2
OVERVIEW Work Origin and Original Cost March 2019 INTRODUCTION This overview document is intended to provide high level support and direction to better understand the importance of populating the Work Origin and Original Cost fields in the Road Assessment and Maintenance Management (RAMM) system. Any relevant current industry guidance and case studies have been referenced, where they provide more detailed assistance. WHAT ARE WORK ORIGIN AND ORIGINAL COST? Work Origin is recorded to associate carriageway surface and pavement layer inventory records with the National Land Transport Programme (NLTP) Work Categories or non-subsidised work activities. This will help to differentiate those surfacings and pavement layers which were rehabilitation, resurfacing, minor improvements, capital works, vested assets or unsubsidised works etc. Original Cost is the total of costs for sealed road resurfacing and rehabilitation activities charged to Work Categories 212 and 214. WHY ARE THEY IMPORTANT? At a national level, recording the Work Origin and Original Cost enables robust comparative reporting of the One Network Road Classification (ONRC) Cost Efficiency performance measures 1 - 3. At a local level, they allow for better measuring and reporting of genuine renewal activity, asset performance analysis and forward works programme development. HOW TO RECORD WORK ORIGIN AND ORIGINAL COST IN RAMM All new carriageway surface and pavement layer records should have a Work Origin recorded. Original Costs are only required for works associated with sealed road resurfacing and rehabilitation, Work Categories 212 and 214. The total Original Cost should only be recorded in the carriageway surface record. RAMM is pre-loaded with a standard set of Work Origin codes based on NLTP Activity Classes and Work Categories, plus two other codes used to associate carriageway surface and pavement layer records with unsubsidised activities or vested assets, e.g. subdivision development etc. Recording the correct Work Category is the critical element for subsidised work. THE STANDARD WORK CATEGORIES IN RAMM ARE NOT TO BE CUSTOMISED. This will create problems in reporting the correct data. Guidance on how to set these up in your RAMM database can be found at WORKING WITH WORK ORIGIN within the RAMM on line help. Work Origin and Original Cost are recorded for resurfacing and rehabilitation activities to enable better comparative reporting of cost efficiency and genuine renewal activity KEY POINTS Work Origin and Original Cost: Work Origin and Original Costs are recorded for resurfacing and rehabilitation activities to enable better reporting of cost efficiency and genuine renewal activity Work Origin associates the carriageway surface or pavement layer records with the appropriate NLTP Work Category or two other work codes for non-subsidised work Original Cost should be recorded for all works delivered under Work Categories 212 and 214 All Original Costs shall only be recorded against the carriageway surface record Both Work Origin and Original Cost are needed for reporting the ONRC Cost Efficiency 1, 2 and 3 Performance Measures Work Origin enables better reporting of genuine renewal activity, analysis of asset performance and forward works programme development Recording the correct Work Category is the key element for subsidised work NLTP Work Categories are not to be customised

REG practice overview – Work origin and original cost · 2019-03-18 · OVERVIEW Work Origin and Original Cost March 2019 INTRODUCTION This overview document is intended to provide

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: REG practice overview – Work origin and original cost · 2019-03-18 · OVERVIEW Work Origin and Original Cost March 2019 INTRODUCTION This overview document is intended to provide

OVERVIEW

Work Origin and Original CostMarch 2019

KEWCo

INTRODUCTION This overview document is intended to provide high level support and direction to better understand the importance of populating the Work Origin and Original Cost fields in the Road Assessment and Maintenance Management (RAMM) system.

Any relevant current industry guidance and case studies have been referenced, where they provide more detailed assistance.

WHAT ARE WORK ORIGIN AND ORIGINAL COST? Work Origin is recorded to associate carriageway surface and pavement layer inventory records with the National Land Transport Programme (NLTP) Work Categories or non-subsidised work activities. This will help to differentiate those surfacings and pavement layers which were rehabilitation, resurfacing, minor improvements, capital works, vested assets or unsubsidised works etc.

Original Cost is the total of costs for sealed road resurfacing and rehabilitation activities charged to Work Categories 212 and 214.

WHY ARE THEY IMPORTANT? At a national level, recording the Work Origin and Original Cost enables robust comparative reporting of the One Network Road Classification (ONRC) Cost Efficiency performance measures 1 - 3.

At a local level, they allow for better measuring and reporting of genuine renewal activity, asset performance analysis and forward works programme development.

HOW TO RECORD WORK ORIGIN AND ORIGINAL COST IN RAMM All new carriageway surface and pavement layer records should have a Work Origin recorded. Original Costs are only required for works associated with sealed road resurfacing and rehabilitation, Work Categories 212 and 214. The total Original Cost should only be recorded in the carriageway surface record.

