and Hydraulic Pumped Mixing,
or shall Gas Mixing only apply?
Please clarify. As per bid document
323) Vol-2, Section
XI, Part 2
198
&
203
Plant & Process
Requirements
2.29 Anaerobic Digesters and 2.35 Digested Sludge Sump & Pump
house. The digester shall work as constant level tanks whenever fresh
sludge is added equal quantity of supernatant shall over flow (page
199). Digested Sludge Sump/Centrifuge Feed Sump & pump house
shall be provided to withdraw the digested sludge from anaerobic
digester and store the same in digested sludge sump/centrifuge feed
sump and then pump the same to sludge dewatering system i.e.
centrifuge system (page 203).
Please confirm the mode of taking out material from the digester: gravity overflow
(probably not supernatant but mixed digested sludge as the digester is continuously
mixed) or pumped (pumping out mixed digested sludge with Progressive Cavity
Pumps). Please kindly resolve discrepancy.
As per bid document
324) Vol-2,
Section:XI,
Part-2
Vol-
2,Section:XI,
Part-4
199
&
339
2.29
2.31
4.2.19
DI K9 gas line of min. 200 mm dia. with a pressure gauge on the top
of digester shall be provided with gas tight/gas leak proof valves of
standard make. It shall be connected
The gas holder shall also have, separate gas inlet and outlet piping,
control valves, vacuum and pressure relief valves with flame
arrestors. There shall be a SS 316 pipeline header coming through
digesters to feed gas holder tank.
Bio Gas piping - SS 316
As the clauses are contradicting with each other, we assume that, Bio-gas piping from
Digester to Bio-gas holder shall be DI K9 Class.
Please confirm.
Refer C&A No. 6, Sl. No. 52
325) Vol. 2 200 Item No. B Regarding Digester Biogas Mixing. We suggest to provide digester gas mixing only with pumping arrangement as against
bio gas through bio gas compressor suggested by you, looking to our experience as
explained above against Point No.4. In many cases, the client has to replace the gas
mixing system provided through bio gas compressor.
As per bid document
326) Vol-2, Section
XI, Part 2
200 Clause 2.29 Anaerobic digesters
Tender specifies “Total minimum 6 nos. of Digesters”
The number of digesters shall be decided by contractor, withstanding the outlet
guarantees. Kindly confirm.
As per bid document
327) Vol-2, Section
XI, Part 2
200 Clause 2.29 Anaerobic digesters
Tender specifies “SRT for digesters as 20 days minimum”
As per bid document
60
For complete VSS digestion inside the digesters, 15 days of retention time is sufficient.
Kindly confirm & revise the same.
328) Vol-2, Section
XI, Part 2
201 2.31 An equal number of MS channels shall also be required on the inner
surface of the RCC walls over which the steel bell shall roll up and
down in the water filled RCC tank under gas pressure of 250 mm of
water gauge.
Normally, Gas Bell is designed with 200 mm WC. As per bid document
329) Vol-2, Section
XI, Part 2
201 Clause 2.31 Gas Holders
This clause specifies the various requirements for rehabilitation of
existing Gas Holders.
Please advise the Size and Capacity of the existing gas holders. This is required to
ascertain the available capacity of gas holders after rehabilitation.
Bidders to verify from site
330) Vol-2, Section
XI, Part 2
201 2.31 Gas Holder The Bidders should be given the option of replacing the existing old RCC-floating MS
Bell Gas Holders with a minimum 2 nos, Dual Membrane Type Gas Holders of
equivalent total capacity, which are now preferred by the Municipal Bodies as these
Dual Membrane GH are simple, safe and not prone to corrosion. Please review and
confirm.
As per bid document
331) Vol-2, Section
XI, Part 2
201 Clause 2.29 Heat Exchanger
Please clarify the Total number of Sludge Heat Exchangers to be considered for sludge
heating purpose.
As per bidder‟s design
332) Vol-2, Section
XI, Part 2
201 Clause 2.31 Plant & Process Please provide the dimensions of existing gas holder. Bidders to verify from site
333) Vol-2, Section
XI, Part 2
201 Clause 2.30 Plant & Process
For digester heating arrangement, please provide the type, configuration and
specification of
1. Heat Exchanger,
2. Recirculation pumps,
3. Heat water pumps,
4. Boilers etc.
As per bidder‟s design
334) Vol-2, Section
XI, Part 2
202 Clause 2.32 Bio Gas Scrubber
As per this clause the Bio Gas Scrubber shall be Bio-Chemical Type
whereas the mechanical specifications (Ref Clause No. 4.2.15 of Vol.
2 Section XI part 4) specifies use of Caustic Scrubbers only.
Please advise if bidders are allowed to use full biological Bio Gas Scrubbing system. As per bid document
335) Vol-2, Section
XI, Part 2
202 Cl. 2.31 As per NIT, Quantity of Biogas holders is mentioned as 3 working units and there are
no standby units. Please clarify whether standby shall not be required for the same.
As per bid document
336) Vol-2, Section
XI, Part 2
202 Plant & Process
Requirements
2.23 Biogas Flare.
The height of burner shall be minimum 6 m above FGL (page 203 of
Part 2) or 10 m (page 325 of Part 4).
Please kindly resolve discrepancy. Refer C&A No. 6, Sl. No. 51
337) Vol. 2, Section
XI, Part-2
203 Clause 2.34.1 Power generation building
Tender Clause states-
“The provision of pipe line should be made to transfer the biogas of
Phase-I WWTP to power generation building of Phase-II plant and
vice versa i.e. transfer of biogas from gas holder of Phase-II WWTP
to power generation building of Phase-I plant”.
We assume that the chemically scrubbed bio-gas connection to be made at the inlet of
biogas engine of phase-I & Phase-II.
Kindly elaborate. Also let us know the size of connecting pipe and connecting
methodology.
As per bid document
As per Bidder Design subject
to the Approval of Engineer-
In charge
338) Vol-2, Section
XI, Part 2
203
&
204
2.35 & 2.36 Digested Sludge Sump& Pump house The retention time in Digested Sludge Sump is specified as 4 hr. As per cl 2.36, Pg.
204, the working of centrifuge specified is 16hr/day and 7 days/week. Considering the
same, the minimum retention time for the digested sludge sump should be 8 hrs.
Kindly review and confirm.
As per bid document
339) Vol-2, Section
XI, Part 2
203
&
205
Part 2 – Plant &
Process
Requirements
2.35 Digested Sludge Sump & Pump house and 2.36 Centrifuge
Building. Minimum quantity of centrifuges is suggested as 8 Nos. (4
working + 4 standby) with feed pump quantity as 8 Nos. (4 working
+ 4 standby) as well. We interpret this that each centrifuge (working
or standby) has its dedicated feed pump (working or standby).
However, this configuration exaggerates the quantity of standby
centrifuges and has poor redundancy.
We suggest the following quantities and configuration: 5 Nos. of centrifuges (4
working + 1 standby) and 10 Nos. of feed pumps (each centrifuge is fed by 1 working
+ 1 standby feed pump, so a total of 5 working + 5 standby feed pumps). Please kindly
confirm.
As per bid document
340) Vol. 2, Section
XI, Part 2
205
& 310
1.Clause 2.36
Poly-Electrolyte Dosing System
Sludge Dewatering Units
As per the table in sub-clause of 2.36 on page 205 (B.iv in the table),
In case of bidder chose to go with Continuous Polymer solution preparation system,
these clauses will not be applicable.
Please confirm.
As per bid document
61
Vol.2, Section
XI, Part 4
2. Clause 4.2.12,
Sub Clause 4
Bidders are allowed to propose continuous polymer solution
preparation system.
This clause (Last para graph) states :
“The polymer solution strength shall not exceed 0.2%. There shall be
two working solution preparation tanks plus 1 standby tank for the
daily poly requirement with the tank agitator having a speed not more
than100RPM”
341) Vol-2, Section
XI, Part 2
205 Plant & Process
Clause 2.36
As per this clause the sludge concentration in the sludge cake should be 25% (+/-) 2 %
w/w which is higher as per Wastewater Engineering – Treatment and Reuse - Metcalf
and Eddy.
As per Wastewater Engineering – Treatment and Reuse - Metcalf and Eddy. (Table 14-
42, Page 1562), for anaerobically digested sludge (Primary and air activated) the cake
solid % from solid bowl centrifuge is 15-20%.
Therefore please revise the sludge concentration to 20 % (+/-) 2% instead of 25%.
As per bid document
342) Vol-2, Section
XI, Part 2
205 2.36 Centrifuge Building For the design, 2.5 Kg/TDS dewatering polyelectrolyte is specified which is very low
compared to the normal practice in STP projects in India wherein the design of
digested sludge dewatering system is based on a minimum of 5 kg/TDS
polyelectrolyte. Kindly review and confirm.
Refer C&A No. 6, Sl. No. 38
343) Vol-2, Section
XI, Part 2
205 2.36
B. (vi)
Polymer dosing pumps 1W+1S poly dosing pump is specified for 4W+4S Dewatering machines. As per our
O&M experience, for better operation, distribution and control, we strongly
recommend the Employer should specify dedicated Polyelectrolyte dosing pump for
each installed Dewatering Machine. Kindly review and confirm.
Refer C&A No. 6, Sl. No. 38
344) Vol-2, Section
XI, Part 2
206 2.36 All piping of the Dosing System - Polypropylene. All the clauses are contradicting with each other. We assume that, the Dosing pipeline
shall be selected as per Table provided in Page No. 340
Please confirm.
Refer C&A No. 6, Sl. No. 52
345) Vol-2, Section
XI, Part 2
206 Part 2 – Plant &
Process
Requirements
2.37 Sludge Drying Beds. Sludge drying beds shall be provided for
10% quantity of the daily sludge produced which will store
dewatered sludge before disposal or as a backup dewatering facility
in the event of unavailability of the mechanical dewatering system for
any reason (page 206). Since the drying beds have either the function
of storing dewatered sludge (at 25% DS) or backup dewatering of
digested sludge (at 4% DS)
Please clarify whether the 10% requirement applies on the quantity of dewatered
sludge (at 25% DS) or digested sludge (at 4% DS). Also, 10% of daily quantity seems
very low, because the storage capacity or backup dewatering capacity will be much
less than a single day
As per bid document
346) Vol-2, Section
X1, Part 2
207 2.38.1 Electrical Specification
MCC-3(Installed in Sludge Treatment MCC Room for sludge de-
watering units
Location of Sludge treatment MCC room is not available in proposed layout, kindly
indicate the same in proposed layout plan.
As per bidder‟s design
347) Vol-2, Section
XI, Part 2
207 Clause 2.38.2 Plant Water Pumps Is it acceptable to use a pumping set with a number of pumps operating according to
the actual load?
As per bid document
348) Vol-2, Section
XI, Part-2
209 2.38.4 The contractor shall design and construct suitable fire fighting system
along with pump sets, fire hydrant shall be provided in the fire
fighting pump house
The locations of Fire Hydrants are as per System Design. Please confirm. Confirmed
349) Vol-2, Section
XI, Part-2
209
& 210
Fire fighting Please specify which code has to be followed for designing the fire-fighting system. As per bid document
350) Vol-2, Section
XI, Part-2
209
& 210
Fire fighting Please mention the units inside STP for which firefighting system (hydrants) have to be
provided.
All Buildings, Pump Stations,
Panel Rooms shall be
provided with Fire Hydrant
system. 351) Vol-2, Section
XI, Part-2
209
& 210
Fire fighting Please specify the capacity of the fire fighting sump. As per bidder‟s design
352) Vol-2, Section
XI, Part-2
210 Clause 2.38.5 Treated Water Tanker Filling Station Please provide a detailed scope for tanker filling station with details of area required
for operator room, tanker paved area details etc.
Refer C&A No. 6, Sl. No. 39
353) Vol-2, Section
XI, Part-2
210 SCADA Control
Room -
“Heat Load of Building shall be considered as 1 TR per 40 m3 building volume.”
We assume that this is the solar load to be considered for the buildings in calculation of
Confirmed
62
Ventilation cooling requirement. Please confirm.
354) Vol-2, Section
XI, Part-2
210 Plant & Process
Clause 2.38.5
We presume that we need not include the power consumption of Tanker Filling Station
in the Power Guarantee. Please confirm.
As per bid document
355) Vol-2, Section
XI, Part-2
210 Plant & Process
Clause 2.38.5
For treated effluent tanker filling station, please provide the quantity of effluent to be
supplied and also operating hours every day in each filling station to calculate the
capacity of pump and to calculate the power consumption.
Refer C&A No. 6, Sl. No. 39
356) Vol-2, Section
XI, Part-2
210 2.38.5 Effluent Tanker Filling Station Kindly confirm the maximum number of Tankers required to be filled at the same time
at the Tanker Filling Stations.
Refer C&A No. 6, Sl. No. 39
357) Vol-2, Section
XI, Part-2
210 2.38.5 Effluent Tanker Filling Station Kindly confirm the capacity and type of pumps to be provided for the Treated effluent
tanker filling station.
Refer C&A No. 6, Sl. No. 39
358) Vol. 2 212 In plant road Kindly clarify the scope of in plant road of subject project. As per bid document 359) Vol. 2 212 Hydro-Power Plant Request to provide level difference for outfall structure for power generation. Refer hydraulic flow diagram
drag no YAP-
III/R2/P/HFD/002(T).
Bidders to verify the levels
from site. 360) Vol-2, Section
XI, Part-2,
Vol-2, Section
XI, Part 4
212
&
305
Clause 2.40
Clause 4.2.9
Micro-Hydro Power Plant
As per these clauses, bidders are to supply and install a micro-hydro
power plant of 37 KW capacity.
Please advise the preferred names of the Vendors/Manufacturers of Micro-Hydro
Power Plant.
The reputed makes will be
allowed with prior approval
of Engineer.
361) Vol. 2 212 2.41 Public Address System No. of hand set units with location distributed inside WWTP, are to be mentioned to
make uniform to all bidders
Refer C&A No. 6, Sl. No. 40
362) Vol 2 –
Section XI –
Vol 4
212 Part 2 / Clause
2.42.1.1
Drawing No :
YAP-
III/R2/P/GAD/00
1 (T) – Rev R
Existing Roads
All existing roads in the plant are bituminous roads and the contractor
shall repair the same and re-carpet with a final bituminous finish coat
as per CPWD specifications.
