Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Registration No. 017/01500 Email address:[email protected]
Postal Address: P. O. Box 96188, Windhoek, Namibia
September 2019
Draft Environmental Management Plan (EMP)
The Proposed Construction and Operation of a Wastewater Treatment
Plant for Linus Shashipapo Secondary School in the Kavango East
Region
Date: 02 September 2019
Proponent: Dunamis Consulting Engineers &
Project Managers (Pty) Ltd
Prepared by: MZ-Fifteen Environmental, Health
& Safety Consultants
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
i
Table of Contents
List of ABBREVIATIONS ............................................................................................................................... ii
1 INTRODUCTION ................................................................................................................................... 1
1.1. Aims of the EMP ........................................................................................................................... 2
1.2. List of Project Phases Covered in this EMP ................................................................................. 2
1.3. Environmental Assessment Practitioner (EAP) ............................................................................. 3
1.4. Environmental Legal Requirements (Permits and Licenses) ........................................................ 3
1.5. Limitations of the EMP .................................................................................................................. 5
2. EMP ROLES AND RESPONSIBILITIES ............................................................................................... 6
3. ENVIRONMENTAL MANAGEMENT ACTION PLANS ......................................................................... 8
3.1. Key Potential Environmental Impacts to be managed .................................................................. 8
3.2. Aim of the Environmental Management Actions ........................................................................... 8
3.3. Phase 1: Planning and Design Phase Management Action Plans ............................................... 9
3.4. Phase 2: Construction Phase Management Action Plans .......................................................... 12
3.5. Phase 3: Operational and Maintenance Phase Management Action Plans ............................... 23
3.6. Phase 4: Decommissioning Phase ............................................................................................. 27
4. ENVIRONMENTAL MONITORING ..................................................................................................... 29
4.1. Physical Environmental Monitoring ............................................................................................. 29
4.2. Occupational Health and Safety Monitoring Program ................................................................. 31
4.2.1. Surveillance of the working environment: ........................................................................... 31
4.2.2. Surveillance of workers health ............................................................................................ 31
4.2.3. Training ............................................................................................................................... 31
4.2.4. Accidents and diseases monitoring..................................................................................... 31
4.2.5. Contingency Plan ................................................................................................................ 32
5. CONCLUSION ..................................................................................................................................... 32
List of Figures
Figure 1: Location of Linus Shashipapo Secondary School (and WWTP Site) in Sharughanda Village,
Kavango East Region ................................................................................................................................... 1
List of Tables
Table 1: List of applicable legislations for which permitting or licensing will be required for the Plant ... 3 Table 2: Summary of key potential environmental impacts per project phase ....................................... 8 Table 3: Management Action Plans for the Planning and Design Phase ............................................ 10 Table 4: Management Action Plans for the Construction Phase .......................................................... 12 Table 5: Management action plans for the Operation and Maintenance Phase ................................... 24
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
ii
Table 6: Management action plans for the Closure (Decommissioning) Phase ................................... 27 Table 7: Environmental monitoring program for the construction and operational phases .................. 30
LIST OF ABBREVIATIONS
Abbreviation Meaning
BOD Biological Oxygen Demand
DEA Department of Environmental Affairs
DWAF Department of Water Affairs and Forestry
EA Environmental Assessment
EAP Environmental Assessment Practitioner
ECC Environmental Clearance Certificate
EIA Environmental Impact Assessment
EMA Environmental Management Act
EMP Environmental Management Plan
ESA Environmental Scoping Assessment
GG Government Gazette
GN Government Notice
HDPE High-density polyethylene
HIV/AIDS Human Immunodeficiency Viruses and Acquired Immune Deficiency
Syndrome
HPP Harambee Prosperity Plan
I&APs Interested and Affected Parties
MAWF Ministry of Agriculture, Water and Forestry
MEAC Ministry of Education, Arts and Culture
MET Ministry of Environment and Tourism
MZ15 EHS MZ-Fifteen Environmental, Health & Safety Consultants cc (the Consultant)
NamWater Namibia Water Corporation Limited
OHS Occupation, Health and Safety
PPE Personal Protective Equipment
Reg Regulation
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
iii
Abbreviation Meaning
S Section
SABS South African Bureau of Standards
SANS South African National Standards
TDS Total Dissolved Solids
TSS Total Suspended Solis
WWTP Wastewater Treatment Plant
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
1
1 INTRODUCTION Dunamis Consulting Engineers & Project Managers (Pty) Ltd (herein after referred to as the Proponent)
proposes to construct a Wastewater Treatment Plant (WWTP) for Linus Shashipapo Secondary School
("the School") in the Sharughanda Village, Ndiyona Constituency of the Kavango East Region. The
School is located about 120 km east of Rundu and 90 km west of Divundu. The locality map of the
proposed Plant site and the School are shown in Figure 1. For the first year of the Plant's operation,
maintenance will be done by the Construction Contractor (as a defect/guarantee period) under Dunamis
Consulting Engineers. After this, the Plant will be operated and maintained by the Ministry of Education,
Arts and Culture (MEAC) through their appointed Plant Maintenance specialist. It should be noted that the
Proponent (Dunamis) may consider transferring the environmental clearance certificate (ECC) ownership
to MEAC (as the future Plant operator) when the need arises in future. However, the change of ECC
ownership is out of the scope of this study.
The Plant would be located within the School land boundary, next to the existing sewage facilities (septic
tanks) about 600 m northwest of the School buildings. The proposed Plant and its associated site
infrastructures would cover a total surface area of 600 m2.
Figure 1: Location of Linus Shashipapo Secondary School (and WWTP Site) in Sharughanda Village, Kavango East Region
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
2
1.1. Aims of the EMP
Regulation 8 of the Environmental Management Act (EMA) (7 of 2007) Environmental Assessment
Regulations (2012) requires that a draft Environmental Management Plan (EMP) be included as part of
the Scoping Environmental Assessment (EA) process. A ‘management plan’ is defined as:
“…a plan that describes how activities that may have significant environments effects on the environment
are to be mitigated, controlled and monitored.”
