Construction Progress Update

Red Bluff CVPIA Presentation 2/17/2011

Embed Size (px)

Citation preview

Page 1: Red Bluff CVPIA Presentation 2/17/2011

Construction Progress Update

Page 2: Red Bluff CVPIA Presentation 2/17/2011

Project Overview The prime objective of the construction is to construct a Pumping Plant that

will initially provide 2,000 cfs flow to the Tehama Colusa Canal and the Corning Canal no later than May, 2012.

The Pumping Plant will be able to be expanded to a full 11 pumps and 2,500 cfs flow in the future.

Primary Components of the project include:

Pumping Plant with 11 bays,

9 Pumps and Motors

Excavation of the Forebay

A Fish Screen (1,118 ft in length)

Canals and a Siphon under nearby Red Bank Creek

Bridge over Red Bank Creek for service access

Closure of a Landfill

Page 3: Red Bluff CVPIA Presentation 2/17/2011

West Bay Builders West Bay Builders were awarded a $21 M contract on December 19th,

2009 to construct the Bridge, Canals and Siphon.

Their project also includes the clean closure of Parcel ‘A’ of the Pactiv Landfill.

Current Status:

Downstream Canal 40% complete

Bridge 25-30% complete

Siphon 50% complete

Landfill excavated and partially backfilled

Upstream canal not yet started

Slightly behind schedule

Page 4: Red Bluff CVPIA Presentation 2/17/2011

West Bay Builders continued Challenges:

Late arrival of Clean Closure Plan

Forced Contractor to reschedule their order of work

Construction of Siphon

Heavy rains in November/December flooded work area

Fish removal & disregard by onsite crews for permit requirements

End Summary

West Bay will likely complete the project on time or close enough to not effect water delivery in May, 2012

Page 5: Red Bluff CVPIA Presentation 2/17/2011

Before Construction Began – West Bay Construction Area

Page 6: Red Bluff CVPIA Presentation 2/17/2011

Construction Progress by West Bay in April 2010

Page 7: Red Bluff CVPIA Presentation 2/17/2011

Construction Progress by West Bay in May 2010

Page 8: Red Bluff CVPIA Presentation 2/17/2011

Construction Progress by West Bay in June 2010

Page 9: Red Bluff CVPIA Presentation 2/17/2011

Construction Progress by West Bay in July 2010

Page 10: Red Bluff CVPIA Presentation 2/17/2011

West Bay Canal & Siphon in August 2010

Page 11: Red Bluff CVPIA Presentation 2/17/2011

West Bay Landfill in August 2010

Page 12: Red Bluff CVPIA Presentation 2/17/2011

West Bay Siphon & Canal in September 2010

Page 13: Red Bluff CVPIA Presentation 2/17/2011

West Bay Landfill in September 2010

Page 14: Red Bluff CVPIA Presentation 2/17/2011

West Bay Pumping Concrete for Siphon, Oct 2010

Page 15: Red Bluff CVPIA Presentation 2/17/2011

West Bay Siphon & Canal October 2010

Page 16: Red Bluff CVPIA Presentation 2/17/2011

West Bay Landfill in October 2010

Page 17: Red Bluff CVPIA Presentation 2/17/2011

West Bay Landfill in November 2010

Page 18: Red Bluff CVPIA Presentation 2/17/2011

West Bay pouring concrete for Siphon, Nov 2010

Page 19: Red Bluff CVPIA Presentation 2/17/2011

West Bay Siphon flooded & Landfill, Dec 2010

Page 20: Red Bluff CVPIA Presentation 2/17/2011

West Bay Canal in December 2010

Page 21: Red Bluff CVPIA Presentation 2/17/2011

West Bay Bridge Piers in December 2010

Page 22: Red Bluff CVPIA Presentation 2/17/2011

West Bay Canal in January 2011

Page 23: Red Bluff CVPIA Presentation 2/17/2011

West Bay Siphon in January 2011

Page 24: Red Bluff CVPIA Presentation 2/17/2011

West Bay Landfill in January 2011

Page 25: Red Bluff CVPIA Presentation 2/17/2011

Moving Waters Industries Moving Waters Industries (MWI) were awarded a $6.9

M contract to supply the pumps and motors for this project on January 16th, 2010.

Primary Components of MWI Contract:

2 x 131.25 cfs pumps and associated motors

7 x 262.5 cfs pumps and associated motors

Installation assistance

Status:

Initial testing March 25th, is slightly behind schedule but not on critical path for water delivery in May, 2012.

Page 26: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Inc. Balfour-Beatty was awarded a $67 M contract on May 11th, 2010 to

construct the Fish Screen and Pumping Plant.

Their project also includes excavation of the Forebay, installation of the Switchyard, clean closure of Parcel ‘B’ of the Pactiv Landfill and now clean closure of the former GENIII property.

Current Status:

Cofferdam for Fish Screen completed, Fish Screen foundation in progress

Forebay excavation 50% complete

Pumping Plant foundation excavation 60%

Switchyard excavation 90%

Page 27: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Inc. continued Challenges:

Changed Conditions

RWQCB dictating a clean closure of the former GENIII property based on materials found there.

Minor weather delays

Fish removal

Between the West Bay contract and Balfour Beatty contract over 2700 fish were removed from the various structures.

End Summary

Balfour-Beatty is on track to deliver water in May, 2012.

Page 28: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Construction Area

Page 29: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty before Construction

Page 30: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Mobilizing in June 2011

Page 31: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Construction Site in July 2011

Page 32: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Stockpiles in August 2011

Page 33: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Switchyard & Pumping Plant, Aug 2011

Page 34: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty driving piles for Fish Screen Cofferdam, Sept 2010

Page 35: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Construction Site in September 2010

Page 36: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Upstream Cofferdam, Oct 2010

Page 37: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Pumping Plant & Switchyard Excavation, October 2010

Page 38: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty downstream Cofferdam and Pumping Plant, Forebay & Switchyard excavation, Nov 2010

Page 39: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Construction Site in November 2010

Page 40: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Construction Site in December 2010

Page 41: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Pumping Plant excavation, Dec 2010

Page 42: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Forebay & Cofferdam for Fish Screen in December 2010

Page 43: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Pumping Plant excavation, Jan 2011

Page 44: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty upstream end of Fish Screen, Jan 2011

Page 45: Red Bluff CVPIA Presentation 2/17/2011

Balfour-Beatty Fish Screen & Forebay, Jan 2011

Page 46: Red Bluff CVPIA Presentation 2/17/2011

Final Product