GOVERNMENT OF ANDHRA PRADESH
PANCHAYATRAJ ENGINEERING DEPARTMENT
Name of the Work : Re-Construction of A.S.R.stadium at El
Estimate Amount :-Rs.723.00 lakhs
PROPOSAL ESTIMATE
8/12/2019 Reconstruction of A.S.R Stadium
2/27
ru
8/12/2019 Reconstruction of A.S.R Stadium
3/27
Name of the work:-Reconstruction of A.S.R.Stadium at Eluru
Est.Cost.Rs.723.00 lakhs
The District Collector,West Godavari District,Eluru issued instructions to inspect the A.S.Rstadium at Eluru and to prepare necessary line estimate for demolition and reconstruction,if necessary.
Accordingly,joint inspection was held by the Engineers of PR&R&B Department on 22.6.2012.
After inspection,the following conclusions are arrived:-
1)The seating galleries G1 and G2 and pavillion complex are in reparable condition.
Hence,there is no need to dismantle them.
2)The remaining galleries are in dilapidated condition.Hence,they may be
dismantled.
3) 8-Lane running track and basket ball court need repairs.
4) Drainage facilities in the ground must be improved.
The copy of thejoint inspection reportis enclosed.The opinion of the M/s Siddartha Engg.College,
Vijayawada is obtained regarding the condition of the existing stadium.They recommended to dismantle
all the galleries.Copy of the Structural stability reportenclosed.
Further,as per the instructions of the Dist.Collector,the following infrastructure facilities are
proposed in the estimate along with reconstruction of galleries and compound wall:-
1)Dormitories accomodating 30 persons each,both for gents and ladies seperately.
2)Toilet facilities inside the stadium.
3)Indoor games complex inside the stadium.
Accordingly,the proposal estimate is prepared with the following provisions:-
1)Dismantling of dilapidated galleries and re-construction of galleries and
compound wall as per the plan enclosed.
2)Construction of the following infra-structural facilities:-
a)Two Nos of Dormitories accomodating 30 persons each
b)Toilet facilities inside the stadium.
c)Indoor games complex inside the stadium.
3)Repairs to basket ball court,running track and laying of new court for tennis
including laying of sports turf/grass
4)Providing drainage facilities in the ground
SPECIFICATION REPORT
8/12/2019 Reconstruction of A.S.R Stadium
4/27
5)Repairs to the pavillion complex and galleries
Further lump sum provisions are made in the estimate for the following items:-
1)Provision for VAT @ 5.00%
2)Provision for Consultancy charges @ 2.00%3)Provision for Q.C charges @ 0.50%
4)Provision for Price escalation @ 10%
The estimate is prepared as per the current SSR,i.e.2011-2012 rates and as per
the A.P Revised Standard data work will be carried out as per APDSS after administrative sanction
Asst.Executive Engineer Dy.Executive Engineer
PRI,Eluru PRI,Eluru
8/12/2019 Reconstruction of A.S.R Stadium
5/27
Name of the Work:-Reconstruction of A.S.R.Stadium at Eluru
Est.Cost. :- Rs.723.00 lakhs
S.No Description of item Amountin Rs.
1 2 3
1 Demolition&Re-Construction of Seating galleries
& Compound wall
32089442.00
2 Construction of infra structure facilities 16322755.00
3 Providing sports turfs,running track and courts 6835278.00
4 Providing drainage facilities in the ground 5076385.00
5 Repairs to Pavillion complex and galleries 1137526.00
TOTAL 61461386.00
6 LS Provision towards VAT@ 5% 3073069.00
7 Provision for [email protected]% 307307.00
8 Provision for consultancy charges@2% 1229228.00
9 Provision for price escalation@10% 6146139.00
10 Rounding--off 82871.00
PART--A TOTAL 72300000.00
Asst. Exe.Engineer Deputy Exe.Engineer
PRI,Eluru Section PRI,Sub division
Eluru
GENERAL ABSTRACT
PART--A
8/12/2019 Reconstruction of A.S.R Stadium
6/27
Sl.
No.
