Upload
others
View
10
Download
0
Embed Size (px)
Citation preview
Ref: SSR/TOR/ADS/2019 Date: 15.02.2019
To
The Director, Government of India,
Ministry of Environment, Forests & Climate Change Indira Paryavaran Bhavan, Jor Bagh Road New Delhi - 110 003
Sub: Submission of ADS Reply - Quartz & Feldspar Mine of Sri S. Ravi
Located at Bandivankacharla Village, Kulkcherla Taluk in Rangareddy District in Telangana State. (ML Area- 56.68 Ha and
the production Capacity of 3,00,000 Tonnes /Annum (TPA) Quartz and Feldspar With Total Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA + Waste : 50432 TPA) –
VIOLATION CASE- Reg.
Ref: 1). Online File No: IA/TG/MIN/73867/2018 Dt: 31.03.2018
2). 17th EAC Meeting Held on 31-01-2019
3). ADS Raised by MoEF & CC 07.02.2019
Dear Sir,
We thank you for giving us opportunity to present our case in front of EAC Vide Reference (2).
As per the ADS raised, we are herewith enclosing the following documents raised for your consideration.
a) Revised Form I duly filled-in b) Revised Pre - Feasibility Report
c) Authenticated Production details
Thanking you,
Yours faithfully,
Sri S Ravi Lessee
Encl.: as above
REVISED FORM – I
&
PRE FEASIBILITY REPORT
Of
Quartz & Feldspar (Area: 56.68 Ha)
Bandivankacharla Village, Kulkcherla Taluk,
Rangareddy District, Telangana State
For
Production of 3,00,000 Tonnes /Annum (TPA) Quartz and Feldspar With Total Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA + Waste : 50,432 TPA)
Of
Sri S. Ravi
February, 2019
Prepared By
< B.S. ENVI-TECH (P) LTD.,
Secunderabad – 500 017
NABET Accreditation No: NABET/EIA/1619/SA064
FORM 1
(As Per New Notification of Mo.E.F dated 1-12-2009 vide SO 3067 (E))
BASIC INFORMATION
S.
No
Item Details
1 Name of the Project/s Quartz & Feldspar mine of Sri S. Ravi
2 S. No. in the schedule 1(a)
3 Proposed capacity/ area/ length/
tonnage to be handled/ command area/ lease area/ number of wells to be drilled
Production of 3,00,000 Tonnes
/Annum (TPA) Quartz and Feldspar With Total Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA +
Waste : 50432 TPA)
Mine lease area: 56.68 Ha
4 New/ expansion/ modernization Operating Mine (Mining operations stopped)
5 Existing capacity/ Area etc. Production of 3,00,000 Tonnes /Annum (TPA) Quartz and Feldspar
With Total Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA +
Waste : 50432 TPA) Mine lease area: 56.68 Ha
6 Category of Project i.e ‘A’ or ‘B’ A
7 Does it attract the general condition? If
yes please specify.
No
8 Does it attract the specific condition? If
yes please specify.
No
9 Location
Plot/ Survey/ Khasra No Survey No: 415p
Village Banivenkacherla
Tehsil Kulkacherla
District Rangareddy
State Telangana.
10 Nearest railway station/ airport along with distance in Kms.
Nearest railway station: Mailaram – 25.0km - N
Rajiv Gandhi International Airport (Shamshabad) Hyderabad – 66.0 km –
ENE
11 Nearest town, city, district head quarters along with distance in kms.
Mahbubnagar – 37.7km - SE
12 Village panchayaths, Zillaparishad, Municipal Corporation, Local body
(Complete postal addresses with telephone nos to be given)
Banivenkacherla Village, Kulkacherla Mandal, Rangareddy Dist., Telangana
State.
13 Name of the applicant Sri S. Ravi
14 Registered address Plot No:6, Road No 51 Silent Lake Valley, Jubilee Hills,
Hyderabad
15 Address for correspondence
Name of the Applicant Sri S. Ravi
Designation (Owner /Partner/ CEO) Lessee
Address Plot No:6, Road No 51
Silent Lake Valley, Jubilee Hills, Hyderabad.
Pincode -
E- mail [email protected]
Telephone no. +9140 23555183
Fax no. +9140 23555182
16 Details of Alternative sites examined, if any location of these sites should be
shown on a topo sheet.
No
17 Interlinked projects None
18 Whether separate application of interlinked project has been submitted?
Not Applicable
19 If yes, date of submission Not Applicable
20 If no, reason Not Applicable
21 Whether the proposal involves
approval/ clearance under: if yes, details of the same and their status to
be given. (a) The Forest (Conservation)Act, 1980
(b) The Wild Life (Protection)Act, 1972 (c) The CRZ Notification, 1991
Not Applicable
Not Applicable Not Applicable
22 Whether there is any Government Order/ Policy relevant/ relating to the site?
None
23 Forest land involved (hectares) None
24 Whether there is any litigation pending
against the project and/or land in which the project is propose to be set up?
(a) Name of the court (b) Case No
(c) Orders/ directions of the court, if any and its relevance with the proposed project.
None
(I) ACTIVITY
1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No. Information/Checklist confirmation
Yes/No Details thereof (with approximate quantities /rates, wherever
possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including
increase in intensity of land use (with respect to local land
use plan)
Yes Total area of 56.68 Ha is Govt. Revenue land.
At the conceptual stage, the land use is detailed in below table
S. No
Land Particulars
Present Use
Conceptual Period Area
In Ha.
1 Area under Excavation
0.5200 21.072
2 Worked out pit
Nil (14.572)*
3 Storage of Top
Soil
Nil 0.0800
4 Overburden Dump
0.2000 6.4520
5 Mineral storage
0.1520 0.1520
6 Infrastructure (Workshop, Administrative Buildings)
0.1000 0.1000
7 Roads 0.2540 1.0000
8 Greenbelt Nil 3.5000
9 Env. Protective measures
Nil 1.0000
10 Mineral
Separation plant
0.4047 -
11 Area
Cultivated
7.0172 -
12 Dump Area Plantation
Nil 3.0000
13 Others (Unutilized Area)
48.0321 20.2240
Total 56.6800 56.6800
1.2 Clearance of existing land,
vegetation and buildings?
Yes Small bushes will be cleared for the
proposed mining activity.
1.3 Creation of new land uses?
Yes Open barren land will be converted
into mining activities.
1.4 Pre-construction investigations
e.g. bore houses, soil testing?
Yes Exploration work is already carried
out. Further exploration is proposed for the deposits of Quartz deposit and minerals.
1.5 Construction works?
Yes Site office, rest shelter, first aid room will be constructed.
1.6 Demolition works? No No demolition works are involved.
1.7 Temporary sites used for construction works or housing
No No Construction works
of construction workers?
1.8 Above ground buildings, structures or earthworks including linear structures, cut
and fill or excavations.
Yes i. Above ground structures : Site office, rest shelter, first aid room ii. Earthworks:
Excavation operations
1.9 Underground works including
mining or tunneling?
