78
REGIONAL WASTEWATER FACILITY STUDY FOR THE CITIES OF DENISON AND POTTSBORO REPORT REPORT July 2005 in association with July 2005 in association with

regional wastewater facility study for the cities of denison and

Embed Size (px)

Citation preview

  • REGIONAL WASTEWATER FACILITY STUDY FOR THE CITIES OF DENISON AND POTTSBORO

    REPORTREPORT

    July 2005

    in association with

    July 2005

    in association with

  • F:\projects\850\0101\Doc\Report\Final\Contents.doc i

    TABLE OF CONTENTS Page List of Tables ......................................................................................................................... ii List of Figures ........................................................................................................................ iii Executive Summary............................................................................................................... ES-1 Chapter I Introduction......................................................................................................... I-1 Background ............................................................................................................................ I-1 Project Scope ......................................................................................................................... I-2 Chapter II Population and Flow Projections....................................................................... II-1 Background ............................................................................................................................ II-1 Chapter III Preliminary Assessment of Site-Specific Permitting Issues ............................ III-1 Evaluation of Discharge Locations........................................................................................ III-1 Little Mineral Creek Arm of Lake Texoma........................................................................... III-1 Unnamed Tributary that Flows Through Hagerman National Wildlife Refuge .................... III-3 Scott Branch........................................................................................................................... III-4 Red River Below Lake Texoma............................................................................................. III-5 Other Considerations ............................................................................................................. III-5 Conclusions............................................................................................................................ III-6 Chapter IV Economic Evaluation of Collection System Costs for Alternative Sites ......... IV-1 Evaluation Criteria ................................................................................................................. IV-1 Option 1: Preston Harbor Development Site ......................................................................... IV-2 Option 2: Regional Treatment Facilities at Existing Pottsboro Plant Site............................. IV-4 Option 3: Regional Facility (Northwest of Grayson County Airport) ................................... IV-8 Option 4: Regional Treatment Facilities on Scott Branch ..................................................... IV-11 Site Selection ......................................................................................................................... IV-14 Chapter V Treatment Process Evaluation ........................................................................... V-1 Existing Pottsboro WWTP..................................................................................................... V-1 Proposed Regional Facility at the Northwest Grayson County Airport Site ......................... V-9 Conventional, Mechanical Treatment System for the Regional Facility............................... V-9 Natural Treatment System for the Regional Facility ............................................................. V-14 Remote Effluent Discharge and Reuse System Considerations ............................................ V-14 Summary................................................................................................................................ V-16 Chapter VI Conclusion and Recommendations.................................................................. VI-1 Appendix A - Natural Treatment Systems - General Discussion Appendix B -TCEQ Meeting Minutes Appendix C - USFWS Meeting Minutes

  • F:\projects\850\0101\Doc\Report\Final\Contents.doc ii

    LIST OF TABLES Table No. Description Page ES-1 Summary of Projected Timing and Capital Costs.............................. ES-5 II-1 Population Projections of Major Cities Including Grayson County .. II-3 II-2 City of Pottsboro Populations and Flows .......................................... II-3 II-3 Drainage Basins and Projected Population ........................................ II-6 II-4 Drainage Basins and Projected Design Flows ................................... II-6 II-5 Drainage Basins and Projected Peak Flows....................................... II-7 IV-1 Opinion of Probable Collection Cost for Option 1 ............................ IV-6 IV-2 Opinion of Probable Collection Cost for Option 2 ............................ IV-10 IV-3 Opinion of Probable Collection Cost for Option 3 ............................ IV-11 IV-4 Opinion of Probable Collection Cost for Option 4 ............................ IV-13 IV-5 Cost Comparison and Ranking .......................................................... IV-14 V-1 Opinion of Probable Project Cost ...................................................... V-19 VI-1 Summary of Projected Timing and Capital Costs.............................. VI-3

  • F:\projects\850\0101\Doc\Report\Final\Contents.doc iii

    LIST OF FIGURES Figure No. Description Page ES-1 Regional System Facilities for Recommended Option...................... ES-2 ES-2 Summary of Projected Schedule........................................................ ES-6 I-1 Drainage Basins ................................................................................. I-3 II-1 Study Area and 2000 Census Blocks ................................................. II-2 II-2 Natural Drainage Basins .................................................................... II-4 II-3 Historical Flows 1998-2003 (Freese and Nichols) ............................ II-5 IV-1 Drainage Basins and Four Potential Sites.......................................... IV-3 IV-2 Sewage Collection System for Site 1 (Option 1) ............................... IV-5 IV-3 Sewage Collection System for Existing Pottsboro WWTP Option 2)............................................................................... IV-7 IV-4 Sewage Collection System for Northwest GCA Site (Option 3).................................................................................... IV-9 IV-5 Sewage Collection System for Potential Site 3 (Option 4)........................................................................................... IV-12 V-1 Process Flow schematic for Existing Pottsboro WWTP.................... V-3 V-2 Site Layout for Existing Pottsboro WWTP ....................................... V-4 V-3 Process Flow schematic for 0.9 MGD Facility.................................. V-6 V-4 Site Layout for 0.9 MGD Facility...................................................... V-7 V-5 Site Layout for 2.0 MGD Facility...................................................... V-8 V-6 Process Flow schematic for 2.0 MGD Facility.................................. V-11 V-7 Process Flow Schematic for Conventional Treatment Plant for First Phase .................................................................................... V-12 V-8 Site Layout for Proposed Consolidated Regional WWTP................. V-13 V-9 Process Flow Schematic for Natural Treatment Plant for First Phase ......................................................................................... V-15 V-10 Treated Effluent Discharge Locations for Existing Pottsboro WWTP............................................................................... V-17 V-11 Treated Effluent Discharge Locations for Northwest GCA Site ....... V-18

  • F:\projects\850\0101\Doc\Report\Final\Executive Summary.doc ES-1

    EXECUTIVE SUMMARY

    The Cities of Denison and Pottsboro recognize the potential for significant commercial and

    residential development along the shore of Lake Texoma in areas generally west of the City of

    Denison. Residential growth in Pottsboro, the potential for commercial, residential, and

    industrial development in the area near the Grayson County Airport, and significant commercial

    and residential developments planned in the Little Mineral Creek area have suggested the need

    for planning for future wastewater services for these areas. The cities of Denison and Pottsboro

    jointly collaborated on this planning effort, with assistance and coordination provided by the

    Greater Texoma Utility Authority (GTUA), and with funding assistance provided by the Texas

    Water Development Board. The following is a synopsis of the conclusions of this evaluation.

    1. Significant potential for development exists in the study area delineated in

    Figure ES-1. It is projected that, within the next 50-60 years, the entire study area

    could produce wastewater flows averaging approximately 7 MGD.

    2. The study area encompasses a relatively large geographic area (possibly larger than

    Denison's current wastewater service area), but with a low initial population

    density. This fact, coupled with the fact that the study area drains into six different

    watersheds, will dictate a regional collection network that will be more expensive

    than would be expected in more densely populated areas.

    3. It has been determined during the study period that the City of Pottsboro's existing

    wastewater treatment plant, while currently near capacity, can likely be permitted

    and expanded (in phases) to a future capacity of approximately 2.0 MGD. This site

    is believed to be the most economical and expeditious location for providing

    wastewater treatment services to the City of Pottsboro and to areas within the City

    of Denison's Certificate of Convenience and Necessity (CCN) lying within the

    peninsula to the east of the Little Mineral Arm of Lake Texoma. However, permit

  • "

    "

    "

    "

    "

    "

    "

    #

    #

    D

    D

    D

    D

    DD

    D

    D DD

    D

    Basin 1

    Basin 5

    Basin 6

    Basin 2

    Basin 3

    Basin 4 Denison

    Pottsboro

    Sherman

    Sadler

    HAGERMAN NATIONAL WILDLIFE REFUGE

    2

    3

    4

    6

    5C

    LMA

    WGCA

    Regional WWTP

    Expanded Pottsboro WWTP

    Monarch Ridge

    Diamond Pointe

    Resort Communties

    Retail Developments

    Retirement Communities

    Grand Pappy Residentials

    Schuler / Preston Harbor

    Northwest Resort Community

    Preston Harbor Town Center

    Preston / 84 West Residentials

    F:\8

    50\0

    101\

    GIS

    \figu

    re-E

    S-1

    .mxd

    cr

    l

    0 1 20.5

    Miles

    Figure ES-1

    Regional System Facilities for Recommended Option

    LegendD Developments

    # Proposed WWTP Sites

    " Future

    " Initial

    Sewer LinesFuture GravityFuture Force MainInitial GravityInitial Force MainRoadsRail Roads

    Lakes

    Streams

    State Park

    Refuges

    Airport

    City

    Drainage BasinsBasin 1

    Basin 2

    Basin 3

    Basin 4

    Basin 5

    Basin 6

  • F:\projects\850\0101\Doc\Report\Final\Executive Summary.doc ES-3

    limits and land availability suggest that this site may not be appropriate for growth

    beyond a 2 MGD capacity.

    4. Consistent with planning conducted in 2000, it is recommended that actions be

    initiated for land acquisition and permitting for a future regional wastewater

    treatment plant to be located along the southwestern boundary of the study area,

    west of the Grayson County Airport. It is suggested that this treatment system be

    initially designed for 0.9 MGD, but that sufficient land be acquired to preserve

    options for future treatment capacity of up to 7 MGD. If permitting difficulties

    make it necessary, it is anticipated that effluent from the regional facility would

    ultimately be pumped northward for discharge into Scott Branch, or to other

    portions of the study area for reclamation.

    5. It is envisioned that the expanded Pottsboro plant site, depending on rate of

    development and reclaimed water demands in the study area, would serve as a

    "water factory" providing high quality treated effluent to golf courses and other

    potential reclaimed water users in its immediate vicinity and northward. On a long-

    term basis, it is recommended that the cities preserve the option to either continue

    discharging from the Pottsboro plant, use the Pottsboro plant for water reclamation

    for the northern and eastern parts of the study area, or pursue abandonment with

    pumping to the proposed regional plant site west of the Grayson County Airport.