Description of Item Length
(m)
Width (m) Thickness
(m)
Quantity Unit Rate
1 2 3 4 5 6 7 8 9
I)DEMOLITION OF OLD GALLERIES:-
1
For footings of opening columns 5 x 6 2.00 2.00 0.35 42.00
For footings of gallery columns 16 x 21 2.00 2.00 0.35 470.40
For plinth beam of Galleries 16 x 1 31.66 0.23 0.30 34.95
Columns of openings(Type-I) 5 x 2 1.74 0.30 0.45 2.35
-----do--- Type-II 5 x 2 3.50 0.30 0.45 4.73
-----do--- Type-III 5 x 2 5.26 0.30 0.45 7.10
Gallery columns(Type-I) 16 x 7 1.74 0.30 0.45 26.31-----do--- Type-II 16 x 7 3.50 0.30 0.45 52.92
-----do--- Type-III 16 x 7 5.26 0.30 0.45 79.53
Gallery main beams 16 x 7 11.14 0.30 0.60 224.58
Main Beams at openings 5 x 2 11.14 0.30 0.60 20.05
Secondary Beams at openings 5 x 2 5.00 0.23 0.45 5.18
Gallery secondary beams 16 x 66 5.00 0.23 0.45 546.48
Seating slabs of galleries--I 16 x 9 31.66 0.77 0.10 351.05
-----do----- II 16 x 1 31.66 1.27 0.10 64.33
Parapet wall 16 x 1 31.66 0.75 0.10 37.99
1969.95 cum 1342.31
2
For footings of opening columns 5 x 6 2.00 2.00 0.30 36.00
For footings of gallery columns 16 x 21 2.00 2.00 0.30 403.20
For plinth beam of Galleries 16 x 1 31.66 0.30 0.30 45.59
484.79 cum 1207.55
II)RECONSTRUCTION OF NEW GALLERIES:-
3
For footings of opening columns 2 x 6 2.00 2.00 3.15 151.20
For footings of gallery columns 9 x 21 2.00 2.00 3.15 2381.40
Footings of compound wallcolumns
1 x 58 1.50 1.50 2.10 274.05
For plinth beam of compound
wall
1 x 1 171.11 0.30 0.30 15.40
For plinth beam of Galleries 9 x 1 31.66 0.30 0.60 128.22
Footings of out side compound
wall columns
1 x 150 1.50 1.50 2.10 708.75
3659.02 cum 119.83
4
For footings of opening columns 2 x 6 2.00 2.00 0.30 14.40
Demolition including stacking of serviceable materials and disposal of unserviceable
materials within 100 metres lead for RCC work
Demolishing and disposal of unserviceable materials within 100 metres lead
Unreinforced cement concrete more than 15 cm thickness
SUB ESTIMATE
Earth workexcavation and depositing on bank with initial lead of 10m and initial lift of
2m in Ordinary Soils for Foundation.(APSS No. 308) (RSSR)
Name of the Sub Work : Demolition&Re-Construction of Seating galleries & Compound wall
No
Filling with Sandin trenches, sides of foundations and basement complete for
finished item of work. (APSS NO. 309 & 310)(CSSR)
8/12/2019 Reconstruction of A.S.R Stadium
7/27
Sl.
No.
Description of Item Length
(m)
Width (m) Thickness
(m)
Quantity Unit Rate
1 2 3 4 5 6 7 8 9
No
For footings of gallery columns 9 x 21 2.00 2.00 0.30 226.80
Footings of compound wall
columns
1 x 58 1.50 1.50 0.30 39.15
Footings of out side compound
wall columns
1 x 150 1.50 1.50 0.30 101.25
For plinth beam of compoundwall 1 x 1 171.11 0.30 0.30 15.40
For plinth beam of Galleries 9 x 1 31.66 0.30 0.30 25.64
422.64 cum 1265.09
5
For footings of opening columns 2 x 6 2.00 2.00 0.30 14.40
For footings of gallery columns 9 x 21 2.00 2.00 0.30 226.80
Footings of compound wall
columns
1 x 58 1.50 1.50 0.30 39.15
Footings of out side compound
wall columns
1 x 150 1.50 1.50 0.30 101.25
For plinth beam of compound
wall
1 x 1 171.11 0.30 0.30 15.40
For plinth beam of Galleries 9 x 1 31.66 0.30 0.30 25.64
422.64 cum 3435.98
6
For footings of opening columns 2 x 6 2.00 2.00 0.35 16.80
For footings of gallery columns 9 x 21 2.00 2.00 0.35 264.60
Footings of compound wall
columns
1 x 58 1.50 1.50 0.35 45.68
Footings of out side compound
wall columns
1 x 150 1.50 1.50 0.35 118.13
445.21 cum 6258.86
7
For plinth beam of compound
wall
1 x 1 171.11 0.23 0.30 11.81
For plinth beam of out side
compound wall
1 x 1 450.00 0.23 0.30 31.05
For plinth beam of Galleries 9 x 1 31.66 0.23 0.30 19.66
62.52 cum 7657.86
8
Columns of openings(Type-I) 2 x 2 1.74 0.30 0.45 0.94
-----do--- Type-II 2 x 2 3.50 0.30 0.45 1.89
-----do--- Type-III 2 x 2 5.26 0.30 0.45 2.84