No Opencast mining is adopted, hence no
underground or tunneling works are involved
1.10 Reclamation works?
Yes Entire broken up area will be backfilled or reclaimed
1.11 Dredging? No No dredging is involved
1.12 Offshore structures? No Mine site is far from the sea coast.
1.13 Production and manufacturing
processes?
Yes Quartz : 300000 TPA
Crushing and Screening
1.14 Facilities for storage of goods or
materials?
Yes Storage of mineral and subgrade
mineral will be stored in earmark area
1.15 Facilities for treatment or disposal of solid waste or liquid effluents?
Yes Solid waste generation will be disposed in the dumping area. Liquid effluent will not generated
during mining operation.
1.16 Facilities for long term housing
of operational workers?
No No long term housing facilities
because of all the workers will be hired from the local villages only.
1.17 New road, rail or sea traffic during construction or operation?
Yes Increase the road traffic is minimal during operation phase.
1.18 New road, rail, air waterborne or other transport
infrastructure including new or altered routes and stations,
ports, airports etc?
No There is no proposed for construction of new road, other transport
infrastructures. Existing road facilities will be utilized.
1.19 Closure or diversion of existing transport routes or
infrastructure leading to changes in traffic movements?
No No diversion of infrastructure.
1.20 New or diverted transmission lines or pipelines?
No There will be no new or diverted transmission lines or pipelines
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology
of watercourses or aquifers?
No There will be no impoundment, damming, culverting, realignment or other changes in the hydrology of
watercourses or aquifers
1.22 Stream crossings? No No streams crossing
1.23 Abstraction or transfers of water from ground or surface
waters?
Yes Ground water will be used for drinking purpose & dust suppression.
1.24 Changes in water bodies or the
land surface affecting drainage or run-off?
Yes Mining operation and exaction can
affect the surface pattern there by changing the course of drainage run-
off.
1.25 Transport of personnel or materials for construction, operation or decommissioning?
No The personnel and materials for construction will be hired from nearby villages.
1.26 Long-term dismantling or decommissioning or restoration
works?
No There will be no long-term dismantling or decommissioning
works.
1.27 Ongoing activity during
decommissioning which could have an impact on the environment?
No Not applicable.
1.28 Influx of people to an area in either temporarily or
permanently?
No Local people are employed for mining activities.
1.29 Introduction of alien species? No The local/ indigenous species will be
planted within the site area.
1.30 Loss of native species or
genetic diversity?
No Only local native species will be
planted which will increase the Biodiversity of the area. There will be no loss of native or genetic diversity.
1.31 Any other actions? No None
2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-
renewable or in short supply):
S.No. Information/Checklist
confirmation
Yes/No Details thereof (with
approximate quantities /rates, wherever possible) with source
of information data
2.1 Land especially undeveloped or agricultural land (ha)
No The entire land is Government Revenue land.
Mine lease area:56.68Ha
2.2 Water (expected source & competing users) unit: KLD
Yes 18 m3/day water will be required for domestic purpose, green belt development and dust
suppression. Source of water will be from Ground Water/Local
Purchase
2.3 Minerals (MT) Yes Mineral reserves - 46,29,946 tons.
2.4 Construction material – stone, aggregates, sand/soil (expected source – MT)
No Not Applicable
2.5 Forests and timber (source – MT) No Forests and timber are not required for this project as proposed project is for extraction
of stone (minor quarry) which will not involve use of forest or timber.
2.6 Energy including electricity and fuels (source, competing users)
Yes Electrical is used for lighting purpose
Unit: fuel (MT), energy (MW) Diesel is used for compressors,
tippers etc.
2.7 Any other natural resources (use appropriate standard units)
No None
3. Use, storage, transport, handling or production of substancesor materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.
S. No.
Information/Checklist confirmation
Yes/No Details thereof (with approximate quantities/ rates,
wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or
the environment (flora, fauna, and water supplies)
No No hazardous substance or materials will be utilized for mining operations.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases)
No No source of occurrence of disease or effect on disease vectors is envisaged through the project.
3.3 Affect the welfare of people e.g. by changing living conditions?
Yes Socioeconomic Development and living conditions will improve after
the start of mining activities.
3.4 Vulnerable groups of people who
could be affected by the project e.g. hospital patients, children, the elderly etc.,
No None
3.5 Any other causes No Not Applicable
4. Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No. Information/Checklist confirmation
Yes/No Details thereof (with approximate quantities/ rates,
wherever possible) with source of
information data
4.1 Spoil, overburden or quarry wastes
Yes Waste generation (O.B. consisting of soil and weathered rock) from
the mine for the life of mine is 6,76,939 tonnes (4,230 t/month) Waste will be disposed to
temporary dump initially and Backfilling at later stage.
4.2 Municipal waste (domestic and or commercial wastes)
Yes Domestic waste (solid waste, food waste and other PVC packets) will be generated, which shall be
disposed into waste bins and disposed.
4.3 Hazardous wastes (as per Hazardous Waste management Rules)
Yes The spent oil from mine machinery and transport vehicles.
4.4 Other industrial process wastes No No other industrial process wastes
will be generated during mining activities.
4.5 Surplus product No No surplus product will be
produced.
4.6 Sewage sludge or other sludge
from effluent treatment
No Domestic sewage generated will be
treated in the septic tanks followed by disposal in soak pits. No effluent
will be generated from the mining operations.
4.7 Construction or demolition
wastes
No Neither any construction of
permanent structure nor any demolition is contemplated.
4.8 Redundant machinery or equipment
Yes Redundancy of machinery or equipment, if any, will be disposed
through authorized recyclers/agencies.
4.9 Contaminated soils or other materials
No No contaminated soil or other materials are envisaged.
4.10 Agricultural wastes No No agriculture waste will be
produced. No agriculture waste will be produced.
4.11 Other solid wastes No Not Applicable
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)
S.No. Information/Checklist confirmation
Yes/No Details thereof (with approximate quantities/ rates,
wherever possible) with source of information data
5.1 Emissions from combustion of
fossil fuels from stationary or mobile sources
Yes Burning of Diesel trucks and
compressors will generate gaseous pollutants.
5.2 Emissions from production processes
Yes Fugitive Dust is the main pollutant, which will be generated
mainly from mining operations which will be controlled by water sprinkling
5.3 Emissions from materials handling including storage or
transport
Yes There will be fugitive emissions generated during material
handling, transportation, loading and unloading etc.
5.4 Emissions from construction activities including plant and equipment
Yes Temporary emission (fugitive dust) during construction.
5.5 Dust or odours from handling of materials including construction
materials, sewage and waste
Yes There will be fugitive emissions generated during material
handling, transportation, loading and unloading
5.6 Emissions from incineration of No Incineration of waste is not
waste envisaged.
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris)
No Not involved.
5.8 Emissions from any other sources No Not Applicable
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No. Information/Checklist confirmation
Yes/ No
Details thereof (with approximate quantities/ rates, wherever possible) with source
of information data
6.1 From operation of equipment
e.g. engines, ventilation plant, crushers
Yes From operation of compressor and
jack hammer. Source emission of 90 dB(A)
expected from above
6.2 From industrial or similar processes
No The present activity is open cast mining hence noise levels from of
industrial activities is nil
6.3 From construction or demolition No No Construction or demolition is
involved.
