69
STAN VITTON & THE FALL 2007 REDRIDGE DAM SENIOR DESIGN MICHIGAN TECHNOLOGICAL UNIVERSITY Analysis of the Redridge Dam

Redridge Dam Presentation

Embed Size (px)

Citation preview

Page 1: Redridge Dam Presentation

STAN VITTON & THE FALL 2007REDRIDGE DAM SENIOR DESIGN

MICHIGAN TECHNOLOGICAL UNIVERSITY

Analysis of the Redridge Dam

Page 2: Redridge Dam Presentation

Special Thanks

Stanton Township BoardMr. Leonard H. Lamb Jr., P.E., Motor Castings CompanyAPL - Metallurgy & Environmental Consulting LabsMichigan Tech FacilitiesMr. Louie Garnell - WeldingDr. Nels Christopherson - AccessMs. Jen Heglund – Hydrology AnalysisDr. Terry Reynolds Social Sciences Dept. MTURedridge Study Group

Page 3: Redridge Dam Presentation

Redridge Dam Presentation Outline

Study ObjectivesBackgroundTrestle Access Barricade Analysis

Stream Flow Analysis Structural Analysis

ConclusionsRecommendationsQuestions?

Page 4: Redridge Dam Presentation

Objectives

Create a timeline of events which occurred at the siteDetermine the original location of the Salmon-Trout

River and its hydrologic flow levelsEvaluate structural stability of the damsProvide technical advise for use by the Stanton Township

Study GroupHelp provide information to Stanton Township to help

manage risks to township and its residentsProvide recommendations for future work

Page 5: Redridge Dam Presentation

Location

Page 6: Redridge Dam Presentation

Location

Lake Superior Elevation 600 feet

Page 7: Redridge Dam Presentation

The Redridge Dam and Beacon Hill/Freda Road

Page 8: Redridge Dam Presentation

The Redridge Dam

Timber Crib Dam

Steel Dam

Current Road Crossing

Old Road Crossing

Page 9: Redridge Dam Presentation

Baltic Stamp Mill

Page 10: Redridge Dam Presentation

Geology

Page 11: Redridge Dam Presentation

Geology – Freda Sandstone

Freda Sandstone Precambrian – 1 billion Reddish brown sandstone

and siltstones, well bedded and consolidated

2,500 feet thick

Page 12: Redridge Dam Presentation

Geology – Freda Sandstone

Page 13: Redridge Dam Presentation

Geology – Freda Sandstone

Page 14: Redridge Dam Presentation

Keweenaw Currents

Page 15: Redridge Dam Presentation

Lake Superior Current

Page 16: Redridge Dam Presentation

Stamp Sand Migration

Page 17: Redridge Dam Presentation

History – Timber Crib Dam

Timber Crib Dam Constructed in 1894 Additional construction 1899 Submerged in 1902 to 1921 1921 till dam lowered?

Page 18: Redridge Dam Presentation

History - Steel Dam

Steel Dam Construction (1900-1901) Completed Nov 1, 1901 Started filling Nov. 15, 1901 Completely filled Jan. 1, 1902 Over topped in 1927, 1941 and

1979

Page 19: Redridge Dam Presentation

History – Steel Dam

Page 20: Redridge Dam Presentation

Spillways

CompletedUnder Construction

Page 21: Redridge Dam Presentation

Location

Emergency Spillway

Page 22: Redridge Dam Presentation

Timeline

1884 Stamp Mill & Dam on the Salmon Trout River completed

May 1899 Construction of Steel Dam Started Nov 1 Construction Completed Nov. 15 Gates Closed Jan. 1 1900 Steel Dam Filled

1912 Atlantic Mill Closed1921 Baltic Mill Closed1927 Dam Overtopped in Spring Runoff1941 Dam Overtopped due to Beaver Dam Break

Page 23: Redridge Dam Presentation

Timeline

Nov. 20, 1953 Dam Drained due to Constrcution of a Tunnel Under Road to Freda

1979 Dam Overtopped1979 Copper Range Cut Four Holes in Steel Dam1986 ASCE Designated the Redridge Dam a Historic Civil

Engineering Landmark1992 Stanton Township Took Ownership of the Dam2004 The Top 12 feet of the Timber Wood Dam Removed

