32
These instructions provide installation and service procedures for all REGAL Chlorinator ejectors to 2,000 PPD, all REGAL Sulphonator ejectors to 500 PPD, and all REGAL Ammoniator ejectors to 100 PPD. The typical installation drawings used in this Instruction Bulletin are meant as a guide only. They are general in nature and may not depict the specific REGAL ejector furnished with your system. All REGAL ejectors contain one or two check valve devices to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is lost due to normal (or non-normal) system shut down. To assure flooding does not occur under these circumstances, routine maintenance of the check valve(s) is necessary. The frequency of needed servicing depends on the cleanliness of the water used to operate the ejector, the cleanliness of the chemical source and therefore the internal cleanliness of the chlorinator system components, the frequency of ejector cycling (ON/OFF), and the pressures the ejector operates against. It is your (the customer’s) responsibility to establish and undertake a SCHEDULED MAINTENANCE PROGRAM. SEE SECTION 5.0 IN THIS MANUAL. INTRODUCTION 1. The entire contents of this manual MUST be read and under- stood prior to installing and operating this equipment. 2. DO NOT discard this instruction manual upon completion of the installation as this manual contains information essential to the safe handling, operation, and maintenance of this equipment. 3. Additional instruction manuals are available at nominal cost from Chlorinators Incorporated. 4. Plastic pipe or tubing connector fittings may be broken or damaged if tightened excessively. HAND TIGHTEN ONLY. IMPORTANT NOTES 1. Before working on any chlorinator system component, CLOSE ALL CYLINDER, CONTAINER, OR MANIFOLD VALVES. 2. This equipment is suitable for use only with the gases specified. DO NOT USE THIS EQUIPMENT WITH OTHER GASES. Such use can result in failures having hazardous consequences. 3. THIS EQUIPMENT IS DESIGNED FOR VACUUM SERVICE ONLY. 4. To insure proper and safe operation of this equipment, use only REGAL parts. The use of non-REGAL parts can result in equipment failures having hazardous consequences and voids the REGAL warranty and insurance coverage. 5. Maintenance should be performed by competent personnel familiar with this type of equipment, such as Chlorinators Incorporated themselves. 6. Piping to and from the ejector should never be smaller than the ejector inlet and outlet sizes. 7. For optimum ejector performance, friction losses in the ejector supply and solution lines (including valves and fittings) should be kept to a maximum of 5' per 100' of pipe length. WARNINGS REGAL Ejector Check Valve Assemblies INSTALLATION/SERVICE MANUAL INSTRUCTION BULLETIN 1900 1044 SE Dixie Cutoff Road, Stuart, Florida 34994 USA Phone: (772) 288-4854 Fax: (772) 287-3238 www.regalchlorinators.com Email: [email protected]

REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

  • Upload
    lykhue

  • View
    218

  • Download
    3

Embed Size (px)

Citation preview

Page 1: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

These instructions provide installation and serviceprocedures for all REGAL Chlorinator ejectors to 2,000PPD, all REGAL Sulphonator ejectors to 500 PPD, andall REGAL Ammoniator ejectors to 100 PPD. The typicalinstallation drawings used in this Instruction Bulletinare meant as a guide only. They are general in natureand may not depict the specific REGAL ejector furnishedwith your system.

All REGAL ejectors contain one or two check valvedevices to prevent water from backing up into thevarious chlorinator or sulphonator system components(FLOODING) when ejector vacuum is lost due to normal

(or non-normal) system shut down. To assure floodingdoes not occur under these circumstances, routinemaintenance of the check valve(s) is necessary. Thefrequency of needed servicing depends on the cleanlinessof the water used to operate the ejector, the cleanlinessof the chemical source and therefore the internalcleanliness of the chlorinator system components, thefrequency of ejector cycling (ON/OFF), and the pressuresthe ejector operates against.

It is your (the customer’s) responsibility to establish andundertake a SCHEDULED MAINTENANCE PROGRAM.SEE SECTION 5.0 IN THIS MANUAL.

INTRODUCTION

1. The entire contents of this manual MUST be read and under-stood prior to installing and operating this equipment.

2. DO NOT discard this instruction manual upon completion of theinstalla tion as this manual contains information essential to thesafe handling, operation, and maintenance of this equipment.

3. Additional instruction manuals are available at nominal cost fromChlorinators Incorporated.

4. Plastic pipe or tubing connector fittings may be broken ordamaged if tightened excessively. HAND TIGHTEN ONLY.

IMPORTANT NOTES

1. Before working on any chlorinator system component, CLOSEALL CYLINDER, CONTAINER, OR MANIFOLD VALVES.

2. This equipment is suitable for use only with the gases specified.DO NOT USE THIS EQUIPMENT WITH OTHER GASES. Suchuse can result in failures having hazardous consequences.

3. THIS EQUIPMENT IS DESIGNED FOR VACUUM SERVICEONLY.

4. To insure proper and safe operation of this equipment, use onlyREGAL parts. The use of non-REGAL parts can result in equipment

failures having hazardous consequences and voids the REGALwarranty and insurance coverage.

5. Maintenance should be performed by competent personnelfamiliar with this type of equipment, such as ChlorinatorsIncorporated themselves.

6. Piping to and from the ejector should never be smaller than theejector inlet and outlet sizes.

7. For optimum ejector performance, friction losses in the ejectorsupply and solution lines (including valves and fittings) should bekept to a maximum of 5' per 100' of pipe length.

WARNINGS

REGAL Ejector Check Valve Assemblies

INSTALLATION/SERVICE MANUAL

INSTRUCTION BULLETIN 1900

1044 SE Dixie Cutoff Road, Stuart, Florida 34994 USAPhone: (772) 288-4854 Fax: (772) 287-3238

www.regalchlorinators.com Email: [email protected]

Page 2: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

Chlorinators Incorporated (hereinafter called “C.I.”) sets forththe follow ing warranties with respect to its REGAL GasChlorinators, Gas Sulphona tors, Gas Ammoniators, SystemComponents and Sub-Assemblies. This war ranty does not applyto the purchase of spare parts or other services performed byC.I. This represents the entire agreement between C.I. andBuyer (also referred to as “end-user”) and shall apply unlessmodified in writing and signed by a C.I. officer, and thiswarranty and its intended terms shall supersede any priornegotiations, correspondence, understand ings, or agreements,written or oral. The Buyer agrees to and accepts all terms ofthis warranty by its contracting for or acceptance of C.I.’sprod ucts, and forms or other documents or statements issuedby Buyer or any other person shall not modify or otherwiseaffect any of the following terms. Buyer should be aware thatreseller must rely entirely upon Chlo rinators Incorporated'swarranties, or assume their own responsibility.

The following states C.I.’s entire warranty andrepresents Buyer’s exclu sive remedy withrespect to its product. Such warranties areexpressly given in lieu of any other warranty,expressed or implied, including but not limitedto those of merchantability and fitness for aparticular purpose. This expressed warranty orany other warranty implied by law shall notcover defects due to accident, improper use, ornon-compliance with C.I.'s operating andmain tenance, assembly, installation manualand instructions.

Recommendations and advice as to specifications, capabilities,design, in stallation, engineering, application, and use of productsare provided as an accommodation, and are intended only as suggestions. C.I. assumes no lia bility for such recommendationsand advice, and they are not to be con strued as constituting anywarranty, expressed or implied.

TERMS OF WARRANTYC.I. warrants its REGAL Gas Chlorinators, Gas Sulphonators,Gas Ammonia tors, System Components and Sub-Assembliesfor a period of one (1) year from date of shipment from C.I.Date of shipment from the factory shall be determined solely onthe basis of the chlorinator serial code stamped on the vacuumregulator back body. The serial number contains a date code.All serial numbers are also registered by ChlorinatorsIncorporated as to date of shipment, model number, chlorinefeed rate capacity, and billing name. If the serial number ismissing, defaced, changed, or in any way ren dered un readable,Chlorinators Incorporated shall, at its option, have the right todeclare the warranty void. If the serial number does not matchthe regis tered model number as to, but not limited to, such itemsas maximum chlorine feed rate, the same option shall be applicable.

The warranty shall apply against material defects in components,and work manship occurring in the course of manufacture.Buyer’s sole remedy for breach of said warranty shall be, atC.I.'s option, either repair or replace ment of any unit which isreceived by C.I. at its plant in Stuart, Florida, (shipping chargesprepaid by buyer) within the time period set forth above andwhich is found by C.I. to be defective by reason of manufacture.

Not withstanding the foregoing, C.I. shall notbe liable to Buyer for damages, includingpersonal injury or death to any person orpersons, or claims of any kind by a third partyor property damage, loss of business orprofits. In no event shall C.I. be liable to Buyerfor consequential or accidental damages ofany kind, even if C.I. was aware of thepossibility of such damages. There are noremedies except those set forth. Further, thatthere are no other authorized warranty repairfacilities other than those at the ChlorinatorsIncorporated factory in Stuart, Florida.

EXCLUSIONSThe following are considered external environmental factorsbeyond the control of C.I., and which may cause damageand/or need for service which will be specifically excludedfrom this warranty (i.e., not a material defect in componentsand workmanship occurring in the course of manufacture).1. Impurities from gas supplies introduced onto sealing and

meter ing surfaces or into any passageways.

2. “Flooding” of unit due to impurities and/or precipitants onejector check valve sealing surfaces.

3. Introduction of liquified gas into the unit.

4. Physical damage due to force, dropping, or other abuse.

5. Use with a material for which the unit is not specifically de signed.

6. Use in an application beyond the rated feed rate capacity orpressures of the unit.

7. Any alteration of design, or use of non-C.I. manufacturedparts.

The exclusions listed above are provided for purposes of clarification, and are not intended to, in any way, limit oreliminate other possible exclu sions.

NO OTHER WARRANTIESUnless otherwise explicitly agreed in writing, and signed bya C.I. officer, it is understood that this is the only writtenwarranty given by C.I. for the systems and components stated.

The dealers or representatives of C.I. may notmake verbal representations that add, modifyor change the written warranties containedherein or change the extent and nature of C.I.’sliability. In no event shall C.I. be liable for direct,consequential, special, incidental or punitive,damages of any kind with respect to the product,including but not limited to those which mayallegedly arise out of breach of warran ty,breach of contract, negligence, strict liability,or any other law, gov ernmental regulation, orcourt decision, except as provided herein.

2

CHLORINATORS INCORPORATED ONE (1) YEAR LIMITED WARRANTY

Page 3: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

3

3.0 PIPING OF EJECTOR

CONTENTS

5.1 High Pressure Ejectors To 500 PPD.

5.2 OPTIONAL Low Pressure Ejectors To 500 PPD.

5.3 OPTIONAL A-927 High/Low Ejector To 100 PPD.

5.4 OPTIONALA-950 Dual Check Valve Ejector To 500 PPD.

5.5 A-2920/A-2922 1000/2000 PPD Ejectors.

5.6 Cleaning/Inspection Of Ejector Nozzles To 500 PPD.

5.7 Cleaning/Inspection Of Ejector Nozzles

@ 1000/2000 PPD.

1.0 INSTALLATION OF EJECTORS TO 500 PPD.

6.0 SECONDARY CHECK VALVES FOR500 PPD AND BELOW EJECTORS

2.0 INSTALLATION OF EJECTORS @ 1000/2000 PPD.

4.0 START-UP

5.0 SERVICE / DISASSEMBLY

DRAWING, PHOTO AND BULLETIN INDEX

Photos No. 1 through No. 11 500 PPD And Below Ejector Photos

Photos No. 12 through No. 13 Secondary Check Valves To 500 PPD

Drawing No. 1 Typical 500 PPD And Below Ejector Installations

Drawing No. 2 Typical 100 PPD And Below Ejector Inlet and Outlet Connections

Drawing No. 3 Typical Installation Drawing Of Remote Mounted Ejector With Solution Line To Point Of Chemical Application

Drawing A-920/A-922/A-925 Parts List Drawing For HIGH PRESSURE Ejectors To 500 PPD CHLORINE SERVICE ONLY

Drawing A-920S/A-922S/A-925S Parts List Drawing For HIGH PRESSURE Ejectors To 500 PPD SULFUR DIOXIDE SERVICE ONLY

Drawing No. A-927/A-927A OPTIONAL Chlorine/Ammonia Service Ejector Assembly (High/Low Pressure)A-301/A-301A OPTIONAL Chlorine/Ammonia Service Check Valve Assembly (High/Low Pressure)

Drawing A-920A Parts List Drawing For HIGH PRESSURE Ejector To 100 PPD AMMONIA SERVICE ONLY

Drawing A-921/A-923/A-926 OPTIONAL Parts List Drawing For LOW PRESSURE Ejectors To 500 PPD CHLORINE SERVICE ONLY

Drawing A-921S/A-923S/A-926S OPTIONAL Parts List Drawing For LOW PRESSURE Ejectors To 500 PPD SULFUR DIOXIDE SERVICE ONLY

Drawing A-921A OPTIONAL Parts Drawing List For LOW PRESSURE Ejector To 100 PPD AMMONIA SERVICE ONLY

Drawing A-930 OPTIONAL HIGH/LOW PRESSURE Ejector Assembly

Drawing A-950/A-949 OPTIONAL Dual Check Valve Ejector to 500 PPD

Drawing A-2920/A-2922 Parts List Drawing For 1000/2000 PPD Ejectors

Drawing A-2000 Parts List Drawing For 1000/2000 PPD Check Valve Assembly

Application Bulletin 1002 Ejector Nozzle Requirements For 500 PPD And Below Ejectors

Application Bulletin 1009 Ejector Nozzle Requirements For 1000/2000 PPD Ejectors

Page 4: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

4

QUALIFYING STATEMENT

These instructions pertain to all REGAL Chlorinatorejectors to 2000 lbs./day, all Sulphonator ejectors to 500PPD, and all Ammoniator ejectors to 100 PPD. The photosand drawings used in this bulletin are general in natureand may not depict the specific REGAL ejector furnishedwith your system. REFER TO THE REGAL EJECTORPARTS LIST DRAWINGS IN THIS BULLETIN FORCORRECT PART AND ASSEMBLY NUMBERS.

1.1 The check valve in the ejector is designed in such a manner that the ejector may be installed in any position.

NOTE: If high pressure ejectors are to be used in low pressureinstallations (>20 psig), it is recommended that the ejectorbe installed so the vacuum tube connector points downwardso gravity can help provide an effective, watertight seal ofthe check valve. A SECONDARY CHECK VALVE SHOULD BECONSIDERED IN THESE INSTANCES. (Photos No. 12 and 13).

