46
Ref: SSR/TOR/ADS/2019 Date: 15.02.2019 To The Director, Government of India, Ministry of Environment, Forests & Climate Change Indira Paryavaran Bhavan, Jor Bagh Road New Delhi - 110 003 Sub: Submission of ADS Reply - Quartz & Feldspar Mine of Sri S. Ravi Located at Bandivankacharla Village, Kulkcherla Taluk in Rangareddy District in Telangana State. (ML Area- 56.68 Ha and the production Capacity of 3,00,000 Tonnes /Annum (TPA) Quartz and Feldspar With Total Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA + Waste : 50432 TPA) – VIOLATION CASE- Reg. Ref: 1). Online File No: IA/TG/MIN/73867/2018 Dt: 31.03.2018 2). 17 th EAC Meeting Held on 31-01-2019 3). ADS Raised by MoEF & CC 07.02.2019 Dear Sir, We thank you for giving us opportunity to present our case in front of EAC Vide Reference (2). As per the ADS raised, we are herewith enclosing the following documents raised for your consideration. a) Revised Form I duly filled-in b) Revised Pre - Feasibility Report c) Authenticated Production details Thanking you, Yours faithfully, Sri S Ravi Lessee Encl.: as above

Ref: SSR/TOR/ADS/2019 Date: 15.02.2019 To The Director ...environmentclearance.nic.in/writereaddata/Online/EDS/0_0_15_Feb_2019_1259301131ADS...Ministry of Environment, Forests & Climate

  • Upload
    others

  • View
    10

  • Download
    0

Embed Size (px)

Citation preview

Ref: SSR/TOR/ADS/2019 Date: 15.02.2019

To

The Director, Government of India,

Ministry of Environment, Forests & Climate Change Indira Paryavaran Bhavan, Jor Bagh Road New Delhi - 110 003

Sub: Submission of ADS Reply - Quartz & Feldspar Mine of Sri S. Ravi

Located at Bandivankacharla Village, Kulkcherla Taluk in Rangareddy District in Telangana State. (ML Area- 56.68 Ha and

the production Capacity of 3,00,000 Tonnes /Annum (TPA) Quartz and Feldspar With Total Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA + Waste : 50432 TPA) –

VIOLATION CASE- Reg.

Ref: 1). Online File No: IA/TG/MIN/73867/2018 Dt: 31.03.2018

2). 17th EAC Meeting Held on 31-01-2019

3). ADS Raised by MoEF & CC 07.02.2019

Dear Sir,

We thank you for giving us opportunity to present our case in front of EAC Vide Reference (2).

As per the ADS raised, we are herewith enclosing the following documents raised for your consideration.

a) Revised Form I duly filled-in b) Revised Pre - Feasibility Report

c) Authenticated Production details

Thanking you,

Yours faithfully,

Sri S Ravi Lessee

Encl.: as above

REVISED FORM – I

&

PRE FEASIBILITY REPORT

Of

Quartz & Feldspar (Area: 56.68 Ha)

Bandivankacharla Village, Kulkcherla Taluk,

Rangareddy District, Telangana State

For

Production of 3,00,000 Tonnes /Annum (TPA) Quartz and Feldspar With Total Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA + Waste : 50,432 TPA)

Of

Sri S. Ravi

February, 2019

Prepared By

< B.S. ENVI-TECH (P) LTD.,

Secunderabad – 500 017

NABET Accreditation No: NABET/EIA/1619/SA064

FORM – I

FORM 1

(As Per New Notification of Mo.E.F dated 1-12-2009 vide SO 3067 (E))

BASIC INFORMATION

S.

No

Item Details

1 Name of the Project/s Quartz & Feldspar mine of Sri S. Ravi

2 S. No. in the schedule 1(a)

3 Proposed capacity/ area/ length/

tonnage to be handled/ command area/ lease area/ number of wells to be drilled

Production of 3,00,000 Tonnes

/Annum (TPA) Quartz and Feldspar With Total Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA +

Waste : 50432 TPA)

Mine lease area: 56.68 Ha

4 New/ expansion/ modernization Operating Mine (Mining operations stopped)

5 Existing capacity/ Area etc. Production of 3,00,000 Tonnes /Annum (TPA) Quartz and Feldspar

With Total Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA +

Waste : 50432 TPA) Mine lease area: 56.68 Ha

6 Category of Project i.e ‘A’ or ‘B’ A

7 Does it attract the general condition? If

yes please specify.

No

8 Does it attract the specific condition? If

yes please specify.

No

9 Location

Plot/ Survey/ Khasra No Survey No: 415p

Village Banivenkacherla

Tehsil Kulkacherla

District Rangareddy

State Telangana.

10 Nearest railway station/ airport along with distance in Kms.

Nearest railway station: Mailaram – 25.0km - N

Rajiv Gandhi International Airport (Shamshabad) Hyderabad – 66.0 km –

ENE

11 Nearest town, city, district head quarters along with distance in kms.

Mahbubnagar – 37.7km - SE

12 Village panchayaths, Zillaparishad, Municipal Corporation, Local body

(Complete postal addresses with telephone nos to be given)

Banivenkacherla Village, Kulkacherla Mandal, Rangareddy Dist., Telangana

State.

13 Name of the applicant Sri S. Ravi

14 Registered address Plot No:6, Road No 51 Silent Lake Valley, Jubilee Hills,

Hyderabad

15 Address for correspondence

Name of the Applicant Sri S. Ravi

Designation (Owner /Partner/ CEO) Lessee

Address Plot No:6, Road No 51

Silent Lake Valley, Jubilee Hills, Hyderabad.

Pincode -

E- mail [email protected]

Telephone no. +9140 23555183

Fax no. +9140 23555182

16 Details of Alternative sites examined, if any location of these sites should be

shown on a topo sheet.

No

17 Interlinked projects None

18 Whether separate application of interlinked project has been submitted?

Not Applicable

19 If yes, date of submission Not Applicable

20 If no, reason Not Applicable

21 Whether the proposal involves

approval/ clearance under: if yes, details of the same and their status to

be given. (a) The Forest (Conservation)Act, 1980

(b) The Wild Life (Protection)Act, 1972 (c) The CRZ Notification, 1991

Not Applicable

Not Applicable Not Applicable

22 Whether there is any Government Order/ Policy relevant/ relating to the site?

None

23 Forest land involved (hectares) None

24 Whether there is any litigation pending

against the project and/or land in which the project is propose to be set up?

(a) Name of the court (b) Case No

(c) Orders/ directions of the court, if any and its relevance with the proposed project.

None

(I) ACTIVITY

1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

S.No. Information/Checklist confirmation

Yes/No Details thereof (with approximate quantities /rates, wherever

possible) with source of information data

1.1 Permanent or temporary change in land use, land cover or topography including

increase in intensity of land use (with respect to local land

use plan)

Yes Total area of 56.68 Ha is Govt. Revenue land.

At the conceptual stage, the land use is detailed in below table

S. No

Land Particulars

Present Use

Conceptual Period Area

In Ha.