6.4 From blasting or piling Yes Noise and vibration due to blasting
6.5 From construction or operational traffic
Yes Operational traffic
6.6 From lighting or cooling systems No Not envisaged
6.7 From any other sources No No other source except the
mentioned above.
7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No. Information/Checklist
confirmation
Yes/No
Details thereof (with approximate quantities/rates, wherever possible) with source of
information data
7.1 From handling, storage, use or
spillage of hazardous materials
Yes Strom water runoff from stockpiles
and dump yards carrying silts may pollute the water bodies.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place
of discharge)
No Not Applicable
7.3 By deposition of pollutants
emitted to air into the land or into water
No Not Applicable
7.4 From any other sources No None
7.5 Is there a risk of long term build
up of pollutants in the environment from these sources?
No There is no risk long term buildup
of pollutants in the environment from the mining operations.
8. Risk of accidents during construction or operation of the Project, which
could affect human health or the environment
S.No. Information/Checklist confirmation
Yes/No Details thereof (with approximate quantities/ rates,
wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use
or production of hazardous substances
Yes Blasting operation
8.2 From any other causes No None
8.3 Could the project be affected by natural disasters causing
environmental damage (e.g. floods, earthquakes, landslides,
cloudburst etc)?
No Zone-II There is no history of flood,
earthquake, cloud burst and landslide reported so far.
9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No. Information/Checklist confirmation
Yes/No Details thereof (with approximate quantities/ rates,
wherever possible) with source of information data
9.1 Lead to development of supporting facilities, ancillary development or development
stimulated by the project which could have impact on the
environment e.g.: • Supporting infrastructure
(roads, power supply, waste or waste water treatment, etc.)
• housing development • extractive industries • supply industries
• other
Yes Improve socio-economic status of villages around the mine
area
Benefit local people due to
employment round the year
Improvements in the
Educational facilities
Provisions of Health facilities
9.2 Lead to after-use of the site,
which could have an impact on the environment
Yes Greenbelt will be developed
9.3 Set a precedent for later developments
Yes Community development activities
9.4 Have cumulative effects due to
proximity to other existing or planned projects with similar
effects
No Not Applicable
(II) ENVIRONMENTAL SENSITIVITY
S.No. Areas Name/
Identity
Aerial distance
(within 15 km.) in KmProposed project location boundary
1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value
Gauraram RF Bompally RF Mothkur RF Mujaithapur RF Kulkacherla RF
Tirumalapur RF
7.6 km – WNW 7.6 km – NNE 6.1 km – ENE 6.2 km – E 5.8 km – E 7.0 km - E
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains,
forests
(Near Doma Village ) Vagu (Near Ainapur
Village ) Cheruvu
– 3.6 km – N – 0.2 km – N
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration
No None
4 Inland, coastal, marine or underground waters
No None
5 State, National boundaries No Telangana – Karnataka –
33.0 km - W
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas
National Highway (NH-44) connecting Secunderabad – Tandur The State Highway (SH-4) connecting Pargi - Kodangal,
35.59 km – E 12.7 km - NNE
7 Defense installations No None
8 Densely populated or built-up area No Mahbubnagar
37.7km - SE
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities)
No None
10 Areas containing important, high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, quarryrals)
No None
11 Areas already subjected to pollution or environmental damage (those where existing legal environmental standards are exceeded)
No None
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)
Zone-II There is no history of flood, earthquake, cloud burst and landslide reported so far.
None
“I hereby give under taking that the data and information given in the
application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is
found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
Date: 15.02.2019 Place: Hyderabad
Signature of the Applicant
(Project proponent/ Authorized signatory)
Name Sri S. Ravi
Designation Lessee
Address Plot No: 6, Road No 51
Silent Lake Valley, Jubilee Hills, Hyderabad
REVISED
PRE-FEASIBILITY REPORT
Of
Quartz & Feldspar Mine (ML Area: 56.68 Ha)
Bandivankacharla Village, Kulkcherla Taluk, Rangareddy District, Telangana State
For Production of 3,00,000 Tonnes /Annum (TPA) of
Quartz and Feldspar With Total Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA + Waste : 50,432 TPA)
Of
Sri S. Ravi
February, 2019
1
Table of Contents
1. Executive Summary
2. Introduction Of The Project/ Background Information
3. Project Description
4. Site Analysis
5. Planning Brief
6. Proposed infrastructure
7. Rehabilitation and resettlement (R & R) Plan
8. Project schedule & Cost Estimates
9. Analysis of proposal (Final Recommendations)
Figure
Table-1 Salient features of project
Figure
Fig-1 Location Map
Fig-2 Key Map
Fig-3 Topographical Map
Fig-4 Surface Plan
Annexures
Annexure –1 Industries and Commerce (Mines-I) Department letter
Annexure – 2 lease Transfer proceeding Letter
2
1.0 EXECUTIVE SUMMARY
The Mining Lease was granted for Quartz and Feldspar Minerals over an
extent of 56.68 Ha in Sy. No.415 of Bandivankacharla Village, Kulkcherla
Taluk, Rangareddy District, Telangana State (formerly Andhra Pradesh) in
favour of Kum. G.L. Nanditha for a period of 20 years and the mining lease
is valid upto 01.12.2022.
Subsequently Kum. G.L. Nanditha has applied for transfer of Mining Lease
in favour of Sri S. Ravi
The Director of Mines & Geology has recommended for transfer of Mining
Lease by Kum. G.L. Nanditha for Quartz & Feldspar Mines and transferred
the lease in favour of Sri S. Ravi for Quartz and Feldspar Minerals over an
extent of 56.68 Ha in Sy. No.415 of Bandivankacharla Village, Kulkcherla
Taluk, Rangareddy District, Telangana State (formerly Andhra Pradesh) vide
G.O.Ms. No.292 dated 31.10.2008 which is valid upto 02.12.2022.
Sri S. Ravi intends to produce 3,00,000 Tonnes /Annum (TPA) of Quartz
and Feldspar with Total Excavation of 3,50,432 TPA (Quartz and Feldspar:
3,00,000 TPA + Waste : 50,432 TPA) from the lease area and applied to
Ministry of Environment and Forests for Terms of Reference. Ministry has
provided TOR to carry out an Environmental Study vide their MOEF Lr. No.
J-11015/05/2010-IA.II [M] dated 09th March 2010.
The Public Hearing was conducted on 04.01.2013. The Final EIA was
submitted to the Ministry on 10.04.2013.
The Project was considered during 11th Meeting of the Reconstituted Expert
Appraisal Committee for Environmental Appraisal of Mining Projects (Non-
Coal) of the Ministry of Environment and Forests on 25th September 2013.
The Committee noted that the mine was operating from 2010 to 2012
without obtaining Environmental Clearance and Project Proponent has
violated the provisions of Environmental Protection Act 1986 and deferred
the Proposal and asked to submit the following information vide letter no. J-
11015/05/2010-IA.II [M] Dt. 31.12.2013.
