Redwood City School District Addendum No. 3 Taft Community School, Phase 1 Page 1 of 3 REDWOOD CITY SCHOOL DISTRICT TAFT COMMUNITY SCHOOL PHASE 1 ADDENDUM No. 3 Owner: Redwood City School District Date: 3/20/2020 750 Bradford Street Redwood City, CA 94063 DSA App. No.: 01-117949 Architect: Harley Ellis Devereaux (HED) PTN No.: 69005-0037 417 Montgomery Street, Suite 400 DSA File No.: 41-22 San Francisco, CA 94104 HED Proj. No.: 2017-03267 Notice is hereby given to all prospective bidders that drawings and specifications on the subject project are modified as hereinafter set forth. This Addendum shall be attached to and form a part of the drawings and specifications. All bidders must acknowledge receipt of this addendum on the Bid Form. In case of difference with previous addenda or communications, this addendum takes precedence. It is the responsibility of all bidders to notify all subcontractors from whom they request bids and from whom they accept bids, of all changes contained in this addendum. Acknowledge receipt of this Addendum by inserting its number and date in the bidding documents. Failure to do so may subject the bidder to disqualification. * See end of addendum summary for all Pre-Bid RFI’s received as of 2/16/2020 and their associated responses. CHANGES TO PREVIOUS ADDENDA: ADD-3.01 Addendum No. 01, Item ADD-1.01, Section 00 01 10 – Table of Contents A. Delete Section 00 01 10 in its entirety and replace with the attached revised Section 00 01 10 – Table of Contents. ADD-3.02 Addendum No 01, Item ADD-1.02, Section 00 01 15 – Drawings, Specifications, Schedules and Scope Statements for Multiple Prime Contracts A. Delete Section 00 01 15 in its entirety and replace with the attached revised Section 00 01 15 – Drawings, Specifications, Schedules and Scope Statements for Multiple Prime Contracts ADD-3.03 Addendum No. 1, Item ADD-1.03, Section 00 11 16 Notice to Bidders A. Section 00 11 16 Notice to Bidders: a. Add Item 7a. “The Shelter In Place (SIP) order which has been issued will not impact the scheduled bid opening date for this project. The bid opening date remains Wednesday, March 25 at 2:00 p.m. In order to comply with the requirements of the SIP, however, we are implementing social distancing protocols which will adjust the manner in which bids are submitted. The bond program office L I C E N S E D A R C H I T E C T ST A T E O F C A LIF O R N I A michael j. myers ren. 3.31.21 c-36095

REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Redwood City School District Addendum No. 3 Taft Community School, Phase 1 Page 1 of 3

REDWOOD CITY SCHOOL DISTRICT TAFT COMMUNITY SCHOOL

PHASE 1

ADDENDUM No. 3

Owner: Redwood City School District Date: 3/20/2020 750 Bradford Street Redwood City, CA 94063 DSA App. No.: 01-117949

Architect: Harley Ellis Devereaux (HED) PTN No.: 69005-0037 417 Montgomery Street, Suite 400 DSA File No.: 41-22 San Francisco, CA 94104 HED Proj. No.: 2017-03267

Notice is hereby given to all prospective bidders that drawings and specifications on the subject project are modified as hereinafter set forth. This Addendum shall be attached to and form a part of the drawings and specifications. All bidders must acknowledge receipt of this addendum on the Bid Form. In case of difference with previous addenda or communications, this addendum takes precedence.

It is the responsibility of all bidders to notify all subcontractors from whom they request bids and from whom they accept bids, of all changes contained in this addendum.

Acknowledge receipt of this Addendum by inserting its number and date in the bidding documents. Failure to do so may subject the bidder to disqualification.

* See end of addendum summary for all Pre-Bid RFI’s received as of 2/16/2020 and their associated responses. CHANGES TO PREVIOUS ADDENDA: ADD-3.01 Addendum No. 01, Item ADD-1.01, Section 00 01 10 – Table of Contents

A. Delete Section 00 01 10 in its entirety and replace with the attached revised Section 00 01 10 – Table of Contents.

ADD-3.02 Addendum No 01, Item ADD-1.02, Section 00 01 15 – Drawings, Specifications, Schedules

and Scope Statements for Multiple Prime Contracts

A. Delete Section 00 01 15 in its entirety and replace with the attached revised Section 00 01 15 – Drawings, Specifications, Schedules and Scope Statements for Multiple Prime Contracts

ADD-3.03 Addendum No. 1, Item ADD-1.03, Section 00 11 16 Notice to Bidders

A. Section 00 11 16 Notice to Bidders: a. Add Item 7a. “The Shelter In Place (SIP) order which has been issued will not

impact the scheduled bid opening date for this project. The bid opening date remains Wednesday, March 25 at 2:00 p.m. In order to comply with the requirements of the SIP, however, we are implementing social distancing protocols which will adjust the manner in which bids are submitted. The bond program office

LICENSED ARCHIT

ECT

STATE OF CALIF

ORN

IA

michael j. myersren. 3.31.21

c-36095

Page 2: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Redwood City School District Addendum No. 3 Taft Community School, Phase 1 Page 2 of 3

doors will remain closed as only one person at a time is permitted to enter to submit a bid. Before being permitted to enter, each bidder will be required to call one of the following two phone numbers to confirm that they are present and ready to submit a bid: bond program office desk phone (650) 482-2840 or project manager cell phone (916) 501-0705. It is critical to arrive early, as there may be a line and it will take longer than usual to submit a bid. While waiting outside of the bond program office, please maintain six feet apart from one another. Mass gatherings of ten or more people are also prohibited. If you do not plan on submitting a bid in person due to the COVID-19 SIP order and concerns about health and safety, please ensure that your bid is otherwise delivered to the bond program office before the bid opening deadline and notify the District so that a count can be taken. It is recommended that bidders do not stay to witness the bid opening so as to avoid a mass gathering per the SIP order – bid results will be communicated via email. For any bidder who does plan to witness the bid opening, it will be held in the gymnasium at Kennedy Middle School with chairs spaced six feet apart.”

CHANGES TO SPECIFICATIONS: ADD-3.04 Geotechnical Evaluation and Geologic Hazard Assessment Taft Community School

A. Section 10.1.6 Chemical Treatment: Provide an Add alternate for 4% and 5% lime treatment based on a soil density of 110 pcf confirmed via subsequent testing by the laboratory of record to confirm.

ADD-3.05 Section 00 01 15 – List of Drawings

A. Change designation of List of Drawings from 00 01 15 to 00 01 14. ADD-3.06 Section 11 41 23 – Walk-in Cooler.

A. Delete Section 11 41 23 in its entirety and replace with the attached revised Section 11 451 23 – Walk-in Cooler.

ADD-3.07 Section 10 21 13.19 – Solid Color Reinforced Composite Toilet Compartments.

A. Delete Section 10 21 13.19 in its entirety and replace with the attached revised Section 10 21 13.19 – Solid Color Reinforced Composite Toilet Compartments.

CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H– Building H – Multi-Use Plans

A. Keynote 7.14: Replace with “Install 8’-0” W x 7’-6” L x 7’-4” H (Nominal), floorless, FineLine Walk-In Cooler by Norlake, with Split-Pak refrigeration system. See spec section 11 41 23.”

B. Keynote 7.29: Replace with “Install corner guard protection at exposed corners. Install per manufacturer’s instructions. See specifications.”

C. Provide power for walk-In equipment and roof top condensing unit. See attached ASK 21.3.

Page 3: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Redwood City School District Addendum No. 3 Taft Community School, Phase 1 Page 3 of 3

ADD-3.09 Drawing L3.1 – Irrigation Plan. See attached revised drawing.

A. Irrigation added to Northwest bioretention planter.

ADD-3.10 ASK 21.1 Elevator Layout Revisions.

A. Reorient elevator, relocate adjacent accessories and relocate and revise adjacent cabinetry niche. See attached ASK21.2 & ASK 21.2.

ADD-3.11 ASK 21.2 Elevator Layout Revisions

A. Various ceiling revisions in open office area. B. Revised cabinetry niche. C. Relocated mailboxes. D. See attached ASK 21.1 & ASK 21.2

ADD-3.12 SSK02 Partial Plans at Revised Elevator Pit/Shaft

A. Revisions to pit location and foundation plan to accommodate elevator shaft. See attached SSK02.

ADD-3.13 S5.3 Foundation Details

A. Detail 16: See revised detail on attached SSK03. ADD-3.14 SSK04 Partial Plans at Revised Elevator Shaft

A. Revisions to second floor and low roof framing plans to accommodate elevator shaft. See attached SSK04.

ADD-3.15 SSK05 Partial High Roof Framing Plan at Revised Elevator Shaft

A. Revisions to high roof framing plan to accommodate elevator shaft. See attached SSK05. ADD-3.16 S1.2 Typical Details

A. Detail 4: Note “Conc slab on grade over 6” crushed rock or AB, see S2.1” to read “Conc slab on grade over 4” crushed rock see S2.1.”

ADD-3.17 S1.4 Typical Details – Exterior Metal Stud Walls

A. Detail 1: Note “Conc slab on grade over 6” crushed rock or AB, see S2.1” to read “Conc slab on grade over 4” crushed rock see S2.1.”

ATTACHMENTS: SPECIFICATIONS Section 00 01 10 – Table of Contents Section 00 01 15 – Drawings, Specifications, Schedules and Scope Statements for Multiple Prime Contracts Section 11 451 23 – Walk-in Cooler. Section 10 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. DRAWINGS L3.1, ASK21.1, ASK 21.2, ASK 21.3, SSK02, SSK03, SSK04, SSK05 END OF ADDENDUM

Page 4: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Taft CS Pre-Bid RFI’s Due No Later Than 3/16/2020

General Trades bid package scope “G” statement RFI’s:

BMI - RFI – E-mail Dated 02/26/2020:

Q1: Blinds-The fabric is PVC free and you can’t use PVC free fabric on a tensioned system like

the skylights. Please advise.

A1: No interior skylights.

Q2: A-401M sets the scope of modernization where cubby cabinets will be added. There is no

elevation that I can find. I assume open upper cabinets with coat hooks below the bottom

as seen in some of the pictures. Is this correct.?

A2: Reference elevation of cubbies shown at 8/A-451D

Q3: Detail 4/S1.2 - Please Clarify which scope is responsible for the 18" of Non-Expansive

Material.

A3: The General Trades contractor is responsible for the 18” non-expansive material.

Page 5: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Q4: Detail 1 /S1.4 Please provide locations and depths of undocumented fill removal or clarify if

this is solely at the discretion of the Geotech Engineer during the excavation activity. This

work will be completed as directed on T&M.

A4: See section 8.6 in the Geotechnical report.

If this is unquantifiable as described, T&M would be acceptable.

Q5: Sheet S2.1, S2.2 - Please confirm Note " 15 Mil Vapor Barrier Over 4" Free-Draining Crushed

Rock"

A5: Confirmed

Page 6: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Q6: Site Concrete Trades Bid Package Scope Statement “C” RFI’s Q7- A7, Q8-A8 - Please Clarify

which scope is responsible for:

A: Which scope is responsible for Slab on Metal Deck?

B: Which scope is responsible for Concrete Filled Pan Stairs?

C: Which scope is responsible for Amphitheater Slab on grade, 15 Mil Vapor Barrier Over 4"

Free- Draining crushed Rock?

D: Which scope is responsible for Polystyrene Fill?

A6:

6A: Concrete Fill over metal deck is the General Trades responsibility.

6B: Concrete Stairs over Metal Deck: General does all the metal decking for stairs, and the

site concrete trades contractor does the concrete fill for the stairs.

6C: Concrete Slab on Grade is the General Trades responsibility.

6D: Expanded polystyrene fill w/ minimum 12 psi strength is site concrete trades

responsibility.

Page 7: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Q7: M BAR C Sheet 1-S-10 - Please Confirm M Bar C Canopy Foundation Detail Do Not Apply,

A7: Confirmation from canopy/product manufacturer required with reference to geotechnical

report recommendations. Any deviations from stamped drawings will require allowance for

CCD process including DSA submittal of changes and possible engineering calculation.

Mechanical Trades Bid Package Scope Statement “E” RFI’s

O.C. Mcdonald - RFI – E-mail Dated 02/25/2020:

Q1: Exterior steel pipe downspouts scope of work is not referenced in Plumbing Bid Package H.

Please confirm which trade contractor or bid package is responsible for this scope of work.

A1: The General Trades contractor is responsible for exterior steel pipe downspouts per their

scope statement.

Q2: Please confirm that the underground site gas scope of work is to be the responsibility of

Underground Utilities Bid Package B.

A2: Confirmed. Underground utilities does all site utilities to 5’ of new buildings and connects

at POC for meterset.

Page 8: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Landscaping Trades Bid Package Scope Statement “F” RFI’s

Scapes Landscape - RFI – E-mail Dated 03/10/2020:

Q1: L3.1 NEW POC is shown.

I understand the backflow and MV and FS to be the landscaper’s responsibility, but would

you please clarify which trade is responsible for the 1” water meter for irrigation?

I don’t see it spelled out in any trade scope of work. Normally done at the same time as

other underground utilities.

A1: The Landscaping Trades Contractor is responsible for installation of irrigation water meters

and backflow devices. This verbiage has been added to the Landscaping Trades contractors

Scope statement in Addendum 3.

Q2: L3.1 and C7.3 Line Bio retention area NE corner of Administration Bldg. shows a bio

retention area. All other bio retention areas are irrigated with precision nozzles or shrub

bubblers. Is the intention to irrigate this area with drip irrigation at similar spacing as non

bio retention areas? This is not the norm as bio retention areas usually have different

irrigation needs due to the different soil profile.

A2: See updated sheet L3.1 included in Addendum #3 that adds irrigation to retention area in

question.

Site Concrete Trades Bid Package Scope Statement “C” RFI’s

DRYCO - RFI – E-mail Dated 03/10/2020:

Q1: In Addendum #1 a new L1.1 sheet was issued but it still does not show any control joints

noted by a grey line. Please confirm this is the case and there are no control joints besides

between paving and walls and paving material changes. Typical CJ spacing is around 20’

o/c.

A1: Controls joints for concrete sidewalks shall be maximum 20’ on center per landscape layout

notes on sheet L0.1 and project specifications for concrete sidewalks.

Q2: In addendum #1 we requested confirmation of the site concrete scope duties, in regard to

the stairs and amphitheater. The response given is still not clear due to the conjunction of

the amphitheater and building concrete. Since the walls of the amphitheater tie into the

building, the most cost-effective option may be to have the general construction contract

covers the walls themselves and then site concrete contractor infills the stairs and slab on

top of the building.

Who is responsible for the excavation of these wall footings?

A2: Refer to Question 6 from BMI and see responses when they come out.

Page 9: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Q3: In addition to the amphitheater area, there is only one other set of exterior stairs. Is the

site concrete contractor only responsible for the infill of the stair pans since they are metal

framed stairs?

A3: Yes, The concrete trades contractor is responsible for the infill of the stair pans and the

general trades contractor will provide decking and other components.

Page 10: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T – Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Document 00 01 10 Addendum No. 1 Redwood City School District Table of Contents - 1

DOCUMENT 00 01 10

TABLE OF CONTENTS

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS INTRODUCTORY INFORMATION

Document 00 01 01 Project Title Page 00 01 05 Consultants Page 00 01 07 Seals Page 00 01 08 Deferred Approval Items 00 01 10 Table of Contents 00 01 14 List of Drawings and Tables 00 01 15 Drawings, Specifications, Schedules and Scope Statements for Multiple Prime

Contactors

PROCUREMENT REQUIREMENTS Document 00 11 16 Notice to Bidders 00 21 13 Instructions to Bidders 00 31 19 Existing Conditions 00 31 26 Existing Hazardous Material Information

Asbestos & Lead Report 00 31 32 Geotechnical Data 00 41 13.X Bid Form and Proposal 00 43 13 Bid Bond 00 43 36 Designated Subcontractors List 00 45 01 Site Visit Certification 00 45 19 Non-Collusion Declaration 00 45 19.01 Iran Contracting Act Certification 00 45 26 Workers’ Compensation Certification 00 45 46.01 Prevailing Wage and Related Labor Requirements Certification 00 45 46.02 Disabled Veteran Business Enterprise Participation

Certification 00 45 46.03 Drug-Free Workplace Certification 00 45 46.04 Tobacco-Free Environment Certification 00 45 46.05 Hazardous Materials Certification 00 45 46.06 Lead-Based Materials Certification 00 45 46.07 Imported Materials Certification 00 45 46.08 Criminal Background Investigation/Fingerprinting Certification 00 45 46.10 Roofing Project Certification 00 45 46.11 Iran Contracting Act Certification 00 45 49 Registered Subcontractor List 00 45 90 Post Bid Interview

CONTRACTING REQUIREMENTS Document 00 51 00 Notice of Award 00 52 13 Agreement 00 55 00 Notice to Proceed 00 56 00 Escrow Bid Documentation 00 57 00 Escrow Agreement in Lieu of Retention 00 61 13.13 Performance Bond 00 61 13.16 Payment Bond 00 63 40 Allowance Expenditure Directive Form 00 63 57 Proposed Change Order Form

Page 11: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T – Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Document 00 01 10 Addendum No. 1 Redwood City School District Table of Contents - 2

00 63 63 Change Order Form 00 65 19.26 Agreement and Release of Any and All Claims 00 65 36 Guarantee Form 00 72 13 General Conditions 00 73 13 Special Conditions 00 73 56 Hazardous Materials Procedures and Requirements 00 73 73 Compliance Monitoring and Enforcement Notice

DIVISION 01 - GENERAL REQUIEMENTS Section 01 11 00 Summary of Work 01 22 00 Alternates and Unit Pricing 01 25 13 Product Options and Substitutions 01 26 00 Changes in the Work 01 29 00 Application for Payment and Conditional and Unconditional Waiver and

Release Forms 01 31 19 Project Meetings and Coordination 01 32 01 Project Coordination 01 32 13 Scheduling of Work 01 33 00 Submittals 01 35 13.23 Site Standards 01 35 16 Alteration Project Procedures 01 41 00 Regulatory Requirements 01 41 15 Additional Requirements for DSA-Reviewed Projects 01 42 13 Abbreviations and Acronyms 01 42 16 Definitions 01 42 19 References 01 43 00 Materials and Equipment 01 45 00 Quality Control

DSA 103 Form - Structural Tests and Special Inspections - 2016 CBC 01 50 00 Temporary Facilities and Controls 01 50 13 Construction Waste Management and Disposal 01 52 13 Field Offices 01 56 39 Tree Preservation and Pruning 01 64 00 Owner-Furnished Products 01 66 00 Product Delivery, Storage and Handling 01 71 23 Field Engineering 01 73 29 Cutting and Patching 01 74 19 Construction Waste Management and Disposal 01 76 00 Alteration Project Procedures 01 77 00 Contract Closeout and Final Cleaning 01 78 23 Operation and Maintenance Data 01 78 36 Warranties 01 78 39 Record Documents

DIVISION 02 - EXISTING CONDITIONS

Section 02 41 13 Selective Site Demolition 02 41 16 Structure Demolition 02 41 19 Selective Demolition

DIVISION 03 - CONCRETE Section 03 11 00 Concrete Forming 03 20 00 Concrete Reinforcing 03 30 00 Cast-In-Place Concrete 03 48 43 Precast Concrete Trim

Page 12: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T – Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Document 00 01 10 Addendum No. 1 Redwood City School District Table of Contents - 3

DIVISION 04 - MASONRY (Not Used)

DIVISION 05 - METALS Section 05 12 00 Structural Steel Framing 05 31 00 Steel Decking 05 40 00 Cold-Formed Metal Framing 05 50 00 Metal Fabrications 05 51 13 Metal Pan Stairs 05 51 33 Metal Ladders 05 52 13 Pipe and Tube Railings

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

Section 06 10 53 Miscellaneous Rough Carpentry 06 16 00 Sheathing 06 20 23 Interior Finish Carpentry 06 41 16 Plastic-Laminate-Clad Architectural Cabinets 06 83 16 Fiberglass Reinforced Plastic (FRP) Paneling

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

Section 07 13 26 Self-Adhering Sheet Waterproofing 07 14 13 Hot Fluid-Applied Rubberized Asphalt Waterproofing 07 16 16 Crystalline Waterproofing Additive 07 18 13 Pedestrian Traffic Coatings 07 21 00 Thermal Insulation 07 25 00 Weather Barriers 07 25 13 Ventilated Rainscreen 07 26 16 Below Grade Vapor Barrier 07 42 13.19 Insulated Metal Spandrel Panels 07 42 93 Soffit Panels 07 52 16.13 SBS Modified Bituminous Membrane Roofing, Cold-Applied 07 62 00 Sheet Metal Flashing and Trim 07 71 29 Manufactured Roof Expansion Joints 07 72 33 Roof Hatches 07 84 13 Penetration Firestopping 07 84 43 Joint Firestopping 07 92 00 Joint Sealants 07 95 13.16 Exterior Expansion Joint Cover Assemblies

DIVISION 08 - OPENINGS Section 08 11 13 Hollow Metal Doors and Frames 08 14 16 Flush Wood Doors 08 14 33 Stile and Rail Wood Doors 08 17 43 FRP Flush Doors 08 31 13 Access Doors and Frames 08 41 13 Aluminum-Framed Entrances and Storefronts 08 44 13 Glazed Aluminum Curtain Walls 08 71 00 Door Hardware 08 71 13 Automatic Door Operators 08 80 00 Glazing 08 91 19 Fixed Louvers 08 92 00 Louvered Equipment Screens

DIVISION 09 - FINISHES Section

Page 13: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T – Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Document 00 01 10 Addendum No. 1 Redwood City School District Table of Contents - 4

09 05 61.13 Moisture Vapor Emission Control 09 21 16.23 Gypsum Board Shaft Wall Assemblies 09 22 16 Non-Structural Metal Framing 09 24 00.13 Acrylic-Modified Portland Cement Plastering 09 29 00 Gypsum Board 09 30 13 Ceramic Tiling 09 51 13 Acoustical Panel Ceilings 09 65 13 Resilient Base and Accessories 09 65 19 Resilient Tile Flooring 09 67 23 Resinous Flooring 09 68 13 Tile Carpeting 09 77 23 Fabric-Covered Tack Paneling 09 91 00 Painting

DIVISION 10 - SPECIALTIES

Section 10 11 00 Visual Display Units 10 14 00 Signage 10 14 19 Dimensional Letter Signage 10 14 63 Electronic Message Signage 10 21 13.19 Solid Color Reinforced Composite Toilet Compartments 10 26 13 Corner Guards 10 28 13 Toilet Accessories 10 44 00 Fire Protection Specialties 10 56 13 Metal Storage Shelving 10 73 16 Pre-Engineered Canopies 10 75 16 Ground-Set Flagpoles

DIVISION 11 - EQUIPMENT Section 11 30 13 Residential Appliances 11 41 23 Walk-In Coolers 11 52 13 Projection Screens

DIVISION 12 - FURNISHINGS Section 12 24 00 Exterior Roller Shades 12 24 13 Roller Window Shades 12 34 50 Manufactured Solid Composite Exterior Casework

DIVISION 13 - SPECIAL CONSTRUCTION (Not Used)

DIVISION 14 - CONVEYING EQUIPMENT

Section 14 24 23 Hydraulic Passenger Elevators

DIVISION 21 - FIRE SUPPRESSION

Section 21 13 00 Fire Sprinkler Systems

DIVISION 22 - PLUMBING

Section 22 00 00 Plumbing Systems

DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING

Section 23 00 00 Heating, Ventilating and Air Conditioning Systems 23 01 01 Energy Management and Temperature Control System

Page 14: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T – Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Document 00 01 10 Addendum No. 1 Redwood City School District Table of Contents - 5

23 01 02 EMTCS/DDS Software 23 05 00 Acceptance Requirements

DIVISION 26 - ELECTRICAL Section 26 05 00 Basic Electrical Materials and Methods 26 05 13 Conductors and Cables 26 05 26 Grounding and Bonding 26 05 33 Raceways and Boxes 26 05 48 Seismic Controls for Electrical Work 26 05 53 Identification for Electrical Systems 26 09 23 Lighting Control Devices 26 24 13 Switchboards 26 24 16 Panelboards 26 27 26 Wiring Devices 26 51 00 Interior Lighting 26 56 00 Exterior Lighting

DIVISION 27 - COMMUNICATIONS

Section 27 00 00 General Technology Requirements 27 05 26 Grounding and Bonding for Communications System 27 15 00 Horizontal Cabling 27 30 00 Emergency Communication System 27 51 23 Intercom and Clock System

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY Section 28 16 00 Intrusion Systems 28 46 00 Fire Alarm System

DIVISION 31 - EARTHWORK

Section 31 00 00 Earthwork and Grading 31 10 00 Site Clearing 31 23 33 Trenching and Backfilling

DIVISION 32 - EXTERIOR IMPROVEMENTS Section 32 12 33 Paving and Surfacing 32 17 13 Parking Bumpers 32 17 23 Pavement Markings 32 17 26 Tactile Warning Surfacing 32 31 13 Chain Link Fences and Gates 32 31 19 Ornamental Metal Fences and Gates 32 33 00 Site Furnishings and Accessories 32 84 00 Irrigation 32 90 00 Landscape Planting

DIVISION 33 - UTILITIES

Section 33 05 13 Utility Grade Adjustment 33 10 00 Water System 33 30 00 Sanitary Sewer System 33 40 00 Storm Drainage 33 46 00 Subdrainage

Page 15: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T – Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Document 00 01 10 Addendum No. 1 Redwood City School District Table of Contents - 6

APPENDIX A (FOR REFERENCE ONLY) Geotechnical Evaluation and Geologic Hazard Assessment Taft Community School, 903 Tenth Avenue, Redwood City, CA Ninyo & Moore, February 23, 2018 Supplement to Geotechnical Evaluation and Geologic Hazard Assessment Taft Community School, 903 Tenth Avenue, Redwood City, CA Ninyo & Moore, January 13, 2020 APPENDIX B (FOR REFERENCE ONLY) Asbestos & Lead (Pb) Report, Limited Pre-Demolition/Renovation Survey & Evaluation Taft Elementary School, 903 Tenth Avenue, Redwood City, CA ProTech Consulting & Engineering, Revised June 29, 2018 APPENDIX C Soil Mitigation Plan Taft Community School, 903 Tenth Avenue, Redwood City, CA McCloskey Consultants, December 19, 2018

END OF DOCUMENT 02/17/20

Page 16: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-1

DOCUMENT 00 01 15

DRAWINGS, SPECIFICATIONS, SCHEDULES AND SCOPE STATEMENTS FOR MULTIPLE PRIME CONTRACTS

Document File number and

application Description

See Cover Sheet of DSA Approved Set of "Taft Community School – New Buildings, Modernization & Site Work" for a complete list of Construction Drawings, and Table of Contents for complete list of Construction Specifications See DSA-103 for required Structural Tests and Inspections See Master Construction Schedule for proposed sequence of work and Milestones See Scope Statement for work to be bid and applicable Drawings and Technical Specification Sections for each Specific Bid Package

41-22,

01-117949

DSA

Approved Set

DSA-103 Statement of Structural Tests and Inspections (Attached herein). Contractor Access Laydown and Staging Plan (Attached herein). Master Construction Schedule (Attached herein). CEQA Mitigation Monitoring or Reporting Program (Attached herein). Scope Statements for specific Bid Packages (Attached herein).

A. Earthwork and Paving Trades B. Underground Utilities Trades C. Site Concrete Trades D. Electrical and Low Voltage Trades E. HVAC Trades F. Landscaping Trades G. General Trades H. Plumbing Trades I. Fire Protection Trades J. Abatement Trades

Page 17: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-2

DSA-103 STATEMENT OF STRUCTURAL TESTS AND SPECIAL INSPECTIONS (ATTACHED BEHIND THIS COVER PAGE)

Page 18: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–
Page 19: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–
Page 20: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–
Page 21: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

APP. INC:REVIEWED FOR

SS FLS ACS

DATE:

IDENTIFICATION STAMP DIV. OF THE STATE ARCHITECT

01-117949

✔ ✔ ✔

12/17/2019

Page 22: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–
Page 23: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–
Page 24: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-3

CONTRACTOR ACCESS, LAYDOWN AND STAGING PLAN (ATTACHED BEHIND THIS COVER PAGE)

Page 25: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Const. Trailers

Portable Toilets

Contractor Staging, Laydown, and Parking

Rock Entrance and Exit

Hose Bib for SWPPP's

Permanent 20' Access/ Exit Gates

Permanent 4' Man Gate

Teacher/ School Parking

Used as student Classrooms - Demo TBD at a later Date

Page 26: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-4

MASTER CONSTRUCTION SCHEDULE

Time limits stated in this Contract are of the essence. By executing the Contract, the Contractor acknowledges and agrees that the scheduled duration of Contractor’s work as set forth on the Construction Schedule enclosed herein is a reasonable period of time for achieving completion of Contractor’s Work. The Construction Manager shall manage, revise, update and control the Construction Schedule throughout the course of the Project. The Construction Manager shall have the right, in its sole discretion, to apportion time between Contractor and all other contractors and subcontractors to complete their work in coordination with each other and in compliance with the Construction Schedule. See General Conditions for additional construction schedule requirements.

Delineation of work required will be in accordance with the Scope Statement and Construction Schedule incorporated herein.

Construction Schedule Start Finish

Taft Community School 4/20/20 11/5/21

Liquidated Damages: The State of California Government Code, Section 53069.85 provides that Public Work projects may establish time limits within which the whole or any specified portion of the work contemplated shall be completed, and that for each day the schedule is delayed beyond the specified time, the delaying Contractor shall pay to such agency involved a specified sum of money to be deducted from any payment due or to become due to the Contractor.

Refer to the Agreement - Document 007213-41 for the amount of liquidated damages applicable to this contract.

