34
Regulatory assessment of new NPP designs and safety cases: UK practices Josephine Holmes Principal Inspector - Nuclear Safety Office for Nuclear Regulation 4 October 2016

Regulatory assessment of new NPP designs and … · Regulatory assessment of new NPP designs and safety cases: UK practices Josephine Holmes Principal Inspector - Nuclear Safety Office

  • Upload
    ngotruc

  • View
    216

  • Download
    0

Embed Size (px)

Citation preview

Regulatory assessment of new

NPP designs and safety cases:

UK practices

Josephine Holmes

Principal Inspector - Nuclear Safety Office for Nuclear Regulation

4 October 2016

Contents

• Introduction - ONR’s regulatory philosophy

• The Generic Design Assessment (GDA) process

• The way we regulate - requirements & expectations

• Final remarks - alignment with Vienna Declaration

Introduction

ONR’s regulatory philosophy

• Non-prescriptive goal setting

• Underpinned by a risk-informed framework

– Tolerability of Risk from Nuclear Power Stations (TOR)

– Consistent with HSE decision-making process - Reducing Risk

Protecting People (R2P2)

• Aimed at developing & sustaining an open & effective dialogue with

duty-holders positive & enabling approach to the permissioning of

activities

• Key pillars of our regulatory work:

– ALARP - As Low As Reasonably Practicable

– The Nuclear Safety Case

– ONR’s Safety Assessment Principles for Nuclear Facilities

(SAPs)

13

The GDA Process

Three elements of new build

Hinkley Point C Sizewell C

Moorside

Wylfa Oldbury

EDF/Areva

Westinghouse

Hitachi-GE

GDA Licensing Construction

Phase 1 Phase 2

The Generic Design Assessment (GDA) • GDA - upfront, step-wise assessment of a generic reactor design - joint

Regulators (ONR / Environment Agency / Natural Resources Wales)

• GDA - developed in 2006 as a process of regulatory assessment of

candidate new reactor designs on a generic basis to be carried out

in advance of:

– site specific proposals

– specific operating organisations

• Aim to permit deployment of the generic design on any site - subject to

site specific safety cases & environmental acceptability

• Allows early regulatory intervention

• Advantage - to identify & resolve key issues - safety / design /

construction - long before build - to reduce risks / build time / costs

• GDA is not a formal regulatory or legislative requirement - but remains

a Government expectation

Current GDA Process & Typical Timescales

DAC: ONR’s Design Acceptance Confirmation (iDAC: interim DAC)

SODA: EA/NRW’s Statement of Design Acceptability (iSODA: interim SODA)

DAC

SoDA

Preparation

Step 1 Overview of

Claims

Step 2 Review of

Arguments

Step 3 Detailed Assessment

of Evidence

Step 4

Le

vel

of

scru

tin

y

iDAC

iSoDA

(EA / NRW)

Public

Consultation

6-9m 6-8m 12m 28m

>12m

Engagement in GDA: Openness &

Transparency

• Openness:

– Requesting Parties’ websites publish safety & environmental reports

– Regulators’ GDA website

– Regulators’ guidance published

• Transparency

– Regulatory Observations (RO) & Regulatory Issues (RI) published

– Regulators’ Assessment Reports published

– Quarterly progress reports

8

http://www.onr.org.uk/new-

reactors/index.htm

Status of GDAs Current and potential

NPP Projects

UK ABWR In Step 4

AP1000® iDAC issued in December

2011 - currently undergoing close-out

phase

Hinkley Point C Nuclear Site Licence

(NSL) granted in December 2012

Sizewell C

UK EPRTM Design Assessment

Confirmation (DAC) issued in

December 2012

HPR1000 Potential new GDA entry

Moorside Site Licence Application

expected 2017

Wylfa Newydd Site Licence

Application expected 2017

Oldbury

Bradwell B

The way we regulate -

requirements &expectations

• The concept of As Low As Reasonably Practicable (ALARP)

• The Nuclear Safety Case

• ONR’s Safety Assessment Principles (SAPs)

• The SAPs’ Numerical Targets

What is ALARP? Health & Safety at Work etc. Act 1974

• Section 2: It shall be the duty

of every employer to ensure,

so far as is reasonably

practicable, the health, safety

and welfare of all of his

employees

• Section 3: it shall be the duty

of every employer to conduct

his undertaking in such a way

as to ensure, so far as is

reasonably practicable, that

people not in his employment

who may be affected thereby

are not exposed to risks to

their health & safety

• The “SFAIRP Principle” is therefore the basic legal requirement to

which an employer needs to conform

• ALARP & SFAIRP require the same tests to be applied & are essentially the same thing

What is ALARP? The “Reasonably Practicable” Principle

• Based on the 1949 Court Case: Edwards vs. National Coal Board

• The Court of Appeal considered whether it was reasonably practicable to

make the roof and sides of a road in a mine secure. The Court of Appeal

held that:

'Reasonably practicable' is a narrower term than 'physically possible' and

seems to me to imply that a computation must be made by the owner in

which the quantum of risk is placed on one scale and the sacrifice

involved in the measures necessary for averting the risk (whether in

money, time or trouble) is placed in the other, and that, if it be shown that

there is a gross disproportion between them - the risk being insignificant

in relation to the sacrifice - the defendants discharge the onus on them."