1. The details of preventive measures to be undertaken for occupational
health of the workers
3
2. Site specific conservation plan for the Scheduled-I species reported in
the study area
3. Copy of Approved mining scheme for the period 2013-2018.
Further MOEFCC has issued a letter no. J-11015/05/2010-IA.II [M] Dt.
31.12.2013. stating that (1) The matter relating to violation has been put to
the Board of Directors of the Company or to the Managing Committee, for
consideration of your environment related policy/plan of action and a
written commitment in the form of a formal resolution is submitted to MoEF
to ensure that violations of the Environment (Protection) Act will not be
repeated (2) The State Government has initiated credible action on the
violation against you under the Environment (Protection) act 1986 and
evidence provided to MoEF of the action taken (3) You close down your
mining operations with immediate effect. And also stated that While
communications against (1) & (2) have been issued separately, these
directions are being issued to ensure (3); and instructed Sri S. Ravi to stop
the mining operations.
Against above, Sri S. Ravi has
1. Submitted written commitment that violations of the Environment
(Protection) Act will not be repeated as Affidavit on 100/- Rupees bond
paper
2. A letter was submitted to principle secretary, Govt. of Telangana for
initiation credible action on 25.02.2015. The process was initiated and
the case was filed in the court of Judicial First Class Magistrate, Pargi.
3. Inspection report from Department of Mines and Geology vide letter
no. 3540/M/2008 Dt. 18.06.2015 states that mining operation was
stopped.
Sri S. Ravi has submitted the reply to the above points in hard copy to
MoEF & CC, Non- Coal Mining Committee on 17.01.2017. Against this
MOEF & CC vide letter no. J-11015/05/2010-IA.II [M] dated 17.07.2017
instructed Sri S. Ravi to submit online the proposal afresh as violation case
submitting the following information.
1. Certificate stating that mining activity of the said mine has
been stopped (with date) and CTO/occupancy Certificate has been
revoked, duly certified by the State Pollution Control Board
4
Submission of Sri S. Ravi: Inspection report from Department of
Mines and geology vide letter no. 3540/M/2008 Dt. 18.06.2015 states
that mining operation was stopped.
2. Detailed statement of Past production since inception/after
1994 to till-date, duly certified by the Department of Mines and
Geology
Submission of Sri S. Ravi: S. Ravi Approached DMG for the same
3. Details of violation proceedings, if any, already initiated or
completed by the State Government in the instant proposal with
supporting documents
Submission of Sri S. Ravi: A letter was submitted to Principle
Secretary, Govt. of Telangana for initiation credible action on
25.02.2015. The process was initiated and the case was filed in the
court of Judicial First Class Magistrate, Pargi.
4. Details of earlier applications made to MoEF & CC, if any, for
grant of EC.
Submission of Sri S. Ravi: File no. J-11015/05/2010-IA.II [M]
Since Sri S. Ravi has already submitted the documents, which are at an
advanced stage of consideration, at this stage when MOEF instructed to
submit afresh on 17.07.2017 letter, Sri S. Ravi has approached the Hon’ble
High Court of Judicature at Hyderabad. Sri S. Ravi has obtained court order
dated 22.09.2017 directed Ministry of Environment, Forests and Climate
Change to receive our application without prejudice to their contention that,
in standing order dated 14.03.2017. Later the proposal was submitted on
16.11.2017 under violation vide Proposal No. IA/TG/MIN/68696/2017.
Since the proposal under violation was submitted on 16.11.2017, we have
resubmitted the proposal under violation in compliance with MoEF & CC
Office Memorandum Dated 16th March, 2018 vide proposal no
IA/TG/MIN/73867/2018 dated 31.03.2018. EAC during the appraisal and
vide ADS dated 07.02.2019 has instructed Project Proponent to submit the
Revised Form – I incorporating the correct name of the lessee as Sri S. Ravi
along with inclusion of total material handling in the proposal. The subject
report is revised PFR prepared incorporating the observations of EAC.
5
The details of the mining lease are given below:
Project Quartz & Feldspar mine
Extent of Lease Area Mine lease area : 56.68 Ha
Location of the Mine Sy. No. 415p, Bandivankacharla Village, Kulkcherla Taluk, Rangareddy District,
Telangana State.
Registered Office Sri Seelam Ravi Chandra
Plot No:6, Road No 51, Silent Lake Valley, Jubilee Hills,, Hyderabad 040 23555183
Designation (Owner /Partner/ CEO
Sri S. Ravi Lessee
Period of mining lease 20 years
Present land use Total mining lease area is Govt. revenue land (56.68Ha). The ML Area is as saddle shaped hillock with
radial Slopes. The highest contour of 160m RL is traversing in central portion of the lease area and lowest contour level is 103 RL is at North-Eastern
of lease area. The general strike direction is almost North South and dipping easterly with
almost vertical dip.
Type of Activity Open Cast Mechanized mining
Mineable reserves & life of mine
46,29,946 tons Life of mine would be 16 years
Waste generation Waste generation (O.B. consisting of soil and weathered rock) from the mine for the life of mine
is 676939 tonnes (4230 t/month) Waste will be disposed to temporary dump initially and Backfilling at later stage
Conceptual landuse Conceptually, about 21.072ha will be mined out area. 14.572 Ha will be backfilled.
Manpower Requirement About 33 persons will be employed in the mine.
Water requirement Water requirement will be 18 m3/day and the same will be sourced from Ground Water
Project Cost Rs 150 Lakhs
6
2. INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION:
(i) Identification of project and project proponent. In case of mining
project, a copy of mining lease / letter of intent should be given.
Sri S. Ravi, Lessee of Quartz & Feldspar mine over an extent of 56.68
Hectares Sy. No.415/P of Bandivankacharla Village, Kulkcherla Taluk,
Rangareddy District, Telangana State.
Earlier the lease was granted in favour of Kum. G.L. Nanditha for a period
of 20 years by Industries and Commerce (Mines-I) Department vide G.O.Ms.
No.292 dated 31.10.2008 which is valid upto 02.12.2022 (Enclosed as
Annexure - 1).
Subsequently, the lease was transferred in favour of Sri S. Ravi from Kum.
G.L. Nanditha vide proceedings No. 3540/M/2008 Dated 21.01.2009
(Enclosed as Annexure - 2).
Sri S. Ravi intends to produce 3,00,000 Tonnes /Annum (TPA) of Quartz
and Feldspar With Total Excavation of 3,50,432 TPA (Quartz and Feldspar:
3,00,000 TPA + Waste : 50,432 TPA). from the lease area and applied to
Ministry of Environment and Forests for Terms of Reference. Ministry has
provided TOR to carry out an Environmental Study vide their MOEF Lr. No.
J-11015/05/2010-IA.II [M] dated 09th March 2010.
The Public Hearing was conducted on 04.01.2013. The Final EIA was
submitted to the Ministry on 10.04.2013.
The Project was considered during 11th Meeting of the Reconstituted Expert
Appraisal Committee for Environmental Appraisal of Mining Projects (Non-
Coal) of the Ministry of Environment and Forests on 25th September 2013.