Page 27: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-5

MASTER CONSTRUCTION SCHEDULE (ATTACHED BEHIND THIS COVER PAGE)

Page 28: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

ID Task Name Duration Start Finish

1 Redwood City School District - Taft Phase 1 412 days Thu 4/9/20 Fri 11/5/21

2 Preconstruction 4 days Thu 4/9/20 Tue 4/14/20

3 Mobilize and Const. Fencing 3 days Thu 4/9/20 Mon 4/13/20

4 Site Temporary Power 1 day Tue 4/14/20 Tue 4/14/20

5 Site Temporary Water 1 day Tue 4/14/20 Tue 4/14/20

6 Trade Contractor Mobilize 1 day Tue 4/14/20 Tue 4/14/20

7 Rough Grade & UG Utilities 91 days Wed 4/15/20 Wed 8/19/20

8 Erosion Control 1 day Wed 4/15/20 Wed 4/15/20

9 Building Safe Off 2 days Thu 4/16/20 Fri 4/17/20

10 Hazardous Material Abatement 5 days Mon 4/20/20 Fri 4/24/20

11 CDC Building Demo 3 days Mon 4/27/20 Wed 4/29/20

12 Shore Up Canopies Near Buildings To Be Demolished 3 days Mon 4/27/20 Wed 4/29/20

13 Buildings D,F,C,B Demo 10 days Thu 4/30/20 Wed 5/13/20

14 Site Utilities Safe Off 4 days Fri 5/8/20 Wed 5/13/20

15 Site Demo 7 days Thu 5/14/20 Fri 5/22/20

16 Install Construction Entrances(2) 2 days Mon 5/25/20 Tue 5/26/20

17 Rough Grade Site 7 days Wed 5/27/20 Thu 6/4/20

18 Traffic Control for City SD Connect 2 days Wed 5/27/20 Thu 5/28/20

19 Install SD To Parking Lot From Existing 5 days Fri 5/29/20 Thu 6/4/20

20 Install SD In Staging/Parking Area 5 days Fri 6/5/20 Thu 6/11/20

21 Install Remaining SD System 5 days Fri 6/12/20 Thu 6/18/20

22 Install Sanitary Sewer 5' From Building 7 days Fri 6/19/20 Mon 6/29/20

23 Install Domestic Water 5' From Building 7 days Tue 6/30/20 Wed 7/8/20

24 Install Fire Water 5' From Building 5 days Thu 7/9/20 Wed 7/15/20

25 Install Irrigation Main 5 days Thu 7/16/20 Wed 7/22/20

26 Install Gas Piping 5' From Building 5 days Thu 7/23/20 Wed 7/29/20

27 Install Underground Electrical Conduit 7 days Thu 7/30/20 Fri 8/7/20

28 Grade and Baserock Parking Area to Subgrade 7 days Mon 8/10/20 Tue 8/18/20

29 Prepare Building Pads And Certify 8 days Mon 8/10/20 Wed 8/19/20

30 New CR/ Library Building D1 & Amphitheater 227 days Thu 8/20/20 Fri 7/2/21

31 Foundation 50 days Thu 8/20/20 Wed 10/28/20

32 Layout Footings 4 days Thu 8/20/20 Tue 8/25/20

33 Underslab Plumbing 7 days Wed 8/26/20 Thu 9/3/20

34 Underslab Elect. 5 days Fri 9/4/20 Thu 9/10/20

35 Excavate Amphitheater Footings 3 days Fri 9/11/20 Tue 9/15/20

36 Excavate Building D1 Footings and Elevator Pit 5 days Wed 9/16/20 Tue 9/22/20

37 Set Rebar & Steel at Footings And Elevator Pit Base 10 days Wed 9/23/20 Tue 10/6/20

38 Place Elevator Pit Base Concrete 1 day Wed 10/7/20 Wed 10/7/20

39 Set Perimeter Formboards 7 days Wed 10/7/20 Thu 10/15/20

40 Form Elevator Pit Walls and Rebar 3 days Thu 10/8/20 Mon 10/12/20

41 Place Concrete at Footings and Elevator Pit Walls 1 day Tue 10/13/20 Tue 10/13/20

42 Complete Slab Forms D1 and Amphitheater 5 days Wed 10/14/20 Tue 10/20/20

4/9/20 Redwood City School District - Taft Phase 1

4/9/20 Preconstruction

4/9/20 Mobilize and Const. Fencing

4/14/20 Site Temporary Power

4/14/20 Site Temporary Water

4/14/20 Trade Contractor Mobilize

4/15/20 Rough Grade & UG Utilities

4/15/20 Erosion Control

4/16/20 Building Safe Off

4/20/20 Hazardous Material Abatement

4/27/20 CDC Building Demo

4/30/20 Buildings D,F,C,B Demo

5/8/20 Site Utilities Safe Off

5/14/20 Site Demo

5/25/20 Install Construction Entrances(2)

5/27/20 Rough Grade Site

5/27/20 Traffic Control for City SD Connect

5/29/20 Install SD To Parking Lot From Existing

6/5/20 Install SD In Staging/Parking Area

6/12/20 Install Remaining SD System

6/19/20 Install Sanitary Sewer 5' From Building

6/30/20 Install Domestic Water 5' From Building

7/9/20 Install Fire Water 5' From Building

7/16/20 Install Irrigation Main

7/23/20 Install Gas Piping 5' From Building

7/30/20 Install Underground Electrical Conduit

8/10/20 Grade and Baserock Parking Area to Subgrade

8/10/20 Prepare Building Pads And Certify

8/20/20 New CR/ Library Building D1 & Amphitheater

8/20/20 Foundation

8/20/20 Layout Footings

8/26/20 Underslab Plumbing

9/4/20 Underslab Elect.

9/11/20 Excavate Amphitheater Footings

9/16/20 Excavate Building D1 Footings and Elevator Pit

9/23/20 Set Rebar & Steel at Footings And Elevator Pit Base

10/7/20 Place Elevator Pit Base Concrete

10/7/20 Set Perimeter Formboards

10/8/20 Form Elevator Pit Walls and Rebar

10/13/20 Place Concrete at Footings and Elevator Pit Walls

10/14/20 Complete Slab Forms D1 and Amphitheater

2019 2020 2021 2022 2023 2024

2014

Page 1

Page 29: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

ID Task Name Duration Start Finish

43 Prepare &Set Rebar for Slab D1 and Amphitheater 4 days Wed 10/21/20 Mon 10/26/20

44 Place Slab Concrete D1 and Amphitheater 2 days Tue 10/27/20 Wed 10/28/20

45 Building Frame 137 days Thu 10/29/20 Fri 5/7/21

46 Set Steel Columns At Amphitheater 5 days Thu 10/29/20 Wed 11/4/20

47 Form Amphitheater Walls 7 days Thu 11/5/20 Fri 11/13/20

48 Set Rebar For Amphitheater Walls 5 days Mon 11/16/20 Fri 11/20/20

49 MEP's Sleeves/Conduit at Amphitheater Walls 4 days Mon 11/23/20 Thu 11/26/20

50 Place Amphitheater Wall Concrete 2 days Fri 11/27/20 Mon 11/30/20

51 Set Steel Columns, Beams, Stairs At Building D1 20 days Thu 11/5/20 Wed 12/2/20

52 2nd Floor Deck 7 days Thu 12/3/20 Fri 12/11/20

53 Roof Deck 7 days Mon 12/14/20 Tue 12/22/20

54 Exterior Wall Framing 1st Floor 10 days Wed 12/23/20 Tue 1/5/21

55 Set 2nd Floor Rebar 4 days Wed 12/23/20 Mon 12/28/20

56 MEP Sleeves 4 days Tue 12/29/20 Fri 1/1/21

57 Place 2nd Floor Concrete 1 day Mon 1/4/21 Mon 1/4/21

58 Exterior Wall Framing 2nd Floor 10 days Tue 1/5/21 Mon 1/18/21

59 Interior Wall Framing 1st Floor 5 days Wed 1/6/21 Tue 1/12/21

60 Interior Wall Framing 2nd Floor 5 days Tue 1/19/21 Mon 1/25/21

61 Soffit Framing 7 days Tue 1/26/21 Wed 2/3/21

62 Exterior Wall Sheathing 12 days Tue 1/19/21 Wed 2/3/21

63 Exterior Frames 8 days Thu 2/4/21 Mon 2/15/21

64 Roofing, Skylights and Gutters 14 days Thu 2/4/21 Tue 2/23/21

65 Set Rooftop HVAC Units 2 days Wed 2/24/21 Thu 2/25/21

66 HVAC Gas and Condensate 4 days Fri 2/26/21 Wed 3/3/21

67 Erect Scaffold 3 days Tue 2/16/21 Thu 2/18/21

68 Windows/Storefronts 7 days Fri 2/19/21 Mon 3/1/21

69 Exterior Wall Weather Barriers 10 days Tue 3/2/21 Mon 3/15/21

70 Stucco 20 days Tue 3/16/21 Mon 4/12/21

71 Remove Scaffold 2 days Tue 4/13/21 Wed 4/14/21

72 Guard Rail/Hand Rails 7 days Tue 4/13/21 Wed 4/21/21

73 Install Downspouts 7 days Thu 4/15/21 Fri 4/23/21

74 Soffit Panels 7 days Thu 4/15/21 Fri 4/23/21

75 Install Sunshades 10 days Thu 4/15/21 Wed 4/28/21

76 Exterior Paint 10 days Mon 4/26/21 Fri 5/7/21

77 MEPs 32 days Tue 1/26/21 Wed 3/10/21

78 Fire Sprinkler Rough 7 days Tue 1/26/21 Wed 2/3/21

79 Plumbing Rough 7 days Thu 2/4/21 Fri 2/12/21

80 Electrical, LV, Fire Alarm Rough 10 days Mon 2/15/21 Fri 2/26/21

81 Mechanical Rough 7 days Mon 3/1/21 Tue 3/9/21

82 Rough MEP Inspection 1 day Wed 3/10/21 Wed 3/10/21

83 Finishes 82 days Thu 3/11/21 Fri 7/2/21

84 Insulation 5 days Thu 3/11/21 Wed 3/17/21

10/21/20 Prepare &Set Rebar for Slab D1 and Amphitheater

10/27/20 Place Slab Concrete D1 and Amphitheater

10/29/20 Building Frame

10/29/20 Set Steel Columns At Amphitheater

11/16/20 Set Rebar For Amphitheater Walls

11/23/20 MEP's Sleeves/Conduit at Amphitheater Walls

11/5/20 Set Steel Columns, Beams, Stairs At Building D1

12/3/20 2nd Floor Deck

12/14/20 Roof Deck

12/23/20 Exterior Wall Framing 1st Floor

12/23/20 Set 2nd Floor Rebar

12/29/20 MEP Sleeves

1/4/21 Place 2nd Floor Concrete

1/5/21 Exterior Wall Framing 2nd Floor

1/6/21 Interior Wall Framing 1st Floor

1/19/21 Interior Wall Framing 2nd Floor

1/26/21 Soffit Framing

1/19/21 Exterior Wall Sheathing

2/4/21 Exterior Frames

2/4/21 Roofing, Skylights and Gutters

2/24/21 Set Rooftop HVAC Units

2/26/21 HVAC Gas and Condensate

2/16/21 Erect Scaffold

2/19/21 Windows/Storefronts

3/2/21 Exterior Wall Weather Barriers

3/16/21 Stucco

4/13/21 Remove Scaffold

4/13/21 Guard Rail/Hand Rails

4/15/21 Install Downspouts

4/15/21 Soffit Panels

4/15/21 Install Sunshades

4/26/21 Exterior Paint

1/26/21 MEPs

1/26/21 Fire Sprinkler Rough

2/4/21 Plumbing Rough

2/15/21 Electrical, LV, Fire Alarm Rough

3/10/21 Rough MEP Inspection

3/11/21 Finishes

3/11/21 Insulation

2019 2020 2021 2022 2023 2024

2014

Page 2

Page 30: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

ID Task Name Duration Start Finish

85 Drywall First Floor 10 days Tue 3/16/21 Mon 3/29/21

86 Drywall Second Floor 10 days Tue 3/23/21 Mon 4/5/21

87 Interior Paint First Floor 6 days Tue 3/30/21 Tue 4/6/21

88 Interior Paint Second Floor 6 days Tue 4/6/21 Tue 4/13/21

89 Ceiling Grid 10 days Wed 4/14/21 Tue 4/27/21

90 Cabinets and Tops 7 days Wed 4/28/21 Thu 5/6/21

91 Tack Wall 5 days Fri 5/7/21 Thu 5/13/21

92 Window Shades 5 days Fri 5/14/21 Thu 5/20/21

93 Floor Tile 15 days Fri 5/21/21 Thu 6/10/21

94 Resin Floor Coating 3 days Fri 5/21/21 Tue 5/25/21

95 Carpet 7 days Wed 5/26/21 Thu 6/3/21

96 Ceramic Tile 5 days Wed 5/26/21 Tue 6/1/21

97 Toilet Partitions 5 days Wed 6/2/21 Tue 6/8/21

98 Toilet Accessories 3 days Wed 6/9/21 Fri 6/11/21

99 Interior Doors and Hardware 5 days Fri 6/4/21 Thu 6/10/21

100 Plumbing Finish 7 days Wed 6/2/21 Thu 6/10/21

101 Drinking Fountains 3 days Fri 6/11/21 Tue 6/15/21

102 Drop Ceiling Tile 3 days Fri 6/11/21 Tue 6/15/21

103 Electrical, LV, Fire Alarm Finish 8 days Fri 6/11/21 Tue 6/22/21

104 Seal Concrete 5 days Wed 6/23/21 Tue 6/29/21

105 Signage 3 days Wed 6/30/21 Fri 7/2/21

106 New CR & Admin Building D2 226 days Thu 12/3/20 Thu 10/14/21

107 Foundation 42 days Thu 12/3/20 Fri 1/29/21

108 Layout Footings 6 days Thu 12/3/20 Thu 12/10/20

109 Underslab Plumbing 7 days Fri 12/11/20 Mon 12/21/20

110 Underslab Elect. 7 days Tue 12/22/20 Wed 12/30/20

111 Excavate Building D2 Footings and Elevator Pit 6 days Thu 12/31/20 Thu 1/7/21

112 Set Rebar & Steel at Footings And Elevator Pit Base 10 days Fri 1/8/21 Thu 1/21/21

113 Place Concrete Elevator Pit Base 1 day Fri 1/8/21 Fri 1/8/21

114 Set Perimeter Formboards 8 days Fri 1/8/21 Tue 1/19/21

115 Form Elevator Pit Walls and Rebar 3 days Mon 1/11/21 Wed 1/13/21

116 Place Concrete at Footings and Elevator Pit Walls 1 day Thu 1/14/21 Thu 1/14/21

117 Complete Slab Forms D2 6 days Fri 1/15/21 Fri 1/22/21

118 Set Rebar For Slab D2 4 days Mon 1/25/21 Thu 1/28/21

119 Place Slab Concrete D2 1 day Fri 1/29/21 Fri 1/29/21

120 Building Frame 143 days Mon 2/1/21 Wed 8/18/21

121 Steel Building Columns, Beams and Stairs 20 days Mon 2/1/21 Fri 2/26/21

122 2nd Floor Deck 7 days Mon 3/1/21 Tue 3/9/21

123 Roof Deck 7 days Wed 3/10/21 Thu 3/18/21

124 Exterior Wall Framing First Floor 10 days Fri 3/19/21 Thu 4/1/21

125 Set 2nd Floor Rebar 4 days Fri 3/19/21 Wed 3/24/21

126 MEP Sleeves 5 days Thu 3/25/21 Wed 3/31/21

3/16/21 Drywall First Floor

3/30/21 Interior Paint First Floor

4/6/21 Interior Paint Second Floor

4/14/21 Ceiling Grid

4/28/21 Cabinets and Tops

5/7/21 Tack Wall

5/14/21 Window Shades

5/21/21 Floor Tile

5/21/21 Resin Floor Coating

5/26/21 Carpet

5/26/21 Ceramic Tile

6/2/21 Toilet Partitions

6/9/21 Toilet Accessories

6/4/21 Interior Doors and Hardware

6/2/21 Plumbing Finish

6/11/21 Drinking Fountains

6/11/21 Drop Ceiling Tile

6/11/21 Electrical, LV, Fire Alarm Finish

6/23/21 Seal Concrete

6/30/21 Signage

12/3/20 New CR & Admin Building D2

12/3/20 Foundation

12/3/20 Layout Footings

12/11/20 Underslab Plumbing

12/22/20 Underslab Elect.

12/31/20 Excavate Building D2 Footings and Elevator Pit

1/8/21 Set Rebar & Steel at Footings And Elevator Pit Base

1/8/21 Place Concrete Elevator Pit Base

1/8/21 Set Perimeter Formboards

1/11/21 Form Elevator Pit Walls and Rebar

1/14/21 Place Concrete at Footings and Elevator Pit Walls

1/15/21 Complete Slab Forms D2

1/25/21 Set Rebar For Slab D2

1/29/21 Place Slab Concrete D2

2/1/21 Building Frame

2/1/21 Steel Building Columns, Beams and Stairs

3/1/21 2nd Floor Deck

3/10/21 Roof Deck

3/19/21 Exterior Wall Framing First Floor

3/19/21 Set 2nd Floor Rebar

3/25/21 MEP Sleeves

2019 2020 2021 2022 2023 2024

2014

Page 3

Page 31: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

ID Task Name Duration Start Finish

127 Place 2nd Floor Concrete 1 day Thu 4/1/21 Thu 4/1/21

128 Exterior Wall Framing 2nd Floor 10 days Fri 4/2/21 Thu 4/15/21

129 Interior Wall Framing 1st Floor 14 days Fri 4/2/21 Wed 4/21/21

130 Interior Wall Framing 2nd Floor 10 days Fri 4/16/21 Thu 4/29/21

131 Soffit Framing 7 days Fri 4/30/21 Mon 5/10/21

132 Exterior Wall Sheathing 12 days Tue 5/11/21 Wed 5/26/21

133 Exterior Frames 8 days Thu 5/27/21 Mon 6/7/21

134 Roofing, Skylights and Gutters 12 days Thu 5/27/21 Fri 6/11/21

135 Set Rooftop HVAC Units 2 days Mon 6/14/21 Tue 6/15/21

136 HVAC Gas and Condensate 4 days Wed 6/16/21 Mon 6/21/21

137 Erect Scaffold 3 days Tue 6/8/21 Thu 6/10/21

138 Windows/Storefronts 7 days Fri 6/11/21 Mon 6/21/21

139 Exterior Wall Weather Barriers 10 days Tue 6/22/21 Mon 7/5/21

140 Stucco 20 days Tue 7/6/21 Mon 8/2/21

141 Remove Scaffold 2 days Tue 8/3/21 Wed 8/4/21

142 Guard Rail/Hand Rails 7 days Thu 8/5/21 Fri 8/13/21

143 Install Downspouts 7 days Thu 8/5/21 Fri 8/13/21

144 Install Sunshades 10 days Thu 8/5/21 Wed 8/18/21

145 Exterior Paint 10 days Thu 8/5/21 Wed 8/18/21

146 MEPs 39 days Fri 4/30/21 Wed 6/23/21

147 Fire Sprinkler Rough 9 days Fri 4/30/21 Wed 5/12/21

148 Plumbing Rough 9 days Thu 5/13/21 Tue 5/25/21

149 Electrical, LV, Fire Alarm Rough 12 days Wed 5/26/21 Thu 6/10/21

150 Mechanical Rough 8 days Fri 6/11/21 Tue 6/22/21

151 Rough MEP Inspection 1 day Wed 6/23/21 Wed 6/23/21

152 Finishes 81 days Thu 6/24/21 Thu 10/14/21

153 Insulation 5 days Thu 6/24/21 Wed 6/30/21

154 Drywall First Floor 12 days Tue 6/29/21 Wed 7/14/21

155 Drywall Second Floor 12 days Tue 7/6/21 Wed 7/21/21

156 Elevator Install 20 days Thu 7/22/21 Wed 8/18/21

157 Interior Paint First Floor 7 days Thu 7/15/21 Fri 7/23/21

158 Interior Paint Second Floor 7 days Thu 7/22/21 Fri 7/30/21

159 Ceiling Grid 10 days Mon 8/2/21 Fri 8/13/21

160 Cabinets and Tops 7 days Mon 8/16/21 Tue 8/24/21

161 Tack Wall 5 days Wed 8/25/21 Tue 8/31/21

162 Window Shades 5 days Wed 9/1/21 Tue 9/7/21

163 Floor Tile 15 days Wed 9/8/21 Tue 9/28/21

164 Resin Floor Coating 3 days Wed 9/8/21 Fri 9/10/21

165 Carpet 7 days Mon 9/13/21 Tue 9/21/21

166 Ceramic Tile 5 days Mon 9/13/21 Fri 9/17/21

167 Toilet Partitions 5 days Mon 9/20/21 Fri 9/24/21

168 Toilet Accessories 3 days Mon 9/27/21 Wed 9/29/21

4/1/21 Place 2nd Floor Concrete

4/2/21 Exterior Wall Framing 2nd Floor

4/2/21 Interior Wall Framing 1st Floor

4/16/21 Interior Wall Framing 2nd Floor

4/30/21 Soffit Framing

5/11/21 Exterior Wall Sheathing

5/27/21 Exterior Frames

5/27/21 Roofing, Skylights and Gutters

6/14/21 Set Rooftop HVAC Units

6/16/21 HVAC Gas and Condensate

6/8/21 Erect Scaffold

6/11/21 Windows/Storefronts

6/22/21 Exterior Wall Weather Barriers

7/6/21 Stucco

8/3/21 Remove Scaffold

8/5/21 Guard Rail/Hand Rails

8/5/21 Install Downspouts

8/5/21 Install Sunshades

8/5/21 Exterior Paint

4/30/21 MEPs

4/30/21 Fire Sprinkler Rough

5/13/21 Plumbing Rough

5/26/21 Electrical, LV, Fire Alarm Rough

6/11/21 Mechanical Rough

6/23/21 Rough MEP Inspection

10/14/216/24/21 Finishes

6/24/21 Insulation

6/29/21 Drywall First Floor

7/6/21 Drywall Second Floor

7/22/21 Elevator Install

7/15/21 Interior Paint First Floor

7/22/21 Interior Paint Second Floor

8/2/21 Ceiling Grid

8/16/21 Cabinets and Tops

8/25/21 Tack Wall

9/1/21 Window Shades

9/8/21 Floor Tile

9/8/21 Resin Floor Coating

9/13/21 Carpet

9/13/21 Ceramic Tile

9/20/21 Toilet Partitions

9/27/21 Toilet Accessories

2019 2020 2021 2022 2023 2024

2014

Page 4

Page 32: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

ID Task Name Duration Start Finish

169 Interior Doors and Hardware 5 days Wed 9/22/21 Tue 9/28/21

170 Plumbing Finish 5 days Mon 9/20/21 Fri 9/24/21

171 Drinking Fountains 3 days Mon 9/27/21 Wed 9/29/21

172 Drop Ceiling Tile 3 days Mon 9/27/21 Wed 9/29/21

173 Electrical, LV, Fire Alarm Finish 7 days Mon 9/27/21 Tue 10/5/21

174 Seal Concrete 4 days Wed 10/6/21 Mon 10/11/21

175 Signage 3 days Tue 10/12/21 Thu 10/14/21

176 Modernization 50 days Mon 6/8/20 Fri 8/14/20

177 Start Date (Manualy Inserted Date) 0 days Mon 6/8/20 Mon 6/8/20

178 Abatement 5 days Mon 6/8/20 Fri 6/12/20

179 Building H 42 days Mon 6/15/20 Tue 8/11/20

180 Protect All Items That Remain 1 day Mon 6/15/20 Mon 6/15/20

181 Selective Demo 2 days Tue 6/16/20 Wed 6/17/20

182 Door Install 2 days Thu 6/18/20 Fri 6/19/20

183 Exterior Patch and Paint 5 days Thu 6/18/20 Wed 6/24/20

184 Plumbing Rough 2 days Thu 6/18/20 Fri 6/19/20

185 Electric, LV, FA Rough 5 days Mon 6/22/20 Fri 6/26/20

186 HVAC Rough 2 days Mon 6/29/20 Tue 6/30/20

187 Walk In Refridgerator Rough In 5 days Wed 7/1/20 Tue 7/7/20

188 Wall Framing 2 days Wed 7/8/20 Thu 7/9/20

189 Insulation Where Applicable 1 day Fri 7/10/20 Fri 7/10/20

190 Drywall 5 days Mon 7/13/20 Fri 7/17/20

191 Door Install 3 days Mon 7/20/20 Wed 7/22/20

192 Interior Paint 4 days Mon 7/20/20 Thu 7/23/20

193 Door Hardware Install 2 days Thu 7/23/20 Fri 7/24/20

194 Cabinets Where Applicable 4 days Fri 7/24/20 Wed 7/29/20

195 Plumbing Finish 2 days Thu 7/30/20 Fri 7/31/20

196 Elect, LV, FA Finish 3 days Mon 8/3/20 Wed 8/5/20

197 HVAC Finish 2 days Thu 8/6/20 Fri 8/7/20

198 Walk In Refridgerator Details 2 days Mon 8/10/20 Tue 8/11/20

199 Clean Up 2 days Mon 8/10/20 Tue 8/11/20

200 Building A 25 days Fri 6/19/20 Thu 7/23/20

201 Protect All Items That Remain 1 day Fri 6/19/20 Fri 6/19/20

202 Selective Demo 2 days Mon 6/22/20 Tue 6/23/20

203 Install Facia 3 days Wed 6/24/20 Fri 6/26/20

204 Door Install 5 days Wed 6/24/20 Tue 6/30/20

205 Exterior Patch and Paint 5 days Wed 7/1/20 Tue 7/7/20

206 Electric, LV, FA Rough 5 days Wed 6/24/20 Tue 6/30/20

207 Interior Paint 4 days Wed 7/1/20 Mon 7/6/20

208 Door Hardware Install 3 days Tue 7/7/20 Thu 7/9/20

209 Cabinets Where Applicable 5 days Fri 7/10/20 Thu 7/16/20

210 Elect, LV, FA Finish 5 days Fri 7/17/20 Thu 7/23/20

9/22/21 Interior Doors and Hardware

9/20/21 Plumbing Finish

9/27/21 Drinking Fountains

9/27/21 Drop Ceiling Tile

9/27/21 Electrical, LV, Fire Alarm Finish

10/6/21 Seal Concrete

10/12/21 Signage

6/8/20 Modernization

6/8/20 Start Date (Manualy Inserted Date)