1 Area under Excavation

0.5200 21.072

2 Worked out pit

Nil (14.572)*

3 Storage of Top

Soil

Nil 0.0800

4 Overburden Dump

0.2000 6.4520

5 Mineral storage

0.1520 0.1520

6 Infrastructure (Workshop, Administrative Buildings)

0.1000 0.1000

7 Roads 0.2540 1.0000

8 Greenbelt Nil 3.5000

9 Env. Protective measures

Nil 1.0000

10 Mineral

Separation plant

0.4047 -

11 Area

Cultivated

7.0172 -

12 Dump Area Plantation

Nil 3.0000

13 Others (Unutilized Area)

48.0321 20.2240

Total 56.6800 56.6800

1.2 Clearance of existing land,

vegetation and buildings?

Yes Small bushes will be cleared for the

proposed mining activity.

1.3 Creation of new land uses?

Yes Open barren land will be converted

into mining activities.

1.4 Pre-construction investigations

e.g. bore houses, soil testing?

Yes Exploration work is already carried

out. Further exploration is proposed for the deposits of Quartz deposit and minerals.

1.5 Construction works?

Yes Site office, rest shelter, first aid room will be constructed.

1.6 Demolition works? No No demolition works are involved.

1.7 Temporary sites used for construction works or housing

No No Construction works

of construction workers?

1.8 Above ground buildings, structures or earthworks including linear structures, cut

and fill or excavations.

Yes i. Above ground structures : Site office, rest shelter, first aid room ii. Earthworks:

Excavation operations

1.9 Underground works including

mining or tunneling?

No Opencast mining is adopted, hence no

underground or tunneling works are involved

1.10 Reclamation works?

Yes Entire broken up area will be backfilled or reclaimed

1.11 Dredging? No No dredging is involved

1.12 Offshore structures? No Mine site is far from the sea coast.

1.13 Production and manufacturing

processes?

Yes Quartz : 300000 TPA

Crushing and Screening

1.14 Facilities for storage of goods or

materials?

Yes Storage of mineral and subgrade

mineral will be stored in earmark area

1.15 Facilities for treatment or disposal of solid waste or liquid effluents?

Yes Solid waste generation will be disposed in the dumping area. Liquid effluent will not generated

during mining operation.

1.16 Facilities for long term housing

of operational workers?

No No long term housing facilities

because of all the workers will be hired from the local villages only.

1.17 New road, rail or sea traffic during construction or operation?

Yes Increase the road traffic is minimal during operation phase.

1.18 New road, rail, air waterborne or other transport

infrastructure including new or altered routes and stations,

ports, airports etc?

No There is no proposed for construction of new road, other transport

infrastructures. Existing road facilities will be utilized.

1.19 Closure or diversion of existing transport routes or

infrastructure leading to changes in traffic movements?

No No diversion of infrastructure.

1.20 New or diverted transmission lines or pipelines?

No There will be no new or diverted transmission lines or pipelines

1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology

of watercourses or aquifers?

No There will be no impoundment, damming, culverting, realignment or other changes in the hydrology of

watercourses or aquifers

1.22 Stream crossings? No No streams crossing

1.23 Abstraction or transfers of water from ground or surface

waters?

Yes Ground water will be used for drinking purpose & dust suppression.

1.24 Changes in water bodies or the

land surface affecting drainage or run-off?

Yes Mining operation and exaction can

affect the surface pattern there by changing the course of drainage run-

off.

1.25 Transport of personnel or materials for construction, operation or decommissioning?

No The personnel and materials for construction will be hired from nearby villages.

1.26 Long-term dismantling or decommissioning or restoration

works?

No There will be no long-term dismantling or decommissioning

works.

1.27 Ongoing activity during

decommissioning which could have an impact on the environment?

No Not applicable.

1.28 Influx of people to an area in either temporarily or

permanently?

No Local people are employed for mining activities.

1.29 Introduction of alien species? No The local/ indigenous species will be

planted within the site area.

1.30 Loss of native species or

genetic diversity?

No Only local native species will be

planted which will increase the Biodiversity of the area. There will be no loss of native or genetic diversity.

1.31 Any other actions? No None

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-

renewable or in short supply):

S.No. Information/Checklist

confirmation

Yes/No Details thereof (with

approximate quantities /rates, wherever possible) with source

of information data

2.1 Land especially undeveloped or agricultural land (ha)

No The entire land is Government Revenue land.

Mine lease area:56.68Ha

2.2 Water (expected source & competing users) unit: KLD

Yes 18 m3/day water will be required for domestic purpose, green belt development and dust

suppression. Source of water will be from Ground Water/Local

Purchase

2.3 Minerals (MT) Yes Mineral reserves - 46,29,946 tons.

2.4 Construction material – stone, aggregates, sand/soil (expected source – MT)

No Not Applicable

2.5 Forests and timber (source – MT) No Forests and timber are not required for this project as proposed project is for extraction

of stone (minor quarry) which will not involve use of forest or timber.

2.6 Energy including electricity and fuels (source, competing users)

Yes Electrical is used for lighting purpose

Unit: fuel (MT), energy (MW) Diesel is used for compressors,

tippers etc.

2.7 Any other natural resources (use appropriate standard units)

No None

3. Use, storage, transport, handling or production of substancesor materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

S. No.

Information/Checklist confirmation

Yes/No Details thereof (with approximate quantities/ rates,

wherever possible) with source of information data

3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or

the environment (flora, fauna, and water supplies)

No No hazardous substance or materials will be utilized for mining operations.

3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases)

No No source of occurrence of disease or effect on disease vectors is envisaged through the project.

3.3 Affect the welfare of people e.g. by changing living conditions?

Yes Socioeconomic Development and living conditions will improve after

the start of mining activities.

3.4 Vulnerable groups of people who

could be affected by the project e.g. hospital patients, children, the elderly etc.,

No None

3.5 Any other causes No Not Applicable

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

S.No. Information/Checklist confirmation

Yes/No Details thereof (with approximate quantities/ rates,

wherever possible) with source of

information data

4.1 Spoil, overburden or quarry wastes

Yes Waste generation (O.B. consisting of soil and weathered rock) from

the mine for the life of mine is 6,76,939 tonnes (4,230 t/month) Waste will be disposed to

temporary dump initially and Backfilling at later stage.

4.2 Municipal waste (domestic and or commercial wastes)

Yes Domestic waste (solid waste, food waste and other PVC packets) will be generated, which shall be

disposed into waste bins and disposed.

4.3 Hazardous wastes (as per Hazardous Waste management Rules)

Yes The spent oil from mine machinery and transport vehicles.

4.4 Other industrial process wastes No No other industrial process wastes

will be generated during mining activities.

4.5 Surplus product No No surplus product will be

produced.

4.6 Sewage sludge or other sludge

from effluent treatment

No Domestic sewage generated will be

treated in the septic tanks followed by disposal in soak pits. No effluent

will be generated from the mining operations.

4.7 Construction or demolition

wastes

No Neither any construction of

permanent structure nor any demolition is contemplated.

4.8 Redundant machinery or equipment

Yes Redundancy of machinery or equipment, if any, will be disposed

through authorized recyclers/agencies.

4.9 Contaminated soils or other materials

No No contaminated soil or other materials are envisaged.

4.10 Agricultural wastes No No agriculture waste will be

produced. No agriculture waste will be produced.

4.11 Other solid wastes No Not Applicable

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

S.No. Information/Checklist confirmation

Yes/No Details thereof (with approximate quantities/ rates,

wherever possible) with source of information data

5.1 Emissions from combustion of

fossil fuels from stationary or mobile sources

Yes Burning of Diesel trucks and

compressors will generate gaseous pollutants.