An EMP is one of the most important outputs of the EA process as it synthesises all of the proposed
mitigation and monitoring actions, set to a timeline and with specific assigned responsibilities. It provides
a link between the impacts identified in the EIA Process and the required environmental management on
the ground during project implementation and operation. It is important to note that an EMP is a legally
binding document and a person who contravenes the provisions of this EMP may face imprisonment
and/or a fine. This EMP is a living document and should be amended to adapt to address project changes
and/or environmental conditions and feedback from compliance monitoring.
The purpose of this document is therefore to guide environmental management throughout the different
phases of the proposed development, namely; planning and design, construction, operational and
decommissioning phases.
1.2. List of Project Phases Covered in this EMP
The following phases are addressed in this EMP:
Planning and Design Phase: the period, prior to the construction phase, during which
preliminary legislative and administrative arrangements are carried out in preparation of
construction activities.
Construction Phase: the phase during which earth works and site preparation works will be
carried out on certain areas of the project site in order to erect the buildings and for the
installation of the necessary services infrastructure required for the Wastewater Treatment Plant.
Operational and maintenance phase: the phase during which the Plant and its related activities
will be operated and managed by the Ministry of Education, Arts and Culture (MEAC) and their
appointed Plant Maintenance specialist. It is during this phase that the School's sewage will be
treated, and the treated water be used for the School's renovation works and irrigation purposes
for both the School, and possibly local community.
Decommissioning phase: the phase during which the MEAC due to unforeseeable reasons, will
decide on the Plant's closure, i.e. cessation of the Plant's operations.
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
3
1.3. Environmental Assessment Practitioner (EAP)
Under the Environmental Impact Assessment (EIA) Regulations (2012) of the Environmental
Management Act (7 of 2007), Section 2.1, 2.3, 8.1 and 9.2, the proposed development is a listed activity
that may not be undertaken without an Environmental Clearance Certificate (ECC). The mentioned EMA
Sections relevant to the project are as follow:
Regulation 2.1 The construction of facilities for waste sites, treatment of waste and disposal of
waste.
Regulation 8.6 The construction of industrial and domestic wastewater treatment plants and
related pipeline systems.
Regulation 9.2 Any process or activity which requires a permit, license or other form of
authorization, or the modification of or changes to existing facilities for any process or activity
which requires an amendment of an existing permit, license or authorization or which requires a
new permit license or authorization in terms of a law governing the generation or release of
emissions, pollution, effluent or waste.
In order to comply with the Environmental Management Act's (7 of 2007) and its 2012 EIA Regulations,
the Proponent appointed MZ-Fifteen Environmental, Health & Safety Consultants CC (hereinafter referred
to as the Environmental Consultant) to undertake the required ESA process and submit the
Environmental Clearance Certificate (ECC) application to the Competent Authority on their behalf. The
application for the ECC accompanied by the Background Information Document (BID) and a CD
(containing preliminary site layouts/drawings) was submitted to the Department of Water Affairs and
Forestry (DWAF), Ministry of Agriculture, Water and Forestry (the Competent Authority). Upon completion
of the assessment process, the environmental scoping assessment report and the EMP (this document)
are to be submitted to the Department of Environmental Affairs at the Ministry of Environment and
Tourism (MET) for evaluation and consideration of an ECC issuance.
This EMP was compiled by Fredrika Shagama, a qualified and experienced hydrogeologist and
experienced and registered environmental assessment practitioner.
1.4. Environmental Legal Requirements (Permits and Licenses)
The legal obligations that govern the proposed Plant in terms of required permits / licenses are presented
in Table 1 below. The detailed legal framework is presented in the environmental report.
Table 1: List of applicable legislations for which permitting or licensing will be required for the Plant
Legislation/Policy/
Guideline
Relevant Provisions Required Permit/Clearance or
License
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
4
Legislation/Policy/
Guideline
Relevant Provisions Required Permit/Clearance or
License
Environmental
Management Act
EMA (No 7 of 2007)
Requires that projects with significant
environmental impacts are subject to an
environmental assessment process (Section 27).
Details principles which are to guide all EAs.
The EMA and its regulations should
inform and guide this EA process.
Should the ECC be issued to the
Proponent, it should be renewed every
3 years, counting from the date of
issue.
Contact details at the Department of
Environmental Affairs (DEA):
Mr. Damian Nchindo or Mr. Josafat
Hiwana
Tel: 061 284 2717 and 061 284 2962
Email: [email protected]
and [email protected],
respectively
In the case of changing ownership of
the ECC, the Proponent should
contact the Office of the
Environmental Commissioner at the
DEA for procedures to be followed.
Environmental
Impact Assessment
(EIA) Regulations
GN 28-30 (GG 4878)
Details requirements for public consultation within
a given environmental assessment process (GN 30
S21).
Details the requirements for what should be
included in a Scoping Report (GN 30 S8) and an
Assessment Report (GN 30 S15).
In the event that the Proponent (Dunamis) may
consider transferring the environmental clearance
certificate (ECC) ownership to MEAC (as the future
Plant operator).
Water Act 54 of 1956 The Water Resources Management Act 11 of 2013
is presently without regulations; therefore the
Water Act No 54 of 1956 is still in force:
Prohibits the pollution of water and
implements the principle that a person
disposing of effluent or waste has a duly
of care to prevent pollution (S3 (k)).
Provides for control and protection of
groundwater (S66 (1), (d (ii)).
Liability of clean-up costs after
closure/abandonment of an activity (S3 (l)).
The protection (both quality and
quantity/abstraction) of water
resources should be a priority
throughout the project life cycle.