    6. Areas north and west of the proposed plant site near the Grayson County Airport

    would eventually be served, as population growth dictates need, by a linked system

    of force mains and lift stations located in individual drainage basins (Basins 2,3,

    and 4). Similarly, Basin 6 (The area lying between Denison and the Little Mineral

    peninsula) would be linked to the regional system as growth and demands justify

    construction of pipeline facilities.

    Our opinion of probable capital costs for "regional" components of the proposed wastewater

    system to be initially constructed (prior to 2010) is approximately $16 million, expressed in 2005

  • F:\projects\850\0101\Doc\Report\Final\Executive Summary.doc ES-4

    dollars. Many of these improvements will be phased in over an extended period of time.

    Table ES-1 lists a proposed schedule and cost associated with the major components anticipated

    to be needed within the initial years of operation. Future components can be constructed as

    dictated by growth and demand in the service area.

    At the time of this report, institutional arrangements between the Cities of Denison and

    Pottsboro, and/or other potentially interested agencies have not been finalized. It is assumed that

    while the Pottsboro WWTP remains in service, it will continue to be owned and operated by the

    City of Pottsboro. Discussions to date regarding the future Regional WWTP preliminary identify

    the City of Denison as the owner and operator of the plant, with the City of Pottsboro being a

    contract customer. These arrangements should be finalized as soon as possible, prior to any

    discharge permit application, land purchase, etc. Some economics of scale benefiting both cities

    may be available through a coordinated or "regional" operation arrangement rather than having

    each City own and operate independent systems. Figure ES-2 shows a suggested table for

    implementation of improvements.

  • TABLE ES-1

    ACTION BUDGET(2005 $)

    EXIST. POTTSBORO EXPANSION TO 0.9 MGD $3,635,000EXIST. POTTSBORO EXPANSION TO 2 MGD $2,669,000" REGIONAL" WWTP (0.9 MGD INTERIM) $5,660,000Note: Cost shown reflects mechanical system. Natural system, if permitted, will be less

    LS, FM, & INTERCEPTOR TO SERVE " REGIONAL" WWTP $3,864,000

    TOTAL OPINION OF PROBABLE COST $15,828,000

    Prepared By Mark A. Perkins Texas PE 60329

    Note: Costs presented above include 15% contingency, along with allowances for engineering, surveying, and land acquisition for major components. Costs associated with connection of the proposed Preston Harbor development to the Pottsboro treatment system are discussed in this report, but are not included in this table.

    GREATER TEXOMA UTILITY AUTHORITYREGIONAL WASTEWATER FACILITIES FOR THE CITIES OF DENISON AND POTTSBORO

    SUMMARY OF PROJECTED PROJECT COSTS

    PRELIMINARY

  • ACTIONPERMIT APPLICATION PREP. FOR EXIST. POTTSBORO PLANT SITE

    PERMIT PROCESSING (TCEQ) FOR EXIST. POTTSBORO SITE

    DESIGN EXIST. POTTSBORO EXPANSION TO 0.9 MGD

    CONSTRUCT EXIST. POTTSBORO EXPANSION TO 0.9 MGD

    DESIGN EXIST. POTTSBORO EXPANSION TO 2 MGD

    CONSTRUCT EXIST. POTTSBORO EXPANSION TO 2 MGD

    SITE SELECTION FOR "REGIONAL" WWTP

    SITE OPTION ACQUISITION *

    PERMIT APPLICATION PREP & PRELIMINARY DESIGN

    PERMIT PROCESSING (TCEQ) FOR "REGIONAL" SITE

    DESIGN "REGIONAL" WWTP (0.9 MGD INTERIM)

    CONSTRUCT " REGIONAL" WWTP (0.9 MGD INTERIM)

    Note: Cost shown reflects mechanical system. Natural system, if permitted, will be less

    DESIGN LS, FM, & INTERCEPTOR TO SERVE " REGIONAL" WWTP

    CONSTRUCT LS, FM, & INTERCEPTOR

    Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q42005 2006 2007 2008 2009

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    FIGURE ES-2GREATER TEXOMA UTILITY AUTHORITY

    REGIONAL WASTEWATER FACILITIESFOR THE CITIES OF DENISON AND POTTSBORO SUMMARY OF PROJECTED SCHEDULE

    PRELIMINARY

    Page 1

    Project: ES-2

  • F:\projects\850\0101\Doc\Report\Final\Chapter I.doc I-1

    CHAPTER I

    INTRODUCTION The Cities of Denison and Pottsboro, with coordination by the Greater Texoma Utility Authority

    and with funding assistance from the Texas Water Development Board, have entered into this

    study to identify wastewater collection and treatment facilities needed for areas lying generally

    west of Denison. The study area boundaries generally encompass the City of Pottsboro, the

    Grayson County Airport, and essentially all currently-unsewered land between Denison and the

    Big Mineral Arm of Lake Texoma. The City of Denison operates an aging wastewater treatment

    system at the Grayson County Airport; the City of Pottsboro operates a plant north of Pottsboro

    along Little Mineral Creek. Neither system is currently sized to handle long-term growth

    anticipated in the area. The cities desire a plan to provide wastewater service to the entire study

    area.

    Background

    Significant growth is expected within Grayson County over the coming years. Among the major

    drivers for this anticipated growth are a large private development along the east side of the

    Little Mineral Arm of Lake Texoma, expansion plans at the Tanglewood development, TxDOTs

    plans to extend S.H 289 further north, and commercial development planned along the western

    portion of the airport property. In turn, these drivers are anticipated to encourage further

    development at the Airport and other areas. Much of this anticipated development lies within the

    CCNs of the Cities of Denison and Pottsboro. Recognizing the need for wastewater facilities to

    accommodate this growth, the Cities of Denison and Pottsboro entered into this cooperative

    agreement to explore the possibility of forming a regional wastewater system to serve these areas

    of anticipated growth. A regional approach offers the possibility of distributing infrastructure

    costs over a larger rate base and consolidating certain operations. A major objective of this study

    is to define recommended components of a regional wastewater system, identify the costs for

    these components, and develop a preliminary implementation plan.

  • F:\projects\850\0101\Doc\Report\Final\Chapter I.doc I-2

    The Greater Texoma Utility Authority (GTUA) agreed to coordinate this the study for Denison

    and Pottsboro, and was responsible for coordinating Texas Water Development Board funding to

    assist with the study. Freese and Nichols, Inc. served as a sub consultant.

    The area studied under this project (Figure I-1) comprises the northwest part of Grayson County

    including the Grayson County Airport and the surrounding area, the City of Pottsboro, a portion

    of Hagerman Wildlife Refugee, developments on the shores of Lake Texoma, and the

    northwestern part of the City of Denison.

    The current capacities of the existing Pottsboro Wastewater Treatment Plant (WWTP) and the

    Grayson County Airport WWTP are 0.35 million gallons per day (MGD) and 0.4 MGD,

    respectively. The combined capacity of both of the plants is inadequate to treat current flows

    from the entire study area, and the plants may not be in ideal locations to accommodate future

    growth. The existing developments at the Lake Texoma shores utilize individual septic tank

    systems for sewage disposal.

    Several major issues have been considered in this evaluation. The major issues include

    potentially stringent permit limits at specific discharge locations, plus challenges associated with

    the fact that the study area naturally drains several different directions.

    Project Scope

    The scope of work includes of the following:

    Analysis of Existing Wastewater Systems:

    o Review Population and Flow Growth and

    o Delineate Sewershed in the study area.

    Master Planning and Flow Projections:

    o Estimating population and flow projections through the year 2060,

    o Identifying up to four locations for the potential regional wastewater treatment

    plant site for the study area, and

    o Studying selected sites from a feasibility perspective.

  • D

    D

    D

    D

    DD

    D

    D DD

    D

    Basin 1

    Basin 5

    Basin 6

    Basin 2

    Basin 3

    Basin 4 Denison

    Pottsboro

    Sherman

    SadlerKnollwood

    HAGERMAN NATIONAL WILDLIFE REFUGE

    Monarch Ridge

    Diamond Pointe

    Resort Communties

    Retail Developments

    Retirement Communities

    Grand Pappy Residentials

    Schuler / Preston Harbor

    Northwest Resort Community

    Preston Harbor Town Center

    Preston / 84 West Residentials

    F:\8

    50\0

    101\

    GIS

    \figu

    re-I-

    1.m

    xd

    crl

    0 1 20.5

    Miles

    Figure I-1

    Drainage Basins

    LegendD Developments

    Rail Roads

    Roads

    Lakes

    Streams

    Refuges

    State Park

    City

    Airport

    Drainage BasinsBasin 1

    Basin 2

    Basin 3

    Basin 4

    Basin 5

    Basin 6

  • F:\projects\850\0101\Doc\Report\Final\Chapter I.doc I-4

    Wastewater Discharge Permit Assessment:

    o Anticipating future permit limits and

    o A Preliminary Assessment of Critical Issues that might make permitting difficult

    or impossible at selected locations.

    Wastewater Treatment Alternatives:

    o Selecting preliminary sites for potential regional wastewater treatment plant(s)

    and

    o Evaluating the feasibility of Natural and Conventional treatment processes.

    Detailed Alternative Analysis:

    o Planning treatment processes and

    o Recommending a suitable site and treatment process.

  • F:\projects\850\0101\Doc\Report\Final\Chapter II.doc II-1

    CHAPTER II

    POPULATION AND FLOW PROJECTIONS This chapter addresses the historical population information for Grayson County, the drainage

    basins comprising the study area, the population and flow projections for each drainage basin.

    Background

    The study area generally lies between the City of Denison and the Big Mineral arm of Lake

    Texoma, and includes the City of Pottsboro, the Grayson County Airport, the Tanglewood area,

    and currently-undeveloped land slated for significant residential development. Figure II-1 shows

    the boundaries of the study area and the year 2000 census blocks.

    Using the spatial information available on the Environmental Systems Research Institute (ESRI)

    website, the study area is divided into the drainage basins according to their natural topography.

    This delineation helped to configure and classify the sewage lines, as gravity and force main,

    throughout the study area and identify the potential locations, if necessary, for wastewater

    treatment facilities.

    Year 2000 census and population projections for Grayson County were obtained from the Texas

    Water Development Board (TWDB) website. The TWDB website also lists the population

    projections for Grayson County through the year 2060. The population projections in the study

    area are calculated by applying the growth coefficients used for the entire Grayson County.