Gallery columns(Type-I) 9 x 7 1.74 0.30 0.45 14.80
-----do--- Type-II 9 x 7 3.50 0.30 0.45 29.77
-----do--- Type-III 9 x 7 5.26 0.30 0.45 44.74
Out side compound wall
columns
1 x 150 3.60 0.23 0.30 37.26
Vibrated reinforced Cement Concrete M20 grade nominal mix using 400 kg. of
cement, 20mm size HBG (SS5) metal complete for finished item of work for footing
(APSS No. 402) (CSSR)
Vibrated reinforced Cement Concrete M20 grade nominal mix using 400 kg. of
cement, 20mm size HBG (SS5) metal complete for finished item of work for Plinth
beams (APSS No. 402) (CSSR)
Vibrated reinforced Cement Concrete M20 grade nominal mix using 400 kg. of
cement, 20mm size HBG (SS5) metal complete for finished item of work for
Columns (APSS No. 402) (CSSR)
Plain Cement Concrete (1:4:8)prop using 40mm size HBG (SS5) metal for finished
item of work for Foundations and Flooring Bed (APSS No. 402)(RSSR)
8/12/2019 Reconstruction of A.S.R Stadium
8/27
Sl.
No.
Description of Item Length
(m)
Width (m) Thickness
(m)
Quantity Unit Rate
1 2 3 4 5 6 7 8 9
No
Compound wall columns 1 x 58 6.65 0.23 0.30 26.61
158.85 cum 6981.10
9
Gallery main beams 9 x 7 11.14 0.30 0.60 126.33
Main Beams at openings 2 x 2 11.14 0.30 0.60 8.02
Secondary Beams at openings 2 x 2 5.00 0.23 0.45 2.07
Gallery secondary beams 9 x 66 5.00 0.23 0.45 307.40
Intermediate beam for
compound wall
1 x 1 171.11 0.23 0.30 11.81
455.63 cum 6773.30
10
Seating slabs of galleries--I 9 x 9 31.66 0.77 ----- 1974.63
-----do----- II 9 x 1 31.66 1.27 ----- 361.87Parapet wall 9 x 1 31.66 0.75 ----- 213.71
2550.21 sqm 826.79
11
Seating slabs of galleries--I 9 x 9 31.66 1.35 ----- 3462.02
-----do----- II 9 x 1 31.66 1.85 ----- 527.14
Parapet wall 9 x 1 31.66 0.75 ----- 213.71
4202.87 sqm 263.04
12
206.585
206.585 MT 60000.00
13
Inner Compound wall A/R 1 x 1 171.11 0.23 4.35 171.20
Deduct columns 1 x 58 0.30 0.23 4.35 -17.41
Out side Compound wall A/R 1 x 1 450.00 0.23 2.10 217.35
Deduct columns 1 x 150 0.30 0.23 2.10 -21.74
349.40 cum 3060.69
14
Inner Compound wall both sides 1 x 2 171.11 ---- 4.35 1488.66
Outer compound wall both sides 1 x 2 450 ---- 2.10 1890.00
Providing high yield strength deformed (HYSD) steel TMT bars (Fe 415 grade as per
IS 1786-1985) of 8mm to 40mm diameters cutting, bending, to required sizes and
shapes placing in position with cover blocks of approved size and binding wire of
20SWG, forming grills for reinforcement work as per approved designs and drawings
including Cost and Conveyance of bars from approved sources to site of work with all
taxes complete for finished item of work (APSS No.126) in all floors (CSSR)
Providing impervious coatover RCC seating slab to required slopes with CM (1:3)
prop. 20mm thick (average) mixed with water proofing compound at 1Kg/bag of
cement, laid over roof slab when it is green, finished smooth with a floating coat of neat
cement and thread lining at regular intervals of 45cmx45cm with thread lining, curing,
lift charges, etc., complete for finished item of work (APSS No. 901 & 903).(CSSR)
Vibrated reinforced Cement Concrete M20 grade nominal mix using 400 kg. of
cement, 20mm size HBG (SS5) metal complete for finished item of work for Seating
slab of 100mm thick (APSS No. 402) (CSSR)
Brick Masonryin superstructure with traditional bricks 23x11x7cms in CM (1:6) prop:
mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing,etc., complete for finished item of work. (APSS No. 501 & 504).(CSSR) for Compound
wall
Vibrated reinforced Cement Concrete M20 grade nominal mix using 400 kg. of
cement, 20mm size HBG (SS5) metal complete for finished item of work for Beams
(APSS No. 402) (CSSR)
Plastering 12mmthick in CM(1:5) including cost and conveyance of all materials and
all labour charges etc.complete for compound wall
8/12/2019 Reconstruction of A.S.R Stadium
9/27
Sl.