An effluent/wastewater discharge
permit should be applied for from the
Department of Water Affairs &
Forestry (Water Environment Division
at the Ministry of Agriculture and
Forestry)
Contact: Ms. Elise Mbandeka
Tel: +264 61 208 7167
Email: [email protected]
Water Resources
Management Act (No
11 of 2013)
The act provides for the management, protection,
development, use and conservation of water
resources; and provides for the regulation and
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
5
Legislation/Policy/
Guideline
Relevant Provisions Required Permit/Clearance or
License
monitoring of water services and to provide for
incidental matters. The objects of this Act are to:
Ensure that the water resources of Namibia are
managed, developed, used, conserved and
protected in a manner consistent with, or
conducive to, the fundamental principles set out in
Section 66 - protection of aquifers, Subsection 1
(d) (iii) provide for preventing the contamination of
the aquifer and water pollution control (Section 68).
Forestry Act 12 of
2001, Amended Act
13 of 2005
Prohibits the removal of any vegetation within 100
m from a watercourse (Forestry Act S22(1)). The
Act prohibits the removal of and transport of
various protected plant species.
Should there be protected plant
species occurring within the project
site, that will be removed, a permit
should be obtained from the nearest
Forestry office (Ministry of
Agriculture, Water & Forestry) prior
to removing them.
At the Ministry's Head Office, please
contact: Mr. Joseph Hailwa
(Director of Forestry)
Tel: +264 61 208 7663
Email: [email protected]
1.5. Limitations of the EMP
This EMP has been drafted with the acknowledgment of the following limitations:
This EMP has been drafted based on the scoping-level Environmental Assessment (EA)
conducted for the proposed Wastewater Treatment Plant. No specialist study was conducted for
the Scoping Assessment.
The mitigation measures recommended in this EMP document are based on the impacts in the
environmental scoping report that were identified based on the project description, site
investigation and public input.
The document was compiled as per project information presented to the Consultant by the
Proponent. It was assumed that all the information and data presented was true and accurate.
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
6
Should the scope of the proposed project change, the impacts will have to be reassessed and
mitigation measures provided accordingly.
The following are the project’s roles and responsibilities to be assigned as deemed necessary by the
Proponent pertaining to the implementation of this EMP.
2. EMP ROLES AND RESPONSIBILITIES
The Proponent is ultimately responsible for the implementation of the EMP. Alternatively, the Proponent
may delegate this responsibility at any time, as they deem necessary during the project phases. The
delegated responsibility for the effective implementation of this EMP will rest on the following key
individuals which may be fulfilled by the same person:
Proponent’s Representative (PR): If the Proponent does not manage all aspects of the planning
and design, construction and operation and maintenance phase activities, decommissioning and
rehabilitation, referred to in this EMP, they should assign this responsibility to a suitably qualified
individual referred to in this plan as the Proponent’s Representative (PR). The Proponent may
decide to assign the role of a PR to one person for both phases or a PR may be appointed to
manage the EMP aspects for each project phase. The PR's responsibilities include:
o Managing the implementation of this EMP and updating and maintaining it when
necessary.
o Management and monitoring of individuals and/or equipment on-site in terms of
compliance with this EMP.
o Issuing fines for contravening EMP provisions.
Alternatively, the Proponent may delegate an Environmental Officer (ECO) from within the Municipality
itself or they may appoint an external ECO to ensure EMP compliance throughout the project life cycle.
Environmental Control Officer (ECO) or Safety, Health & Environmental (SHE) Officer /
Occupational Health specialist (OHS): The Proponent should assign the responsibility of
overseeing the implementation of the whole EMP on the ground from the operation and
maintenance to decommissioning phase and rehabilitation to a designated member of staff or
external qualified and experienced person, referred to in this EMP as the Environmental Control
Officer (ECO)/SHE/OHS. The ECO will have the following responsibilities:
o Management and facilitation of communication between the Proponent, PR and
Interested and Affected Parties (I&APs) with regard to this EMP.
o Conducting site inspections (recommended frequency is monthly during the
construction phase and bi-annually for the operation and maintenance) of all
areas with respect to the implementation of this EMP (monitor and audit the
implementation of the EMP).
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
7
o Advising the PR on the removal of person(s) and/or equipment not complying
with the provisions of this EMP.
o Making recommendations to the PR with respect to the issuing of fines for
contraventions of the EMP.
o Undertaking an annual review of the EMP and recommending additions and/or
changes to this document.
Site manager: Overall responsibility for all activities that take place on the project site will reside
with the applicable phase site manager. In this regard the following roles and responsibilities are
applicable:
o The implementation of and compliance with the environmental management
measures proposed in this document.
o Ensuring compliance with relevant environmental and related authorisations and
license conditions.
o Identifying and appointing of appropriately qualified specialists (were necessary)
to undertake the programmes in a timeous manner and to acceptable standards.
Contractors: All contractor EHS representative or site supervisors (as appropriate) will:
o Ensure the relevant commitments contained in the EMP Action Plans are
adhered to;
o Compile relevant procedures and method statements for approval by the
applicable phase site manager prior to initiation of activities;
o Ensure relevant staff are trained in procedures; and
o Maintain records of all relevant environmental documentation.
Specialists: Specialized skills that may be required on an ad-hoc basis or in terms of
environmental support services and independent compliance monitoring and auditing or
maintenance, The Proponent or MEAC will need to contract or appoint suitable/relevant
professionals, as and when required.
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
8
3. ENVIRONMENTAL MANAGEMENT ACTION PLANS
3.1. Key Potential Environmental Impacts to be managed
From the assessment conducted, the following key potential negative impacts have been identified per
project phase and are summarized in Table 2 below.
Table 2: Summary of key potential environmental impacts per project phase
Project Phase Potential impacts identified
1 Planning and design Planning and design failures
2. Construction Soil and water pollution, general environmental pollution, loss
of biodiversity, noise (nuisance), air pollution, odour, vehicular
traffic, health and safety, archaeological or cultural heritage,
social nuisance and property disturbance. Impact on water
use, especially during the construction phase.