    Table II-1 shows the population projections of the major cities and Grayson County as a whole.

  • Study Limits

    Refuge

    Pre

    sto n

    Plainview

    Helen

    Wright

    Day

    Kat

    y

    Mi ri

    c k

    TexasHull

    Airp

    ort

    Main

    Hagerman

    Texoma

    Morton

    United S

    tat es Highw

    ay 75

    Davy

    Sears

    Har

    den b

    ergEn t

    erpr

    ise

    Old

    Sa d

    ler

    Terr

    y

    Cor

    del l

    L ill is

    Arthur

    Bennett

    Highway

    75

    Farm-to-Market Road 120

    Ther

    e sa

    Des

    v oig

    nes

    Georgetown

    Earl

    Aus

    t in

    Har

    vey

    Keyes

    Fann

    in

    Reeves

    Farm- to-M

    arket Road 9 01

    Dickey

    Bar

    ret t

    Juan

    ita

    Locust

    Pea

    rce

    Ke e

    fer

    Ha n

    na

    Cemetery

    Wildli

    fe

    Arm

    stron

    g

    Sta

    te H

    igh w

    a y 9

    1

    Ffa

    Ray

    Well

    Mil l

    Cre

    ek

    Ky ke r

    Big Mineral

    Quail Run

    Farm-to-Market Road 691

    Eis

    enho

    wer

    Hig

    hlan

    d

    Randell L ake

    F ar m

    -to-M

    arke

    t Roa

    d 14

    17

    Cedar Mills

    Law

    ren c

    e

    Tra vis

    Lake

    Par

    k

    Trail

    6th

    F ul ton

    Rus

    k

    Loy

    Lake

    United States Highway 69

    Edd

    y

    Brady

    Kus

    c h

    Kirk

    Morgan

    5th

    Fran

    k

    Toy

    Farm-to-Market Road 406

    Mau

    ri ce

    Short

    County

    Brooks

    Rio R

    o xo

    Murray

    Dripping Spring

    Elliot

    Arkansas

    Randell

    McC

    lain

    Farm

    -to-M

    arke

    t Roa

    d 13

    1

    Kel

    soe

    Tang

    lew

    ood

    Preston BendD

    ot y

    Denton

    Flora

    Middle

    GiesC

    ooks

    Co r

    n er

    Squ

    irre l

    Hillcrest

    Cemetary

    Richerson

    Loy

    Col

    lege

    Pelts

    Glenwood

    F F

    A

    United S

    tates Highw

    ay 377

    Hill

    Fallon

    Oxford

    Sco

    tt H

    ill

    Cleve

    Cole

    Lee

    Ans

    l ey

    Dove

    La Cim

    a

    St Park Rd 20

    Coe

    Nayl or

    Ranger

    Paris

    Shannon

    Silliman

    Harshberger

    Ken

    nonC

    l oun

    t z

    Balboa

    Willo

    w

    Maple

    Blue FlameTerrell

    Coffin

    Ash

    Elks

    Highport

    Max

    wel

    l

    Layne

    J

    Lil Ole

    Wis

    dom

    Anderson

    Harbor

    Martin

    Walnut Creek

    Angus

    Hom

    esite

    8th

    F Pad

    9th

    Woo

    dlaw

    n

    Lariat

    Elm

    Rid

    ge

    Wat erl oo Lake

    Ch i

    l es

    By r d

    Elm

    Front

    7th

    Ivy

    Circle

    Sheryl

    Hol

    der

    J ul ia

    Jack C

    ole

    Potts

    boro

    O Pad

    Sierra

    Weis

    1st

    Kreager Magnus

    Perimeter

    Bla

    ck D

    iam

    ond

    Guilloud

    Castle

    Cra

    wfo

    rd

    Pat

    L Pad

    Dal

    las

    N-Tec

    Power Plant

    H Pad

    Riv

    er O

    ak

    Gattis

    Lazy Acre

    Hill Clark

    Teja

    s

    Russell

    Rc Vaughan

    Pau

    la La n g

    Arr

    oyo

    Wild

    Kin

    gdom

    Oas is

    Ann

    Eton Charlsie

    Sharpes

    Cou

    ntry

    Clu

    b

    Acheson

    Old Airport

    Nelson

    Miller

    Win

    d

    Siebman

    Lakev ie w

    Cotton w

    ood

    Lutheran

    Jade

    Flyi

    ng M

    Mano

    J Pad

    Joy

    Cres

    cent

    Sunset

    Loes Highport

    Ward

    Yo u n g

    State Spu

    r 503

    Vine

    Cedar Hills

    Sun

    rise

    Dav

    i s

    Jeanette's

    North

    Hof

    ma n

    Lake Poi nt

    Hol

    land

    Viol

    a

    Methodist

    Stanford

    Doug Morgan

    Luc k

    y 13

    Sp r

    o ut S

    prin

    g

    Antler

    Mountain Climb

    Hilltop

    Ildew

    ild

    Peterson

    Mim

    osa

    Be l

    le

    Strait Highgr

    ove

    Grayson

    Carter

    Vfw

    Dickey

    Wrig

    ht

    Kee

    f er

    Dripping Spring

    7th

    Brooks Law

    ren c

    ePark

    Loy L

    ake

    Squir

    rel

    Texoma

    Eisenhower

    Clo

    untz

    Brooks

    8th

    Wildlife

    Har

    b or

    Terry

    Paw

    Paw

    Cree

    k

    Deav

    er C

    reek

    Iron Ore Creek

    Har

    ris C

    reek

    Martin Branch

    Little Mineral Creek

    Cedar Creek

    Duck Creek

    Mill Creek

    Duck Creek

    Harris Creek

    Shawne

    e Cree

    k

    Myer Branch

    Lake Texoma

    Big Mineral Arm

    Little Mineral Arm

    Lake Texoma

    Randell Lake

    Russel Lake

    Lake

    Loy Lake

    R and G Club Lake

    Meadow Pond

    Deaver Pond

    Russel Pond

    Elm Pond

    Little Mineral Creek

    Old Goose Pond

    Red River

    HAGERMAN NATIONAL WILDLIFE REFUGE

    EISENHOWER SP

    1 0 10.5

    Miles

    F:\p

    roje

    cts\

    850\

    0101

    \GIS

    \figu

    re-II

    -1.m

    xd r

    onl

    Study Li

    mits

    Study Limits

    LegendRoadsRailroad

    Census Blocks

    Streams

    Lakes

    State Park

    Wildlife Refuge

    Figure II-1

    Study Area and Census 2000 Blocks

    Stud

    y Li

    mits

    Stud

    y Li

    mits

  • F:\projects\850\0101\Doc\Report\Final\Chapter II.doc II-3

    Table II-1 Population Projections of Major Cities

    Including Grayson County

    Population City/Year

    2000 2010 2020 2030 2040 2050 2060

    Sherman 35,082 39,300 44,400 50,600 57,700 67,000 80,000 Denison 22,773 25,000 28,000 30,000 31,000 32,000 33,000 Pottsboro 1,579 3,000 5,000 7,000 9,000 11,000 12,000 Entire Grayson County 110,595 133,913 163,711 188,537 208,936 230,413 253,568

    Figure II-2 shows the study area divided into the natural drainage basins with the year 2000

    census blocks. The population within each drainage basin is calculated and potential growth for

    the drainage basins is calculated by applying the growth coefficients for the entire Grayson

    County as previously mentioned.

    The existing City of Pottsboro Wastewater Treatment Plant (WWTP) has a rated capacity of 0.35

    million gallons per day (MGD). Table II-2 shows population projections and expected average

    daily flows through the year 2060 for the City of Pottsboro.

    Table II-2 City of Pottsboro Populations and Flows

    Population Projections1

    City 2000 2010 2020 2030 2040 2050 2060

    Pottsboro 1,579 3,000 5,000 7,000 9,000 11,000 12,000 Flow Projections2 (MGD) = 0.21 0.41 0.68 0.95 1.22 1.49 1.62

    1 TWDB population growth coefficients for Grayson County are applied to the drainage basins. 2 Wastewater produced per capita = 135 gallons per day per capita.

    The Pottsboro WWTP was expanded to 350,000 gallons per day (gpd) in 1999/2000. After the

    plant expansion was placed into service, the City of Pottsboro began a program to locate and

    repair sources of inflow and infiltration (I&I). Around the same time the plant was placed in

    service, an underground utility contractor horizontally bored into a sewer main, causing a major