1.2 The point of injection should be carefully chosen so thatthe water pressure at this point is as low as possible.Water supply pressure to the nozzle MUST be highenough to overcome total system back pressure. REFERTO APPLICATION BULLETIN 1002.

1.2.1 All REGAL low pressure ejector assemblies aredesigned for total system back pressures up to20 psig.

1.2.2 All REGAL high pressure ejector assembliesare designed for total system back pressuresfrom 20 psig to 200 psig as standard.

1.3 Generally, the amount of water (GPM) required to operatethe ejector depends upon the chemical flow ratesneeded (lbs./day or gms./hr). The higher the chemicalflow rate, the greater the water flow needed. REFERTO APPLICATION BULLETIN 1002.

1.4 The water supply pressure needed to create the necessaryoperating vacuum is dependent upon the pressure intowhich the chemical solution is injected. Therefore, it isimportant that the minimum pressure differential andwater flow for your installation be determined prior toinstallation and start-up. REFER TO APPLICATIONBULLETIN 1002.

1.5 Follow these steps for installing close-coupled diffuserand ejector.

1.5.1 Unscrew the diffuser from the assembly. DONOT install the diffuser when assembled asdamage to component parts may occur.

1.5.2 Put Teflon pipe thread tape on the 3/4" pipethreads and screw the diffuser into the pipe.These are high-impact plastic parts, but like allplastic pipe fittings, care should be exercisedin tightening. Tighten carefully with properlyadjusted wrench. See Photo No. 1.

NOTE: Make sure the diffuser outlet holes are in the mainstream. The end of an open type diffuser should not allowstrong chlorine or sulfur dioxide solution to come in contact withthe wall of the pipe or fittings as serious corrosion will result.See Photo No. 1.

1.5.3 Place a gasket into the recess on each side ofthe check valve body. Insert the nozzle throughthe check valve body (See Photo No. 2). Holdthe check valve body against the diffuser at1/8 turn COUNTER CLOCKWISE from its finalposition. See Photo No. 3. The check valve maybe installed in any position (up, down, sideways).

1.5.4 Screw the nozzle into the diffuser by hand untilcontact is made against both gaskets. Turn thecheck valve body and the nozzle, at the sametime, 1/8 turn clockwise to the final, tight position.See Photo. No. 3.

1.5.5 Attach water supply hose (or pipe) and tightenclamps. See Photo No. 4.

1.6 Other types of diffuser and ejector installations are possibledepending on the needs of the installation. See DrawingsNo. 1 and 2.

1.6.1 Sometimes, the ejector assembly is mountednear the gas feed system components. In thisinstance, a wall mounting bracket for the ejectorcan be provided, and the ejector outlet can besupplied with various size adapters for solutionhose or pipe.

1.6.2 If the ejector is to be remotely installed with solutionpipe or hose running to the point of application,be certain to cut off the tip of the diffuser beforeinstalling into the pipe or hose. FAILURE TODO THIS WILL RESULT IN EXCESSIVEBACK PRESSURE CAUSING LOSS OFOPERATING VACUUM.

1.6.3 The entire ejector assembly may be submersedin an open channel or tank.

1.6.4 Special diffuser outlets can be used with PVCball valves. See Drawings No. 1 and 2.

1.0 INSTALLATION OF EJECTORS TO 500 PPD (See Photos No. 1, 2, 3 and 4)

Page 5: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

2.1 The check valve in the ejector is designed so that theejector may be installed in any position. The check valveassembly, components, and piping MUST be supportedto prevent breakage due to water hammer, vibration, etc. A horizontal mounting of the ejector is preferred.

2.2 The point of injection should be carefully chosen so thatwater pressure is as low as possible. Vacuum is createdin the ejector by the nozzle so water pressure to thenozzle must be high enough to overcome the backpressure and create a strong jet in the nozzle.

2.3 The standard ejector is designed to withstand staticback pressures up to 70 psig (4.9 kg/cm2).

2.4 Generally, the amount of water (GPM) required to operatethe ejector depends on the chemical feed rate (lbs/24 hrs.or kg/hr). The higher the chlorine feed rate, the greaterthe water flow needed. REFER TO APPLICATIONBULLETIN 1009 IN THIS MANUAL.

2.5 Ejector water supply pressure must be greater than thepressure into which the chemical solution is injected.The amount of pressure differential may vary with theapplication. Generally, the greater the pressure into whichthe chemical will be injected, the greater the differentialpressure must be. However, the minimum pressuredifferential and water flow for your installation should bedetermined prior to installation and start-up. REFER TOAPPLICATION BULLETIN 1009 IN THIS MANUAL.

2.6 Follow these steps for installing the ejector assembly.

2.6.1 The nozzle (water) inlet and throat (chemicalsolution) outlet connections are 2" NPT for usewith customer furnished fittings, flanges, unions,etc.

2.6.2 The ejector chemical gas inlet connection is1" NPT.

2.6.3 Use teflon tape on all threaded connections.Tighten threaded connections carefully, usingproperly sized wrenches, and being careful notto over tighten, as damage to the parts could result.

0/2000 P

3.1 For most 500 PPD and below ejector applications, theejector water supply line should be brought to within 3'-5'of the nozzle using rigid pipe materials.

For most 1000/2000 PPD ejector applications, the waterand solution lines will be rigid sch. 80 PVC pipe.

3.2 Shut-off valves, unions, y-strainers, gauges, etc., are valuableservice tools and are recommended. See Drawing No. 1.

3.3 For 500 PPD and below ejectors, connect a flexiblehose line between the rigid incoming ejector watersupply line and the ejector nozzle. Clamp the hosesecurely at both ends with single or double clamps. SeePhoto No. 4.

4.1 The ejector, with its water supply and solution lines orpiping must be properly installed and operating beforechecking the chlorinator, sulphonator or ammoniator.

4.2 Unless the ejector is creating a vacuum, the chlorinator,sulphonator or ammoniator WILL NOT work. Followthese steps:

4.2.1 For 500 PPD and below ejectors, disconnectthe vacuum tubing at the ejector fitting. For1000/2000 PPD ejectors, unscrew the 1" PVCunion at the ejector vacuum connection.

4.2.2 With the booster pump running or the pressurizedwater supply connected, open the ejector waterline supply valve and any other valves that mayexist between the ejector outlet and the point ofchemical application. The ejector should now bein operation and creating a strong vacuum.

4.2.3. For 500 PPD and below ejectors, check forproper vacuum by placing your finger againstthe vacuum tubing connector opening. For1000/2000PPD ejectors, place your hand overthe vacuum union opening.

A STRONG VACUUM SHOULD EXIST. If thereis no vacuum or only a weak vacuum, be certainthat water supply pressure and flow is sufficientand that the nozzle and piping is not plugged.CORRECT THE CONDITION AND OBTAINPROPER VACUUM BEFORE PROCEEDING.

4.2.4 Shut off the water supply to the ejector andmake sure no water comes out of the vacuumtubing connector. If water is observed leakingpast the check valve, correct before proceeding.Once the problem is corrected, cycle the ejectoron and off a few times to make sure the checkvalve is tightly sealed. Water leaks at this pointCANNOT be tolerated.

4.2.5 Reconnect the vacuum tubing or piping to theejector fitting.

5

3.0 PIPING OF EJECTOR

4.0 START-UP

2.0 INSTALLATION OF 1000/2000 PPD EJECTORS

Page 6: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

6

PREVENTIVE MAINTENANCE SCHEDULE REGAL SYSTEMS AND SYSTEM COMPONENTS

The best, most cost effective, and easiest way to assure thatyour gas feed system and equipment will provide continuous,dependable, trouble free operation, is to establish a PREVENTIVEMAINTENANCE SCHEDULE. This will assure minimumunscheduled down time. The maintenance schedule should bein writing and include as a minimum, the date of installation,the scheduled date of maintenance, the actual date themaintenance was performed, the parts used, and any applicablenotes.

All REGAL products are engineered for easy maintenance andthis manual provides step by step procedures to properlyservice and maintain each component within the system. It isyour, (the customer’s) responsibility to establish and undertakea SCHEDULED MAINTENANCE PROGRAM.

To support this program, we have available a variety of“REPAIR KITS” containing the parts we feel you may need forminor emergency repairs. We recommend that these kits beavailable in your stock at all times. When this kit, or any partsare used, the kit should be replaced immediately. This manualcontains complete parts lists for each system component.As such, you can order and stock additional parts as deemednecessary.

AT A MINIMUM, THIS EQUIPMENT SHOULD RECEIVESCHEDULED MAINTENANCE AT LEAST ONCE A YEAR.Depending on the installation, application, location ofcomponents, quality of gas, etc., this equipment may needscheduled maintenance more than once a year. This issomething that needs to be determined on a job by job basis.

Spare parts and/or repair kits may be ordered directly from thecompany who supplied your equipment, or they may beordered directly from our inventory in Stuart, Florida.

IMPORTANT: Maintenance on REGAL Systems or SystemComponents should be performed by competent personnelfamiliar with this type of equipment such as; authorizedREGAL Dealers or, Chlorinators Incorporated themselves.

WARNING: Even if the gas feed rate drops to zero as evidencedby the position of the ball or float in the metering tube and/orthe out of gas indicator, and even if the supply containerappears to be empty, SOME LIQUID CHEMICAL MAY STILLBE LEFT IN THE CYLINDER OR CONTAINER.

NEVER disconnect the vacuum regulator from the cylinder orcontainer/manifold valve until ALL cylinder, container, or manifoldvalves are FULLY CLOSED or a highly dangerous chemicalleak causing severe injuries or death could occur.

CYLINDER AND CONTAINER VALVES ARE ALWAYSCLOSED BY TURNING THE VALVE STEM IN A CLOCKWISEDIRECTION.

GENERALA check valve is installed in the ejector to prevent water frombacking into the gas feed system components when the ejectoris shut off. If dirt or impurities from the chemical source, or fromthe water supply line lodge between the check valve and itsseat, water will back into the system requiring cleaning orreplacement of the check valve components.

IMPORTANT: The photos and drawings in this instructionbulletin should be viewed and used with this procedure asnecessary.

Section 5.1 - Service procedures for all REGAL HIGH PRESSUREEjectors to 500 PPD.

Section 5.2 - Service procedures for all REGAL (OPTIONAL)LOW PRESSURE Ejectors to 500 PPD.

Section 5.3 - Service procedures for the REGAL (OPTIONAL)A-927 HIGH/LOW Ejector Check Valve to 100 PPD.

Section 5.4 - Service procedures for the REGAL (OPTIONAL)A-950 DUAL CHECK VALVE Ejector to 500 PPD.

Section 5.5 - Service procedures for all REGAL 1000/2000PPD Ejectors.

Section 5.6 - Cleaning/Inspection of REGAL Ejector Nozzlesto 500 PPD.

Section 5.7 - Cleaning/Inspection of REGAL Ejector Nozzlesat 1000/2000 PPD.

5.1 HIGH PRESSURE EJECTORS ONLYTO 500 PPD(See Drawing A-920/A-922/A-925)

5.1.1 Shut off the water supply to the ejector and thewater in the main.

5.1.2 Remove the vacuum tubing.

NOTE: CHLORINE GAS TRAPPED BETWEEN THE VACUUMREGULATOR AND EJECTOR MAY DISCHARGE INTO THEATMOSPHERE WHEN THE VACUUM LINE IS DISCONNECTED.

5.1.3 Unscrew the check valve seat counter clockwiseand remove it from the ejector body. Use a pair ofpliers if necessary.

5.1.4 Carefully lift the edge of the check valve (SeePhoto No. 5) and inspect for dirt and deposits.Clean both the valve and seating surface asnecessary.

5.1.5 When reinstalling the check valve seat, put a smallamount of Vaseline petroleum jelly or Dow CorningDC33 Silicone grease on the seat o-ring andgasket for lubrication.

5.1.6 Screw the check valve seat (clockwise) into theejector body. USE NO TOOLS, HAND TIGHTENONLY.

5.0 SERVICE/DISASSEMBLY

Page 7: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

7

5.1.7 Cycle the ejector on and off several times beforereconnecting the vacuum tubing to ensure that thecheck valve is sealing properly.

REPLACING THE HIGH PRESSURE EJECTOR CHECKVALVE ON EJECTORS TO 500 PPD.

5.1.8 After inspecting the check valve as describedabove, if wear or damage is noted, the check valveshould be replaced. Proceed as follows:

a. Grasp the outer edges of the check valve andapply a steady pulling force until the "umbrella"tip pops free of the seat. Be certain it iscompletely removed.

b. Examine the check valve seat sealing surfacefor deposits and clean with warm water oralcohol.

c. Check the seat sealing surface with astraight edge to be sure that it is completelyflat. If the center of the seat is slightly raised,you will see light under the straight edge or itwill "rock" over the center. If the seat sealingsurface is not flat, use a very fine sand paperor emery cloth on a flat surface (plate glass),and gently sand the check valve seat in afigure 8 pattern only. See Photo No. 6.

d. Coat the tip of a new check valve with a verylight film of Vaseline petroleum jelly or DC33Silicone grease. Put the tip of the check valvein the check valve seat hole and, using thehandle of a screwdriver or other roundedobject, push against the center of the checkvalve until the tip snaps into the seat. SeePhoto No. 7. DO NOT TWIST THE CHECKVALVE OR DAMAGE MAY OCCUR.

e. Examine the check valve seat o-ring andgasket for wear or damage and replace asnecessary.

f. When reinstalling the check valve seat, put asmall amount of Vaseline petroleum jelly orDC33 Silicone grease on the seat o-ring andseat gasket for lubrication.

g. Screw the check valve seat (clockwise) intothe ejector body. USE NO TOOLS. HANDTIGHTEN ONLY.

5.2 OPTIONAL LOW PRESSUREEJECTOR CHECK VALVE TO 500 PPD-CLEANING AND REPLACING(See appropriate Parts Drawing A-921/A-923/A-926,A-921S/A-923S/A-926S or A-921A)

5.2.1 To remove and clean the check valve, proceed asfollows:

a. Close the cylinder/container/manifold valve(s)before working on any system component.

b. Shut off the water supply to the ejector andthe water pressure in the main.

c. Remove the vacuum tubing from the fittingon top of the ejector assembly.

d. Unscrew (counterclockwise) the entirecheck valve assembly out of the ejectorbody. Make sure the seat gasket remains inplace and is in good condition. Replace ifnecessary.

e. Using a “spanner” wrench in the holes locatedin the underside of the outlet body, unscrewthe outlet body from the clamping ring. Donot lose the spring or the diaphragmassembly.