No.
Description of Item Length
(m)
Width (m) Thickness
(m)
Quantity Unit Rate
1 2 3 4 5 6 7 8 9
No
3378.66 sqm 90.65
15
Stairs bottom 9 x 9 31.66 1.35 ----- 3462.02
----do---- 9 x 1 31.66 1.85 ----- 527.14
Gallery main beams 9 x 7 11.14 ---- 1.50 1052.73
Main Beams at openings 2 x 2 11.14 ---- 1.50 66.84
Secondary Beams at openings 2 x 2 5.00 ---- 0.58 11.60
Gallery secondary beams 9 x 66 5.00 ---- 0.58 1722.60
6842.93 sqm 106.49
16
Galleries top:-
Seating slabs of galleries--I 9 x 9 31.66 1.35 ----- 3462.02
-----do----- II 9 x 1 31.66 1.85 ----- 527.14
Parapet wall 9 x 1 31.66 0.75 ----- 213.71
Galleries bottom:-
Stairs bottom 9 x 9 31.66 1.35 ----- 3462.02
----do---- 9 x 1 31.66 1.85 ----- 527.14
Gallery main beams 9 x 7 11.14 ---- 1.50 1052.73
Main Beams at openings 2 x 2 11.14 ---- 1.50 66.84
Secondary Beams at openings 2 x 2 5.00 ---- 0.58 11.60
Gallery secondary beams 9 x 66 5.00 ---- 0.58 1722.60
Compound walls:-
Inner Compound wall both sides 1 x 2 171.11 ---- 4.35 1488.66
Outer compound wall both sides 1 x 2 450 ---- 2.10 1890.00
14424.46 sqm 87.39
Total
Deputy Executive Engineer, Assistant Executive Engin
PRI Sub-Division, Eluru PRI, Eluru
Painting to new walls with 2 coats of plastic emulsion paint of approved brand and
shade over a primary coat white cement paint after thoroughly brushing the surface to
remove all dirt and remains of loose powdered materials, including cost and
conveyance of all materials to work site and all operational, incidental, labour charges
etc. complete for finished item of work as per SS 911 for external walls
Ornamental Plasteringwith CM (1:3), 12 mm thick including cost and conveyance of
all materials and all labour charges etc.complete
8/12/2019 Reconstruction of A.S.R Stadium
10/27
Amount
10
2644284
585408
438460
8/12/2019 Reconstruction of A.S.R Stadium
11/27
Amount
10
534678
1452183
2786507
478769
8/12/2019 Reconstruction of A.S.R Stadium
12/27
Amount
10
1108948
3086119
2108488
1105523
12395079
1069405
8/12/2019 Reconstruction of A.S.R Stadium
13/27
Amount
10
306276
728704
1260611
32089442
er,
8/12/2019 Reconstruction of A.S.R Stadium
14/27
Sl.
No.
Description of Item Length
(m)
Width (m) Thickness
(m)
Quantity Unit
1 2 3 4 5 6 7 8
1
Construction of Dormitory-I 1 x 1 35.80 10.52 ----- 376.62
Construction of Dormitory-II 1 x 1 35.80 10.52 ----- 376.62
Construction of Indoor Games
complex
1 x 1 31.66 10.52 ----- 333.06
Construction of Toilet block-I 1 x 1 15.32 10.52 ----- 161.17
Construction of Toilet block-II 1 x 1 16.34 10.52 ----- 171.90
1419.37 sqm
Deputy Executive Engineer, Assistant Executi
PRI Sub-Division, Eluru PRI, Eluru
Construction of the following infra structural facilities for the A.S.R stadium including
construction of structure,plasterings,paintings,doors,windows,flooring with tiles of
necessary quality and compound wall etc.complete
SUB ESTIMATE
Name of the Sub Work : Construction of infrastructure facilities
No
8/12/2019 Reconstruction of A.S.R Stadium
15/27
Rate Amount
9 10
11500 16322755
Total 16322755
ve Engineer,
8/12/2019 Reconstruction of A.S.R Stadium
16/27
Sl.