  • Refuge

    Pre

    sto n

    Plainview

    Helen

    Wright

    Day

    Kat

    y

    Mi ri

    c k

    TexasHull

    Airp

    ort

    Main

    Hagerman

    Texoma

    Morton

    United S

    tat es Highw

    ay 75

    Davy

    Sears

    Har

    den b

    ergEn t

    erpr

    ise

    Old

    Sa d

    ler

    Terr

    y

    Cor

    del l

    L ill is

    Arthur

    Bennett

    Highway

    75

    Farm-to-Market Road 120

    Par

    k

    T her

    e sa

    Des

    v oig

    nes

    Georgetown

    Earl

    Aus

    t in

    Ha r

    vey

    Keyes

    Fann

    in

    Reeves

    Farm- to-M

    arket Road 9 01

    Dickey

    Bar

    ret t

    Juan

    ita

    Locust

    Pea

    rce

    Ke e

    fer

    Ha n

    na

    Cemetery

    Wildli

    fe

    Arm

    stron

    g

    Sta

    te H

    igh w

    a y 9

    1

    Ffa

    Ray

    Well

    Mil l

    Cre

    ek

    Ky ke r

    Big Mineral

    Quail Run

    Farm-to-Market Road 691

    Eis

    enho

    wer

    Hig

    hlan

    d

    Randell L ake

    F ar m

    -to-M

    arke

    t Roa

    d 14

    17

    Cedar Mills

    Law

    ren c

    e

    Tra vis

    Lake

    Trail

    6th

    F ul ton

    Rus

    k

    Loy

    Lake

    United States Highway 69

    Edd

    y

    Brady

    Kus

    c h

    Kirk

    Morgan

    5th

    Fran

    k

    Toy

    Farm-to-Market Road 406

    Mau

    ri ce

    Short

    County

    Brooks

    Rio R

    o xo

    Murray

    Dripping Spring

    Elliot

    Arkansas

    Randell

    McC

    lain

    Farm

    -to-M

    arke

    t Roa

    d 13

    1

    Kel

    soe

    Tang

    lew

    ood

    Preston BendD

    oty

    Denton

    Flora

    Middle

    Gies

    Coo

    ks C

    o rn e

    r

    Squ

    irre l

    Hillcrest

    Cemetary

    Richerson

    Loy

    Col

    lege

    Pelts

    Glenwood

    F F

    A

    United S

    tates Highw

    ay 377

    Hill

    Fallon

    Oxford

    Sco

    tt H

    ill

    Cleve

    Cole

    Lee

    Ans

    ley

    Dove

    La Cim

    a

    Nay l or

    St Park Rd 20

    Coe

    Ranger

    Paris

    Shannon

    Silliman

    Harshberger

    Ken

    nonC

    l oun

    t z

    Balboa

    Willo

    w

    Maple

    Blue FlameTerrell

    Coffin

    Ash

    Elks

    Highport

    Max

    wel

    l

    Layne

    J

    Lil Ole

    Wis

    dom

    Anderson

    Harbor

    Martin

    Walnut Creek

    HilltopSha

    dow

    Angus

    Hom

    esite

    8th

    F Pad

    9th

    Woo

    dlaw

    n

    Lariat

    Elm

    Rid

    ge

    Florence

    Waterl oo Lake

    Ch i

    l es

    By r d

    Elm

    Front

    7th

    Ivy

    Circ

    l e

    Sheryl

    Hol

    der

    J ul ia

    Jack C

    ole

    Potts

    boro

    O Pad

    Sierra

    Weis

    1st

    Kreager Magnus

    Perimeter

    Bla

    ck D

    iam

    ond

    Guilloud

    Castle

    Cra

    wfo

    rd

    Pat

    Dal

    las

    N-Tec

    Power Plant

    H Pad

    Riv

    er O

    ak

    Gattis

    Lazy Acre

    Hill Clark

    Teja

    s

    Russell

    Rc Vaughan

    Lang

    Arr

    oyo

    Wild

    Kin

    gdom

    Oas is

    Ann

    Eton Charlsie

    Sharpes

    Cou

    ntry

    Clu

    b

    Acheson

    Old Airport

    Nelson

    Miller

    Win

    d

    Siebman

    Lakev ie w

    Cotton w

    ood

    Lutheran

    Jade

    Flyi

    ng M

    Mano

    J Pad

    JoyCr

    esce

    nt

    Sunset

    Loes Highport

    Ward

    Yo u n g

    State Sp

    ur 503

    Vine

    Cedar Hills

    Sun

    rise

    Dav

    i s

    Jeanette's

    North

    Hof

    ma n

    Lake Poi nt

    Hol

    land

    Viol

    a

    Odell

    Methodist

    Stanford

    Doug Morgan

    Luc k

    y 13

    Sp r

    o ut S

    prin

    g

    Antler

    Ildew

    ild

    Peterson

    Mim

    osa

    Be l

    le

    Strait

    Grayson

    Carter

    Vfw

    Wildlife

    Kee

    fer

    Ha r

    b or

    Cordell Dripping Spring

    Brooks

    Dickey

    7th

    Brooks

    Loy L

    ake

    Texoma

    Squir

    rel

    Clo

    untz

    Hilltop

    Eisenhower

    Wrig

    ht

    Park

    Terry

    Law

    ren c

    e

    8th

    Paw

    Paw

    Cree

    k

    Deav

    er C

    reek

    Iron Ore Creek

    Har

    ris C

    reek

    Martin Branch

    Little Mineral Creek

    Cedar Creek

    Duck Creek

    Mill Creek

    Duck Creek

    Harris Creek

    Shawne

    e Cree

    k

    Myer Branch

    Lake Texoma

    Big Mineral Arm

    Little Mineral Arm

    Lake Texoma

    Randell Lake

    Russel Lake

    Lake

    Loy Lake

    R and G Club Lake

    Meadow Pond

    Deaver Pond

    Russel Pond

    Elm PondTaylor Pond

    Little Mineral Creek

    Old Goose Pond

    Red River

    HAGERMAN NATIONAL WILDLIFE REFUGE

    EISENHOWER SP

    1 0 10.5

    Miles

    F:\p

    roje

    cts\

    850\

    0101

    \GIS

    \figu

    re-II

    -2.m

    xd r

    onl

    Study Li

    mits

    Study Limits

    Study Limits

    LegendRoadsRailroad

    Census Blocks

    Streams

    Lakes

    State Park

    Wildlife RefugeBASINID

    Basin 1

    Basin 2

    Basin 3

    Basin 4

    Basin 5

    Basin 6

    Figure II-2

    Study Area Divided Into Drainage Basinsand Census 2000 Blocks

  • F:\projects\850\0101\Doc\Report\Final\Chapter II.doc II-5

    0

    200,000

    400,000

    600,000

    800,000

    1,000,000

    1,200,000

    1,400,000

    1,600,000

    Gal

    lon

    s/D

    ay

    1990 1991 1992 1993 1994 1998 1999 2000 2001 2002 2003

    Annual AvgMax MonthMax Day

    Permitted Flow350,000 gpd

    source of inflow. The damage was located and repaired in early 2003. The data clearly shows

    that repair of this major inflow source and other I&I elimination work has had a significant

    impact on the wet weather flows to the treatment plant. See Figure II-3.

    Figure II-3 Historical Flows 1998-2003

    City of Pottsboro Wastewater Treatment Plant

    Discussion with the study participants regarding the study area and anticipated development is

    considered in calculating the projected flows. The projected population for each basin has been

    developed considering the anticipated private development plans in the study area. Projections

    for each basin are listed in Table II-3. Table II-4 shows the projected flows, which includes the

    flows from the anticipated development around the Grayson County Airport and the proposed

    Preston Harbor development, through the year 2060.

    Due to lack of significant historical data, the peaking factor is assumed to be four per Texas

    Commission of Environmental Quality (TCEQ) standards, Chapter 317. The projected peak

    flows through the year 2060 are listed in Table II-5.

  • F:\projects\850\0101\Doc\Report\Final\Chapter II.doc II-6

    Table II-3 Grayson County Study Area

    Basins and Projected Population

    Population Projections1 Basin ID

    2000 2010 2020 2030 2040 2050 2060

    21.08% 22.25% 15.16% 10.82% 10.28% 10.05%

    Basin 1 5,299 6,416 7,844 9,033 10,010 11,039 12,149

    Basin 2 1,100 1,331 1,628 1,874 2,077 2,291 2,521

    Basin 3 475 576 704 810 898 991 1,090

    Basin 4 70 85 104 120 133 146 161

    Basin 5 1,435 1,737 2,124 2,446 2,711 2,989 3,290

    Basin 6 1,649 1,996 2,440 2,810 3,114 3,435 3,780

    Tanglewood Development 0 1,000 2,000 2,000 2,000 2,000 2,000

    Preston Harbor Development 0 2444 9926 9926 9926 9926 9926

    Total Population = 10,028 18,031 36,695 38,946 40,795 42,743 44,842

    1 TWDB population growth coefficients for Grayson County are applied to the drainage basins.

    Table II-4 Grayson County Study Area

    Basins and Projected Design Flows

    Design Flow Projections1 (MGD) Basin ID 2000 2010 2020 2030 2040 2050 2060

    21.08% 22.25% 15.16% 10.82% 10.28% 10.05% Basin 12 0.72 1.20 2.40 2.56 2.69 2.83 2.98 Basin 2 0.15 0.18 0.22 0.25 0.28 0.31 0.34 Basin 3 0.06 0.08 0.10 0.11 0.12 0.13 0.15 Basin 4 0.01 0.01 0.01 0.02 0.02 0.02 0.02 Basin 53 0.32 0.78 1.24 1.73 2.17 2.60 3.07 Basin 6 0.22 0.27 0.33 0.38 0.42 0.46 0.51

    Total Flow = 1.48 2.52 4.29 5.05 5.70 6.36 7.07 1 Flow Per Capita = 135 gallons per day 2 Includes flow from Preston Harbor private development 3 From APAI Grayson County Airport Master Plan Development Report October 2000.

  • F:\projects\850\0101\Doc\Report\Final\Chapter II.doc II-7

    Table II-5 Grayson County Study Area

    Basins and Projected Peak Flows

    Peak Flow Projections1 (MGD) Basin ID 2000 2010 2020 2030 2040 2050 2060

    21.08% 22.25% 15.16% 10.82% 10.28% 10.05% Basin 12 2.86 4.78 9.60 10.24 10.77 11.32 11.92 Basin 2 0.59 0.72 0.88 1.01 1.12 1.24 1.36 Basin 3 0.26 0.31 0.38 0.44 0.49 0.53 0.59 Basin 4 0.04 0.05 0.06 0.06 0.07 0.08 0.09 Basin 53 1.27 3.14 4.95 6.92 8.66 10.41 12.30 Basin 6 0.89 1.08 1.32 1.52 1.68 1.85 2.04

    Total Flow = 5.91 10.08 17.18 20.19 22.79 25.44 28.29 1 Peaking factor = 4. 2 Includes flow from Preston Harbor private development 3 From APAI Grayson County Airport Master Plan Development Report October 2000.

  • F:\projects\850\0101\Doc\Report\Final\Chapter III.doc III-1

    CHAPTER III

    PRELIMINARY ASSESSMENT OF SITE-SPECIFIC PERMITTING ISSUES

    During the course of the preliminary evaluation, four potential discharge locations have been

    identified, as described in Chapter 2. Each of these locations has been evaluated to determine the

    following:

    Is there a potential fatal flaw that could render the discharge location unacceptable for

    discharging effluent from a regional facility, based on permitting considerations?

    Are there, potentially, significant differences in the permit limits for discharges to the

    various locations?

    To assist in making these determinations meetings were held with the Texas Commission on

    Environmental Quality (TCEQ) and U.S. Fish and Wildlife Service (USFWS). Minutes from the

    respective meetings are included in Appendix E and Appendix F. Following is a summary of the

    results of the evaluations.

    EVALUATION OF DISCHARGE LOCATIONS

    It has been determined that there may be significant differences in the ease with which a permit

    can be obtained and the possible stringency of permit limits at the four discharge locations.