5.2 Emissions from production processes

Yes Fugitive Dust is the main pollutant, which will be generated

mainly from mining operations which will be controlled by water sprinkling

5.3 Emissions from materials handling including storage or

transport

Yes There will be fugitive emissions generated during material

handling, transportation, loading and unloading etc.

5.4 Emissions from construction activities including plant and equipment

Yes Temporary emission (fugitive dust) during construction.

5.5 Dust or odours from handling of materials including construction

materials, sewage and waste

Yes There will be fugitive emissions generated during material

handling, transportation, loading and unloading

5.6 Emissions from incineration of No Incineration of waste is not

waste envisaged.

5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris)

No Not involved.

5.8 Emissions from any other sources No Not Applicable

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

S.No. Information/Checklist confirmation

Yes/ No

Details thereof (with approximate quantities/ rates, wherever possible) with source

of information data

6.1 From operation of equipment

e.g. engines, ventilation plant, crushers

Yes From operation of compressor and

jack hammer. Source emission of 90 dB(A)

expected from above

6.2 From industrial or similar processes

No The present activity is open cast mining hence noise levels from of

industrial activities is nil

6.3 From construction or demolition No No Construction or demolition is

involved.

6.4 From blasting or piling Yes Noise and vibration due to blasting

6.5 From construction or operational traffic

Yes Operational traffic

6.6 From lighting or cooling systems No Not envisaged

6.7 From any other sources No No other source except the

mentioned above.

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

S.No. Information/Checklist

confirmation

Yes/No

Details thereof (with approximate quantities/rates, wherever possible) with source of

information data

7.1 From handling, storage, use or

spillage of hazardous materials

Yes Strom water runoff from stockpiles

and dump yards carrying silts may pollute the water bodies.

7.2 From discharge of sewage or other effluents to water or the land (expected mode and place

of discharge)

No Not Applicable

7.3 By deposition of pollutants

emitted to air into the land or into water

No Not Applicable

7.4 From any other sources No None

7.5 Is there a risk of long term build

up of pollutants in the environment from these sources?

No There is no risk long term buildup

of pollutants in the environment from the mining operations.

8. Risk of accidents during construction or operation of the Project, which

could affect human health or the environment

S.No. Information/Checklist confirmation

Yes/No Details thereof (with approximate quantities/ rates,

wherever possible) with source of information data

8.1 From explosions, spillages, fires etc from storage, handling, use

or production of hazardous substances

Yes Blasting operation

8.2 From any other causes No None

8.3 Could the project be affected by natural disasters causing

environmental damage (e.g. floods, earthquakes, landslides,

cloudburst etc)?

No Zone-II There is no history of flood,

earthquake, cloud burst and landslide reported so far.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

S.No. Information/Checklist confirmation

Yes/No Details thereof (with approximate quantities/ rates,

wherever possible) with source of information data

9.1 Lead to development of supporting facilities, ancillary development or development

stimulated by the project which could have impact on the

environment e.g.: • Supporting infrastructure

(roads, power supply, waste or waste water treatment, etc.)

• housing development • extractive industries • supply industries

• other

Yes Improve socio-economic status of villages around the mine

area

Benefit local people due to

employment round the year

Improvements in the

Educational facilities

Provisions of Health facilities

9.2 Lead to after-use of the site,

which could have an impact on the environment

Yes Greenbelt will be developed

9.3 Set a precedent for later developments

Yes Community development activities

9.4 Have cumulative effects due to

proximity to other existing or planned projects with similar

effects

No Not Applicable

(II) ENVIRONMENTAL SENSITIVITY

S.No. Areas Name/

Identity

Aerial distance

(within 15 km.) in KmProposed project location boundary

1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value

Gauraram RF Bompally RF Mothkur RF Mujaithapur RF Kulkacherla RF

Tirumalapur RF

7.6 km – WNW 7.6 km – NNE 6.1 km – ENE 6.2 km – E 5.8 km – E 7.0 km - E

2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains,

forests

(Near Doma Village ) Vagu (Near Ainapur

Village ) Cheruvu

– 3.6 km – N – 0.2 km – N

3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration

No None

4 Inland, coastal, marine or underground waters

No None

5 State, National boundaries No Telangana – Karnataka –

33.0 km - W

6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas

National Highway (NH-44) connecting Secunderabad – Tandur The State Highway (SH-4) connecting Pargi - Kodangal,

35.59 km – E 12.7 km - NNE

7 Defense installations No None

8 Densely populated or built-up area No Mahbubnagar

37.7km - SE

9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities)

No None

10 Areas containing important, high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, quarryrals)

No None

11 Areas already subjected to pollution or environmental damage (those where existing legal environmental standards are exceeded)

No None

12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

Zone-II There is no history of flood, earthquake, cloud burst and landslide reported so far.

None

“I hereby give under taking that the data and information given in the

application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is

found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.

Date: 15.02.2019 Place: Hyderabad

Signature of the Applicant

(Project proponent/ Authorized signatory)

Name Sri S. Ravi

Designation Lessee

Address Plot No: 6, Road No 51

Silent Lake Valley, Jubilee Hills, Hyderabad

REVISED

PRE-FEASIBILITY REPORT

Of

Quartz & Feldspar Mine (ML Area: 56.68 Ha)

Bandivankacharla Village, Kulkcherla Taluk, Rangareddy District, Telangana State

For Production of 3,00,000 Tonnes /Annum (TPA) of

Quartz and Feldspar With Total Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA + Waste : 50,432 TPA)

Of

Sri S. Ravi

February, 2019

1

Table of Contents

1. Executive Summary

2. Introduction Of The Project/ Background Information

3. Project Description

4. Site Analysis

5. Planning Brief

6. Proposed infrastructure

7. Rehabilitation and resettlement (R & R) Plan

8. Project schedule & Cost Estimates

9. Analysis of proposal (Final Recommendations)

Figure

Table-1 Salient features of project

Figure

Fig-1 Location Map

Fig-2 Key Map

Fig-3 Topographical Map

Fig-4 Surface Plan

Annexures

Annexure –1 Industries and Commerce (Mines-I) Department letter

Annexure – 2 lease Transfer proceeding Letter

2

1.0 EXECUTIVE SUMMARY

The Mining Lease was granted for Quartz and Feldspar Minerals over an

extent of 56.68 Ha in Sy. No.415 of Bandivankacharla Village, Kulkcherla

Taluk, Rangareddy District, Telangana State (formerly Andhra Pradesh) in

favour of Kum. G.L. Nanditha for a period of 20 years and the mining lease

is valid upto 01.12.2022.

Subsequently Kum. G.L. Nanditha has applied for transfer of Mining Lease

in favour of Sri S. Ravi

The Director of Mines & Geology has recommended for transfer of Mining

Lease by Kum. G.L. Nanditha for Quartz & Feldspar Mines and transferred

the lease in favour of Sri S. Ravi for Quartz and Feldspar Minerals over an

extent of 56.68 Ha in Sy. No.415 of Bandivankacharla Village, Kulkcherla

Taluk, Rangareddy District, Telangana State (formerly Andhra Pradesh) vide

G.O.Ms. No.292 dated 31.10.2008 which is valid upto 02.12.2022.