6/8/20 Abatement

6/15/20 Building H

6/15/20 Protect All Items That Remain

6/16/20 Selective Demo

6/18/20 Plumbing Rough

6/22/20 Electric, LV, FA Rough

6/29/20 HVAC Rough

7/1/20 Walk In Refridgerator Rough In

7/10/20 Insulation Where Applicable

7/13/20 Drywall

7/20/20 Door Install

7/20/20 Interior Paint

7/24/20 Cabinets Where Applicable

7/30/20 Plumbing Finish

8/3/20 Elect, LV, FA Finish

8/6/20 HVAC Finish

8/10/20 Walk In Refridgerator Details

6/19/20 Building A

6/19/20 Protect All Items That Remain

6/22/20 Selective Demo

6/24/20 Electric, LV, FA Rough

7/1/20 Interior Paint

7/7/20 Door Hardware Install

7/10/20 Cabinets Where Applicable

7/17/20 Elect, LV, FA Finish

2019 2020 2021 2022 2023 2024

2014

Page 5

Page 33: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

ID Task Name Duration Start Finish

211 Replace Blinds Where Applicable 3 days Fri 7/17/20 Tue 7/21/20

212 Exterior Roller Shades 2 days Wed 7/8/20 Thu 7/9/20

213 Clean Up 2 days Wed 7/22/20 Thu 7/23/20

214 Building B 25 days Thu 6/25/20 Wed 7/29/20

215 Protect All Items That Remain 1 day Thu 6/25/20 Thu 6/25/20

216 Selective Demo 2 days Fri 6/26/20 Mon 6/29/20

217 Install Facia 3 days Tue 6/30/20 Thu 7/2/20

218 Door Install 5 days Tue 6/30/20 Mon 7/6/20

219 Exterior Patch and Paint 5 days Tue 7/7/20 Mon 7/13/20

220 Electric, LV, FA Rough 5 days Tue 6/30/20 Mon 7/6/20

221 Drywall Repair 3 days Tue 6/30/20 Thu 7/2/20

222 Interior Paint 4 days Tue 7/7/20 Fri 7/10/20

223 Door Hardware Install 3 days Mon 7/13/20 Wed 7/15/20

224 Cabinets Where Applicable 5 days Thu 7/16/20 Wed 7/22/20

225 Elect, LV, FA Finish 5 days Thu 7/23/20 Wed 7/29/20

226 Replace Blinds Where Applicable 3 days Thu 7/23/20 Mon 7/27/20

227 VCT Tile 2 days Thu 7/23/20 Fri 7/24/20

228 Clean Up 2 days Thu 7/23/20 Fri 7/24/20

229 Building C 25 days Wed 7/1/20 Tue 8/4/20

230 Protect All Items That Remain 1 day Wed 7/1/20 Wed 7/1/20

231 Selective Demo 2 days Thu 7/2/20 Fri 7/3/20

232 Install Facia 2 days Mon 7/6/20 Tue 7/7/20

233 Door Install 5 days Mon 7/6/20 Fri 7/10/20

234 Exterior Patch and Paint 5 days Mon 7/13/20 Fri 7/17/20

235 Electric, LV, FA Rough 5 days Mon 7/6/20 Fri 7/10/20

236 Interior Paint 4 days Mon 7/13/20 Thu 7/16/20

237 Door Hardware Install 3 days Fri 7/17/20 Tue 7/21/20

238 Cabinets Where Applicable 5 days Wed 7/22/20 Tue 7/28/20

239 Elect, LV, FA Finish 5 days Wed 7/29/20 Tue 8/4/20

240 Replace Blinds Where Applicable 3 days Wed 7/29/20 Fri 7/31/20

241 Clean Up 2 days Wed 7/29/20 Thu 7/30/20

242 Building E 25 days Tue 7/7/20 Mon 8/10/20

243 Protect All Items That Remain 1 day Tue 7/7/20 Tue 7/7/20

244 Selective Demo 2 days Wed 7/8/20 Thu 7/9/20

245 Install Facia 3 days Fri 7/10/20 Tue 7/14/20

246 Door Install 5 days Fri 7/10/20 Thu 7/16/20

247 Exterior Patch and Paint 5 days Fri 7/17/20 Thu 7/23/20

248 Electric, LV, FA Rough 5 days Fri 7/10/20 Thu 7/16/20

249 Interior Paint 3 days Fri 7/17/20 Tue 7/21/20

250 Door Hardware Install 4 days Wed 7/22/20 Mon 7/27/20

251 Cabinets Where Applicable 5 days Tue 7/28/20 Mon 8/3/20

252 Elect, LV, FA Finish 5 days Tue 8/4/20 Mon 8/10/20

7/17/20 Replace Blinds Where Applicable

7/22/20 Clean Up

6/25/20 Building B

6/25/20 Protect All Items That Remain

6/26/20 Selective Demo

6/30/20 Door Install

7/7/20 Exterior Patch and Paint

6/30/20 Electric, LV, FA Rough

6/30/20 Drywall Repair

7/7/20 Interior Paint

7/13/20 Door Hardware Install

7/16/20 Cabinets Where Applicable

7/23/20 Elect, LV, FA Finish

7/23/20 Replace Blinds Where Applicable

7/23/20 VCT Tile

7/23/20 Clean Up

7/1/20 Building C

7/1/20 Protect All Items That Remain

7/2/20 Selective Demo

7/6/20 Door Install

7/13/20 Exterior Patch and Paint

7/6/20 Electric, LV, FA Rough

7/13/20 Interior Paint

7/17/20 Door Hardware Install

7/22/20 Cabinets Where Applicable

7/29/20 Elect, LV, FA Finish

7/29/20 Replace Blinds Where Applicable

7/29/20 Clean Up

7/7/20 Building E

7/7/20 Protect All Items That Remain

7/8/20 Selective Demo

7/10/20 Door Install

7/17/20 Exterior Patch and Paint

7/10/20 Electric, LV, FA Rough

7/17/20 Interior Paint

7/22/20 Door Hardware Install

7/28/20 Cabinets Where Applicable

8/4/20 Elect, LV, FA Finish

2019 2020 2021 2022 2023 2024

2014

Page 6

Page 34: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

ID Task Name Duration Start Finish

253 Replace Blinds Where Applicable 3 days Tue 8/4/20 Thu 8/6/20

254 Clean Up 2 days Tue 8/4/20 Wed 8/5/20

255 Building G 25 days Mon 7/13/20 Fri 8/14/20

256 Protect All Items That Remain 1 day Mon 7/13/20 Mon 7/13/20

257 Selective Demo 2 days Tue 7/14/20 Wed 7/15/20

258 Door Install 5 days Thu 7/16/20 Wed 7/22/20

259 Exterior Patch and Paint 5 days Thu 7/23/20 Wed 7/29/20

260 Electric, LV, FA Rough 5 days Thu 7/16/20 Wed 7/22/20

261 Interior Paint 3 days Thu 7/23/20 Mon 7/27/20

262 Door Hardware Install 4 days Tue 7/28/20 Fri 7/31/20

263 Cabinets Where Applicable 5 days Mon 8/3/20 Fri 8/7/20

264 Elect, LV, FA Finish 5 days Mon 8/10/20 Fri 8/14/20

265 Replace Blinds Where Applicable 3 days Mon 8/10/20 Wed 8/12/20

266 Clean Up 2 days Mon 8/10/20 Tue 8/11/20

267 Building I 17 days Fri 7/17/20 Mon 8/10/20

268 Protect All Items That Remain 1 day Fri 7/17/20 Fri 7/17/20

269 Selective Demo 2 days Mon 7/20/20 Tue 7/21/20

270 Door Install 3 days Wed 7/22/20 Fri 7/24/20

271 Exterior Patch and Paint 4 days Wed 7/22/20 Mon 7/27/20

272 Electric, LV, FA Rough 4 days Wed 7/22/20 Mon 7/27/20

273 Interior Paint 3 days Tue 7/28/20 Thu 7/30/20

274 Door Hardware Install 2 days Fri 7/31/20 Mon 8/3/20

275 Cabinets Where Applicable 2 days Tue 8/4/20 Wed 8/5/20

276 Elect, LV, FA Finish 3 days Thu 8/6/20 Mon 8/10/20

277 Clean Up 2 days Thu 8/6/20 Fri 8/7/20

278 Finish Site Work & Close Out 80 days Thu 7/1/21 Wed 10/20/21

279 Finish SD Branch Lines 7 days Thu 7/1/21 Fri 7/9/21

280 Excavate Bioswales 4 days Mon 7/12/21 Thu 7/15/21

281 Extend SD Lines to Downspouts 4 days Mon 7/12/21 Thu 7/15/21

282 Complete Subgrade for Concrete Amphitheater, Retaining Walls, Steps, Curbs, Stair Footings7 days Fri 7/16/21 Mon 7/26/21

283 Form, Rebar, Place Concrete at Amphitheater Steps , Retaining Walls, Steps, Curbs, Etc.20 days Wed 7/21/21 Tue 8/17/21

284 Complete Irrigation Lines and Control Wires 7 days Wed 8/4/21 Thu 8/12/21

285 Install Bollards 2 days Fri 8/13/21 Mon 8/16/21

286 Asphalt Subgrade,Paving, Signage, and Striping For New Parking Lot10 days Tue 8/17/21 Mon 8/30/21

287 Finish Grade For Concrete Flatwork 7 days Tue 8/17/21 Wed 8/25/21

288 Install Fence/ Gate Posts in Concrete Areas 2 days Tue 8/24/21 Wed 8/25/21

289 Install Walkway Canopy 7 days Tue 8/24/21 Wed 9/1/21

290 Complete Forms, Rebar, Placement of Remaining Site Concrete Flatwork14 days Thu 8/26/21 Tue 9/14/21

291 Install Handrails, Guardrails, Seats, Tables, And Benches 7 days Wed 9/15/21 Thu 9/23/21

292 Grade Landscape Areas 3 days Wed 9/15/21 Fri 9/17/21

293 Complete Fence and Gates 14 days Wed 9/15/21 Mon 10/4/21

294 Complete Irrigation, Soil Ammendments And Planting 12 days Tue 10/5/21 Wed 10/20/21

8/4/20 Replace Blinds Where Applicable

8/4/20 Clean Up

7/13/20 Building G

7/13/20 Protect All Items That Remain

7/14/20 Selective Demo

7/16/20 Door Install

7/16/20 Electric, LV, FA Rough

7/23/20 Interior Paint

7/28/20 Door Hardware Install

8/3/20 Cabinets Where Applicable

8/10/20 Elect, LV, FA Finish

8/10/20 Replace Blinds Where Applicable

8/10/20 Clean Up

7/17/20 Building I

7/17/20 Protect All Items That Remain

7/20/20 Selective Demo

7/22/20 Door Install

7/22/20 Exterior Patch and Paint

7/22/20 Electric, LV, FA Rough

7/28/20 Interior Paint

7/31/20 Door Hardware Install

8/4/20 Cabinets Where Applicable

8/6/20 Elect, LV, FA Finish

8/6/20 Clean Up

7/1/21 Finish Site Work & Close Out

7/12/21 Excavate Bioswales

7/12/21 Extend SD Lines to Downspouts

7/16/21 Complete Subgrade for Concrete Amphitheater, Retaining Walls, Steps, Curbs, Stair Footings

7/21/21 Form, Rebar, Place Concrete at Amphitheater Steps , Retaining Walls, Steps, Curbs, Etc.

8/13/21 Install Bollards

8/17/21 Asphalt Subgrade,Paving, Signage, and Striping For New Parking Lot

8/17/21 Finish Grade For Concrete Flatwork

8/24/21 Install Walkway Canopy

8/26/21 Complete Forms, Rebar, Placement of Remaining Site Concrete Flatwork

9/15/21 Install Handrails, Guardrails, Seats, Tables, And Benches

9/15/21 Grade Landscape Areas

9/15/21 Complete Fence and Gates

2019 2020 2021 2022 2023 2024

2014

Page 7

Page 35: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

ID Task Name Duration Start Finish

295 Remove Temporary Construction Road & Grade 4 days Mon 9/20/21 Thu 9/23/21

296 Restore Sprinklers At Grass Field 5 days Fri 9/24/21 Thu 9/30/21

297 Hydroseed Grass Area 1 day Fri 10/1/21 Fri 10/1/21

298 Testing, Punch List, Close Out 23 days Wed 10/6/21 Fri 11/5/21

299 Commission HVAC Systems 5 days Wed 10/6/21 Tue 10/12/21

300 Install Owner Supplied Data Equipment 7 days Wed 10/6/21 Thu 10/14/21

301 Demobilize Office, Containers, and Restore to Existing Conditions3 days Wed 10/6/21 Fri 10/8/21

302 Punch List And Completion 20 days Wed 10/6/21 Tue 11/2/21

303 Clean Up 3 days Wed 11/3/21 Fri 11/5/21

304 Beneficial Occupancy 0 days Fri 11/5/21 Fri 11/5/21

9/20/21 Remove Temporary Construction Road & Grade

10/1/21 Hydroseed Grass Area

10/6/21 Testing, Punch List, Close Out

10/6/21 Commission HVAC Systems

10/6/21 Install Owner Supplied Data Equipment

10/6/21 Demobilize Office, Containers, and Restore to Existing Conditions

10/6/21 Punch List And Completion

11/3/21 Clean Up

11/5/21

2019 2020 2021 2022 2023 2024

2014

Page 8

Page 36: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-6

CEQA MITIGATION MONITORING OR REPORTING PROGRAM (ATTACHED BEHIND THIS COVER PAGE)

Page 37: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

916.930.0736 P2015 H Street, Sacramento, CA 95811 916.930.0788 F

Taft Community School MMRP Page | 1

Redwood City School District (RCSD)Taft Community School Modernization Project

Mitigation Monitoring Reporting Program (MMRP)Environmental

Factors Potentially Affected

Mitigation MeasureResponsible

PartyTimeline for Implementation

BiologicalResources

MM 1) Migratory Bird Treaty Act Tree removal and construction activities shall be scheduled to commence prior to the beginning of nesting activity (March 1) or after fledging (August 15). If this is infeasible, the District shall retain a biologist to conduct pre-construction surveys between March 1 and August 15 in potential nesting habitat to identify nest sites. Surveys should be conducted within one week of tree removal and the start of construction to identify active nests prior to the initiation of construction activities. If an active raptor nest is observed within 350 feet of the Project Site, the District shall contact California Department of Fish and Wildlife (CDFW) for guidance and/or establish a 350-foot buffer around the nest tree. If a passerine bird nest is observed within 100 feet of the Project Site, the District shall contact CDFW for guidance and/or establish a 100-foot buffer around the nest tree. If construction activities cannot be prohibited within the established buffers until young have fledged, District consultation with CDFW shall be conducted for a reduced buffer zone based on nesting phenology, site conditions, and recommendation(s) of a biological monitor. The District shall prohibit construction activities in the buffer zone until the young have fledged.

District appointed

Construction Superintendent

Prior to construction if tree removal to occur during

nesting season

Cultural Resources

MM 2) Archaeological SignageIn accordance with guidelines section §15064.5, the School District will ensure that the following language is included in all construction contracts and permits: “If archaeological resources are accidentally discovered during construction, work will be halted within 50 feet of the find until it can be evaluated by a qualified professional archaeologist. If the find is determined to be significant, appropriate mitigation measures will be formulated and implemented.”

District appointed

Construction Superintendent

Prior to any ground

disturbing activities

Page 38: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

916.930.0736 P2015 H Street, Sacramento, CA 95811 916.930.0788 F

Taft Community School MMRP Page | 2

Cultural Resources

MM 3) Communication of Archaeological Site Deposit Indicators All construction personnel involved in site clearing, subsequent grading, and trenching will be informed of the potential for subsurface cultural resource unearthing. Indicators ofarchaeological site deposits include but are not limited to the following: Soil that is darker than the surrounding soils, evidence of fire (ash, fire altered rock and earth, carbon flecks, concentrations of stone, bone and shellfish, artifacts of these materials and animal or human burials.

District appointed

Construction Superintendent

Prior to any ground

disturbingactivities

Cultural Resources

MM 4) In the Event of Cultural Resources DiscoveredIf cultural resources are encountered during Site grading, or construction activities, all work shall be halted within 50 feet of the discovery and RCSD shall engage a qualified archaeologist to assess and protect the discovery as appropriate. No further soil disturbance shall occur within the 50-foot buffer until the preceding assessment has been completed and the resource has been recovered.

District appointed

Construction Superintendent

Prior to and during any

ground disturbing activities

Cultural Resources

MM 5) Paleontological Construction Contracts and Permits LanguageDue to the possibility that significant buried paleontological resources may be found during construction activities, the Redwood City School District will ensure that the following language is included in all construction contracts and permits:“If paleontological resources are encountered during subsurface construction activities, all work within 50 feet of the discovery will be redirected until a qualified paleontologist can evaluate the finds and make recommendations. If the paleontological resources are found to be significant, they will be avoided by project construction activities and recovered by a qualified paleontologist. Upon completion of the recovery, a paleontological assessment will be conducted by a qualified paleontologist to determine if further monitoring for paleontological resources is required. The assessment will include:I) The results of any geotechnical investigation prepared for the project site;2) Specific details of construction plans for the project site;3) Background research; and4) Limited subsurface investigation within the project site.If a high potential to encounter paleontological resources is confirmed, a monitoring plan of further project subsurface construction will be prepared in conjunction with this assessment. After project subsurface construction has ended, a report documenting monitoring, methods, findings, and further recommendations regarding paleontological resources will be prepared.”

District appointed

Construction Superintendent

Prior to any ground

disturbing activities

Page 39: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

916.930.0736 P2015 H Street, Sacramento, CA 95811 916.930.0788 F

Taft Community School MMRP Page | 3

Cultural Resources

MM 6) Policies and Procedures for Inadvertently Discovered Human Remains Because site disturbance may adversely impact undocumented human remains or unintentionally discover significant historic or archaeological materials, the following policies and procedures for treatment and disposition of inadvertently discovered human remains or archaeological materials will apply. If human remains are discovered, it is probable they are the remains of Native Americans.

a) If human remains are encountered, these remains would be treated in accordance with Section 7050.5 of the California Health and Safety Code and Section 5097.98 of the Public Resources Code, as appropriate. With these regulations in place, no impact on human remains is anticipated.

b) In the event that known or suspected Native American remains are encountered, or significant historic or archaeological materials are discovered, ground-disturbing activities will be immediately stopped. Examples of significant historic or archaeological materials include, but are not limited to, concentrations of historic artifacts (e.g., bottles, ceramics) or prehistoric artifacts (chipped chert or obsidian, arrow points, ground stone mortars and pestles), culturally altered ash-stained midden soils associated with pre-contact Native American habitation sites, concentrations of fire-altered rock and/or burned or charred organic materials, and historic structure remains such as stone-lined building foundations, wells or privy pits. Ground-disturbing project activities may continue in other areas that are outside the discovery locale.

c) An “exclusion zone” where unauthorized equipment and personnel are not permitted will be established (e.g., taped off) around the discovery area plus a reasonablebuffer zone by the Contractor Foreman or authorized representative, or party who made the discovery and initiated these protocols, or if on-site at the time or discovery, by the Monitoring Archaeologist (typically 25-50ft for single burial or archaeological find).

d) The discovery locale will be secured (e.g., 24-hour surveillance) as directed by the School District if considered prudent to avoid further disturbances.

e) The Contractor, Foreman, authorized representative, or party who made the discovery and initiated these protocols will be responsible for immediately contacting by telephone the parties listed below to report the find and initiate the consultation process for treatment and disposition:

• The Redwood City School District Superintendent, John Baker

District appointed

Construction Superintendent

During any ground

disturbing activities

Page 40: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

916.930.0736 P2015 H Street, Sacramento, CA 95811 916.930.0788 F

Taft Community School MMRP Page | 4

(650) 482-2200• The Contractor’s Point(s) of Contact • The Coroner of the County of San Mateo (if human remains found)

(650) 312-5562f) The Coroner has two working days to examine the remains after being notified of

the discovery. If the remains are Native American, the Coroner has 24 hours to notify the NAHC.

g) After notification by the NAHC, the MLD will be granted permission to inspect the discovery site if they so choose.

h) After notification by the NAHC, the MLD may recommend to the Administrator of District Support Services the recommended means for treating or disposing, with appropriate dignity, the human remains and any associated grave goods. The MLD has 48 hours after accessing the Site to make recommendations to the property owner as specified in Public Resources Code section 5097.98 (a). The recommendation may include the scientific removal and nondestructive or destructive analysis of human remains and items associated with Native American burials.

i) If the MLD recommendation is rejected by the School District the parties will attempt to mediate the disagreement with the NAHC. If mediation fails, then the remains and all associated grave offerings will be reburied with appropriate dignity on the property in a location not subject to further subsurface disturbance.

Geology and Soils

MM 7) Seismic Design CriteriaDue to the significant potential for strong ground motion at the Project Site, the District shall implement section 10.2 of the Geotechnical report performed by Ninyo & Moore Geotechnical & Environmental Sciences Consultants. The RCSD shall incorporate the geotechnical recommendation for design and construction of the proposed project. This includes earthwork recommendations, seismic design criteria, foundation recommendations, retaining wall, exterior flatwork, concrete, moisture vapor retarder, and surface drainage and site maintenance; see Geotechnical Evaluation and Geologic HazardAssessment at Appendix G.

District appointed

ConstructionSuperintendent

Prior to the start of construction

activities

Page 41: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

916.930.0736 P2015 H Street, Sacramento, CA 95811 916.930.0788 F

Taft Community School MMRP Page | 5

Geology and Soils

MM 8) Expansive SoilsTo Reduce the potential for differential movement and distress, the recommendations provided in the Geotechnical Evaluation and Geologic Hazard Assessment performed by Ninyo & Moore shall be implemented to improve shrink/swell behavior for remedial grading, foundation embedment depths, and subgrade preparation during projectexecution; see section 10 of the Geotechnical report, attached hereto as Appendix G.

District appointed

ConstructionSuperintendent

Prior to the start of construction

activities

Hazards and Hazardous Materials

MM 9) SMP: Remediation and Site ManagementThe District shall follow the protocols outlined in the Soil Mitigation Plan (SMP) completed by McCloskey Consultants, Inc. on December 19, 2018. The proposed removal activities shall be performed by a California-certified contractor appointed by the District to assist with the following activities: Site-specific health and safety worker requirements, pre-field activities, site control, excavation of impacted soil, dust and erosion control, air monitoring, decontamination, field documentation, and confirmation soil sampling; see SMP at Appendix J.

DistrictSuperintendent,

District appointed

hazardous waste contractor, and

Districtappointed California-

certifiedcontractor

Prior to SMPactivities

Hazards and Hazardous Materials

MM 10) SMP: Site-Specific Health and Safety Worker RequirementsDistrict appointed contractors shall be responsible for the health and safety of their own employees and are required to have their own Health and Safety Plan (HSP) and Injury and Illness Prevention Plans (IIPPs) to comply with OSHA. The HSP shall be implemented at the Site. Contractors may utilize the HSP provided in the SMP, Appendix D, as a template to create their company-specific HSP. The HSPs shall provide general health and safety guidance such that field activities can be conducted in a safe manner. Per Cal/OSHA requirements (California Code of Regulations, Title 8), each contractor working at the Site shall prepare a health and safety plan that addresses the safety and health hazards during each phase of Site operations that includes the requirements and procedures for employee protection. The HSPs will provide standard operating procedures for personnel involved in activities that may expose them to chemical and physical hazards associated with the removal of impacted soil at the Site. The plan must be kepton-Site during soil removal and loading activities. Prior to conducting work on-Site, project management and field staff must be familiar with the contents of the HSP; see SMP at Appendix J.

Districtappointedcontractors

Prior to and during SMP

activities

Page 42: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

916.930.0736 P2015 H Street, Sacramento, CA 95811 916.930.0788 F

Taft Community School MMRP Page | 6

Hazards and Hazardous Materials

MM 11) SMP: Pre-Field ActivitiesSeveral pre-field activities shall be required prior to the initiation of Site removal activities. Pre-field activities include permitting, utility clearance, work zone designation, and set up of support zones/staging areas. These pre-field activities shall be performed as outlined in the SMP; see SMP at Appendix J.

Districtappointedcontractors

Prior to SMPactivities

Hazards and Hazardous Materials

MM 12) SMP: Site ControlSite control is intended to control the potential spread of contamination from the Site. The affected area shall be separated from the public by a temporary fencing, to be installed by the remediation contractor. Prior to field activities, the Site will be divided into three zones: exclusion zone, decontamination zone, and support zone. Within the exclusion zone are individual work zones where contaminated material is being excavated, stockpiled, or loaded. Ingress to and egress from the Site will be controlled via locking gates. The excavated soil will be stockpiled at the closest available area on plastic sheeting; see SMP at Appendix J.

Districtappointedcontractors

Prior to and during SMP

activities

Hazards and Hazardous Materials

MM 13) SMP: Excavation of impacted soilThe District appointed contractor shall be responsible for assisting the District with excavation/relocation procedures, stockpiling of soil, truck loading procedures, and transportation procedures. Soil excavation activities will remove approximately 115 cubic yards of pesticide and metal containing soil and transportation of the material to off-Site disposal facilities. For arsenic and pesticide removal areas, the initial excavations are estimated to be 1 to 1½ feet deep and include portion of one side of existing structures, two areas in the garden/outdoor classroom and one area on the southwestern portion of the Site. The depths of the excavations are estimated, and contamination may be present in deeper soils in limited areas. These areas will be determined after the initially planned excavations and confirmation sampling. The estimated yardage includes a contingency that additional soil (up to 30%) may need to be excavated should some confirmation samples have contaminants that exceed the Site remediation goal concentrations. Site grading and the construction of the new school buildings shall not take place until after the remedial activities; see SMP at Appendix J.

Districtappointedcontractors

Prior to and during SMP

activities

Hazards and Hazardous Materials

MM 14) SMP: Dust and Erosion ControlSite control procedures shall be established to control the potential generation of dust andexposure to worker and Site neighbors. These controls include a variety of dust control methods and practices designed to minimize the generation and spread of dust. A water truck or other source of water shall be used to deliver water to the Site for dust control

Districtappointedcontractors

Prior to and during SMP

activities

Page 43: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

916.930.0736 P2015 H Street, Sacramento, CA 95811 916.930.0788 F

Taft Community School MMRP Page | 7

purposes. Experience at similar sites in the area has shown that if good dust control is maintained, dust emissions can be kept below action levels. Air monitoring shall be conducted by a Hazmat Consultant to control dust emissions during Site remedial activities. The dust control measures are outlined in the SMP and shall be followed at all times during remedial activities; see SMP at Appendix J.

Hazards and Hazardous Materials

MM 15) SMP: Air MonitoringAir monitoring will be performed by a Hazmat Consultant along the perimeter of the Site to evaluate the effectiveness of the dust control measures. Details of the air monitoring trigger and action levels are summarized in the SMP. If the Trigger Level of “visible dust” is reached, dust control measures must be increased visible dust is not present. Work shall stop if the action levels of 0.05 mg/m3 is reached, exceeded, or the Site cannot be reliably controlled. If the Action Levels are exceeded, the District project manager shall be notified immediately; see SMP at Appendix J.

Districtappointedcontractors

During SMPactivities

Hazards and Hazardous Materials

MM 16) SMP: DecontaminationAs stated in the SMP, decontamination procedures shall be followed before equipment or personnel exit the exclusion zone as part of general protocols for preventing or reducing the physical transfer of impacted materials from the affected areas. The District appointed contractor shall be responsible for assisting the District with equipment decontamination, track-out controls, and worker decontamination protection; see SMP at Appendix J.

Districtappointedcontractors

During SMPactivities

Hazards and Hazardous Materials

MM 17) SMP: Field DocumentationA McCloskey Consultant, Inc. (MCI) field engineer shall be present on-Site on an as-needed basis during the chemically-affected soil excavation, perimeter dust monitoring, and dust handling activities. This individual shall monitor the soil excavation work, collect confirmation soil samples, perimeter air monitoring and collect stockpile soil samples. As part of this process, a field log shall be utilized to document Site activities. A scaled Site map shall be implemented to document removal areas and confirm sampling locations. Site activities shall be photographed periodically by MCI to document implementation of the removal activities. The photographs shall be made available for inspection by District authorized personnel for the duration of the project and shall be included in the Removal Action Completion Report; see SMP at Appendix J.

Districtappointedcontractors

During SMPactivities

Page 44: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

916.930.0736 P2015 H Street, Sacramento, CA 95811 916.930.0788 F

Taft Community School MMRP Page | 8

Hazards and Hazardous Materials

MM 18) SMP: Confirmation Soil SamplingIn accordance with the SMP, confirmation soil samples shall be collected from the bottom and sidewalls of the excavation areas to document adequate removal of COC contaminated soils; see SMP at Appendix J.

Districtappointedcontractors

During SMPactivities

Hydrology and Water Quality

MM 19) Stormwater Pollution Prevention PlanThe District shall obtain discharge authorization under an appropriate National Pollutant Discharge Elimination System (NPDES) and shall ensure implementation of a Stormwater Pollution Prevention Plan (SWPPP) to abide by water quality standards and waste discharge requirements.

Districtappointed Civil

Engineer or Architect

andappointed

ConstructionSuperintendent

Prior to the start of construction

andprior to

occupancy of school

Noise

MM 20) Noise Suppression Attachments and Minimal IdlingThe contractor shall employ appropriate noise suppression attachments (e.g., mufflers,etc.) on all equipment. Equipment idling shall be kept to a minimum and equipmentturned off when not in use. Project activities shall not operate at more than 110 dB and are limited to the hours of 7:00 a.m. to 5:00 p.m. Monday through Friday of any week.

District appointed

Construction Superintendent

During construction

Tribal Cultural Resources

MM 21) Avoidance and Preservation of Tribal Cultural ResourcesIn the event that tribal cultural resources are discovered, the District shall practice avoidance and preservation of tribal cultural resources in place. This includes, but is not limited to, planning and construction to avoid the resources and protect the cultural and natural context, or planning greenspace, parks, or other open space, to incorporate the resources with culturally appropriate protection and management criteria. The District shall treat the resources with culturally appropriate dignity taking into account the tribal cultural values and meaning of the resource, including, but not limited to protection of the cultural character & integrity of the resource, protection of the traditional resource use, and protection of confidentiality regarding the resource. Where necessary, the District shall implement the use of permanent conservation easements or other interests in real property, with culturally appropriate management criteria for the purposes of preserving or utilizing the resources or places.

District appointed

Construction Superintendent

During any ground

disturbing activities

Page 45: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-7

SCOPE STATEMENTS

The attached Scope Statements describe the intent and outline of work to be completed as a part of this bid. In the event that this scope statement contains sequences, scope, work functions, materials or equipment not generally related to the technical specifications associated with the work of this bid, the Scope Statement shall govern in the assignment of work and/or the responsibility of furnishing and/or installing materials or services in addition to the materials and services named in the plans and specifications. The Scope Statement is provided as a guide and describes the minimum scope of construction activities and/or service to be provided and/or material and equipment to be furnished/installed and unless explicitly directed otherwise within the Scope Statement, this bid shall require the furnishing and installation of all materials or equipment identified within the Scope Statement. This work will be conducted by multiple prime contractors. The owner reserves the right to perform work related to the Project with the Owner’s own forces, and to award separate contracts in connection with other portions of the Project or other construction or operations on the Site under Conditions of the Contract identical or substantially similar to these including those portions related to insurance and waiver of subrogation. The bidder shall have thoroughly examined all bid documents relative to the execution of the bid as submitted and is expected to have visited the site of the work to determine all conditions effecting the execution of the work of this bid. The bidder shall have obtained first-hand knowledge of the site relative to the receiving, transportation, handling and storage of material or equipment and all other concerns related to the requirements of the bidding documents. It being further understood that no additional compensation will be allowed for the failure of the bidder to have availed himself/herself of this information or the procedures as outlined herewith. Site visitation will be as conducted during the pre-bid conference. Additional visits may be arranged if cleared and coordinated through the project manager. Alternates may be included in the bid for this work. See the Bid Form and Proposal and the Contract Drawings for definitions of required alternates. Failure to price alternates shall be grounds for finding the Bid non-responsive. Unit Price Allowances may be included in the bid for this work. See the Bid Form and Proposal and the Contract Drawings for definitions of Unit Price Allowances. Failure to price unit price allowances and include the total in your base bid shall be grounds for finding the Bid non-responsive. When separate contracts are awarded for different portions of the Project or other construction or operations on the Site, the term “Contractor” in the Contract documents in each case shall mean the Contractor who executes each separate Owner/Contractor Agreement. The Contractor shall afford the Owner and separate contractor’s reasonable opportunity for delivery and storage of their materials and equipment and performance of their activities and shall connect and coordinate the separate contractors’ construction and operations with theirs as required by the Contract Documents. If part of the Contractor’s Work depends upon proper execution or results from work by the Owner or a separate contractor, the Contractor shall, prior to proceeding with that portion of its Work, promptly report in writing to the Construction Manager apparent discrepancies or

Page 46: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-8

defects in such other construction that would render Contractor unable to perform that portion of its Work. Failure of the Contractor to so report shall constitute an acknowledgment that the Owner’s or separate contractors completed or partially completed construction is fit and proper to receive the Contractor’s Work, except as to defects not then reasonably discoverable. The Contractor will check drawing information against actual field conditions. Inspect related work and interfaces of all conditions that prevent proper execution of the Work of this bid package. Tests and inspections are to be provided by the District unless otherwise noted in the Technical Specifications. Contractor’s requiring specific tests are to make required notifications and schedule required tests.