    Following, potential permit concerns and possible permit limits are discussed for each location.

    The discharge locations are discussed in the order of increasing ability to obtain less stringent

    permit limits; i.e., the most unfavorable location is discussed first, and the most favorable

    location is discussed last.

    Little Mineral Creek Arm of Lake Texoma

    Several locations on the Little Mineral Creek, which discharges to the Little Mineral Creek arm

    of Lake Texoma, have been identified as potential discharge sites for a regional facility. The

    City of Pottsboro currently discharges treated effluent at one of the potential locations.

  • F:\projects\850\0101\Doc\Report\Final\Chapter III.doc III-2

    Depending on the ultimate flow anticipated at the regional facility, any of these potential

    locations could be problematic.

    Recent water quality modeling performed by the TCEQ indicates that, for an effluent flow of

    2.0 million gallons per day (MGD), an effluent set of 10 milligrams per liter (mg/L) for the 5-day

    Carbonaceous Biochemical Oxygen Demand (CBOD5), 2 mg/L for ammonia- nitrogen (NH-N3),

    and 6 mg/L for dissolved oxygen (DO) would be required. Consistent treatment of domestic

    wastewater to this level is generally achievable. However, as flows exceed 2.0 MGD, the limits

    for CBOD5 and NH3 quickly decrease to levels that are much more stringent. As flows approach

    7 MGD, which may be a long-term requirement, CBOD5 limits of approximately 5 mg/L and

    NH-N3 limits below 2 mg/L would likely result. While currently available technology can

    achieve these treatment levels, it is more difficult to operate a treatment plant and consistently

    meet these limits.

    There are other potential permitting issues associated with the Little Mineral Creek Arm. These

    issues are summarized as follows:

    Historically, the models used to predict the impacts of effluent discharges on receiving

    streams have been continually revised. As they have been revised, they have predicted a

    need for more stringent effluent quality limits. If this trend continues, effluent limits for

    even a 2.0 MGD discharge in this location could become very stringent.

    Due to the proximity of the discharge to Lake Texoma and the extent of recreational

    usage of the Little Mineral Creek Arm, nutrients are likely to be a concern in the future.

    The TCEQ is currently developing nutrient criteria for reservoirs. If nutrient limits were

    required for this permit, the potential Phosphorus permit limits could be between

    0.5 mg/L and 1 mg/L. Although less likely, there could be a requirement to limit total

    nitrogen. A potential permit limit for total nitrogen is 10 mg/L

    The impacts of the discharge on bacteriological quality could be raised as a concern by

    the public, because of the amount of contact recreational use of the Little Mineral Creek

    Arm.

  • F:\projects\850\0101\Doc\Report\Final\Chapter III.doc III-3

    Because the Little Mineral Creek Arm is popular for contact recreational uses, there is a

    significant probability that any proposal to increase the discharges to Little Mineral Creek

    will be protested by the public, and a public hearing will be required. A public hearing

    will increase the cost and the time required to obtain a permit, and can result in the

    imposition of unpredictable permit limits and conditions or even a denial of the permit.

    Due to uncertainties about future permit limits and requirements and the potential for public

    opposition, Little Mineral Creek and the Little Mineral Arm of Lake Texoma should be

    considered an unfavorable location for a proposed long-term discharge site for the regional

    facility.

    Unnamed Tributary that Flows Through Hagerman National Wildlife Refuge

    It may be possible to obtain a permit to discharge to the tributary to the Big Mineral Arm of Lake

    Texoma that flows through the Hagerman National Wildlife Refuge. There are currently two

    small discharges to this stream. However, the permit limits for a discharge to this stream may be

    relatively stringent, and there may be additional special requirements in the permit because of the

    presence of the refuge. Permit considerations associated with a discharge to this stream are as

    follows:

    The configuration of the cove where the tributary enters the lake is probably not as

    limiting as the configuration of the upper reach of the Little Mineral Arm. However, there

    is an area at the mouth of the tributary where a small cove is created by a weir

    constructed by the USFWS to improve duck habitat. Until there are cross-section

    measurements for this reach and a model is developed, it is not possible to confirm

    whether there are permit limits that will maintain the water quality standard for DO. It is

    possible that there are no permit limits that can be shown to maintain the existing

    standard. If so, it may not be possible to obtain a permit for a discharge to this stream. If

    limits are identified that achieve the water quality standard, it can be anticipated that they

    will be very stringent, perhaps at the following level:

    CBOD5 = 5 mg/L

    NH3-N = 1 mg/L

  • F:\projects\850\0101\Doc\Report\Final\Chapter III.doc III-4

    Nutrients are not as likely to be a concern in the Big Mineral Arm as in the Little Mineral

    Arm because the primary uses of the Big Mineral Arm are fishing and bird habitat.

    Higher concentrations of algae are more acceptable for these uses than are generally

    acceptable for waters with significant contact recreational use. If any nutrient limitation is

    proposed, it would be for phosphorus, and it would not be expected to be more stringent

    than 1 mg/L.

    The USFWS is concerned that chlorination malfunctions or overdosages of chlorine

    could adversely affect fish and wildlife in the refuge. An ultraviolet (UV) disinfection

    system may be more appropriate than chlorination for a discharge at this location.

    The USFWS also is concerned that general plant malfunctions could release untreated or

    partially treated wastewater to the stream that would adversely impact the refuge. It may

    be necessary to address this concern by constructing a wetland between the treatment

    facility and the receiving stream to provide ongoing, natural backup treatment capability.

    Scott Branch

    Scott Branch also discharges to the Big Mineral Arm of Lake Texoma. The configuration of the

    cove receiving the flow from Scott Branch is the most favorable of any cove evaluated for this

    study. Possible permit limits for a discharge to Scott Branch are discussed below.

    Potential permit limits for CBOD5 and NH3-N cannot be precisely identified until site-

    specific data are obtained on the configuration of the cove, and a model is developed.

    However, the limits are expected to be in the following ranges:

    CBOD5 = 5 mg/L 10 mg/L

    NH3-N = 1 mg/L 3 mg/L

    This discharge location is the least likely to require nutrient limits due to both the

    configuration of the cove and the primary uses of the Big Mineral Arm of the lake.

  • F:\projects\850\0101\Doc\Report\Final\Chapter III.doc III-5

    Red River Below Lake Texoma

    Based solely on permit considerations, this is the most favorable location for a discharge.

    Releases from Lake Texoma provide substantial base flow in the stream, which results in a

    stream with a large assimilative capacity. The seven-day average low flow with a recurrence

    interval of two years (the 7Q2 flow) in the Red River below Lake Texoma has been identified by

    TCEQ as 200 cubic feet per second (129 million gallons per day [MGD]).

    The permit limit for a discharge to this reach of the river could be CBOD5 = 20 mg/L. An NH3-N

    limit may not be required, and there is no expectation that a phosphorus limit would be required.

    If there are any potential problems associated with a discharge to the Red River, they would be

    of an economic or procedural nature. The configuration and flow variability of the Red River in

    this location may require special considerations when the outfall structure is designed.

    The procedural issues will include determining how to coordinate with the State of Oklahoma.

    In this reach, the Oklahoma border is the southern bank of the Red River. Therefore, if the

    discharge is to the Red River, it would be a discharge to Oklahoma waters. At the present time,

    the States of Texas and Oklahoma have not resolved how to permit a facility that treats

    wastewater in Texas but discharges to Oklahoma waters. If this alternative were pursued, it

    would be desirable to evaluate discharging to Shawnee Creek, just upstream of the Red River

    confluence. An evaluation would be needed to determine a location that would be far enough

    upstream not to be subject to Oklahoma requirements, but not so far upstream that a requirement

    for rigorous permit limits would be triggered.

    Other Considerations

    Other considerations are the potential for a protest to the proposed permit and the potential

    impacts of inclusion on the List of Impaired Waters prepared by TCEQ pursuant to Section

    303(d) of the Clean Water Act [303(d) List]. Each of these considerations is discussed briefly

    below.

    Any time a new permit is proposed, there is a significant potential that there will be a protest

    from the public or from other government entities. When the plant site and discharge location are

  • F:\projects\850\0101\Doc\Report\Final\Chapter III.doc III-6

    selected, land ownership adjacent to the plant site and below the discharge location should be

    determined. These landowners should be contacted and provided an opportunity to discuss the

    proposed project prior to the time they receive the mailed notice of the proposed permit or see

    the published notice in the newspaper. If there are concerns, it is better to resolve these concerns

    prior to issuing the notice of the proposed permit.

    At the present time, the only one of the potential receiving waters that is on the 303(d) list is the

    Big Mineral Arm of Lake Texoma. The parameter of concern is bacteria. This type of listing

    typically does not affect permit limits or permit issuance because wastewater treatment plants

    provide disinfection. However, if a discharge location is selected such that the effluent ultimately

    flows to the Big Mineral Arm, the TCEQ 303(d) policies should be monitored periodically to

    verify they have not changed.

    CONCLUSIONS

    The two most preferable locations for effluent discharge from a regional facility are Scott Branch

    and the Red River below Lake Texoma. If a decision is made to discharge to the Red River,

    consideration should be given to locating the outfall on Shawnee Creek far enough upstream of

    the confluence of Shawnee Creek and the Red River such that the State of Oklahoma has no

    interest in the permit. A determination of how far upstream that would be has not been made.

    A permit to discharge to the unnamed tributary that flows through the Hagerman National

    Wildlife Refuge is expected to have more stringent limits and more types of permit requirements

    than a permit to discharge to either Scott Branch or the Red River. Before a decision is made to

    pursue a request to discharge to this stream, additional study is needed to verify that permit limits

    can be identified for CBOD5 and NH3-N that will maintain compliance with the water quality

    standard for DO. It is possible that a permit cannot be obtained for this discharge location or that

    the permit limits will be very stringent.

    The location considered to have the most limitations as a site for a long-term regional facility is

    Little Mineral Creek on the Little Mineral Arm of Lake Texoma. This is because of the

    configuration of the lake in this area, the extent of recreational development, and the types of

    recreational activities in that area. All of these factors can be expected to result in stringent

  • F:\projects\850\0101\Doc\Report\Final\Chapter III.doc III-7

    permit limits, permit limits for more parameters, and a greater potential for protests when these

    are permit actions.