The Committee noted that the mine was operating from 2010 to 2012
without obtaining Environmental Clearance and Project Proponent has
violated the provisions of Environmental Protection Act 1986 and deferred
the Proposal and asked to submit the following information vide letter no. J-
11015/05/2010-IA.II [M] Dt. 31.12.2013.
1. The details of preventive measures to be undertaken for occupational
health of the workers
7
2. Site specific conservation plan for the Scheduled-I species reported in
the study area
3. Copy of Approved mining scheme for the period 2013-2018.
Further, MOEFCC has issued a letter no. J-11015/05/2010-IA.II [M] Dt.
31.12.2013. stating that (1) The matter relating to violation has been put to
the Board of Directors of the Company or to the Managing Committee, for
consideration of your environment related policy/plan of action and a
written commitment in the form of a formal resolution is submitted to MoEF
to ensure that violations of the Environment (Protection) Act will not be
repeated (2) The State Government has initiated credible action on the
violation against you under the Environment (Protection) act 1986 and
evidence provided to MoEF of the action taken (3) You close down your
mining operations with immediate effect. And also stated that While
communications against (1) & (2) have been issued separately, these
directions are being issued to ensure (3) and instructed Sri S. Ravi to stop
the mining operations.
Against above, Sri S. Ravi has
1. Submitted written commitment that violations of the Environment
(Protection) Act will not be repeated as Affidavit on 100/- Rupees bond
paper
2. A letter was submitted to principle secretary, Govt. of Telangana for
initiation credible action on 25.02.2015. The process was initiated and
the case was filed in the court of Judicial First Class Magistrate, Pargi.
3. Inspection report from Department of Mines and Geology vide letter
no. 3540/M/2008 Dt. 18.06.2015 states that mining operation was
stopped.
Sri S. Ravi has submitted the reply to the above points in hard copy to
MoEF & CC, Non- Coal Mining Committee on 17.01.2017. Against this
MOEF & CC vide letter no. J-11015/05/2010-IA.II [M] dated 17.07.2017
instructed Sri S. Ravi to submit online the proposal afresh as violation case
submitting the following information.
5. Certificate stating that mining activity of the said mine has
been stopped (with date) and CTO/occupancy Certificate has been
revoked, duly certified by the State Pollution Control Board
8
Submission of Sri S. Ravi: Inspection report from Department of
Mines and geology vide letter no. 3540/M/2008 Dt. 18.06.2015 states
that mining operation was stopped.
6. Detailed statement of Past production since inception/after
1994 to till-date, duly certified by the Department of Mines and
Geology
Submission of Sri S. Ravi: SRS Approached DMG for the same
7. Details of violation proceedings, if any, already initiated or
completed by the State Government in the instant proposal with
supporting documents
Submission of Sri S. Ravi: A letter was submitted to principle
secretary, Govt. of Telangana for initiation credible action on
25.02.2015. The process was initiated and the case was filed in the
court of Judicial First Class Magistrate, Pargi.
8. Details of earlier applications made to MoEF & CC, if any, for
grant of EC.
Submission of Sri S. Ravi: File no. J-11015/05/2010-IA.II [M]
Since Sri S. Ravi has already submitted the documents, which are at an
advanced stage of consideration, at this stage when MOEF instructed to
submit afresh on 17.07.2017 letter, Sri S. Ravi has approached the Hon’ble
High Court of Judicature at Hyderabad. Sri S. Ravi has obtained court order
dated 22.09.2017 directed Ministry of Environment, Forests and Climate
Change to receive our application without prejudice to their contention that,
in standing order dated 14.03.2017. Later the proposal was submitted on
16.11.2017 under violation vide Proposal No. IA/TG/MIN/68696/2017.
Since the proposal under violation was submitted on 16.11.2017, we are
here with resubmitting the proposal under violation in compliance with
MoEF & CC Office Memorandum Dated 16th March, 2018.
(ii) Brief Description of the Nature of the Project.
Project is Quartz and feldspar over an extent of 56.68 Ha. It is proposed to
produce 3,00,000 Tonnes /Annum (TPA) of Quartz and Feldspar with Total
9
Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA + Waste :
50,432 TPA)by means of Open cast -Mechanized mining method. The
material is transported for crushing and screen plant by tippers.
(iii) Need For The Project And Its Importance To The Country.
The mining industry will improve the economic status of the people in and
around the lease area. Continued mining activities, will benefit the local
people due to job opportunities created.
Quartzite deposits in this area form mineral wealth, as the ore is major raw
material for the manufacture of Glass and Concrete Making. Since, the
Quartzite ore reserves of this area are economically viable, their proper
utilization will improve the economic status of the people and the Country
(iv) Demand– Supply Gap
Nature and occurrence of ROM generated at this mine is more suitable for
making glass as fill and to create molds in industry processing, water-
filtration, glass manufacture, industrial casting, sand blasting, to produce
concrete, adding texture to slick roads.
(v) Imports Vs Indigenous Production.
The Quartz & Feldspar produced will be transported directly to the
consumer/buyer after crushing and screening with required sizes.
(vi) Export Possibility.
No exports of Quartz & Feldspar are proposed.
(vii) Domestic / Export Markets
The Quartz & Feldspar produced will be transported directly to the
consumer/ buyer after crushing and screening with required sizes.
(viii) Employment Generation (Direct and Indirect) Due to Project.
The employment potential of the project would be about 33 persons.
10
3. PROJECT DESCRIPTION:
(i) Type of Project (including interlinked and interdependent project,
if any)
Project is Quartz and feldspar over an extent of 56.68 Ha. It is proposed to
produce 3,00,000 Tonnes /Annum (TPA) of Quartz and Feldspar With Total
Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA + Waste :
50,432 TPA). It is an opencast mining for quartz and feldspar production
through conventional method. The ore is used for the manufacture of Glass
and Concrete Making.
It is categorized as Category ‘A’ Project under Schedule 1(a) hence it
necessitates obtaining Environment Clearance from Ministry of
Environment, Forest and Climate Change (MoEF & CC).
(ii) Location (map showing general location, specific location and
project boundary & project site specific layout) with coordinates.
Sri S. Ravi, Lessee of Quartz & Feldspar mine over an extent of 56.68
Hectares Sy. No.415/P of Bandivankacharla Village, Kulkcherla Taluk,
Rangareddy District, Telangana State.
The Mining Lease Area is a part of the Survey of India Toposheet No.
56/G/16. The site falls between 1) 17°01'50.01"N- 77°49'22.73"E 2)
17°01'51.61"N- 77°49'30.88"E 3) 17° 2'45.83"N- 77°49'29.33"E 4) 17°
2'41.41"N- 77°49'19.38"E, North and East Longitude with an average
altitude of 625 m above MSL. The location map of the Mining Lease Area is
shown in Fig – 1.
Nearest railway line connecting Secunderabad - Tandur of South Central
Railway line, at a distance of 25.0 km to Northern direction from the Mining
Lease Area. Key map showing the location of various features around the
Mining Lease Area is shown in Fig – 2. Mahbubnagar is major town at a
distance of 37.7 km in SE direction.
The National Highway (NH-44) connecting Hyderabad - Mahbubnagar, at a
distance of about 35.5 km in Eastern direction, The nearest railway station
is Mailaram at 25.0 km in Northern direction.