3. Operation and maintenance
4. Decommissioning Loss of employment and lack of proper sewage management
facility.
3.2. Aim of the Environmental Management Actions
The aim of the management actions of the EMP is to avoid potential negative impacts where possible.
Where impacts cannot be avoided, measures are provided to reduce the significance of these impacts.
Management actions recommended for the potential impacts rated in the EIA carried out for the proposed
Plant establishment were based on the four project phases listed below:
Planning and design (Table 3)
Construction (Table 4)
Operation and maintenance phase(Table 5)
Decommissioning (Closure) (Table 6).
The responsible persons at the Dunamis Consulting Engineers & Project Managers and/or their
contractors should assess these commitments in detail and should acknowledge their commitment to the
specific management actions detailed in the phases given under the following subchapters.
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
9
3.3. Phase 1: Planning and Design Phase Management Action Plans
The management requirements detailed in Table 3 need to be carried out before any tenders are drafted
for the construction of services infrastructure while necessary preliminary legislative and administrative
arrangements are made in preparation for the operation of the Plant. These management requirements
are also applicable for the period during which engineering designs/drawings are carried out or finalized.
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
10
Table 3: Management Action Plans for the Planning and Design Phase
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe / when?
EMP training Lack of EMP
awareness and
the implications
thereof
Employees appointed for construction work on respective
infrastructure must ensure that all personnel are aware of
necessary health, safety and environmental considerations
applicable to their respective work.
Proponent : ECO Pre-construction
EMP
Implementation
If necessary, a Proponent’s Representative (PR) should be
appointed. The PR that will act as their on-site implementing
agent. This person should be responsible to ensure that the
Proponent’s responsibilities are executed in compliance with
relevant legislation and this EMP.
Proponent: Human
Resources Unit
Pre-construction
Wastewater
Treatment
Technology
Machinery and
equipment
All manufactured materials will be required to bear the mark of
SABS/SANS approval.
The Proponent should ensure that the Plant machinery and
equipment are designed in such a way mechanical failures are
minimal to none.
Proponent
Construction/Mechanical
Engineer
Pre-construction
Water Wastewater /
Effluent discharge
An effluent/wastewater permit should be applied for and obtained
from the Department Water Affairs and Forestry (Water
Environment Division).
Proponent Pre-operational
phase
Water pollution
control
Site stormwater management plans (discharge points) should be
properly designed to prevent the potentially contaminated run-off
from reaching water resources.
To prevent waste discharges from contaminating surface and
groundwater, the discharges must be diverted away from surface
water and onto turf areas or other appropriate areas.
Planning / Structural /
Construction Engineer
Proponent: ECO
Pre-construction
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
11
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe / when?
The site effluent / wastewater and slurry ponds and/or dams
should be lined in order to prevent waste from leaching into the
ground, and potentially into groundwater
Vegetation Site clearing Should the Proponent need to remove certain protected tree
species on and/or around the site, a relevant permit should be
applied for and obtained from the Directorate of Forestry.
Proponent: ECO Pre-removal of the
tree(s)
Labour
recruitment
Priority for most work to be done during the construction and
operational phases should be given to locals, if they have the
skills to undertake the work.
Employment of out-of-area people should only be considered if
the local community does not have the required skills.
Employment should be conducted through the Ndiyona
Constituency office, as this way, the Constituency councillor can
assist the Proponent and/or contractor in obtaining the suitable
people to work on site.
Recruitment of workers should not be done on site, but only
through the Constituency office.
Employment of women, marginalised people and people with
disability should be encouraged.
Proponent and Construction
Contractor / Engineer
Human Resources Units
Pre-construction (for
construction works)
Pre-operational
phase (for operations
works)
Construction
schedule
Schedule A convenient construction work/schedule should be prepared and
be shared with the Ndiyona Constituency office and local
Traditional Authority, so that they can inform the local
communities of when to expect the construction works in the area.
Proponent: ECO or Planning
Unit
Pre-construction
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
12
3.4. Phase 2: Construction Phase Management Action Plans
The management requirements detailed in Table 4 below will be implemented for the construction phase, as per the timeframe provided thereto.
Table 4: Management Action Plans for the Construction Phase
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
EMP training Lack of EMP
awareness and
the implications
thereof
Employees appointed for construction works on respective areas
of the site must ensure that all personnel are aware of necessary
health, safety and environmental considerations applicable to their
respective works.
Proponent: ECO / Safety,
Health & Environment (SHE)
Officer / Occupational Health
specialist (OHS)
Ongoing
Monitoring EMP non-
compliance
The ECO or the Proponent should monitor the implementation of
this EMP.
The ECO should inspect the site operation throughout the
construction period on a weekly basis (4 times a month).
An EMP non-compliance penalty system should be implemented
on site.
Proponent: ECO / SHE Officer
Ongoing
Site Preparation Site Earmarking The Contractor should mark out (e.g. on the ground or with danger
tape) the areas of all Plant buildings before any workers,
equipment or building materials are brought on site. A 2-metre
buffer can be allowed around the perimeter of buildings to allow
construction activities.
The marked-out area should be inspected and approved by the
Site Manager. Thereafter, all site staff should be clearly informed
that they may not move or disturb any areas beyond those limits.
The only land area that may be cleared on site is the roads, the
areas where buildings will be erected, parking bays, driveways
and pathways.
As far as possible, all lay-down areas, such as the areas where
Proponent: ECO / SHE Officer
Site Manager / Construction
Contractor
Pre-construction
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
13
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
building materials and equipment are stockpiled, should be areas
that will later be used for parking, building, or driveways. In other
words, materials should not be stockpiled in surrounding areas
beyond the actual final camp footprint and 2 metre buffer distance.