We presume that, the repair and rehabilitate of existing road (9.0m wide) length of
around 860m between the Phase I and Phase II as per Vol 4 – Drawing No : YAP-
III/R2/P/GAD/001 (T) – Rev R0 are not in this scope of contract.
Please confirm.
It is in bidder‟s scope.
363) Vol 2 –
Section XI -
213 Part 2 / Clause
2.42.3
Storm Water Drains Storm water side drains shall be designed and
constructed only along one side of the internal roads. These drains
shall be covered with factory made perforated concrete covers.
We presume that, we will provide the storm water drain along one side for the new
road only. Please confirm.
As per bid document
364) Vol 2 –
Section XI -
213 Part 2 / Clause
2.42.3
Storm water Drains We presume that, the material of construction of the storm water drain shall be with
brick work upto a depth of 0.75m and RCC for greater than 0.75m depth as mentioned
in the Clause 3.4.9.4, Page 251, Part 3, Section XI, Vol 2. In addition bidder shall
provide the pipe drain also depending on the design requirements. Please confirm.
As per bid document
365) Vol 2 –
Section XI -
213 Part 2 / Clause
2.42.5
Cable and pipe Trenches We presume that, the cable outside the building shall be provided as buried cable.
Please confirm
As Per Bid Document.
366) Vol. 2 214 2.42.9 CCTV No. of Cameras with location distributed inside WWTP, are to be mentioned to make
uniform to all bidders
As per Bidder Design subject
to the Approval of Engineer-
In charge 367) Vol-2, Sec -XI,
Part-2 & 3
214
& 226
2.42.8, 3.3(iv)
& 3.4.9.5
Fencing, Gate & Security Room There is an ambiguity in regards to specification of chain link Fencing. Please confirm
that PVC Coated Chain link fencing will be acceptable.
As per bid document
368) Vol. 2
Section XI-
Part-2 : Plant
& Process
Requirements
221
&
487
2.38.6 SCADA
Control Room
cum Laboratory
Building
6.12.6.2
Peripheral
Subsystem
The Conference Room, Control Room, Plant Manager Room and
Staff Room for Management /Supervisors shall have the following
facilities (minimum):
d) Two UPS of size as directed by Engineer
1 No. of 10KVA UPS for Control room hardware
2 Nos. of 3 KVA UPS at all Remote Locations
Query 01 : Kindly clarify if the Two UPS mentioned in this clause correspond to the 2
nos. of 3 KVA UPS mentioned in the Instrumentation specification.
Query 02 : Kindly clarify the quantity of UPS as clause no 6.12.6.2 states 2 nos. of
3KVA UPS but "Hardware Component" column states that 3 KVA UPS at all Remote
Locations. Clause 2.38.6 calls for only supply of 2 nos. of UPS
As per bid documents.
Refer C&A No. 6, Sl. No. 76
369) Vol. 2
Section XI -
224 Part 3 / Clause
3.2.3
Design Conditions for Completely / Partly Underground Liquid
Retaining Structures
We presume that, the proposed water retaining structure shall be designed as per IS
3370 – 2009 Clause 4.4 by limit state method with allowable crack width of 0.2mm.
Please confirm
As per bid document
370) Vol-2, Sec –
XI, Part-3
224
3.2.3 (6)
Design conditions for completely/ Partly underground Liquid
Retaining Structures Water Table
Kindly provide the “Design Ground Water Table” Level to be considered in the design. As per bid document
63
371) Vol -2,
Part -3
225 3.2.4 PRV‟s for Structures. The Employer has allowed PRVs in most of its STPs in Delhi, whereas in this project,
PRVs are not allowed. We recommend PRVs should be allowed in this project also as
it will help in optimizing the cost of the civil structures. Please review and confirm.
As per bid document
372) Vol 2 –
Section XI -
227 Part 3 / Clause 3.3 Particular civil requirements
xxv. Outer surface of all RCC structures shall be painted with two or
more coats of water proof cement paint of make as approved by
Engineer in charge.
We presume that, this clause is applicable for outer surface of the water retaining
structure.
Please confirm.
Confirmed
373) Volume 2 230 Section XI Part 3,
3.4.2.1
Steel reinforcement bars are proposed as (Gr Fe 415/TMT 500 confirming to BIS code
1786-1985. However, it is indicated to carry out structural design based on FE 415.
If we use TMT 500 for actual construction, kindly clarify the need to carry out
structural design based on Fe 415.
Kindly request you to re-consider the statement given in NIT & allow us to carry out
structural design as per Fe 500 if TMT 500 is used for actual construction.
As per bid document
374) Vol-2,
Sec –XI
38. Part-3
230
3.4.2.1(i) General Civil Specification:
Use of Reinforcement for design
The Approved Manufacturers have discontinued the manufacturing of Fe 415 grade
reinforcement steel. We request to change the grade of reinforcement steel to Fe-500 in
design and construction.
It may be noted that when structures are designed for Fe-415 grade and Fe-500 grade is
used in actual construction, the designed section will behave as over-reinforced
sections, which is not a good engineering practice and the structure tends to fail
suddenly, as the structure loses its ductility. Hence, it is strongly recommended to
allow the use of Fe-500 grade reinforcement steel conforming to IS 1786 in design as
well.
Please review and confirm.
As per bid document
375) Vol 2, As-Built
drawings of
existing units.
251 3.5 Rehabilitation Work Kindly provide the As-built drawings of the existing structures to be retained /
rehabilitated, and/or demolished, to ascertain the actual status of the structures and the
quantum of the work required for proper work planning and pricing.
Bidders to verify from site
376) Vol 2 –
Section XI -
252 Part 3 / Clause
3.5.1
Rehabilitation Work
Requirements
NDT report(s) are available in the office of the EE(C) DR XI for
general information and guidance. The bidder can collect the copy of
the same in CD in PDF format from the office of the EE(C) DR XI.
Please provide the NDT report. As per bid document.
377) Vol. 2, Section
XI, Part-4,
270 Clause 4.2.1.7 Screen Washing System
1. The Contractor shall supply and install spray washing system that
effectively cleans the screen area and screening press. The
Contractor shall provide a high-pressure clean water supply for the
washing system.
2. As per Clause No. 4.2.1.4, Fine Screens can be either movable bar
type or perforated band type.
Please note that the spray washing system is ok and workable for perforated band
screens but for movable bar screens (Multi-Rake type), Spray washing is not workable.
Please arrange to modify this clause stating that Spray washing system shall be
required for perforated band screens only.
As per bid document
378) Vol. 2, Section
XI, Part-4, Sub
clause e)
284
& 285
Clause no. 4.2.5
Diffusers
Tender Clause states -
“Diffuser membranes - Silicon membrane with laser drilled holes
Please confirm the MOC of Diffuser Refer C&A No. 6, Sl. No. 28
379) Vol-2, Section
XI, Part-4
285 4.2.5 1. A) Stainless steel (SS 316) Drop Legs.
Stainless steel (SS 316) Air Distribution Header.
We assume that, Air header from Air Blower to Aeration tank shall be SS 316, We led
pipe, 10 S or as per Design Thickness.
Please confirm.
Refer C&A No. 6, Sl. No. 52
380) Vol-2, Section
XI, Part-4
285 4.2.5 Diffuser Fouling Factor for Retrievable type Diffusers A very conservative Fouling Factor of 0.9 is specified for Retrieval type Diffusers. It
will result in an under-design of the Aeration System (Process Air Blower, Diffusers),
and frequent replacement of the Diffusers during plant operation. In the STP Projects
in India and abroad, the typical value is from 0.7 to 0.8. Hence, we suggest that instead
of 0.9, a suitable value between 0.7 to 0.8 should be specified for the design Fouling
Factor for Retrievable type Diffusers. Kindly review and confirm.
Refer C&A No. 6, Sl. No. 28
381) Vol. 2,
Section XI,
Part-4
285 Clause 4.2.5 Diffusers
d) Maximum air to diffusers
Tender Clause states –
i) Disc Type - 60 m3/m2 of membrane area
Please confirm if these values are m3/m2/hr. Confirmed
64
ii) Tubular Type - 45 m3/m2 of membrane area
382) Vol-2, Section
XI, Part-4
286 Mechanical works
Clause 4.2.5
1-A-xxi
In clause 4.2.5 it is mentioned that type and number of diffusers are left to bidder
design and in the same clause two type of diffuser provided as options i.e Retrievable
type and Fixed type.
In Clause 4.2.5 point no 1 – A – xxi, contractor has to provide details of a suitable
lifting method to remove the banks of diffuser for maintenance.
The above two clause are contradicting, we assume that the bidder can choose the type
and number of diffuser as per bidder design. Please confirm.
Refer C&A No. 6, Sl. No. 28
383) Vol-2, Section
XI, Part-4
288 4.2.5 1. C) An on-line cleaning system shall be provided as an option to allow
for cleaning of diffusers without taking aeration system off-line.
The arrangement of on-line cleaning system shall be as per Bidder's Design.
Please confirm.
As per bid document
384) Vol-2, Section
XI, Part-4
292
&
295
Clause 4.2.8.1
Clause 4.2.8.6
Chlorine booster pumps - 6 Nos. (4W+2S)
Chlorination system
Tender Clause states -
“Bidder shall design the complete chlorine dosing system (with 100%
standby)”
Booster pumps
Tender Clause states -
“Booster pumps shall be required on the motive water supply system
to the ejectors. At least 4 pumps (2 duty + 2 standby) shall be
furnished.”
Refer C&A No. 6, Sl. No. 45
Refer C&A No. 6, Sl. No. 46
385) Vol-2,
Section :XI,
Part-4
296 4.2.8.7 Chlorine Gas
(Vacuum Regulator To Ejectors): 80CPVC 700mbar
Vacuum Gauges
Chlorine Solution
(Ejectors to Dosing Points):80CPVC 15kg/cm²
Pressure Gauges
We assume that, the pipe line shall be CPVC, Sch 80.
Please confirm.
As per bid document
386) Vol-2, Section
: XI, Part-4
311 4.2.12, Point no. 5 Interconnecting Pipe works The polymer pipe work shall be stainless-steel and valves shall be PP ball valves. As per bid document
387) Vol-2,
Section : XI,
Part-4
311 4.2.13 All gas mixing pipe work shall be designed and installed in
accordance with best practices with velocities kept below 10m/sec on
the low pressure side and 20m/sec on the high pressure side to assist
condensate removal and pressure drop reduction
Please note that, the Bio-gas will get condensed, if the line velocity exceeds more than
6.0 m/s. We assume that, we shall be design the Bio-gas pipe lines with the velocity of
3.5 to 6.0 m/s.
Please confirm.
Refer C&A No. 6, Sl. No. 52
388) Vol. - 2,
Section –XI
313 4.2.14 Bio Gas Holder Kindly provide the GA drawings of the existing biogas holder, or at-least details like
diameter, height etc.
Bidders to verify from site
389) Volume-2
Section:X1,
Part 4
Electrical
Specification/
315 4.2.17.1 It is proposed to generate maximum possible power out of the
available sewage gas by using highly efficient gas generators. The
power generated from Power Plant will be used for In-house
consumption of the Sewage treatment plant equipment.
We understand that the synchronized output of bio gas engine will be used primarily
for the plant supply and rest of the plant will be fed by TPDDL power supply; kindly
confirm.
Confirmed
390) Volume – 2
Section XI
Part-4
315 &
322
4.2.17.1 Minimum capacity of each gas genset at alternator terminals shall be
1000 KW x 3 nos. (2 working + 1 Standby)
It is proposed to operate all the 3 nos. generators in parallel.
These two clauses are contradictory.
Please clarify.
Refer C&A No. 6, Sl. No. 50
391) Vol. 2,
Section XI,
Part-4
316 Clause 4.2.17.1 Biogas engine
4. Main components
Tender Clause states- Single cylinder head made of special cast iron
with four valves…
Please note that the Single Cylinder head valve design shall be as per manufacturer‟s
standard.
Please confirm your acceptance.
Refer C&A No. 6, Sl. No. 48
392) Vol-2,
Section XI-
Part 4
316 4.2.17.1
Point -4
Biogas Engine While a total of 7 Vendors are specified for Single Fuel Gas Engines, the tender
specification requiring “Biogas Engines shall have single cylinder head made of
special cast iron with four valves” is specific to a particular Supplier, and shall limit
the choice and Competition. We suggest the Gas Engines with two valves should also
be allowed. Kindly review and revise the same.
Refer C&A No. 6, Sl. No. 48
393) Vol. 2,
Section XI,
317 Clause 4.2.17.1 Biogas engine
5. Alternator
We understand that these clauses are applicable for static operations only, please
confirm.
As per bid document
65
Part-4 Tender Clause states-
Assembled engine and generator shall be operated under the
following conditions;
Ø Momentary speed variation shall not exceed at 10% in no time
Ø Normal speed variation shall not exceed 5%
Ø Recovery time shall be within 10 seconds
394) Vol. 2,
Section XI,
Part-4
317 Clause 4.2.17.1 Biogas engine
5. Alternator
Tender Clause states-
Each engine shall be provided with following components;
1. Rotating meters, thermometers & flow meters
2. Anchor bolts
1. Regarding Rotating meters bidder's understanding is indication of engine RPM and
same shall be displayed on graphic display screen of gen set control panel but not
through rotating meter. Pl confirm.
2. Anchor bolts are not required for engine/ gen set
Confirmed
Refer C&A No. 6, Sl. No. 49
395) Volume 2,
Section -XI,
Part 4
317 Cl. 4.2.17.1 Bio‐Gas Engines
5. Alternator
Alternator shall be connected with flexible power cable for power evacuation.
Kindly confirm, from alternator to LV switchboard shall be used copper flexible power
cables. Also confirm bidder should consider copper flexible power cables only for the
bio-gas generator alternator of this tender scope.