1) The diaphragm is made from a specialcorrosion resistant plastic. Inspect it carefullyfor nicks or cuts. Replace as necessary.

2) The check valve action is accomplishedby the diaphragm bolt sealing tightly onthe o-ring located in the center of theinlet body when the ejector is shut off.As such, the diaphragm bolt sealingsurface and the o-ring must be free ofdirt or impurities that may prevent aneffective seal. Clean or replace as necessary.

f. Reassemble by reversing steps “a” through“d” above.

5.3 OPTIONAL A-927 HIGH/LOW EJECTOR CHECK VALVE TO 100 PPD -CLEANING & REPLACING(See Parts Drawing A-927/A-927A)

5.3.1 The high/low check valve assembly is installedin the ejector assembly to prevent water frombacking into the system when the ejector isshut off. If flooding has occurred or maintenanceis due, proceed as follows:

a. Close the cylinder/container/manifold valve (s)before working on any system component.

b. Shut off the water supply to the ejector andthe water pressure in the main.

c. Remove vacuum tubing from the fitting on top of the ejector assembly.

d. Unscrew (counterclockwise) the entire checkvalve assembly out of the ejector body. Makesure the seat gasket remains in place and is in good condition. Replace if necessary.

e. Grasp the outer edges of the check valve,E-250, and apply a steady pulling force until the “umbrella” shaped stem “pops” free. Becertain it is completely removed.

f. Examine the check valve seat sealing surfacefor deposits, and clean with denatured alcohol.

g. Check the seat sealing surface with a straightedge to be certain it is completely flat. If thecenter is slightly raised, you will see light underthe straight edge, or it will “rock” over thecenter. If the seat sealing surface is not flat,use a very fine sandpaper or emery cloth on a flat surface (e.g., plate glass) and gently movethe check valve seat in a figure 8 pattern(Photo 6). Do not rub back and forth, or theseat will become distorted.

Page 8: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

h. Using a new E-250, wet the tip of the newcheck valve with a very light film (make shinyonly) of Vaseline or Dow Corning DC33. Put the tip of the check valve in the “center” checkvalve seat hole and, using the handle of ascrewdriver or other rounded object, pushagainst the center of the check valve untilthe tip snaps into the seat (Photo 7). DO NOTTWIST THE CHECK VALVE OR DAMAGEMAY OCCUR.

i. Using a “spanner” wrench in the holes locatedin the underside of the outlet body, unscrewthe outlet body from the clamping ring. Donot lose the spring or the diaphragm assembly.

1) The diaphragm is made from a specialcorrosion resistant plastic. Inspect it carefullyfor nicks or cuts. Replace as necessary.

2) The check valve action is accomplishedby the diaphragm bolt sealing tightly onthe o-ring located in the center of theinlet body when the ejector is shut off.As such, the diaphragm bolt sealingsurface and the o-ring must be free of dirtor impurities that may prevent an effectiveseal. Clean all parts or replace as necessary.Always use a new check valve seal o-ring.

j. Reassemble, using a spanner wrench inholes, located in underside of outlet body.Tighten outlet body and clamp ring.

k. When reinstalling the check valve assemblyin ejector, put a thin film of Vaseline or DowCorning DC33 on the seat o-ring and seatgasket for lubrication. Use very sparingly(make it shiny only). DO NOT USE ANY OTHERPETROLEUM BASED GREASES OR OILS.

l. Screw the check valve assembly clockwiseinto the ejector body. Use no tools. Handtighten only.

m. Pressurize the ejector and cycle on and offseveral times before reconnecting the vacuumtubing to ensure that the check valve is sealingproperly. Follow start-up procedures in Section 4.0.

5.4 OPTIONAL DUAL CHECK VALVEEJECTOR TO 500 PPD(See Drawing A-950/A-949)

The NEW REGAL A-950 Dual Check Valve Ejector hasa ball check valve as the primary check valve backed upby a spring loaded o-ring/poppet check valve. To servicethis check valve, proceed as follows:

5.4.1 Shut off the water supply to the ejector and thewater in the main.

5.4.2 Remove the vacuum tubing.

NOTE: CHLORINE GAS TRAPPED BETWEEN THE VACUUMREGULATOR AND EJECTOR MAY DISCHARGE INTO THEATMOSPHERE WHEN THE VACUUM LINE IS DISCONNECTED.

5.4.3 Unscrew (counter clockwise) the complete A-949Check Valve Assembly from ejector body E-557.A properly sized wrench can be used on themachined "flats" of bottom body E-552 if necessaryto loosen the ejector body. DO NOT USE PLIERS.

5.4.4 Make sure the o-ring S-413 located on bottom bodyE-552 is in good shape. Replace as necessary.

5.4.5 To gain access to the check valve components,unscrew (counter clockwise) clamp ring E-301from bottom body E-552 and lift the top bodyE-551 with the clamp ring off of the bottom body.BE CAREFUL NOT TO LOSE POPPET E-554,SPRING E-555, OR O-RING S-416 AS THESEITEMS CAN EASILY FALL OUT.

5.4.6 Inspect the o-ring S-418 located on the E-554poppet and replace as necessary. THIS IS THESECONDARY CHECK VALVE SEAL AND MUSTBE IN LIKE NEW CONDITION.

5.4.7 Inspect and clean as necessary the flat surfaceinside top body E-551. Since this is the sealingsurface for the S-418 sealing o-ring, THIS SURFACEMUST BE CLEAN AND PERFECTLY FLAT.

5.4.8 The primary check valve is located inside bottombody E-552. To gain access to the primary checkvalve, proceed as follows:

a. Using Drawing A-950/A-949 as a guide, carefullyunscrew (counter clockwise) the spring/ballretainer E-553 from bottom body E-552. THEOUTER CIRCUMFERENCE OF THESPRING/BALL RETAINER IS KNURLEDTO MAKE IT EASIER TO UNSCREW.

ONCE REMOVED, THE BALL E-556 IS FREETO FALL OUT. BE CAREFUL NOT TO LOSEOR DAMAGE THE BALL.

b. Inspect the ball E-556 and make sure it isfree of all deposits, nicks, and pits. If in doubt,replace as necessary.

c. Poppet E-553 contains two o-rings. The S-415o-ring is a sealing o-ring and MUST remainin its groove when reassembling the checkvalve components. Inspect this o-ring for wearand replace as necessary.

d. The second poppet o-ring S-417 is a criticalo-ring as it is the sealing surface for theprimary check device (ball E-556). This o-ringis located in an undercut groove at the baseof spring/ball retainer E-553.

If o-ring S-417 shows any signs of wear or, ifo-ring S-417 is flattened due to the check actionof ball E-556, replace with a new one.

5.4.9 Clean all check valve parts with warm waterand/or a mild solvent such as denatured alcohol.

5.4.10 Make sure all parts are thoroughly dry and allo-rings are in place and reassemble by reversingthe steps outlined in Section 5.4.

8

Page 9: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

9

5.5 EJECTOR CHECK VALVE 1000/2000PPD -CLEANING OR REPLACING (Refer to Drawing A-2920/2922)

5.5.1 A-2000 CHECK VALVE

A check valve is installed in the ejector assemblyto prevent water from backing into the systemwhen the ejector is shut off. The check valvedesign is such that it is extremely difficult for dirtto lodge under the valve, but it might, if largeamounts of sand or other impurities are presentin the water supply; and dirt could possibly enterfrom the chemical side. To remove and cleanthe valve, proceed as follows:

a. Close the manifold valve that the vacuumregulator is attached to before working onany system components.

b. Shut off the water supply to the ejector andthe water pressure in the main.

c. Open the 1˝ PVC vacuum union MS-19 byunscrewing (counter clockwise) the unionring and move the vacuum piping out ofthe way. Be careful not to lose the vacuumunion o-ring.

NOTE: CHLORINE GAS TRAPPED BETWEEN THE VACUUMREGULATOR AND EJECTOR MAY DISCHARGE INTO THEATMOSPHERE WHEN THE VACUUM LINE IS DISCONNECTED.

d. Using Parts List Drawing A-2000 as a guide,unscrew clamp ring CV-2004 and lift the topbody CV-2002 with clamp ring off bottombody CV-2001 and set aside. BE SURE NOTTO LOSE O-RING S-804.

e. Carefully lift out poppet CV-2003 andspring CV-2005.

f. Poppet CV-2003 contains an o-ring S-805which is the check valve seal. THIS O-RINGMUST BE IN PERFECT SHAPE, FREE OFNICKS, CUTS, ETC. IF NECESSARY,REPLACE IT WITH A NEW ONE.

IF O-RING S-805 SHOWS SIGNS OF BEINGFLATTENED DUE TO THE ACTION OFTHE CHECK VALVE, REPLACE IT WITH ANEW ONE.

g. Inspect the flat surface inside top bodyCV-2002 to be sure it is flat and clean. THISIS THE SURFACE O-RING S-805 SEALSAGAINST.

h. Clean all check valve parts with warm wateror a mild solvent such as alcohol and drythoroughly.

i. Reassemble the ejector check valve assemblyby reversing steps “a” through “e”.

5.6 CLEANING/INSPECTION OF EJECTORNOZZLE TO 500 PPD5.6.1 To remove the ejector nozzle for cleaning, the

water pressure in the main must first be shut offunless the ejector was initially installed with a valveon the inlet side and a ball valve or corporation stopin the outlet, so that isolation of the ejector is possible.

a. Close the cylinder/container/manifold valve(s)before working on any system component.

5.6.2 Remove the ejector supply hose and gas vacuumtubing from the ejector assembly.

5.6.3 Rotate the complete ejector body counterclockwise,making certain that the solution diffuser remainsfixed in the solution piping or main. (Photo 1).

5.6.4 Unscrew the nozzle from the ejector body.Check the gaskets located in each side of thebody and replace if necessary. (Photo 3).

5.6.5 Nozzle plugging can be caused by:

a. A piece of foreign material (pipe sealer, stone,or dirt) lodging in the nozzle orifice. This canusually be blown out in the reverse direction.DO NOT USE SHARP TOOLS OR ALTERTHE SIZE OF THE ORIFICE IN ANY WAY.

b. Excess plastic pipe solvent or glue used duringinitial installation running into the orifice areaof the nozzle. If this cannot be cleaned outeasily, the nozzle may need to be replaced.

c. Build-up of deposit. This could be a chemicalbuild-up or iron, manganese, or some othermaterial which usually can be removed byimmersing the nozzle in muriatic acid and rinsing.CAUTION: READ ALL WARNING LABELSON THE MURIATIC ACID CONTAINER, ANDAVOID SKIN CONTACT. It is recommendedthat safety goggles or face shield be usedwhen working with any strong acid. Somewaters are such that build-up of deposits cancause an ejector to become inoperative in ashort period of time.

5.6.6 To reinstall the nozzle:

a. Insert the nozzle through the ejector bodyand screw into the solution diffuser. Makesure the gaskets are in place and in goodcondition. (Photo 3).

b. Hold the ejector body against the diffuserat 1/8 turn counterclockwise from its finalposition. (Photo 3).

c. Screw the nozzle into the diffuser by handuntil contact is made against both gaskets.

d. Turn the ejector body and the nozzle at thesame time, 1/8 turn clockwise to the finaltight position. THE PARTS ARE PLASTIC,AND EXCESSIVE TIGHTENING MAY CAUSEBREAKAGE. DO NOT USE TOOLS.

e. Reinstall the ejector supply hose and vacuumtubing. (Photo 4).

5.6.7 Open all valves and check for proper operatingvacuum.

Page 10: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

5.7 CLEANING / INSPECTION OF1000/2000 PPD EJECTOR NOZZLE 5.7.1 The ejector nozzle and throat thread into the

ejector body. To inspect and clean these parts,proceed as follows:

a. Close the manifold valve that the vacuumregulator is attached to before working on anysystem component.

b. Shut off the water supply pressure to theejector, and close any valves in the chlorinesolution line so as to isolate the ejector assembly.

c. Open the 1˝ PVC vacuum union MS-19 byunscrewing (counter clockwise) the union ringand move the vacuum piping out of the way.

Be careful not to lose the vacuum union o-ring.

NOTE: CHLORINE GAS TRAPPED BETWEEN THE VACUUMREGULATOR AND EJECTOR MAY DISCHARGE INTO THEATMOSPHERE WHEN THE VACUUM LINE IS DISCONNECTED.

d. Open or disconnect the 2˝ unions, flanges,fittings, etc., holding the ejector assemblyinto the pipeline, and remove the ejector.WHEN REMOVING AND/OR INSTALLINGTHE COMPLETE EJECTOR ASSEMBLY,BE CAREFUL NOT TO LOOSEN OROVERTIGHTEN THE NOZZLE AND THROATWHICH COULD CAUSE DAMAGE TOTHESE PARTS AND/OR WATER LEAKS.

e. Carefully clean or remove any foreign materialthat may have accumulated in the ejectornozzle or throat area, being careful not toscratch or mar the nozzle orifice.

NOTE: DO NOT USE SHARP TOOLS OR ALTER THE SIZEOF THE ORIFICE IN ANY WAY.

f. If chemical deposits have built up in the nozzleor throat area, immerse the part in muriaticacid. REMOVE ALL O-RINGS OR GASKETSFIRST.

IMPORTANT: READ ALL WARNING LABELS ON MURIATICACID CONTAINER AND FOLLOW ALL SAFETY INSTRUCTIONS.

g. Reassemble by reversing steps “a” through “e”.

If frequent ejector check valve failures causing flooding of thegas feed system components are a concern due to poor qualitywater, etc., Chlorinators Incorporated offers as an optionalaccessory “SECONDARY CHECK VALVE ASSEMBLIES.” (SeePhotos 12 and 13).

The SECONDARY CHECK VALVE ASSEMBLY is installed inseries with the primary check valve in the ejector. This nowmeans that both the primary and the secondary checkvalves must fail in order to flood the remainder of the systemcomponents.

For best protection, the primary check valve device should bechecked for failures as often as necessary and repaired assoon as a failure is detected. THE FREQUENCY OF CHECKINGTHE PRIMARY CHECK VALVE IS DETERMINED BY THESYSTEM, THE QUALITY OF THE CHEMICAL BEING USEDAND, THE QUALITY OF THE EJECTOR SOURCE WATER.