Sourcing of
materials
Construction
materials
Sand required for construction and other locally-derived building
materials should only be procured from sites that are
environmentally cleared, i.e. sand mining sites that have been
issued with Environmental Clearance Certificates (ECCs).
Proponent: ECO / SHE Officer
Site Manager / Construction
Contractor
Pre-construction
Biodiversity Loss of fauna and
flora
Workers should refrain from killing species (big or small) that may
be found on and around the site.
Workers should refrain from disturbing, killing or stealing locals’
animals and/or small soil animals species found on site.
Environmental awareness on the importance of biodiversity
preservation should be provided to the site contractors and
workers.
With regards to the vegetation on or within proximity of site, the following
mitigation measures should be implemented:
Even if certain vegetation is found within actual site footprint, this
does not mean that it should be removed. Therefore, care should
be taken when preparing the site without destroying the
vegetation.
Vegetation found on the sites, but not on the site infrastructure
footprint should not be removed or disturbed in any way, but
should be left to preserve biodiversity on the site.
Environmental awareness on the importance of biodiversity
Proponent: ECO / SHE Officer
Workers involved in this phase
Ongoing
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
14
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
preservation should be provided to the workers.
Soils Land degradation
and Pollution
Spill control preventative measures should be put in place to
manage soil contamination, no matter how small the amount of
pollution (spill) is.
Spill control preventative measures should be put in place to
manage soil contamination.
Potential contaminants such as hydrocarbons, and wastewater
should be contained on site and disposed of in accordance to
municipal wastewater discharge standards so that they do not
contaminate surrounding soils.
An emergency plan should be available for both major and minor
spills on site in both project phases.
Where hydrocarbons and other chemicals are used during the
project’s phases on site, impermeable liners should be laid on
such sites to capture possible spills, and prevent these substances
from reaching the site soils.
Drip trays should be made available for project vehicles, especially
heavy trucks to contain possible fuel leaks and spills while parked
on site.
In an event that any of the substances mentioned above, spill on
the soil, the contaminated soil should be cleaned up immediately
and dispose of in a designated hazardous waste bin and
transported to the nearest approved landfill site. The contaminated
Proponent: ECO / SHE Officer
Ongoing
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
15
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
and removed soil should be replaced with clean soil.
Air Quality Dust generation The Proponent should ensure that the construction schedule is
limited to the given number of days of the week, but not every day.
This will keep the vehicle-related dust level minimal in the area,
especially when it is windy.
In extremely windy days, a reasonable amount of water should be
used to suppress the dust that may be emanating from certain site
areas (limited to the site only) or certain parts of the local utilized
gravel roads that is generating a lot of dust.
Project vehicles and heavy machines should not be left idling
when not in use, such that they emit air polluting gases.
Proponent: ECO / SHE Officer
Ongoing
Odour The first step in solving any odour problem is identifying the
source. Since this could be caused by a number of different things,
it is best to pinpoint the source of odours with the help of a
professional/specialist in wastewater treatment.
The Proponent should ensure that the Plant machinery and
equipment are designed in such a way or contain technologies
that can help to control or minimize odour.
Some further odour controlling measures can be obtained from
https://www.pollutionequipmentnews.com/how-to-control-odors-at-
wastewater-treatment-plants and these are:
Some options, such as adding chemicals to the water or using
Proponent: Planning / Design
Engineers
Pre- Construction
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
16
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
deodorizing misting systems, reportedly work well to a certain
extent. A sudden change in wastewater composition or weather
can cause the odors to intensify. Fine-tuning the wastewater
treatment process itself is another odor control tactic, but this can
be complex and costly
Covering the problem: Many wastewater treatment plants choose
to seal the source of odour (a tank, basin, or lagoon) with an
industrial-grade cover, thereby preventing the diffusion of odor
vapors. Covering a tank or lagoon to control odors is a rare
example of when covering up a problem makes perfect sense.
Water
Resources
Pollution Potential contaminants such as hydrocarbons (diesel) should be
contained on site and disposed of in accordance to the nearest
municipal wastewater discharge standards so that they do not
contaminate surrounding soils and eventually groundwater.
All run off materials such as hydrocarbons, wastewater and other
potential contaminants should be contained on site in designated
containers and disposed of in accordance to municipal waste
water discharge standards, so that they do not reach to water
systems.
Stormwater management plans (discharge points) should be
constructed on site to prevent the potentially contaminated run-off
from reaching water resources, such as the Kavango River.
The effluent / wastewater containers or ponds should be lined in
order to prevent dissolving waste from leaching into the ground,
Proponent: ECO / SHE officer
Workers involved in this phases
and subsequent phases
Proponent:
Planning/Construction
Engineers
Ongoing and as
when required
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
17
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
and potentially into groundwater.
The transferring of wastewater from the septic tanks to the Plant
should be properly handled, such that spills are avoided at all cost.
This is to ensure that there are no sewage leaks or spills onto the
soils and eventually water resources.
Water availability
(impact on over
abstraction of
water resources
on construction
demands)
Although water is needed for many aspects of construction, it
should be used sparingly at all times.
Water reuse/recycling methods should be implemented as far as
practicable for the construction works.
All water pipes and tanks must be managed and maintained so
that they do not leak and waste water in such manner.
The Proponent should adhere to any licence/permit requirements
of the applicable water and wastewater legislation.
The amount of water supplied by NamWater from the existing
supply line should be used to inform the abstraction rate and water
consumption practices during construction of the proposed Plant.
As per the preceding point, the water management awareness will
aid in ensuring that the construction works are not affecting other
existing users (the School and the local community) that rely on
the same water supply line. This will also lead to an effective water
use and management.
Proponent: ECO / SHE officer
Planning Department
(Proponent) and Construction
Engineers/ Contractor
Ongoing
Health and
Safety
Health and safety
of the workers
As part of their induction, the workers should be provided with
awareness training on how to use site equipment as well as the
Proponent: ECO /
Environmental, Health & Safety
Ongoing
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
18
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
risks of mishandling equipment and materials.