Page 24: Redridge Dam Presentation

The Trestle

Page 25: Redridge Dam Presentation

Trestle Access Barricade

Both barricades that prevented access to trestle needed repair

Barricade design repair and reconstruction

4” Gaps or smaller (Chap. 10 International Building Code 2006)

No horizontal bracing to deter climbing

Used steel angle iron and rebar: 130 feet of angle iron 290 feet of rebar

Barbwire placed around ends & top to discourage climbing around barricade

Page 26: Redridge Dam Presentation

Trestle Access Barricade

Page 27: Redridge Dam Presentation

Stream Analysis

10/25/2007

Page 28: Redridge Dam Presentation

Bathymetric Map

Page 29: Redridge Dam Presentation

River Channel Location

Page 30: Redridge Dam Presentation

Salmon Trout River Location Under Steel Dam

Page 31: Redridge Dam Presentation

Salmon Trout River Location Under Steel Dam

Salmon Trout River noted at bottom of picture

Pipes located to the west side of dam

Page 32: Redridge Dam Presentation

Analysis – Stream Flow

Hydrology Base flow - 50cubic feet per

second Area 42.8 mi2

CN – 58 Lag time 26.7 hours Elevation-storage-outflow

relationship Spring Snow Melt

Salmon-Trout River Watershed

Page 33: Redridge Dam Presentation

Analysis – Stream Flow

Design Storm Event 100 year storm 12, 24, 48, 96 hours Reservoir elev. 652 ft+/-at a

max runoff discharge of 1246 cfs

Page 34: Redridge Dam Presentation

Current Spillways

Base FlowSpring Flow

Page 35: Redridge Dam Presentation

Analysis – Stream Flow

Discharge Holes cut at elev 649-652 3 Models Q637 = 43 cfs Q692 =450 cfs Q653 = 1700 cfs (with holes) Q692 =6400 cfs (with holes)

Drainage Time (to elev 650) Elev 664 – 6.6 hours

12’ +/- of Snowmelt Runoff

692

652

637

Page 36: Redridge Dam Presentation

Structural Stability

Timber Crib Dam

Steel Dam – Gravity Dam

Material Life

Steel

Concrete

Timber

Page 37: Redridge Dam Presentation

Analysis – Steel

Page 38: Redridge Dam Presentation

Analysis – Steel

Page 39: Redridge Dam Presentation

Analysis – Steel

Steel Analysis Chemical Analysis:

The sample is approximately 1006 or 1010 plain carbon structural steel.

Tensile Test: Tensile Strength = 71,700 psi Yield Strength = 54,500 psi % Elongation = 22%

Birnell Hardness (10 mm ball @ 3000kg): 126 BHN

The Electron Energy Dispersive X-Ray Spectrometry (EDS) indicated a non-metallic film or coating on the surface.