The State Highway (SH-4) connecting Pargi - Kodangal, at a distance of
about 12.7 km in NNE direction,
11
LOCATION MAP
FIG - 1
TELANGANA
N
ADILABAD
KOMARAM BHEEMNIRMAL
NIZAMABAD
JAGITYAL
KAMAREDDY
KARIMNAGAR
PEDDAPALLE
JAYASHANKAR
SANGAREDDY
RANGAREDDY
MAHABUBNAGAR
WANAPARTHY
NAGARKURNOOL
NALGONDA
KHAMMAM
KOTHAGUDEM
WARANGAL
YADADRI
SHAMSHABAD
HYDERABAD
MEDAK
SIDDIPET
INDIA
OTHER ROAD
LEGEND
DISTRICT BOUNDARY
MAJOR ROAD
NATIONAL HIGHWAY
RAILWAY LINE
RIVER
STATE BOUNDARY
DISTRICT HEAD QUARTER
MAJOR TOWN
OTHER TOWN
563
MINING LEASE AREA
MANCHERIAL
KOMARAM BHEEM
MANCHERIAL
RANGA REDDY DISTRICT
Venkatapuram
Mailwarram
Miryan
Tandur
ShahabadPargi
Markal
Nancherla
Muhammadabad
Doma
Morangpalli
Peddamal
Elal
Kotepalli
Patlur
Marpalli
Changomal
Chevella
Shankarpalli
Vikarabad
Ibrahimpatanam
Yacharam
Maisaram
BolaramMaula Ali
Medchal
HYDERABAD
Tukkuguda
SecunderabadGundipet
Golkonda
MINING LEASE AREA
7
7
9
13
There are no wild life sanctuaries, national parks, elephant/tiger reserves
within 10km radius of the study area.
Nearest Settlements from the Mining Lease Area
Bandivankacharla – 1.3 km – E
Govindnaik Tanda – 0.2 km – S
Nearest Reserved Forests from the Mining Lease Area
Gauraram R F – 7.6 km – WNW
Bompally R F – 7.6 km – NNE
Mothkur R F – 6.1 km – ENE
Mujaithapur R F – 6.2 km – E
Kulkacherla R F – 5.8 km – E
Tirumalapur R F – 7.0 km - E
Salient features of Mining Lease Area are given in Fig - 3 and Table – 1
shows the study area of 10 km radius around the Mining Lease Area
(iii) Details of alternate sites considered and the basis of selecting
the proposed site, particularly the environmental considerations gone
into should be highlighted.
No alternate sites were considered as the project is mineral specific.
(iv) Size or Magnitude of operation.
It is proposed to mine about 3,00,000 Tons/annum of Quartz and Feldspar.
(v) Project Description with Process details (a schematic diagram/
Flow chart showing the project layout, components of the project etc.
should be given.
Type of Mining
Mining is proposed to work this deposit by open cast mechanized method.
The southern part of strike length of quartz reef zone will be opened and
faces will be advanced across and along the strike in benches of 6m height
and minimum bench width of 6m. The faces shall be moved from hanging
wall side to footwall side, In the process of maintaining benches, the clay as
side burden shall be stripped during movement of faces. The ore is
mechanically loaded into the tippers and sent to the crushing plan't which is
located outside the mining lease.
15
TABLE – 1
SALIENT FEATURES OF THE MINING LEASE AREA
Feature Details
Altitude 625m above msl
Longitude & Latitude 1) 17° 1'50.01"N- 77°49'22.73"E 2) 17° 1'51.61"N-
77°49'30.88"E 3) 17° 2'45.83"N- 77°49'29.33"E 4) 17° 2'41.41"N- 77°49'19.38"E,
Village, Tehsil, District, State
Bandivankacharla Village, Kulkcherla Taluk, Rangareddy District, Telangana.
IMD Station Hyderabad – 80km - ENE
Max. Temp. 0C 45.5
Min. Temp. 0C 6.1
Relative Humidity, % 23 - 82
Annual rainfall 812.5 mm
Topography Hilly Terrain
Nearest water bodies (Near DOMA Village ) Vagu – 3.6 km – N
(Near Ainapur Village ) Cheruvu – 0.2 km – N
Nearest Highway National Highway (NH-44) connecting Secunderabad –
Tandur – 35.59 km – E
The State Highway (SH-4) connecting Pargi - Kodangal, - 12.7 km - NNE
Nearest Railway station
Mailaram – 25.0km - N
Nearest Industries None within 10 km Radius
Nearest Villages Bandivankacharla – 1.3 km – E
Govindnaik Tanda – 0.2 km – S
Nearest Town Mahbubnagar – 37.7km - SE
Inter State Boundary Telangana – Karnataka – 33.0 km - W
National Parks/ Bird Sanctuaries
None within 10 km Radius
Nearest Port Krishnapatnam Port (Nellore )- 395.0 km – SE
Nearest Air port Rajiv Gandhi International Airport (Shamshabad) Hyderabad – 66.0 km – ENE
Nearest Forest Gauraram R F – 7.6 km – WNW Bompally R F – 7.6 km – NNE
Mothkur R F – 6.1 km – ENE Mujaithapur R F – 6.2 km – E Kulkacherla R F – 5.8 km – E
Tirumalapur R F – 7.0 km - E
Historical places None within 10 km Radius * All distances mentioned in the above table are aerial distances.
16
FLOW SHEET OF CRUSHING AND SCREENING PLANT WITH MATERIAL BALANCE
a) Brief Description (Method of working)
The Method of mining is open cast mechanized mining method using 115
mm dia. DTH Drilling and blasting. The blasted material shall be loaded into
the tippers and sent to crushing plant (located outside the Ml Area) & stock
by the help of excavator. The same excavator will also be used for handling
of waste/ rejection. Wheel loaders will be utilized for feeding to the plant
from stock and loading for dispatch as and when required.
Mining of Ore
The basic operations involved in the mining of ore are mechanically. The
interstitial waste is directly loading into tippers and transportation to the
reject dump yard. In the ore zone, the ore is directly loaded in the tippers
trucks and is dispatched to the designated places. The oversize boulders are
separately loaded and transported to SGMD stack yard for breaking
The system of working shall be mechanized opencast mining method. The
various operations involved are.
a) Drilling- 115mm dia DTH drill shall be used for the purpose. The
burden and spacing shall be kept 3 m and 3.5 m respectively.
b) Blasting - To blast the drilled holes slurry explosives and Ammonical
Nitrate Fuel Oil mixture shall be used
c) After blasting the loose materia1 shall be loaded by excavators into
tippers
17
d) The tippers after loading shall transport the material to the crushing
and screening plant, which is located outside the mining lease
e) The sub grade material if available shall be transported and stacked
separately in the location already marked and shall be blended
whenever required
f) The rejects shall be transported and clamped separately m the rejection
dumping yard
Drilling
Type Nos. Dia of Hole mm
Make Motive Power
DTH Drill 2 115 Atlas copco Compressed Air
Blasting
Multiple rows of holes shall be blasted using milli-second delay detonators
tubes.