When working on site, employees (for both phases) should be
properly equipped with personal protective equipment (PPE) such
as coveralls, gloves, safety boots, earplugs, safety glasses, etc
depending on the type of work being done.
No employee should be allowed to drink alcohol prior to and
during working hours as this may lead to mishandling of
equipment which results into injuries and other health and safety
risks.
Employees should not be allowed on site if under the influence of
alcohol.
The Proponent should ensure that site is equipped with "danger"
or "cautionary" signs for any potential danger or risk area identified
on site.
During construction phase, a temporary enclosed fence should be
constructed around the site. This is done to control access to the
site, in such a way that the public, especially children do not
access the site and play with equipment and machinery on days
when no work is done.
The site should be equipped with security control gate, once in
operation. This is to limit restrict access to authorized personnel
only
Officer / Occupational Health
specialist
Workers involved in this phases
and subsequent phases
Noise Nuisance The construction times should be set such that, no work is carried
out during the night or very early in the mornings.
Proponent: ECO / SHE Officer
Ongoing
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
19
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
Construction hours should be restricted to between 08h00 and
17h00 to avoid noise generated by construction equipment and
the movement of vehicles before or after hours.
When operating the blasting and drilling machinery onsite, workers
should be equipped with personal protective equipment (PPE)
such as earplugs to reduce noise exposure.
Vehicular Traffic Traffic Safety Drivers of the construction and operational vehicles should be in
possession of valid and appropriate driving licenses.
Vehicle drivers should adhere to the road safety rules.
The Proponent should ensure that the site access road is well
upgraded and in a good condition to cater for vehicles travelling to
and from site throughout the Plant's existence.
Project vehicles should be in a road worthy condition and serviced
regularly in order to avoid accidents as a result of mechanical
faults of vehicles.
Vehicle drivers should only make use of designated site access
roads provided.
Vehicles drivers should not be allowed to operate vehicles while
under the influence of alcohol.
Sufficient parking bays for all project vehicles should be
constructed on site.
The Proponent should make provision for safe offloading and
loading zones on site.
Proponent: ECO / SHE Officer
Workers involved in this phases
and subsequent phases
Ongoing
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
20
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
No heavy trucks or project related vehicles should be parked
outside the project site boundary.
Truck movements, frequency, times and routes should be carefully
planned and scheduled – please refer to the next point.
In order to control traffic movement on site, deliveries from and to
site should be carefully scheduled. This should optimally be during
weekdays and between the hours of 08h00 and 17h00.
Construction vehicles should have a scheduled time for loading
and offloading materials at the site so that they do not interfere
with daily traffic in the area whenever.
Site access and on-site parking and manoeuvring should be
designed in such ways that they do not interfere with other traffic
on site and/or compromise traffic safety.
Waste Environmental
Pollution
Construction and operational workers should be sensitized to
dispose of waste in a responsible manner and not to litter.
After each daily works, the Proponent should ensure that there is
no waste left scattered on site, but rather be disposed of in
allocated site waste bins.
No waste may be buried or burned on site or anywhere else
throughout the project lifecycle.
All domestic and general construction waste produced on a daily
basis should be contained until such that time it will be transported
to designated waste sites on a bi-weekly basis during construction
and on a weekly basis during operations.
The sites should be equipped with separate waste bins for
Proponent: ECO / SHE Officer
Workers involved in this phase
Ongoing
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
21
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
hazardous and general waste/domestic.
A penalty system for irresponsible disposal of waste on site and
anywhere in the area should be implemented.
Hazardous waste and other chemicals should be safely stored on
site and later (as required) transported to the nearby approved
hazardous waste sites for safe disposal.
No waste should be improperly disposed of on site or in the
surroundings, i.e. unapproved waste sites.
Empty hazardous substance containers should not be disposed of
anywhere on the project site or its surrounding, but should be
stored on site and safely taken to the nearest approved hazardous
waste sites.
Human Health Hazardous waste, including emptied chemical containers used
during this phase should be safely stored on site where they
cannot be reached and used by the unsuspecting and uniformed
locals for personal use. No waste should be improperly disposed
of on site or its surroundings, i.e. unapproved waste sites.
As an emphasis on the preceding point, empty hazardous
substance containers should not be disposed of anywhere on the
project site or its surrounding, but instead they should be kept at a
designated storing place on site until such time that they can be
safely taken and disposed of at the nearest approved hazardous
waste sites.
Proponent: ECO / SHE Officer
Archaeological Impact on
unknown cultural
or heritage
The Proponent should consider having a qualified and
experienced archaeologist on standby during the construction
phase. This measure will be to assist on the possible of
Proponent: ECO / SHE Officer
As and when
required
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
22
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
sites/objects uncovering of sub-surface graves or other cultural/heritage objects
during site preparation (earthworks) and advice the Proponent
accordingly.
Identified of any archaeological significant objects on the site
should not be disturbed, but are to be reported to the project
Environmental officer or National Heritage Council offices for
further instructions and actions.
Workers should be educated to not destroy or throw away but
report (to the environmental officer) of any unknown object
found/discovered on site during earthworks during the construction
or even during operations.
Social Influx of outsiders
into the area
The Proponent and its project contractors should prioritize the
employment of local people, and only if necessary and due to lack
of skills in the area, out-of-area people can be given some of the
work. This is to avoid the influx of outsiders into the area.
The locals to be employed during the project phases should be
provided with the necessary training of skills required for the
project to avoid bringing in many out-of-area employees.
The workers should be engaged in health talks and training about
the dangers of engaging in unprotected sexual relations which
results in contracting HIV/AIDS and other sexual related infections.
Out-of-area workers that may be employed (due to their unique
work skills) on site should be sensitized on the importance of
respecting the local values and norms, so that they can co-live in
harmony with the local community.