    When a plant site and a discharge location are selected, adjacent and downstream landowners

    should be identified. They should be contacted prior to the time they receive a notice from TCEQ

    (or see the published notice in the newspaper) that a permit application has been filed. They

    should be given information on the project and provided an opportunity to identify their

    concerns. If possible, their concerns should be addressed before the notice is issued.

  • F:\projects\850\0101\Doc\Report\Final\Chapter IV.doc IV-1

    CHAPTER IV

    ECONOMIC EVALUATION OF COLLECTION SYSTEM COSTS FOR ALTERNATIVE SITES

    Four potential locations have been identified for potential regional wastewater treatment

    facilities. This chapter evaluates these four locations from an economic feasibility standpoint.

    This evaluation presents unique technical challenges in that the study area is naturally drained by

    six or more natural watersheds, each going a different general direction. Furthermore, the

    relatively large geographic area encompassed, coupled with a low current population density,

    will make collection components more expensive than would be expected in more highly

    populated areas.

    Evaluation Criteria

    The following criteria were considered in selecting the preliminary locations for the consolidated

    regional WWTP location.

    Engineering Considerations

    o Gravity Flow/Force Main Requirements

    o Geology and Topography

    Zoning/Ownership of Adjacent Land

    Land Ownership/Availability

    Political and Regulatory Acceptance

    o Permitting Requirements

    o Local Land Use

    Environmental Issues

    o Wetlands

    o Wildlife Habitat

    Floodplain Designation

    Proximity to Potential Water Reclamation and Reuse Locations

  • F:\projects\850\0101\Doc\Report\Final\Chapter IV.doc IV-2

    Figure IV-1 shows the drainage basins and the four potential locations for the regional WWTP.

    These four locations are also compared to each other from a collection cost standpoint.

    The following are assumptions made in planning the collection system components for the study

    area.

    Maximum Velocity thru a force main = 8 feet per second (fps)

    Minimum Velocity thru a force main = 2 fps

    Minimum Diameter for a force main = 6 inches

    Peaking Factor = 4

    C-Factor = 140

    The opinion of probable collection cost only includes the major "regional" components of the

    collection system such as the pipes and lift stations, etc. The costs shown are based upon 2060

    flow projections from the entire study area. In some cases, opportunities for phasing or "partial"

    implementation may be available.

    Option 1: Preston Harbor Development Site

    The proposed Preston Harbor site is located on property owned by a private developer who has

    communicated a plan for developing the property on the east side of the Little Mineral Arm of

    Lake Texoma. Historically, many developments around the lake have utilized septic systems to

    dispose of residential and commercial wastewater. The proposed development density will not

    likely support on-site disposal.

    This site is considered desirable from an economic standpoint, as it can receive wastewater from

    half of drainage Basin No. 1 under gravity. The developer has preliminarily indicated that land

    could be made available for the potential treatment plant. Adjacent land is mostly reserved for

    residential housing and commercial development.

  • #

    #

    #

    #

    D

    D

    D

    D

    DD

    D

    D DD

    D

    Basin 1

    Basin 5

    Basin 6

    Basin 2

    Basin 3

    Basin 4 Denison

    Pottsboro

    Sherman

    SadlerKnollwood

    HAGERMAN NATIONAL WILDLIFE REFUGE

    Potential Site #3

    Potential Site #2

    Potential Site #1

    Existing Pottsboro WWTP

    Monarch Ridge

    Diamond Pointe

    Resort Communties

    Retail Developments

    Grand Pappy Residentials

    Schuler / Preston Harbor

    Northwest Resort Community

    Preston Harbor Town Center

    Preston / 84 West ResidentialsPreston / 84 East Residentials

    F:\8

    50\0

    101\

    GIS

    \figu

    re-IV

    -1.m

    xd

    crl

    0 1 20.5

    Miles

    Figure IV-1Drainage Basins and Four Potential Sites

    LegendD Developments

    # Proposed WWTP Sites

    Rail Roads

    Roads

    Lakes

    Streams

    Refuges

    State Park

    City

    Airport

    Drainage BasinsBasin 1

    Basin 2

    Basin 3

    Basin 4

    Basin 5

    Basin 6

  • F:\projects\850\0101\Doc\Report\Final\Chapter IV.doc IV-4

    For this option, the collected raw wastewater from drainage Basin Nos. 2, 3, and 4 would be

    pumped to "Lift Station 5A" located in the drainage Basin No. 5 and then pumped to a high point

    to gravity flow collected sewage in to the existing Pottsboro WWTP. Raw wastewater from

    drainage Basin No. 6 is also collected at the existing Pottsboro WWTP and then, with

    wastewater collected from Basin Nos. 2, 3, 4, and 5, transported to Preston Harbor site under

    gravity. It is assumed that approximately 50 percent of the Basin No. 1 flow would be

    transported under gravity from the Pottsboro WWTP site to the Preston Harbor plant site, and the

    remaining 50 percent Basin No. 1 flow is connected directly to the Preston Harbor site.

    Figure IV-2 shows the potential location of the regional wastewater treatment plant, lift stations

    required to collect sewage under gravity for each basin, and the force main routing from various

    lift stations to the WWTP. Table IV-1 shows the opinion of the probable construction cost for

    various lift stations and force main piping. It is anticipated that Lift Stations 5A and 5C would

    be constructed initially, and that Lift Stations 2, 3, 4, and 6 would be deferred until justified by

    development in individual watersheds.

  • "

    "

    "

    "

    "

    "#

    #

    #

    #

    D

    D

    D

    D

    DD

    D

    D DD

    D

    Basin 1

    Basin 5

    Basin 6

    Basin 2

    Basin 3

    Basin 4 Denison

    Pottsboro

    Sherman

    SadlerKnollwood

    HAGERMAN NATIONAL WILDLIFE REFUGE

    6

    4

    3

    2

    5A

    5C

    Potential Site #3

    Potential Site #2

    Potential Site #1

    Existing Pottsboro WWTP

    Monarch Ridge

    Diamond Pointe

    Resort Communties

    Retail Developments

    Grand Pappy Residentials

    Schuler / Preston Harbor

    Northwest Resort Community

    Preston Harbor Town Center

    Preston / 84 West ResidentialsPreston / 84 East Residentials

    F:\8

    50\0

    101\

    GIS

    \figu

    re-IV

    -2.m

    xd

    crl

    0 1 20.5

    Miles

    Figure IV-2

    Sewage Collection System for Site 1(Option 1)

    LegendD Developments

    # Proposed WWTP Sites

    " Proposed Lift Stations

    Force Main

    Gravity Line

    Rail Roads

    Roads

    Lakes

    Streams

    Refuges

    State Park

    City

    Airport

    Drainage BasinsBasin 1

    Basin 2

    Basin 3

    Basin 4

    Basin 5

    Basin 6

  • F:\projects\850\0101\Doc\Report\Final\Chapter IV.doc IV-6

    Table IV-1

    Opinion of Probable Collection Cost for Option 1

    Opinion of Construction Cost Option 1 (Regional Plant Near Proposed Preston Harbor Development)

    Item Description Cost 2005 $

    Lift Stations

    Ultimate Capacity

    Lift Station 2* 1.4MGD 499,000 Lift Station 3* 2.0MGD 463,000 Lift Station 4* 2.0MGD 484,000 Lift Station 5A 14.3MGD 5,874,000 Lift Station 5C 8.6MGD 3,350,000 Lift Station 6* 2.0MGD 485,000

    Pipelines Lift Station 2 to Lift Station 3 (8 Dia.)* 9,504Feet 625,000 Lift Station 3 to Lift Station 4 (8 Dia.)* 23,760Feet 1,563,000 Lift Station 4 to Lift Station 5A (8 Dia.)* 15,312Feet 1,007,000 Lift Station 5A to Pottsboro WWTP (24 Dia.) 21,120Feet 4,277,000 Lift Station.5C to Lift Station 5A (18 Dia.) 13,200Feet 1,914,000 Lift Station 6 to WWTP (10 Dia.)* 29,568Feet 2,451,000 Pottsboro to WWTP (30 Dia. gravity line) 9,504Feet 1,758,000 Lift Station 5 to Pottsboro WWTP (24 Dia. gravity line) 7,392Feet 1,220,000

    Subtotal 25,970,000Contingencies15% 3,895,500

    Total Construction Cost 29,865,500Engineering and Surveying, Permitting, and Construction Administration 20% 5,973,100

    Total Project Cost 35,800,000* Timing to be deferred until needed for growth in individual watersheds.

    Option 2: Regional Treatment Facilities at Existing Pottsboro Plant Site

    The existing Pottsboro WWTP is located at the north side of the City of Pottsboro and

    approximately in the center of the study area. The Pottsboro WWTP currently utilizes a

    conventional treatment process that includes screenings, aeration, and secondary clarification to

    treat the influent wastewater flows. The plant receives wastewater from City of Pottsboro

    through an existing collection system.

  • F:\projects\850\0101\Doc\Report\Final\Chapter IV.doc IV-7

    Figure IV-3 shows the location of existing Pottsboro WWTP, lift stations required to collect

    flows under gravity for each basin, and the force main routing from various lift stations to the

    WWTP. On a long-term basis, the Pottsboro WWTP is assumed to be receiving approximately

    30 percent of the flows under gravity and remaining flow would be pumped to the site.

    The collected raw wastewater from drainage Basins 2, 3, and 6 would be pumped directly to the

    existing Pottsboro WWTP. The wastewater collected from Basin No. 4 and is pumped to Lift

    Station 5A. Flows from Basin Nos. 4 and 5 are pumped to a high point to achieve gravity flow to

    the existing Pottsboro WWTP. Approximately 30 percent of the Basin No. 2 flow is assumed to

    be gravity flow directly into the Pottsboro WWTP and the remaining 70 percent is pumped.

    Table IV-2 shows the opinion of the probable construction cost for various lift stations and force

    main piping, which does not include the sewage collection system upgrades that might be needed

    inside Pottsboro.

    As was proposed for the previous option, it is anticipated that collection facilities in Basins 2, 3,

    4, and 6 would be deferred until necessitated by growth in the service area.