Sri S. Ravi intends to produce 3,00,000 Tonnes /Annum (TPA) of Quartz

and Feldspar with Total Excavation of 3,50,432 TPA (Quartz and Feldspar:

3,00,000 TPA + Waste : 50,432 TPA) from the lease area and applied to

Ministry of Environment and Forests for Terms of Reference. Ministry has

provided TOR to carry out an Environmental Study vide their MOEF Lr. No.

J-11015/05/2010-IA.II [M] dated 09th March 2010.

The Public Hearing was conducted on 04.01.2013. The Final EIA was

submitted to the Ministry on 10.04.2013.

The Project was considered during 11th Meeting of the Reconstituted Expert

Appraisal Committee for Environmental Appraisal of Mining Projects (Non-

Coal) of the Ministry of Environment and Forests on 25th September 2013.

The Committee noted that the mine was operating from 2010 to 2012

without obtaining Environmental Clearance and Project Proponent has

violated the provisions of Environmental Protection Act 1986 and deferred

the Proposal and asked to submit the following information vide letter no. J-

11015/05/2010-IA.II [M] Dt. 31.12.2013.

1. The details of preventive measures to be undertaken for occupational

health of the workers

3

2. Site specific conservation plan for the Scheduled-I species reported in

the study area

3. Copy of Approved mining scheme for the period 2013-2018.

Further MOEFCC has issued a letter no. J-11015/05/2010-IA.II [M] Dt.

31.12.2013. stating that (1) The matter relating to violation has been put to

the Board of Directors of the Company or to the Managing Committee, for

consideration of your environment related policy/plan of action and a

written commitment in the form of a formal resolution is submitted to MoEF

to ensure that violations of the Environment (Protection) Act will not be

repeated (2) The State Government has initiated credible action on the

violation against you under the Environment (Protection) act 1986 and

evidence provided to MoEF of the action taken (3) You close down your

mining operations with immediate effect. And also stated that While

communications against (1) & (2) have been issued separately, these

directions are being issued to ensure (3); and instructed Sri S. Ravi to stop

the mining operations.

Against above, Sri S. Ravi has

1. Submitted written commitment that violations of the Environment

(Protection) Act will not be repeated as Affidavit on 100/- Rupees bond

paper

2. A letter was submitted to principle secretary, Govt. of Telangana for

initiation credible action on 25.02.2015. The process was initiated and

the case was filed in the court of Judicial First Class Magistrate, Pargi.

3. Inspection report from Department of Mines and Geology vide letter

no. 3540/M/2008 Dt. 18.06.2015 states that mining operation was

stopped.

Sri S. Ravi has submitted the reply to the above points in hard copy to

MoEF & CC, Non- Coal Mining Committee on 17.01.2017. Against this

MOEF & CC vide letter no. J-11015/05/2010-IA.II [M] dated 17.07.2017

instructed Sri S. Ravi to submit online the proposal afresh as violation case

submitting the following information.

1. Certificate stating that mining activity of the said mine has

been stopped (with date) and CTO/occupancy Certificate has been

revoked, duly certified by the State Pollution Control Board

4

Submission of Sri S. Ravi: Inspection report from Department of

Mines and geology vide letter no. 3540/M/2008 Dt. 18.06.2015 states

that mining operation was stopped.

2. Detailed statement of Past production since inception/after

1994 to till-date, duly certified by the Department of Mines and

Geology

Submission of Sri S. Ravi: S. Ravi Approached DMG for the same

3. Details of violation proceedings, if any, already initiated or

completed by the State Government in the instant proposal with

supporting documents

Submission of Sri S. Ravi: A letter was submitted to Principle

Secretary, Govt. of Telangana for initiation credible action on

25.02.2015. The process was initiated and the case was filed in the

court of Judicial First Class Magistrate, Pargi.

4. Details of earlier applications made to MoEF & CC, if any, for

grant of EC.

Submission of Sri S. Ravi: File no. J-11015/05/2010-IA.II [M]

Since Sri S. Ravi has already submitted the documents, which are at an

advanced stage of consideration, at this stage when MOEF instructed to

submit afresh on 17.07.2017 letter, Sri S. Ravi has approached the Hon’ble

High Court of Judicature at Hyderabad. Sri S. Ravi has obtained court order

dated 22.09.2017 directed Ministry of Environment, Forests and Climate

Change to receive our application without prejudice to their contention that,

in standing order dated 14.03.2017. Later the proposal was submitted on

16.11.2017 under violation vide Proposal No. IA/TG/MIN/68696/2017.

Since the proposal under violation was submitted on 16.11.2017, we have

resubmitted the proposal under violation in compliance with MoEF & CC

Office Memorandum Dated 16th March, 2018 vide proposal no

IA/TG/MIN/73867/2018 dated 31.03.2018. EAC during the appraisal and

vide ADS dated 07.02.2019 has instructed Project Proponent to submit the

Revised Form – I incorporating the correct name of the lessee as Sri S. Ravi

along with inclusion of total material handling in the proposal. The subject

report is revised PFR prepared incorporating the observations of EAC.

5

The details of the mining lease are given below:

Project Quartz & Feldspar mine

Extent of Lease Area Mine lease area : 56.68 Ha

Location of the Mine Sy. No. 415p, Bandivankacharla Village, Kulkcherla Taluk, Rangareddy District,

Telangana State.

Registered Office Sri Seelam Ravi Chandra

Plot No:6, Road No 51, Silent Lake Valley, Jubilee Hills,, Hyderabad 040 23555183

Designation (Owner /Partner/ CEO

Sri S. Ravi Lessee

Period of mining lease 20 years

Present land use Total mining lease area is Govt. revenue land (56.68Ha). The ML Area is as saddle shaped hillock with

radial Slopes. The highest contour of 160m RL is traversing in central portion of the lease area and lowest contour level is 103 RL is at North-Eastern

of lease area. The general strike direction is almost North South and dipping easterly with

almost vertical dip.

Type of Activity Open Cast Mechanized mining

Mineable reserves & life of mine

46,29,946 tons Life of mine would be 16 years

Waste generation Waste generation (O.B. consisting of soil and weathered rock) from the mine for the life of mine

is 676939 tonnes (4230 t/month) Waste will be disposed to temporary dump initially and Backfilling at later stage

Conceptual landuse Conceptually, about 21.072ha will be mined out area. 14.572 Ha will be backfilled.

Manpower Requirement About 33 persons will be employed in the mine.

Water requirement Water requirement will be 18 m3/day and the same will be sourced from Ground Water

Project Cost Rs 150 Lakhs

6

2. INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION:

(i) Identification of project and project proponent. In case of mining

project, a copy of mining lease / letter of intent should be given.

Sri S. Ravi, Lessee of Quartz & Feldspar mine over an extent of 56.68

Hectares Sy. No.415/P of Bandivankacharla Village, Kulkcherla Taluk,

Rangareddy District, Telangana State.

Earlier the lease was granted in favour of Kum. G.L. Nanditha for a period

of 20 years by Industries and Commerce (Mines-I) Department vide G.O.Ms.

No.292 dated 31.10.2008 which is valid upto 02.12.2022 (Enclosed as

Annexure - 1).

Subsequently, the lease was transferred in favour of Sri S. Ravi from Kum.

G.L. Nanditha vide proceedings No. 3540/M/2008 Dated 21.01.2009

(Enclosed as Annexure - 2).