Construction workers or any project related worker should be
prohibited from getting involved in sexual relations and/or engage
Proponent and Contractor(s):
Human Resources Unit
Pre-construction
and/or Operational
Phase
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
23
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
in sexual activities with school learners. This does not only apply
to Linus Shashipapo Secondary School learners, but all the
schools in the area.
Any construction worker who will be found or seen engaging in
sexual relations with a school learner shall be reported to the site
manager and necessary actions taken against that worker.
Potential damage
or disturbance to
private properties
The Proponent and its project contractors should inform their
workers on the importance of respecting the locals' properties by
not intruding or damage their homes, fences or killing their
livestock.
Any workers or site employees that will be found guilty of intruding
peoples 'privately owned properties should be called in for
disciplinary hearing and/or dealt with as per their employer's code
of employment conduct
Site workers should be advised to respect the community and
local's private properties, values and norms.
No worker should be allowed to wander in people's private yards
or fences.
Site workers are not allowed to kill or in any way disturb local
livestock.
No worker should be allowed to, without permission cut down or
damage trees belonging either to the School, neighbouring
homestead or in the community vegetation/forests.
3.5. Phase 3: Operational and Maintenance Phase Management Action Plans
The management action plans recommended for operations and site maintenance are presented in Table 5 below.
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
24
Table 5: Management action plans for the Operation and Maintenance Phase
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
EMP training Lack of EMP
awareness and
the implications
thereof
Employees appointed for construction works on respective areas of
the site must ensure that all personnel are aware of necessary
health, safety and environmental considerations applicable to their
respective works.
Proponent: ECO / SHE
Officer
Ongoing
Monitoring EMP non-
compliance
The ECO or the Proponent should monitor the implementation of this
EMP.
The ECO should inspect the site operation throughout the
operational phase on a bi-annual basis (every 6 months).
An EMP non-compliance penalty system should be implemented on
site.
Proponent: ECO / SHE
Officer
Ongoing
Biodiversity Loss of fauna and
flora
Management action plans provided under the Construction Phase apply
to this phase
Proponent: ECO / SHE
Officer
Workers involved this phase
Ongoing
Soils Land degradation
and Pollution
Management action plans provided under the Construction Phase apply
to this phase
Proponent: ECO / SHE
Officer
Ongoing
Air Quality Dust generation Management action plans provided under the Construction Phase apply
to this phase
Proponent: ECO / SHE
Officer
Ongoing
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
25
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
Water
Resources
Pollution Potential contaminants such as hydrocarbons (diesel) should be
contained on site and disposed of in accordance to the nearest
municipal wastewater discharge standards so that they do not
contaminate surrounding soils and eventually groundwater.
An emergency plan should be available for major / minor
hydrocarbon spills during construction activities and during the
transportation of the product(s) to the site.
Proponent: ECO / SHE
Officer
Workers involved this phase
Ongoing
Health and
Safety
Health and safety
of the workers
As part of their induction, the workers should be provided with an
awareness training of the risks of mishandling equipment and
materials on site.
When working on site, employees should be properly equipped with
personal protective equipment (PPE) such as coveralls, gloves,
safety boots, earplugs, safety glasses, etc depending on the type of
work being done.
Employees should not be allowed on site if under the influence of
alcohol.
The Proponent should ensure that site is equipped with "danger" or
"cautionary" signs for any potential danger or risk area identified on
site. This will not only safeguard the site workers, but the community
accessing the site during visitations and burials during the operation
phase.
No employee should be allowed to drink alcohol prior to and during
working hours as this may lead to mishandling of equipment which
results into injuries and other health and safety risks.
Proponent: ECO / SHE
Officer
Workers involved in this
phase
Ongoing
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
26
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
Vehicular Traffic Traffic Safety Drivers of the construction and operational vehicles should be in
possession of valid and appropriate driving licenses.
Vehicle drivers should adhere to the road safety rules.
Project vehicles and machinery should be serviced regularly in order
to avoid accidents as a result of mechanical faults of vehicles and
machines.
Proponent: ECO / SHE
Officer
Ongoing
Noise nuisance Operational works should be limited carried out on between 08h 00
and 17h 00.
For the rest of the management action plans, please refer to
management action plans provided under the Construction Phase
Proponent: ECO / SHE
Officer
Ongoing
Waste
generation
Environmental
Pollution
Management action plans provided under the Construction Phase apply
to this phase
Proponent: ECO / SHE
Officer
Ongoing
Human health Hazardous waste, including emptied chemical containers (liquid
chlorine, sodium hypochlorite) and other chemicals used for
disinfection in the operational phase should be safely stored on site
where they cannot reached and used by the unsuspecting and
uniformed locals for personal use. No waste should be improperly
disposed of on site or its surroundings, i.e. unapproved waste sites.
In order to discourage the unsuspecting and uniformed local
community from eyeing the empty hazardous containers, if possible
holes should be drilled in these containers while kept on site (before
transporting the containers to the waste site). This is also where the
fencing of the site is vital throughout the two project phases to
Proponent: ECO / SHE
Officer
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
27
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
restrict unauthorized public/local site access.
Archaeological Impact on
unknown cultural
or heritage
sites/objects
Management action plans provided under the Construction Phase apply
to this phase
Proponent: ECO / SHE
Officer
As required
Waste Environmental
pollution
Management action plans provided under the Construction Phase apply
to this phase
Proponent: ECO / SHE
Officer
Workers involved in this
phase
Ongoing
3.6. Phase 4: Decommissioning Phase
The management action plans recommended for closure are presented in Table 6 below.
Table 6: Management action plans for the Closure (Decommissioning) Phase
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
Plant closure Lack of proper
wastewater
management and
Loss of
employment
The Proponent should, consider making arrangements well in
time for new irrigation water provisions and to continue with
managing the School' sewage.