  • "

    "

    "

    "

    "

    "

    #

    #

    #

    #

    D

    D

    D

    D

    DD

    D

    D DD

    D

    Basin 1

    Basin 5

    Basin 6

    Basin 2

    Basin 3

    Basin 4 Denison

    Pottsboro

    Sherman

    Sadler

    HAGERMAN NATIONAL WILDLIFE REFUGE

    4

    3

    2

    6

    5A

    5C

    Potential Site #3

    Potential Site #2

    Potential Site #1

    Existing Pottsboro WWTP

    Monarch Ridge

    Diamond Pointe

    Resort Communties

    Retail Developments

    Grand Pappy Residentials

    Schuler / Preston Harbor

    Northwest Resort Community

    Preston Harbor Town Center

    Preston / 84 West ResidentialsPreston / 84 East Residentials

    F:\8

    50\0

    101\

    GIS

    \figu

    re-IV

    -3.m

    xd

    crl

    0 1 20.5

    Miles

    Figure IV-3

    Sewage Collection Systemfor Existing Pottsboro WWTP

    (Option 2)LegendD Developments

    # Proposed WWTP Sites

    " Proposed Lift Stations

    Force MainGravity LineRoadsRail Roads

    Lakes

    Streams

    Refuges

    City

    Airport

    State Park

    Drainage BasinsBasin 1

    Basin 2

    Basin 3

    Basin 4

    Basin 5

    Basin 6

  • F:\projects\850\0101\Doc\Report\Final\Chapter IV.doc IV-9

    Table IV-2 Opinion of Probable Collection Cost for Option 2

    Opinion of Construction Cost

    Option 2 (Regional Plant at Existing Pottsboro Plant Site)

    Item Description Cost 2005 $ Lift Stations Ultimate Capacity

    Lift Station 2* 1.4MGD 499,000 Lift Station 3* 2.0MGD 463,000 Lift Station 4* 0.1MGD 200,000 Lift Station 5A 12.4MGD 5,096,000 Lift Station 5C 8.6MGD 3,350,000 Lift Station 6* 2.0MGD 485,000

    Pipelines Lift Station 2 to Lift Station 3 (8 Dia.)* 9,504Feet 625,000 Lift Station 3 to WWTP (8 Diameter.)* 39,072Feet 2,570,000 Lift Station 4 to Lift Station 5 (4 Dia.)* 15,312Feet 483,000 Lift Station 5A to WWTP (20 Dia.) 21,120Feet 3,467,000 Lift Station 5C to Lift Station 5A (18 Dia.) 13,200Feet 1,914,000 Lift Station 6 to WWTP (10 Dia.)* 29,568Feet 2,451,000 Lift Station 5B to Pottsboro WWTP (21 Dia. Gravity Line) 7,392Feet 1,146,000

    Subtotal 22,749,000 Contingencies 15% 3,412,350

    Total Construction Cost 26,161.350 Engineering and Surveying, Permitting, and Construction Administration 20% 5,232,270

    Total Project Cost 31,400,000 * Timing to be deferred until needed for growth in individual watersheds.

    Option 3: Regional Facility (Northwest of Grayson County Airport) Potential "Site 2" is located on an unnamed tributary of the Big Mineral Arm of Lake Texoma

    and at the northwest side from the Grayson County Airport in the drainage Basin No. 5. The low

    level of existing development and close proximity from the anticipated residential and

    commercial development near the Grayson County Airport makes this site suitable for a potential

    regional wastewater treatment plant site.

    Under this option, the collected raw wastewater from drainage Basin Nos. 2, 3, and 4 is pumped

    to the potential Site 2 located in the drainage basin No. 5. Raw wastewater from the drainage

    Basin No. 1 would be collected at the existing Pottsboro WWTP and pumped with collected

    sewage from the drainage Basin No. 6 to the Potential Site 2. Approximately 70 percent of the

    wastewater will be collected in Lift Station 5C (See Figure IV-4) and the remaining 30 percent

    will flow directly into the plant.

  • "

    "

    "

    "

    "

    #

    #

    #

    #

    D

    D

    D

    D

    DD

    D

    D DD

    D

    (Northwest GCA Site)

    Basin 1

    Basin 5

    Basin 6

    Basin 2

    Basin 3

    Basin 4 Denison

    Pottsboro

    Sherman

    Sadler

    HAGERMAN NATIONAL WILDLIFE REFUGE

    2

    3

    4

    6

    5C

    Potential Site #3

    Potential Site #2

    Potential Site #1

    Existing Pottsboro WWTP

    Monarch Ridge

    Diamond Pointe

    Resort Communties

    Retail Developments

    Grand Pappy Residentials

    Schuler / Preston Harbor

    Northwest Resort Community

    Preston Harbor Town Center

    Preston / 84 West ResidentialsPreston / 84 East Residentials

    F:\8

    50\0

    101\

    GIS

    \figu

    re-IV

    -4.m

    xd

    crl

    0 1 20.5

    Miles

    Figure IV-4

    Sewage Collection System for"Northwest GCA Site"

    (Option 3)LegendD Developments

    # Proposed WWTP Sites

    " Proposed Lift Stations

    Force MainRoadsRail Roads

    Lakes

    Streams

    State Park

    Refuges

    Airport

    City

    Drainage BasinsBasin 1

    Basin 2

    Basin 3

    Basin 4

    Basin 5

    Basin 6

  • F:\projects\850\0101\Doc\Report\Final\Chapter IV.doc IV-11

    Table IV-3 shows the opinion of the probable construction cost for various lift stations and force

    main piping, which does not include local sewage collection cost inside Pottsboro or in new

    subdivisions.

    As was proposed for the previous option, it is anticipated that collection facilities in Basins 2, 3,

    4, and 6 would be deferred until necessitated by growth in the service area.

    Table IV-3 Opinion of Probable Collection Cost for Option 3

    Opinion of Construction Cost

    Option 3 (Regional Plant Northwest of Grayson County Airport)

    Item Description Cost 2005 $ Lift Stations Ultimate Capacity

    Lift Station 2* 1.4MGD 499,000 Lift Station 3* 2.0MGD 463,000 Lift Station 4* 2.0MGD 484,000 Lift Station 6* 2.0MGD 485,000 Pottsboro WWTP 14.0MGD 5,722,000 Lift Station 5C 8.6MGD 3,350,000

    Force Mains Lift Station 2 to Lift Station 3 (8 Dia.)* 9,504Feet 625,000 Lift Station 3 to Lift Station 4 (8 Dia.)* 23,760Feet 1,563,000 Lift Station 4 to WWTP (8 Dia.)* 15,312Feet 1,007,000 Lift Station 6 to Pottsboro WWTP (10 Dia.)* 29,568Feet 2,451,000 Pottsboro WWTP to Regional WWTP (24 Dia.) 30,624Feet 6,201,000 Lift Station 5C to Regional WWTP (18 Dia.) 13,200Feet 1,914,000

    Subtotal 24,764,000 Contingencies 15% 3,714,600

    Total Construction Cost 28,478,600 Engineering and Surveying, Permitting, and Construction Administration 20% 5,695,720

    Total Project Cost 34,200,000 * Timing to be deferred until needed for growth in individual watersheds.

    Option 4: Regional Treatment Facilities on Scott Branch This potential site (Site 3) is located in drainage Basin No. 3 and on would be Scott Branch of

    the Big Mineral Arm of Lake Texoma. The collected wastewater from Basin No. 2 would be

    directly pumped to the potential plant site. Raw wastewater from Basins 4 and 5 would be

    collected and pumped to the site also. Raw wastewater in drainage Basin No. 1 would be

  • F:\projects\850\0101\Doc\Report\Final\Chapter IV.doc IV-12

    collected at the existing Pottsboro WWTP and pumped with collected sewage from drainage

    Basin No. 6 to the regional plant site. Refer to Figure IV-5 for the routing of collection sewer

    lines.

    Table IV-4 shows the probable construction cost for various lift stations and force main piping,

    which does not include the sewage collection and transportation cost inside drainage Basin

    No. 3.

    As was proposed for the previous option, it is anticipated that collection facilities in Basins 2, 3,

    4, and 6 would be deferred until necessitated by growth in the service area.

  • "

    "

    "

    "

    "#

    #

    #

    #

    D

    D

    D

    D

    DD

    D

    D DD

    D

    Basin 1

    Basin 5

    Basin 6

    Basin 2

    Basin 3

    Basin 4

    HAGERMAN NATIONAL WILDLIFE REFUGE

    Denison

    Pottsboro

    Sherman

    Sadler

    6

    4

    2

    5A

    5C

    Potential Site #3

    Potential Site #2

    Potential Site #1

    Existing Pottsboro WWTP

    Monarch Ridge

    Diamond Pointe

    Resort Communties

    Retail Developments

    Grand Pappy Residentials

    Schuler / Preston Harbor

    Northwest Resort Community

    Preston Harbor Town Center

    Preston / 84 West ResidentialsPreston / 84 East Residentials

    F:\8

    50\0

    101\

    GIS

    \figu

    re-IV

    -5.m

    xd

    crl

    0 1 20.5

    Miles

    Figure IV-5

    Sewage Collection System for Potential Site 3(Option 4)

    LegendD Developments

    # Proposed WWTP Sites

    " Proposed Lift Stations

    Force MainRoads

    Lakes

    StreamsRail Roads

    State Park

    Airport

    City

    Refuges

    Drainage BasinsBasin 1

    Basin 2

    Basin 3

    Basin 4

    Basin 5

    Basin 6

  • F:\projects\850\0101\Doc\Report\Final\Chapter IV.doc IV-14

    Table IV-4 Opinion of Probable Collection Cost for Option 4

    Opinion of Construction Cost

    Option 4 (Regional Plant in Scott Branch Area)

    Item Description Cost 2005 $ Lift Stations Ultimate Capacity

    Lift Station 2* 1.4MGD 499,000 Lift Station 5C 8.6MGD 3,350,000 Lift Station 5A 12.3MGD 5,060,000 Lift Station 4 12.4MGD 5,096,000 Lift Station 6* 2.0MGD 485,000 Pottsboro WWTP 14.0MGD 5,722,000

    Force Mains Lift Station 2 to WWTP (8 Dia.)* 19,536Feet 1,285,000 Lift Station 5C to Lift Station 5A (18 Dia.) 13,200Feet 1,914,000 Lift Station 5A to Lift Station 4 (24 Dia.) 15,312Feet 3,101,000 Lift Station 4 to WWTP (24 Dia.) 15,840Feet 3,208,000 Lift Station 6 to Pottsboro WWTP (10 Dia.)* 29,568Feet 2,451,000 Pottsboro WWTP to Regional WWTP (24 Dia.) 34,320Feet 6,950,000

    Subtotal 39,121,000 Contingencies 15% 5,868,150

    Total Construction Cost 44,989,150 Engineering and Surveying, Permitting, and Construction Administration 20% 8,977,830

    Total Project Cost 54,000,000 * Timing to be deferred until needed for growth in individual watersheds.