The holes shall be blasted using 25 m, 50 m and 100 m cord relays and
17m/25m/42m so that charge per delay would not exceed the permissible
limits
It is preferred to use 10% High explosives of slurry cartridge of 83 mm as a
prime charge and 90% Ammonium Nitrate fuel oil mixture.
Powder factor shall be avg. 3.50 t/kg of explosives in the entire strata to be
blasted
Explosives material Calculation for blasting (Charge/hole)
Height of the bench = 6.0 m
Hole depth = 6.0 m
Burden = 3.0 m
Spacing = 3.5 m
Bulk Density = 2.5 t/m3
The maximum material to be blasted per annum shall be = 3.41,689 tonnes
Burden x Spacing x Depth x Bulk Density
Quantity broken/hole = 3 m x 3.5 in x 6.0 m x 2.5 tonnes / m x 80%
= 126.0 tonnes / Hole
Powder factor = 3.50 tonnes /kg for a good fragmentation
Explosives required per hole= 126 tonnes/3.50 tonnes = 36 kg/hole
18
Total quantity of Explosive required = 341689/3.50 = 97625 Kg
= 98 tonnes
ANFO @ 90% of 98 tonnes = 88.20 tonnes
High Explosives required = 9.80 tonnes
Total = 98.00 tonnes
Secondary Blasting
Secondary blasting will be to the tune of 10 % of the total blasted quantity
for reducing the size of the boulders to -300 mm which can be fed to the
plant.
Storage of explosives
Magazine is proposed in the eastern corner of the lease boundary. The
capacity of the same will be enhanced and the explosive van will be used to
bring the explosives to cater to the need of mining.
Removal Of Over Burden
The Over/side burden constitutes of shale and waste within quartz is
ferruginous shale horizon. The soft waste will be separated from the ore and
directly excavated and transported to the designated site earmarked for the
purpose.
Extent of Mechanization
Open cast mechanized mining operation will be adopted. The following
mentioned mine machinery will be deployed.
LIST OF MACHINERY
S. No. Type of machine No
1 Excavator 2
2 Dumpers 6
3 Drillers 2
4 Water Tanker 1
5 Rock breaker 1
6 Wheel Loader 1
Stock yard
After completion of dressing, the quartz will be transported to stock yard.
19
(vi) Raw Material / Consumables Required along with estimated
quantity, likely source, marketing area of final product, mode of
transport of raw material and finished product
No raw materials are required. Consumables and finished goods will be
transported by means of road transport only.
(vi) Resource optimization/ recycling and reuse envisaged in
project, if any, should be briefly outlined.
Waste generated from the mined out area will be concurrently backfilled.
(vii) Availability of water, it’s source, Energy/power requirement and
source should be given.
Water:
The water environment will not get disturbed by the mining operations.
Water requirement will be 18 m3/day and the same will be met from ground
water.
Energy and Power Requirement and Source
Power requirement for illumination will be met from grid.
(ix) Quantity of wastes to be generated (liquid and solid) and scheme for
their management / disposal.
Waste generation from the mine is estimated to be about 82,950 tonnes
during the scheme period.
(x) Schematic representations of the feasibility drawing which give
information of EIA purpose.
The subject project is mining of Quartz & Feldspar with production
capacity of 300000 TPA from mining lease area of 56.68 Ha. Based on
the threshold levels as per MoEF& CC Notification “S.O. 1533” Dated
14.09.2006 and amendment thereof the subject project is categorised as
Category ‘A’ listed under Schedule 1(a) of SO 1533.
21
4. SITE ANALYSIS
i) Connectivity
Nearest railway line connecting Secunderabad - Tandur of South Central
Railway line, at a distance of 25.0 km to Northern direction from the Mining
Lease Area.
The National Highway (NH-44) connecting Hyderabad - Mahbubnagar, at a
distance of about 35.5 km in Eastern direction,
The nearest railway station is Mailaram at 25.0 km in Northern direction.
The State Highway (SH-4) connecting Pargi - Kodangal, at a distance of
about 12.7 km in NNE direction,
ii) Land Form, Land use and Land Ownership
Total mining lease area is Govt. Revenue Land (56.68 ha).
The detailed land use is given below:
LAND USE BREAKUP
S. No LAND PARTICULARS PRESENT USE CONCEPTUAL
PERIOD AREA IN HA.
1 Area under Excavation 0.5200 21.072 (14.572
backfilling)
2 Storage of Top Soil Nil 0.0800
3 Overburden Dump 0.2000 6.4520
4 Mineral storage 0.1520 0.1520
5 Infrastructure (Workshop,
Administrative Buildings)
0.1000 0.1000
6 Roads 0.2540 1.0000
7 Greenbelt Nil 3.5000
8 Env. Protective measures Nil 1.0000
9 Mineral Separation plant 0.4047 -
10 Area Cultivated 7.0172 -
11 Dump Area Plantation Nil 3.0000
12 Others (Unutilized Area) 48.0321 20.2240
Total 56.6800 56.6800
22
The ML Area is as saddle shaped hillock with radial Slopes. The highest
contour of 160m RL is traversing in central portion of the lease area and
lowest contour level is 103 RL is at North-Eastern of lease area. The general
strike direction is almost North South and dipping easterly with almost
vertical dip. Surface Plan is enclosed as Fig – 4.
FIG – 4 SURFACE PLAN
130
133
136
139
142
148
157
151
151
148
145
141
139
139
136
133
130
127
124
121
118
115
112
109
106
103
118
124
127
133
139
S5
GC
P-2
N1
7°
01
' 50
.01"
E 7
7°
49
' 22.7
3"
N1
4°
01
' 51
.61"
E 7
7°
49
' 30.8
8"
N1
7°
02
' 41
.41"
E 7
7°
49
' 19.3
8"
GC
P-1
GC
P-3
MN
W
S
E
115
118
121
124
130
133
Cru
shin
g &
Scr
ee
nin
g
Pla
nt
LE
AS
E B
OU
ND
AR
Y
CO
NT
OU
R
LE
GE
ND RO
AD
MIN
E W
OR
KIN
GS
ST
RE
AM
S
TB
M
RL
=1
00
M
N2000
N1800
N1600
N1400
N1200
N1000
N800
N600
N400
N200
00
E200
E400
E600
E200
E400
E600
N2000
N1800
N1600
N1400
N1200
N1000
N800
N600
N400
N200
00
PR
OJE
CT
:
TIT
LE
:
SU
RF
AC
E E
PL
AN
FIG
- 4
CL
IEN
T :
Sri. S
. R
AV
I
Ba
nd
iva
nka
cha
rla
Vill
ag
e,
Ku
lkch
erl
a M
an
da
l,
Ra
ng
aR
ed
dy
Dis
tric
t, T
ela
ng
an
a.
Q
UA
RT
Z &
F
EL
DS
PA
R M
IN
E - 5
6.6
8 H
a
23
iii) Existing land use pattern (agriculture, non-agriculture, forest,
water bodies (including area under CRZ), shortest distances from the
periphery of the project to periphery of the forests, national park, wild
life sanctuary, eco sensitive areas, water bodies (distance from the HFL
of the river), CRZ, in case of notified industrial area, a copy of the
Gazette notification should be given.