10

6.0 SECONDARY CHECK VALVES FOR500 PPD AND BELOW EJECTORS

Page 11: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

2

1

4

DIFFUSER

GASKET

11

5 76

CHECK VALVE CHECK VALVE SEAT TEFLON TAPE

USE “FIGURE 8”PATTERN

ONLY

3

EJECTOR BODY

DIFFUSER

NOZZLE

GASKET

GASKET

Page 12: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

12

8 9 10

11 12

13

Page 13: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

#1 The ejector is installed directly at the application point using the standard spray diffuser furnished with most REGAL Gas Feed Systems. An advantage with this installation is that “total” back pressure is equal to the application point pressure and the booster pump therefore need only be large enough to supply the hydraulic requirements of the nozzle.

A disadvantage with this installation is that the water main has to be shut down and de-pressurized in order to service the ejector assembly, booster pump, etc.

#2 In this installation, the end of the standard spray diffuser is cut-off to allow unimpeded flow through the ejector. A corrosion resistant valve such as a PVC ball valve is then screwed onto the cut-off end of the diffuser and a remote spray or open end diffuser is screwed into the other end of the ball valve. The ejector with ball valve and remote diffuser is then installed directly at the application point.

As long as the ball valve and diffuser are sized properly, this installation, like the #1 installation above, has the advantage of “total” back pressure being equal to the application point pressure plus an added advantage since the ejector, booster pump, etc. can now be serviced WITHOUT shutting down and/or de-pressurizing the water main.

#3 Often, the ejector is installed remote from the application point. Even though this is an acceptable (but not the preferred) installation, special consideration must be given to the following:

a. A chlorine solution line is a dangerous chlorine pressure line with a chlorine solution strength as high as 3500 parts per million. If this line breaks, the high concentration of chlorine will present a hazard to personnel and/or property.

b. The solution line and solution line fittings must be sized properly to assure that friction losses in this line DO NOT exceed 5' per 100' of equivalent pipe length.

c. A diaphragm protected pressure gauge should always be installed as close to the discharge side of the ejector as possible. This gauge provides a reading of "total" back pressure (application point pressure plus all additional pressures due to frictionlosses created by the solution line, fittings, elevation differences, etc.).

13

DRAWING NO. 1Typical 500 PPD And Below Ejector Installations

Page 14: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

Ejector Installation with Ball Valve to Allow Positive Shut-off when Servicing of the Ejector is Required

Remote Mounted Ejector Installation for Gas Feed Rates up to 100 PPD.

NOTES:1. This installation is suitable for back pressures up to 150 psig and gas feed rates up to 100 PPD.2. If necessary, ejector can be installed at a remote location from the ball valve and diffuser.

NOTE:Threaded and hose interconnection sizes and ball valve size must be adequate to limit friction losses to a maximum of 5' per 100'of pipe or hose length.

14

DRAWING NO. 2Typical 100 PPD And Below Ejector Inlet And Outlet Connections

Page 15: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

NOTE:1. When the REGAL Ejector is mounted at a location remote from the application point, the end of the standard diffuser (E-240)

MUST be cut off to allow unrestricted flow or, an E-248 1" long open end diffuser should be furnished with the system when ordered.

2. The chlorine solution line shown above is oversized to minimize additional back pressure due to friction losses. A rule of thumb is to keep friction losses to a maximum of 5' per 100' of equivalent pipe length. This calculation MUST take into consideration: elevation differences, number of elbows, valves, fittings, etc.A. Depending on the variables noted above, the water supply line to the ejector MAY need to be oversized as well.

3. To determine the hydraulic requirements needed to operate the REGAL Ejector, refer to Application Bulletin 1002 or 1009.

DRAWING NO. 3Typical Installation Of Remote Mounted Ejector With Solution Line To Point Of Chemical Application

15

Page 16: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

16

Ref. No. Part No. Quantity Description

1 E-533 (50X) 1 Nozzle2 G-203 2 Seat Gasket3 S-405 1 Seat O-Ring4 G-204 2 Body Gasket5 ZZ-271 1 5/8” OD Tube Fitting6 E-520 1 Check Valve Seat7 E-210 1 Ejector Body8 E-250 1 Check Valve 9 E-540 1 Nozzle Retainer

NOTE: Include Chlorinator Serial Number and Capacity and Size (OD) of Vacuum Tubing Being Used.

Ejector Assembly A-920Check Valve Assembly E-225 Includes Ref. No. 2, 3, 5, 6, 8Max. Capacity: 100 lbs./24 hrs. (2000 g/hr)

Ejector Assembly A-922Check Valve Assembly E-227 Includes Ref. No. 2, 3, 5, 6, 8Max. Capacity: 250 lbs./24 hrs. (5000 g/hr)

Ejector Assembly A-925Check Valve Assembly E-525 Includes Ref. No. 2, 3, 5, 6, 8Max. Capacity: 500 lbs./24 hrs. (10 kg/hr)

DRAWING NO. A-920/A-922/A-925 Ejector Assembly (Standard)E-225/E-227/E-525 Check Valve Assembly Chlorine Service

High Pressure - For Back Pressure Over 20 PSI (1.4KG/CM2)

EJECTOR MODEL A-920EJECTOR MODEL A-922

EJECTOR MODEL A-925

Ref. No. Part No. Quantity Description

1 E-230 (3A,4A,5A) 1 Nozzle E-234 (17A)

2 G-203 1 Seat Gasket3 S-405 1 Seat O-Ring4 G-204 2 Body Gasket5 Z-250 1 3/8” OD Tube Fitting6 E-220 1 Check Valve Seat7 E-210 1 Ejector Body8 E-250 1 Check Valve 9 E-240 1 Diffuser

Ref. No. Part No. Quantity Description

1 E-234 (18A) 1 Nozzle2 G-203 2 Seat Gasket3 S-405 1 Seat O-Ring4 G-204 2 Body Gasket5 ZZ-260 1 1/2” OD Tube Fitting6 E-222 1 Check Valve Seat7 E-210 1 Ejector Body8 E-250 1 Check Valve 9 E-240 1 Diffuser

Page 17: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

17

NOTE: Include Sulphonator Serial Number and Capacity and Size (OD) of Vacuum Tubing Being Used.

Ejector Assembly A-920SCheck Valve Assembly E-225S Includes Ref. No. 2, 3, 5, 6, 8Max. Capacity: 100 lbs./24 hrs. (2000 g/hr)

Ejector Assembly A-922SCheck Valve Assembly E-227S Includes Ref. No. 2, 3, 5, 6, 8Max. Capacity: 250 lbs./24 hrs. (5000 g/hr)

Ejector Assembly A-925SCheck Valve Assembly E-525S Includes Ref. No. 2, 3, 5, 6, 8Max. Capacity: 500 lbs./24 hrs. (10 kg/hr)

Ref. No. Part No. Quantity Description

1 E-230 (3A, 4A, 5A) 1 NozzleE-234 (17A)

2 G-203 1 Seat Gasket3 S-405 1 Seat O-Ring4 G-204 2 Body Gasket5 ZZ-250 1 3/8” OD Tube Fitting6 E-720 1 Check Valve Seat7 E-710 1 Ejector Body8 E-250 1 Check Valve 9 E-240 1 Diffuser

Ref. No. Part No. Quantity Description

1 E-234 (18A) 1 Nozzle2 G-203 2 Seat Gasket3 S-405 1 Seat O-Ring4 G-204 2 Body Gasket5 ZZ-260 1 1/2” OD Tube Fitting6 E-722 1 Check Valve Seat7 E-710 1 Ejector Body8 E-250 1 Check Valve 9 E-240 1 Diffuser

Ref. No. Part No. Quantity Description

1 E-533 (50X) 1 Nozzle2 G-203 2 Seat Gasket3 S-405 1 Seat O-Ring4 G-204 2 Body Gasket5 ZZ-271 1 5/8” OD Tube

Fitting x 3/8 NPT6 E-725 1 Check Valve Seat7 E-710 1 Ejector Body8 E-250 1 Check Valve 9 E-540 1 Nozzle Retainer

DRAWING NO. A-920S/A-922S/A-925S Ejector Assembly (Standard)E-225S/E-227S/E-525S Check Valve Assembly Sulfur Dioxide Service

High Pressure - For Back Pressure Over 20 PSI (1.4KG/CM2)

EJECTOR MODEL A-920SEJECTOR MODEL A-922S

EJECTOR MODEL A-925S

Page 18: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

18

NOTE: Include Ammoniator Serial Number, Capacity and Size (OD) of Vacuum Tubing Being Used.

DRAWING NO. A-927/A-927A High/Low Pressure Ejector Assembly (Optional)A-301/A-301A High/Low Pressure Check Valve Assembly

Chlorine/Ammonia Service - Max. Capacity: 100 PPD (2000GM/HR)

DRAWING NO. A-920A Ejector Assembly (Standard)E-225A Check Valve Assembly Ammonia Service

High Pressure - For Back Pressure Over 20 PSI (1.4 KG/CM2)

EJECTOR MODEL A-920A

Ref. No.

1

2345 6789

Quantity

1

11211111

Description

Nozzle

Seat GasketSeat O-RingBody Gasket3/8” OD Tube FittingCheck Valve SeatEjector BodyCheck ValveDiffuser

Part No.

E-230 (3A, 4A, 5A) E-234 (17A)G-203SA-405G-204Z-250E-222E-210EA-250E-240

Ejector Assembly A-920ACheck Valve Assembly E-225A Includes Ref No. 2, 3, 5, 6, 8Max. Capacity: 100 lbs./24 hrs. (2000 g/hr)

Part No. Quantity Description

E-301 1 Clamp RingE-302 1 Inlet BodyE-303 1 Diaphragm BoltE-304 1 DiaphragmE-305 1 Diaphragm NutE-306 1 SpringE-309 1 Outlet BodyE-250 1 Check ValveS-302 1 O-RingS-405 1 O-RingZ-250 1 Tube Fitting (3/8" OD)

HIGH/LOW CHECK VALVE ASSEMBLY

A-301 CHLORINE SERVICE

*

***

Part No. Quantity Description

A-301 1 High/Low C.V. AssemblyE-210 1 Ejector BodyE-240 1 DiffuserG-203 1 Seat GasketG-204 2 Body Gasket

1 Nozzle per PPD

Substitute the following parts

A-301A 1 High/Low C.V. Assembly

HIGH/LOW EJECTOR ASSEMBLY MAX. 100 PPD (2000GM/HR)

A-927 CHLORINE SERVICE

A-927A AMMONIA SERVICE

*

*

Substitute the following parts

E-310 1 SpringEA-250 1 Check ValveSA-302 1 O-RingSA-405 1 O-Ring

A-301A AMMONIA SERVICE*

Page 19: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

19

Ref. No.

1

234567891011121314

Quantity

1

1111111111121

Description

Nozzle

Ejector BodyOutlet BodySpringClamping RingInlet BodyTube FittingCheck Valve SealDiaphragm BoltDiaphragmDiaphragm NutSeat GasketBody GasketDiffuser/Nozzle Retainer

Part No.

E-230 (3A, 4A, 5A) E-234 (17A)

E-210E-307E-306E-301E-302

Z-250 (3/8" OD)S-302E-303E-304E-305G-203G-204E-240

Part No.

E-234 (18A)

E-210E-307E-306E-301E-302

ZZ-260 (1/2" OD)S-302E-303E-304E-305G-203G-204E-240

Part No.

E-533 (50X)

E-210E-307E-306E-301E-302

ZZ-270 (5/8" OD)S-302E-303E-304E-305G-203G-204E-540

NOTE: Include Chlorinator Serial Number and Capacity and Size (OD) of Vacuum Tubing Being Used.

Ejector AssemblyMax. Capacity

A-921100 lbs./24hrs. (2000 g/hr)

A-923250 lbs./24 hrs. (5000 g/hr)

A-926500 lbs./24 hrs. (10 kg/hr)

DRAWING NO. A-921/A-923/A-926 Ejector Assembly (Optional)A-300/A-320/A-350 Check Valve Assembly Chlorine Service

Low Pressure - For Back Pressure Up to 20 PSI (1.4KG/CM2)

EJECTOR MODEL A-921 100 PPD (2000 g/hr.)EJECTOR MODEL A-923 250 PPD (5000 g/hr.)

A-300/A-320/A-350Low Pressure Check Valve Assembly

A-300 up to 100 lbs./24 hrs.A-320 @ 250 lbs./24 hrs.A-350 @ 500 lbs./24 hrs.

EJECTOR MODEL A-926 500 PPD (10 kg/hr.)

Page 20: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

20

Ref. No.

1

234567891011121314

Quantity

1

1111111111121

Description

Nozzle

Ejector BodyOutlet BodySpringClamping RingInlet BodyTube FittingCheck Valve SealDiaphragm BoltDiaphragmDiaphragm NutSeat GasketBody GasketDiffuser/Nozzle Retainer

Part No.

E-230 (3A, 4A, 5A)E-234 (17A)

E-710E-707E-310E-701E-702

ZZ-250 (3/8” OD)S-302E-703E-304E-705G-203G-204E-240

Part No.

E-234 (18A)E-710E-707E-310E-701E-702

ZZ-260 (1/2” OD)S-302E-703E-304E-705G-203G-204E-240

Part No.

E-533 (50X)E-710E-707E-310E-701E-702

ZZ-270 (5/8” OD)S-302E-703E-304E-705G-203G-204E-540

NOTE: Include Sulphonator Serial Number and Capacity and Size (OD) of Vacuum Tubing Being Used.

Ejector AssemblyMax. Capacity

A-921S100 lbs./24hrs. (2000 g/hr)

A-923S250 lbs./24 hrs. (5000 g/hr)

A-926S500 lbs./24 hrs. (10 kg/hr)

DRAWING NO. A-921S/A-923S/A-926S Ejector Assembly (Optional)A-300S/A-320S/A-350S Check Valve Assembly Sulfur Dioxide Service

Low Pressure - For Back Pressure Up To 20 PSI (1.4KG/CM2)

A-300S / A-320S / A-350SLow Pressure Check Valve Assembly

A-300S up to 100 lbs./24 hrs.A-320S @ 250 lbs./24 hrs.A-350S @ 500 lbs./24 hrs.

EJECTOR MODEL A-926S 500 PPD (10 kg/hr.)

EJECTOR MODEL A-921S 100 PPD (2000 g/hr.)EJECTOR MODEL A-923S 250 PPD (5000 g/hr.)

Page 21: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

21

Ref. No.