Page 47: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-9

SCOPE STATEMENTS (ATTACHED BEHIND THIS COVER PAGE)

Page 48: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-10

SCOPE STATEMENT – Bid Package A, Earthwork and Paving Trades TAFT COMMUNITY SCHOOL - NEW BUILDINGS, MODERNIZATION & SITEWORK ALL SCOPE OF WORK DEFINED BELOW AND IN ACCORDANCE WITH THE CONTRACT DRAWINGS, DIVISION OO, DIVISION O1, DSA 103 Statement of Structural Tests and Special Inspections,

AND TECHNICAL SPECIFICATION SECTIONS: 024113, 024116, 079200, 310000, 311000, 312333, 321233, 321713, 321723

DRAWINGS: Taft Community School - New Buildings, Modernization & Sitework applicable drawings and details as they pertain to the Scope of Work designated below. Required scope and details for this bid package may be shown on General, Civil, Landscape, and Architectural drawings.

DESCRIPTION: Project will be phased per the construction schedule included herein. Furnish all labor, materials, equipment and services required for the above listed specification sections covering related work as per project plans and specifications and as described below:

S C O P E O F W O R K

SECTION A - GENERAL ITEMS; SPECIAL ATTENTION SHOULD BE GIVEN TO THE FOLLOWING:

1. Overhead, bonds and insurance: Contractor shall include all costs for home office overhead, field overhead, performance and payment bonds and insurance as required in the contract documents.

2. Security: Contractor will be responsible for compliance with Department of Justice requirements for school construction. All on site employees will be required to wear a construction badge or be escorted or accompanied by a badged contractor or school district representative through non construction areas.

3. The Construction Manager shall provide a debris box for general cleanup. Contractors will be required to clean up daily and load their trash in the debris box. Job clean-up will be at the direction of the Construction Manager. Note: If demolition is called for in Contractor’s scope of work, Contractor is responsible for providing his own debris box and removing all demolition debris from the site in a timely manner, but in no case longer than seven (7) days from the date of demolition. The Construction Manager’s debris box shall not be used for depositing selective demolition debris.

4. The Construction Manager shall provide portable toilets and hand wash stations. 5. Earthwork and Paving Trades Contractor shall be responsible for their own scaffolding,

lifts, and hoists. 6. The Construction Manager will provide temporary fencing around the jobsite perimeter,

as necessary. Contractor will be responsible for maintaining if relocated and/or disassembled.

7. Earthwork and Paving Trades Contractor shall be responsible for maintaining safety compliance and weekly safety meetings.

8. Earthwork and Paving Trades Contractor shall be responsible for their own phone service and drinking water.

Page 49: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-11

9. Earthwork and Paving Trades Contractor employees will park in parking spaces or designated parking area identified by the Construction Manager.

10. Earthwork and Paving Trades Contractor shall be required to coordinate their work with other Prime Contractors, attend weekly coordination meetings and provide 3 week look ahead schedule and daily Task(s), manpower and equipment reports.

11. Time is of the essence on this project. Earthwork and Paving Trades Contractor shall adhere to the Construction Schedule as provided by Construction Manager and may be financially responsible for delays to the schedule in accordance with the contract.

12. Earthwork and Paving Trades Contractor shall refer to the Contractor Access, Laydown and Staging Plan for limits of construction, temporary power and water location. Specific areas for laydown and staging for each trade shall be as determined by the Construction Manager.

13. Earthwork and Paving Trades Contractor shall ensure a superintendent or foreman who is an employee of the contractor shall be present at all times while contractor or subcontractor workers are on site.

14. Earthwork and Paving Trades Contractor shall ensure payment of prevailing wages and timely submission of certified payrolls for all contractor employees and subcontractors.

15. Earthwork and Paving Trades Contractor shall protect from damage to all existing utilities, trees, buildings, hardscape and landscaping to remain.

16. Earthwork and Paving Trades Contractor shall review all Trade Scope Statements carefully and understand other Prime Contractors’ responsibilities. Contractor shall request pre-bid clarifications for items that are missing in scope, repeated in scopes, or may require coordination.

17. Earthwork and Paving Trades Contractor shall be responsible for cleaning pavement and streets from dirt and debris due to their work. Contractors will provide daily clean-up for their work.

18. Any contractor that disturbs SWPPP measures is responsible for returning them to their previous conditions.

19. All Prime Trades Contractors and their Sub-Contractors shall follow, maintain, repair and or replace Erosion Control and storm water pollution prevention measures (BMPs) as their work impacts the established BMP’s as per plans and at the direction of the Construction Manager.

20. All Trades Contractors and your subcontractors will strictly comply with all SWPPP, BMP, CEQA, MND, MMRP, SMP, HazMat, Geological, survey(s), Drawings reports managing measures as it applies to your work. If you disrupt or expose a previously protected and contained element or component during your construction processes, you are required to restore, protect and or contain the affected area(s) restoring the integrity of the area(s) disrupted or exposed as described within the above mentioned documents and as identified by the Construction Management Team.

21. Any and All Contractors off-hauling Soils, Concrete and Asphalt, are to follow the specific guidelines set forth within the Site Specific CEQA and Geotechnical report including MND, MMRP, and SMP Reports.

22. All Trades Contractors must adhere and comply with and to the findings and recommendations stated in the Geotechnical Evaluation and Geologic Hazard Assessment Report(s) including its Addendum 1 provided by Ninyo and Moore (project #402965006, dated December 11, 2017 & November 16, 2018) and at the direction of The District. This statement supersedes any contradictory verbiage which may be in the contract documents.

Page 50: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-12

SECTION B – SPECIFIC ITEMS FOR THIS BID PACKAGE:

Do not exclude any of the following from your bid. Exclusions of any items may render your bid non-responsive.

1. Work is scheduled for a 5-day work week per the attached schedule. Overtime and weekend work is not mandatory unless where designated on the project schedule, however contractor shall ensure sufficient straight time manpower is provided to complete tasks within the durations indicated. If work is delayed due to circumstances beyond the contractor’s control, then the construction manager may adjust the schedule or authorize overtime via change order in order to maintain the schedule.

2. Provide for costs of bonds, insurance, secure equipment and materials storage, provide supervision of sub-trade contractor labor, coordination with other trade contractors, safety, Cal-OSHA approved protection, costs for DOJ background checks, copying, telephones and fax service, office trailers and temporary utilities if needed (location to be determined by Construction Manager), computers and printers.

3. All Trades Contractors shall provide required submittals, shop drawings, RFI’s, PCO’s and any required documents through “ColbiDocs”, The District’s online document processing program.

4. Earthwork and Paving Trades Contractor must recycle building materials and waste to their fullest extent.

5. All contractors are required to submit certified payroll for their forces as well as sub tier trades directly to the Department of Industrial Relations. Contractors and subcontractors will be required to register and submit payroll reports electronically.

6. Earthwork and Paving Trades Contractor must provide survey staking and layout of Earthwork and Paving Contractors work.

7. Earthwork and Paving Trades Contractor shall include two days of utility locating service.

8. Earthwork and Paving Trades contractor must coordinate with Geotechnical Consultant and IOR for all compaction tests and inspections.

9. Earthwork and Paving Trades Contractor shall include all allowances and unit price items in bid as called for in this scope statement and on the bid form.

10. Earthwork and Paving Trades contractor shall abate and demo all items with less than 1% contamination and dispose of debris as appropriate, (Abatement of Lead and Asbestos greater than 1% shall be done by the Abatement Trades Contractor) per ProTech Consulting & Engineering report.

11. Earthwork and Paving Trades Contractor must phase their demo work to accommodate the transitioning of (E) MSB and (N) MSB electrical to the school, at the direction of the Construction Manager. (Note: The school must have continuous power for all operations for all areas outside the construction site. Temporary power for construction will be provided by the Electrical & Low Voltage contractor.)

12. Earthwork and Paving Trades Contractor and/or their Subcontractors is required to have proper DOSH Certification and provide disclosure of said certification upon disposal of unregulated materials with less than 1% contamination as needed at an appropriate disposal site per Section “A” of this document.

13. All Trade Contractors will replace in kind the winterization rock when disturbed by their work.

Drawings Specific Scope of work: (NOTE ALL ITEMS IN RED ADDED DURING ADDENDUM 1 & 3) 1. Earthwork and Paving Trades Contractor shall excavate and remove soils specified by

the site control plan within the soils mitigation plan and dispose of soils to an

Page 51: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-13

appropriate landfill per requirements stated in section “A item #’s 20 & 21 of this document.

2. Earthwork and Paving Trades Contractor shall provide initial set up of erosion control per, but not limited to the erosion control plans, see plan sheets C9.0, C9.1, and C9.2, phasing as directed by the Construction Manager.

3. Earthwork and Paving Trades Contractor shall sawcut, demolish and remove existing site AC, concrete, curbs, landscaping, chain link fence and other site improvements within demo limits indicated on the plans. (Some fencing will stay in place for security purposes & is to be removed in phases at the direction of the Construction Manager.)

4. Note: Any additional site demolition not shown in plans and only as directed by the authorized District representative will be compensated as terms and costs are determined at time of identification of work.

5. All excavation spoils are to be removed to an appropriate landfill per requirements stated in section “A item #’s 20 & 21” of this document

6. All demolition materials are to be removed from the site and recycled as applicable. 7. Protect or Remove trees as identified on plans and maintain tree protection as outlined

in Sec. 015639 and as it pertains to any of your specific work areas you have impacted. 8. Earthwork and Paving Trades Contractor shall perform all site, building, canopy and

associated foundation demolition. Also, site clearing within limits of work shown on the demolition drawings (ASD-01, ASD-02, ASD-121, PSD-01, PSD-02, S9.1, S9.2, C3.0, C3.1).

9. Earthwork and Paving Trades Contractor will remove all abandoned utilities, underground electrical, storm drain, sanitary and irrigation lines as discovered. Excavations to be backfilled and compacted per the Geotechnical Report.

10. Safe-off of storm drain, sanitary sewer, gas and waterlines are the responsibility of the UG Utilities contractor. Safe off of electrical by Electrical contractor. New utility trenches and backfill is the responsibility of the respective UG Utilities, Landscaping and Electrical contractors.

11. Earthwork and Paving Trades Contractor will perform all site clearing, subgrade preparation and compaction for all the building pads, site AC, concrete walls, vertical curbs, concrete planters, decomposed granite, pervious concrete paving and concrete paving. Provide engineered fill including applicable base rock for sidewalks, flatwork and AC paving as per plans & specs. Provide compaction of subgrade and fill material to specified standards per the Geotechnical report and plans & Specs. Screen and remove rocks in backfill material per the Geotechnical report.

12. Earthwork and Paving Trades Contractor shall provide grade checking to set accurate grades for building sites, elevation transitions, retaining walls, site concrete, concrete curbs, seat walls, and bio-retention areas and AC paving. Provide remobilizations as necessary to accommodate site grade & pave activities. Coordinate closely with All Other Trade Contractors.

13. Earthwork and Paving Trades Contractor shall perform over-excavation, back fill and compaction for all building pads and structures per the geotechnical report and plans.

14. Provide fine grading associated with re-establishing site concrete subgrade. Coordinate closely with Site Concrete Trades Contractor.

15. Earthwork and Paving Trades Contractor shall perform excavation for all bioretention systems at bioretention areas. (Note: The U.G. Utilities Trades Contractor will provide perforated piping, drain inlets, and class II permeable rock, and river rock, The Landscaping Trades Contractor will provide the biotreatment soil mix and the planting, The Site Concrete Trades Contractor will provide concrete planter boxes as needed).

16. Earthwork and Paving Trades Contractor will provide all AC pavement work, including header boards transitioning your work with any others, vehicular Wheel Stops, Parking lot/ADA striping and Signage. (Note: Decorative or Playground striping, and door swing

Page 52: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-14

caution lines are the responsibility of the GC. Painting for concrete curbs is the responsibility of the site concrete trades contractor.) Earthwork & Paving Contractor to coordinate with GC and site concrete trades.

17. Earthwork and Paving Trades Contractor shall provide and install joint sealants and expansion joint caulking related to Earthwork and Paving as specified.

18. The district will pay or reimburse for city street AC paving improvements permit fee and the Earthwork and Paving Trades Contractor will apply and obtain the permit and perform work per plans.

19. Earthwork and Paving Trades Contractor shall provide required safety measures for Pedestrian and Automobile traffic during any onsite or offsite AC Paving improvement work where any pedestrian or vehicle traffic may be present.

20. Earthwork and Paving Trades Contractor shall provide winterization to the limits of construction as exposed and directed by the Construction Manager. All Rough graded areas will be held 6” below designed grade, compacted per the soils report and signed off by the Soils Tech. The final 6” of fill will be Class II Aggregate Base Rock compacted to 95% to designed subgrade and building pad grades. In all cases grades will be established to direct rain water to catch basins, retention ponds, silt ponds or other devices to keep the building site free from standing water during the rainy season. When there is no choice but to direct water to an area that cannot drain, a float activated sump pump and discharge pipe will be installed to facilitate. The Earthwork and Paving trade will be responsible to maintain the pump in working condition while in service.

21. Earthwork and Paving Trades Contractor to include $100,000 Allowance in their bid for any additional work requested by the district.

22. Earthwork and Paving Trades Contractor shall lime treat (or at the direction of a authorized district representative, provide Engineered Fill per Plan & Spec) a minimum of 5’ beyond parameter limits for building footings and building pads extend continuous to below planned subgrade or building footing, whichever is deeper.

23. Earthwork and Paving Trades Contractor shall encapsulate, demo, handle and dispose of all lead-based components in the appropriate methods, following all regulations and per the Hazmat report Titled “HazMat Report for Asbestos & Lead (Pb) Report Limited Pre-Demolition/Renovation Survey & Evaluation” for Taft dated 06/29/18. The work shall not cause or allow the lead-based items to become friable.

24. Earthwork and Paving Trades Contractor shall coordinate with the General Trades Contractor for protection and shoring of partially demoed canopy.

25. Prior to Demolition, the Earthwork and Paving Trades contractor shall remove contaminated soils per the “Site Plan – Removal Areas & Site Control Plan” sheet within the “181220 Taft CEQA soils mitigation plan Final” Figure #’s 3 & 4, and dispose of soils to an appropriate landfill per requirements stated in section “A item #’s 20 & 21” of this document.

END OF EARTHWORK AND PAVING SCOPE STATEMENT

Page 53: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-15

SCOPE STATEMENT – Bid Package B, Underground Utilities Trades TAFT COMMUNITY SCHOOL - NEW BUILDINGS, MODERNIZATION & SITEWORK SCOPE OF WORK DEFINED BELOW AND IN ACCORDANCE WITH THE CONTRACT DRAWINGS, DIVISION OO, DIVISION O1, DSA 103 Statement of Structural Tests and Special Inspections,

AND TECHNICAL SPECIFICATION SECTIONS: 211300, 220000, 312333, 328400, 330513, 331000, 333000, 334000, 334600

DRAWINGS: Taft Community School - New Buildings, Modernization & Sitework applicable drawings and details as they pertain to the Scope of Work designated below. Required scope and details for this bid package may be shown on General, Civil, Landscape, Plumbing, Fire Protection, and Energy Compliance drawings.

DESCRIPTION: Project will be phased per the construction schedule included herein. Furnish all labor, materials, equipment and services required for the above listed specification sections covering related work as per project plans and specifications and as described below:

S C O P E O F W O R K

SECTION A - GENERAL ITEMS; SPECIAL ATTENTION SHOULD BE GIVEN TO THE FOLLOWING:

1. Overhead, bonds and insurance: Contractor shall include all costs for home office overhead, field overhead, performance and payment bonds and insurance as required in the contract documents.

2. Security: Contractor will be responsible for compliance with Department of Justice requirements for school construction. All on site employees will be required to wear a construction badge or be escorted or accompanied by a badged contractor or school district representative through non construction areas.

3. The Construction Manager shall provide a debris box for general cleanup. Contractors will be required to clean up daily and load their trash in the debris box. Job clean-up will be at the direction of the Construction Manager. Note: If demolition is called for in Contractor’s scope of work, Contractor is responsible for providing his own debris box and removing all demolition debris from the site in a timely manner, but in no case longer than seven (7) days from the date of demolition. The Construction Manager’s debris box shall not be used for depositing selective demolition debris.

4. The Construction Manager shall provide portable toilets and hand wash stations. 5. Underground Utilities Trades Contractor shall be responsible for their own scaffolding,

lifts, and hoists. 6. The Construction Manager will provide temporary fencing around the jobsite perimeter,

as necessary. Contractor will be responsible for maintaining if relocated and/or disassembled.

7. Underground Utilities Trades Contractor shall be responsible for maintaining safety compliance and weekly safety meetings.

8. Underground Utilities Trades Contractor shall be responsible for their own phone service and drinking water.

Page 54: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-16

9. Underground Utilities Trades Contractor employees will park in parking spaces or designated parking area identified by the Construction Manager.

10. Underground Utilities Trades Contractor shall be required to coordinate their work with other Prime Contractors, attend weekly coordination meetings and provide 3 week look ahead schedule and daily task(s), manpower and equipment reports.

11. Time is of the essence on this project. Underground Utilities Trades Contractor shall adhere to the Construction Schedule as provided by Construction Manager and may be financially responsible for delays to the schedule in accordance with the contract.

12. Underground Utilities Trades Contractor shall refer to the Contractor Access, Laydown and Staging Plan for limits of construction. temporary power and water location. Specific areas for laydown and staging for each trade shall be as determined by the Construction Manager.

13. Underground Utilities Trades Contractor shall ensure a superintendent or foreman who is an employee of the contractor shall be present at all times while contractor or subcontractor workers are on site.

14. Underground Utilities Trades Contractor shall ensure payment of prevailing wages and timely submission of certified payrolls for all contractor employees and subcontractors.

15. Underground Utilities Contractor shall protect from damage to all existing utilities, trees, buildings, hardscape and landscaping to remain.

16. Underground Utilities Trades Contractor shall review all Trade Scope Statements carefully and understand other Prime Contractors’ responsibilities. Contractor shall request pre-bid clarifications for items that are missing in scope, repeated in scopes, or may require coordination.

17. Underground Utilities Trades Contractor shall be responsible for cleaning pavement and streets from dirt and debris due to their work. Contractors will provide daily clean-up for their work.

18. Any contractor that disturbs SWPPP measures is responsible for returning them to their previous conditions.

19. All Prime Trades Contractors and their Sub-Contractors shall follow, maintain, repair and or replace Erosion Control and storm water pollution prevention measures (BMPs) as their work impacts the established BMP’s as per plans and at the direction of the Construction Manager.

20. All Trades Contractors and your subcontractors will strictly comply with all SWPPP, BMP, CEQA, MND, MMRP, SMP, HazMat, Geological, survey(s), Drawings reports managing measures as it applies to your work. If you disrupt or expose a previously protected and contained element or component during your construction processes, you are required to restore, protect and or contain the affected area(s) restoring the integrity of the area(s) disrupted or exposed as described within the above mentioned documents and as identified by the Construction Management Team.

21. Any and All Contractors off-hauling Soils, Concrete and Asphalt, are to follow the specific guidelines set forth within the Site Specific CEQA and Geotechnical report including MND, MMRP, and SMP Reports.

22. All trades contractors must adhere and comply with and to the findings and recommendations stated in the Geotechnical Evaluation and Geologic Hazard Assessment Report(s) including its Addendum 1 provided by Ninyo and Moore (project #402965006, dated December 11, 2017 & November 16, 2018) and at the direction of The District. This statement supersedes any contradictory verbiage which may be in the contract documents.

Page 55: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-17

SECTION B – SPECIFIC ITEMS FOR THIS BID PACKAGE:

Do not exclude any of the following from your bid. Exclusions of any items may render your bid non-responsive.

1. Work is scheduled for a 5 day work week per the attached schedule. Overtime and weekend work is not mandatory unless where designated on the project schedule, however contractor shall ensure sufficient straight time manpower is provided to complete tasks within the durations indicated. If work is delayed due to circumstances beyond the contractor’s control, then the construction manager may adjust the schedule or authorize overtime via change order in order to maintain the schedule.

2. Provide for costs of bonds, insurance, secure equipment and materials storage, provide supervision of sub-trade contractor labor, coordination with other trade contractors, safety, Cal-OSHA approved protection, costs for DOJ background checks, copying, telephones and fax service, office trailers and temporary utilities if needed (location to be determined by Construction Manager), computers and printers.

3. All Trades Contractors shall provide required submittals, shop drawings, RFI’s, PCO’s and any required documents through “ColbiDocs”, The District’s online document processing program.

4. Underground Utilities Trades Contractor must Recycle Materials and Waste to their fullest extent.

5. All contractors are required to submit certified payroll for their forces as well as sub tier trades directly to the Department of Industrial Relations. Contractors and subcontractors will be required to register and submit payroll reports electronically.

6. Underground Utilities Trades Contractor shall provide survey staking and layout of Underground Utilities Trade Contractor’s work.

7. Underground Utilities Trades Contractor shall provide utility locating services as necessary to perform all work.

8. Underground Utilities Trades Contractor shall coordinate with Geotechnical consultant and IOR for all compaction tests and inspections.

9. Underground Utilities Trades Contractor shall Include all allowances and unit price items in bid as called for in this scope statement and on the bid form.

10. Underground Utilities Trades Contractor shall provide sterilization, chlorination and bacteria testing for new domestic water system.

11. Underground Utilities Trades Contractor shall protect all existing utilities, trees, buildings, hardscape and landscaping to remain.

12. All Trades Contractors will replace in kind the winterization rock when disturbed by their work.

Drawings Specific Scope of Work: 1. Underground Utilities Trades Contractor shall remove spoils from excavation of trenches

specified within the soils mitigation plan and dispose of soils to an appropriate landfill per requirements stated in section “A” item #’s 20 & 21 of this document.

2. All excess excavation spoils are to be removed to an appropriate landfill per the requirements stated in section “A” item #’s 20 & 21 of this document.

3. Underground Utilities Trades Contractor shall safe off their utilities prior to demolition for both new building construction and modernization. Pothole, shut down utility, cut and remove section of pipe and cap end where existing utility will remain and recharge the utility system. (Note: abandoned utility demolition will be performed by the Earthwork and Paving Contractor and electrical utility safe off will be performed by the Electrical Contractors Trade).

Page 56: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-18

4. Underground Utilities Trades Contractor shall, except as necessary to make new POC connections, exclude the removal of abandoned utilities lines and subsequent backfill and compaction. Note Earthwork and Paving contractor to remove abandoned utilities.

5. Underground Utilities Trades Contractor shall perform trench excavation, backfill & compaction to adjacent grade for all site fire water, domestic water, gas, sanitary sewer and storm drain systems.

6. Underground Utilities Trades Contractor will provide and install all site fire service, 7. domestic water, gas, sanitary sewer and storm drain work. Provide all excavation,

subgrade preparation, bedding, backfill & compaction to adjacent grade for their work. Include all connections, valves, boxes, devices, inlets, trench drains, finish grates, concrete collars, thrust blocks, PIV, FDC and other necessary work for complete utility services to and for the building and site per plans. This includes utilities underneath the new buildings. Temporarily cap utility pipe below grade and as-build locations for future final connections approximately 5 feet from the New Building(s). Note: Final utility connections at the New Building(s) will be done by the plumbing trades contractor.

8. Underground Utilities Trades Contractor shall provide potholing to identify exact location for utility points of connection.

9. Underground Utilities Trades Contractor shall install necessary domestic water meters and backflow devices per plans and specs.

10. Underground Utilities Trades Contractor to include installation of fire line risers to approximately 12 inches above interior slabs (FF) at fire riser locations and provide sleeves through floor slabs as indicated on plans.

11. Underground Utilities Trades Contractor will provide and install piping, drain inlets, and class II permeable rock, and river rock for all bioretention systems at bioretention areas. (Note: The Earthwork and Paving Trades Contractor shall perform excavation to subgrade, The Landscaping Trades Contractor will provide the biotreatment soil mix and the planting, The Site Concrete Trades Contractor will provide concrete planter boxes as needed).

12. Underground Utilities Trades Contractor will protect old and new storm drain inlet locations, indicated on the stormwater management plan and provide removal upon completion of project at direction of Construction Manager. Temporarily cap and protect all pipe ends until final connections are made.

13. Provide accurate as built drawings with dimensions to all capped lines scheduled for future connection.

14. Underground Utilities Trades Contractor to provide final connections to their tamper switches on their

15. perspective fire protection equipment, electrical contractor to provide conduits & wires to the tamper switches.

16. Underground Utilities Trades Contractor shall provide and install specified backfill material and compact all utility trenches in accordance with the Geotechnical Report. All excavation spoils are to be removed to an appropriate landfill per the requirements stated in section “A” of this document.

17. Underground Utilities Trades Contractor shall provide base rock and compaction, asphalt and concrete to match existing conditions for all utility installations extending outside the limits of the demolition shown on sheet C7.0, C7.1, and C7.2.

18. Underground Utilities Trades Contractor shall provide specified backfill above initial sand backfill and compact to adjacent finish grade in all planter and field areas.

19. Underground Utilities Trades Contractor shall obtain and provide all necessary permits for work for connections to be done to city utilities per plans on, but not limited to Sheet C7.0. Underground Utilities Trades Contractor will be reimbursed by the district for the cost of obtaining permits.

Page 57: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-19

20. Underground Utilities Trades Contractor shall install all necessary concrete bases for backflow devices of their water and fire water utilities if applicable.

21. Underground Utilities Trades Contractor shall provide and install 3 temporary hose bibs and temporary water, per direction by the construction manager, for construction activities and site dust control mitigation Truck Wash Out and remove at the end of the project at the direction of the Construction Manager.

22. Underground Utilities Trades Contractor shall provide and install as necessary, temporary sewer systems if applicable per direction by the construction manager.

23. Underground Utilities Trades Contractor shall provide “No Dumping! Flows To Bay” Stenciling as Required per plan C7.3.

END OF UNDERGROUND UTILITIES SCOPE STATEMENT

Page 58: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-20

SCOPE STATEMENT – Bid Package C, Site Concrete Trades TAFT COMMUNITY SCHOOL - NEW BUILDINGS, MODERNIZATION & SITEWORK SCOPE OF WORK DEFINED BELOW AND IN ACCORDANCE WITH THE CONTRACT DRAWINGS, DIVISION OO, DIVISION O1, DSA 103 Statement of Structural Tests and Special Inspections,

AND TECHNICAL SPECIFICATION SECTIONS: 031100, 032000, 033000, 071813, 321726

DRAWINGS: Taft Community School - New Buildings, Modernization & Sitework applicable drawings and details as they pertain to the Scope of Work designated below. Required scope and details for this bid package may be shown on General, Civil, Landscape, Architectural, and Structural.

DESCRIPTION: Project will be phased according to the construction schedule included herein. Furnish all labor, materials, equipment and services required for the above listed specification sections covering related work as per project plans and specifications and as described below:

S C O P E O F W O R K

SECTION A - GENERAL ITEMS; SPECIAL ATTENTION SHOULD BE GIVEN TO THE FOLLOWING:

1. Overhead, bonds and insurance: Contractor shall include all costs for home office overhead, field overhead, performance and payment bonds and insurance as required in the contract documents.

2. Security: Contractor will be responsible for compliance with Department of Justice requirements for school construction. All on site employees will be required to wear a construction badge or be escorted or accompanied by a badged contractor or school district representative through non construction areas.

3. The Construction Manager shall provide a debris box for general cleanup. Contractors will be required to clean up daily and load their trash in the debris box. Job clean-up will be at the direction of the Construction Manager. Note: If demolition is called for in Contractor’s scope of work, Contractor is responsible for providing his own debris box and removing all demolition debris from the site in a timely manner, but in no case longer than seven (7) days from the date of demolition. The Construction Manager’s debris box shall not be used for depositing selective demolition debris.

4. The Construction Manager shall provide portable toilets and hand wash stations. 5. Site Concrete Trades Contractor shall be responsible for their own scaffolding, lifts, and

hoists. 6. The Construction Manager will provide temporary fencing around the jobsite perimeter,

as necessary. Contractor will be responsible for maintaining if relocated and/or disassembled.

7. Site Concrete Trades Contractor shall be responsible for maintaining safety compliance and weekly safety meetings.

8. Site Concrete Trades Contractor shall be responsible for their own phone service and drinking water.

9. Site Concrete Trades Contractor employees will park in parking spaces or designated parking area identified by the Construction Manager.

Page 59: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-21

10. Site Concrete Trades Contractor shall be required to coordinate their work with other Prime Contractors, attend weekly coordination meetings and provide 3 week look ahead schedule and daily task, manpower and equipment reports.

11. Time is of the essence on this project. Site Concrete Trades Contractor shall adhere to the Construction Schedule as provided by Construction Manager and may be financially responsible for delays to the schedule in accordance with the contract.

12. Site Concrete Trades Contractor shall refer to the Contractor Access, Laydown and Staging Plan for limits of construction. temporary power and water location. Specific areas for laydown and staging for each trade shall be as determined by the Construction Manager.

13. Site Concrete Trades Contractor shall ensure a superintendent or foreman who is an employee of the contractor shall be present at all times while contractor or subcontractor workers are on site.

14. Site Concrete Trades Contractor shall ensure payment of prevailing wages and timely submission of certified payrolls for all contractor employees and subcontractors.

15. Site Concrete Trades Contractor shall protect from damage to all existing utilities, trees, buildings, hardscape and landscaping to remain.

16. Site Concrete Trades Contractor shall review all Trade Scope Statements carefully and understand other Prime Contractors’ responsibilities. Contractor shall request pre-bid clarifications for items that are missing in scope, repeated in scopes, or may require coordination.