The Proponent should inform the employed people on site of their
intentions to close the Plant and the expected date of such
closure (at least 6 months in advance). This will provide the
Proponent: Planning
Department
Proponent: ECO / SHE
Officer
Pre-decommissioning
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
28
Environmental Feature
Impact Management Actions Responsible person(s) / Implementation responsibility
Timeframe (When?)
employees with enough time to search for work elsewhere and to
seek alternate employment in the event that they seek to avoid
formal retrenchment.
The Proponent should raise awareness of the possibilities for
work in similar or other sectors in the area or Kavango Regions.
29
4. ENVIRONMENTAL MONITORING
Monitoring is the primary way of establishing how well the management system is operating. The
extent of monitoring will depend on the size, scale and nature of the facility, the proximity of any
developed or urban, and the nature of the local environment (edited after Latto et. al., 2000). In other
words, to maintain a low significance rating of potential impacts through implementation of
management action plans, it is worthwhile that regular monitoring of the mainly affected
environmental components is conducted.
4.1. Physical Environmental Monitoring
The following components have been identified suitable for monitoring:
Water (both surface and groundwater);
Dust;
Soils; and
Waste (waste water/effluent, slurry and manure).
The list of environmental components to be monitored and their details are given in Table 7.
30
Table 7: Environmental monitoring program for the construction and operational phases
Component Parameter Project
Phase
Frequency Location
Groundwater Water quality: Ammonium nitrogen, chloride,
nitrate-nitrogen, nitrite-nitrogen, potassium, total
dissolved phosphorus, pH, electrical conductivity
(EC), bicarbonate, calcium, dissolved organic
carbon, magnesium, sodium, sulphate, total
dissolved solids, an ion balance, and Escherichia
coli
Operational Quarterly (in April and
then October)
Readings should be taken from all nearby
boreholes within 2 km of the project site. The
right boreholes to be tested for water quality
would be upstream (south of the Plant site) and
downstream (north of the Plant). However, there
are no recorded boreholes downstream of the
site. In this case, surface water monitoring
should be emphasized.
Surface water Water quality Operational Monthly (during rainy
season)
In the nearest open water bodies (Kavango
River)
Soil Phosphorus, nitrate nitrogen (NO3-N), EC, pH
and Chloride
Operational Bi-annually Next to sewage/wastewater tanks or dams sites,
and truck loading and offloading areas
Dust Fallout Construction Weekly To the east and west of site
Effluent /
wastewater
pH, electrical conductivity, orthophosphate-P,
potassium, sodium adsorption ratio, total
nitrogen, total phosphorus, Total Suspended
Solids (TSS) and Total Dissolved Solids (TDS)
Operational Bi-annually (every 6
months)
At the effluent collecting and storing ponds or
dams. This will mainly be determined by the
effluent discharge permit from the Department of
Water Affairs and Forestry.
31
4.2. Occupational Health and Safety Monitoring Program
According to Mafuta Environmental Consultants (2018), the occupational health and safety monitoring
program should include the following:
4.2.1. Surveillance of the working environment:
The Proponent and/or eventual Plant Operator should document compliance using an appropriate
combination of portable and stationary sampling and monitoring instruments. Monitoring of
environmental parameters given under Table 7 above should be conducted according to
internationally recognized methods and standards and as recommended. Generally, monitoring
should be performed during commissioning of facilities or equipment and at the end of the defect and
liability period, and otherwise repeated according to the monitoring plan.
4.2.2. Surveillance of workers health
When extraordinary protective measures are required, workers should be provided appropriate and
relevant health surveillance prior to first exposure and at regular intervals thereafter. The surveillance
should, if deemed necessary, be continued after termination of the employment.
4.2.3. Training
Training activities for employees and visitors should be adequately monitored and documented
(curriculum, duration, and participants). Emergency exercises, including fire drills, should be
documented adequately. Service providers and contractors should be contractually required to submit
to the Project Proponent / Owner / Operator adequate training documentation before commencing
with their assignment / task at the site.
4.2.4. Accidents and diseases monitoring
The Proponent or the Contractors should establish procedures and systems for reporting and
recording:
Occupational accidents and diseases; and
Dangerous occurrences and incidents.
These systems should enable workers to report immediately to their immediate supervisor any
situation they believe presents a serious danger to life or health. The systems and the Proponent /
Operator should further enable and encourage workers to report to management all:
Occupational injuries and near misses;
Suspected cases of occupational disease; and
Dangerous occurrences and incidents.
Environmental Management Plan (EMP)
Linus Shashipapo Secondary School Wastewater Treatment Plant - September 2019
32
All reported occupational accidents, occupational diseases, dangerous occurrences, and incidents
together with near misses should be investigated with the assistance of a person knowledgeable/
competent in occupational safety. The investigation should:
Establish what happened;
Determine the cause of what happened; and
Identify measures necessary to prevent a recurrence.
4.2.5. Contingency Plan
An emergency is an unplanned event when a project operation loses control, or could lose control of a
situation that may result in risks to human health, property, or the environment, either within the
facility or in the local community. Emergencies do not normally include safe work practices for
frequent upsets or events that are covered by occupational health and safety. The Emergency
Preparedness and Response Plan should include the following basic elements:
Administration (policy, purpose, distribution, definitions, etc.);
Organization of emergency areas (command centres, assembly points, fire suppression
equipment and escape plans);
Roles and responsibilities;
Communication systems;
Emergency response procedures;
Emergency resources;
Training and updating;
Checklists (role and action list and equipment checklist); and
Business Continuity and Contingency.
5. CONCLUSION
MZ-15 EHS Consultants are confident that the potential negative impacts associated with the
proposed Plant activities, can be adequately mitigated by the implementation and monitoring of
recommended management action plans. Therefore, it is recommended that the project be issued
with an Environmental Clearance Certificate. This will be on condition that the EMP is implemented
and actions contained therein are monitored in order to maintain low significance and ensure medium
rating impacts get to a low rating.