• ALARP is not the result of a mathematical formula there is no precise legal factor or algorithm for gross disproportion

How to establish if the risk is ALARP?

Tolerability of risk (TOR) framework

Dutyholder’s application of Relevant Good Practice (RGP)

Numerical risk estimates & explicit comparisons

• ONR’s judgements on whether dutyholders’ ALARP

justifications are robust are made by looking at:

The tolerability of risk framework

Expectation for

new facilities

Unacceptable

region

Tolerable

region

Broadly

acceptable

region

A

L

A

R

P Basic Safety Objectives (BSOs)

Basic Safety Levels (BSLs)

Note: this is discussed further later in this presentation

The use of relevant good practice

• In most cases demonstrating ALARP is not done through explicit

comparison of costs & benefits but by applying established relevant

good practice (RGP)

• RGP - those standards for controlling the risk - judged & recognised

by ONR as satisfying the law, when applied appropriately

• RGP is the starting point in any ALARP demonstration - focus on:

– appropriate engineering, operations & management of safety

– defence-in-depth / hierarchy of control measures

– prevent the hazard protect mitigate

• Sources of RGP are - ONR’s Safety Assessment Principles (SAPs) &

Technical Assessment Guides (TAGs) - IAEA Standards - other nuclear

industry standards - what is done on similar facilities elsewhere

ALARP for new reactors: ONR’s

expectations

• RGP must be met (or alternative solutions for achieving

the same safety outcome put forward)

• What more can be done? evaluation of options

• Proper use of risk assessment to help identify potential

improvements & justify the claimed level of safety

Clear conclusion that there are no further reasonably

practicable improvements that could be implemented

Cost Benefit Analysis (CBA) is unlikely to be considered

an adequate argument on its own to demonstrate ALARP

Meeting the risk targets in isolation is not an acceptable

means of demonstrating ALARP

The Nuclear Safety Case

• The safety case encompasses the totality of the documentation

developed by a designer, licensee or duty-holder to demonstrate

high standards of nuclear safety & radioactive waste management

• A safety case is a logical & hierarchical set of documents that

describes:

– risk in terms of the hazards presented by the facility - for the

site & all modes of operation - potential faults & accident

scenarios

&

– those reasonably practicable measures that need to be

implemented to prevent or minimise harm

ONR’s Safety Assessment Principles for

Nuclear Facilities (SAPs)

• Principles to be followed by ONR Inspectors when assessing Safety

Cases

• http://www.onr.org.uk/saps/saps2014.pdf

• Provide a framework for consistent regulatory judgements on the

acceptability of Safety Cases

• Also include numerical targets (discussed later)

• Are in line with IAEA standards & guidance

• Are supported by more detailed Technical Assessment Guides

(http://www.onr.org.uk/operational/tech_asst_guides/index.htm)

Structure of ONR’s SAPs

• Fundamental principles

• Leadership & management for safety

• The regulatory assessment of safety

cases

• Siting aspects

• Engineering principles

• Radiation protection

• Fault analysis

• Numerical targets

• Accident management &

emergency preparedness

• Radioactive waste management

• Decommissioning

• Land quality management

Vienna

Declaration

Principle 1

New nuclear power plants are

to be designed, sited &

constructed, consistent with

the objective of preventing

accidents in the

commissioning & operation &,

should an accident occur,

mitigating possible releases

of radionuclides causing long-

term off site contamination &

avoiding early radioactive

releases or radioactive

releases large enough to

require long-term protective

measures & actions

ONR’s SAPs (cont.)

Key Engineering Principles:

EKP.1 Inherent safety

EKP.2 Fault tolerance

EKP.3 Defence-in-depth

EDR.2 Redundancy, diversity &

segregation

Fault Analysis Principles Para 611

… the severe accident analyses (SAA)

should form part of a demonstration that

potential severe accident states have

been “practically eliminated”. To

demonstrate practical elimination, the

safety case should show either that it is

physically impossible for the accident

state to occur or that design provisions

mean that the state can be considered to

be extremely unlikely with a high degree

of confidence.