Sri S. Ravi intends to produce 3,00,000 Tonnes /Annum (TPA) of Quartz

and Feldspar With Total Excavation of 3,50,432 TPA (Quartz and Feldspar:

3,00,000 TPA + Waste : 50,432 TPA). from the lease area and applied to

Ministry of Environment and Forests for Terms of Reference. Ministry has

provided TOR to carry out an Environmental Study vide their MOEF Lr. No.

J-11015/05/2010-IA.II [M] dated 09th March 2010.

The Public Hearing was conducted on 04.01.2013. The Final EIA was

submitted to the Ministry on 10.04.2013.

The Project was considered during 11th Meeting of the Reconstituted Expert

Appraisal Committee for Environmental Appraisal of Mining Projects (Non-

Coal) of the Ministry of Environment and Forests on 25th September 2013.

The Committee noted that the mine was operating from 2010 to 2012

without obtaining Environmental Clearance and Project Proponent has

violated the provisions of Environmental Protection Act 1986 and deferred

the Proposal and asked to submit the following information vide letter no. J-

11015/05/2010-IA.II [M] Dt. 31.12.2013.

1. The details of preventive measures to be undertaken for occupational

health of the workers

7

2. Site specific conservation plan for the Scheduled-I species reported in

the study area

3. Copy of Approved mining scheme for the period 2013-2018.

Further, MOEFCC has issued a letter no. J-11015/05/2010-IA.II [M] Dt.

31.12.2013. stating that (1) The matter relating to violation has been put to

the Board of Directors of the Company or to the Managing Committee, for

consideration of your environment related policy/plan of action and a

written commitment in the form of a formal resolution is submitted to MoEF

to ensure that violations of the Environment (Protection) Act will not be

repeated (2) The State Government has initiated credible action on the

violation against you under the Environment (Protection) act 1986 and

evidence provided to MoEF of the action taken (3) You close down your

mining operations with immediate effect. And also stated that While

communications against (1) & (2) have been issued separately, these

directions are being issued to ensure (3) and instructed Sri S. Ravi to stop

the mining operations.

Against above, Sri S. Ravi has

1. Submitted written commitment that violations of the Environment

(Protection) Act will not be repeated as Affidavit on 100/- Rupees bond

paper

2. A letter was submitted to principle secretary, Govt. of Telangana for

initiation credible action on 25.02.2015. The process was initiated and

the case was filed in the court of Judicial First Class Magistrate, Pargi.

3. Inspection report from Department of Mines and Geology vide letter

no. 3540/M/2008 Dt. 18.06.2015 states that mining operation was

stopped.

Sri S. Ravi has submitted the reply to the above points in hard copy to

MoEF & CC, Non- Coal Mining Committee on 17.01.2017. Against this

MOEF & CC vide letter no. J-11015/05/2010-IA.II [M] dated 17.07.2017

instructed Sri S. Ravi to submit online the proposal afresh as violation case

submitting the following information.

5. Certificate stating that mining activity of the said mine has

been stopped (with date) and CTO/occupancy Certificate has been

revoked, duly certified by the State Pollution Control Board

8

Submission of Sri S. Ravi: Inspection report from Department of

Mines and geology vide letter no. 3540/M/2008 Dt. 18.06.2015 states

that mining operation was stopped.

6. Detailed statement of Past production since inception/after

1994 to till-date, duly certified by the Department of Mines and

Geology

Submission of Sri S. Ravi: SRS Approached DMG for the same

7. Details of violation proceedings, if any, already initiated or

completed by the State Government in the instant proposal with

supporting documents

Submission of Sri S. Ravi: A letter was submitted to principle

secretary, Govt. of Telangana for initiation credible action on

25.02.2015. The process was initiated and the case was filed in the

court of Judicial First Class Magistrate, Pargi.

8. Details of earlier applications made to MoEF & CC, if any, for

grant of EC.

Submission of Sri S. Ravi: File no. J-11015/05/2010-IA.II [M]

Since Sri S. Ravi has already submitted the documents, which are at an

advanced stage of consideration, at this stage when MOEF instructed to

submit afresh on 17.07.2017 letter, Sri S. Ravi has approached the Hon’ble

High Court of Judicature at Hyderabad. Sri S. Ravi has obtained court order

dated 22.09.2017 directed Ministry of Environment, Forests and Climate

Change to receive our application without prejudice to their contention that,

in standing order dated 14.03.2017. Later the proposal was submitted on

16.11.2017 under violation vide Proposal No. IA/TG/MIN/68696/2017.

Since the proposal under violation was submitted on 16.11.2017, we are

here with resubmitting the proposal under violation in compliance with

MoEF & CC Office Memorandum Dated 16th March, 2018.

(ii) Brief Description of the Nature of the Project.

Project is Quartz and feldspar over an extent of 56.68 Ha. It is proposed to

produce 3,00,000 Tonnes /Annum (TPA) of Quartz and Feldspar with Total

9

Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA + Waste :

50,432 TPA)by means of Open cast -Mechanized mining method. The

material is transported for crushing and screen plant by tippers.

(iii) Need For The Project And Its Importance To The Country.

The mining industry will improve the economic status of the people in and

around the lease area. Continued mining activities, will benefit the local

people due to job opportunities created.

Quartzite deposits in this area form mineral wealth, as the ore is major raw

material for the manufacture of Glass and Concrete Making. Since, the

Quartzite ore reserves of this area are economically viable, their proper

utilization will improve the economic status of the people and the Country

(iv) Demand– Supply Gap

Nature and occurrence of ROM generated at this mine is more suitable for

making glass as fill and to create molds in industry processing, water-

filtration, glass manufacture, industrial casting, sand blasting, to produce

concrete, adding texture to slick roads.

(v) Imports Vs Indigenous Production.

The Quartz & Feldspar produced will be transported directly to the

consumer/buyer after crushing and screening with required sizes.

(vi) Export Possibility.

No exports of Quartz & Feldspar are proposed.

(vii) Domestic / Export Markets

The Quartz & Feldspar produced will be transported directly to the

consumer/ buyer after crushing and screening with required sizes.

(viii) Employment Generation (Direct and Indirect) Due to Project.

The employment potential of the project would be about 33 persons.

10

3. PROJECT DESCRIPTION:

(i) Type of Project (including interlinked and interdependent project,

if any)

Project is Quartz and feldspar over an extent of 56.68 Ha. It is proposed to

produce 3,00,000 Tonnes /Annum (TPA) of Quartz and Feldspar With Total

Excavation of 3,50,432 TPA (Quartz and Feldspar: 3,00,000 TPA + Waste :

50,432 TPA). It is an opencast mining for quartz and feldspar production

through conventional method. The ore is used for the manufacture of Glass

and Concrete Making.

It is categorized as Category ‘A’ Project under Schedule 1(a) hence it

necessitates obtaining Environment Clearance from Ministry of

Environment, Forest and Climate Change (MoEF & CC).

(ii) Location (map showing general location, specific location and

project boundary & project site specific layout) with coordinates.

Sri S. Ravi, Lessee of Quartz & Feldspar mine over an extent of 56.68

Hectares Sy. No.415/P of Bandivankacharla Village, Kulkcherla Taluk,

Rangareddy District, Telangana State.

The Mining Lease Area is a part of the Survey of India Toposheet No.