RAMM is pre-loaded with a standard set of Work Origin codes based on NLTP Activity Classes and Work Categories, plus two other codes used to associate carriageway surface and pavement layer records with unsubsidised activities or vested assets, e.g. subdivision development etc.

Recording the correct Work Category is the critical element for subsidised work. THE STANDARD WORK CATEGORIES IN RAMM ARE

NOT TO BE CUSTOMISED. This will create problems in reporting the correct data.

Guidance on how to set these up in your RAMM database can be found at WORKING WITH WORK ORIGIN within the RAMM on line help.

Wo areanenrepan

rk Origin and Original Cost recorded for resurfacing

d rehabilitation activities to able better comparative orting of cost efficiency

d genuine renewal activity

Y POINTSork Origin and Original st: Work Origin and Original Costsare recorded for resurfacing andrehabilitation activities to enablebetter reporting of cost efficiencyand genuine renewal activity

Work Origin associates thecarriageway surface orpavement layer records with theappropriate NLTP WorkCategory or two other workcodes for non-subsidised work

Original Cost should be recordedfor all works delivered underWork Categories 212 and 214

All Original Costs shall only berecorded against thecarriageway surface record

Both Work Origin and OriginalCost are needed for reportingthe ONRC Cost Efficiency 1, 2and 3 Performance Measures

Work Origin enables betterreporting of genuine renewalactivity, analysis of assetperformance and forward worksprogramme development

Recording the correct WorkCategory is the key element forsubsidised work

NLTP Work Categories are notto be customised

Page 2: REG practice overview – Work origin and original cost · 2019-03-18 · OVERVIEW Work Origin and Original Cost March 2019 INTRODUCTION This overview document is intended to provide

THE ROAD EFF

Work Origin The Work Origin field is currently only available in the Carriageway Surface and Pavement Layer tables in RAMM. This functionality is expected to become available in other asset inventory tables.

A WORK ORIGIN IS A COMBINATION OF ACTIVITY CLASS AND WORK CATEGORY.

The standard NLTP Work Categories for road maintenance, renewals and improvements are shown in the adjacent table. There is a different Activity Class code for Local Authority and state highway networks.

Two further standard codes are available to be used to associate asset records with non-subsidised activities, e.g. new vested assets associated with private development or unsubsidised works by the Council.

Original CostThe total amount of Original Cost recorded against the carriageway surfacing record should include costs for the surfacing and rehabilitation as described below.

Costs for surfacing (Work Category 212) should include:

Payments to the contractor to construct surfacing (including any preparatory milling)

Amendments to service covers Reinstatement of road markings and raised pavement

markers Cost of design and supervision of work charged to

Work Category 212 – Sealed Road Resurfacing

Costs for rehabilitation (Work Category 214) should include:

Payments to the contractor to construct the renewed section of road including drainage works (where funded from pavement rehabilitation)

Pavement preparation and construction amendments to services and/or covers

Surfacing Reinstatement of road markings and raised pavement

markers Cost of design and supervision of works charged to

Work Category 214 – Sealed Road Rehabilitation

Rehabilitation work can be extensive, and can include significant work on formation (earthworks) and external service relocations. These costs need to be included where they have been charged to the sealed road rehabilitation Work Category, to understand cost drivers in this work.

All surfacing and rehabilitation costs shall be attributed to the surfacing record (first coat seal or AC surface applied as part of the project). The reason for this is that attributing costs to the constituent pavement layer components is seen as very complex. It is this “Original Cost” and “Work Origin” which will be used in the ONRC Performance Measures Reporting Tool (PMRT).

Work Category Code

Work Category Description

111 Sealed pavement maintenance

112 Unsealed pavement maintenance

140 Minor events

141 Emergency works

211 Unsealed road metalling

212 Sealed road resurfacing

214 Sealed road pavement rehabilitation

323 New roads

324 Road improvements

325 Seal extension

341 Minor improvements

- Vested assets

- Unsubsidised

REFEREN

ONRC Perfor

RAMM Worki

Surfacing Da

NZTA Plannin

REG is a collLocal Govern Agency.

For more info

Road EfficieRoadEfficienc

CONCLUWork Origin acomparative reporting of g

Work Origin iactivities. Ori be recorded against the associated surfacing record.

CES

mance Measure Reporting Tool help and support

ng with Work Origin

ta Overview document

g & Investment Knowledge Base

ICIENCY GROUP

aborative project between ment and the NZ Transport

rmation, please contact:

ncy Group [email protected]

SION nd Original Cost are recorded for resurfacing and rehabilitation activities to enable better

reporting of the ONRC Cost Efficiency performance measures. This will in turn help with better enuine renewal activity, asset performance analysis and forward works programming.

s defined by the standard NLTP Work Categories plus two further codes for non-subsidised ginal Costs for surfacing and rehabilitation works charged to Work Categories 212 and 214 are to

Version 2.0

Published 19-03-19