Vienna

Declaration

Principle 1

New nuclear power plants are

to be designed, sited &

constructed, consistent with

the objective of preventing

accidents in the

commissioning & operation &,

should an accident occur,

mitigating possible releases

of radionuclides causing long-

term off site contamination &

avoiding early radioactive

releases or radioactive

releases large enough to

require long-term protective

measures & actions

SAP EKP.3 - Defence-in-depth

DBA & PSA

• Design basis analysis (DBA) a robust demonstration of the fault

tolerance of the facility & the effectiveness of its safety measures

• Its principal aims are to guide the engineering requirements of the

design - to determine limits to safe operation (operating rules) - so

that safety functions can be delivered reliably during all modes of

operation & under reasonably foreseeable faults

• In DBA risk is not quantified - adequacy of the design & the suitability

& sufficiency of the safety measures are assessed against

deterministic rules.

• Probabilistic safety analysis (PSA) undertaken to understand

the overall risk presented by the facility & allow comparisons to be

made against SAPs Numerical targets - understand strengths &

weaknesses of a design with complex systems & interdependencies

SAPs - 3 Methods of fault analysis

SAPs Numerical Targets

• Numerical targets are established in the UK for ONR Inspectors to

use when judging whether the duty holder is controlling radiological

hazards adequately & reducing risks ALARP

• These are described in paragraphs 695 to 767 of the SAPs

(http://www.onr.org.uk/saps/saps2014.pdf)

• The structure of the targets included in the SAPs is based on the

1988 (revised 1992) TOR framework

(www.onr.org.uk/documents/tolerability.pdf)

• The basis and derivation of the numerical targets are explained in

Annex 2 of the SAPs

Basic Safety Levels (BSLs) &

Basic Safety Objectives (BSOs)

• The numerical targets of the SAPs are expressed as bands with a

Basic Safety Level (BSL) & Basic Safety Objective (BSO)

• BSLs & BSOs translate the Tolerability of Risk (TOR) framework into

actual targets & guide decision making by inspectors

• The targets are not mandatory - they are guides to inspectors indicating

if additional safety measures should be considered

• Two BSLs are legal dose limits those are mandatory

Basic Safety Levels (BSLs)

• BSLs indicate risks which all facilities should meet (as a minimum)

• Meeting the BSLs does not mean that risks are ALARP the

application of ALARP may drive the risks lower

• BSLs provide benchmarks for existing facilities - unless level of “gross disproportion” is very high ONR’s policy to press duty holders to

evaluate / implement options to reduced risks below the BSLs

• Where a BSL is exceeded - consideration is given to regulatory action

to prohibit the activity or shut down the facility

Basic Safety Objectives

(BSOs)

• BSOs form benchmarks that reflect modern standards & expectations

• BSOs have been set at a level where ONR considers it not to be a

good use of its resources to pursue further improvements in safety

However, even if the BSOs are met - duty-holders cannot stop

at this point

If it is reasonably practicable to provide a higher standard of

safety - duty-holder must do so by law

• BSOs mark the start of the “Broadly

Acceptable” region in the TOR framework

SAP’s Numerical Targets

NT.1 comprises the following targets:

• Dose targets & legal limits for normal operation for persons on the site:

Targets 1, 2 & 3

• BSLs in Target 4 are used as screening criteria for consideration of Initiating

Events within / outside the Design Basis

• Numerical targets for accidents for persons on the site: Targets 5 & 6

• Numerical targets for accidents for persons off the site: Targets 7, 8 & 9

the following slides will focus on the numerical targets for faults for

persons off the site (Targets 7, 8 and 9) because of their particular

relevance for the purpose of this TM

Target 7 - Individual Risk

Target 7 addresses the overall risk to individuals from the public for all

potential accidents from all the sources of radioactivity in a nuclear

power plant

Target 8 - Dose Targets

The “dose-band staircase” in Target 8 is based on the principle that

the larger the consequences of an accident, the smaller should be its

frequency

Target 9 - Societal Risk

• Target 9 has been defined as a measure of the societal concerns that

would result from major accidents

• The societal risk should be calculated taking into account:

– Frequencies of release categories associated with source terms

able to cause 100 deaths or more over a 100 year period

– Meteorological data appropriate to the site

– Current policy on countermeasures

– On-site and Off-site (within the UK) population

Final Remarks

• UK requirement to demonstrate risks are reduced ALARP - application

Relevant Good Practice

• Demonstrate through Safety Case - robust DBA - PSA & SAA

– prevent the hazard protect mitigate

– defence-in-depth

• BSOs of the SAPs - benchmark that reflect modern standards &

expectations - ONR expects BSOs to be met for new reactors

• ONR seeks confirmation that it is not reasonably practicable to reduce

risk further by implementing additional improvements.

• We believe that our approach is aligned with the first principle of the

Vienna Declaration

Thank you

Any Questions?