56/G/16. The site falls between 1) 17°01'50.01"N- 77°49'22.73"E 2)

17°01'51.61"N- 77°49'30.88"E 3) 17° 2'45.83"N- 77°49'29.33"E 4) 17°

2'41.41"N- 77°49'19.38"E, North and East Longitude with an average

altitude of 625 m above MSL. The location map of the Mining Lease Area is

shown in Fig – 1.

Nearest railway line connecting Secunderabad - Tandur of South Central

Railway line, at a distance of 25.0 km to Northern direction from the Mining

Lease Area. Key map showing the location of various features around the

Mining Lease Area is shown in Fig – 2. Mahbubnagar is major town at a

distance of 37.7 km in SE direction.

The National Highway (NH-44) connecting Hyderabad - Mahbubnagar, at a

distance of about 35.5 km in Eastern direction, The nearest railway station

is Mailaram at 25.0 km in Northern direction.

The State Highway (SH-4) connecting Pargi - Kodangal, at a distance of

about 12.7 km in NNE direction,

11

LOCATION MAP

FIG - 1

TELANGANA

N

ADILABAD

KOMARAM BHEEMNIRMAL

NIZAMABAD

JAGITYAL

KAMAREDDY

KARIMNAGAR

PEDDAPALLE

JAYASHANKAR

SANGAREDDY

RANGAREDDY

MAHABUBNAGAR

WANAPARTHY

NAGARKURNOOL

NALGONDA

KHAMMAM

KOTHAGUDEM

WARANGAL

YADADRI

SHAMSHABAD

HYDERABAD

MEDAK

SIDDIPET

INDIA

OTHER ROAD

LEGEND

DISTRICT BOUNDARY

MAJOR ROAD

NATIONAL HIGHWAY

RAILWAY LINE

RIVER

STATE BOUNDARY

DISTRICT HEAD QUARTER

MAJOR TOWN

OTHER TOWN

563

MINING LEASE AREA

MANCHERIAL

KOMARAM BHEEM

MANCHERIAL

RANGA REDDY DISTRICT

Venkatapuram

Mailwarram

Miryan

Tandur

ShahabadPargi

Markal

Nancherla

Muhammadabad

Doma

Morangpalli

Peddamal

Elal

Kotepalli

Patlur

Marpalli

Changomal

Chevella

Shankarpalli

Vikarabad

Ibrahimpatanam

Yacharam

Maisaram

BolaramMaula Ali

Medchal

HYDERABAD

Tukkuguda

SecunderabadGundipet

Golkonda

MINING LEASE AREA

7

7

9

12

13

There are no wild life sanctuaries, national parks, elephant/tiger reserves

within 10km radius of the study area.

Nearest Settlements from the Mining Lease Area

Bandivankacharla – 1.3 km – E

Govindnaik Tanda – 0.2 km – S

Nearest Reserved Forests from the Mining Lease Area

Gauraram R F – 7.6 km – WNW

Bompally R F – 7.6 km – NNE

Mothkur R F – 6.1 km – ENE

Mujaithapur R F – 6.2 km – E

Kulkacherla R F – 5.8 km – E

Tirumalapur R F – 7.0 km - E

Salient features of Mining Lease Area are given in Fig - 3 and Table – 1

shows the study area of 10 km radius around the Mining Lease Area

(iii) Details of alternate sites considered and the basis of selecting

the proposed site, particularly the environmental considerations gone

into should be highlighted.

No alternate sites were considered as the project is mineral specific.

(iv) Size or Magnitude of operation.

It is proposed to mine about 3,00,000 Tons/annum of Quartz and Feldspar.

(v) Project Description with Process details (a schematic diagram/

Flow chart showing the project layout, components of the project etc.

should be given.

Type of Mining

Mining is proposed to work this deposit by open cast mechanized method.

The southern part of strike length of quartz reef zone will be opened and

faces will be advanced across and along the strike in benches of 6m height

and minimum bench width of 6m. The faces shall be moved from hanging

wall side to footwall side, In the process of maintaining benches, the clay as

side burden shall be stripped during movement of faces. The ore is

mechanically loaded into the tippers and sent to the crushing plan't which is

located outside the mining lease.

14

15

TABLE – 1

SALIENT FEATURES OF THE MINING LEASE AREA

Feature Details

Altitude 625m above msl

Longitude & Latitude 1) 17° 1'50.01"N- 77°49'22.73"E 2) 17° 1'51.61"N-

77°49'30.88"E 3) 17° 2'45.83"N- 77°49'29.33"E 4) 17° 2'41.41"N- 77°49'19.38"E,

Village, Tehsil, District, State

Bandivankacharla Village, Kulkcherla Taluk, Rangareddy District, Telangana.

IMD Station Hyderabad – 80km - ENE

Max. Temp. 0C 45.5

Min. Temp. 0C 6.1

Relative Humidity, % 23 - 82

Annual rainfall 812.5 mm

Topography Hilly Terrain

Nearest water bodies (Near DOMA Village ) Vagu – 3.6 km – N

(Near Ainapur Village ) Cheruvu – 0.2 km – N

Nearest Highway National Highway (NH-44) connecting Secunderabad –

Tandur – 35.59 km – E

The State Highway (SH-4) connecting Pargi - Kodangal, - 12.7 km - NNE

Nearest Railway station

Mailaram – 25.0km - N

Nearest Industries None within 10 km Radius

Nearest Villages Bandivankacharla – 1.3 km – E

Govindnaik Tanda – 0.2 km – S

Nearest Town Mahbubnagar – 37.7km - SE

Inter State Boundary Telangana – Karnataka – 33.0 km - W

National Parks/ Bird Sanctuaries

None within 10 km Radius

Nearest Port Krishnapatnam Port (Nellore )- 395.0 km – SE

Nearest Air port Rajiv Gandhi International Airport (Shamshabad) Hyderabad – 66.0 km – ENE

Nearest Forest Gauraram R F – 7.6 km – WNW Bompally R F – 7.6 km – NNE

Mothkur R F – 6.1 km – ENE Mujaithapur R F – 6.2 km – E Kulkacherla R F – 5.8 km – E

Tirumalapur R F – 7.0 km - E

Historical places None within 10 km Radius * All distances mentioned in the above table are aerial distances.

16

FLOW SHEET OF CRUSHING AND SCREENING PLANT WITH MATERIAL BALANCE

a) Brief Description (Method of working)

The Method of mining is open cast mechanized mining method using 115

mm dia. DTH Drilling and blasting. The blasted material shall be loaded into

the tippers and sent to crushing plant (located outside the Ml Area) & stock

by the help of excavator. The same excavator will also be used for handling

of waste/ rejection. Wheel loaders will be utilized for feeding to the plant

from stock and loading for dispatch as and when required.

Mining of Ore

The basic operations involved in the mining of ore are mechanically. The

interstitial waste is directly loading into tippers and transportation to the

reject dump yard. In the ore zone, the ore is directly loaded in the tippers

trucks and is dispatched to the designated places. The oversize boulders are

separately loaded and transported to SGMD stack yard for breaking

The system of working shall be mechanized opencast mining method. The

various operations involved are.

a) Drilling- 115mm dia DTH drill shall be used for the purpose. The

burden and spacing shall be kept 3 m and 3.5 m respectively.

b) Blasting - To blast the drilled holes slurry explosives and Ammonical

Nitrate Fuel Oil mixture shall be used

c) After blasting the loose materia1 shall be loaded by excavators into

tippers

17

d) The tippers after loading shall transport the material to the crushing

and screening plant, which is located outside the mining lease

e) The sub grade material if available shall be transported and stacked

separately in the location already marked and shall be blended

whenever required

f) The rejects shall be transported and clamped separately m the rejection

dumping yard

Drilling

Type Nos. Dia of Hole mm

Make Motive Power

DTH Drill 2 115 Atlas copco Compressed Air

Blasting

Multiple rows of holes shall be blasted using milli-second delay detonators

tubes.