17. Site Concrete Trades Contractor shall be responsible for cleaning pavement and streets from dirt and debris due to their work. Contractors will provide daily clean-up for their work.

18. Any contractor that disturbs SWPPP measures is responsible for returning them to their previous conditions.

19. All Prime Trades Contractors and their Sub-Contractors shall follow, maintain, repair and or replace Erosion Control and storm water pollution prevention measures (BMPs) as their work impacts the established BMP’s as per plans and at the direction of the Construction Manager.

20. All Trades Contractors and your subcontractors will strictly comply with all SWPPP, BMP, CEQA, MND, MMRP, SMP, HazMat, Geological, survey(s), Drawings reports managing measures as it applies to your work. If you disrupt or expose a previously protected and contained element or component during your construction processes, you are required to restore, protect and or contain the affected area(s) restoring the integrity of the area(s) disrupted or exposed as described within the above mentioned documents and as identified by the Construction Management Team.

21. Any and All Contractors off-hauling Soils, Concrete and Asphalt, are to follow the specific guidelines set forth within the Site Specific CEQA and Geotechnical report including MND, MMRP, and SMP Reports.

22. All trades contractors must adhere and comply with and to the findings and recommendations stated in the Geotechnical Evaluation and Geologic Hazard Assessment Report(s) including its Addendum 1 provided by Ninyo and Moore (project #402965006, dated December 11, 2017 & November 16, 2018) and at the direction of The District. This statement supersedes any contradictory verbiage which may be in the contract documents.

Page 60: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-22

SECTION B – SPECIFIC ITEMS FOR THIS BID PACKAGE:

Do not exclude any of the following from your bid. Exclusions of any items may render your bid non-responsive.

1. Work is scheduled for a 5-day work week per the attached schedule. Overtime and weekend work is not mandatory unless where designated on the project schedule, however contractor shall ensure sufficient straight time manpower is provided to complete tasks within the durations indicated. If work is delayed due to circumstances beyond the contractor’s control, then the construction manager may adjust the schedule or authorize overtime via change order in order to maintain the schedule.

2. Provide for costs of bonds, insurance, secure equipment and materials storage, provide supervision of sub-trade contractor labor, coordination with other trade contractors, safety, Cal-OSHA approved protection, costs for DOJ background checks, copying, telephones and fax service, office trailers and temporary utilities if needed (location to be determined by Construction Manager), computers and printers.

3. All Trades Contractors shall provide required submittals, shop drawings, RFI’s, PCO’s and any required documents through “ColbiDocs”, The District’s online document processing program.

4. Building Materials and waste must be recycled to their fullest extent. 5. All contractors are required to submit certified payroll for their forces as well as sub tier

trades directly to the Department of Industrial Relations. Contractors and subcontractors will be required to register and submit payroll reports electronically.

6. Site Concrete Trades Contractor shall provide survey staking and layout of Site Concrete Contractor’s work.

7. Site Concrete Trades Contractor shall provide and install water proofing for concrete where applicable.

8. Site Concrete Trades contractor must coordinate with Geotechnical Consultant and IOR for all compaction tests and inspections.

9. Site Concrete Trades Contractor shall include all allowances and unit price items in bid as called for in this scope statement and on the bid form as applicable.

10. All Trades Contractors will replace in kind the winterization rock when disturbed by their work.

Drawings Specific Scope of work: (NOTE ALL ITEMS IN RED ADDED DURING ADDENDUM 1 & 3)

1. Site Concrete Trades Contractor will provide formwork, reinforcement and concrete per the 2. drawings and specifications for all site concrete. Include city sidewalks, pervious concrete 3. paving, vertical/flush/retaining curbs and gutters, non-CMU concrete retaining walls, seat

walls, planter walls, Amphitheatre walls, & their foundations, concrete stairs, landings and ramps at modernization. (Note: New building foundations and slabs are General Trades Contractor. Subgrade and compacted base rock are by The Earthwork and Paving Trades Contractor. Coordinate closely with the Earthwork and Paving and other Trades Contractors to ensure proper elevations are maintained for all site concrete.)

4. Site Concrete Trades Contractor will provide concrete planter boxes as needed for all bioretention systems at bioretention areas. (Note: Earthwork and Paving Trades Contractor shall perform excavation of subgrade, The U.G. Utilities Trades Contractor will provide perforated piping, drain inlets, and class II permeable rock, and river rock, The Landscaping Trades Contractor will provide the biotreatment soil mix and the planting).

5. Site Concrete Trades Contractor shall provide and install joint sealants and expansion joint caulking related to site concrete as specified.

Page 61: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-23

6. Site Concrete Trades Contractor shall provide and install all tactile detectable warning surfaces as described on plans.

7. Site Concrete Trades Contractor shall excavate for concrete paving thickened edge as applicable.

8. Site Concrete Trades Contractor shall coordinate rebar placement with GC to allow for guard / handrail post concrete coring / Sleeving to be done by General Trades Contractor.

9. Site Concrete Trades contractor is not responsible for concrete bases of light posts or poles, backflow devices, flag poles, or fence posts. Each respective trade is responsible for concrete bases of their own posts, backflow devices and housekeeping pads.

10. Site Concrete Trades Contractor to provide selective demolition to ensure clean transitions between their new work and existing.

11. Site Concrete Trades Contractor shall provide and install bollards including painting of bollards within their site concrete if applicable.

12. Site Concrete Trades Contractor is responsible for painting of concrete at vehicle curbs as needed.

13. The district will pay or reimburse for city improvements permit fee and the Site Concrete Trades contractor will apply and obtain the permit and perform work per plans of not performed by others.

14. Provide required safety measures for Pedestrian and Automobile traffic during any onsite or offsite concrete improvement work where any pedestrian or vehicle traffic may be present.

15. Site Concrete Trades Contractor shall provide sealed concrete associated with the amphitheater and any other exterior concrete as per plans and specs (excluding second floor metal decking which is provided by the GC).

16. The Site Concrete Trades Contractor shall excavate and remove soils specified by the site control plan within the soils mitigation plan and dispose of soils to an appropriate landfill per requirements stated in section “A item #’s 20 & 21” of this document.

17. All excavation spoils are to be removed to an appropriate landfill per requirements stated in section “A item #’s 20 & 21” of this document.

END OF SITE CONCRETE TRADES SCOPE STATEMENT

Page 62: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-24

SCOPE STATEMENT – Bid Package D, Electrical and Low Voltage Trades TAFT COMMUNITY SCHOOL - NEW BUILDINGS, MODERNIZATION & SITEWORK SCOPE OF WORK DEFINED BELOW AND IN ACCORDANCE WITH THE CONTRACT DRAWINGS, DIVISION OO, DIVISION O1, DSA 103 Statement of Structural Tests and Special Inspections,

AND TECHNICAL SPECIFICATION SECTIONS: 024119, 078413, 078443, 079200, 087113, 101463, 114123, 122400, 122413, 142423, 230000, 230101, 230102, 260500, 260513, 260526, 260533, 260548, 260553, 260923, 262413, 262726, 265100, 265600, 270000, 270526, 271500, 275123, 281600, 283100, 312333, 330513

DRAWINGS: Taft Community School - New Buildings, Modernization & Sitework applicable drawings and details as they pertain to the Scope of Work designated below. Required scope and details for this bid package may be shown on General, Landscape, Architectural, Structural, Mechanical, Electrical, Fire Alarm, Elevator, and Energy Compliance drawings.

DESCRIPTION: Project will be phased per the construction schedule included herein. Furnish all labor, materials, equipment and services required for the above listed specification sections covering related work as per project plans and specifications and as described below:

S C O P E O F W O R K

SECTION A - GENERAL ITEMS; SPECIAL ATTENTION SHOULD BE GIVEN TO THE FOLLOWING:

1. Overhead, bonds and insurance: Contractor shall include all costs for home office overhead, field overhead, performance and payment bonds and insurance as required in the contract documents.

2. Security: Contractor will be responsible for compliance with Department of Justice requirements for school construction. All on site employees will be required to wear a construction badge or be escorted or accompanied by a badged contractor or school district representative through non construction areas.

3. The Construction Manager shall provide a debris box for general cleanup. Contractors will be required to clean up daily and load their trash in the debris box. Job clean-up will be at the direction of the Construction Manager. Note: If demolition is called for in Contractor’s scope of work, Contractor is responsible for providing his own debris box and removing all demolition debris from the site in a timely manner, but in no case longer than seven (7) days from the date of demolition. The Construction Manager’s debris box shall not be used for depositing selective demolition debris.

4. The Construction Manager shall provide portable toilets and hand wash stations. 5. Electrical and Low Voltage Trades Contractor shall be responsible for their own

scaffolding, lifts and hoists. Utilize the correct equipment to prevent damages to the completed site work.

6. The Construction Manager will provide temporary fencing around the jobsite perimeter, as necessary. Contractor will be responsible for maintaining if relocated and/or disassembled.

7. Electrical and Low Voltage Trades Contractor shall be responsible for maintaining safety compliance and weekly safety meetings.

Page 63: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-25

8. Electrical and Low Voltage Trades Contractor shall be responsible for their own phone service and drinking water.

9. Electrical and Low Voltage Trades Contractor employees will park in parking spaces or designated parking area identified by the Construction Manager.

10. Electrical and Low Voltage Trades Contractor shall be required to coordinate their work with other Prime Contractors, attend weekly coordination meetings and provide 3 week look ahead schedule and daily manpower and equipment reports.

11. Time is of the essence on this project. Electrical and Low Voltage Trades Contractor shall adhere to the Construction Schedule as provided by Construction Manager and may be financially responsible for delays to the schedule in accordance with the contract.

12. Electrical and Low Voltage Trades Contractor shall refer to the Contractor Access, Laydown and Staging Plan for limits of construction. temporary power and water location. Specific areas for laydown and staging for each trade shall be as determined by the Construction Manager.

13. Electrical and Low Voltage Trades Contractor shall ensure a superintendent or foreman who is an employee of the contractor and is present at all times while contractor or subcontractor workers are on site.

14. Electrical and Low Voltage Trades Contractor shall ensure payment of prevailing wages and timely submission of certified payrolls for all contractor employees and subcontractors.

15. Electrical and Low Voltage Trades Contractor shall protect from damage to all existing utilities, trees, buildings, hardscape and landscaping to remain.

16. Electrical and Low Voltage Trades Contractor shall review all Trade Scope Statements carefully and understand other Prime Contractors’ responsibilities. Contractor shall request pre-bid clarifications for items that are missing in scope, repeated in scopes, or may require coordination.

17. Electrical and Low Voltage Trades Contractor shall be responsible for cleaning pavement and streets from dirt and debris due to their work. Contractors will provide daily clean-up for their work.

18. Any contractor that disturbs SWPPP measures is responsible for returning them to their previous conditions.

19. All Prime Trades Contractors and their Sub-Contractors shall follow, maintain, repair and or replace Erosion Control and storm water pollution prevention measures (BMPs) as their work impacts the established BMP’s as per plans and at the direction of the Construction Manager.

20. All Trades Contractors and your subcontractors will strictly comply with all SWPPP, BMP, CEQA, MND, MMRP, SMP, HazMat, Geological, survey(s), Drawings reports managing measures as it applies to your work. If you disrupt or expose a previously protected and contained element or component during your construction processes, you are required to restore, protect and or contain the affected area(s) restoring the integrity of the area(s) disrupted or exposed as described within the above mentioned documents and as identified by the Construction Management Team.

21. Any and All Contractors off-hauling Soils, Concrete and Asphalt, are to follow the specific guidelines set forth within the Site Specific CEQA and Geotechnical report including MND, MMRP, and SMP Reports.

22. All trades contractors must adhere and comply with and to the findings and recommendations stated in the Geotechnical Evaluation and Geologic Hazard Assessment Report(s) including its Addendum 1 provided by Ninyo and Moore (project #402965006, dated December 11, 2017 & November 16, 2018) and at the direction of The District. This statement supersedes any contradictory verbiage which may be in the contract documents.

Page 64: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-26

SECTION B – SPECIFIC ITEMS FOR THIS BID PACKAGE:

Do not exclude any of the following from your bid. Exclusions of any items may render your bid non-responsive.

1. Work is scheduled for a 5-day work week per the attached schedule. Overtime and weekend work is not mandatory unless where designated on the project schedule, however contractor shall ensure sufficient straight time manpower is provided to complete tasks within the durations indicated. If work is delayed due to circumstances beyond the contractor’s control, then the construction manager may adjust the schedule or authorize overtime via change order in order to maintain the schedule.

2. Provide for costs of bonds, insurance, secure equipment and materials storage, provide supervision of sub-trade contractor labor, coordination with other trade contractors, safety, Cal-OSHA approved protection, costs for DOJ background checks, copying, telephones and fax service, office trailers and temporary utilities if needed (location to be determined by Construction Manager), computers and printers.

3. All Trades Contractors shall provide required submittals, shop drawings, RFI’s, PCO’s and any required documents through “ColbiDocs”, The District’s online document processing program.

4. Electrical Trades Contractor must recycle building materials and waste to their fullest extent.

5. All contractors are required to submit certified payroll for their forces as well as sub tier trades directly to the Department of Industrial Relations. Contractors and subcontractors will be required to register and submit payroll reports electronically.

6. Electrical and Low Voltage Trades Contractor shall provide layout of Electrical and Low Voltage Trades Contractor’s work.

7. Electrical and Low Voltage Trades Contractor shall provide two days of utility locating service.

8. Electrical and Low Voltage Trades Contractor shall provide all required tests and inspections.

9. Electrical and Low Voltage Trades Contractor shall include all allowances and unit price items in bid as called for in this scope statement and on the bid form.

10. All Trades Contractors will replace in kind the winterization rock when disturbed by their work.

Drawings Specific Scope of work: (NOTE ALL ITEMS IN RED ADDED DURING ADDENDUM 1)

1. Electrical Trades Contractor shall remove spoils from excavation of trenches specified

within the soils mitigation plan and dispose of soils to an appropriate landfill per requirements stated in section “A” item #’s 20 & 21 of this document.

2. All excess excavation spoils are to be removed to an appropriate landfill per the requirements stated in section “A” item #’s 20 & 21 of this document.

3. Electrical and Low Voltage Trades Contractor shall provide and maintain temporary power distribution to the project site and project trailers for the duration of the project. Include 600 LF of temp power cord and 6 distribution boxes (Spider Boxes) as directed by the construction manager, including temporary lighting to the interior of the buildings.

4. Electrical and Low Voltage Trades Contractor shall provide safe-off of electrical and low voltage to existing buildings prior to any new construction demolition and Modernization demolition as needed.

Page 65: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-27

5. Electrical and Low Voltage Trades Contractor must phase their safe off work to accommodate the transitioning of (E) MSB and (N) MSB electrical to the school, at the direction of the Construction Manager in conjunction with the Earthwork & Paving contractor and their demo work. (Note: The school must have continuous power for all operations for all areas outside the construction site. Temporary power for construction will be provided by the Electrical & Low Voltage contractor.)

6. Electrical and Low Voltage Trades Contractor shall provide and install all necessary underground electrical power and low voltage routes and reroutes.

7. Electrical and Low Voltage Trades Contractor will provide all power conductors and energize connections to distribution panels.

8. Electrical and Low Voltage Trades Contractor shall provide and install all site power and low voltage system requirements to and within the new and modernization buildings, including raceways, conductors, cabling, grounding, supports and suspension system, panels, breakers, circuits, devices, light fixtures, IDFs/MDF’s, data/telephone and equipment, clock/bell/PA, and fire alarm. Provide complete programming, testing, and training per plans and specifications. for the interior and exterior of the new building(s) and modernization building(s). (Portable flat screen TV’s are OFCI.)

9. Electrical and Low Voltage Trades Contractor will field verify and reuse electrical raceways, electrical data and conduits, and electrical outlets stated on, but not limited to sheet A-401M for all work related to the electrical and low voltage trade contractor.

10. Electrical and Low Voltage Trades Contractor will provide and install all underground electrical and low voltage distribution, conduits, panels, conductors, pull boxes, vaults, pads, equipment and associated trenching, backfill and pavement patching. All excess excavation spoils are to be removed to an appropriate landfill as directed in Section “A” of this document.

11. Electrical and Low Voltage Trades Contractor shall provide saw cutting and removal of asphalt and concrete paving as needed for installation of new site electrical and low voltage. Remove all demolition materials from the site and recycle to their fullest extent possible. All excavation spoils are to be removed to an appropriate landfill directed in Section A of this document. Provide asphalt and concrete patching to restore existing hard scape outside the limits of demolition shown on the plans. Trench backfill and compact to finish grade with soils as directed within specs and or Geo Report in landscape areas and areas with site demo by others.

12. Electrical and Low Voltage Trades Contractor shall provide and install electrical and or demo including safe off’s as described on the plans and specs, fire alarm, electrical lines, fiber optics).

13. Electrical and Low Voltage Trades Contractor shall provide and install seismic expansion joints for electrical and low voltage conduits as required per plans.

14. Electrical and Low Voltage Trades Contractor shall provide all trade related wall and roof flashings, vents, and access panels including layout. General Trades Contractor to install said items.

15. Electrical and Low Voltage Trades Contractor shall provide and install fire alarm and associated conduit, wiring, and terminations to the fire sprinkler risers and bell assemblies.

16. Electrical and Low Voltage Trades Contractor to provide power and land to the bell. 17. Electrical and Low Voltage Trades Contractor to provide power to the tamper switch at

Riser. (FP to land power to their Riser Tamper Switch in the Riser Room) 18. Electrical and Low Voltage Trades contractor to provide conduits & wires to tamper

switches at site fire riser & backflow devices.

Page 66: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-28

19. Electrical and Low Voltage Trades Contractor shall provide all conduit and rough-in boxes and for a complete intrusion alarm system and is to coordinate with the security company and or District IT Department in regards to cabling in the new buildings.

20. Electrical and Low Voltage Trades Contractors to safe off and remove any non-needed empty conduits surface mounted per plans for building modernization.

21. Electrical and Low Voltage Trades Contractor shall provide and install conduits and wire for HVAC and water heater controls and energy management system. Coordinate conduit installation with the respective contractor. (HVAC, Landscape & Plumbers to land their equipment)

22. Electrical and Low Voltage Trades Contractor to provide and install new cable, conduits, and backboxes for new cameras, and Install only Avigilon system, provide security system, and any related EMS systems for new buildings and building modernization.

23. Electrical and Low Voltage Trades Contractor to do all electrical work in the modernization buildings including electrical safe off, electrical stub ups, district specific security cameras, Fire Alarm work and final tie in.

24. Electrical and Low Voltage Trades Contractor to provide and install WAPs per plans and Specs.

25. Electrical and Low Voltage Trades Contractor shall place concrete for their own house keeping pads if applicable.

26. Electrical and Low Voltage Trades Contractor shall provide and install conduit, raceways, wiring for power, signal, communications and shunt control to elevator. Provide power and signal connections to the elevator control panel. General Trades Contractor will install elevator power and low voltage from the control panel to the elevator system. General Trades Contractor shall provide and install the complete hydraulic passenger elevator for Building.

27. Electrical and Low Voltage Trades Contractor shall provide and install electrical power to walk-in refrigerator equipment as provided by GC.

28. Electrical Trades Contractor shall salvage WAP’s, MDF/IDF racks, panels, strobes, data/telephone and equipment, Clock/Bell/PA, and fire alarm devices in existing buildings which are to be demoed. The District will store these items for later use.

END OF ELECTRICAL AND LOW VOLTAGE TRADES SCOPE STATEMENT

Page 67: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-29

SCOPE STATEMENT – Bid Package E, HVAC Trades TAFT COMMUNITY SCHOOL - NEW BUILDINGS, MODERNIZATION & SITEWORK SCOPE OF WORK DEFINED BELOW AND IN ACCORDANCE WITH THE CONTRACT DRAWINGS, DIVISION OO, DIVISION O1, DSA 103 Statement of Structural Tests and Special Inspections,

AND TECHNICAL SPECIFICATION SECTIONS: 024119, 077233, 078413, 078443, 079200, 220000, 230000, 230101, 230102, 230500

DRAWINGS: Taft Community School - New Buildings, Modernization & Sitework applicable drawings and details as they pertain to the Scope of Work designated below. Required scope and details for this bid package may be shown on Structural, Mechanical, Plumbing, and Energy Compliance drawings.

DESCRIPTION: Project will be phased according to the construction schedule included herein. Furnish all labor, materials, equipment and services required for the above listed specification sections covering related work as per project plans and specifications and as described below:

S C O P E O F W O R K

SECTION A - GENERAL ITEMS; SPECIAL ATTENTION SHOULD BE GIVEN TO THE FOLLOWING:

1. Overhead, bonds and insurance: Contractor shall include all costs for home office overhead, field overhead, performance and payment bonds and insurance as required in the contract documents.

2. Security: Contractor will be responsible for compliance with Department of Justice requirements for school construction. All on site employees will be required to wear a construction badge or be escorted or accompanied by a badged contractor or school district representative through non construction areas.

3. The Construction Manager shall provide a debris box for general cleanup. Contractors will be required to clean up daily and load their trash in the debris box. Job clean-up will be at the direction of the Construction Manager. Note: If demolition is called for in Contractor’s scope of work, Contractor is responsible for providing his own debris box and removing all demolition debris from the site in a timely manner, but in no case longer than seven (7) days from the date of demolition. The Construction Manager’s debris box shall not be used for depositing selective demolition debris.

4. The Construction Manager shall provide portable toilets and hand wash stations. 5. HVAC Trades Contractor shall be responsible for their own scaffolding, lifts and hoists.

Utilize the correct equipment to prevent damages to the completed site work. 6. The Construction Manager will provide temporary fencing around the jobsite perimeter,

as necessary. Contractor will be responsible for maintaining if relocated and/or disassembled.

7. HVAC Trades Contractor shall be responsible for maintaining safety compliance and weekly safety meetings.

8. HVAC Trades Contractor shall be responsible for their own phone service and drinking water.

9. HVAC Trades Contractor employees will park in parking spaces or designated parking area identified by the Construction Manager.

Page 68: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-30

10. HVAC Trades Contractor shall be required to coordinate their work with other Prime Contractors, attend weekly coordination meetings and provide 3 week look ahead schedule and daily task, manpower and equipment reports.

11. Time is of the essence on this project. HVAC Trades Contractor shall adhere to the Construction Schedule as provided by Construction Manager and may be financially responsible for delays to the schedule in accordance with the contract.

12. HVAC Trades Contractor shall refer to the Contractor Access, Laydown and Staging Plan for limits of construction. temporary power and water location. Specific areas for laydown and staging for each trade shall be as determined by the Construction Manager.

13. HVAC Trades Contractor shall ensure a superintendent or foreman who is an employee of the contractor shall be present at all times while contractor or subcontractor workers are on site.

14. HVAC Trades Contractor shall ensure payment of prevailing wages and timely submission of certified payrolls for all contractor employees and subcontractors.

15. HVAC Trades Contractor shall protect from damage to all existing utilities, trees, buildings, hardscape and landscaping to remain.

16. HVAC Trades Contractor shall review all Trade Scope Statements carefully and understand other Prime Contractors’ responsibilities. Contractor shall request pre-bid clarifications for items that are missing in scope, repeated in scopes, or may require coordination.

17. HVAC Trades Contractor shall be responsible for cleaning pavement and streets from dirt and debris due to their work. Contractors will provide daily clean-up for their work.

18. Any contractor that disturbs SWPPP measures is responsible for returning them to their previous conditions.

19. All Prime Trades Contractors and their Sub-Contractors shall follow, maintain, repair and or replace Erosion Control and storm water pollution prevention measures (BMPs) as their work impacts the established BMP’s as per plans and at the direction of the Construction Manager.

20. All Trades Contractors and your subcontractors will strictly comply with all SWPPP, BMP, CEQA, MND, MMRP, SMP, HazMat, Geological, survey(s), Drawings reports managing measures as it applies to your work. If you disrupt or expose a previously protected and contained element or component during your construction processes, you are required to restore, protect and or contain the affected area(s) restoring the integrity of the area(s) disrupted or exposed as described within the above mentioned documents and as identified by the Construction Management Team.

21. Any and All Contractors off-hauling Soils, Concrete and Asphalt, are to follow the specific guidelines set forth within the Site Specific CEQA and Geotechnical report including MND, MMRP, and SMP Reports.

22. All trades contractors must adhere and comply with and to the findings and recommendations stated in the Geotechnical Evaluation and Geologic Hazard Assessment Report(s) including its Addendum 1 provided by Ninyo and Moore (project #402965006, dated December 11, 2017 & November 16, 2018) and at the direction of The District. This statement supersedes any contradictory verbiage which may be in the contract documents.

Page 69: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-31

SECTION B – SPECIFIC ITEMS FOR THIS BID PACKAGE:

Do not exclude any of the following from your bid. Exclusions of any items may render your bid non-responsive.

1. Work is scheduled for a 5-day work week per the attached schedule. Overtime and weekend work is not mandatory unless where designated on the project schedule, however contractor shall ensure sufficient straight time manpower is provided to complete tasks within the durations indicated. If work is delayed due to circumstances beyond the contractor’s control, then the construction manager may adjust the schedule or authorize overtime via change order in order to maintain the schedule.

2. Provide for costs of bonds, insurance, secure equipment and materials storage, provide supervision of sub-trade contractor labor, coordination with other trade contractors, safety, Cal-OSHA approved protection, costs for DOJ background checks, copying, telephones and fax service, office trailers and temporary utilities if needed (location to be determined by Construction Manager), computers and printers.

3. All Trades Contractors shall provide required submittals, shop drawings, RFI’s, PCO’s and any required documents through “ColbiDocs”, The District’s online document processing program.

4. HVAC Trades Contractor must recycle building materials and waste to their fullest extent.

5. All contractors are required to submit certified payroll for their forces as well as sub tier trades directly to the Department of Industrial Relations. Contractors and subcontractors will be required to register and submit payroll reports electronically.

6. HVAC Trades Contractor shall provide layout of HVAC Trades Contractor’s work. 7. HVAC Trades Contractor shall include all allowances and unit price items in bid as called

for in this scope statement and on the bid form. 8. All Trades Contractors will replace in kind the winterization rock when disturbed by their

work. Drawings Specific Scope of Work: 1. The HVAC contractor will provide and install New Buildings HVAC & Fans equipment and

distribution including all HVAC units and sleeper platforms, ductwork, ductwork insulation, equipment, flashings, sealants, diffusers, vents, exhaust fan, equipment pads, ventilators, and associated materials. (Note: The Electrical Contractor will provide and install required conduit, wiring, and terminations for power to all mechanical systems. The Plumbing Trades Contractor will provide and install all new interior domestic water and gas to the HVAC units) HVAC contractor will provide condensate line install and their final connections.

2. HVAC Trades Contractor shall provide and install all seismic bracing, hangers, and seismic supports for their ductwork and all associated HVAC materials and systems.

3. HVAC Trades Contractor shall provide and install HVAC systems and controls, EMS system for New Buildings. (Note: Electrical Trades Contractor will provide and install conduits, raceways, wires to the HVAC, water heater controls and energy management system.) Final connections will be the responsibility of the HVAC Contractor to their units.

4. HVAC Trades Contractor shall provide materials and layout for all HVAC related wall and roof flashings, vents, and access panels for New Building(s) work. General Trades Contractor to install.

5. HVAC Trades will provide and install all required joint sealants and fire caulking related to their work.

Page 70: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-32

6. HVAC Trades Contractor shall provide and install seismic expansion joints for HVAC work as required per plans.

7. HVAC Trades Contractor shall Provide coordination drawings associated in accordance with specifications.

8. HVAC Trades Contractor shall Provide testing and balancing as necessary to comply with specifications and commissioning requirements.

9. HVAC Trades Contractor for Bldg H: Install new ductwork as required to extend existing branch to new register or grille, remove and relocate supply registers, return grilles, thermostats and associated wiring in new locations, check, test and start RTU’s to ensure proper functionality, Protect existing equipment’s in the MU/Food Services Building.

END OF HVAC TRADES SCOPE STATEMENT

Page 71: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-33

SCOPE STATEMENT – Bid Package F, Landscaping Trades TAFT COMMUNITY SCHOOL - NEW BUILDINGS, MODERNIZATION & SITEWORK SCOPE OF WORK DEFINED BELOW AND IN ACCORDANCE WITH THE CONTRACT DRAWINGS, DIVISION OO, DIVISION O1, DSA 103 Statement of Structural Tests and Special Inspections,

AND TECHNICAL SPECIFICATION SECTIONS: 312333, 328400, 329000, 330513, 334600

DRAWINGS: Taft Community School - New Buildings, Modernization & Sitework applicable drawings and details as they pertain to the Scope of Work designated below. Required scope and details for this bid package may be shown on General, Civil, and Landscape drawings.

DESCRIPTION: Project will be phased according to the construction schedule included herein. Furnish all labor, materials, equipment and services required for the above listed specification sections covering related work as per project plans and specifications and as described below:

S C O P E O F W O R K

SECTION A - GENERAL ITEMS; SPECIAL ATTENTION SHOULD BE GIVEN TO THE FOLLOWING:

1. Overhead, bonds and insurance: Contractor shall include all costs for home office overhead, field overhead, performance and payment bonds and insurance as required in the contract documents.

2. Security: Contractor will be responsible for compliance with Department of Justice requirements for school construction. All on site employees will be required to wear a construction badge or be escorted or accompanied by a badged contractor or school district representative through non construction areas.

3. The Construction Manager shall provide a debris box for general cleanup. Contractors will be required to clean up daily and load their trash in the debris box. Job clean-up will be at the direction of the Construction Manager. Note: If demolition is called for in Contractor’s scope of work, Contractor is responsible for providing his own debris box and removing all demolition debris from the site in a timely manner, but in no case longer than seven (7) days from the date of demolition. The Construction Manager’s debris box shall not be used for depositing selective demolition debris.