1

234567891011121314

Quantity

1

1111111111121

Description

Nozzle

Ejector BodyOutlet BodySpringClamping RingInlet BodyTube FittingCheck Valve SealDiaphragm BoltDiaphragmDiaphragm NutSeat GasketBody GasketDiffuser/Nozzle Retainer

Part No.

E-230 (3A, 4A, 5A)E-234 (17A)

E-210E-307E-310E-301E-302

Z-250 (3/8” OD)SA-302E-303E-304E-305G-203G-204E-240

NOTE: Include Ammoniator Serial Number and Capacity and Size (OD) of Vacuum Tubing Being Used.

Ejector AssemblyMax. Capacity

A-921A100 lbs./24hrs. (2000 g/hr)

DRAWING NO. A-921A Ejector Assembly (Optional)A-300A Check Valve Assembly Ammonia Service

Low Pressure - For Back Pressure Up to 20 PSI (1.4 KG/CM2)

A-300ALow Pressure Check Valve Assembly

A-300A up to 100 lbs./24 hrs.

EJECTOR MODEL A-921A 100 PPD (2000 g/hr.)

Page 22: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

22

DRAWING NO. A-930 High/Low Pressure Ejector Assembly (Optional)

A-305 HIGH/LOW PRESSUREBALL CHECK VALVE ASSEMBLY

CUT OFF END OF E-240 DIFFUSER WHEN INSTALLING INTO A SOLUTION LINE

E-210 EJECTOR BODY

E-230 or E-234 NOZZLE

G-204 BODY GASKET (2)

E-240 DIFFUSER

A-305 HIGH/LOW PRESSURE BALL CHECK VALVE ASSEMBLY100 PPD (2000 GM/HR) MAXIMUM

Part No. Quantity Description

Z-250 1 Tube Fitting (3/8" O.D.)

E-302 1 Inlet Body

S-302 1 O-Ring

E-303 1 Diaphragm Bolt

E-304 1 Diaphragm

E-301 1 Clamp Ring

Part No. Quantity Description

E-316 1 Outlet Body

E-305 1 Diaphragm Nut

G-203 1 Seat Gasket

E-306 1 Spring

S-405 1 O-Ring

S-417 1 O-Ring

E-556 1 Ball

Page 23: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

23

DRAWING NO. A-950/A-949 Ejector / Dual Check Valve Assembly (Optional) Chlorine Service Only

Max Capacity: Up to 500 PPD (10KG/HR)

TUBE FITTING PER PPD(not shown)

E-551

E-554

E-555

E-301

E-552

E-557

E-240 DIFFUSER ORE-540 NOZZLE RETAINER PER PPD

G-204

E-553

E-556

S-418

S-416

S-415

S-417

S-413

G-204

NOZZLE

A-949 DUAL CHECK VALVE ASSEMBLY

A-950 EJECTOR ASSEMBLY

Part No. Quantity Description

E-301 1 Clamp RingE-551 1 Top BodyE-552 1 Bottom BodyE-553 1 Spring/Ball RetainerE-554 1 PoppetE-555 1 SpringE-556 1 BallS-418 1 O-RingS-413 1 O-RingS-415 1 O-RingS-416 1 O-RingS-417 1 O-Ring

1 Tube Fitting Per PPDZZ-252 — 3/8" OD Tube (to 100 PPD)ZZ-262 — 1/2" OD Tube (250 PPD)ZZ-272 — 5/8" OD Tube (500 PPD)

Part No. Quantity Description

A-949 1 Dual Check Valve AssemblyE-557 1 Ejector Body— 1 Nozzle - Sized Per PPD— 1 Diffuser or Nozzle Retainer Per PPDE-240 — Diffuser (1.5 to 250 PPD)E-540 — Nozzle Retainer

(500 PPD-50X Nozzle Only)G-204 2 Gasket

Page 24: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

24

DRAWING NO. A-2000 Check Valve Assembly — Chlorine Service Only1000 PPD (20KG/HR) / 2000 PPD (40KG/HR)

MS-19 1" NPT UNION WITH S-407 O-RING

MS-21 1" NPT NIPPLE

MS-21 1" NPT NIPPLE

CV-2002 TOP BODY

CV-2004 CLAMP RING

CV-2003 POPPET

CV-2005 SPRING

CV-2001 BOTTOM BODY

S-805 O-RING

S-804 O-RING

A-2000 CHECK VALVE ASSEMBLY (STANDARD)

OUTLET TO E-827 EJECTOR BODYSEE A-2920/A-2922 EJECTOR ASSEMBLY DRAWING

DRAWING NO. A-2920/A-2922 Ejector Assembly — Chlorine Service Only1000 PPD (20KG/HR) / 2000 PPD (40KG/HR)

EJECTOR BODY/NOZZLE/THROAT ASSEMBLYE-840 (1000PPD) = E-827, E-830, E-833, G-1000(2)E-841 (2000PPD) = E-827, E-830, E-831, G-1000(2)

E-831 NOZZLE (2000 PPD)

E-833 NOZZLE (1000 PPD)

E-827 EJECTOR BODYE-830 EJECTOR THROAT

G-1000 GASKET (2)

2" NPT

2" NPT

2" NPT

A-2000 CHECK VALVE ASSEMBLY

(STANDARD)

Page 25: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

25

Application Bulletin No. 1002

IMPORTANT NOTE: The following nozzle selection charts are forCHLORINATORS, SULPHONATORS and AMMONIATORS.When the ejectors are used on gases other than chlorine, besidematerial changes, a factor must be used to determine the equivalentchlorine capacity before using these charts.

Since the density of Sulfur Dioxide is essentially the same as chlorine,the nozzle sizing is the same and the charts can be used as printed.

For ammonia, multiply the capacity by 0.5 and size using theappropriate chlorinator chart.

HYDRAULIC CONSIDERATIONS

In order to achieve proper operation of the chlorinator, it is essentialthat you carefully identify and consider the various factors relatedto installation of the ejector. These hydraulic conditions (listedbelow) must be known in order to create sufficient vacuum tofeed the desired amount of chlorine gas.

1. BACKPRESSURE

a. Backpressure is simply the total water pressure measuredimmediately downstream of the ejector outlet. In Figure 1, ifa pressure gauge were to be installed between the ejectoroutlet and the water main, it would read the backpressure.

b. Beware of “ASSUMING” the backpressure to be the sameas the water system pressure. Pressures throughout awater system can vary greatly.

c. Always consider the maximum backpressure.

2. SUPPLY PRESSURE

a. Supply pressure is the water pressure measured at the inletof the ejector.

b. A pressure gauge should be permanently installed in theejector supply line, as close as possible to the ejector inlet.

c. The required ejector supply pressure can be obtainedfrom any source, as long as the minimum pressureand water flow are available (See Ejector NozzleRequirements charts on the following pages). A boosterpump must be added if necessary.

3. DIFFERENTIAL PRESSURE

a. This is the difference in pressures between the ejector supplypressure and the backpressure. This is often referred to asthe pressure “drop” across the ejector.

b. The differential pressure required to properly operate thechlorinator at a particular chlorine feed rate, will vary asthe backpressure increases or decreases. Generally, asbackpressure increases, the required differential pressurewill increase.

c. Water “booster” pumps are commonly used to create adifferential pressure by raising the system pressure andthen passing the higher pressure water through the ejectorand back into the system (See Fig. 1). However, a boosterpump is not always necessary to obtain the requireddifferential pressure.

4. FRICTION LOSS

a. Friction loss is a term used to describe RESISTANCE towater flowing through pipes, valves and fittings. In general,smaller pipe diameters, longer pipe length, and increasednumbers of valves and fittings, will create more friction loss.

b. In ejector installations, it is important to determine if anysignificant friction loss can occur:

EJECTOR SUPPLY - friction loss on the water supply sideof the ejector will result in lower water pressure available.

BACKPRESSURE - friction loss between the ejector outletand the point of chlorine solution injection, will create higherbackpressure.

c. Friction loss can be calculated from information found instandard books, such as Cameron’s Hydraulic Data, orfrom tables published by pipe and fitting suppliers.

HOW TO USE THE EJECTOR NOZZLEREQUIREMENTS CHART

The charts on the following pages represent minimum values(Ejector Supply Pressures and Water Flow Rates through theejector) necessary to operate a REGAL Series 200 GasChlorinator at each maximum metering tube (rotameter) capacity,against specific backpressures.

THE NOZZLE (or Venturi)

The nozzle in your REGAL ejector is chosen to give you thewidest range of serviceability in most standard applications at themaximum chlorine gas feed rate on the metering tube.Chlorinators Inc. has designed several different sizes of nozzles.Figure 2, below, shows the location of the stamped size designation:

STANDARD NOZZLE

The “Standard Nozzle” shown on each chart is the one whichwould be supplied with a REGAL Series 200 Gas Chlorinatorbased on the maximum capacity of the system. (EXAMPLE: achlorinator with a maximum capacity of 25 PPD (500 gr./hr.) willnormally be supplied with a size 5A nozzle).

Diaphragm Protected SupplyPressure Gauge

Ejector Assembly WithHigh And/Or LowPressure Check Valve

1" Supply Line May Need To Be Oversized InSome Applications

Y-Strainer

Ball Valve (typ.)

DiaphragmProtected BackPressure Gauge

Unions (Typ.) For EasyInstallation And ServiceOf Ejector Assembly

Minimum 1" ChlorineSolution Line. MostApplications Will RequireA Larger Line To AllowFor Friction Losses.

REGAL E-265Spray Diffuser

MAIN WATER SUPPLY LINE

FIG. 1 – Typical Installation Of Remote Mounted Ejector with Solution Line to Point of Application

REGAL E-240 DiffuserWith End Cut Off

Tubing To Vacuum Regulator

BOOSTERPUMP

SCHEDULE 80 PVC RECOMMENDEDFOR ALL PIPES AND FITTINGS

a. Nozzle number stamped here after April 1, 1984

b. Nozzle number stamped here after January 1, 2008

FIG. 2 – Typical REGAL Nozzle

17A

17A

Page 26: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

26

Maximum Chlorine Feed Rate — 4 PPD (75 Grams/Hr.) See Note.

NOZZLE Standard Nozzle No. 4A* No. 3A No. 5A No. 17AEJECTOR

BACKPRESSUREREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow Rate

PSIG

0102030

40506070

8090100110

120130140150

160

PSIG @ GPM

7 @ 1.518 @ 2.733 @ 3.947 @ 4.9

64 @ 5.681 @ 6.396 @ 7.2109 @ 8.3

126 @ 8.9140 @ 9.4154 @ 9.9173 @ 10.3

188 @ 10.8204 @ 11.0220 @ 11.6235 @ 11.8

245 @ 12.1

PSIG @ GPM

5 @ 1.020 @ 2.037 @ 2.649 @ 3.2

66 @ 3.781 @ 4.597 @ 5.3111 @ 5.7

125 @ 6.2139 @ 6.5151 @ 6.7166 @ 6.9

182 @ 7.2196 @ 7.5211 @ 7.8 225 @ 8.1

kg/cm2 @ l/sec.

0.49 @ 0.091.27 @ 0.172.32 @ 0.253.30 @ 0.31

4.50 @ 0.355.69 @ 0.406.75 @ 0.457.66 @ 0.52

8.86 @ 0.569.84 @ 0.5910.83 @ 0.6212.16 @ 0.65

13.22 @ 0.6814.34 @ 0.6915.47 @ 0.7316.52 @ 0.74

17.22 @ 0.76

kg/cm2 @ l/sec.

0.35 @ 0.061.41 @ 0.132.60 @ 0.163.44 @ 0.20

4.64 @ 0.235.69 @ 0.286.82 @ 0.337.80 @ 0.36

8.79 @ 0.399.77 @ 0.4110.62 @ 0.4211.67 @ 0.44

12.97 @ 0.4513.78 @ 0.4714.83 @ 0.49 15.82 @ 0.51

PSIG @ GPM

7 @ 2.118 @ 4.033 @ 5.646 @ 7.3

63 @ 8.777 @ 9.691 @ 11.0108 @ 11.8

122 @ 12.6137 @ 13.7150 @ 14.2168 @ 14.9

184 @ 15.5199 @ 16.2213 @ 17.0220 @ 17.5

242 @ 18.4

kg/cm2 @ l/sec.

0.49 @ 0.131.27 @ 0.252.32 @ 0.353.23 @ 0.46

4.43 @ 0.555.41 @ 0.616.40 @ 0.697.59 @ 0.74

8.58 @ 0.799.63 @ 0.8610.55 @ 0.9011.81 @ 0.94

12.94 @ 0.9813.99 @ 1.0214.97 @ 1.0715.47 @ 1.10

17.01 @ 1.16

PSIG @ GPM

6 @ 2.619 @ 7.035 @ 10.555 @ 12.6

74 @ 14.790 @ 16.2104 @ 17.3122 @ 19.5

137 @ 20.7155 @ 21.8173 @ 23.0190 @ 24.0

209 @ 25.0228 @ 25.6245 @ 26.0263 @ 27.4

284 @ 28.8

kg/cm2 @ l/sec.

0.42 @ 0.161.34 @ 0.442.46 @ 0.663.87 @ 0.79

5.20 @ 0.936.33 @ 1.027.31 @ 1.098.58 @ 1.23

9.63 @ 1.3110.90 @ 1.3812.16 @ 1.4513.36 @ 1.51

14.69 @ 1.5816.03 @ 1.6117.22 @ 1.6418.49 @ 1.73

19.97 @ 1.82

kg/cm2

00.701.402.10

2.813.514.214.92

5.626.327.037.73

8.449.149.8410.55

11.25

*Standard Nozzle Supplied with Chlorinator for Indicated Maximum Feed Rate. NOTE: GPM is U.S. Gallons. Metric is liters per sec. (l/sec.)

REGAL EJECTOR NOZZLE REQUIREMENTS

USING THE CHARTSTo find out what hydraulic conditions you need to operate thechlorinator, follow these steps:

1. a. Determine the maximum required feed rate for thesystem to be treated.

b. Refer to the Maximum Chlorine Feed Rate Charts onthe following pages. Select the chart for the feed ratethat is next higher than your system’s required maximum.Ideally, your system’s requirement should be about50% to 75% of the chlorinator’s maximum feed rate.Do not select a chart for a feed rate that exactlymatches your system’s requirement. Use the nexthigher chart. With this approach, the metering ballshould be in the upper half of the metering tube formost adjustments that you might have to make.

IMPORTANT NOTE: You may not need to feed the maximumrate of gas flow on the metering tube, but you should still usethe values given for that maximum capacity.