As per bid document
396) Vol. 2,
Section XI,
Part-4
318 Clause 4.2.17.1 Biogas engine
6. Engine body
Tender Clause states-
Common bed shall provide with shock prevention device and its
stoppers
Bed / Base frame shall be as per manufacturer standard design and sylomer strips shall
be used as anti-vibration device.
Please confirm your acceptance.
As per bid document
397) Vol. 2,
Section XI,
Part-4
318 Clause 4.2.17.1 Biogas engine
6. Engine body
Tender Clause states-
Total vibration value at common base on duty shall not be exceeded
0.3 mm measured by axial and horizontal direction respectively.
Total vibration of gas gen set shall be within allowed limits of manufacturer and the
same will be as per relevant international standard.
Please confirm your acceptance.
As per bid document
398) Vol. 2, Section
XI, Part-4
318 Clause 4.2.17.1 Biogas engine
6. Engine body
Tender Clause states-
Crankshaft and impeller shaft shall be made by grade AA forged steel
Material of crankshaft and impeller shaft shall be as per manufacturer standard design.
Please confirm your acceptance.
As per bid document
399) Vol. 2,
Section XI,
Part-4
318 Clause 4.2.17.1 Biogas engine
6. Engine body
Tender Clause states-
Combustion system shall provide with air filter, gas carburetor, spark
plugs and air compressor
We understand this as mixture (air and Fuel gas) compressor instead of air compressor.
Please confirm.
Confirmed.
400) Vol. 2,
Section XI,
Part-4
318 Clause 4.2.17.1 Biogas engine
8. Cooling
Tender Clause states-
The engine shall have a high temperature cooling circuit for jacket
cooling water and for this complete required arrangement i. e. flame
proof electric motor driven pumps for HT and LT circuits, pipe work,
valves and fittings etc. are to be provided.
Pump in the HT cooling circuit shall be engine driven. Pump in LT cooling circuit
shall be part of imported supply (from manufacturer) and the same shall be with Non-
flame proof standard electric motors as this is manufacturer's standard.
All fittings, valves, pipe work and motors of imported supply i.e. gen set shall be Non-
flame proof type.
Please confirm your acceptance.
As per bid document
401) Vol. 2,
Section XI,
Part-4
318 Clause 4.2.17.1 Biogas engine
7. Lubrication
Tender Clause states-
A full-flow filter having a pressure operated by-pass valve shall be
provided on the delivery side.
As per manufacturer‟s standard design full flow lube oil filter without by-pass valve
will be provided.
Please confirm your acceptance.
As per bid document
402) Vol-2
Sec XI-Part 4
318 4.2.17.1
Point -4
Biogas Engine The tender specifications that “crankshaft & propeller shaft shall be made by grade AA
forged steel” is not the Standard Specification of most of the Manufactures of Single
Fuel Gas Engine listed in of approved Vendors. Kindly confirm that Manufacture‟s
Standard Specifications will also be acceptable.
As per bid document
403) Vol. 2,
Section XI,
Part-4
319 Clause 4.2.17.1 Biogas engine
12. Wiring
Tender Clause states-
1. Please note that the design of cables and cubicles for the engine shall be as per
manufacturer's standards. Pl confirm acceptance.
2. Please note that Standard / Documents HD 21.1 S4:2002 and HD 22.1 S4:2002 are
As per bid document
66
Engine-mounted wiring shall be insulated with heat resistant
insulation to CENELEC Harmonization Documents HD 21.1
S4:2002 and HD 22.1 S4:2002 and associated parts thereof for use at
temperature of up to 85 Deg C. Conductor shall be multi-strand
copper of minimum cross-sectional area 1.5 mm2 excepting special
types such as screened cables.
expired on 17/01/2014.
3. Some manufacturer's complies with CENELEC HD 21.13, CENELEC HD 21.7 and
CENELEC HD 22.
4.Please confirm your acceptance.
404) Vol. 2,
Section XI,
Part-4
319 Clause 4.2.17.1 Biogas engine
13. Pipe Work
Tender Clause states-
Fuel piping work shall be produced from seamless steel tubing with
welded or compression type steel fittings. All other pipe work shall
be either seamless copper tubing with brazed or compression type
gunmetal fitting or seamless steel tubing with welded or compression
type steel fittings. ……. Flexible fuel and lubricating oil connections
shall additionally have flame resistance sleeves. All pipe flanges shall
comply with BS 4504-3.3:1989 and screwed connections with BS
21:1985.
1. Please note that all pipe work on the engine (imported supply) shall be as per
manufacturer‟s standard design.
2. Provision of additional flame resistance sleeves for fuel and lube oil connections,
shall be as per manufacturer's standard.
Please confirm your acceptance.
As per bid document
405) Vol. 2,
Section XI,
Part-4
321 Clause 4.2.17.1 Biogas engine
17. Engine Management
Tender Clause states-
The Engine Management System shall generally include display and
processing of the following values on the generating set.
- Inlet water inlet
- Outlet water outlet
- Combustion Chamber temperature for each cylinder
- Crankcase pressure
Please note that some manufacturer's standard design do not have crank case pressure
value display and processed as they provide closed loop blow by system.
Please confirm your acceptance.
As per bid document
406) Vol 2, Section
XI Part-4
322 Do . 18 It is proposed to operate all the 3 nos. generators in parallel. These two clauses are contradictory.
Please clarify.
Refer C&A No. 6, Sl. No. 50
407) Vol. 2,
Section XI,
Part-4
323 Clause 4.2.17.1 Biogas engine
19. Design of power generation and distribution systemTender
Clause states-Synchronization both “Automatic” and “Manual”
synchronization facilities shall be provided.
As per manufacturer‟s standard design facility for “Manual” synchronization is not
provided. However, facility for manual initialization of synchronization is provided.
Please confirm your acceptance.
As per bid document
408) Volume 2
Section XI
Part-4
323 Clause 4.2.17.1 Biogas engine
19. Design of power generation and distribution system
Tender Clause states –
Protections: -
…………… for software based protection, software and
programming devices for the system shall be provided free-of cost to
the Client.
Please note that Gen set control and protection software and it‟s programming is a
proprietary item and as per manufacturer‟s policy programming devices for these
software is not provided to client. Programming of this software is done during the
commissioning of the gas gen sets by certified engineers under commissioning
services.
Please confirm your acceptance.
As per bid document
409) Vol-2,
Section : XI,
Part-4
339 4.2.19 Pipe (Pressurized Lines) Common Header pipeline from Air Blower
to Aeration Tank - DI K 9
We assume that, Air header from Air Blower to Aeration tank shall be SS 316, We led
pipe, 10 S or as per Design Thickness.
Please confirm.
Refer C&A No. 6, Sl. No. 52
410) Vol-2,
Section : XI,
Part-4
339 4.2.19 Bio Gas piping velocity shall be 8 -10 m/s (desirable). Please note that, the Bio-gas will get condensed, if the line velocity exceeds more than
6.0 m/s. We assume that, we shall be design the Bio-gas pipe lines with the velocity of
3.5 to 6.0 m/s.
Please confirm.
Refer C&A No. 6, Sl. No. 52
411) Vol-2,
Section : XI,
Part-4
339 4.2.19 Pipe Sizing & Material : Basis velocity Criteria. The water velocity in the suction branches of a pump shall not exceed 1.5m/s, delivery
1.8 m/s for horizontal pumps and in the discharge branch shall not exceed 2.1 m/s for
submersible pumps when the pump is operating within its specified working range.
Kindly confirm
Refer C&A No. 6, Sl. No. 52
412) Vol-2,
Section : XI,
Part-4
340 4.2.19.4 Stainless Steel Pipes
All gas pipes, fittings and other related components inside the
digester shall be of stainless steel SS- 316.
As the clauses are contradicting with each other, we assume that, Bio-gas piping from
Digester to Bio-gas holder shall be DI K9 Class.
Please confirm.
Refer C&A No. 6, Sl. No. 52
67
413) Vol-2,
Section : XI,
Part-4
345 4.2.19, Point no.
8
Butterfly Valve:- Unless otherwise specified, valve body and disc
shall be of close-grained grey cast iron. Valves shall be mounted with
shafts horizontal
Please note that, the type of Shaft either Horizontal or Vertical, is based on
Manufacturer's Design.
Please confirm.
Confirmed
414) Vol-2,
Section : XI,
Part-4
345 4.2.19, Point no.
8
We assume that, all the Butterfly Valves above 600 mm shall be
provided with Electrical Actuator.
We assume that, all the Butterfly Valves above 600 mm shall be provided with
Electrical Actuator.
Refer C&A No. 6, Sl. No. 53
415) Vo-2,
Section - XI,
Part-5
364 5.1 Valid Electrical Contractor‟s License The Contractor of such STP projects usually sub-contracts the Electrical Works to the
specialist Electrical Sub-contractors having valid Electrical License of appropriate
Class. Hence, we understand that the stated requirement of Electrical Contractor‟s
License is applicable to the Electrical Sub-contractor, as has been the practice in DJB,
and not to the Contractor of the STP Project. Please confirm.
Refer C&A No. 6, Sl. No. 55
416) Volume-2
Section:X1,
Part 5
365 Electrical
Specification
5.1.1
11kV dedicated duplicate power supply is available at site at BSES
metering panel.
Kindly provide the location of BSES metering panel to consider the dismantling of HT
cables from metering panel to HT switchgear
Bidder to verify from site
417) Volume 2,
Section -XI,
Part 5
365
&
368
5.1.1 Power Supply Information, 5.1.2 Design Criteria for Electrical
Equipment/ System & SLD
Refer to clause 5.1.1 indicated 3phase, 3 wire 11 kV system fault Level 350 MVA
(Minimum) & page 368, CL.5.1.2 indicated the values of fault level for designing the
electrical system shall be based on transformer capacity, its impedance and system
fault level. But whereas in SLD indicated for HV side I/C VCB 16kA & O/G VCB
26.2kA. Kindly confirm which clause fault level to follow bidder for designing the
electrical system.
Refer C&A No. 6, Sl. No. 89
418) Volume-2
Section:X1,
Part 5
Electrical
Specification
366 5.1.2 Efficiency of Motors : As per Manufacturer‟s Catalogue (Energy
efficient eff3)
(Energy efficient, high performance motors (eff3 category) shall be
provided for optimum utilization of energy).
We understand that the given class (EFF3) is a typo-graphical error. Kindly confirm
that as IE3 or clarify
Confirmed
419) Volume-2
Section:X1,
Part 5
Electrical
Specification
368 5.1.3 Majority of the electrical equipment such as switchgear, HT cables,
and lighting installation are required to be replaced. Sufficient details
by way of tentative Bill of Quantities for installation items such as
cables, lighting fixtures, lighting DBs, cable trays etc. have been
furnished.
Tentative BOQ is not available with the tender specification, kindly provide the same. Refer C&A No. 6, Sl. No. 56
420) Volume-2
Section:X1,
Part 5
Electrical
Specification
368 5.1.3 The scope also includes cabling, lighting, earthing and lightning
protection installation for the all the three phases of the plant.
Kindly clarify the scope of work involved, as it is mentioned that electrical works such
as cabling, lighting, earthing and lightning protection installation for all the three
phases to be taken care. In that case, provide the details of all the three plants
requirement like rehabilitation of existing plant, replacement of existing electrical
works etc.
Refer C&A No. 6, Sl. No. 56
421) Volume 2,
Section -XI,
Part 5
368 5.1.3 System Description and scope As per tender SLD. DRG.NO. YAP- III/R2/E/SLD/001 (T) the 11kV indoor
switchboard both incomers are normally closed & bus coupler is normally open so that
both distribution transformers shall provide 2x100% capacity to cater load on PMCC-1
& PMCC-2 with developing necessary interlock logics and Bio gas power generation
is a primary source shall be suitable for parallel operation. Kindly confirm
Refer C&A No. 6, Sl. No. 89
422) Volume-2
Section:X1,
Part 5
Electrical
Specification
369 5.1.3 All the dismantled equipment shall be properly packed suitable for
transport and storage for a long time, transported to and stored at
DJB‟s designated store.
Kindly indicate the location of DJB‟s designated store to calculate the transportation
charges.
Refer C&A No. 6, Sl. No. 57
423) Volume-2
Section:X1,
Part 5
Electrical
Specification
369 5.1.3 All the dismantled equipment shall be properly packed suitable for
transport and storage for a long time, transported to and stored at
DJB‟s designated store.
We understand that the responsibility of the bidder is upto transporting and storing the
existing electrical equipment in the designated location. The security / protection of the
stored equipment will be in client's responsibility. Kindly confirm.
Refer C&A No. 6, Sl. No. 57
424) Vol. 2 370 5.2.2 HT panel of Phase-II Location of HT panel of Phase-II or HT cable length from New HT panel of Phase-I to
HT panel of Phase-II is to be specified.
Bidders to verify from site
425) Volume-2
Section:X1,
370 5.2.2 Supply, laying , testing and commission of 11 KV (E) of adequate
size and length of cables, Aluminum conductor, XLPE insulated, GI
Kindly provide the distance between HT Panel of Phase-I to HT Panel of Phase-II to
consider the cables.
Bidder to verify from site
68
Part 5
Electrical
Specification
strip armoured cables between HT Panel of Phase-I to HT Panel of
Phase-II.
426) Volume-2
Section:X1,
Part 5
Electrical
Specification
370 5.2.2 All the dismantled cables shall be recovered after excavation, wound
on Bidder supplied wooden drums, transported and stored at DJB's
designated store.
Kindly provide the existing cable schedule and existing cable routing drawings to
estimate the wooden cable drums requirement.
Bidder to verify from site
427) Volume-2
Section:X1,
Part 5
Electrical
Specification /
370 5.2.2 Supply, laying , testing and commission of 11 KV (E) of adequate
size and length of cables, Aluminium conductor, XLPE insulated, GI
strip armoured cables between HT Panel of Phase-I to HT Panel of
Phase-II.
Kindly provide the demand of Phase-II to size the rating of 11kV breaker and the 11kV
cable.