Total area of 56.68 Ha is Govt. waste land
There are no wild life sanctuaries, national parks, elephant/tiger reserves
within 10km radius of the study area.
Nearest Reserved Forests from the mining lease area
Gauraram R F – 7.6 km – WNW
Bompally R F – 7.6 km – NNE
Mothkur R F – 6.1 km – ENE
Mujaithapur R F – 6.2 km – E
Kulkacherla R F – 5.8 km – E
Tirumalapur R F – 7.0 km - E
iv) Existing infrastructure
None within the mining lease.
v) Soil classification
The area is covered with thin soil of thickness varying from 0.1 to 0.20 m in
the slopes. The area is mixed with quartz float and pieces of schist rock.
About 4200 tonnes of top soil is likely to be generated in this scheme period
which is preserved and is used during plantation on the dumps.
vi) Climatic data from Secondary Sources
The area is hot during most part of the year. The average annual rainfall on
the area is around 680 mm per year. The highest and lowest temperature in
the lease area varies between 420 to 280 respectively. The drainage pattern
in the area is Sub-Dendritic in nature. The most of the lands in western side
of the lease are of cultivable nature and crops like paddy maize, jawar and
groundnut etc., are grown.
vii) Social infrastructure available.
The haul roads will be developed for carrying capacities by the waste
obtained from the mining/ extraction of ore. The approach roads are
sufficient to cater to the proposed production. The proposed project will
provide employment and benefits
24
CHAPTER – 5 PLANINIG BRIEF
5. PLANNING BRIEF:
i) Planning Concept (type of industries, facilities, transportation, etc.,)
town and country Planning / Development authority classification:
The subjected mine is the Quartz and Feldspar mine of Sri S. Ravi at
Bandivankacharla Village, Kulkcherla Taluk, Rangareddy District,
Telangana State in over an extent of 56.68 Ha. The present proposal is for
production of 3,00,000 TPA Quartz and Feldspar mineral.
ii) Population Projection:
Since there will not be any major influx of people from outside in this region
because of the project, there will hardly be any population explosion. Most of
the workers will be people from surrounding villages only.
A total of 33 persons will be employed for mining operations.
iii) Land use planning (breakup along with greenbelt etc.,)
The detailed conceptual land use is given below:
CONCEPTUAL LAND USE
S. No LAND PARTICULARS AREA IN HA.
1 Area under Excavation 21.072 (14.572
backfilling)
2 Storage of Top Soil 0.0800
3 Overburden Dump 6.4520
4 Mineral storage 0.1520
5 Infrastructure (Workshop,
Administrative Buildings)
0.1000
6 Roads 1.0000
7 Greenbelt 3.5000
8 Env. Protective measures 1.0000
9 Dump Area Planation 3.0000
10 Others (Unutilized Area) 20.2240
Total 56.6800
25
iii) Assessment of Infrastructure Demand ( Physical & Social):
The proposed will provide the direct employment to about 33 people in
addition there will be indirect employment to many more people, in the form
of contractual jobs, business opportunities, service facilities etc. This will
enhance the economic status of the area.
iv) Amenities /Facilities:
All the necessary infrastructure facilities such as office, Canteen, rest
shelters, drinking water, Medical facilities, transport and others will be
provided.
26
CHAPTER – 6 PROPOSED INFRASTRUCTURE
6. PROPOSED INFRASTRUCTURE:
(i) Industrial
No mineral processing technique will be adopted. The final product will be
transported directly to the consumer/ buyer after crushing and screening
with required sizes.
The ore/mineral will be accumulated by doing drilling & blasting, at once
excavation & loading will be commenced so that the effective cost saving of
the excavator will be done.
(ii) Residential
No residential facilities are proposed at mine site.
(iii) Greenbelt
7.5 m barrier zone along the mine boundary will be developed under
greenbelt in a phased manner.
(iv) Social Infrastructure
The mining activity carried out in the area rather has a positive socio-
economic impact upon the nearby human settlement as indirect
employment potential is created due to mining and allied activities in the
area. Apart from these, the company promotes health and education
awareness in the area time to time by organizing health and education
camps.
(v) Connectivity
Nearest railway line connecting Secunderabad - Tandur of South Central
Railway line, at a distance of 25.0 km to Northern direction from the Mining
Lease Area.
The National Highway (NH-44) connecting Hyderabad - Mahbubnagar, at a
distance of about 35.5 km in Eastern direction,
The nearest railway station is Mailaram at 25.0 km in Northern direction.
27
The State Highway (SH-4) connecting Pargi - Kodangal, at a distance of
about 12.7 km in NNE direction,
(vi) Drinking Water Management (Source and Supply of Water)
Water requirement for is 18 m3/day for drinking, dust suppression, and
Afforestation. The water requirement will be sourced from ground water.
(vii) Sewerage System
No wastewater generation except for domestic waste from toilet which will be
treated in septic tank followed by soak pit.
(viii) Solid Waste Management
Waste generation (O.B. consisting of soil and weathered rock) from the mine
for the life of mine is 6,76,939 tonnes (4230 t/month)
Waste will be disposed to temporary dump initially and Backfilling at later
stage
The non-mineralized area within the mining lease will be used as temporary
waste dump yard which will be rehandled for part backfilling of the mined-
out area at conceptual stage.
(ix) Power Requirement & Supply / Source.
Power requirement for illumination will be met from grid.
28
CHAPTER – 7 REHABILITATION AND RESETTLEMENT (R & R) PLAN
7.0 Rehabilitation and resettlement (R & R) Plan
i. Policy to be adopted (central / state) in respect of the project affected persons including home oustees, land oustees and landless labourers (a brief out line to be given).
The mine area does not cover any habitation. Hence the mining
activities do not involve any displacement of human settlement. No
public buildings, places, monuments etc., exist within the lease area
or in the vicinity. The mining operations will not disturb/relocate any
village.
CHAPTER – 8 PROJECT SCHEDULE & COST ESTIMATES
8.0 Project schedule & Cost Estimates
i. Likely date of start of construction and likely date of completion
(time schedule for the project to be given).
Mining operations will be commenced after obtaining EC, CFE, CFO and all
other regulatory clearances. Life of the mine @ 3,00,000 Tonnes /Annum
(TPA) of Quartz and Feldspar With Total Excavation of 3,50,432 TPA
(Quartz and Feldspar: 3,00,000 TPA + Waste : 50,432 TPA) for the proved
mineral reserve of 46,29,946 million tonnes would be 16 years.
ii. Estimated project cost along with analysis in terms of economic
viability of the project.
Project cost is estimated to be about Rs 150 Lakhs
CHAPTER – 9 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
9.0 Analysis of proposal (Final Recommendations)
i. Financial and social benefits with special emphasis on the benefit
to the local people including tribal population, if any, in the area.
Economic development of the region depends largely upon the nature
of activities undertaken in the surrounding region. Corporate
development invariably contributes towards acceleration of the
process of socio-economic upliftment of the rural society by means
of employment, health & study programme, medical camps etc.,