2. Using the column headed “EJECTOR BACKPRESSURE”find the maximum backpressure for your system (seedefinition of “backpressure” on previous page) in English units of PSIG or Metric units of (kg/cm2).

3. Follow the backpressure line across to the first column underthe heading “STANDARD NOZZLE,” marked with an (*).

4. Read the required minimum “EJECTOR SUPPLY PRESSURE” in PSIG or (kg/cm2) and immediately to the right of EJECTOR SUPPLY PRESSURE, read the requiredminimum “WATER FLOW RATE” in U.S. GPM or (liters/sec).

5. The difference between the Ejector Supply Pressure andthe Backpressure is the required DIFFERENTIAL PRESSURE(see previous page).

Example: Using a water treatment system as in Fig. 1, with apressure in the water main at the ejector of 60 PSIG maximum(4.21 kg/cm2) and a desired chlorine feed rate of 18 PPD.

a. Use the 25 PPD chart.

b. Under “EJECTOR BACKPRESSURE” locate 60 PSI(4.21 kg/cm2) and read across to the “STANDARDNOZZLE No. 5A*” column.

c. The EJECTOR SUPPLY PRESSURE must be at least94 PSI (6.61 kg/cm2) and the nozzle will require atleast 10.8 U.S. GPM (0.68 l/sec.) WATER FLOW.

d. Therefore, the DIFFERENTIAL PRESSURE necessaryis 34 PSI (2.40 kg/cm2) or 94 (6.61) minus 60 (4.21).

e. In this example, a booster pump is used to take waterfrom the system and raise (boost) the pressure atleast 34 PSI (2.40 kg/cm2).

NOTE: However, if another, independent water source wereavailable that could provide the ejector with at least 94 PSI(6.61 kg/cm2) pressure at 10.8 U.S. GPM (0.68 l/sec.) thatwater source could be used to operate the ejector without abooster pump.

USING A NON-STANDARD NOZZLE

It may be necessary to use a nozzle which is not “standard” forthe capacity of the chlorinator. This is usually caused when:1. A REGAL Gas Chlorinator is replacing an older, existinggas chlorinator and available hydraulic conditions do notmatch the specifications for the “standard” REGAL nozzle.

2. Or, an existing booster pump is not capable of providingrequired water flow and/or pressure.

3. Or, the water supply and/or solution pipe may be toosmall compared to the flow rate for the standard nozzle. Adifferent nozzle may require a lesser flow for a givencapacity and therefore produce less friction.

In these cases, use the chart appropriate for the MaximumChlorine Feed Rate. Find the EJECTOR BACKPRESSURE,and look across the nozzle columns to find EJECTOR SUPPLYPRESSURE and WATER FLOW RATE which the system canmeet. Use the nozzle shown at the top of that column.

NOTE: If it does not appear that your application can meet therequirements shown, contact Chlorinators Incorporated.

Page 27: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

27

Maximum Chlorine Feed Rate — 10 PPD (200 Grams/Hr.) See Note.

NOZZLE Standard Nozzle No. 4A* No. 3A No. 5A No. 17AEJECTOR

BACKPRESSUREREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow Rate

PSIG

0102030

40506070

8090100110

120130140150

160

PSIG @ GPM

10 @ 1.724 @ 3.335 @ 4.350 @ 5.0

64 @ 5.781 @ 6.696 @ 7.2110 @ 8.0

125 @ 8.6139 @ 9.2154 @ 9.7169 @ 10.2

183 @ 10.6199 @ 11.3214 @ 11.5232 @ 11.9

245 @ 12.4

PSIG @ GPM

10 @ 1.425 @ 2.341 @ 2.955 @ 3.5

68 @ 3.984 @ 4.397 @ 4.6111 @ 5.0

125 @ 5.8139 @ 6.4153 @ 6.7170 @ 7.1

183 @ 7.4199 @ 7.7212 @ 7.8230 @ 8.0

242 @ 8.3

kg/cm2 @ l/sec.

0.70 @ 0.111.69 @ 0.212.46 @ 0.273.52 @ 0.32

4.50 @ 0.365.69 @ 0.426.75 @ 0.457.73 @ 0.50

8.79 @ 0.549.77 @ 0.5810.83 @ 0.6111.88 @ 0.64

12.86 @ 0.6713.99 @ 0.7115.04 @ 0.7316.31 @ 0.75

17.22 @ 0.78

kg/cm2 @ l/sec.

0.70 @ 0.091.76 @ 0.152.88 @ 0.183.87 @ 0.22

4.78 @ 0.255.91 @ 0.276.82 @ 0.297.80 @ 0.32

8.79 @ 0.379.77 @ 0.4010.76 @ 0.4211.95 @ 0.45

12.86 @ 0.4713.99 @ 0.4914.90 @ 0.5016.17 @ 0.51

17.01 @ 0.52

PSIG @ GPM

9 @ 2.323 @ 4.534 @ 6.249 @ 7.7

64 @ 8.878 @ 9.793 @ 10.8110 @ 11.7

122 @ 12.7138 @ 13.7151 @ 14.3168 @ 14.9

184 @ 15.9199 @ 16.3212 @ 17.2228 @ 17.5

241 @ 18.2

kg/cm2 @ l/sec.

0.63 @ 0.151.62 @ 0.282.39 @ 0.393.44 @ 0.49

4.50 @ 0.565.48 @ 0.616.54 @ 0.687.73 @ 0.74

8.58 @ 0.809.70 @ 0.8610.62 @ 0.9011.81 @ 0.94

12.94 @ 1.0013.99 @ 1.0314.90 @ 1.0816.03 @ 1.10

16.94 @ 1.15

PSIG @ GPM

8 @ 3.023 @ 7.337 @ 10.657 @ 12.8

76 @ 14.991 @ 16.4106 @ 17.9124 @ 19.7

139 @ 20.9157 @ 22.0174 @ 23.2192 @ 24.2

213 @ 25.2232 @ 26.2248 @ 27.1270 @ 28.3

288 @ 29.1

kg/cm2 @ l/sec.

0.56 @ 0.191.62 @ 0.462.60 @ 0.674.01 @ 0.81

5.34 @ 0.946.40 @ 1.037.45 @ 1.138.72 @ 1.24

9.77 @ 1.3211.04 @ 1.3912.23 @ 1.4613.50 @ 1.53

14.97 @ 1.5916.31 @ 1.6517.43 @ 1.7118.98 @ 1.79

20.25 @ 1.84

kg/cm2

00.701.402.10

2.813.514.214.92

5.626.327.037.73

8.449.149.8410.55

11.25

Maximum Chlorine Feed Rate — 25 PPD (500 Grams/Hr.) See Note.

NOZZLE Standard Nozzle No. 5A* No. 3A No. 4A No. 17AEJECTOR

BACKPRESSUREREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow Rate

PSIG

0102030

40506070

8090100110

120130140150

160

PSIG @ GPM

14 @ 3.128 @ 5.447 @ 7.562 @ 8.6

71 @ 9.281 @ 9.994 @ 10.8109 @ 12.1

122 @ 12.7139 @ 13.8153 @ 14.4168 @ 15.0

183 @ 15.9199 @ 16.3214 @ 17.0220 @ 17.5

233 @ 18.4

PSIG @ GPM

16 @ 1.735 @ 2.755 @ 3.575 @ 4.0

94 @ 4.5106 @ 4.9117 @ 5.2131 @ 5.5

143 @ 5.8156 @ 6.0169 @ 6.3179 @ 6.5

191 @ 6.6204 @ 6.9220 @ 7.1235 @ 7.4

256 @ 7.7

kg/cm2 @ l/sec.

0.98 @ 0.201.97 @ 0.343.30 @ 0.474.36 @ 0.54

4.99 @ 0.585.69 @ 0.626.61 @ 0.687.66 @ 0.76

8.58 @ 0.809.77 @ 0.8710.76 @ 0.9111.81 @ 0.95

12.86 @ 1.0013.99 @ 1.0315.04 @ 1.0715.47 @ 1.10

16.38 @ 1.16

kg/cm2 @ l/sec.

1.12 @ 0.112.46 @ 0.173.87 @ 0.225.27 @ 0.25

6.61 @ 0.287.45 @ 0.318.23 @ 0.339.21 @ 0.35

10.05 @ 0.3710.97 @ 0.3811.88 @ 0.4012.58 @ 0.41

13.43 @ 0.4214.34 @ 0.4415.47 @ 0.4516.52 @ 0.47

18.00 @ 0.49

PSIG @ GPM

16 @ 2.435 @ 3.350 @ 4.966 @ 5.9

78 @ 6.594 @ 7.1107 @ 7.6117 @ 8.1

130 @ 8.6142 @ 9.2158 @ 9.8174 @ 10.3

189 @ 10.8204 @ 11.3220 @ 11.6235 @ 11.9

250 @ 12.4

kg/cm2 @ l/sec.

1.12 @ 0.152.46 @ 0.213.52 @ 0.314.64 @ 0.37

5.48 @ 0.416.61 @ 0.457.52 @ 0.488.23 @ 0.51

9.14 @ 0.549.98 @ 0.5811.11 @ 0.6212.23 @ 0.65

13.29 @ 0.6814.34 @ 0.7115.47 @ 0.7316.52 @ 0.75

17.58 @ 0.78

PSIG @ GPM

11 @ 3.426 @ 7.544 @ 10.859 @ 12.9

78 @ 15.193 @ 16.8107 @ 18.2126 @ 20.0

142 @ 21.0161 @ 22.2179 @ 23.5195 @ 24.5

215 @ 25.5235 @ 26.5252 @ 27.3273 @ 28.5

291 @ 29.4

kg/cm2 @ l/sec.

0.77 @ 0.211.83 @ 0.473.09 @ 0.684.15 @ 0.81

5.48 @ 0.956.54 @ 1.067.52 @ 1.158.86 @ 1.26

9.98 @ 1.3211.32 @ 1.4012.58 @ 1.4813.71 @ 1.55

15.11 @ 1.6116.52 @ 1.6717.72 @ 1.7219.19 @ 1.80

20.46 @ 1.85

kg/cm2

00.701.402.10

2.813.514.214.92

5.626.327.037.73

8.449.149.8410.55

11.25

Maximum Chlorine Feed Rate — 50 PPD (900 Grams/Hr.) See Note.

NOZZLE Standard Nozzle No. 17A* No. 3A No. 4A No. 5AEJECTOR

BACKPRESSUREREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow Rate

PSIG

0102030

40506070

8090100110

120130140150

160

PSIG @ GPM

15 @ 5.029 @ 7.845 @ 11.061 @ 13.0

80 @ 15.397 @ 17.0109 @ 18.5129 @ 20.3

144 @ 21.3164 @ 22.5182 @ 23.7199 @ 24.7

218 @ 25.9238 @ 26.9256 @ 27.7277 @ 28.9

295 @ 29.8

PSIG @ GPM

23 @ 2.256 @ 3.585 @ 4.3108 @ 4.8

126 @ 5.4146 @ 5.8167 @ 6.2189 @ 6.5

208 @ 6.8225 @ 7.2240 @ 7.6261 @ 7.9

272 @ 8.3293 @ 8.5

— —

kg/cm2 @ l/sec.

1.05 @ 0.322.04 @ 0.493.16 @ 0.694.29 @ 0.82

5.62 @ 0.976.82 @ 1.077.66 @ 1.179.07 @ 1.28

10.12 @ 1.3411.53 @ 1.4212.79 @ 1.4913.99 @ 1.56

15.33 @ 1.6316.73 @ 1.7018.00 @ 1.7519.47 @ 1.82

20.74 @ 1.88

kg/cm2 @ l/sec.

1.62 @ 0.143.94 @ 0.225.98 @ 0.277.59 @ 0.30

8.86 @ 0.3410.26 @ 0.3711.74 @ 0.3913.29 @ 0.41

14.62 @ 0.4315.82 @ 0.4516.87 @ 0.4818.35 @ 0.50

19.12 @ 0.5220.60 @ 0.54

— —

PSIG @ GPM

26 @ 3.457 @ 5.586 @ 6.9111 @ 7.8

133 @ 8.9147 @ 9.5170 @ 10.0187 @ 10.3

199 @ 11.0213 @ 11.4228 @ 11.6232 @ 12.0

255 @ 12.5265 @ 12.6272 @ 12.8285 @ 13.1

kg/cm2 @ l/sec.

1.83 @ 0.214.01 @ 0.356.05 @ 0.447.80 @ 0.49

9.35 @ 0.5610.33 @ 0.6011.95 @ 0.6313.15 @ 0.65

13.99 @ 0.6914.97 @ 0.7216.03 @ 0.7316.31 @ 0.76

17.93 @ 0.7918.63 @ 0.8019.12 @ 0.8120.04 @ 0.83

PSIG @ GPM

17 @ 3.838 @ 6.663 @ 8.683 @ 10.0

101 @ 11.2112 @ 12.5122 @ 12.8136 @ 13.6

152 @ 14.3166 @ 15.0173 @ 15.3183 @ 15.9

191 @ 16.1206 @ 16.7221 @ 17.4233 @ 18.0

248 @ 18.5

kg/cm2 @ l/sec.

1.20 @ 0.242.67 @ 0.424.43 @ 0.545.83 @ 0.63

7.10 @ 0.717.87 @ 0.798.58 @ 0.819.56 @ 0.86

10.69 @ 0.9011.67 @ 0.9512.16 @ 0.9712.86 @ 1.00

13.43 @ 1.0214.48 @ 1.0515.54 @ 1.1016.38 @ 1.14

17.43 @ 1.17

kg/cm2

00.701.402.10

2.813.514.214.92

5.626.327.037.73

8.449.149.8410.55

11.25

*Standard Nozzle Supplied with Chlorinator for Indicated Maximum Feed Rate. NOTE: GPM is U.S. Gallons. Metric is liters per sec. (l/sec.)

Page 28: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

28

Maximum Chlorine Feed Rate — 100 PPD (2000 Grams/Hr.) See Note.

NOZZLE Standard Nozzle No. 17A* No. 3A No. 4A No. 5AEJECTOR

BACK-PRESSURE

REQUIRED Ejector Supply Pressure and

Water Flow Rate

REQUIRED Ejector Supply Pressure and

Water Flow Rate

REQUIRED Ejector Supply Pressure and

Water Flow Rate

REQUIRED Ejector Supply Pressure and

Water Flow Rate

PSIG

0102030

40506070

8090100110

120130140150

160

PSIG @ GPM

23 @ 7.443 @ 10.057 @ 12.170 @ 13.5

84 @ 15.5101 @ 17.3113 @ 18.9132 @ 20.6

146 @ 21.8167 @ 23.0185 @ 24.0202 @ 25.0

220 @ 26.1241 @ 27.1260 @ 28.2281 @ 29.0

298 @ 29.9

PSIG @ GPM

59 @ 3.6100 @ 4.7148 @ 5.8188 @ 6.5

242 @ 7.3268 @ 7.9

— —

————

————

kg/cm2 @ l/sec.