Bidders to verify from site
428) Volume-2
Section:X1,
Part 5
Electrical
Specification
370 5.2.5 Dismantle Existing 415 V Main Lighting Distribution Board During our site visit, we have not found any MLDB in the plant, kindly clarify. Bidder to verify from site
429) Volume-2
Section:X1,
Part 5
Electrical
Specification
370 5.2.1 Dismantle 5-panel existing switch boards located at Sub Station
Phase-I transporting and storing them to DJB designated store.
We found one more 1-panel switchboard feeding to phase-II other than the mentioned
5-panel during our site visit, kindly clarify whether the dismantling of 11kV 1-panel is
to be considered in the scope of bidder or not.
As per bid document
430) Volume-2
Section:X1,
Part 5
Electrical
Specification
370 5.2 Scope of work In existing substation building (PMCC-I), we have seen metering panels and other
11kV breaker panels during our site visit, kindly clarify whether these panels have to
be dismantled or not.
As per bid document
431) Vol-2 ,
Sec-V
&
Vol-4
(SLD)
370 5.2.1 (ii)
&
SLD-
III/R2/E/BD/002(
T) Rev: R0
11 kV Switchgear For Phase-II Power Supply, the existing 11 kV, 5 nos. Panel board has 2 nos.
Incomers, and the electric power is directly fed from the Metering Panel of TPDDL.
However, now in the tender, only one no. Outgoing feeder feeding 11 kV power to the
Phase-II plant is mentioned. Please clarify how the power consumption of Phase- I & II
shall be independently measured.
As per bid document
432) Volume 2
Scope Of
Work
370 5.2 Dismantled Electrical Material of Phase-I Please specify the location and/or the road distance between Rithala Site and
designated DJB Store for the Bidders to estimate the cost of transportation of the
dismantled electrical items of Phase-I.
Refer C&A No. 6, Sl. No. 57
433) Volume-2
Section:X1,
Part 5
Electrical
Specification
371 5.2.6 Installation, Testing and commissioning of Local Push Button
Stations mounted near to all the proposed motors. The starters for all
the motors shall be housed inside the LT switchboards installed at
various locations.
Kindly provide the details of LPBS like Type, Material of construction, degree of
protection, etc.
Refer C&A No. 6, Sl. No. 59
434) Volume-2
Section:X1,
Part 5
Electrical
Specification
SLD for
Rithala WWTP
phase-I
371 5.2.5
YAP-
III/R2/E/SLD/001
(T)
Supply, Installation, testing and commission of 415 V Inlet works
control Panel for controlling the driven equipment located on the
Inlet works considering the load proposed by bidder.
415V Inlet works control panel
Kindly clarify from which 415V panel the 415V inlet works control panel is getting
incoming power supply, since the same is not shown in the tender SLD, also clarify the
no. of incoming feeders considered for 415V Inlet works control panel
Primary Treatment MCC-1
shall feed the power to Inlet
work control panel.
435) Volume-2
Section:X1,
Part 5
Electrical
372 5.2.11 All the existing LT cables are in physically bad conditions and most
of the cables are required to be replaced and all the dismantled cables
shall be recovered after excavation, wound on Bidder supplied
wooden drums, transported to and stored at DJB's designated store.
Kindly provide the cable schedule and cable routing drawings of existing plant to
estimate wooden drums requirement to wind the excavated cables.
Bidders to verify from site
69
Specification
436) Volume-2
Section:X1,
Part 5
Electrical
Specification
372 5.2.11 All the existing LT cables are in physically bad conditions and most
of the cables are required to be replaced and all the dismantled cables
shall be recovered after excavation, wound on Bidder supplied
wooden drums, transported to and stored at DJB's designated store.
Kindly provide the existing cable schedule and existing cable routing drawings to
estimate the wooden cable drums requirement.
Bidder to verify from site
437) Volume-2
Section:X1,
Part 5
Electrical
Specification
372 5.2.11 All the existing LT cables are in physically bad conditions and most
of the cables are required to be replaced and all the dismantled
cables shall be recovered after excavation, wound on Bidder supplied
wooden drums, transported to and stored at DJB's designated store.
Excavation of earth and removing existing cable without knowing the cable routing is
very difficult, kindly provide the existing cable routing , cable schedule details and the
SLD with the Cable rating to identify the excavation cable BOQ.
Bidders to verify from site
438) Volume 2 372 Section -XI, Part
5,
5.2.10 Cable
Trays
Dismantle all the rusted, outdoor cable trays at all the various units of Phase I in the
plant.
Kindly confirm dismantling of substation / switchgear room cable trays.
As per bid document
439) Volume-2
Section:X1,
Part 5
Electrical
Specification
373 5.2.12 Dismantle all the existing 30V DC battery and battery charger located
at various locations and shall be transported to DJB designated store.
During our site visit, we have not found any 30V DC battery and battery charger in the
plant, kindly clarify where these mentioned existing 30V DC system is located and
provide the quantity of the same to include in the dismantling works.
Bidder to verify from site
440) Volume 2 374 Section -XI, Part
5,
5.3 Specification
Of Electrical
Equipment‟s &
5.3.1 Power
Transformers
Technical parameters of the transformer indicated percentage impedance voltage shall
be as per IEC/BIS.
Kindly note that as per IEC60076-5, page.13, Cl. 3.2.2.4, Table 2, for example
2500kVA transformer rating the percentage impedance voltage is 6% and IS2026 also
same 6%, but whereas BIS1180 latest amendment the percentage impedance voltage is
6.25%. Hence kindly confirm which standard bidder to comply.
As per bid document
441) Vol-2,
Section-XI,
Part-5
375
&
379
5.3.1.1
&
5.3.1.7
Type of Tap Changer for Transformers The type of Tap Changer for Transformers specified at these pages is contradictory.
Please confirm the requirement.
As per bid document
442) Volume 2
Section : XI,
PART 5 -
Electrical
Specifications
383 5.3.2.1 Circuit
Breaker
Separate limit switches, each having a minimum of 2 „NO‟ + 2 „NC‟
contacts, shall be provided for both „Service‟ and „Test‟ positions of
the circuit breakers for future SCADA.
Kindly clarify "Future SCADA" mentioned in the clause. We understand that 'future
SCADA" is excluded from the scope of supply in this project.
Refer C&A No. 6, Sl. No. 61
443) Vol. 2 395 I -Motor Method of Starting i.e. Starter for motors Correction is to be made as under -
a. Star-Delta starter for 7.5KW & above up to 55KW
b. Soft starter for 75Kw & above rating.
As per bid document
444) Volume 2
Section XI,
Part 5,
395 General
Clause I :Motors
Irrespective of motor kW rating, the nominal operating voltage of the motors shall be
415V AC 50Hz. Kindly confirm
As per bid document
445) Volume 2
Section : XI,
PART 5 -
Electrical
Specifications
396 I.MOTORS Motors shall have space heaters suitable for 230 V, single phase 50
Hz AC supply. These shall be placed in easily accessible positions in
the lower part of motor frame. Provision shall be made to measure
temperature of bearing by inserting hand held temperature measuring
device.
Kindly specify from which motor rating space heater to be considered. Refer C&A No. 6, Sl. No. 62
446) Volume 2 398 II-Soft Starter –I
(b)
By pass Arrangement Inbuilt By pass shall be provided. Pl confirm. As per bid document
447) Volume 2
Section : XI,
PART 5 -
Electrical
Specifications
398 II. SOFT
STARTERS FOR
LV MOTORS
b) shorting (bypass) arrangement Kindly specify the type of bypass arrangement required for soft starters. Refer C&A No. 6, Sl. No. 63
70
448) Volume 2 400 III-Capacitor
panel/capacitor
Type of capacitor insulation All Poly Propylene APP Type or Mixed dielectric type Pl confirm. As per bid document
449) Volume 2 400 Section -XI, Part
5,
III. Capacitors
And APFC Panel
Technical parameters of the capacitors indicated control supply 110V DC.
Kindly confirm the requirement since it is not included in Vol-2, Sec. XI, Part5,
Cl.5.2.12, 110 V DC battery chargers along with distribution board required to control
of all 11 kV and 415V circuit breakers.
Capacitor control panel
control supply is 110 V AC
however control supply for
other panel shall be as per bid
specification. 450) Volume 2 400 Section -XI, Part
5,
III. Capacitors
And APFC Panel
MV capacitors shall be provided for connection across MV motor terminals.
We understand that there is no MV motors part of this tender, hence MV capacitor not
to consider bidder.
As per bid document
451) Volume 2 404 Section -XI, Part
5,
V. LV Indoor
Switchboard
LV indoor switchboard degree of enclosure protection indicated IP-5X, enclosure
thickness for frame – 2.5,
Doors/Covers – 2.0 but whereas page 382, Cl.5.3.2, MV (11 KV) indoor switchboard
& page 401, Sr.no.4, APFC capacitor panels constructional requirement indicated IP-
4X, enclosure thickness of cold rolled sheet steel for Frame – 2.0 &Doors/Covers –
2.0.
Refer C&A No. 6, Sl. No. 60
452) Vol. 2 405 V- LT
SWITCHBOARD
Type of Motor starter –Draw out or fixed Motor starter will be fixed or draw out type.
Pl confirm.
Refer C&A No. 6, Sl. No. 64
453) Volume 2
Section : XI,
PART 5 -
Electrical
Specifications
406
V. LV INDOOR
SWITCHBOARD
Motor protection circuit breaker (MPCB) shall be used for motor
feeder instead of MCCBs.
From the clauses we understand that MPCB can be used for motor ratings upto 3.7kW
and MCCB for ratings above 3.7kW.
Confirmed
454) Volume 2 406 Section -XI, Part
5,
V. LV Indoor
Switchboard, Sr.
No. 2. Moulded
Case Circuit
Breaker (MCCB)
MCCB shall be suitable for remote On-Off-Trip operation. Necessary spare auxiliary
contacts (minimum 2NO+2NC) shall be provided for future use.
We understand that ACB/MCCB/MCB is not applicable for remote ON/OFF control
from PLC. Also confirm the requirement of ON/OFF/TRIP/L_R feedback status of the
all these circuit breakers for remote monitoring from PLC.
Kindly confirm
As per bid document
455) Section : XI,
PART 5 -
Electrical
Specifications
411 VII. VARIABLE
FREQUENCY
DRIVES (VFD)
1. General
All frequency dives shall be suitable for data connectivity with
PLC/SCADA system and shall have suitable communication port and
protocol.
Kindly clarify the protocol to be adopted for the communication interface between
variable frequency drives and the PLC/SCADA system
As per bid document
456) Volume 2
Section XI,
Part 5,
417 VIII. Lighting
System
Equipment
Sr.no. 2. Lighting
Fixtures and its
Accessories
Street Lighting:
Page 417- Operation & Maintenance manual under general requirements, Sr.no. 2.
Lighting Fixtures and its Accessories indicated Suitable type and rating of solar
operated lighting fixtures with LED lamps shall be used. System shall be hybrid type to
facilitate the charging facility at the event of non-sunny days. Refer to page 413, VIII.
Lighting system equipment in broad performance specifications indicated autonomy 3
days or minimum 42 operating hours per permissible discharge. Even though bidder
should consider hybrid charger type
As per bid document
457) Volume 2
Section : XI,
PART 5 -
Electrical
Specifications
419 VII. LIGHTING
SYSTEM
EQUIPMENT
6.Water Coolers
General
Water cooler shall conform to IS 1475/78 with latest amendment
suitable for operation on 230 volts ±10%, 50 cycle‟s single phase AC
supply. It shall be supplied with hermetically sealed type suction
cooled compressor with overload protection conforming to IS 10167.
It shall have cooling capacity of 40 liters per hour with storage
capacity as 80 liters. Water coolers shall be required for site office.
Two nos. water coolers shall be installed and make them in operation.
Kindly clarify & provide the details of the requirement for water cooler in detail
mentioned in the specification.
As per bid document
458) Volume 2
Section : XI,
421 XI. CABLING
SYSTEM
Where groups of HV, LV and control cables are to be laid along the
same route, suitable metallic barriers to segregate them physically
Kindly clarify the requirement since it is not clear. Refer C&A No. 6, Sl. No. 66
71
PART 5 -
Electrical
Specifications
INSTALLATION shall be DJB or their representative.
459) Volume 2
Section : XI,
PART 5 -
Electrical
Specifications
421 XI. CABLING
SYSTEM
INSTALLATION
CABLING SYSTEM INSTALLATION We understand from the tender specification that the cables inside the electrical rooms
/ sub stations will be laid in cable trenches and cables in outdoor areas will be directly
buried with necessary mechanical protections. Kindly confirm.
As per bid document
460) Volume-2
Section:X1,
Part 5
Electrical
Specification
421 XI. CABLING
SYSTEM
INSTALLATION
Cable installation in outdoor areas shall be carried out in
directly buried cable trenches where RCC trench will not be
possible.
All cables in outdoor areas will be laid in directly buried cable trenches. Kindly
confirm.
As per bid document
461) Volume 2 428 Section -XI, Part
5,
X I. Non-
segregated Phase
Bus Duct
The enclosure shall conform to IP: 55 for outdoor and IP: 54 for indoor.
Whereas all HV, LV & capacitor switchboards suitable for indoor installation with
degree of enclosure protection is IP40 mentioned in the specification clauses as per
query Sr.no.8. Kindly confirm the bus duct degree of protection for indoor portion.
As per bid document
462) Vol-2,
Section-XI,
Part-5
428 XI Non-Segregated Phase Bus Duct The material of Busbar mentioned under sub-clauses 1 & 2 is contradictory. Please
confirm the requirement.
Refer C&A No. 6, Sl. No. 67
463) Volume-2
Section:X1,
Part 5
Electrical
Specification /
430 XII. MICRO -
HYDRO POWER
PLAN
MICRO - HYDRO POWER PLANT Kindly clarify, under what condition hydro electric power generated to be used for
plant like critical or standby or parallel operation.
Refer C&A No. 6, Sl. No. 89
464) Volume 2 430 Section -XI, Part
5,
XII. MICRO-
Hydro Power
Plant, Sr.no.2.
Scope of Works
Grid Synchronization Works:
Synchronization of generated power at main LT panel of the Plant.