4. The Construction Manager shall provide portable toilets and hand wash stations. 5. Landscaping Trades Contractor shall be responsible for their own scaffolding, lifts, and

hoists. 6. The Construction Manager will provide temporary fencing around the jobsite perimeter,

as necessary. Contractor will be responsible for maintaining if relocated and/or disassembled.

7. Landscaping Trades Contractor shall be responsible for maintaining safety compliance and weekly safety meetings.

8. Landscaping Trades Contractor shall be responsible for their own phone service and drinking water.

9. Landscaping Trades Contractor employees will park in parking spaces or designated parking area identified by the Construction Manager.

10. Landscaping Trades Contractor shall be required to coordinate their work with other Prime Contractors, attend weekly coordination meetings and provide 3 week look ahead schedule and daily tasks, manpower and equipment reports.

Page 72: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-34

11. Time is of the essence on this project. Landscaping Trades Contractor shall adhere to the Construction Schedule as provided by Construction Manager and may be financially responsible for delays to the schedule in accordance with the contract.

12. Landscaping Trades Contractor shall refer to the Contractor Access, Laydown and Staging Plan for limits of construction. temporary power and water location. Specific areas for laydown and staging for each trade shall be as determined by the Construction Manager.

13. Landscaping Trades Contractor shall ensure a superintendent or foreman who is an employee of the contractor shall be present at all times while contractor or subcontractor workers are on site.

14. Landscaping Trades Contractor shall ensure payment of prevailing wages and timely submission of certified payrolls for all contractor employees and subcontractors.

15. Landscaping Trades Contractor shall protect from damage to all existing utilities, trees, buildings, hardscape and landscaping to remain.

16. Landscaping Trades Contractor shall review all Trade Scope Statements carefully and understand other Prime Contractors’ responsibilities. Contractor shall request pre-bid clarifications for items that are missing in scope, repeated in scopes, or may require coordination.

17. Landscaping Trades Contractor shall be responsible for cleaning pavement and streets from dirt and debris due to their work. Contractors will provide daily clean-up for their work.

18. Any contractor that disturbs SWPPP measures is responsible for returning them to their previous conditions.

19. All Prime Trades Contractors and their Sub-Contractors shall follow, maintain, repair and or replace Erosion Control and storm water pollution prevention measures (BMPs) as their work impacts the established BMP’s as per plans and at the direction of the Construction Manager.

20. All Trades Contractors and your subcontractors will strictly comply with all SWPPP, BMP, CEQA, MND, MMRP, SMP, HazMat, Geological, survey(s), Drawings reports managing measures as it applies to your work. If you disrupt or expose a previously protected and contained element or component during your construction processes, you are required to restore, protect and or contain the affected area(s) restoring the integrity of the area(s) disrupted or exposed as described within the above mentioned documents and as identified by the Construction Management Team.

21. Any and All Contractors off-hauling Soils, Concrete and Asphalt, are to follow the specific guidelines set forth within the Site Specific CEQA and Geotechnical report including MND, MMRP, and SMP Reports.

22. All trades contractors must adhere and comply with and to the findings and recommendations stated in the Geotechnical Evaluation and Geologic Hazard Assessment Report(s) including its Addendum 1 provided by Ninyo and Moore (project #402965006, dated December 11, 2017 & November 16, 2018) and at the direction of The District. This statement supersedes any contradictory verbiage which may be in the contract documents.

SECTION B – SPECIFIC ITEMS FOR THIS BID PACKAGE: (NOTE ALL ITEMS IN RED ADDED DURING ADDENDUM 1 & 3)

Do not exclude any of the following from your bid. Exclusions of any items may render your bid non-responsive.

1. Work is scheduled for a 5 day work week per the attached schedule. Overtime and weekend work is not mandatory unless where designated on the project schedule,

Page 73: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-35

however contractor shall ensure sufficient straight time manpower is provided to complete tasks within the durations indicated. If work is delayed due to circumstances beyond the contractor’s control, then the construction manager may adjust the schedule or authorize overtime via change order in order to maintain the schedule.

2. Provide for costs of bonds, insurance, secure equipment and materials storage, provide supervision of sub-trade contractor labor, coordination with other trade contractors, safety, Cal-OSHA approved protection, costs for DOJ background checks, copying, telephones and fax service, office trailers and temporary utilities if needed (location to be determined by Construction Manager), computers and printers.

3. All Trades Contractors shall provide required submittals, shop drawings, RFI’s, PCO’s and any required documents through “ColbiDocs”, The District’s online document processing program.

4. Building Materials and waste must be recycled to their fullest extent. 5. All contractors are required to submit certified payroll for their forces as well as sub tier

trades directly to the Department of Industrial Relations. Contractors and subcontractors will be required to register and submit payroll reports electronically.

6. Landscape Trades Contractor shall provide layout of Landscape Contractor’s work. 7. Landscape Trades Contractor shall provide potholing to identify exact locations of

existing irrigation and control wiring connections. 8. Landscape Trades Contractor shall provide survey staking and layout of Landscape

Contractor’s work. 9. Landscape Trades Contractor shall include all allowances and unit price items in bid as

called for in this scope statement and on the bid form. 10. Landscape Trades Contractor shall coordinate with Geotechnical consultant for all

compaction tests and inspections. 11. All Trades Contractors will replace in kind the winterization rock when disturbed by their

work. Drawings Specific Scope of Work: 1. Safe off irrigation system prior to site demolition. Relocate active irrigation to clear

construction zone and restore system at end of project or at the direction of the Construction Manager.

2. Landscape Trades Contractor shall perform trench excavation, backfill and compaction for all irrigation main/lateral lines, sleeves, valves, boxes and irrigation control wiring indicated. All excavation spoils are to be removed to an appropriate landfill directed in Section “A item #’s 20 & 21” of this document.

3. Landscape Trades Contractor shall modify or reroute existing irrigation systems as indicated and directed by the authorized District representative to continue irrigation to non-construction impacted areas.

4. Landscape Trades Contractor shall provide and install complete irrigation system and controls as indicated.

5. Landscape Trades Contractor is to provide final connections to their control box(s) and Climate Weather Sensor.

6. Landscape Trades Contractor shall provide rototilling and fine grading for new landscaping as needed per plans and specs.

7. Landscaping Trades Contractor shall provide and install all mulch, and topsoil’s as indicated within the landscape plan pages.

8. Landscape Trades Contractor shall provide and install soil amendments/mixes/media. 9. Landscape Trades Contractor shall provide install trees, shrubs, plants and ground

cover, Root Barriers as indicated.

Page 74: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-36

10. Note: General Trades Contractor will provide and install all site furniture, fencing, tree grates and gates shown on the Landscape drawings.

11. Landscaping contractor shall provide and install landscape header boards where not transitioning with Earth Work & Paving contractors work.

12. Landscaping Trades Contractor shall provide irrigation sleeves under areas of existing and future concrete walkways and paving as applicable. Provide mobilizations as necessary to get this work done.

13. Landscaping Trades Contractor shall provide and place concrete base for their irrigation backflow devices if applicable.

14. The Landscaping Trades Contractor will provide the biotreatment soil mix and the planting for all bioretention systems at bioretention areas. (Note: The Earthwork and Paving Trades Contractor shall perform excavation to subgrade, The U.G. Utilities Trades Contractor will provide perforated piping, drain inlets, and class II permeable rock, and river rock, The Site Concrete Trades Contractor will provide concrete planter boxes as needed).

15. Landscaping trades contractor shall install necessary water meters and backflow devices for irrigation per plans and specs.

END OF LANDSCAPING TRADES SCOPE STATEMENT

Page 75: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-37

SCOPE STATEMENT – Bid Package G, General Trades TAFT COMMUNITY SCHOOL - NEW BUILDINGS, MODERNIZATION & SITEWORK SCOPE OF WORK DEFINED BELOW AND IN ACCORDANCE WITH THE CONTRACT DRAWINGS, DIVISION OO, DIVISION O1, DSA 103 Statement of Structural Tests and Special Inspections,

AND TECHNICAL SPECIFICATION SECTIONS (NOTE ALL ITEMS IN RED ADDED DURING ADDENDUM 1): 024119, 031100, 032000, 033000, 033507, 034843, 051200, 053100, 054000, 055000, 055113, 055133, 055213, 061053, 061600, 062023, 064116, 068316, 071326, 071413, 071616, 071813, 072100, 072500, 072513, 072616, 074213.19, 074293, 075216.13, 076200, 077129, 077233, 078413, 078443, 079200, 079513.16, 081113, 081416, 081433, 081743, 083113, 084113, 084413, 087100, 087113, 088000, 089119, 089200, 090561.13, 092116.23, 092216, 092400.13, 092900, 093013, 095113, 096513, 096519, 096723, 096813, 097723, 099100, 101100, 101400, 101419, 101463, 102113.19, 102613, 102813, 104403, 107113, 107316 (M Bar C), 107516, 114123, 115123, 122400, 122413, 123450, 142423, 220000, 230000, 260500, 323113, 323119, 323300

DRAWINGS: Taft Community School - New Buildings, Modernization & Sitework applicable drawings and details as they pertain to the Scope of Work designated below. Required scope and details for this bid package may be shown on General, Civil, Landscape, Architectural, Structural, Mechanical, Plumbing, Fire Protection, Electrical, Fire Alarm, Elevator, and Energy Compliance drawings.

DESCRIPTION: Project will be phased according to the construction schedule included herein. Furnish all labor, materials, equipment and services required for the above listed specification sections covering related work as per project plans and specifications and as described below:

S C O P E O F W O R K

SECTION A – GENERAL ITEMS; SPECIAL ATTENTION SHOULD BE GIVEN TO THE FOLLOWING:

1. Overhead, bonds and insurance: Contractor shall include all costs for home office overhead, field overhead, performance and payment bonds and insurance as required in the contract documents.

2. Security: Contractor will be responsible for compliance with Department of Justice requirements for school construction. All on site employees will be required to wear a construction badge or be escorted or accompanied by a badged contractor or school district representative through non construction areas.

3. The Construction Manager shall provide a debris box for general cleanup. Contractors will be required to clean up daily and load their trash in the debris box. Job clean-up will be at the direction of the Construction Manager. Note: If demolition is called for in Contractor’s scope of work, Contractor is responsible for providing his own debris box and removing all demolition debris from the site in a timely manner, but in no case longer than seven (7) days from the date of demolition. The Construction Manager’s debris box shall not be used for depositing selective demolition debris.

4. General Trades Contractor shall be responsible for their own scaffolding, lifts, and hoists.

5. The Construction Manager shall provide portable toilets and hand wash stations.

Page 76: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-38

6. The Construction Manager will provide temporary fencing around the jobsite perimeter, as necessary. Contractor will be responsible for maintaining if relocated and/or disassembled.

7. General Trades Contractor shall be responsible for maintaining safety compliance and weekly safety meetings.

8. General Trades Contractor shall be responsible for their own phone service and drinking water.

9. General Trades Contractor employees will park in parking spaces or designated parking area identified by the Construction Manager.

10. General Trades Contractor shall be required to coordinate their work with other Prime Contractors, attend weekly coordination meetings and provide a 3 week look ahead schedule and daily manpower & equipment reports.

11. Time is of the essence on this project. General Trades Contractor shall adhere to the Construction Schedule as provided by Construction Manager and may be financially responsible for delays to the schedule in accordance with the contract.

12. General Trades Contractor shall refer to the Contractor Access, Laydown and Staging Plan for limits of construction. temporary power and water location. Specific areas for laydown and staging for each trade shall be as determined by the Construction Manager.

13. General Trades Contractor shall ensure a superintendent or foreman who is an employee of the contractor shall be present at all times while contractor or subcontractor workers are on site.

14. General Trades Contractor shall ensure payment of prevailing wages and timely submission of certified payrolls for all contractor employees and subcontractors.

15. General Trades Contractor shall protect from damage to all existing utilities, trees, buildings, hardscape and landscaping to remain.

16. General Trades Contractor shall review all Trade Scope Statements carefully and understand other Prime Contractors’ responsibilities. Contractor shall request pre-bid clarifications for items that are missing in scope, repeated in scopes, or may require coordination.

17. General Trades Contractor shall be responsible for cleaning pavement and streets from dirt and debris due to their work. Contractors will provide daily clean-up for their work.

18. Any contractor that disturbs SWPPP measures is responsible for returning them to their previous conditions.

19. All Prime Trades Contractors and their Sub-Contractors shall follow, maintain, repair and or replace Erosion Control and storm water pollution prevention measures (BMPs) as their work impacts the established BMP’s as per plans and at the direction of the Construction Manager.

20. All Trades Contractors and your subcontractors will strictly comply with all SWPPP, BMP, CEQA, MND, MMRP, SMP, HazMat, Geological, survey(s), Drawings reports managing measures as it applies to your work. If you disrupt or expose a previously protected and contained element or component during your construction processes, you are required to restore, protect and or contain the affected area(s) restoring the integrity of the area(s) disrupted or exposed as described within the above mentioned documents and as identified by the Construction Management Team.

21. Any and All Contractors off-hauling Soils, Concrete and Asphalt, are to follow the specific guidelines set forth within the Site Specific CEQA and Geotechnical report including MND, MMRP, and SMP Reports.

22. All trades contractors must adhere and comply with and to the findings and recommendations stated in the Geotechnical Evaluation and Geologic Hazard Assessment Report(s) including its Addendum 1 provided by Ninyo and Moore (project #402965006, dated December 11, 2017 & November 16, 2018) and at the direction of

Page 77: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-39

The District. This statement supersedes any contradictory verbiage which may be in the contract documents.

SECTION B – SPECIFIC ITEMS FOR THIS BID PACKAGE:

Do not exclude any of the following from your bid. Exclusions of any items may render your bid non-responsive.

1. Work is scheduled for a 5-day work week per the attached schedule. Overtime and weekend work is not mandatory unless where designated on the project schedule, however contractor shall ensure sufficient straight time manpower is provided to complete tasks within the durations indicated. If work is delayed due to circumstances beyond the contractor’s control, then the construction manager may adjust the schedule or authorize overtime via change order in order to maintain the schedule.

2. Provide for costs of bonds, insurance, secure equipment and materials storage, provide supervision of sub-trade contractor labor, coordination with other trade contractors, safety, Cal-OSHA approved protection, costs for DOJ background checks, copying, telephones and fax service, office trailers and temporary utilities if needed (location to be determined by Construction Manager), computers and printers.

3. All Trades Contractors shall provide required submittals, shop drawings, RFI’s, PCO’s and any required documents through “ColbiDocs”, The District,s online document processing program.

4. General Trades Contractor shall recycle building materials and waste to their fullest extent.

5. All contractors are required to submit certified payroll for their forces as well as sub tier trades directly to the Department of Industrial Relations. Contractors and subcontractors will be required to register and submit payroll reports electronically.

6. General Trades Contractor must provide layout of General Contractors work. 7. General Trades Contractor shall provide exterior building scaffolding, scaffold stair

tower to the second floor and roof for each building until exterior finishes, stairs and roof access has been completed and determined safe. Scaffolding will be used by building trades subcontractors and other district prime contractors.

8. General Trades Contractor will coordinate all required tests and inspections associated with their work.

9. General Trades Contractor shall include all allowances and unit price items in bid as called for in this scope statement and on the bid form.

10. Work done by others: Abatement of Lead and Asbestos per ProTech report. 11. All Trades Contractors will replace in kind the winterization rock when disturbed by their

work. Drawings Specific Scope of Work: (NOTE ALL ITEMS IN RED ADDED DURING ADDENDUM 1) 1. General Trades Contractor shall provide DSA deferred submittals to include structural

calculations, submittal documentation, drawings as required per specifications and plans for Elevator guide rails, Glazed Aluminum Curtain Walls, Aluminum Storefront Systems and Windows.

2. The General Trades Contractor is responsible for the New Two-Story Classroom buildings, all existing modernization of buildings construction and selective demolition and selective improvements on said buildings as noted in the plans & specs.

3. After the abatement phase, the general trades contractor will perform modernization selective demolition where indicated per plans.

Page 78: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-40

4. General Trades Contractor is to protect all temporarily exposed openings against adverse weather, wind and water intrusion.

5. For the New Classroom buildings, the General Trades Contractor will provide, install and perform finish excavation/grade for building footings and SOG (note: rough subgrade is by the Earthwork and Paving Contractor), under slab crushed rock and vapor barrier, vapor emission control system, interior housekeeping pads if applicable, structural steel, all metal decking including building & decking roof and misc. steel and metal fabrications, steel reinforcing, embeds for posts in new concrete, complete building hand and guard railing, complete stair assemblies, lightweight concrete, building rough framing (metals and wood), wood/metal blocking for all trades, furring and backing for all trades, nailers, building structural concrete, provide beam penetrations as needed and coordinate with electrical and fire sprinkler, plumbing, mechanical contractors, architecturally exposed structural steel framing, building expansion / seismic joint assemblies, light gauge metal framing for walls and ceilings, welding, misc. rough carpentry including fire treated plywood, interior and exterior finish carpentry, soffits, all building insulations, roofing, roof accessories, gutters, downspouts, scuppers, sheet metal flashing and trim, fire stopping doors, frames, door and window hardware, door grilles, aluminum store front system, windows, translucent walls/ skylights, glass glazing, louvers, vents, access ladder(s), access hatch(s), drywall installation and finishing, exterior walls, plaster, trim, screeds and lath, ceramic tile, mortar bed, wood wall panels, all casework countertops, shelving, all interior and exterior painting, provide anti-graffiti coatings, CMU walls/Pilasters, steel & concrete columns/beams, roof trim/facia, cement plaster / wood / metal / drywall soffits, Glazing, interior gypsum board, per plans & specs, Include paint for door swing caution lines & Exclude paint for concrete curbs, (Site Concrete Trade will provide curb paint), flooring, walk off mats, floor base including VCT flooring, roller window shades, entrance floor grills, sealants, signage for buildings and gates/fences, fire extinguishers and cabinets, all restroom epoxy floor and tile, wall coverings, toilet accessories and partitions, hand dryers, cane detection railing, Markerboards, Flag Pole and concrete foundation, final janitorial and cleaning.

6. General Trade Contractor shall Install related wall and roof flashings, vents and access panels for HVAC, Electrical, Fire Protection and Plumbing Trades (note: the related wall and roof flashings, vents and access panels will be provided to the General Trades Contractor by the respective trade contractors).

7. Any Core structural penetrations must be coordinated with electrical, HVAC, Plumbing and fire sprinkler contractors for any penetration locations.

8. General Trade Contractor shall be responsible to supply, coordinate, provide and Install All Modernization work and materials for MU/Food Services Building H including but not limited to, Selective Demolition, patch and repair drywall, Paint, walk-in refrigerator Install, Condensate lines, plumbing, and associated connections for walk-in refrigerator, Protect existing equipment’s in the MU/Food Services Building. The GC shall provide materials, labor and installation for the collateral work associated with and for plumbing, and concrete matching adjacent surfaces . (excluding all electrical safe off, electrical stub ups, district specific security cameras and Fire Alarm work and final tie-in, this work will go to the Electrical Prime Contractor).

9. General Trade Contractor shall be responsible to supply and install all Modernization work and materials for Buildings “A, B, C, E, H, and I”. General Trades Contractor to provide selective demolition and modifications of Building “A, B, C, E, H, and I” per plans and specs, Including patch, repair, match adjacent surfaces, paint, Door and Door Hardware upgrades, Exterior Soffit work, Manual roller shades upgrade per sheet AS-104 Note 9, Motorized Roller Shades, VCT Flooring & rubber wall base. (Note: The

Page 79: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-41

electrical Trades contractor will provide campus fire alarm, low voltage, security system and cameras).

10. General Trades Contractor shall provide and install fences and gates including Provide and install chain-link fencing, and ornamental fencing per new building and modernization plans.

11. General Trades Contractor to provide decorative striping. (parking lot and associated vehicular striping to be provided by the Earth Work & Paving Contractor.)

12. General Trades Contractor shall provide and install all Site Furnishings including those items on the landscaping drawings. Trash Receptacle(s), Bike Rack(s), Park Bench(s)/Precast Seat Pad(s), Tree Grate(s) (see divisions, 323300) (Note: Bollards to be installed by Site Concrete Contractor)

13. General Trades Contractor shall provide and install all epoxy flooring system, polish concrete and sealed concrete flooring. General Trades Contractor to provide and install all carpet tile and associated base.

14. General Trades Contractor shall provide pedestrian traffic coating where applicable per plans and specs to those items within and attached to the buildings.

15. General Trades Contractor shall provide and install the complete hydraulic passenger elevator for New Building. (Electrical and Low Voltage Trades Contractor shall provide and install conduit, raceways, wiring for power, signal, and shunt control to elevator. Provide power and signal connections to the elevator control panel.) General Trades Elevator Contractor will install elevator power and low voltage from the control panel to the elevator system.

16. General Trades Contractor shall obtain and provide all necessary permits for Elevator as applicable. The General Trades Contractor will be reimbursed by the district for the cost of obtaining permits.

17. General Trades Contractor shall provide and apply building joint sealants and caulking’s as it applies to the GC’s trades work.

18. General Trades Contractor shall provide and install locksets, district specific cores and hardware assemblies associated with all doors, storefronts, and gates per plans and specs for new buildings and modernization.

19. General Trades Contractor shall install all roof penetration flashings, provided by Plumbing, Electrical, Fire Sprinkler, landscape and Mechanical trade contractors as applicable.

20. General Trade Contractor shall install all sun control/sunshades/canopy and associated components that are connected to the new buildings.

21. General Trades Contractor shall provide and install M bar C Canopies. See sheets AS-101, and AS-121. (The General Trades Contractor shall obtain proprietary M bar C geotechnical report for canopies and oversee and manage to ensure that M bar C will adhere and comply with and to the findings and recommendations stated in the Geotechnical Evaluation.)

22. The General Trades Contractor to include Two Hundred Thousand Dollars ($200,000.00) allowance for oversight, for management and implementation of M bar C Canopy/Geotechnical report, for unforeseen modernization finish repairs, for patch and repair of existing walls and ceiling finishes at existing Modernization buildings and MU/Food Services as a result of installation of upgraded MU/Food Services items, and for winterization of excavated foundations and installation of foundations for protection in the event of adverse weather or subsurface water, and beam penetrations.

23. General Trades Contractor shall provide a bid for add alternates in the modernization plans, and shall be responsible to supply and install the alternate work per district approval. (See A-561M)

a. Add Alternate 1A: Provide pricing per, but not limited to sheet A-561M. b. Add Alternate 1B: Provide pricing per, but not limited to sheet A-561M.

Page 80: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-42

c. Add Alternate 2: Provide pricing per, but not limited to sheet A-561M. 24. The General Trades Contractor is to provide all shoring and support for the partially

demoed canopy per, but not limited to Sheets S9.4, and S9.5, and is to coordinate with the Earthwork and Paving Trades Contractor during partial demo phase in order to provide support and shoring per the plans.

END OF GENERAL TRADES SCOPE STATEMENT

Page 81: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-43

SCOPE STATEMENT – Bid Package H, Plumbing Trades TAFT COMMUNITY SCHOOL - NEW BUILDINGS, MODERNIZATION & SITEWORK SCOPE OF WORK DEFINED BELOW AND IN ACCORDANCE WITH THE CONTRACT DRAWINGS, DIVISION OO, DIVISION O1, DSA 103 Statement of Structural Tests and Special Inspections,

AND TECHNICAL SPECIFICATION SECTIONS: 024119, 078413, 078443, 079200, 114123, 123450, 230000, 312333, 330513, 331000, 333000

DRAWINGS: Taft Community School - New Buildings, Modernization & Sitework applicable drawings and details as they pertain to the Scope of Work designated below. Required scope and details for this bid package may be shown on General, Civil, Structural, Mechanical, Plumbing, Fire Protection, Electrical, and Energy Compliance drawings.

DESCRIPTION: Project will be phased according to the construction schedule included herein. Furnish all labor, materials, equipment and services required for the above listed specification sections covering related work as per project plans and specifications and as described below:

S C O P E O F W O R K

SECTION A - GENERAL ITEMS; SPECIAL ATTENTION SHOULD BE GIVEN TO THE FOLLOWING:

1. Overhead, bonds and insurance: Contractor shall include all costs for home office overhead, field overhead, performance and payment bonds and insurance as required in the contract documents.

2. Security: Contractor will be responsible for compliance with Department of Justice requirements for school construction. All on site employees will be required to wear a construction badge or be escorted or accompanied by a badged contractor or school district representative through non construction areas.

3. The Construction Manager shall provide a debris box for general cleanup. Contractors will be required to clean up daily and load their trash in the debris box. Job clean-up will be at the direction of the Construction Manager. Note: If demolition is called for in Contractor’s scope of work, Contractor is responsible for providing his own debris box and removing all demolition debris from the site in a timely manner, but in no case longer than seven (7) days from the date of demolition. The Construction Manager’s debris box shall not be used for depositing selective demolition debris.

4. The Construction Manager shall provide portable toilets and hand wash stations. 5. Plumbing Trades Contractor shall be responsible for their own scaffolding, lifts, and

hoists. 6. The Construction Manager will provide temporary fencing around the jobsite perimeter,

as necessary. Contractor will be responsible for maintaining if relocated and/or disassembled.

7. Plumbing Trades Contractor shall be responsible for maintaining safety compliance and weekly safety meetings.

8. Plumbing Trades Contractor shall be responsible for their own phone service and drinking water.

9. Plumbing Trades Contractor employees will park in parking spaces or designated parking area identified by the Construction Manager.

Page 82: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-44

10. Plumbing Trades Contractor shall be required to coordinate their work with other Prime Contractors, attend weekly coordination meetings and provide 3 week look ahead schedule and daily tasks, manpower and equipment reports.

11. Time is of the essence on this project. Plumbing Trades Contractor shall adhere to the Construction Schedule as provided by Construction Manager and may be financially responsible for delays to the schedule in accordance with the contract.

12. Plumbing Trades Contractor shall refer to the Contractor Access, Laydown and Staging Plan for limits of construction. temporary power and water location. Specific areas for laydown and staging for each trade shall be as determined by the Construction Manager.

13. Plumbing Trades Contractor shall ensure a superintendent or foreman who is an employee of the contractor shall be present at all times while contractor or subcontractor workers are on site.

14. Plumbing Trades Contractor shall ensure payment of prevailing wages and timely submission of certified payrolls for all contractor employees and subcontractors.

15. Plumbing Trades Contractor shall protect from damage to all existing utilities, trees, buildings, hardscape and landscaping to remain.

16. Plumbing Trades Contractor shall review all Trade Scope Statements carefully and understand other Prime Contractors’ responsibilities. Contractor shall request pre-bid clarifications for items that are missing in scope, repeated in scopes, or may require coordination.

17. Plumbing Trades Contractor shall be responsible for cleaning pavement and streets from dirt and debris due to their work. Contractors will provide daily clean-up for their work.

18. Any contractor that disturbs SWPPP measures is responsible for returning them to their previous conditions.

19. All Prime Trades Contractors and their Sub-Contractors shall follow, maintain, repair and or replace Erosion Control and storm water pollution prevention measures (BMPs) as their work impacts the established BMP’s as per plans and at the direction of the Construction Manager.

20. All Trades Contractors and your subcontractors will strictly comply with all SWPPP, BMP, CEQA, MND, MMRP, SMP, HazMat, Geological, survey(s), Drawings reports managing measures as it applies to your work. If you disrupt or expose a previously protected and contained element or component during your construction processes, you are required to restore, protect and or contain the affected area(s) restoring the integrity of the area(s) disrupted or exposed as described within the above mentioned documents and as identified by the Construction Management Team.

21. Any and All Contractors off-hauling Soils, Concrete and Asphalt, are to follow the specific guidelines set forth within the Site Specific CEQA and Geotechnical report including MND, MMRP, and SMP Reports.

22. All trades contractors must adhere and comply with and to the findings and recommendations stated in the Geotechnical Evaluation and Geologic Hazard Assessment Report(s) including its Addendum 1 provided by Ninyo and Moore (project #402965006, dated December 11, 2017 & November 16, 2018) and at the direction of The District. This statement supersedes any contradictory verbiage which may be in the contract documents.

Page 83: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-45

SECTION B – SPECIFIC ITEMS FOR THIS BID PACKAGE:

Do not exclude any of the following from your bid. Exclusions of any items may render your bid non-responsive.

1. Work is scheduled for a 5-day work week per the attached schedule. Overtime and weekend work is not mandatory unless where designated on the project schedule, however contractor shall ensure sufficient straight time manpower is provided to complete tasks within the durations indicated. If work is delayed due to circumstances beyond the contractor’s control, then the construction manager may adjust the schedule or authorize overtime via change order in order to maintain the schedule.

2. Provide for costs of bonds, insurance, secure equipment and materials storage, provide supervision of sub-trade contractor labor, coordination with other trade contractors, safety, Cal-OSHA approved protection, costs for DOJ background checks, copying, telephones and fax service, office trailers and temporary utilities if needed (location to be determined by Construction Manager), computers and printers.

3. All Trades Contractors shall provide required submittals, shop drawings, RFI’s, PCO’s and any required documents through “ColbiDocs”, The District’s online document processing program.

4. Plumbing Trades Contractor must recycle building materials and waste to their fullest extent.

5. All contractors are required to submit certified payroll for their forces as well as sub tier trades directly to the Department of Industrial Relations. Contractors and subcontractors will be required to register and submit payroll reports electronically.

6. Plumbing Trades Contractor must provide layout of Plumbing Contractors work. 7. Plumbing Trades Contractor shall include all allowances and unit price items in bid as

called for in this scope statement and on the bid form. 8. All Trades Contractors will replace in kind the winterization rock when disturbed by their

work. Drawings Specific Scope of Work: 1. Plumbing Trades Contractor shall remove spoils from excavation of trenches specified

within the soils mitigation plan and dispose of soils to an appropriate landfill per requirements stated in section “A” item #’s 20 & 21 of this document.