1.62 @ 0.473.02 @ 0.634.01 @ 0.764.92 @ 0.85

5.91 @ 0.987.10 @ 1.097.94 @ 1.199.28 @ 1.30

10.26 @ 1.3811.74 @ 1.4513.01 @ 1.5114.20 @ 1.58

15.47 @ 1.6516.94 @ 1.7118.28 @ 1.7819.75 @ 1.83

20.95 @ 1.89

kg/cm2 @ l/sec.

4.15 @ 0.237.03 @ 0.3010.40 @ 0.3713.22 @ 0.41

17.01 @ 0.4618.84 @ 0.50

— —

————

————

PSIG @ GPM

50 @ 5.1108 @ 7.8165 @ 9.7213 @ 11.3

251 @ 12.4285 @ 13.0

— —

————

————

kg/cm2 @ l/sec.

3.52 @ 0.327.59 @ 0.4911.60 @ 0.6114.97 @ 0.71

17.65 @ 0.7820.04 @ 0.82

— —

————

————

PSIG @ GPM

27 @ 5.157 @ 8.493 @ 10.8119 @ 12.8

143 @ 14.0169 @ 15.1188 @ 16.1202 @ 16.7

220 @ 17.4236 @ 18.2261 @ 19.3279 @ 19.9

295 @ 20.5———

kg/cm2 @ l/sec.

1.90 @ 0.324.01 @ 0.536.54 @ 0.688.37 @ 0.81

10.05 @ 0.8811.88 @ 0.9513.22 @ 1.0214.20 @ 1.05

15.47 @ 1.1016.59 @ 1.1518.35 @ 1.2219.61 @ 1.26

20.74 @ 1.29———

kg/cm2

00.701.402.10

2.813.514.214.92

5.626.327.037.73

8.449.149.8410.55

11.25

No. 18AREQUIRED Ejector

Supply Pressure and Water Flow Rate

PSIG @ GPM

19 @ 9.135 @ 11.250 @ 13.864 @ 15.7

76 @ 17.290 @ 19.6106 @ 21.3120 @ 23.2

137 @ 24.7153 @ 26.4168 @ 27.6183 @ 28.7

202 @ 30.1218 @ 31.3235 @ 32.5251 @ 33.4

272 @ 33.7

kg/cm2 @ l/sec.

1.34 @ 0.572.46 @ 0.713.52 @ 0.874.50 @ 0.99

5.34 @ 1.086.33 @ 1.247.45 @ 1.348.44 @ 1.46

9.63 @ 1.5610.76 @ 1.6711.81 @ 1.7412.86 @ 1.81

14.20 @ 1.9015.33 @ 1.9716.52 @ 2.0517.65 @ 2.11

19.12 @ 2.13

Maximum Chlorine Feed Rate — 200 PPD (4000 Grams/Hr.) See Note.

NOZZLE Standard Nozzle No. 18A* No. 17A No. 50X Standard Nozzle No. 18A*

EJECTORBACK-

PRESSURE

REQUIRED Ejector Supply Pressure and

Water Flow Rate

REQUIRED Ejector Supply Pressure and

Water Flow Rate

REQUIRED Ejector Supply Pressure and

Water Flow Rate

REQUIRED Ejector Supply Pressure and

Water Flow Rate

PSIG

0102030

40506070

8090100110

120130140150

160

PSIG @ GPM

26 @ 9.351 @ 13.867 @ 16.283 @ 18.4

97 @ 20.2110 @ 21.8124 @ 23.5135 @ 24.4

147 @ 25.5160 @ 26.7173 @ 27.8190 @ 28.9

207 @ 30.1222 @ 31.3239 @ 32.4255 @ 33.4

275 @ 34.5

PSIG @ GPM

27 @ 7.858 @ 12.480 @ 14.396 @ 16.1

107 @ 17.3123 @ 18.9138 @ 20.1147 @ 21.0

163 @ 22.1176 @ 23.4193 @ 24.4209 @ 25.5

228 @ 26.3245 @ 27.3267 @ 28.4288 @ 29.2

306 @ 30.2

kg/cm2 @ l/sec.

1.83 @ 0.593.59 @ 0.874.71 @ 1.025.83 @ 1.16

6.82 @ 0.277.73 @ 1.388.72 @ 1.489.49 @ 1.54

10.33 @ 1.6111.25 @ 1.6812.16 @ 1.7513.36 @ 1.82

14.55 @ 1.9015.61 @ 1.9716.80 @ 2.0417.93 @ 2.11

19.33 @ 2.18

kg/cm2 @ l/sec.

1.90 @ 0.494.08 @ 0.785.62 @ 0.906.75 @ 1.02

7.52 @ 1.098.65 @ 1.199.70 @ 1.2710.33 @ 1.32

11.46 @ 1.3912.37 @ 1.4813.57 @ 1.5414.69 @ 1.61

16.03 @ 1.6617.22 @ 1.7218.77 @ 1.7920.25 @ 1.84

21.51 @ 1.91

PSIG @ GPM

22 @ 8.634 @ 12.747 @ 15.567 @ 19.3

88 @ 22.4109 @ 25.3130 @ 27.9148 @ 29.9

169 @ 31.9192 @ 34.5210 @ 36.8228 @ 38.5

————

kg/cm2 @ l/sec.

1.55 @ 0.542.39 @ 0.803.30 @ 0.984.71 @ 1.22

6.19 @ 1.417.66 @ 1.609.14 @ 1.7610.40 @ 1.89

11.88 @ 2.0113.50 @ 2.1814.76 @ 2.3216.03 @ 2.43

————

PSIG @ GPM

50 @ 13.470 @ 15.992 @ 18.1103 @ 19.8

118 @ 21.8130 @ 23.9143 @ 25.1158 @ 25.9

172 @ 27.3183 @ 28.5195 @ 29.1211 @ 30.2

214 @ 31.0238 @ 31.9253 @ 33.3272 @ 34.3

288 @ 35.6

kg/cm2 @ l/sec.

3.52 @ 0.854.92 @ 1.006.47 @ 1.147.24 @ 1.25

8.03 @ 1.389.14 @ 1.5110.05 @ 1.5811.11 @ 1.63

12.09 @ 1.7212.86 @ 1.8013.71 @ 1.8414.83 @ 1.91

15.04 @ 1.9616.73 @ 2.0117.79 @ 2.1019.12 @ 2.16

20.25 @ 2.25

kg/cm2

00.701.402.10

2.813.514.214.92

5.626.327.037.73

8.449.149.8410.55

11.25

No. 50XREQUIRED Ejector

Supply Pressure and Water Flow Rate

PSIG @ GPM

27 @ 11.537 @ 13.849 @ 16.168 @ 19.5

89 @ 22.7109 @ 25.3130 @ 27.9148 @ 29.9

169 @ 31.9192 @ 34.5210 @ 36.8228 @ 38.5

————

kg/cm2 @ l/sec.

1.90 @ 0.732.60 @ 0.873.44 @ 1.024.78 @ 1.23

6.26 @ 1.437.66 @ 1.609.14 @ 1.7610.40 @ 1.89

11.88 @ 2.0113.50 @ 2.1814.76 @ 2.3216.03 @ 2.43

————

Maximum Chlorine Feed Rate — 500 PPD (10 Kg./Hr.) See Note.

NOZZLE Standard Nozzle No. 50X*

EJECTOR BACKPRESSURE REQUIRED Ejector Supply Pressure and Water Flow Rate

PSIG

0102030

40506070

8090100110

PSIG @ GPM

72 @ 20.789 @ 23.197 @ 24.1105 @ 25.2

113 @ 26.3125 @ 27.3138 @ 29.0155 @ 31.5

173 @ 32.2192 @ 34.5210 @ 36.8228 @ 38.5

kg/cm2 @ l/sec.

5.06 @ 1.316.26 @ 1.466.82 @ 1.527.38 @ 1.59

7.94 @ 1.668.79 @ 1.729.70 @ 1.8310.90 @ 1.99

12.16 @ 2.0313.50 @ 2.1814.76 @ 2.3216.03 @ 2.43

kg/cm2

00.701.402.10

2.813.514.214.92

5.626.327.037.73

Maximum Chlorine Feed Rate — 250 PPD (4900 Grams/Hr.) See Note.

*Standard Nozzle Supplied with Chlorinator for Indicated Maximum Feed Rate. NOTE: GPM is U.S. Gallons. Metric is liters per sec. (l/sec.)

Page 29: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

29

Maximum Chlorine Feed Rate — 4 PPD (75 Grams/Hr.) See Note.

NOZZLE No. 13A No. 14A No. 15A No. 16AEJECTOR

BACKPRESSUREREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow Rate

PSIG

0102030

40506070

8090100110

120130140150

160

PSIG @ GPM

5 @ 1.022 @ 1.932 @ 2.546 @ 3.0

61 @ 3.577 @ 3.890 @ 4.2106 @ 4.5

120 @ 4.6134 @ 4.9149 @ 5.1162 @ 5.3

178 @ 5.6192 @ 5.8207 @ 6.0222 @ 6.2

236 @ 6.4

PSIG @ GPM

4 @ 1.318 @ 2.831 @ 3.347 @ 3.9

62 @ 4.577 @ 5.092 @ 5.4106 @ 5.8

120 @ 6.1135 @ 6.5150 @ 6.7164 @ 7.1

179 @ 7.5192 @ 7.7208 @ 8.1 223 @ 8.4

237 @ 8.6

kg/cm2 @ l/sec.

.352 @ .0631.55 @ .1202.25 @ .1583.23 @ .189

4.29 @ .2215.41 @ .2406.33 @ .2597.45 @ .284

8.44 @ .2909.42 @ .30910.48 @ .32211.40 @ .334

12.51 @ .35313.50 @ .36614.55 @ .37915.61 @ .391

16.59 @ .404

kg/cm2 @ l/sec.

.281 @ .0981.27 @ .2122.18 @ .2503.30 @ .295

4.36 @ .3415.41 @ .3796.47 @ .4097.45 @ .439

8.44 @ .4629.49 @ .49210.55 @ .50811.53 @ .538

12.58 @ .56813.50 @ .58314.62 @ .614 15.68 @ .636

16.66 @ .652

PSIG @ GPM

2 @ 1.924 @ 4.041 @ 4.958 @ 5.7

74 @ 6.491 @ 7.0107 @ 7.7124 @ 8.2

141 @ 8.7158 @ 9.2173 @ 9.7188 @ 10.1

205 @ 10.5222 @ 10.9238 @ 11.3255 @ 11.7

270 @ 12.0

kg/cm2 @ l/sec.

0.14 @ .1201.69 @ .2522.88 @ .3094.08 @ .360

5.20 @ .4036.40 @ .4427.52 @ .4868.72 @ .517

9.91 @ .54911.11 @ .58012.16 @ .61213.22 @ .637

14.41 @ .66215.61 @ .68816.73 @ .71317.93 @ .738

18.98 @ .757

PSIG @ GPM

3 @ 2.220 @ 4.736 @ 6.256 @ 7.5

74 @ 8.587 @ 9.6104 @ 10.6120 @ 11.3

138 @ 12.0155 @ 12.7171 @ 13.3188 @ 13.9

205 @ 14.5221 @ 14.9238 @ 15.6254 @ 16.0

270 @ 16.5

kg/cm2 @ l/sec.

.211 @ .1391.41 @ .2972.53 @ .3913.94 @ .473

5.20 @ .5366.12 @ .6067.31 @ .6698.44 @ .713

9.70 @ .75710.90 @ .80112.02 @ .83913.22 @ .877

14.41 @ .91515.54 @ .94016.73 @ .98417.86 @ 1.01

18.98 @ 1.04

kg/cm2

00.701.402.10

2.813.514.214.92

5.626.327.037.73

8.449.149.8410.55

11.25

Maximum Chlorine Feed Rate — 10 PPD (200 Grams/Hr.) See Note.

NOZZLE No. 13A No. 14A No. 15A No. 16AEJECTOR

BACKPRESSUREREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow Rate

PSIG

0102030

40506070

8090100110

120130140150

160

PSIG @ GPM

10 @ 1.226 @ 2.339 @ 2.750 @ 3.1

62 @ 3.576 @ 3.890 @ 4.2104 @ 4.5

118 @ 4.8132 @ 5.1147 @ 5.3161 @ 5.5

175 @ 6.0188 @ 6.2204 @ 6.4217 @ 6.6

230 @ 6.8

PSIG @ GPM

6 @ 1.721 @ 2.732 @ 3.352 @ 4.0

62 @ 4.578 @ 5.092 @ 5.4108 @ 5.8

121 @ 6.1136 @ 6.4151 @ 6.8167 @ 7.1

180 @ 7.4195 @ 7.7209 @ 8.0 224 @ 8.3

238 @ 8.6

kg/cm2 @ l/sec.

.703 @ .0761.83 @ .1392.74 @ .1703.52 @ .196

4.36 @ .2215.34 @ .2406.33 @ .2657.31 @ .284

8.30 @ .3039.28 @ .32210.34 @ .33411.32 @ .347

12.30 @ .37913.22 @ .39114.34 @ .40415.26 @ .416

16.17 @ .429

kg/cm2 @ l/sec.

.422 @ .1071.48 @ .1702.53 @ .2083.94 @ .252

4.78 @ .2845.91 @ .3157.03 @ .3418.16 @ .366

9.28 @ .38510.48 @ .40411.39 @ .42912.51 @ .448

13.57 @ .46714.69 @ .48615.82 @ .505 16.87 @ .523

18.00 @ .543

PSIG @ GPM

4 @ 2.124 @ 3.840 @ 4.858 @ 5.7

74 @ 6.391 @ 7.0108 @ 7.6124 @ 8.2

140 @ 8.7157 @ 9.2174 @ 9.7189 @ 10.1

206 @ 10.5222 @ 10.8238 @ 11.3254 @ 11.6

269 @ 12.0

kg/cm2 @ l/sec.