Bidder required clarity on this clause of requirement whether the generated power is to
be connected with power grid (i.e. Power evocation at power grid) or the generated
power shall be utilized as stated like Bio-gas power generation as primary source shall
be utilized for the plant.
Refer C&A No. 6, Sl. No. 89
465) Volume 2
Section XI
Part-5
430 Cl-XII.1 It is estimated that a discharge of 182 MLD at a head of 2.5 m
approximately will be available to generate 37 kW of power.
Please confirm the head for turbine. Turbine efficiencies will differ as per the head
available. Since LD is applicable on guaranteed output, head should be fixed.
As per bidder‟s design
subject to the approval of the
Engineer in charge
466) Volume 2 436 Section XI Part 5,
Technical
specifications-
Hydro Turbines -
Output and
Efficiency
Guarantee for
Turbine
Generator Set
“The efficiencies of the generator and turbine at rated head at 100% & 50% or
minimum output shall be guaranteed.”
We request to modify this clause. The efficiencies and other details of the equipment
can be furnished during detailed engineering.
Refer C&A No. 6, Sl. No. 69
467) Volume 2
Section XI
Part-5
436 (Output &
Efficiency)
The efficiency of the generator & turbine at rated head at 100 % &
50% or minimum output shall be guaranteed.
do Refer C&A No. 6, Sl. No. 69
468) Volume 2
Section XI
Part-5
436 (Output &
Efficiency)
The bidder shall have to produce test certificate for typical turbine of
their make in the past by any independent laboratory inclusive of
their own regarding performance/efficiency of turbines and related
equipment devices offered by bidder.
Test certificates for the typical turbine offered may be submitted during project
execution before approval of the drawings/designs. Please confirm.
As per bid document
469) Volume-2 440 XII. MICRO - Synchronisation Panel As per the clause solar generated power is not clear and it is understood Client will be Refer C&A No. 6, Sl. No.89
72
Section:X1,
Part 5
Electrical
Specification
HYDRO POWER
PLANT
One swing type synchronization panel shall be provided. The
synchronization panel shall be used for synchronization of triple units
(Hydro generated power, solar generated power and grid power at
415 V LT side of transformer) in future.
responsible for providing the solar generated power, kindly confirm and provide the
details of solar power generated.
470) Volume 2 440 Section -XI, Part
5,
XII. Micro-
Hydro Power
Plant
Synchronisation Panel:
One swing type synchronization panel shall be provided. The synchronization panel
shall be used for synchronization of triple units (Hydro generated power, solar
generated power and grid power at 415V LT side of transformer) in future.
No clarity on requirement of this clause, however we understand that there is no solar
power generation except solar street lighting. Kindly confirm the requirement this
clause.
Refer C&A No. 6, Sl. No. 70
471) Volume 2 441 Section -XI, Part
5,
XIII. Preliminary
Details To Be
Submitted With
Bid
We understand from this clause the data, engineering calculations, transformers losses,
etc., to be submitted by bidder as a preliminary details & during detailed design bidder
shall be confirmed the actual requirement of the plant. Kindly confirm
As per bid document
472) Volume-2
Section:X1,
Part 5
Electrical
Specification
442 XIV. SPECIFIC
SPECIFICATIO
N-E&I WORK /
5.3.15.1
MPCB of adequate rating and KA capacity shall be used for motors
rated up to 3.7 Kw.
From the clauses we understand that MPCB can be used for motor ratings upto 3.7kW
and MCCB for ratings above 3.7kW.
Confirmed
473) Volume-2
Section:X1,
Part 5
Electrical
Specification
442 XIV. SPECIFIC
SPECIFICATIO
N-E&I WORK /
5.3.15.1
Incomer rating of LT Panels /MCCs shall be selected considering
total running load +50% standby load+ 10% spares load and
additional 15% capacity of the calculated capacity.
Generally, incomer rating of LT Panels will be selected based on transformer
secondary current rating. kindly confirm.
As per bid document
474) Volume-2
Section:X1,
Part 5
Electrical
Specification
442 XIV. SPECIFIC
SPECIFICATIO
N-E&I WORK /
5.3.15.1
Incomer rating of LT Panels /MCCs shall be selected considering
total running load +50% standby load+ 10% spares load and
additional 15% capacity of the calculated capacity.
Generally running loads of the plant only will be considered for electrical equipment
sizing and standby loads will not be considered. Kindly confirm.
As per bid document
475) Volume-2
Section:X1,
Part 5
Electrical
Specification
442 XIV. SPECIFIC
SPECIFICATIO
N-E&I WORK /
5.3.15.1
Incomer rating of LT Panels /MCCs shall be selected considering
total running load +50% standby load+ 10% spares load and
additional 15% capacity of the calculated capacity.
Kindly clarify the mentioned 10% spares load i.e. 10% of the total working load or
10% of the connected load.
Refer C&A No. 6, Sl. No. 71
476) Volume-2
Section:X1,
Part 5
Electrical
Specification
442 XIV. SPECIFIC
SPECIFICATIO
N-E&I WORK /
5.3.15.1
Incomer rating of LT Panels /MCCs shall be selected considering
total running load +50% standby load+ 10% spares load and
additional 15% capacity of the calculated capacity.
Kindly clarify what is meant the calculated capacity mentioned in "15% capacity of the
calculated capacity"
Refer C&A No. 6, Sl. No. 71
477) Volume-2
Section:X1,
Part 5
Electrical
Specification
442 XIV. SPECIFIC
SPECIFICATIO
N-E&I WORK /
5.3.15.1
Transformer
a. Transformer ratings shall be considered based on the total load
(Motor load+ Lighting load+ HVAC load). In addition to that 20%
margin shall be considered for contingency.
We understand that the motor load mentioned here is running / working load only.
Kindly confirm that the maximum demand will be calculated based on the running load
only.
Confirmed
478) Volume-2
Section:X1,
Part 5
Electrical
Specification
442 XIV. SPECIFIC
SPECIFICATIO
N-E&I WORK /
5.3.15.1
11. Vendors have to check the adequacy of the existing substation
buildings at Substation-I.
Kindly confirm if the existing sub-station is not adequate to accommodate the
proposed electrical equipment, bidder shall be allowed to construct or extend the
existing substation building and all other electrical rooms.
Confirmed
479) Volume 2 442 Section -XI, Part
5,
Minimum size of power cable shall be 2.5 sq. mm copper conductor or 6 sq.mm
Aluminium conductor cable.
As per bid document
73
XIV. Specific
Specification–
Electrical &
Instrumentation
Work, 5.3.15.1
General
Kindly note that majority of cable manufactures have minimum copper power cable
size is 4Sq.mm, less than 4Sq.mm shall be control cable with solid core.
480) Volume 2 442 Section -XI, Part
5,
XIV. Specific
Specification–
Electrical &
Instrumentation
Work, 5.3.15.1
General
HT panel shall be suitable for 11KV, 500 MVA (26.2 kA for 1 Sec) whereas page 365,
CL.5.1.1 for power supply information mentioned connection 3 phase, 3wire 11 kV
system fault Level 350 MVA(Minimum).
Kindly confirm.
Refer C&A No. 6, Sl. No.89
481) Volume 2
Section : XI,
Part - 6
Instrumentatio
n and
Automation
Specifications
445 6.1 General The plant data collected through online monitoring of water quality
and flow shall be displayed locally where the instrument is installed
and also transferred to the PLC / SCADA control room. The data
shall also be made available via the internet to various statutory
bodies / locations.
Query 01: We understand that the data collected through online monitoring water
quality and flow - refers to the quality and flow parameters at Plant inlet and Plant
outlet only. Kindly clarify
Query 02: Kindly clarify the number and details for the various statutory
bodies/locations where the Data has to be made available via the internet.
As per bid document
Refer C&A No. 6, Sl. No. 72
482) Volume 2
Section : XI,
Part - 6
Instrumentatio
n and
Automation
Specifications
451 6.5 Design
Requirements for
Control And
Instrumentation
Systems (C&I)
The installation arrangements for meters measuring conductivity, pH,
and dissolved oxygen, chlorine residual and ionic concentration shall
include a sample bench and other facilities for operating portable test
meters. Each installation shall incorporate a valve and pipework for
obtaining a sample representative of the fluid at the position of the
permanent meter, tundish and drain.
We understand that analysers can be located in field and the arrangements of sample
bench and other facilities for operating portable test meters , tunish , pipework etc. are
not applicable for in field installations of conductivity, pH , Dissolved Oxygen,
Chlorine residual and ionic concentration , Turbidity analysers. However such
arrangements shall be provided in the Laboratory. Kindly confirm if understanding is
correct.
As per bid document
483) Volume 2
Section : XI,
Part - 6
Instrumentatio
n and
Automation
Specifications
451 6.5.1 Instrument
Design Criteria
As far as possible and depending upon the location and availability of
wireless services (GPRS / GSM, etc.), all transmitting instruments
and data loggers shall be of wireless type. In case of non-feasibility,
the output of the transmitting instruments shall be 4-20 mA / 0-10V
DC linear having two wire system.
a) All instruments such as Pressure Transmitter, Level transmitter, Flow transmitters
etc shall communicate to the Control centre (i.e. control room) through hardwired 4 -
20mA signal only.
b) All pH Analyser, Conductivity, DO Analyser etc shall communicate to the Control
centre (i.e. control room) through hardwired 4 -20mA signal only.
c) All special analyser (BOD, COD, TSS etc.) shall communicate to the control centre
(i.e. control room) though hardwired 4 -20 mA signal only.
d) The control system shall have GPRS facility to communicate with third party
system.
Confirmed
Confirmed
Confirmed
Confirmed 484) Volume 2 451 Section : XI, Part
6,
6.5.1 Instrument
Design Criteria
As per referred clause 6.12.1, All online monitoring analyzer data transfer shall be
through wireless communication to control center. As per our system architecture we
are providing RIO Based Panel at every specified location, which will be transmitting
the data through high end optical fiber cable.
Kindly amend the field Instruments wireless data transfer to wire type data transfer up
to control center.
Refer C&A No. 6, Sl. No.75
485) Vol-2 ,
Section –XI,
Part -6
451
&
456
6.5.1 On-line Instrument We understand that the Bidder is responsible for the Supply of the On-line Instruments
as listed in the Table (On-Line Instrument) starting page no. 452, whereas the
parameter in Cl. 6.6, Table-2 which are not covered by the Online Instruments
provided as per the Table referred above shall be analyzed in the plant laboratory..
Kindly review and confirm.
Refer C&A No. 6, Sl. No. 73
486) Volume 2 452 Section : XI
Part 6
We assume that only list of instruments specified in the table has be continuously
online monitored. Please Confirm.
Refer C&A No. 6, Sl. No. 73
74
Instrumentation
Clause 6.5.1
Some of the analyzer such as COD, Oil and grease and total phosphorous analyzers
may not be required. Since it does not have any impact on process control. Please
confirm.
487) Volume 2 453 Section XI
Part 6
Instrumentation
Clause 6.5.1
As per this clause electromagnetic flow meter to be provided in the common header of
Primary Sludge Pump and inlet to sludge thickener.
These 2 flow meter are in the same line which may not be required. We assume that
the flow meter shall be considered for inlet of anaerobic digester (i.e From thickened
sludge sump common header line to anaerobic digester) instead of inlet of sludge
thickener. Please confirm.
Refer C&A No. 6, Sl. No. 73
488) Volume 2 453 Section XI
Part 6
Instrumentation
Clause 6.5.1
In NIT, the requirement of flow-meters is not mentioned for the following lines:
(i) Inlet to digesters
(ii) Discharge of centrifuge feed pump
(iii) Discharge of polymer dosing pump
Please clarify whether same shall be required or not.
Refer C&A No. 6, Sl. No. 73
489) Vo-2,
Section-XI,
Part-6
471 6.9 Cabinets for Field Instruments Cabinets of Die-cast material are specified. Kindly note that Non-metallic Cabinets
made of FRP / Duopolistic etc. suitable for outdoor installation are also available,
which are also more suitable for the corrosive atmosphere in the STP. Hence, we
suggest only Non-metallic Cabinets made of FRP / Duopolistic etc. should be allowed.
Refer C&A No. 6, Sl. No. 74
490) Vol-2 ,
Section-XI,
Part-6
487 6.12.6.2
UPS UPS is specified to be designed with 2 hrs. back up time. However, considering that
Gas Engine shall be operational and will provide the additional backup during power
failure, we recommend UPS with upto 1 hour backup. Please confirm.
Refer C&A No. 6, Sl. No.76
491) Volume 2
Section : XI,
Part - 6
Instrumentatio
n and
Automation
Specifications
497 6.12.7.12 PLC (1
No.)
5. Input / Output
Devices
All the I/O modules shall have max 8 channels for the Analog and 16
channels for the Digital modules.
With wide experience in Water and Wastewater treatment we suggest use of 32
channel digital modules, 16 analog input modules and 8 channel analog output
modules. This will ensure efficient control room space utilization and shall provide
cost benefit.
This will be sufficient for the safe and reliable operation of the plant. Kindly confirm
your acceptance.
Refer C&A No. 6, Sl. No. 77
492) Volume 2
Section : XI,
Part - 6
Instrumentatio
n and
Automation
Specifications
500 6.13.7
System
Architecture
The system should be capable of Remote I/O modules architecture at
various remote locations near to the major equipment sensors to
reduce the commissioning. There will be two remote I/O module
stations. Please refer the Annexure 1 & 2 of the system architecture.
The Clause states that there will be two remote I/O module stations whereas the
Annexure -1B# -PLC Distribution in Plant (General Arrangement) , there are 10 nos.
Remote I/O PLC.
Query 01 : Please clarify the required quantity of remote I/O modules.
Query 02 : We understand that Remote I/O Station refers to panels only with I/O
modules and communication module which communicate to a centrally located
processor/controller module . Please clarify if this understanding is correct or should
remote I/O station have processor/controller module in the same panel.
Query 03 : Please clarify if each process area should be supplied with a redundant PLC
or can process areas be supplied with Remote I/O Modules which will communicate to
a Central PLC.