2. All excess excavation spoils are to be removed to an appropriate landfill per the requirements stated in section “A” item #’s 20 & 21 of this document.

3. Plumbing Trades Contractor shall provide all necessary safe off prior to selective demolition for building modernization. (see, but not limited to: PS-101, PSD-01)

4. Plumbing Trades Contractor is responsible to land connections for electrical to Insta hots, toilets, and other plumbing fixtures and accessories which have electrical components in new classroom buildings. (Note: Electrical contractor to provide conduit and wiring stub up to all plumbing utilities and plumbing trades contractor to make final connections).

5. Plumbing Trades Contractor shall provide materials and labor for final utility connections from the field to the New Building(s). Underground Utilities Trades Contractor shall extend their respective utilities to within five feet of the New Building(s).

6. Plumbing Trades Contractor is to provide, from UG supplied stubs, all final utility connections to the buildings.

7. Plumbing Trades Contractor will provide and install for all New Building(s) piping and conveyance systems for domestic water, gas, sanitary sewer, plumbing vents, floor

Page 84: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-46

drains, fixtures, sinks, drinking fountains, hangers, valves, valve boxes, gas regulators, lockable steel cages for gas shut-off valves, back flow preventers associated with domestic plumbing, water fountains, sinks, toilets, urinals, water heaters, insta-hots, drywells, plumbing insulation, and ID labeling , condensate piping and drains ,as indicated in the plans.

8. Plumbing Trades Contractor will provide and install HVAC condensate piping to condensate neutralizer, and HVAC Trades Contractor is to make their connection from the neutralizer to the Plumber Trades supplied condensate line.

9. Plumbing Trades Contractor shall install all seismic expansion joint piping and hangars as required per plans and shall be coordinated with all building systems and Trades Contractors.

10. Plumbing Trades Contractor shall provide materials and layout for all plumbing related wall and roof flashings, vents, and access panels for New Building(s) work. General Trades Contractor to install.

11. Plumbing Trades Contractor shall provide and install all required joint sealants and fire caulking related to plumbing work.

12. Plumbing Trades Contractor shall provide all building domestic water sterilization, testing and flush pipes clean for New and effected modernization.

13. Plumbing Trades Contractor shall connect new cold water to existing cold water piping, and install new wall mounted ¾” CW pipe on existing building B, C, and E as shown, but not limited to, details 14, 15, 16, and 17, on sheet PS-101.

14. Plumbing Trades Contractor is to install and restore above ground gas as shown on, but not limited to, notes 11, 12, 13, 19, 20 and 21 on sheet PS-101 for existing modernization buildings.

15. Note: Underground Utilities Trades Contractor is to install all below grade site gas service to new classroom buildings stubbed 5’ from new buildings (See line item 3 in this document under “Drawings Specific Scope of Work”).

16. Plumbing Trades Contractor to perform Tie-Ins from meters and valves supplying gas to buildings New & Modernization.

END OF PLUMBING TRADES SCOPE STATEMENT

Page 85: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-47

SCOPE STATEMENT – Bid Package I, Fire Protection Trades TAFT COMMUNITY SCHOOL - NEW BUILDINGS, MODERNIZATION & SITEWORK SCOPE OF WORK DEFINED BELOW AND IN ACCORDANCE WITH THE CONTRACT DRAWINGS, DIVISION OO, DIVISION O1, DSA 103 Statement of Structural Tests and Special Inspections,

AND TECHNICAL SPECIFICATION SECTIONS: 078413, 078443, 079200,104400, 142423, 211300, 283100

DRAWINGS: Taft Community School - New Buildings, Modernization & Sitework applicable drawings and details as they pertain to the Scope of Work designated below. Required scope and details for this bid package may be shown on General, Civil, Landscape, Architectural, Structural, Mechanical, Plumbing, Fire Protection, Electrical, Fire Alarm, Elevator, and Energy Compliance drawings.

DESCRIPTION: Project will be phased according to the construction schedule included herein. Furnish all labor, materials, equipment and services required for the above listed specification sections covering related work as per project plans and specifications and as described below:

S C O P E O F W O R K

SECTION A - GENERAL ITEMS; SPECIAL ATTENTION SHOULD BE GIVEN TO THE FOLLOWING:

1. Overhead, bonds and insurance: Contractor shall include all costs for home office overhead, field overhead, performance and payment bonds and insurance as required in the contract documents.

2. Provide for costs of bonds, insurance, secure equipment and materials storage, provide supervision of sub-trade contractor labor, coordination with other trade contractors, safety, Cal-OSHA approved protection, costs for DOJ background checks, copying, telephones and fax service, office trailers and temporary utilities if needed (location to be determined by Construction Manager), computers and printers.

3. Security: Contractor will be responsible for compliance with Department of Justice requirements for school construction. All on site employees will be required to wear a construction badge or be escorted or accompanied by a badged contractor or school district representative through non construction areas.

4. The Construction Manager shall provide a debris box for general cleanup. Contractors will be required to clean up daily and load their trash in the debris box. Job clean-up will be at the direction of the Construction Manager. Note: If demolition is called for in Contractor’s scope of work, Contractor is responsible for providing his own debris box and removing all demolition debris from the site in a timely manner, but in no case longer than seven (7) days from the date of demolition. The Construction Manager’s debris box shall not be used for depositing selective demolition debris.

5. The Construction Manager shall provide portable toilets and hand wash stations. 6. Fire Protection Trades Contractor shall be responsible for their own scaffolding, lifts,

and hoists. 7. The Construction Manager will provide temporary fencing around the jobsite perimeter,

as necessary. Contractor will be responsible for maintaining if relocated and/or disassembled.

Page 86: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-48

8. Fire Protection Trades Contractor shall be responsible for maintaining safety compliance and weekly safety meetings.

9. Fire Protection Trades Contractor shall be responsible for their own phone service and drinking water.

10. Fire Protection Trades Contractor employees will park in parking spaces or designated parking area identified by the Construction Manager.

11. Fire Protection Trades Contractor shall be required to coordinate their work with other Prime Contractors, attend weekly coordination meetings and provide 3 week look ahead schedule and daily manpower reports.

12. Time is of the essence on this project. Fire Protection Trades Contractor shall adhere to the Construction Schedule as provided by Construction Manager and may be financially responsible for delays to the schedule in accordance with the contract.

13. Fire Protection Trades Contractor shall refer to the Contractor Access, Laydown and Staging Plan for limits of construction. temporary power and water location. Specific areas for laydown and staging for each trade shall be as determined by the Construction Manager.

14. Fire Protection Trades Contractor shall ensure a superintendent or foreman who is an employee of the contractor is present at all times while contractor or subcontractor workers are on site.

15. Fire Protection Trades Contractor shall ensure payment of prevailing wages and timely submission of certified payrolls for all contractor employees and subcontractors.

16. Fire Protection Trades Contractor shall protect from damage to all existing utilities, trees, buildings, hardscape and landscaping to remain.

17. Fire Protection Trades Contractor shall review all Trade Scope Statements carefully and understand other Prime Contractors’ responsibilities. Contractor shall request pre-bid clarifications for items that are missing in scope, repeated in scopes, or may require coordination.

18. Fire Protection Trades Contractor shall be responsible for cleaning pavement and streets from dirt and debris due to their work. Contractors will provide daily clean-up for their work.

19. Any contractor that disturbs SWPPP measures is responsible for returning them to their previous conditions.

20. All Prime Trades Contractors and their Sub-Contractors shall follow, maintain, repair and or replace Erosion Control and storm water pollution prevention measures (BMPs) as their work impacts the established BMP’s as per plans and at the direction of the Construction Manager.

21. All Trades Contractors and your subcontractors will strictly comply with all SWPPP, BMP, CEQA, MND, MMRP, SMP, HazMat, Geological, survey(s), Drawings reports managing measures as it applies to your work. If you disrupt or expose a previously protected and contained element or component during your construction processes, you are required to restore, protect and or contain the affected area(s) restoring the integrity of the area(s) disrupted or exposed as described within the above mentioned documents and as identified by the Construction Management Team.

22. Any and All Contractors off-hauling Soils, Concrete and Asphalt, are to follow the specific guidelines set forth within the Site Specific CEQA and Geotechnical report including MND, MMRP, and SMP Reports.

23. All trades contractors must adhere and comply with and to the findings and recommendations stated in the Geotechnical Evaluation and Geologic Hazard Assessment Report(s) including its Addendum 1 provided by Ninyo and Moore (project #402965006, dated December 11, 2017 & November 16, 2018) and at the direction of The District. This statement supersedes any contradictory verbiage which may be in the contract documents.

Page 87: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-49

SECTION B – SPECIFIC ITEMS FOR THIS BID PACKAGE:

Do not exclude any of the following from your bid. Exclusions of any items may render your bid non-responsive.

1. Work is scheduled for a 5 day work week per the attached schedule. Overtime and weekend work is not mandatory unless where designated on the project schedule, however contractor shall ensure sufficient straight time manpower is provided to complete tasks within the durations indicated. If work is delayed due to circumstances beyond the contractor’s control, then the construction manager may adjust the schedule or authorize overtime via change order in order to maintain the schedule.

2. Provide for costs of bonds, insurance, secure equipment and materials storage, provide supervision of sub-trade contractor labor, coordination with other trade contractors, safety, Cal-OSHA approved protection, costs for DOJ background checks, copying, telephones and fax service, office trailers and temporary utilities if needed (location to be determined by Construction Manager), computers and printers.

3. All Trades Contractors shall provide required submittals, shop drawings, RFI’s, PCO’s and any required documents through “ColbiDocs”, The District’s online document processing program.

4. Fire Protection Trades Contractor must recycle building materials and waste to their fullest extent.

5. All contractors are required to submit certified payroll for their forces as well as sub tier trades directly to the Department of Industrial Relations. Contractors and subcontractors will be required to register and submit payroll reports electronically.

6. Fire Protection Trades Contractor shall provide layout of Fire Protection Trade Contractor’s work.

7. Fire Protection Trades Contractor shall be responsible for their own scaffolding, lifts and hoists. Utilize the correct equipment to prevent damages to the completed site work.

8. Fire Protection Trades Contractor shall include all allowances and unit price items in bid as called for in this scope statement and on the bid form.

9. The district will pay or reimburse for permit fee and the Fire Protection Trades Contractor will apply and obtain the permit and perform work per plans.

10. All Trades Contractors will replace in kind the winterization rock when disturbed by their work.

Drawings Specific Scope of Work: 1. Fire Protection Trades Contractor will provide and install all interior fire sprinkler

system, Include fire riser flow/tamper switches, gages, valves, labeling and bell/Audible System. (note: exterior fire distribution and installation of fire line risers to approximately 12 inches above interior slabs at fire riser locations is by UG Utility Trades contractor. The Electrical Trades Contractor will provide conduits, wiring, and termination to the fire riser F/A signal devices and bell).

2. Fire Protection Trades Contractor to land final power to their Riser Tamper Switch in the Riser Room.

3. Fire Protection Trades Contractor shall provide and install all fire sprinkler piping, hangers, seismic bracing, seismic expansion joint and sprinklers as required per plans and shall be coordinated with all building systems Trades Contractors. (Note: General Trades Contractor will provide required blocking.)

4. Fire Protection Trades Contractor shall provide and install spare sprinkler cabinets near each riser outfitted with the appropriate heads, cages, wrench(s).

Page 88: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-50

5. Note: Underground Utilities Contractor will flush underground piping prior to Fire Protection Trades riser tie-in & installation of fire system.

6. Fire Protection Trades contractor shall provide caulking for all penetrations for the fire protection trades contractors work.

7. Fire Protection Trades Contractor shall provide materials and layout for all Fire Protection related wall and roof flashings, vents, and access panels for New Building(s) work. General Trades Contractor to install.

END OF FIRE PROTECTION TRADES SCOPE STATEMENT

Page 89: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-51

SCOPE STATEMENT – Bid Package J, Abatement Trades TAFT COMMUNITY SCHOOL - NEW BUILDINGS, MODERNIZATION & SITEWORK SCOPE OF WORK DEFINED BELOW AND IN ACCORDANCE WITH THE CONTRACT DRAWINGS, DIVISION OO, DIVISION O1, DSA 103 Statement of Structural Tests and Special Inspections,

AND TECHNICAL SPECIFICATION SECTIONS: 024119

DRAWINGS: Taft Community School - New Buildings, Modernization & Sitework applicable drawings and details as they pertain to the Scope of Work designated below.

DESCRIPTION: Project will be phased according to the construction schedule included herein. Furnish all labor, materials, equipment and services required for the above listed specification sections covering related work as per project plans and specifications and as described below:

S C O P E O F W O R K

SECTION A - GENERAL ITEMS; SPECIAL ATTENTION SHOULD BE GIVEN TO THE FOLLOWING:

1. Overhead, bonds and insurance: Contractor shall include all costs for home office overhead, field overhead, performance and payment bonds and insurance as required in the contract documents.

2. Security: Contractor will be responsible for compliance with Department of Justice requirements for school construction. All on site employees will be required to wear a construction badge or be escorted or accompanied by a badged contractor or school district representative through non construction areas.

3. The Construction Manager shall provide a debris box for general cleanup. Contractors will be required to clean up daily and load their trash in the debris box. Job clean-up will be at the direction of the Construction Manager. Note: If demolition is called for in Contractor’s scope of work, Contractor is responsible for providing his own debris box and removing all demolition debris from the site in a timely manner, but in no case longer than seven (7) days from the date of demolition. The Construction Manager’s debris box shall not be used for depositing selective demolition debris.

4. The Construction Manager shall provide portable toilets and hand wash stations. 5. Abatement Trades Contractor shall be responsible for their own scaffolding, lifts, and

hoists. 6. The Construction Manager will provide temporary fencing around the jobsite perimeter,

as necessary. Contractor will be responsible for maintaining if relocated and/or disassembled.

7. Abatement Trades Contractor shall be responsible for maintaining safety compliance and weekly safety meetings.

8. Abatement Trades Contractor shall be responsible for their own phone service and drinking water.

9. Abatement Trades Contractor employees will park in parking spaces or designated parking area identified by the Construction Manager.

10. Abatement Trades Contractor shall be required to coordinate their work with other Prime Contractors, attend weekly coordination meetings and provide a 3 week look ahead schedule and daily manpower & equipment reports.

Page 90: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-52

11. Time is of the essence on this project. Abatement Trades Contractor shall adhere to the Construction Schedule as provided by Construction Manager and may be financially responsible for delays to the schedule in accordance with the contract.

12. Abatement Trades Contractor shall refer to the Contractor Access, Laydown and Staging Plan for limits of construction. temporary power and water location. Specific areas for laydown and staging for each trade shall be as determined by the Construction Manager.

13. Abatement Trades Contractor shall ensure a superintendent or foreman who is an employee of the contractor shall be present at all times while contractor or subcontractor workers are on site.

14. Abatement Trades Contractor shall ensure payment of prevailing wages and timely submission of certified payrolls for all contractor employees and subcontractors.

15. Abatement Trades Contractor shall protect from damage to all existing utilities, trees, buildings, hardscape and landscaping to remain.

16. Abatement Trades Contractor shall review all Trade Scope Statements carefully and understand other Prime Contractors’ responsibilities. Contractor shall request pre-bid clarifications for items that are missing in scope, repeated in scopes, or may require coordination.

17. Abatement Trades Contractor shall be responsible for cleaning pavement and streets from dirt and debris due to their work. Contractors will provide daily clean-up for their work.

18. Any contractor that disturbs SWPPP measures is responsible for returning them to their previous conditions.

19. All Prime Trades Contractors and their Sub-Contractors shall follow, maintain, repair and or replace Erosion Control and storm water pollution prevention measures (BMPs) as their work impacts the established BMP’s as per plans and at the direction of the Construction Manager.

20. All Trades Contractors and your subcontractors will strictly comply with all SWPPP, BMP, CEQA, MND, MMRP, SMP, HazMat managing measures as it applies to your work. If you disrupt or expose a previously protected and contained element or component during your construction processes, you are required to restore, protect and or contain the affected area(s) restoring the integrity of the area(s) disrupted or exposed as described within the above mentioned documents and as identified by the Construction Management Team.

21. Any and All Contractors off-hauling Soils, Concrete and Asphalt, are to follow the specific guidelines set forth within the Site Specific CEQA and Geotechnical report including MND, MMRP, and SMP Reports.

22. All trades contractors must adhere and comply with and to the findings and recommendations stated in the Geotechnical Evaluation and Geologic Hazard Assessment Report(s) including its Addendum 1 provided by Ninyo and Moore (project #402965006, dated December 11, 2017 & November 16, 2018) and at the direction of The District. This statement supersedes any contradictory verbiage which may be in the contract documents.

SECTION B – SPECIFIC ITEMS FOR THIS BID PACKAGE:

Do not exclude any of the following from your bid. Exclusions of any items may render your bid non-responsive.

1. Work is scheduled for a 5 day work week per the attached schedule. Overtime and weekend work is not mandatory unless where designated on the project schedule, however contractor shall ensure sufficient straight time manpower is provided to

Page 91: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

REDWOOD CITY SCHOOL DISTRICT DRAWINGS, SPECIFICATIONS,

SCHEDULES AND SCOPE STATEMENTS TAFT COMMUNITY SCHOOL NEW BUILDINGS, MODERNIZATION & SITEWORK

DOCUMENT 00 01 15-53

complete tasks within the durations indicated. If work is delayed due to circumstances beyond the contractor’s control, then the construction manager may adjust the schedule or authorize overtime via change order in order to maintain the schedule.

2. Provide for costs of bonds, insurance, secure equipment and materials storage, provide supervision of sub-trade contractor labor, coordination with other trade contractors, safety, Cal-OSHA approved protection, costs for DOJ background checks, copying, telephones and fax service, office trailers and temporary utilities if needed (location to be determined by Construction Manager), computers and printers.

3. All Trades Contractors shall provide required submittals, shop drawings, RFI’s, PCO’s and any required documents through “ColbiDocs”, The District’s online document processing program.

4. Abatement Trades Contractor must recycle building materials and waste to their fullest extent.

5. All contractors are required to submit certified payroll for their forces as well as sub tier trades directly to the Department of Industrial Relations. Contractors and subcontractors will be required to register and submit payroll reports electronically.

6. Abatement Trades Contractor to Provide layout of Abatement Trade Contractors work. 7. Abatement Trades Contractor shall Provide all notices and permits required to execute

the abatement and demolition work. 8. Abatement Trades Contractor shall include all allowances and unit price items in bid as

called for in this scope statement and on the bid form. 9. Abatement Trades Contractor shall Protect all existing utilities, trees, buildings,

hardscape and landscaping to remain. 10. Abatement of Lead and Asbestos greater than 1% shall be done by Abatement Trades

Contractor, (Earthwork and Paving Trades contractor shall abate and demo all items with less than 1% contamination) per ProTech Consulting & Engineering report.

11. All Trades Contractors will replace in kind the winterization rock when disturbed by their work.

Drawings Specific Scope of Work: (NOTE ALL ITEMS IN RED ADDED DURING ADDENDUM 1) 1. Prior to building demolition, and Modernization demolition, the Abatement Trades

Contractor shall properly abate and dispose of all asbestos, lead, light tubes, and any other regulated hazardous materials in the quantities and manner indicated in the document “HazMat Report for Asbestos & Lead (Pb) Report Limited Pre-Demolition/Renovation Survey & Evaluation” for Taft dated 06/29/18. Obtain all necessary clearances prior to proceeding with building demolition. Coordinate all abatement activities with the District’s hazardous materials consultant (ProTech).

2. In the event that any unforeseen asbestos, lead, light tubes, ballasts, and any other hazardous regulated materials are discovered, The abatement Trades Contractor shall inform the district representative and properly abate in the manner indicated in the documents stated in section “A” of this document and in the “HazMat Report for Asbestos & Lead (Pb) Report Limited Pre Demolition/Renovation Survey & Evaluation” at the direction of Construction Manager.

3. Abatement Trades Contractor shall include an allowance of Fifty Thousand Dollars ($50,000.00) for any unforeseen asbestos, lead, light tubes, ballasts, and any other hazardous regulated materials discovered.

4. The Abatement Trades contractor will not provide abatement of lead-based items, unless the lead-based materials have been compromised and deemed to have become friable in the process of demolition.

END OF ABATEMENT TRADES SCOPE STATEMENT

END OF DOCUMENT

Page 92: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 11 41 23 Addendum No. 2 Redwood City School District Walk-in Cooler - 1

SECTION 11 41 23

WALK-IN COOLER

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Walk-in Cooler at Existing Building H (Multi-Use).

B. Related Documents: The Conditions of the Contract and Division 1 apply to this section as fully as if repeated herein.

1.2 REFERENCES

A. The editions of specifications and standards referenced herein, published by the following organizations, apply to the construction only to the extent specified by the reference. Refer to Section 01 42 19 for information concerning availability and use of references.

American Welding Society (AWS) ASTM International National Sanitation Foundation (NSF)

Underwriters Laboratories (UL)

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for Walk-in Coolers and accessories.

B. Shop Drawings:

1. Include plans, elevations, sections, and details. 2. Include specifications of panels and shelving (construction material, foam etc.) and

list current (International Green Construction Code) ICC-ES number or other approved listing.

3. Detail fabrication and installation of walk-in cooler and shelving, including methods of anchoring walk-in cooler to building structure at locations recommended by manufacturer and as required for seismic restraint.

4. Indicate compliance with insulation requirements of the 2016 CA Energy code – including the following: a. Cooler walls, ceilings and doors: R-25 Minimum.

5. Provide door opening device and door hardware in compliance with CBC sections 1114B.1.2 and 1104B.5.

C. Samples:

1. Paint Finish: Submit samples of paint finish to be used on metal surfaces.

D. Submittal procedures and quantities are specified in Section 01 33 00.

1.4 INFORMATIONAL SUBMITTALS

Page 93: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 11 41 23 Addendum No. 2 Redwood City School District Walk-in Cooler - 2

A. Submit documentation of compliance with NSF®, UL, and C-UL.

B. Qualification Data: For Installer.

C. Installation Instructions: Submit a complete set of installation instructions covering all phases of panel erection, accessories, and maintenance procedures.

D. Sample Warranty: For manufacturer's special warranty.

1.5 CLOSEOUT SUBMITTALS

A. Operating and Maintenance Data: For Walk-in Coolers, to include in maintenance manuals.

B. Nameplates: Provide permanently affixed, corrosion resistant nameplate, proportionate to size of fixture, bearing manufacturer's name, model and serial numbers, and ratings and characteristics for servicing and maintenance, where applicable, on each item of equipment.

1.6 QUALITY ASSURANCE

A. Requirements of Regulatory Agencies:

1. NSF approved. 2. UL classified for flame spread. 3. UL and CSA electrical listing on door sections. UL Sanitation is Underwriters

Laboratories Sanitation Mark which indicates that UL has tested the equipment to applicable NSF Standards.

4. UL, C-UL listing on complete Capsule Pak™ refrigeration systems. UL Sanitation is Underwriters Laboratories Sanitation Mark which indicates that UL has tested the equipment to applicable NSF Standards.

5. California State listed. 6. DOE compliant. 7. USDA accepted.

B. Walk-in construction is approved by NSF International and shall have the NSF seal on the

door section. C. Walk-in panels shall have foam cores with a UL flame spread rating of 25. D. The door section shall be UL and CSA approved as an electrically approved assembly.

1.7 QUALIFICATIONS

A. Installer: Company specializing in Work of this Section with minimum five (5) years documented experience; manufacturer approved.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Delivery of Equipment:

1. Coordinate delivery with proper schedule and jobsite conditions. 2. Deliver equipment in manufacturer's original packaging, clearly identified as to

product and manufacturer,

Page 94: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 11 41 23 Addendum No. 2 Redwood City School District Walk-in Cooler - 3

3. Where possible, deliver each item of equipment in one (1) piece. If not possible, assemble equipment in the building in accordance with workmanship standards specified herein.

B. Storage of Equipment:

1. Store equipment in protected areas, in manufacturer's original packaging where possible, in such a way as to prevent damage to equipment and finishes, and to the structure. Damaged or defective materials and equipment shall be replaced at no cost to the Owner.

1.9 FIELD CONDITIONS

A. Examine appropriate existing job site areas and notify Owner’s Representative if conditions exist which will impede, inhibit, or prevent the contractor from completing the Work. In the absence of such notification it will be assumed that no such conditions exist.

B. To assure proper operation, site conditions should be controlled. The walk-in product should be in a well-ventilated location. Indoor ambient conditions should be controlled, relative humidity between 30%-60% and maintaining a dew point of 50 deg F (or less).

1.10 WARRANTY

A. Manufacturer shall provide a written warranty to the Owner stating the product is free from defects or workmanship under normal use and service. Warranty shall become effective following the Date of Substantial Completion.

B. Furnish 15 year panel warranty for walk-in cooler insulated panels.

C. Furnish 18 months parts and labor warranty for refrigeration system.

D. Furnish additional 5 year compressor warranty.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Walk-in cooler to be constructed of pre-fabricated, precision formed, modular panels designed for quick field assembly.

2.2 MANUFACTURER

A. Acceptable manufacturers or equal:

Nor-Lake Incorporated, Hudson, Wi.; www.norlake.com Cool Manufacturing Inc, Brisbane, Ca.; www.coolsolutions.us Cold Storage Manufacturing; Union City, Ca.; www.coldstoragemfg.com Cooper Hawkins, San Francisco, Ca.; www.cooperhawkins.com East Bay Restaurant Supply; Oakland, Ca.; www.eastbayrestaurantsupply.com Thor Mechanical, San Francisco, Ca.; www.thormechanical.com Substitutions: Section 01 25 13 – Product Options and Substitutions.

B. Basis-of-Design Manufacturer and Model: FineLine™ Walk-Ins, by Norlake.

Page 95: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 11 41 23 Addendum No. 2 Redwood City School District Walk-in Cooler - 4

1. 8’-0” wide x 7’-6” long x 7’-4” high (nominal), supplied without a floor.

2.3 GENERAL

A. Walk-in coolers and freezers to consist of precision constructed modular 4” or 5” thick rigid polyurethane foamed-in-place interchangeable panels. Panels are designed for easy installation, expansion and relocation.

B. Panels shall be prefabricated modular construction consisting of 100% foamed-in-place polyurethane insulation, bonded by an adhesive to the interior and the exterior metal pan skins and heat cured for life long stability.

C. Each wall panel skin is to be formed using a double 90° bend on each edge to add strength and rigidity. Panels are to be in 6 inch increments, with a minimum width of 12 inches.

D. All panels are to bear the UL and NSF label. The panels shall incorporate cam lock type fasteners with reverse wing structural support as joining devices for the adjacent tongue and groove panels. Each device is to consist of a cam action locking arm and a steel rod in adjoining panel so that by rotating the locking arm, the hook engages over the rod and the cam action draws the panel together. The resulting panel joints shall be sealed by a foamed-in-place, continuous one piece gasket.

E. Panel joints are to be precisely formed male and female tongue and groove shapes fabricated to force the male edge to contact the female edge, providing additional seal. The panel joint shall have a gasket which provides a positive seal that meets NSF standards. Gasket shall be “locked” to the skins and run in a continuous piece, completely around the panel with only one break to provide the optimal seal.

2.4 INSULATION

A. Insulation shall be a full 4 inches or 5 inches thick, UL Class 1 rigid foamed-in-place HFO polyurethane with a minimum 2.15 lbs/cubic foot density. Foam polyurethane shall be injected into the panels by means of a high output, high impingement mixer.

B. The R-values for 4” HFO panels are: 1. Cooler:

a. Walls/Ceilings R-value 25. b. Doors R-value 25.

2. Freezer: a. Walls/Ceilings R-value 32. b. Doors R-value 32 Floors R-value 28.

C. Insulation shall be 90% closed cell structure. Flame spread rating of the foam core according to ASTM E-84/UL 723 shall be 25 or less.

D. The use of an HFC as a blowing agent is specifically prohibited.

2.5 FLOOR STYLE

A. Less-floor, 4” wall walk-ins shall be supplied with a 4-3/8” high foam screed sealer. Screed shall be of similar construction to wall panels with matching finish.

Page 96: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 11 41 23 Addendum No. 2 Redwood City School District Walk-in Cooler - 5

B. Cove Molding: Shall be factory provided for complete interior of prefabricated room. Cove molding to be 0.040” embossed aluminum, and installed with water-resistant contact adhesive. Comply with NSF requirements for sanitary floor practices.

2.6 CEILING PANELS

A. Ceiling panels shall be a full 4 inches or 5 inches thick with one piece foamed-in-place edge caps. Edge caps include metal formed adhesion edges which result in the edge caps being a foamed integrated member of the ceiling panels. Glued-in-place edge caps are not acceptable.

B. Metal face skins are to incorporate seams using a double 90° bend at a maximum width of two feet for additional strength. The joint between the ceiling and wall shall form a 45° angle to allow for easy cleaning.

2.7 FINISHES

A. The interior and exterior walls and interior ceiling shall be supplied with 26 gauge corrosion resistant stucco-embossed coated steel.

2.8 DOOR CONSTRUCTION

A. Entrance door shall be in fitting, flush design. The door section shall provide a full 4 inches or 5 inches of polyurethane HFO insulation, construction and finish shall be the same as the adjoining wall panels.

B. The door shall be 4 inches thick, constructed to incorporate heavy duty, molded ABS breaker strip, which is permanently foamed-in-place. Bottom of door shall seal with double sweep gaskets, uniquely designed to provide complete seal between door, threshold, and door jamb.

C. Door jamb to be a fully coved, extruded, welded, structural anodized aluminum, rigid frame design for easy cleaning and maintenance.

D. Threshold plate provided shall be constructed of fiberglass reinforced plastic (FRP) or extruded aluminum for bearing strength. All doors shall have an anti-sweat heater wire around the entire perimeter of the door opening and under threshold.