0.28 @ .1321.69 @ .2402.81 @ .3034.08 @ .360

5.20 @ .3976.40 @ .4427.59 @ .4808.72 @ .517

9.84 @ .54911.04 @ .58012.23 @ .61213.29 @ .637

14.48 @ .66215.61 @ .68116.73 @ .71517.86 @ .732

18.91 @ .757

PSIG @ GPM

5 @ 2.820 @ 4.939 @ 6.755 @ 7.8

74 @ 9.087 @ 10.2103 @ 11.2120 @ 11.8

138 @ 12.6155 @ 13.2172 @ 13.8188 @ 14.5

205 @ 15.0222 @ 15.6239 @ 16.2256 @ 16.7

272 @ 17.2

kg/cm2 @ l/sec.

.352 @ .1771.41 @ .3092.74 @ .4233.87 @ .492

5.20 @ .5686.12 @ .6447.24 @ .7078.44 @ .744

9.70 @ .79510.90 @ .83312.09 @ .87113.22 @ .915

14.41 @ .94615.61 @ .98416.80 @ 1.0218.00 @ 1.05

19.12 @ 1.09

kg/cm2

00.701.402.10

2.813.514.214.92

5.626.327.037.73

8.449.149.8410.55

11.25

Maximum Chlorine Feed Rate — 25 PPD (500 Grams/Hr.) See Note.

NOZZLE No. 13A No. 14A No. 15A No. 16AEJECTOR

BACKPRESSUREREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow Rate

PSIG

0102030

40506070

8090100110

120130140150

160

PSIG @ GPM

15 @ 1.638 @ 2.760 @ 3.376 @ 3.6

83 @ 4.0100 @ 4.4103 @ 4.4114 @ 4.6

125 @ 4.8139 @ 5.4154 @ 5.6167 @ 5.8

179 @ 6.1193 @ 6.3207 @ 6.5222 @ 6.7

236 @ 6.9

PSIG @ GPM

11 @ 2.228 @ 3.042 @ 3.755 @ 4.2

66 @ 4.978 @ 5.293 @ 5.7108 @ 6.1

122 @ 6.5138 @ 6.8152 @ 7.3168 @ 7.7

182 @ 7.9200 @ 8.3209 @ 8.5 224 @ 8.8

239 @ 9.1

kg/cm2 @ l/sec.

1.05 @ .1012.67 @ .1704.22 @ .2085.34 @ .227

6.19 @ .2527.03 @ .2657.80 @ .2788.44 @ .290

9.35 @ .30310.05 @ .32810.83 @ .35311.74 @ .366

12.58 @ .38513.57 @ .39714.55 @ .41015.61 @ .423

16.59 @ .435

kg/cm2 @ l/sec.

.773 @ .1391.97 @ .2212.95 @ .2713.87 @ .303

4.64 @ .3285.48 @ .3536.54 @ .3797.59 @ .404

8.58 @ .4239.70 @ .45410.69 @ .47311.81 @ .498

12.80 @ .52414.06 @ .54314.69 @ .562 15.75 @ .580

16.80 @ .599

PSIG @ GPM

6 @ 2.224 @ 3.836 @ 4.653 @ 5.4

69 @ 6.187 @ 6.8103 @ 7.4118 @ 8.0

135 @ 8.5153 @ 9.0168 @ 9.5184 @ 9.8

201 @ 10.3217 @ 10.8233 @ 11.2250 @ 11.5

266 @ 11.8

kg/cm2 @ l/sec.

0.42 @ .1391.69 @ .2402.53 @ .2903.73 @ .341

4.85 @ .3856.12 @ .4297.24 @ .4678.30 @ .505

9.49 @ .53610.76 @ .56811.81 @ .59912.94 @ .618

14.13 @ .65015.26 @ .68116.38 @ .70717.58 @ .726

18.70 @ .744

PSIG @ GPM

7 @ 2.723 @ 5.038 @ 6.155 @ 7.5

73 @ 8.690 @ 9.5105 @ 10.3123 @ 11.2

139 @ 12.0156 @ 12.6172 @ 13.2189 @ 13.9

206 @ 14.4223 @ 15.0240 @ 15.6257 @ 16.1

273 @ 16.6

kg/cm2 @ l/sec.

.492 @ .1701.62 @ .3152.67 @ .3853.87 @ .473

5.13 @ .5436.33 @ .5997.38 @ .6508.65 @ .707

9.77 @ .75710.97 @ .79512.09 @ .83313.29 @ .877

14.48 @ .90815.68 @ .94616.87 @ .98418.07 @ 1.02

19.19 @ 1.05

kg/cm2

00.701.402.10

2.813.514.214.92

5.626.327.037.73

8.449.149.8410.55

11.25

*Standard Nozzle Supplied with Chlorinator for Indicated Maximum Feed Rate. NOTE: GPM is U.S. Gallons. Metric is liters per sec. (l/sec.)

Page 30: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

30

Maximum Chlorine Feed Rate — 50 PPD (900 Grams/Hr.) See Note.

NOZZLE No. 13A No. 14A No. 15A No. 16AEJECTOR

BACKPRESSUREREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow Rate

PSIG

0102030

40506070

8090100110

120130140150

160

PSIG @ GPM

29 @ 2.465 @ 3.595 @ 4.1111 @ 4.6

125 @ 4.9138 @ 5.5150 @ 5.7161 @ 5.9

172 @ 6.1185 @ 6.2192 @ 6.4205 @ 6.5

215 @ 6.6224 @ 6.8236 @ 7.0248 @ 7.1

260 @ 7.2

PSIG @ GPM

10 @ 3.145 @ 4.263 @ 4.880 @ 5.4

94 @ 5.8108 @ 6.2120 @ 6.5132 @ 6.8

143 @ 7.2155 @ 7.4166 @ 7.6176 @ 7.9

190 @ 8.1203 @ 8.4214 @ 8.6 228 @ 8.8

241 @ 9.2

kg/cm2 @ l/sec.

2.04 @ .1514.57 @ .2216.68 @ .2597.80 @ .290

8.79 @ .3099.70 @ .35310.55 @ .36011.32 @ .372

12.09 @ .38513.00 @ .39113.50 @ .40414.41 @ .410

15.12 @ .41615.75 @ .42916.59 @ .44217.44 @ .448

18.28 @ .461

kg/cm2 @ l/sec.

1.69 @ .1963.16 @ .2654.43 @ .3035.62 @ .341

6.61 @ .3667.59 @ .3918.44 @ .4109.28 @ .429

10.05 @ .45410.90 @ .46711.67 @ .47912.37 @ .498

13.36 @ .51114.27 @ .53615.05 @ .543 16.03 @ .568

16.94 @ .593

PSIG @ GPM

13 @ 3.139 @ 4.853 @ 5.568 @ 6.1

82 @ 6.795 @ 7.4108 @ 7.9125 @ 8.4

142 @ 8.9158 @ 9.4174 @ 9.8190 @ 10.3

206 @ 10.7223 @ 11.2240 @ 11.5255 @ 11.7

271 @ 12.2

kg/cm2 @ l/sec.

0.84 @ .1962.74 @ .3033.73 @ .3474.79 @ .385

5.77 @ .4236.68 @ .4677.59 @ .4988.79 @ .530

9.98 @ .56211.11 @ .59312.23 @ .61813.36 @ .650

14.48 @ .67515.68 @ .70716.87 @ .72617.93 @ .738

19.05 @ .770

PSIG @ GPM

13 @ 3.731 @ 5.847 @ 6.959 @ 7.7

73 @ 8.689 @ 9.6106 @ 10.4123 @ 11.2

140 @ 12.1158 @ 12.7174 @ 13.3191 @ 13.9

207 @ 14.6224 @ 15.1241 @ 15.6257 @ 16.1

275 @ 16.6

kg/cm2 @ l/sec.

.914 @ .2332.18 @ .3663.30 @ .4354.15 @ .486

5.13 @ .5436.26 @ .6067.45 @ .6568.65 @ .707

9.84 @ .76311.11 @ .80112.23 @ .83913.43 @ .877

14.55 @ .92115.75 @ .95316.94 @ .98418.07 @ 1.02

19.33 @ 1.05

kg/cm2

00.701.402.10

2.813.514.214.92

5.626.327.037.73

8.449.149.8410.55

11.25

Maximum Chlorine Feed Rate — 100 PPD (2000 Grams/Hr.) See Note.

NOZZLE No. 13A No. 14A No. 15A No. 16AEJECTOR

BACKPRESSUREREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow RateREQUIRED Ejector Supply

Pressure and Water Flow Rate

PSIG

0102030

40506070

8090100110

120130140150

160

PSIG @ GPM

55 @ 3.6102 @ 4.4136 @ 5.0162 @ 5.4

181 @ 5.6198 @ 5.9216 @ 6.1230 @ 6.4

244 @ 6.6258 @ 6.7269 @ 7.0

————

PSIG @ GPM

48 @ 4.276 @ 5.3100 @ 6.0118 @ 6.4

136 @ 6.8153 @ 7.3168 @ 7.7185 @ 8.0

201 @ 8.3213 @ 8.5222 @ 8.8232 @ 9.0

247 @ 9.2260 @ 9.5273 @ 9.6 284 @ 9.8

295 @ 10.0

kg/cm2 @ l/sec.

3.87 @ .2277.17 @ .27810.55 @ .31512.73 @ .341

14.48 @ .35315.90 @ .36617.15 @ .38518.14 @ .404

19.76 @ .41620.67 @ .42921.58 @ .435

————

kg/cm2 @ l/sec.

3.37 @ .2655.34 @ .3347.03 @ .3798.30 @ .404

9.56 @ .42910.76 @ .46111.81 @ .48613.01 @ .505

14.13 @ .52414.98 @ .53615.61 @ .55516.31 @ .568

17.37 @ .58018.28 @ .59919.19 @ .618 19.97 @ .637

20.74 @ .662

PSIG @ GPM

31 @ 4.358 @ 5.675 @ 6.492 @ 7.1

108 @ 7.7122 @ 8.1136 @ 8.6151 @ 8.9

165 @ 9.3180 @ 9.8193 @ 10.1207 @ 10.4

221 @ 10.8236 @ 11.2250 @ 11.5265 @ 11.8

281 @ 12.2

kg/cm2 @ l/sec.

2.18 @ .2714.08 @ .3535.27 @ .4046.47 @ .448

7.59 @ .4868.58 @ .5119.56 @ .54310.62 @ .562

11.60 @ .58712.66 @ .61813.57 @ .63714.55 @ .656

15.54 @ .68116.59 @ .70617.58 @ .72618.63 @ .744

19.76 @ .770

PSIG @ GPM

22 @ 5.249 @ 7.569 @ 8.885 @ 9.7

101 @ 10.5116 @ 11.2128 @ 11.8139 @ 12.3

150 @ 12.8164 @ 13.4180 @ 14.0195 @ 14.5

212 @ 15.0227 @ 15.5245 @ 16.2261 @ 16.7

278 @ 17.2

kg/cm2 @ l/sec.

1.55 @ .3283.45 @ .4734.85 @ .5555.98 @ .612

7.10 @ .6628.16 @ .7079.00 @ .7449.77 @ .776

10.55 @ .80811.53 @ .84512.66 @ .88313.71 @ .915

14.91 @ .94615.96 @ .97817.23 @ 1.0218.35 @ 1.05

19.55 @ 1.09

kg/cm2

00.701.402.10

2.813.514.214.92

5.626.327.037.73

8.449.149.8410.55

11.25

*Standard Nozzle Supplied with Chlorinator for Indicated Maximum Feed Rate. NOTE: GPM is U.S. Gallons. Metric is liters per sec. (l/sec.)

Page 31: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

Application Bulletin No. 1009

REQUIRED Ejector Supply Pressure & Water Flow RateEJECTOR

BACKPRESSURE A-2920 EJECTOR - 0.563˝ (STD) A-2922 EJECTOR - 0.750˝

PSIG kg/cm2 PSIG @ GPM kg/cm2 @ 1/sec PSIG @ GPM kg/cm2 @ 1/sec

0 0.00 15 @ 34.5 1.05 @ 2.18 8 @ 46.0 0.57 @ 2.90

10 0.70 35 @ 43.7 2.43 @ 2.76 16 @ 65.6 1.13 @ 4.13

20 1.41 58 @ 52.9 4.04 @ 3.34 30 @ 84.0 2.10 @ 5.30

30 2.11 85 @ 62.1 5.98 @ 3.92 48 @ 98.9 3.40 @ 6.24

40 2.81 115 @ 71.3 8.08 @ 4.50 67 @ 112.7 4.69 @ 7.11

50 3.52 147 @ 82.8 10.35 @ 5.22 87 @ 126.5 6.14 @ 7.98

60 4.22 — — 108 @ 136.9 7.60 @ 8.63

70 4.92 — — 129 @ 149.5 9.05 @ 9.43

REGAL Series 2000 Gas Chlorinators

1000 LBS/24 HRS. (20kg/hr)

REQUIRED Ejector Supply Pressure & Water Flow RateEJECTOR

BACKPRESSURE A-2922 EJECTOR - 0.750˝ (STD) A-2920 EJECTOR - 0.563˝

PSIG kg/cm2 PSIG @ GPM kg/cm2 @ 1/sec PSIG @ GPM kg/cm2 @ 1/sec

0 0.00 41 @ 104.7 2.91 @ 6.60 41 @ 48.3 2.91 @ 3.05

10 0.70 48 @ 108.1 3.40 @ 6.82 78 @ 62.1 5.50 @ 3.92

20 1.41 58 @ 110.4 4.04 @ 6.96 102 @ 71.3 7.20 @ 4.50

30 2.11 68 @ 117.3 4.77 @ 7.40 124 @ 77.1 8.73 @ 4.86

40 2.81 81 @ 126.5 5.66 @ 7.98 146 @ 81.7 10.27 @ 5.15

50 3.52 97 @ 134.6 6.79 @ 8.49 — —

60 4.22 113 @ 141.5 7.92 @ 8.92 — —

70 4.92 130 @ 154.1 9.14 @ 9.72 — —

2000 LBS/24 HRS. (40kg/hr)

31

Page 32: REGAL Ejector Check Valve Assemblies - Chlorinators to prevent water from backing up into the various chlorinator or sulphonator system components (FLOODING) when ejector vacuum is

Copyright 2015 Chlorinators Incorporated Printed in U.S.A.Pub. No. 1015-1

1044 SE Dixie Cutoff Road, Stuart, Florida 34994 USA Phone: (772) 288-4854 • Fax: (772) 287-3238 • www.regalchlorinators.com • Email: [email protected]