As per Bidder Design subject
to the Approval of the
Engineer-In Charge.
Bidder understanding is
correct.
Each process area needs
Remote I/Os modules for
communicating to Central
PLC. 493) Volume 2 514 Section : XI, Part
6,
6.25
ANNEXURES
We presumed that RIO System Architecture Annexure A is tentative; The same shall
be designed as per the system requirements.
System architecture is
indicative however bidder
have to submit the same as
per their own design which
will be subject the Approval
of Engineer In- charge 494) Volume – 2,
Section : XI,
Part 7
550 7.16 Test on Completion Kindly confirm the duration of the following Tests on Completion:
- Manual Commissioning Tests (cl. 7.16.2)
- Manual Operation Test (cl 7.16.3)
- Automatic Commissioning Tests (cl. 7.16.4)
As per bid document
75
- Dry Test (cl. 7.17)
- Hydraulic Wet Test (cl. 7.18.1)
- Performance Test (cl. 7.19)
For Performance Test -Refer
C&A No. 6, Sl. No.78 495) Vo -2,
Section : XI,
Part-7
555 7.1 Performance Test Kindly provide Technical Schedule Section IV, Part-1 as referred in this section. Refer Part-9 of Volume-2 of
bid document
496) Vo -2 , Section
: XI, Part-7
555 7.1 Performance Test Kindly confirm the duration (as number of days) for the Performance Test. Refer C&A No. 6, Sl. No. 78
497) Vol. 2, XI
Technical
Specifications
556 Operation and
Maintenance
Treated Sludge Disposal
The contractor shall operate the Waste Water Treatment Plant such
that the sludge produced is of a spade-ale consistency and the volume
of sludge produced after treatment specified, is minimum. The sludge
generated from the WWTP shall be disposed of by the contractor to a
proper landfill site, or other sites as directed by the Employer. The
digested Excess Sludge disposal shall be identified by the bidder.
We understand during Interim O&M period sludge disposal land shall be provided by
DJB free of cost. All statutory approvals shall be taken by DJB. Kindly confirm.
Refer Clause 8.1.4 (iii) at
page 562
498) Vol. 2,
XI Technical
Specifications
559 Operation and
Maintenance
Operating and Maintaining the plant with the existing equipment‟s
after necessitating repair as that may be necessary to keep them in
service for a period X months ii) Operating and Maintaining the plant
with liquid stream of the rehabilitated and upgraded plant along with
the necessary repair and maintenance including the effect on the
upgraded equipment‟s “total life” for a period of Y months.
We request client to provide the flow record for last 2 years and also the Sewage and
treated sewage Analysis report for last 2 years to enable the bidders to understand the
plant performance.
Bidders to visit site and
obtain required details
499) Vol. 2,
Section XI -
Technical
Specification
561 Output and
Operational
Guarantee
The contractor is fully responsible for treating all the sewage
reaching at the inlet chamber. The performance of the contractor shall
be treated as non-compliance if the treated effluent does not meet
with the guarantees listed under this clause unless in Force Majeure
condition
We understand the contractor shall be responsible of treating the design Sewage
quantity and the excess flow shall not be taken for treatment. Pls confirm
As per bid document.
500) Vol. 2,
Section XI -
Technical
Specification
561 Output and
Operational
Guarantee
The contractor is fully responsible for treating all the sewage
reaching at the inlet chamber. The performance of the contractor shall
be treated as non-compliance if the treated effluent does not meet
with the guarantees listed under this clause unless in Force Majeure
condition
We presume if the inlet flow is above than the Design (excess flow) contractor shall
not be liable to achieve the Treated effluent Quality as give in Vol2, Section XI
Technical Specifications, Part 8 - Operation and Maintenance, Page 556 Pls confirm.
As per bid document.
501) Vol. 2,
Section XI -
Technical
Specification
561 Output and
Operational
Guarantee
The contractor is fully responsible for treating all the sewage
reaching at the inlet chamber. The performance of the contractor shall
be treated as non-compliance if the treated effluent does not meet
with the guarantees listed under this clause unless in Force Majeure
condition
We understand the excess chemical, Electricity cost shall be borne by the Employer
when the flow is excess than the design flow when it reaches the inlet chamber. Kindly
clarify.
As per bid document.
502) Vol. 2
XI Technical
Specifications
562 Operation and
Maintenance
Sludge Disposal
The contractor shall operate the Waste Water Treatment Plant such
that the sludge produced is of a spade-ale consistency and the volume
of sludge produced after treatment specified, is minimum. The sludge
generated from the WWTP shall be disposed of by the contractor to a
proper landfill site, or other sites as directed by the Employer. The
digested Excess Sludge disposal shall be identified by the bidder.
We understand that the Employer will provide the Sludge Disposal Land free of cost
with required statutory approval.
Refer Clause 8.1.4 (iii) at
page 562
503) Volume 2
Section XI,
Part 8
562 The contractor shall operate the Waste Water Treatment Plant such
that the sludge produced is of a spade-ale consistency and the volume
of sludge produced after treatment specified, is minimum. The sludge
generated from the WWTP shall be disposed of by the contractor
within plant premises as directed by the Employer‟s Representative.
As we understand that the operation period is for 10 years. The land provided in the
plant premises is feasible for 10 years sludge disposal. If not Employer shall provide
the approved landfill site for sludge disposal. Kindly confirm
As per bid document
504) Vol. 2 562 Sludge Disposal During interim O&M period the effluent parameter to be achieved are given in referred
clause. Please furnish the old O&M reports to substantiate the effluent quality.
Bidders to verify records
maintained at Phase-I plant
site. 505) Volume-2
Part-8
562 Sludge Disposal
- In the event of the landfill/ SDB not sufficient during Operations & Maintenance of
plant, additional ready to dispose site/ location/ space with all statutory approvals and
As per bid document
76
8.1.4 iii) preparations shall be provided by Employer. At such an event contractor shall only be
responsible for disposal of sludge to the new designated area at an additional mutually
decided cost if the distance of new disposal area is more (if any) than the current
disposal site from the WWTP plant.
506) Vol. 2,
XI Technical
Specifications
563 Operation and
Maintenance
Treated Sludge Disposal
The contractor shall operate the Waste Water Treatment Plant such
that the sludge produced is of a spade-ale consistency and the volume
of sludge produced after treatment specified, is minimum. The sludge
generated from the WWTP shall be disposed of by the contractor to a
proper landfill site, or other sites as directed by the Employer. The
digested Excess Sludge disposal shall be identified by the bidder.
Please provide the disposal Land Distance from the STP. Refer Clause 8.1.4 (iii) at
page 562
507) Vol. 2
XI Technical
Specifications
564 Operation and
Maintenance
Treated Sludge Disposal
The contractor shall operate the Waste Water Treatment Plant such
that the sludge produced is of a spade-ale consistency and the volume
of sludge produced after treatment specified, is minimum. The sludge
generated from the WWTP shall be disposed of by the contractor to a
proper landfill site, or other sites as directed by the Employer. The
digested Excess Sludge disposal shall be identified by the bidder.
Is there any dump fees to be considered during Operation and Maintenance sludge
Disposal. If yes request to provide the fees.
Refer Clause 8.1.4 (iii) at
page 562
508) Volume 2
Section XI,
Part 9
577 All costs related to handling and disposal of the by-products,
including but not limited to license application, transportation, tests
and treatment shall be borne by the Contractor and deemed to be
included in the Operation Fees
We understand that all the duping fee, licence for disposal in approved landfill site
shall be borne by Employer. Kindly confirm.
All such fee shall be borne by
the bidder
509) Volume II
Sludge
Disposal
Volume-2;
Part -8
577 Handling &
Disposal of Waste
Water Treatment
By Product
As per Clause 8.2.8: Handling & Disposal of Waste Water Treatment By- product,
Page 577 of tender document it is mentioned that Provision of sufficient vehicles
throughout the Operation Period to transport the by-products from the Facility to the
landfill site for disposal.
We request the department to kindly provide us the distance of sludge disposal site
from the proposed STP site.
We also understand there is no additional charges/royalty to be paid for the disposal of
sludge to disposal site. Kindly confirm.
If it includes any royalty charges, Kindly mention the price of disposal/MT of sludge to
bring all the bidders at par.
As per bid document
510) Volume 2
Section XI,
Part 8
584 The stock level of spare parts shall be sufficient for 2 years operation
from the date of Handover Certificate.
Kindly confirm the handover spares at the end of O&M period is for 2 years or 4 years. Refer C&A No. 6, Sl. No. 15
511) Vol. -2,
Sec-XI, Part -9
608 9.8 Mechanical Data Sheets The evaluation criteria that “DDE” and “as per manufactures standards” written in the
Bidders Technical schedules would essentially be taken as non-responsive, is
unjustified at the Bid Stage. It is to be noted that the Tender Data sheets are extremely
exhaustive requiring a lot of data which is not critical for evaluation at the bid stage in
a DBO Contract, and which can be more realistically and reliably provided during the
detailed engineering with the committed inputs from the Vendors. It is not possible to
generate such exhaustive data for the data sheets in a short span of bid stage. Also,
changes in the data sheet during the detailed engineering as per the actual design and
vendor inputs will become difficult.
Hence, we request that such a criteria for the bid evaluation should be deleted from the
tender. If any critical information / data is not provided in the bid which is hampering
the fair evaluation, the same may be requested from the Bidder as a part of the Post-
Bid Clarifications. Kindly review and confirm.
As per bid document
512) Vol.-2 613 10.1 Make of equipments
Triveni Engineering & Industries Ltd. is a reputed make for manufacturing &
supply of Mechanical equipment‟s such as Screen, Grit mechanism, Clarifier,
Thickeners, Agitator & Mixers, Belt filter press/Combi unit and DAF etc.
As per bid document
77
We request you to add Triveni to Approved make‟s list.
List of installations & Supply are attached to vouch our credentials.
513) Vol-2, Sec-XI,
Part-9
680 Power Guarantee Power consumption/generation has to be considered for 10 years (Jan-Dec).
Please provide the flows on a yearly basis which have to be considered for
guaranteeing the power consumption/generation.
As per bid document
514) Vol-2, Sec-XI,
Part-9
680 Section XI
Part 9
Technical
Schedule
Clause 9.10
Please provide month and year wise sewage flow for 10 years to calculate the year
wise power consumption and power generation from biogas.
As per bid document
515) Volume 2
Section XI
Part-9
681 (Power
Guarantee)
The Bidders offer shall be evaluated on Net Guaranteed Power only We understand that Net Guaranteed power will be calculated as below-
P = Total Power Consumption – Power Generation from Bio gas – Power Generation
from Hydro Plant. Please confirm.
Confirmed.
516) Volume 2
683 Section XI
Part 10,
List of Approved makes
Kindly add “Passavant Energy & Environment” in the make list for Anaerobic
digesters and gas mixing system. PE&E has experience in the installation of more than
1,500 digesters & mixing system worldwide.
As per bid document
517) Volume 2 683 Section XI
Part 10,
List of Approved makes
Majority of the approved makes doesn‟t include various reputed makes in the market
which are currently active and supplying in various STP‟s. Kindly allow that makes
equivalent to the mentioned makes can be considered by bidder.
As per bid document
518) Vol. -2 683 Sec- XI Tertiary Treatment Filter makes Makes of filters specified in Sl. 13, 26 & 27. We request you to allow other equivalent
makes except of this.
As per bid document
519) Vol. 2
683
695
Section XI List of Approved Makes :- for Mechanical There are few vendors shown under „Approved make‟ for supply of various
equipments required for proposed STP. Since bidder has to operate & maintain the
facilities for 10 years , it is requested to let the bidder select make of equipment
considering its continuous performance for longer period. This will help in selecting
and providing reliable equipment which requires less maintenance during O & M
period. Else kindly incorporate „ HNB‟ make equipments which are approved by water
supply & sanitation dept. of Govt. of Maharashtra ( MJP) for various process
equipments like mechanical & manual( coarse& fine) screens, degritings, mixers,
agitators, aerators. Belt conveyors Non clog pumps, thickeners, decanters , clarifier,
Penstock gates , filter pumps etc. to assure trouble free maintenance of process
equipment.
As per bid document
520) Volume 2 683 Section 11, Part
X, List of
Approved Makes
We wish to highlight that the approved makes are not exhaustive and can include some
more reputed firms. Hence we request to include „equivalent‟ which can be approved
by Engineer In Charge during detail engineering.
As per bid document
521) Volume 2
Section XI
Part-10
683 (Approved
makes)
Makes for Bar Screen, Screening Conveyance
Compaction and Dewatering
We request to add following suppliers in the approved make list for these items –
1. Triveni Engineering & Ind Ltd, Noida
2. GMW Pvt Ltd, Baroda
As per bid document
522) Vol. 2 683 Section XI
Part 10
Make as Approved Manufacturer We request you to add the name of the following manufacturer / make as Approved
Manufacturer.
a. Centrifuge M/s. GEA Westfalia Separator India Pvt. Ltd.
b. Chlorination System M/s. Chloro Tech Equipments Pvt. Ltd.,
c. Process Equipment like M/s. Shiv Pad Engineers Pvt. Ltd.- Jash
Clarifier, Thickener,
Screen, Grit Mechanism
d. Membrane Filter M/s. Inge GmBH, Germany.
e. Submersible Mixer M/s. Xylem ( Make : FLYGT )
f. Submersible Pump M/s. Kishor Pumps Pvt. Ltd.,
As per bid document
78
g. Centrifugal Turbo Blower M/s. TurboMAX
523) Section XI – 683 Part 10 – List of
Approved Makes
List of Approved Makes for Mechanical Equipment. Please
clarify whether vendors are strictly limited to those listed or whether
proposed equivalent vendors can be approved during the course of
evaluation of the Technical Bid.
Please kindly confirm. As per bid document
524) Volume-2
General Buildings constructed under contract The buildings i.e. Administrative building, work shop etc. constructed under contract
will be allowed for use of contractor during O & M period without any extra cost.