The holes shall be blasted using 25 m, 50 m and 100 m cord relays and

17m/25m/42m so that charge per delay would not exceed the permissible

limits

It is preferred to use 10% High explosives of slurry cartridge of 83 mm as a

prime charge and 90% Ammonium Nitrate fuel oil mixture.

Powder factor shall be avg. 3.50 t/kg of explosives in the entire strata to be

blasted

Explosives material Calculation for blasting (Charge/hole)

Height of the bench = 6.0 m

Hole depth = 6.0 m

Burden = 3.0 m

Spacing = 3.5 m

Bulk Density = 2.5 t/m3

The maximum material to be blasted per annum shall be = 3.41,689 tonnes

Burden x Spacing x Depth x Bulk Density

Quantity broken/hole = 3 m x 3.5 in x 6.0 m x 2.5 tonnes / m x 80%

= 126.0 tonnes / Hole

Powder factor = 3.50 tonnes /kg for a good fragmentation

Explosives required per hole= 126 tonnes/3.50 tonnes = 36 kg/hole

18

Total quantity of Explosive required = 341689/3.50 = 97625 Kg

= 98 tonnes

ANFO @ 90% of 98 tonnes = 88.20 tonnes

High Explosives required = 9.80 tonnes

Total = 98.00 tonnes

Secondary Blasting

Secondary blasting will be to the tune of 10 % of the total blasted quantity

for reducing the size of the boulders to -300 mm which can be fed to the

plant.

Storage of explosives

Magazine is proposed in the eastern corner of the lease boundary. The

capacity of the same will be enhanced and the explosive van will be used to

bring the explosives to cater to the need of mining.

Removal Of Over Burden

The Over/side burden constitutes of shale and waste within quartz is

ferruginous shale horizon. The soft waste will be separated from the ore and

directly excavated and transported to the designated site earmarked for the

purpose.

Extent of Mechanization

Open cast mechanized mining operation will be adopted. The following

mentioned mine machinery will be deployed.

LIST OF MACHINERY

S. No. Type of machine No

1 Excavator 2

2 Dumpers 6

3 Drillers 2

4 Water Tanker 1

5 Rock breaker 1

6 Wheel Loader 1

Stock yard

After completion of dressing, the quartz will be transported to stock yard.

19

(vi) Raw Material / Consumables Required along with estimated

quantity, likely source, marketing area of final product, mode of

transport of raw material and finished product

No raw materials are required. Consumables and finished goods will be

transported by means of road transport only.

(vi) Resource optimization/ recycling and reuse envisaged in

project, if any, should be briefly outlined.

Waste generated from the mined out area will be concurrently backfilled.

(vii) Availability of water, it’s source, Energy/power requirement and

source should be given.

Water:

The water environment will not get disturbed by the mining operations.

Water requirement will be 18 m3/day and the same will be met from ground

water.

Energy and Power Requirement and Source

Power requirement for illumination will be met from grid.

(ix) Quantity of wastes to be generated (liquid and solid) and scheme for

their management / disposal.

Waste generation from the mine is estimated to be about 82,950 tonnes

during the scheme period.

(x) Schematic representations of the feasibility drawing which give

information of EIA purpose.

The subject project is mining of Quartz & Feldspar with production

capacity of 300000 TPA from mining lease area of 56.68 Ha. Based on

the threshold levels as per MoEF& CC Notification “S.O. 1533” Dated

14.09.2006 and amendment thereof the subject project is categorised as

Category ‘A’ listed under Schedule 1(a) of SO 1533.

20

21

4. SITE ANALYSIS

i) Connectivity

Nearest railway line connecting Secunderabad - Tandur of South Central

Railway line, at a distance of 25.0 km to Northern direction from the Mining

Lease Area.

The National Highway (NH-44) connecting Hyderabad - Mahbubnagar, at a

distance of about 35.5 km in Eastern direction,

The nearest railway station is Mailaram at 25.0 km in Northern direction.

The State Highway (SH-4) connecting Pargi - Kodangal, at a distance of

about 12.7 km in NNE direction,

ii) Land Form, Land use and Land Ownership

Total mining lease area is Govt. Revenue Land (56.68 ha).

The detailed land use is given below:

LAND USE BREAKUP

S. No LAND PARTICULARS PRESENT USE CONCEPTUAL

PERIOD AREA IN HA.

1 Area under Excavation 0.5200 21.072 (14.572

backfilling)

2 Storage of Top Soil Nil 0.0800

3 Overburden Dump 0.2000 6.4520

4 Mineral storage 0.1520 0.1520

5 Infrastructure (Workshop,

Administrative Buildings)

0.1000 0.1000

6 Roads 0.2540 1.0000

7 Greenbelt Nil 3.5000

8 Env. Protective measures Nil 1.0000

9 Mineral Separation plant 0.4047 -

10 Area Cultivated 7.0172 -

11 Dump Area Plantation Nil 3.0000

12 Others (Unutilized Area) 48.0321 20.2240

Total 56.6800 56.6800

22

The ML Area is as saddle shaped hillock with radial Slopes. The highest

contour of 160m RL is traversing in central portion of the lease area and

lowest contour level is 103 RL is at North-Eastern of lease area. The general

strike direction is almost North South and dipping easterly with almost

vertical dip. Surface Plan is enclosed as Fig – 4.

FIG – 4 SURFACE PLAN

130

133

136

139

142

148

157

151

151

148

145

141

139

139

136

133

130

127

124

121

118

115

112

109

106

103

118

124

127

133

139

S5

GC

P-2

N1

01

' 50

.01"

E 7

49

' 22.7

3"

N1

01

' 51

.61"

E 7

49

' 30.8

8"

N1

02

' 41

.41"

E 7

49

' 19.3

8"

GC

P-1

GC

P-3

MN

W

S

E

115

118

121

124

130

133

Cru

shin

g &

Scr

ee

nin

g

Pla

nt

LE

AS

E B

OU

ND

AR

Y

CO

NT

OU

R

LE

GE

ND RO

AD

MIN

E W

OR

KIN

GS

ST

RE

AM

S

TB

M

RL

=1

00

M

N2000

N1800

N1600

N1400

N1200

N1000

N800

N600

N400

N200

00

E200

E400

E600

E200

E400

E600

N2000

N1800

N1600

N1400

N1200

N1000

N800

N600

N400

N200

00

PR

OJE

CT

:

TIT

LE

:

SU

RF

AC

E E

PL

AN

FIG

- 4

CL

IEN

T :

Sri. S

. R

AV

I

Ba

nd

iva

nka

cha

rla

Vill

ag

e,

Ku

lkch

erl

a M

an

da

l,

Ra

ng

aR

ed

dy

Dis

tric

t, T

ela

ng

an

a.