Microstructural analysis: Material appears to be ferritic / pearlitic

steel

Page 40: Redridge Dam Presentation

Analysis – Structural

Slag stringer

Page 41: Redridge Dam Presentation

Analysis – Steel Corrosion

Page 42: Redridge Dam Presentation

Analysis – Steel Corrosion Acceleration

Page 43: Redridge Dam Presentation

Analysis – Steel Corrosion Acceleration

Page 44: Redridge Dam Presentation

Analysis – Concrete

Concrete Deterioration Caused by water flowing

over foundation through holes cut in steel dam

Estimate of Deterioration Rate Approximately 43 yd3

currently deteriorated Rate is 1.6 yd3 per year

100 year estimation is 202 yd3 of deteriorate

Page 45: Redridge Dam Presentation

Analysis – Concrete

Page 46: Redridge Dam Presentation

Concrete Analysis

Main weight (gravity dam) of the Redridge Dam comes from the concrete

There are two types of concrete; a capping concrete and a primary base concrete

Page 47: Redridge Dam Presentation

Analysis – Concrete

Capping Concrete Approx. 4 – 5 in thick Encases the entire

foundation of Dam Protects the primary

concrete Low permeability, very

dense

Page 48: Redridge Dam Presentation

Analysis – Concrete

Primary Concrete Approx. 12 - 15% voids Design - 145 pcf - pounds/foot3

Test results 1901 165 pcf – Measured on site 1800 psi – 26 Day

Actual – 134 pcf ASTM (C -642) Large Aggregates

Mine Rock Small amounts of Copper Large Voids

Page 49: Redridge Dam Presentation

Analysis – Steel Dam Stability

Stability of Steel Dam Gravity Dam - weight of

structure plus downward component of water resist sliding

Factor of Safety (FS) when fully loaded with water at 692 feet Currently FS ~1.40 for 134

pcf concrete FS ~1.35 after 100 yrs of

concrete deterioration

Page 50: Redridge Dam Presentation

Steel Dam Stability

Factor of Safety current condition significantly higher

Steel corrosion of support members as well as concrete pedestals is a concern if the dam becomes fully loaded

However, we believe that the current loading on the steel support member is very low and is not significant to the stability of the dam

Rehabilitation of both the steel and the concrete is possible

Page 51: Redridge Dam Presentation

Timber Crib Dam – Structural Stability

Page 52: Redridge Dam Presentation

Timber Crib Dam – Structural Stability

The Civil Engineers Pocket Book, John Trautwine. 1886

Page 53: Redridge Dam Presentation

Timber Crib Rockfill Dam

Page 54: Redridge Dam Presentation

Timber Crib Dam – Structural Stability

Page 55: Redridge Dam Presentation

Timber Crib Dam Elements

Page 56: Redridge Dam Presentation

Bathymetric Map

Page 57: Redridge Dam Presentation

1894 Condition

Page 58: Redridge Dam Presentation

Timber Crib - Date Unknown

Page 59: Redridge Dam Presentation

1899 Condition

Page 60: Redridge Dam Presentation

Timber Crib Dam Mid-1960’s

Page 61: Redridge Dam Presentation

2004 Condition

Page 62: Redridge Dam Presentation

Timber Crib Post 2004

Page 63: Redridge Dam Presentation

Steel Dam Conclusions

Our analysis indicates: More than likely the Salmon

Trout River is located in its original location

The stability of the steel dam against sliding even under fully loaded conditions is good

The current emergency spillway appears adequate for a 100 year event

Page 64: Redridge Dam Presentation

Steel Dam Conclusions

Our analysis indicates: The emergency spillway has

accelerated deterioration of the steel and concrete in the dam

Deterioration of concrete has not significantly affected the factor of safety of the steel dam against sliding

Deterioration of the steel and concrete pedestals is of some concern and should be address sometime in the future

Page 65: Redridge Dam Presentation

Timber Crib Dam Conclusions

Our analysis indicates: A rock fill dam supports the

timber cribbing and acts as an energy dissipating system

Timber planking was used as a water cutoff wall between rock fill and timber crib

As the wood planks deteriorate over time the timber crib dam will no longer be able to hold back water

Page 66: Redridge Dam Presentation

Timber Crib Dam Conclusions

Timber crib dam stability The removal of the upper 12

feet of the dam significantly improved its stability and appears to be very stable

Over time, however, the timber cribbing will deteriorate and the rock fill inside the cribbing will come to an equilibrium consistent with the rock’s angle of repose of the rock and water flow conditions

Page 67: Redridge Dam Presentation

Recommendations

Conduct a more detailed stability analysis of the steel and rock crib dams based on the following issues: Current condition Condition based on

Rate of steel corrosion Rate of concrete deterioration Deterioration of the timber

cribbing and planking

Page 68: Redridge Dam Presentation

Recommendations

Determine how long the dams can remain stable without intervention

Consider the following two options: Restoration of Salmon Trout

River by removing a section of the concrete base below the steel dam; thus, preserving the historical integrity of the dam

Alternate uses of the dams or portions of the dams in a originally designed condition

Page 69: Redridge Dam Presentation

Questions?