Please confirm
Confirmed if these new
buildings are constructed
under this contract
525) Date of submission Kindly extend date of submission by 3-4 weeks after receipt of prebid reply. Refer C&A No. 5
526) Vol. 2 - - Scope of Work Being a rehabilitation work kindly clarify the extent of repair of the existing civil
structures that are to be retained as specified in bid document, confirm. Further note
that existing structures that are retained, civil specifications shall be as constructed at
the time of project implementation whereas new specs will be used for new
construction/rehabilitation works of repaired structures.
As per bid document
527) Vol. 2 - - Disposal points. Confirm, disposal land/ area will be provided free of cost by DJB.
Provide the point & distance of disposal point for excavated earth as well as dumping
of demolished structures material.
As per bid document
528) Vol. 2 - - Work Permit Work permit for Subcontractor to execute work on site would be given by Delhi Jal
Board. Kindly confirm.
As per bid document
529) Vol. 2 - - Labour Placement Kindly provide the location for labor hutment. Also provide distance of tapping point
of water & electricity from site, please mark al 3 in project plan.
Bidders to visit site and
verify
530) Vol. 2 - - In Plant Road Kindly specify the scope of in plant road. As per bid document
531) Vol. 2 - - Out fall Structure Provide the drawing for outfall structure with levels to plan hydro power generation. Refer hydraulic flow diagram
drag no YAP-
III/R2/P/HFD/002(T).
Bidders to verify the levels
from site.
532) -
Volume-2
- - General The distance of dumping site of civil structures demolition waste from proposed STP
site
As per bid document
533) General
Volume-2
- - HT / LT motor limits Kindly provide the HT & LT motor segregation to design HT & LT panels.( i.e. Upto -
-kW in LT and above in HT)
As per bid document
534) General
Volume-2
- - Spare requirement Kindly provide the details of spare capacity to be considered in the 11kV Switchgear
panel feeders, 415V LV Panels outgoing feeders, cable trays, conduits, hume pipes,
trenches etc.
Refer C&A No. 6, Sl. No. 71
535) General
Volume-2
- - Existing plant details Kindly provide the details of existing electrical drawings to consider the rehabilitation
works appropriately.
Bidder to verify from site
536) General
Volume-2
- - DG set requirement We understand from the tender specification and SLD that DG set is not required for
the plant, kindly confirm.
Refer C&A No. 6, Sl. No.89
537) General
Volume-2
- - MCC Type We understand that MCCs in this project are conventional MCCs and are not
Intelligent MCCs. Kindly confirm
As per bid document
538) General
Volume-2
Rehabilitation of existing structures We presume that, the bidder shall not provide any guarantee on structural parts of the
Rehabilitated units as they are existing structures and rehabilitation works will be
carried out as per details prescribed in
Price schedule A3.
Please confirm.
As per bid document.
539) General
Volume-2
- - Variability of Throughput: In the event the Sewage Flow to the
system is Higher than and/or adversely high than the Design Limit of
181 MLD in Phase I and 181 MLD in Phase II, the same shall be
If the Employer insists the contractor to treat the excess flow we understand the
additional chemical cost to treat excess flow shall be compensated by the employer.
As per bid document.
79
intimated to client.
540) General
Volume-2
- - Variability of Throughput: In the event the Sewage Flow to the
system is higher than and/or adversely high than the Design Limit of
181 MLD in Phase I and 181 mld in Phase II, the same shall be
intimated to client.
If the Employer insists the contractor to treat the excess flow we understand contractor
shall not be responsible to achieve the Design Parameters as per guarantee during that
period of treating excess flow.
Refer SLA Section XV, Page
732, Volume -3
541) General
Volume-2
- - Variability of Throughput: In the event the Sewage Flow to the
system is higher than and/or adversely high than the Design Limit of
181 MLD in Phase I and 181 mld in Phase II, the same shall be
intimated to client.
For a sustained period of higher throughput from the facility, the contractor shall be
allowed to frame and submit the proposal and Employer and the contractor shall
mutually agree and implement the same.
As per bid document.
542) NA
Volume-2
NA NA Load list of existing plant Kindly provide us the load list section wise for the existing plant to understand the
working philosophy of phased manner interim operation for the electrical system.
Bidders to verify from site
543) NA
Volume-2
Part-2
NA NA
2.38.1
Extension of existing electrical Buildings Kindly clarify if the electrical buildings can be extended if the existing dimension is
not sufficient to accommodate the proposed electrical equipment.
As per bid document
544) NA
Volume-2
NA NA Dimension of existing electrical equipment in the existing buildings Kindly provide us the dimensions of existing electrical equipment in the existing
buildings as some of the buildings were in closed condition during the site visit.
Bidders to verify from site
545) NA
Volume-2
NA NA Power supply to the Phase 2 Kindly confirm that the contractor Is not responsible for providing supply to the Phase
2 plant till the installation of new HT panel and HT cables.
As per bid document
546) NA
Volume-2
NA NA Existing MCC room near Digesters During the site visit we found an electrical room inside the digester area which is not
shown in the tender layout. Kindly clarify.
Refer C&A No. 6, Sl. No. 17
547) NA
Volume-2
NA NA PLC & SCADA system- Existing We understand that the existing plant does not have a PLC & SCADA system for
control and monitoring of the plant. Kindly confirm.
Confirmed
548) Volume-2
Section-III-A
Evaluation
Criteria
Please provide the O&M NPV discount rate which will be considered for evaluation. Refer C&A No. 6, Sl. No. 3
549) Volume-2
Section-III-A
Evaluation
Criteria
Please provide the Price Adjustment Formula for O&M period. Refer C&A No. 6, Sl. No. 3
550) Volume 2
General Please confirm the availability of the proposed land for the 182 MLD WWTP works
for the contractor from the first day.
It is an existing WWTP
551) Volume 2
General Please confirm whether Excise Duty exemption is applicable or not. As per bid document
552) Volume 2
General Please confirm that the Environmental Clearance for the entire duration of contract is
in Employer‟s Scope.
As per bid document
553) Volume 2 Gener
al
Section XI Part 2,
Disposal Point
Please mention the distance of the Nangloi supplementary drain from the Rithala-Phase
I STP Campus.
Bidders to verify from site
554) Volume 2
General Please provide the Dimension and MOC of all existing isolation gates, Pipe and Valves
which has to replaced/rehabilitated.
Bidders to verify from site
555) Volume 2
General Please provide the present outlet quality of treated water for the following parameters
1. pH
2. BOD 5
3. COD
4. TSS
5. Oil and Grease
6. Ammonia – Nitrogen (NH4 – N)
7. Dissolved Phosphate
Bidders to verify from site
556) - Volume 2
- General – Pile
foundation
Please confirm us if there are any existing structures within the WWTP phase-1 with
pile foundation.
If yes, please furnish the depth of pile below ground level. This will be helpful for
Bidders to verify from site
80
structures which has to be dismantled completely.
557) - Volume 2
- General –
Boundary wall
We presume that existing boundary wall is sufficient for the plant. However, fencing
will be provided between phase 1 & phase 2 plant.
Kindly specify if any additional scope is there for boundary wall. If yes, please furnish
MOC for the same.
As per bid document
558) - Volume 2
- General Please furnish the electrical equipment lay out of the Existing PMMC-1 switchgear
room.
Bidders to verify from site
559) - Volume 2
- General Please furnish the existing 11KV/0.433 KV transformer room dimensions with clear
Height.
Bidders to verify from site
560) - Volume 2
- General Please furnish the Existing 11 KV HT Panel (5 panel) room dimensions with clear
height.
Bidders to verify from site
561) - Volume 2
- General Please furnish the Existing 11 KV HT Panel (5 panel) room dimensions with clear
height.
Bidders to verify from site
562) - Volume 2
- General Please furnish the existing cable routing from 5 Panel 11KV HT VCB to 11/0.433 KV
Transformer and then PMCC-1
Bidders to verify from site
563) General
Volume 2
ROW/ROU We understand that the entire ROU / ROW, is the scope of the client. The Contractor
will be provided clear ROW. Please provide ROU/ROW width
Bidders to verify from site
564) General
Volume 2
Treated sewage discharge distance and discharge point level. Kindly provide us the exact distance of discharge point from Plant Site location where
treated sewage to be discharged of STP location .We understand the HFL will be the
same as indicated in the Bid Document, Pls confirm.
Bidders to verify from site
565) General STP plot area Kindly furnish the area availability of STP, with contour levels
As per bid document
566) General
Volume 2
Land status Kindly confirm the details of Ownership of Land & current status of the Land
Acquisition for Rithala WWTP.
This is existing WWTP
567) General
Volume 2
Lead Distance Please provide us the lead distance from SITE location to debris/disposal points.
Kindly confirm.
As per bid document
568) General
Volume 2
Storage of Un-Treated Sewage Please mention the capacity of storage to be
provided to store untreated sewage in case of
WWTP / Power break down.
As per bid document
569) General
Volume 2
Intermittent Sludge
Storage space
Please mention the intermittent sludge storage space to be provided at WWTP site. As per bid document
570) Disposal of
Treated
Sewage
Volume-2
New Treated
Effluent Channel
We understand that the treated effluent from Chlorination /de-chlorination tank shall be
taken to the outfall point of discharge body through newly constructed channel.
Kindly provide us the distance of effluent disposal point from proposed STP site. We
also request the department to kindly provide the length of the new treated effluent
channel to be constructed.
Bidders to verify from site
571) Volume 2
General
Diesel
Requirement
Whether diesel generator is required as a backup during the power failure from the grid
and when the bio gas production is insufficient for power generation. Kindly confirm.
As per bid document
572) General
Volume 2
Details for WWTP Please provide the following details of nearby Nallah for final disposal of treated
sewage.
Maximum water level of nallah.
HFL of nallah
Distance of nallah from WWTP.
Bidders to verify from site
573) General
Volume 2
Power Cut Please provide average duration of power cut in order to assess diesel consumption
during construction & O&M period.
Bidders to verify from site
574) General
Volume 2
Change in Quality or Price
Necessary clause provisions are requested to include as compensation for the
following.
- Adverse change of Raw Sewage Quality.
As per bid document
81
- Reduction of Raw Sewage quantity from the required level.
- Non availability of entire quantity of raw sewage water ( Full dry condition)
575) Volume 2
Section XI,
Part 2,
General
As per tender suggested modifications, secondary treatment is based on Modified
Ludzack- Ettinger ( MLE process) with construction of new Bioreactor Tank (Aeration
tank) and addition of two new secondary settling tanks followed by tertiary treatment
based on
a) Travelling Bridge Filters
b) Cloth media disk filters
c) UF ( both submerged and pressurized, however pressurized will require pre
filter)
We request you to allow bidders to opt for Combined secondary and tertiary treatment
using membrane Bio Reactor ( MBR) technology using existing civil structures of
Bioreactor tank and secondary settling tanks with necessary modifications.
As per bid document
576) Vol 2 –
Section XI
Vol 4
Part 2 / Clause
2.42.8
Drawing No :
YAP-
III/R2/P/GAD/00
1 (T) – Rev R0
Fencing, Gate & Security Room
The fencing is to essentially isolate Phase 1 & Phase –II plants.
……….
Fencing arrangement
Please confirm that, as the existing fencing is already available along the Phase II and
isolated from Phase I, new fencing arrangement as indicated in drawing near and along
the Phase II area is not in this contract scope. Please confirm
Refer to legend given in
proposed layout drag no
YAP-III/R2/P/GAD/001 (T)
– Rev R. fencing shown in
green colour is in the scope
of bidder.
577) Volume 2
Technical
Deodorization There is no information about deodorization facility - should bidder take into account
any odour management?
As per bid document
578) General
Volume 2
Land for Storage Land for storage & Labor Camp: We understand that land for storage and Labor Camp
shall be provided free of cost to contractor, Pls confirm.
Bidders to verify from site
579) Volume 2 Section XI Part 8 Power Failure Period
We presume that there will be 24 hours power supply during DLP & O&M period by
the employer and contractor need not consider DG & Diesel charges in his offer.
As per bid document
580) Vol. 3,
Section XII
698
Schedule of
payment
- In the absence of any preamble to Financial proposal, we understand that the schedule
of payment (a) and/or (b) is not required to be filled and submitted at the bid
submission stage. The same shall be referred to during the course of execution after
award of contract. Kindly confirm
As per bid document
581) Volume 3 698 Section XII Schedule of Payment and prices
Kindly specify payment commitment period (in days) from the date of bill
certification.
As per bid document
582) Volume 3 707 Section : XII ,
Price Schedule:
A3, item A
Request you to furnish as built drawings (of existing structures at site) of items listed
from A1 to A5 in order to carry out a detailed estimate for demolition works.
Bidders to verify from site
583) Vol. 3,
Section XII
Schedule of
Payment and
Prices
717 Interim Operation
and Maintenance
of the existing &
partly
rehabilitated
WWTP during
construction &
rehabilitation
period (36
months)
Sl.No Description
Nos. of Month
Sludge Disposal Cost During interim period We request client to provide distance of Sludge Disposal land from the STP to dispose
the sludge during interim O&M period
Refer Clause 8.1.4 (iii) at
page 562
82
(Bidders to
Indicate) Total
Price
584) Volume 3
Price Schedule
-A4
717 Interim Operating and Maintenance & Partly rehabilitated WWTP
during construction & rehabilitation period of (36 months)
Please clarify and confirm, whether the employer shall provide free of cost the
material/consumable/lubricants required for O&M under construction and
rehabilitation
As per bid document
585) Vol 3,
XII Schedule
of Payment
and Prices
719 B1 Price
Schedule
Operation and maintenance includes the supply of all spares parts as
required including the supply of all labour, materials, consumables,
equipment‟s, tools and tackles and comprehensive operation and
maintenance of 182 MLD (40 MGD) Waste Water Treatment Plant
and other related associated/allied appurtenant works as necessary
during the operation and maintenance period of 10 years after
successful completion of defect liability period.
Kindly confirm that the DLP Payment should include in the O&M price schedule or in
the Works Price schedule. Kindly confirm
As per bid document.
586) Volume 3 719 Financial
proposal, Price
Schedule B1
The Fixed charges has been mentioned that it shall not exceed 60% of the Monthly
Operating Charges which practically may not be possible for a Process job as the
Manpower cost will be predominant over chemical cost.