Q

UA

RT

Z &

F

EL

DS

PA

R M

IN

E - 5

6.6

8 H

a

23

iii) Existing land use pattern (agriculture, non-agriculture, forest,

water bodies (including area under CRZ), shortest distances from the

periphery of the project to periphery of the forests, national park, wild

life sanctuary, eco sensitive areas, water bodies (distance from the HFL

of the river), CRZ, in case of notified industrial area, a copy of the

Gazette notification should be given.

Total area of 56.68 Ha is Govt. waste land

There are no wild life sanctuaries, national parks, elephant/tiger reserves

within 10km radius of the study area.

Nearest Reserved Forests from the mining lease area

Gauraram R F – 7.6 km – WNW

Bompally R F – 7.6 km – NNE

Mothkur R F – 6.1 km – ENE

Mujaithapur R F – 6.2 km – E

Kulkacherla R F – 5.8 km – E

Tirumalapur R F – 7.0 km - E

iv) Existing infrastructure

None within the mining lease.

v) Soil classification

The area is covered with thin soil of thickness varying from 0.1 to 0.20 m in

the slopes. The area is mixed with quartz float and pieces of schist rock.

About 4200 tonnes of top soil is likely to be generated in this scheme period

which is preserved and is used during plantation on the dumps.

vi) Climatic data from Secondary Sources

The area is hot during most part of the year. The average annual rainfall on

the area is around 680 mm per year. The highest and lowest temperature in

the lease area varies between 420 to 280 respectively. The drainage pattern

in the area is Sub-Dendritic in nature. The most of the lands in western side

of the lease are of cultivable nature and crops like paddy maize, jawar and

groundnut etc., are grown.

vii) Social infrastructure available.

The haul roads will be developed for carrying capacities by the waste

obtained from the mining/ extraction of ore. The approach roads are

sufficient to cater to the proposed production. The proposed project will

provide employment and benefits

24

CHAPTER – 5 PLANINIG BRIEF

5. PLANNING BRIEF:

i) Planning Concept (type of industries, facilities, transportation, etc.,)

town and country Planning / Development authority classification:

The subjected mine is the Quartz and Feldspar mine of Sri S. Ravi at

Bandivankacharla Village, Kulkcherla Taluk, Rangareddy District,

Telangana State in over an extent of 56.68 Ha. The present proposal is for

production of 3,00,000 TPA Quartz and Feldspar mineral.

ii) Population Projection:

Since there will not be any major influx of people from outside in this region

because of the project, there will hardly be any population explosion. Most of

the workers will be people from surrounding villages only.

A total of 33 persons will be employed for mining operations.

iii) Land use planning (breakup along with greenbelt etc.,)

The detailed conceptual land use is given below:

CONCEPTUAL LAND USE

S. No LAND PARTICULARS AREA IN HA.

1 Area under Excavation 21.072 (14.572

backfilling)

2 Storage of Top Soil 0.0800

3 Overburden Dump 6.4520

4 Mineral storage 0.1520

5 Infrastructure (Workshop,

Administrative Buildings)

0.1000

6 Roads 1.0000

7 Greenbelt 3.5000

8 Env. Protective measures 1.0000

9 Dump Area Planation 3.0000

10 Others (Unutilized Area) 20.2240

Total 56.6800

25

iii) Assessment of Infrastructure Demand ( Physical & Social):

The proposed will provide the direct employment to about 33 people in

addition there will be indirect employment to many more people, in the form

of contractual jobs, business opportunities, service facilities etc. This will

enhance the economic status of the area.

iv) Amenities /Facilities:

All the necessary infrastructure facilities such as office, Canteen, rest

shelters, drinking water, Medical facilities, transport and others will be

provided.

26

CHAPTER – 6 PROPOSED INFRASTRUCTURE

6. PROPOSED INFRASTRUCTURE:

(i) Industrial

No mineral processing technique will be adopted. The final product will be

transported directly to the consumer/ buyer after crushing and screening

with required sizes.

The ore/mineral will be accumulated by doing drilling & blasting, at once

excavation & loading will be commenced so that the effective cost saving of

the excavator will be done.

(ii) Residential

No residential facilities are proposed at mine site.

(iii) Greenbelt

7.5 m barrier zone along the mine boundary will be developed under

greenbelt in a phased manner.

(iv) Social Infrastructure

The mining activity carried out in the area rather has a positive socio-

economic impact upon the nearby human settlement as indirect

employment potential is created due to mining and allied activities in the

area. Apart from these, the company promotes health and education

awareness in the area time to time by organizing health and education

camps.

(v) Connectivity

Nearest railway line connecting Secunderabad - Tandur of South Central

Railway line, at a distance of 25.0 km to Northern direction from the Mining

Lease Area.

The National Highway (NH-44) connecting Hyderabad - Mahbubnagar, at a

distance of about 35.5 km in Eastern direction,

The nearest railway station is Mailaram at 25.0 km in Northern direction.

27

The State Highway (SH-4) connecting Pargi - Kodangal, at a distance of

about 12.7 km in NNE direction,

(vi) Drinking Water Management (Source and Supply of Water)

Water requirement for is 18 m3/day for drinking, dust suppression, and

Afforestation. The water requirement will be sourced from ground water.

(vii) Sewerage System

No wastewater generation except for domestic waste from toilet which will be

treated in septic tank followed by soak pit.

(viii) Solid Waste Management

Waste generation (O.B. consisting of soil and weathered rock) from the mine

for the life of mine is 6,76,939 tonnes (4230 t/month)

Waste will be disposed to temporary dump initially and Backfilling at later

stage

The non-mineralized area within the mining lease will be used as temporary

waste dump yard which will be rehandled for part backfilling of the mined-

out area at conceptual stage.

(ix) Power Requirement & Supply / Source.

Power requirement for illumination will be met from grid.

28

CHAPTER – 7 REHABILITATION AND RESETTLEMENT (R & R) PLAN

7.0 Rehabilitation and resettlement (R & R) Plan

i. Policy to be adopted (central / state) in respect of the project affected persons including home oustees, land oustees and landless labourers (a brief out line to be given).

The mine area does not cover any habitation. Hence the mining

activities do not involve any displacement of human settlement. No

public buildings, places, monuments etc., exist within the lease area

or in the vicinity. The mining operations will not disturb/relocate any

village.

CHAPTER – 8 PROJECT SCHEDULE & COST ESTIMATES

8.0 Project schedule & Cost Estimates

i. Likely date of start of construction and likely date of completion

(time schedule for the project to be given).

Mining operations will be commenced after obtaining EC, CFE, CFO and all

other regulatory clearances. Life of the mine @ 3,00,000 Tonnes /Annum

(TPA) of Quartz and Feldspar With Total Excavation of 3,50,432 TPA

(Quartz and Feldspar: 3,00,000 TPA + Waste : 50,432 TPA) for the proved

mineral reserve of 46,29,946 million tonnes would be 16 years.

ii. Estimated project cost along with analysis in terms of economic

viability of the project.

Project cost is estimated to be about Rs 150 Lakhs

CHAPTER – 9 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

9.0 Analysis of proposal (Final Recommendations)

i. Financial and social benefits with special emphasis on the benefit

to the local people including tribal population, if any, in the area.

Economic development of the region depends largely upon the nature

of activities undertaken in the surrounding region. Corporate

development invariably contributes towards acceleration of the

process of socio-economic upliftment of the rural society by means

of employment, health & study programme, medical camps etc.,

ANNEXURE - 1

ANNEXURE - 2