E. The heater wire (standard in both coolers and freezers) shall provide enough heat to prevent condensation. All conduit for the inner-wiring of the door panel shall be totally concealed in the polyurethane foam panel, exposed conduit is not acceptable.

F. Door section to be field-wired to surface mounted junction box on the interior door panel. The door size, location and swing to be as indicated on Drawings.

G. Door hardware shall be highly-polished chromium-plated steel. Hardware shall include a spring actuated door closer, field adjustable cam lift hinges, one spring-hinge and deadbolt locking handle with independent key/padlock feature and inside safety release. All hardware shall be attached to extra large 1/2-inch thick, nonconducting synthetic tapping plates.

H. Digital thermometer calibrated to indicate interior walk-in temperature shall be provided with each entrance door.

I. High-output low-profile LED light with approximately twice the light output of a standard 60W incandescent or 13-15W CFL, guaranteed for 5 years or 35,000 hours. Light is

Page 97: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 11 41 23 Addendum No. 2 Redwood City School District Walk-in Cooler - 6

positioned above the door to prevent interference with shelving or product. Locate light switch with pilot light adjacent to door, on exterior handle side of door section, with all inner wiring in conduit concealed inside the door section and terminated at a surface mounted junction box on the interior door frame. Fixture shall operate on 120 VAC.

2.9 SHELVING SYSTEM

A. Provide manufacturer’s U-shaped shelving kit specifically designed for each walk-in configuration. These kits are shipped with the walk-in so that all necessary components are at your location promptly when you need them. The shelving sets are coded to correspond to the walk-in configuration ordered; provide in four tier configuration.

B. Shelving Finish: Nor-Lake Standard Chrome Kote™ Shelving: Plated quality wire and steel. Surface nickel chrome plated.

C. Shelving posts are engineered for maximum strength. Shelves are adjustable on 1" centers.

All shelves are NSF. listed. Special clips are utilized to gain the maximum square footage of storage space for each model. 14”, 18” and 24” wide shelves are used as required for maximum storage capacity in each set. This wire shelving is ideal for storage of all refrigerated or frozen products, as well as non-refrigerated storage.

D. Shelves:

1. Shelves to have #9 (0.148") ga. crosswires spaced 3/4" on centers with crossbraces 1/4" (0.192") minimum of 4-3/4" on center.

2. Shelf Frames: Channel to be 9/16" x 1" x 0.075" thick. 3. Shelf Collars: A round tapered 1-5/16" high steel collar to be welded at each corner.

E. Posts: Posts to be 0.062" thick 1" O.D. round tubing notched every 1" on each corner of the post.

F. Post Levelers: Installed on the bottom of each post is nylon housing for a steel leveler 3/8"-

16 x 1-3/4".

2.10 REMOTE REFRIGERATION SYSTEM

A. Split-Pak™ Pre-Assembled Remote Systems: Pre-assembled systems shall be furnished for remote condensing unit installations using the basic components described under the general section.

1. Condensing unit shall be factory mounted to a galvanized steel rack. 2. Rack is to include a control box enclosing factory pre-wired pressure controls and

contactor for three phase units. 3. Optional condensing unit housing and low ambient controls for the specific

application shall be factory installed. 4. Liquid line filter drier, sight glass, expansion valve and temperature control shall be

factory installed. 5. A time clock housed in an enclosure shall be provided loose, for field installation. 6. The systems shall be designed to require no evaporator/ condensing unit inter-wiring. 7. Field provided two point electrical connection and refrigerant piping shall be required.

B. General:

1. Ambient temperatures around the system should be less than +90°F and 50% RH.

Page 98: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 11 41 23 Addendum No. 2 Redwood City School District Walk-in Cooler - 7

2. Condensing unit shall use air-cooled scroll compressor, designed for industrial use, to meet DOE requirements.

3. Condensing units shall be factory assembled and UL listed. 4. Systems shall be supplied with R449A refrigerant 5. Evaporators shall be forced air type designed for ceiling installation. Evaporators

shall be equipped with gravity-feed condensate line with pea trap for discharge through exterior building wall.

6. Air discharge shall be parallel to the walk-in ceiling. 7. Fan motors, guards, multi-fin and tube-type coil shall be housed in heavy gauge

aluminum housing. 8. Unit shall have drain pan with suitable drain pipe connection. 9. Freezer evaporators shall have an automatic electric defrost system including

heaters, time clock, defrost end and fan delay control and heated drain pan. 10. Defrost shall be time initiated and temperature terminated with built-in failsafe control. 11. All cooler systems are equipped with an "off cycle" timer to maximize heat transfer

and maintain optimum energy efficiency. 12. Evaporators shall be U.L. listed and be available in Lo-Profile design.

2.11 ACCESSORIES

A. Provide manufacturer’s standard seismic hardware package (Tap-con Anchors, etc.) and installation accessories as needed, based on walk-in cooler dimensions.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine areas, with Installer present, for compliance with requirements for installation tolerances, location of framing and reinforcements, and other conditions affecting performance of the Work.

B. Take field measurements; report variance between plan and field dimensions.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Field Measurements: Prior to fabricating, ordering, or delivering equipment verify essential measurements at the Work Site. Verify mechanical and electrical conditions having bearing on the work, as well as pertinent existing equipment and architectural conditions. Make every effort necessary to clarify conditions not accessible to visual examination.

3.3 INSTALLATION

A. Standards: Comply with NSF standards in methods of installing, mounting, and securing equipment.

B. Installation:

1. Utility penetrations: Provide penetrations required at panels to accommodate electrical and refrigeration lines and sufficient quantities of 5” diameter matching escutcheon plates to dress off utility penetrations, including drain lines. Escutcheon blanks’ hole cutting and sealing around penetrations to be performed by other trades.

Page 99: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 11 41 23 Addendum No. 2 Redwood City School District Walk-in Cooler - 8

2. Erection, installation, start-up, and testing shall be done by a California State Licensed Refrigeration Contractor, authorized by the manufacturer of the Walk-In Cooler for the work.

3. Seismic Anchoring: Provide and install seismic fasteners and anchors per manufacturer’s recommendation and local governing seismic codes.

3.4 FIELD QUALITY CONTROL

A. After installation, test mechanical and electrical equipment including, but not limited to refrigeration systems, and in general valves, regulators, tubing, wiring, piping, connections, gauges, safety devices, sensors, and other devices required for the proper operation of the equipment, for operating efficiency and conformance to requirements specified. Test and re-test until equipment is properly operating.

B. Manufacturer's Representative Field Service: Representative of the Walk-In Cooler manufacturer shall make inspections during installation and upon completion of installation to ascertain that the entire system has been installed according to manufacturer's specifications and approved details.

2.5 CLEANING AND PROTECTING

A. Perform fitting, joining, leveling, fastening, scribing, sealing, and adjusting of fixed equipment. Do cutting, drilling, and fitting in equipment necessary to accommodate work of mechanical and electrical trades.

B. Cleaning: Remove from equipment stains, paint spots, protective wrappings, coatings, tapes, grease, oil, plaster, dust, polishing compounds, rust, and other foreign substances.

C. Touch-up: After installation, damaged, stained, or otherwise disfigured portions of the work shall be touched up, refinished, or replaced to the satisfaction of the Owner’s representative.

END OF SECTION 03/20/20

Page 100: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 10 21 13.19 Addendum No. 3 Redwood City School District Solid-Color Reinforced Composite Toilet Compartments - 1

SECTION 10 21 13.19

SOLID-COLOR REINFORCED COMPOSITE TOILET COMPARTMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Floor-anchored, overhead-braced, solid color reinforced composite substrate toilet compartments configured as toilet enclosures and urinal screens.

B. Related Documents: The Conditions of the Contract and Division 1 apply to this section as fully as if repeated herein.

C. Related Requirements:

1. Section 09 22 16 - Non-Structural Metal Framing: Coordination with blocking in walls to secure panels, wall posts, and stiles.

2. Section 09 29 00 - Gypsum Board, coordination with blocking. 3. Section 09 30 13 - Ceramic Tiling, coordination with layout and installation. 4. Section 10 28 13 - Toilet Accessories.

1.2 SEQUENCING

A. Ensure that products of this section are supplied to affected trades in time to prevent interruption of construction progress.

1.3 ACTION SUBMITTALS

A. Product Data: Submit manufacturer's technical data for materials, fabrication, finishes, fastenings, hardware, and installation details.

B. Shop Drawings: Submit shop drawings indicating elevations of partitions, thickness of SCRC material, fastenings, proposed method of anchoring, size and spacing of anchors, details of construction, hardware, fittings, mountings and other related items and installation details.

C. Selection Samples: For each finish product specified, two complete sets of color chips representing manufacturer's full range of available colors and patterns.

D. Verification Samples: For each finish product specified, two samples, minimum size 6 inches square representing actual product, color, and patterns.

D. Product Schedule: For toilet compartments, prepared by or under the supervision of supplier, detailing location and selected colors for toilet compartment material.

E. Submittal procedures and quantities are specified in Section 01 33 00.

1.4 CLOSEOUT SUBMITTALS

A. Maintenance Data: For toilet compartments to include in maintenance manuals.

Page 101: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 10 21 13.19 Addendum No. 3 Redwood City School District Solid-Color Reinforced Composite Toilet Compartments - 2

1.5 QUALITY ASSURANCE

A. Manufacturer Qualifications: Minimum 10 years experience manufacturing similar products.

B. Installer Qualifications: Minimum 2 years experience installing similar products.

C. Single Source Requirements: To the greatest extent possible provide products from a single manufacturer.

D. Coordination: Furnish inserts and anchorages that must be built into other construction for installation of toilet compartments.

E. Regulatory Requirements: Provide toilet compartments meeting the requirements for the physically disabled of the 2016 California Building Code (CBC) Title 24 Part 2, and 2010 ADA Standards for Accessible Design.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Deliver and store materials in the manufacturer's original protective packaging except that should packaging become wet, remove it immediately to avoid wet storage stains.

B. Store materials in an enclosed shelter providing protection from damage and exposure to the elements.

1.7 PROJECT CONDITIONS

A. Field Measurements: Verify actual locations of toilet fixtures, walls, columns, ceilings, and other construction contiguous with toilet compartments by field measurements before fabrication.

B. Maintain environmental conditions (temperature, humidity, and ventilation) within limits recommended by manufacturer for optimum results. Do not install products under environmental conditions outside manufacturer's recommended limits.

1.8 WARRANTY

A. Submit manufacturer’s extended warranty under the provisions of Section 01 78 36.

B. Submit Manufacturer's standard 25 year limited warranty for panels, doors, and stiles against breakage, corrosion, delamination, and defects in factory workmanship.

C. Submit Manufacturer's standard 1 year guarantee against defects in material and workmanship for stainless steel door hardware and mounting brackets

PART 2 - PRODUCTS

2.1 MANUFACTURER

A. Basis-of-Design Products: Based on the quality and performance requirements of the project, specifications are based solely on the products of Bobrick Washroom Equipment, Inc.; www.bobrick.com; as represented by R.E. Edwards & Assoc 925-829-2942. Location of manufacturing shall be the United States.

Page 102: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 10 21 13.19 Addendum No. 3 Redwood City School District Solid-Color Reinforced Composite Toilet Compartments - 3

B. Substitutions: Section 01 25 13 – Product Options and Substitutions.

2.2 SOLID COLOR REINFORCED COMPOSITE (SCRC) SUBSTRATE (SierraSeries)

A. Solid Color Reinforced Composite (SCRC) Toilet Partitions: Bobrick 1092G.67P

SierraSeries.

1. Design Type: a. Standard Height.

1) Door/Panel Height: 58 inches. 2) Floor Clearance: 12 inches.

2. Privacy Style Partitions: No sightlines with gap-free interlocking doors and stiles routed 0.300 inches from the edge to allow for 0.175 inch overlap to prevent line-of-sight into the toilet compartment. Privacy strips fastened or adhered onto the partition material are not acceptable.

3. Mounting: a. Floor-Mounted, overhead-braced with satin finish, extruded anodized

aluminum headrails, 0.065 inch thick with anti-grip profile. 1) Stile Maximum Height: 83 inches.

B. Solid Color Reinforced Composite (SCRC) Urinal Screens: Bobrick SierraSeries. 1. Basis-of-Design: Bobrick 1095 SierraSeries Wall-Hung Urinal Screens.

a. Brackets: 11 gauge, double thickness. 2. Mounting Configuration: Wall hung.

a. Screen Height: 48 inches with 12 inches of floor clearance.

C. Materials: Solid color reinforced composite (SCRC) material for stiles, panels, doors, and screens with Bobrick GraffitiOff® coating, thermoset and integrally fused into homogenous piece; high density polyethylene (HDPE), high density polypropylene not acceptable.

1. Composition: Dyes, organic fibrous material, and polycarbonate/phenolic resins. 2. Surface Treatment: Non-ghosting, graffiti resistant surface integrally bonded to core

through a series of manufacturing steps requiring thermal and mechanical pressure. 3. Edges: Same color as the surface. 4. Provide material not less than 3/4-inch thick, with edges eased and free from saw

marks. a. Color(s): As selected by Architect from manufacturer’s standard SierraSeries

range. 5. Acceptable SCRC Products: Basis-of-Design manufacturer, or one of the following:

a. Ultimate Corian System by Shower Shapes. b. WilsonArt Gibraltar Material. c. WilsonArt EarthStone Material.

D. Performance Requirements:

1. Graffiti Resistance (ASTM D 6578): Passed cleanability test; 5 staining agents. 2. Scratch Resistance (ASTM D 2197): Maximum load value exceeds 10 kilograms. 3. Impact Resistance (ASTM D 2794): Maximum impact force exceeds 30 inch-pounds. 4. Smoke Developed Index (ASTM E 84): Less than 450. 5. Flame Spread Index (ASTM E 84): Less than 75. 6. National Fire Protection Association/International Building Code Interior Wall and

Ceiling Finish: Class B. 7. Uniform Building Code: Class II.

Page 103: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 10 21 13.19 Addendum No. 3 Redwood City School District Solid-Color Reinforced Composite Toilet Compartments - 4

E. Finished Thickness:

1. Stiles and Doors: 3/4 inch. 2. Panels and Screens: 1/2 inch.

F. Stiles: Floor-anchored stiles furnished with expansion shields and threaded rods.

1. Leveling Devices: 7 gauge, 3/16 inches thick, corrosion-resistant, chromate-treated,

double zinc-plated steel angle leveling bar bolted to stile; furnished with 3/8 inch diameter threaded rods, hex nuts, lock washers, flat washers, spacer sleeves, expansion anchors, and shoe retainers.

2. Stile Shoes: One-piece, 22 gauge, 18-8 S, Type 304 stainless steel, 4 inch height; tops with 90 degree return to stile. One-piece shoe capable of adapting to 3/4 inch or 1 inch stile thickness and capable of being fastened (by clip) to stiles starting at wall line.

G. Wall Posts: Pre-drilled for door hardware, 18-8 S, Type 304, 16 gauge stainless steel with

satin finish; 1 inch x 1-1/2 inches x 58 inches high. H. Anchors: Expansion shields and threaded rods at floor connections as applicable. I. Hardware: Stainless steel. Chrome-plated “Zamak”, aluminum, extruded plastic hardware

not acceptable.

1. Compliance: Operating force of less than 5 lb. 2. Emergency Access: Hinges, latch allow door to be lifted over keeper from outside

compartment on in-swing doors. 3. Materials: 18-8 S, Type 304, heavy-gauge stainless steel with satin finish. 4. Doorstops: Prevents in-swinging doors from swinging out beyond stile; on out-swing

doors, doorstop prevents door from swinging in beyond stile. 5. Fastening: Hardware secured to door and stile by through-bolted, theft-resistant, pin-

in-head Torx stainless steel machine screws into factory-installed, threaded brass inserts. Fasteners secured directly into core not acceptable. a. Threaded Brass Inserts: Factory-installed; withstand direct pull force

exceeding 1500 lb per insert. 6. Coat Hooks: Combination hook and rubber-tipped bumper, sized to prevent door

from hitting mounted accessories, projecting no more than 1-1/8 inch from face of door. Mount hook at 48-inches above finish floor.

7. Hardware Type: Institutional Hardware (.67). 8. Door Latch: Track of door latch prevents inswing doors from swinging out beyond

stile; on outswing doors, door keeper prevents door from swinging in beyond stile; 16 gauge sliding door latch, 11 gauge keeper. Door latch slides on a shock-resistant nylon track.

9. Locking: Door locked from inside by sliding door latch into keeper. 10. Hinge Type:

a. Standard: 1) Balanced, with field-adjustable cam to permit door to be fully closed or

partially open when compartment is unoccupied. 11. Mounting Brackets: Full-Height.

a. Mounting Brackets: 18 gauge stainless steel and extend full height of panel. b. U-Channels: 18 gauge stainless steel; secure panels to stiles. c. Angle Brackets: Secure stiles-to-walls and panels to walls.

12. Door handles and latches have operable parts that are operable with one hand and do not require tight grasping, pinching, or twisting of the wrist; and comply with ADA Sections 404.2.7 and 309.4. The force required to activate the operable parts shall be 5 pounds maximum.

Page 104: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 10 21 13.19 Addendum No. 3 Redwood City School District Solid-Color Reinforced Composite Toilet Compartments - 5

13. Door pull handles (2) are provided for installation on both sides of the Wheelchair Accessible and Ambulatory Toilet Compartment door adjacent to the door latch, 34" minimum to 48" maximum above the floor, to comply with CBC 11B-604.8.1.2.

2.3 FABRICATION

A. Fabrication, General: Fabricate toilet compartment components to sizes indicated. Coordinate requirements and provide cutouts for through-partition toilet accessories where required for attachment of toilet accessories.

B. Floor-Anchored Units: Provide manufacturer's standard corrosion-resistant anchoring assemblies with leveling adjustment nuts at pilasters for structural connection to floor. Provide shoes at pilasters to conceal anchorage.

C. Door Size and Swings: Unless otherwise indicated, provide 24-inch wide in-swinging doors for standard toilet compartments and 36-inch wide out-swinging doors with a minimum 32-inch wide clear opening for compartments designated as accessible.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine areas and conditions, with Installer present, for compliance with requirements for fastening, support, alignment, operating clearances, and other conditions affecting performance of the Work.

1. Confirm location and adequacy of blocking and supports required for installation.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Prepare substrates including but not limited to blocking and supports in walls and ceilings at

points of attachment using methods recommended by the manufacturer for achieving the best result for the substrates under the project conditions. 1. Inspect areas scheduled to receive compartments for correct dimensions, plumbness

of walls, and soundness of surfaces that would affect installation of mounting brackets.

2. Verify spacing of plumbing fixtures to assure compatibility with installation of compartments.

B. If preparation is the responsibility of another installer, notify Architect in writing of deviations

from manufacturer’s recommended installation tolerances and conditions. C. Do not proceed with installation until substrates have been properly prepared with blocking

and supports in walls and ceilings at points of attachment and deviations from manufacturer’s recommended tolerances are corrected. Commencement of installation constitutes acceptance of conditions.

3.3 INSTALLATION

Page 105: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

Measure T - Phase 1

2017-03267 Taft Community School - New Buildings, Modernization and Sitework Section 10 21 13.19 Addendum No. 3 Redwood City School District Solid-Color Reinforced Composite Toilet Compartments - 6

A. General: Comply with manufacturer's written installation instructions. Install units rigid, straight, level, and plumb. Secure units in position with manufacturer's recommended anchoring devices.

1. Maximum Clearances:

a. Pilasters and Panels: 1/2 inch. b. Panels and Walls: 1 inch.

2. Full-Height (Continuous) Brackets: Secure panels to walls and to pilasters with full-height brackets.

a. Locate bracket fasteners so holes for wall anchors occur in tile joints. b. Align brackets at pilasters with brackets at walls. c. At light gage steel framed walls fasten brackets with toggle or molly bolts into

metal studs or backing plates fastened directly to the studs.

B. Overhead-Braced Units: Secure pilasters to floor and level, plumb, and tighten. Set pilasters with anchors penetrating not less than 1-3/4 inches into structural floor unless otherwise indicated in manufacturer's written instructions. Secure continuous head rail to each pilaster with no fewer than two fasteners. Hang doors to align tops of doors with tops of panels, and adjust so tops of doors are parallel with overhead brace when doors are in closed position.

C. Urinal Screens: Attach with anchoring devices to suit supporting structure. Set units level and plumb, rigid, and secured to resist lateral impact.

3.4 ADJUSTING AND CLEANING

A. Hardware Adjustment: After installation, carefully adjust hardware for proper operation. Except for accessible stalls, set hinges on in-swinging doors to hold open approximately 30 degrees from the closed position when unlatched. Set hinges on out-swinging doors to return to the fully closed position. Adjust doors so that bottoms of doors are level with the bottoms of the pilasters when the doors are in the closed position. Accessible stall doors shall be self-closing.

B. Touch-up, repair or replace damaged products.

C. Cleaning: Clean compartments and doors upon completion of work and leave free from imperfections.

END OF SECTION 03/11/20

Page 106: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

WFHB WF

WF

WF

WF

WF

WF

WF

WF

HBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHB

HBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHB

HBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHB

HBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHBHB

WF

WF

WF

WF

WF

WF

WF

DG NS

DG

DG

DG

DG

DG

DG

DG

DG

DG

DG

DG

NSNSNSNSNSNSNSNSNSNSNSNSNSNSNSNSNS

NSNSNSNSNSNSNSNSNSNSNSNSNSNSNSNS

WF

WF

CEO

CEO

CEO

CEO

CEO

CEO

ARO

ARO

AROCEO

CEO

CEO ARO

ARO

LNA LNALNA

LNA LNA LNA

LNA

LNAMC

GBP

CEO CEO

UPFUPF

UPF

UPF

UPF

UPF

UPF

GBP

GBP

GBP

GBP

GBP

GBP

LNA

LNA

LNA

LNA

LNA

LNALNA

MULCH BENEATH EXISTINGTREES, TYP.

MULCH BENEATH EXISTINGTREES, TYP.

EXISTINGBUILDING "B"

EXISTINGPLAY

APPARATUS

T

MSB

NEWBUILDING "D"

EXISTINGBUILDING "C"

EXISTINGBUILDING "E"

BUILDING "D"NEW

1

1

0

0" 12" 1" 2"

10' 20' 40'

2671 CROW CANYON RD. SAN RAMON, CA 94583T 925.736.8176 www.dgates.com

GATEA SOCI ATESS

LANDSCAPE ARCHITECTURE

LAND PLANNING URBAN DESIGN

S

DOCUMENTS

11/21/18 100% CONSTRUCTION

© 2018

PROJECT NUMBER:

SHEET TITLE:

SHEET NO:

11

/8

/2

01

9 1

:3

8:5

4 P

M

2017-03267-000

Taft Community

School - Measure T

Phase 1 - New

Buildings,

Modernization &

Site Work

RS

N://s

fc

-h

ar-rv

s0

1/K

12

/R

CS

D/2

01

7-0

32

67

_T

aftC

om

mS

ch

Ma

in

Pro

j/2

01

7-0

32

67

_A

rc

h_

HE

D.rv

t

750 Bradford St | Redwood City, CA |

94063 | 650.423.2200

Redwood City

School District

903 Tenth Ave | Redwood City, CA |

94063 |

417 Montgomery Street

Suite 400

San Francisco, California

94108 USA

(415) 981-2345

WWW.HED.DESIGN

Date Issued For

12/15/17 SCHEMATIC DESIGN

04/13/18 100% DESIGN

DEVELOPMENT

08/10/18 50% CONSTRUCTION

DOCUMENTS

11/21/18 100% CONSTRUCTION

DOCUMENTS

12/24/18 DSA SUBMISSION

11/20/19 DSA BACK CHECK

02/17/20 ADDENDUM 11

L3.1

IRRIGATION PLAN

1"=20'-0"

Page 107: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

D5.1 D5.1

D5 D5

DG

DG DF

DF

DE.7

DE.7DF.7

DF.7

3

A-483D

4

A-483D

ELEV

D-ELEV1

OPEN OFFICE

D-110

HALLWAY

D-113

MACHINE RM

D-109A

8' - 0" CLEAR

9'-7

" C

LE

AR

3' - 0" 8' - 0" CLEAR

K4A4

A4

A4

C4

C4

E-02

ASK21.2/

ADD-34

D5.1

D5

D4 D4

DF DE.7

1

A-302D

DF.7

3

A-483D

4

A-483D

ELEV

D-ELEV2

STEAM CLASSRM

D-206

6' -

6"

CLE

AR

3' -

1"

5' -

0"

CLE

AR

1' -

7"

1' -

5"

8' - 0" CLEAR

8' - 0" CLEAR 3' - 0"

9'-7"

CL

EA

R

CLE

AR

3'-0

" CLR

1'-3

"

ADDENDUM

Project#:DSA App#: 01-117949Date:

Elevator Layout RevisionASK 21.1/ ADD-3 1/4" = 1'-0"

Taft Community School - Measure T Phase 1 - New Buildings, Modernization & Site Work2017-03267-000

03/20/20

417 Montgomery Street (415) 981-2345Suite 400 WWW.HED.DESIGNSan Francisco, California94104 USA

1/4" = 1'-0"1

1ST FLOOR ENLARGED PLAN -ELEVATOR

1/4" = 1'-0"2

2ND FLOOR ENLARGED PLAN -ELEVATOR

3

3

3

3

LICENSED ARCHIT

ECT

STATE OF CALIF

ORN

IA

michael j. myers

ren. 3.31.21c-36095

Page 108: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

DE

DE DD

DD

D5.1 D5.1

D5 D5

D4 D4

DF

DF

DE.7

DE.7

3

A-502D

DE.3

DE.3

DF.7

DF.7

OFFICE

D-116

OPEN OFFICE

D-110

9' - 7 1/2" ACPELEV

D-ELEV1

8' - 6" GYP-1

EQ

EQ

3

A-502D

9' - 6" GYP-1

7' - 0" GYP-1

1'-6"

12

"

2.40

A-572

Sim2.40

A-572

Sim

1'-6"

D5.1 D5.1

D5 D5

DF

DF

DE.7

DE.7DF.7

DF.7

89 SF

ELEV

D-ELEV2

10' - 0"

1HR RATING

1'-0

"

1'-6" 1'-6"

OPENTO

BEYOND7

'-0

"

10232 33

24

10232 33

24

10232 33

24

2'-10

"

PADDED WALL PANELING (4' WIDE PANELS)

DE

DE

D3 D3

D2.5 D2.5

DE.3

DE.3

ASK21.2/

ADD-35

10234 36

24

10234 36

24

10234 36

24

33.5 33.5 33.5

8'-6"

1

ASK14 / ADD-1

ADDENDUM

Project#:DSA App#: 01-117949Date:

Elevator Layout RevisionASK 21.2/ ADD-3As indicated

Taft Community School - Measure T Phase 1 - New Buildings, Modernization & Site Work2017-03267-000

03/20/20

417 Montgomery Street (415) 981-2345Suite 400 WWW.HED.DESIGNSan Francisco, California94104 USA

1/8" = 1'-0"1

SECTOR D2 LEVEL 1 RCP 1/8" = 1'-0"

2SECTOR D2 LEVEL 2 RCP

1/4" = 1'-0"4

ELEVATION - CABINETRY

3

3

3

3

3

1/4" = 1'-0"3

1ST FLR ENLARGED PLAN - MAILBOX

3

1/4" = 1'-0"5

ELEVATION - MAILBOX

3

LICENSED ARCHIT

ECT

STATE OF CALIF

ORN

IA

michael j. myers

ren. 3.31.21c-36095

Page 109: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–

H1 H2

HB

WALK-IN REFR

H-115

8'-7

" V

IF

8'-4" VIF

PANTRY

H-116

7.4

7.5

7.6

7.4

L

7.12

7.14

7.29

7.3

7.26

H1 H2

HB

HC

7.16

7.7

7.10

7.9

7.22

10'-0" MIN. 7.23 12

A-531

ADDENDUM

Project#:DSA App#: 01-117949Date:

Power Supply for Walk-InASK 21.3/ ADD-3 1/4" = 1'-0"

Taft Community School - Measure T Phase 1 - New Buildings, Modernization & Site Work2017-03267-000

03/20/20

417 Montgomery Street (415) 981-2345Suite 400 WWW.HED.DESIGNSan Francisco, California94104 USA

1/4" = 1'-0"1

ENLARGED PLAN - WALK-INREFRIGERATOR

1/4" = 1'-0"2

ENLARGED ROOF PLAN - BUILDING HADD 3

PROVIDE NEMA 6-20R , 250V , 2P SINGLE RECEPTACLE IN NEMA 3R ENCLOSURE AND INSTALL NEXT TO CONDENSING UNIT ON THE ROOF. HOMERUN RECEPTACLE TO EXISTING ELECTRICAL PANEL LOCATED IN THE ELECTRICAL ROOM OF MULTI PURPOSE BUILDING, WIRE SIZE SHALL BE 2#12 &1#12GROUND IN 3/4”C.IN ADDITION, PROVIDE 20A/2P,250V CIRCUIT BREAKER IN THE EXISTING PANEL FOR HOMERUN WIRES TO CONNECT.

PROVIDE ADDITIONAL RECEPTACLE TO POWER WALK-IN UNIT MISC EQUIPMENT, AS REQUIRED. CONFIRM REQUIREMENTS WITH MANUFACTURER. HOMERUN RECEPTACLE TO EXISTING ELECTRICAL PANEL LOCATED IN THE ELECTRICAL ROOM OF MULTI PURPOSE BUILDING.

3

3

3

LICENSED ARCHIT

ECT

STATE OF CALIF

ORN

IA

michael j. myers

ren. 3.31.21c-36095

Page 110: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–
Page 111: REDWOOD CITY SCHOOL DISTRICT michael j. myers TAFT … · 2020-03-23 · 21 13.19 – Solid Color Reinforced Composite Toilet Compartments. CHANGES TO DRAWINGS: ADD-3.08 Drawing A-401H–