We request to revise the charges as below:
Fixed : 85%
Variable : 15%
As per bid document
587) Vol. –3,
Section -XI
719 Price Schedule –
B1
Operation and Maintenance The requirement that Fixed charges shall not exceed 60% of the Monthly Operating
Charges is not realistic in STP.
We would like to mention that the major cost of the O & M is electricity, Manpower
and Chemicals, replacements, repairs, sludge disposal etc.
Electricity in scope of Client. Chemical is Variable.
Chemical is around 15% of the O & M. Hence Fixed cost cannot be less than 85% of
the O & M cost.
The 60 % mentioned is too low and shall be at-least changed to 85%.
As per bid document
588) Vol. 3,
XII
720 B1 Price
Schedule
Payment in proportion to volume of treated Sewage proposed to be
treated per day 182 MLD
We understand that the Sl no in B1 price schedule, every bidder should estimate the
flow of 182 MLD throughout the O&M period. Flow variation should not be accepted.
Kindly confirm.
As per bid document.
589) Vol. 3,
XII
720 B1 Price
Schedule
During DLP period Cost towards Spare parts, Tools & tackles shall
be included in the Capital cost and no extra payment shall be made
during DLP period.
Kindly confirm the items to be included in the DLP price column in O&M price
schedule.
As per bid document.
590) Vol-3,
Section XII
720 Evaluation
criteria
NPV Discounting rate Kindly confirm the NPV Discounting Rate, and the Number of Years to be considered
in Bid Evaluation.
Refer C&A No. 6, Sl. No. 3
591) Vol. 3,
Section XIII
726 Appendix to
Financial
Proposal, Sr. no.
2
Advance payment shall be released in two (2) equal instalments Kindly clarify what shall be precedent condition fulfilling criteria for advance
payments. Also inform the time gap between the payment of both the instalments.
As per bid document
592) Volume – 3,
Section : XIII
726 Mobilization
advance
We understand that the mobilization advance available for this project is interest free.
Kindly confirm
As per bid document
593) Volume – 3,
Section : XIII
726 Mobilization
advance
Please note that considering the design build period of 36 months the repayment of
mobilization advance (from 5th month onwards within 10 equal instalments) may lead
to negative cash flow. Thus in view of the same we request DJB to kindly consider the
repayment of Mobilization advance starting from 5th month of construction in equal
monthly instalments upto 80% of the completion of the work.
Kindly confirm.
As per bid document
594) Vol-3,
Section XIV
728 - Interim Period O&M Service Level Agreement Please provide the Bidders the Performance Report of the existing Phase-1 plant
confirming that this plant in its present state is already meeting the performance
requirements for the parameters as listed in the Table in this section, and which is
required to be guaranteed by the Contractor during the Interim Operation of this plant.
Bidders to verify from site
595) Vol-3,
Section XIV
728 - Interim Period O&M Service Level Agreement In case it is not possible for the Employer to reliably confirm the present state and
adequacy of the existing plant and equipment in meeting the tender specified Interim
As per bid document
83
Performance requirement, and since it impossible for the Bidders to evaluate the
present health of the plant during the short duration available at the bid stage, we
suggest that such a study should be carried out Post-Contract jointly by the Contractor
and the Employer, within 3 months of the contract coming into force, and the KPIs for
the Interim O&M should be mutually agreed according to the outcome of this Study.
Kindly review and confirm.
596) Vol. 3,
Section XV
731 3rd Paragraph
below the MAC
table
Non-compliance to demonstrate the plant performance during the
completion tests with respect to treated water quality and sludge
quality for a continuous period of 72 hours, is not acceptable and the
Contractor shall rectify the facility to demonstrate the performance.
Not being able to demonstrate the plant performance shall render the
plant as “Non-Acceptable” leading to a liquidity damage of 10% and
shall forfeit the performance securities.
We understand that 72 hours PGTR shall be done after 6 months commissioning &
trial run. We request DJB to accept that in the event of noncompliance of guaranteed
parameters, the contractor shall be allowed to modify the equipment as required to
enable the system meet the guarantees test results without imposing any Liquidated
Damage. In such case, Performance and Guarantee Tests shall be repeated within one
month from the date the equipment is ready for re-tests and costs for modifications
including labour, materials and the cost of additional testing to prove that the
equipment meets the guarantees shall be borne by the Contractor. Kindly confirm.
As per bid document
597) Vol-3,
Sec-XV
731 - SLA As per the SLA, it is required that plant has to meet the performance even at 110% of
design pollution freight in kg/day.
This requirement will exceed the Plant Design Basis in which Pollution Freight in
kg/day plays the most critical role, and, is therefore, the main deciding factor for plant
performance.
We suggest this SLA performance requirement should be amended to “75% to 110%
of the Pollution Design Concentration as mg/l, as along as the actual Pollution Freight
in kg/day does not exceed the Design Pollution Freight in kg/day. Kindly review and
confirm.
As per bid document
598) Vol-3,
Sec-XV
731 - SLA We feel that the paragraph “Non-compliance to demonstrate the plant ……..and shall
forfeit the performance securities” is irrelevant to SLA, and hence, should be deleted.
Please confirm.
As per bid document
599) Volume3,
Section XV
731 Service Level Agreement
Please confirm that the MAC values for the treated effluent parameters listed under the
Table represents the values in a 24-hours composite sample, and that the MAC value in
an individual grab sample shall not be more than 2 times of these values.
As per bid document
600) Vol-3,
Section-XV
731 - LDs during Completion Tests As per the paragraph “Non-compliance to demonstrate the plant performance during
the completion tests………….forfeit the performance securities”, we understand that
the maximum cumulative amount of LD for all the non-compliant parameters shall be
10% of the Works Contract Price. Considering that there are several parameters in the
treated effluent quality and sludge quality to demonstrated the plant performance,
kindly specify the weightage for each parameter to be considered while applying such
LD.
As per bid document
601) Vol. 3,
Section XIV
732 However, if pollutant load (kg/day) exceeds the design pollutant load
per day basis, or total flow exceeds 33 MGD (24 hrs Basis), no
penalty shall be applicable
Pls explain the basis of arriving this total flow of 33 MGD. The total design flow of
Phase I, II, III is 45 MGD. Pls clarify
Query not clear and not
pertain to the subject tender
602) Vol-3
Section: XV
732 Conditions A
Service Level Agreement
For Performance Monitoring and Liquidated Damages, Total Nitrogen (TN) is required
to be reported Online, whereas in the Table for Online Instruments in Vol-2, section
XI, Part-6, Online Instrument for TN measurement is not listed. Kindly review and
clarify the requirement.
As per bid document
603) Vol. 3,
Section XV
733 Condition D:
Liquidated
Damages for not
meeting the
Electric
Consumption
Guarantee
Damages payable by Contractor to Employer on excess consumption
of net electric energy and on Reduction in Power Generation from
WWTP
We request employer to agree that any shortfall in power requirement due to
insufficient power generation with Biogas or through Micro Hydro Plant shall be
drawn by the grid and the cost of same shall be borne by Employer. Kindly confirm.
As per bid document
604) Vol-3,
Section XV
733 - Service Level Agreement
Unlike the conventional STPs designed and operated for old effluent quality standards
(typ. BOD<20 mg/l and TSS<30 mg/l), the Biological process with Nitrification and
Denitrification to be implemented now in Rithala Phase-1, and with very stringent
As per bid document
84
treated effluent quality to be guaranteed, especially for TN<10 mg/l, the power failure
in the plant shall have long term adverse impact on the plant performance and the
effluent quality. As per our experience, a prolonged / frequent and/or cumulative
power failure typically exceeding 8 hour per day, especially during the periods of cold
water temperature, will require 72 hrs or more for the recovery of the process and
performance, inspite of the best efforts. Hence, at-least 72 hours should be allowed for
the plant recovery after every such event. Kindly review and confirm.
605) General
Volume 3
Mobilization Advance Payment We request you to please provide us “INTEREST FREE” Mobilization Advance
minimum 10% in single instalment against the equivalent amount of Bank Guarantee.
Kindly accept and confirm.
As per bid document
606) Vol. 4- Section
XVII
Geo-Tech
(soil) Report
Package
4 2.1.1.1 Water table We presume that, the ground water table is at 7.50m below GL as per the Geotechnical
report, hence the same will be considered as design water table also for the designing
of proposed water retaining structures for uplift criteria if any.
Please confirm.
As per bid document
607) Vol. 4- Section
XVII
Geo-Tech
(soil) Report
Package
4 6.0 Recommendation
Foundation
Depth below
existing
ground,
level, m
Recommend
ed Net
Allowable
Bearing
Pressure,
T/m2
Modulus of
Sub grade
reaction,
kg/cm3
2.0 10.5 1.0
3.0 12.4 1.2
4.0 15.0 1.5
5.0 17.3 1.7
We presume that, if the recommended bearing capacity value as in the Geo technical
report is varied during detailed engineering then the bidder can eligible to claim the
extra cost.
Please confirm
As per bid document
608) Volume 4 7 Section XVII Geo
Tech Report ,
2.1.1.1
A seasonal variation of +/- 1m (from the currently proposed water table level) will be
considered as design ground water table for structural design. Please confirm.
As per bid document
609) Volume-4
SLD for
Rithala WWTP
phase-I
- YAP-
III/R2/E/SLD/001
(T)
11kV Proposed switchgear and metering panel Kindly provide the distance between proposed 11kV Metering panel (by TPDDL)and
11kV proposed switchboard for estimating the cable required between them.
Bidder to verify from site
610) Volume-4
SLD for
Rithala WWTP
phase-I
- YAP-
III/R2/E/SLD/001
(T)
location of 11kV Metering panel Kindly clarify the location of 11kV Metering panel (by TPDDL) if indoor or outdoor Bidder to verify from site
611) Volume-4
SLD for
Rithala WWTP
phase-I
- YAP-
III/R2/E/SLD/001
(T)
Tapping of 11kV power supply We understand from the SLD that bidder scope starts from 11kV cable from 11kV
Metering panel(by TPDDL). kindly confirm.
Confirmed
612) Volume-4
SLD for
Rithala WWTP
phase-I
- YAP-
III/R2/E/SLD/001
(T)
11kV Fault level Kindly clarify the fault level of VCB as it is mentioned as 16kA for incoming 11kV
VCB and 26.2kA for outgoing 11kV VCB.
Refer C&A No. 6, Sl. No. 89
613) Volume-4
Proposed
layout plan of
Rithala phase-I
WWTP
- YAP-
III/R2/P/GAD/00
1 (T)
Micro Hydro Power generation system location It is understood from specification power generated by hydro power plant to be utilised
for WWTP operation, from the layout the distance between the LT main panel located
at substation building and the Micro Hydro Power generation system seems to be very
high, how two are going to make sure the generated power is going to reach the
substation without any voltage loss or we have to consider step up transformer, kindly
clarify.
As per bidder design subject
to the Approval of the
Engineer-In Charge
614) Vol 4 – - Drawing No :
YAP-
We presume that, the bidder scope is limited upto Phase I and not in Phase II area.
Please confirm.
As per bid document
85
III/R2/P/GAD/00
1 (T) – Rev R0
615) Volume-4
SLD for
Rithala WWTP
Phase-1
- Tender SLD.
DRG.NO. YAP-
III/R2/E/SLD/001
(T)
Provide Phase-II electrical load details to arrive rating of 11kV VCB tie-feeder to feed
11kV power supply from proposed 11kV indoor switchboard (8panel).
Bidders to verify from site
616) Volume – 4,
Section : XVI
- General We request you to furnish the AutoCAD copies of all the drgs. furnished along with
the NIT.
This helps us to understand the clear distances available between units & plan for
placement of nearby units.
As per bid document
617) 4
Volume-4
Drawings Please provide the AutoCAD drawings of Topo survey, Proposed Layout, Existing
plant layout and HFD.
As per bid document
618) Vol-4,
Drawings
YAP-
III/R2/P/GAD/00
1(T)
Proposed Layout Plan of Rithala Phase – I WWTP Kindly provide Autocad drawing of the Tender Layout of the Plant.
As per bid document
619) Volume 4 and
general:
Technical Data
Please kindly provide:
Details of existing process with flow diagrams
Mass balance
Details of existing civil infrastructure
List of spares available for the interim O&M
Operational reports of existing plant, including chemicals used and samples of
raw water and treated water.
Environmental Impact Assessment
As per bid document
620) Geo-tech
Report
Volume-4
- - Liquefaction Analysis The Project Site is located in Earthquake Zone-IV as per IS 1893:2002. Hence, kindly
provide the Liquefaction Analysis as a part of Tender Geo-tech considering ground
water table for design recommended to be specified by the Employer.
The desired details to be
ascertained along with
confirmatory geotechnical
investigations by the
contractor.
621) Vol-4
(SLD)
- SLD -
III/R2/E/BD/002(
T) Rev: R0
Draw-out ACB v/s Fixed type ACB As per our experience in STPs in India, and in Delhi, the moving contacts of Draw-out
ACB‟s gets over heated & welded because of presence of corrosive gases in the STP
atmosphere. Hence, we strongly recommend “only FIXED type ACBs”. Please
confirm.
As per bid document
622) -
Volume-4
- General – NDT
reports
We request you to furnish the NDT reports of WWTP structures (which is available
with DJB) in order to evaluate the structural stability of tanks/buildings to be retained.
Also please clarify, what has to be done in case a structure is found unsound as per the
reports but is suggested in NIT to be used for rehabilitation.
As per bid document
623) General
Volume 4
Drawings Please provide the route map, L-section, Road/Nallah crossing, Contour map of the
site.
Bidders to verify from site
624) General
Volume 4
Drawings The furnished PDF drawing is illegible. Please provide the AutoCAD drawing
As per bid document
625) General
Volume-4
Details for WWTP Please provide the following details….like
- List of existing units/buildings and the
Sizes of the same; If any.
- Marking of boundary wall.
- Position of outfall sewer.
As per bid document
626) General
Volume-4
Layout We request client to please provide the AutoCAD file of the proposed Layout and
other drawings.
As per bid document