    Site Selection The above-mentioned four sites are evaluated and ranked on the collection cost basis in the

    Table IV-5. From the collection standpoint, Option 2, the existing wastewater treatment plant at

    Pottsboro, is the most feasible option. However, only Option 4 is significantly more expensive.

    Therefore, due to the higher collection system cost of Option 4, and the discharge permitting

    concerns involving Option 1 (as discussed in Chapter III), those options will not be considered

    further. Since Options 2 and 3 are very similar in collection system cost, both will be evaluated

    for potential regional treatment processes.

  • F:\projects\850\0101\Doc\Report\Final\Chapter IV.doc IV-15

    Table IV-5 Cost Comparison and Ranking

    Potential Sites Total Collection Cost of

    Raw Wastewater to the Plant (Full-Development Scenario)

    Rank

    Option 1 - "Preston Harbor" Site $35,800,000 3 Option 2 - Existing Pottsboro WWTP Site $31,400,000 1 Option 3 - "Northwest GCA" Site $34,200,000 2 Option 4 - "Scott Branch" Site $54,000,000 4

    The opinion of probable collection cost only includes the major "regional" components of the

    collection system, and does not include "local" components. Additionally, Options 2 thru 4 do

    not include a pump station and force main tying the Preston Harbor development into the

    regional system. The costs shown are for the flows projected through the year 2060 covering the

    entire study area, and are expressed in 2005 dollars.

  • F:\projects\850\0101\Doc\Report\Final\Chapter V.doc V-1

    CHAPTER V

    TREATMENT PROCESS EVALUATION This chapter presents the proposed treatment options for both expansion of the existing Pottsboro

    wastewater treatment plant and construction of a new regional treatment plant near the Grayson

    County Airport. This chapter addresses the facility needs for the plants under the proposed

    construction and expansion scenarios.

    At the Pottsboro plant, the initial expansion would be to 0.9 MGD with a later expansion to

    2 MGD. The initial regional plant at the Grayson Airport site would be at a capacity of about

    0.9 MGD with expansions to 2 MGD, 4 MGD, 6 MGD, and 7 MGD. This expansion schedule is

    based on current trends in the service area. It could be modified based on future growth patterns

    and development.

    For treatment plants that range in size from less than 1 MGD to as much as 7 MGD, there are

    typically a number of options regarding the selection of treatment processes and the phasing of

    expansions. The treatment processes appropriate for a plant less than one MGD may not be the

    most appropriate for the later expansions. The decision regarding the type of process is a

    function of land availability, effluent limits, expansion timing, and operations training and

    involvement. Both conventional mechanical and natural treatment systems are considered.

    EXISTING POTTSBORO WWTP

    The existing Pottsboro WWTP is permitted to discharge 0.35 MGD with permit limits of 10/15/3

    and 4 mg/l dissolved oxygen (DO). An influent lift station pumps all flow from the collection

    system to the treatment plant. The treatment plant consists of the following unit processes:

    Coarse bar screen (manually cleaned)

    Two Orbal treatment units with internal clarifiers, operating in the extended aeration

    mode

    One 35 diameter, 10 SWD external clarifier

    Chlorine contact tank

  • F:\projects\850\0101\Doc\Report\Final\Chapter V.doc V-2

    Effluent flow measurement (Parshall Flume)

    Sludge drying box (trailer mounted) and sludge drying beds for sludge dewatering

    Figure V-1 presents the process flow diagram and Figure V-2 presents the site plan for the

    existing treatment plant.

    It appears the plant could be expanded up to 2 MGD within the bounds of the existing property

    and making beneficial use of the existing facilities. Expansion of the plant beyond 2 MGD

    would likely require acquisition of additional land and large scale demolition and replacement of

    existing unit processes. It is not likely that the Pottsboro plant would be expanded beyond

    2 MGD unless development and permitting of an alternative site for the regional system is not

    possible.

    It is anticipated that the initial expansion of the Pottsboro plant would be up to 0.9 MGD. The

    rationale for the smaller incremental expansion is to meet the short-term needs of Pottsboro and

    the proposed high density residential and resort development in Basin 1 during the time period

    while a regional system is planned, designed, permitted and constructed. After a regional system

    is developed, it is likely the Pottsboro plant would remain in operation to produce reclaimed

    water for irrigation of nearby existing and proposed golf courses.

    Water quality modeling of the Little Mineral Creek recently completed by TCEQ suggests that

    Pottsboros WWTP can be expanded up to 1 MGD under the same discharge permit limits as the

    existing plant (10/15/3 and 4 mg/l DO). If the plant is expanded to 2 MGD, the permit limits

    may be slightly more stringent for ammonia nitrogen (2 mg/l) and DO (6 mg/l).

    Expansion of the plant to 0.9 MGD would involve addition of new headworks facilities (fine

    screen and grit removal), first stage aeration tank, conversion of the existing Orbal units from

    extended aeration to conventional activated sludge operating mode, conversion of the existing

    internal clarifiers to additional aeration tank volume, a new 50 diameter clarifier, return sludge

  • BarScreen

    Wastewater

    Influent

    Lift Station Splitter

    Box

    Clarifier

    Clarifier

    Orbal

    Unit

    Orbal

    Unit

    RA

    SR

    AS

    Manhole WA

    SW

    AS

    Manhole

    Sludge Drying Beds

    PolymerSludgeDewatering Box

    Clarifier

    Manhole

    SludgePump Station

    RAS

    WAS

    Filtr

    ate

    Dewatered Sludge to Landfill

    Chlorine Contact Basin

    Flow Measurement

    Effluent to Little Mineral Creek

    Figure V-1Process Flow Schematic

    For Existing Pottsboro WWTPFor 10/15/03 Permit Limits

    Filtrate

    Liquid Processing Unit

    Key

    Sludge Processing Unit

  • F:\projects\850\0101\Doc\Report\Final\Chapter V.doc V-5

    (RAS) pump station, new UV disinfection system, conversion of the existing chlorine contact

    tank to aerated sludge storage, and miscellaneous site, yard piping, electrical and instrumentation

    work. If there are opportunities to reuse a portion of the plant effluent for irrigation of the

    nearby golf courses, then effluent filtration would be required. For the purposes of this

    evaluation, it is assumed that effluent reuse will be possible, and filters are therefore included in

    the estimated project costs. Sludge handling would continue to be accomplished using the

    trailer-mounted sludge dewatering boxes and disposal at the landfill. Figures V-3 and V-4

    present process flow diagram and site plan for the initial expansion up to 0.9 MGD.

    If the proposed resort and residential development requires additional capacity prior to the time

    when a new regional facility can be brought on line, the Pottsboro plant can be expanded to

    2 MGD with additional first stage aeration tanks, and a second final clarifier. At that time, the

    existing 35 diameter clarifier could be converted to aerated sludge storage. Figure V-5 presents

    the site plan for the next expansion up to 2.0 MGD.

    Preliminary opinion of probable project costs for expansion of Pottsboros WWTP to 0.9 MGD

    are $2,910,000 construction and $3,492,000 total project. For the additional expansion to

    2.0 MGD the preliminary opinion of probable project costs are $2,224,000 construction and

    $2,669,000 total project.

    If for some reason the proposed expansion of the Pottsboro WWTP resulted in a more stringent

    set of discharge limits (5/5/2/1), it would be necessary to provide additional first stage aeration

    tank volume and chemical addition for precipitation of phosphorous. Under the more stringent

    discharge limits, the estimated project cost for the expansion of the Pottsboro WWTP from

    0.35 MGD to 0.9 MGD is approximately $4.4 million and the estimated project cost for the

    expansion to 2.0 MGD is approximately $3.4 million. It is not recommended that expansion of

    the Pottsboro plant beyond 2 MGD be considered.

  • FineScreen

    Waste Water Influent

    Lift Station

    Splitter Box

    RA

    SR

    AS

    Sludge Drying Beds

    Polymer SludgeDewatering Box

    Filtr

    ate

    Dewatered Sludge to Landfill

    Flow Measurement

    Effluent to Little Mineral Creek

    Figure V-3Process Flow Schematic

    For Expanded Pottsboro WWTPFor 10/15/03 Permit Limits

    Liquid Processing Unit

    Key

    Sludge Processing Unit

    Grit Removal

    First Stage Aeration

    Activated

    Sludge Reactor

    Activated

    Sludge Reactor

    Splitter BoxSplitter Box

    Splitter Box

    Aerated Sludge Holding Tank

    WAS

    Clarifier

    Clarifier

    UV Disinfection

    Filters

    Return Sludge Pump Station

    Filtrate

  • F:\projects\850\0101\Doc\Report\Final\Chapter V.doc V-9

    PROPOSED REGIONAL FACILITY AT THE NORTHWEST GRAYSON COUNTY

    AIRPORT SITE

    Based on the evaluation of potential permit conditions provided in Chapter III and the site

    selection evaluation presented in Chapter IV, it is recommended that the regional treatment

    facility be located at a site on the northwest side of the Grayson County Airport. The treated

    effluent is assumed to be either discharged into Scott Branch or transported to potential reuse

    customers, unless a 10/15/3 local discharge permit can be obtained. The effluent limits for the

    first phases of the proposed plant are anticipated to be 10/15/7 or possibly 10/15/3 depending on

    whether the proposed plant receives the same effluent limits as the existing Denison plant located

    at the airport. It is expected that future expansions may receive permit limits as low as 5 mg/L

    CBOD, 5 mg/L TSS, 1 mg/L ammonia-nitrogen, and 0.5 mg/L phosphorus (5/5/1/0.5). The

    TCEQ has indicated that limits for total nitrogen are unlikely within the near future.

    Two alternative types