No.
Description of Item Length
(m)
Width (m) Thickness
(m)
Quantity Unit
1 2 3 4 5 6 7 8
1
Ditches in ground 1 x 1 80.00 9.50 0.450 342.00
Ditches in ground 1 x 2 15.00 30.00 0.500 450.00Ditches in ground 1 x 2 25.00 30.00 0.600 900.00
Ditches in ground 1 x 1 40.00 32.00 0.550 704.00
2396.00 cum
2
For track 1 x 8 430.88 1.22 0.300 1261.62
For tennis court 1 x 1 23.97 10.97 0.300 78.89
1340.51 cum
3
For track 1 x 8 430.88 1.22 0.200 841.08
For tennis court 1 x 1 23.97 10.97 0.200 52.59
893.67 cum
4
For basket ball court 1 x 1 28.00 15.00 0.100 42.00 cum
5
Foot ball/Hockey ground 1 x 1 91.44 54.86 ----- 5016.40
Inside running track 1 x 1 156.36 76.36 ----- 11939.65
16956.05 sqm
Filling of ditcheswith approved material obtained from borrow pits with all lifts,
transporting to site, spreading, grading to required slope and compacting to meet
requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical
Specification Clause 301.5 MORD / 305 MORTH
Construction of granular sub baseby providing well graded material / Close graded
material, spreading in uniform layers with motor grader on prepared surface, mixing by
mix in place method with rotavator at OMC, and compacting with smooth wheel roller
80-100 kN / Vibratory Roller to achieve the desired density, complete as per
Technical Specification Clause 401 MORD / MORTH.
Construction of sports running trackby providing selected carted earth, spreading in
uniform layers with motor grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with smooth wheel roller 80-100 kN /
Vibratory Roller to achieve the desired density
Plain Cement Concrete (1:2:4)prop using 20mm size HBG (SS5) metal for finished
item of work for Basket ball court waering coat
SUB ESTIMATE
Name of the Sub Work : Providing sports tufs,Running track and courts
No
Laying of Sports turf/ grassincluding preparartion of ground for
levelling,transportation of grass to the work spot,labour charges and maintenance for a
period of one month including application of manures,weeding and mulching
etc.complete
8/12/2019 Reconstruction of A.S.R Stadium
17/27
Deputy Executive Engineer, Assistant Executi
PRI Sub-Division, Eluru PRI, Eluru
8/12/2019 Reconstruction of A.S.R Stadium
18/27
Rate Amount
9 10
250.00 599000
949.10 1272278
560.00 500455
5346.00 224532
250.00 4239013
8/12/2019 Reconstruction of A.S.R Stadium
19/27
Total 6835278
ve Engineer,
8/12/2019 Reconstruction of A.S.R Stadium
20/27
8/12/2019 Reconstruction of A.S.R Stadium
21/27
6
3.518
3.518 MT
7
Towards North side 1 x 20 80.00 ----- ----- 1600.00 Rmt
Deputy Executive Engineer, Assistant Executi
PRI Sub-Division, Eluru PRI, Eluru
Providing high yield strength deformed (HYSD) steel TMT bars (Fe 415 grade as per IS
1786-1985) of 8mm to 40mm diameters cutting, bending, to required sizes and shapes
placing in position with cover blocks of approved size and binding wire of 20SWG,
forming grills for reinforcement work as per approved designs and drawings including
Cost and Conveyance of bars from approved sources to site of work with all taxes
complete for finished item of work (APSS No.126) in all floors (CSSR)
Cost,supply and fixing of 450mm dia NP3 class pipes for connecting track drain to
peripheral drain including transportation and fixing charges
8/12/2019 Reconstruction of A.S.R Stadium
22/27
Rate Amount
9 10
119.83 72895
1265.09 153911
3435.98 418021
5230.00 1272616
826.79 387847
8/12/2019 Reconstruction of A.S.R Stadium
23/27
60000.00 211095
1600.00 2560000
Total 5076385
ve Engineer,
8/12/2019 Reconstruction of A.S.R Stadium
24/27
Sl.
No.
Description of Item Length
(m)
Width (m) Thickness
(m)
Quantity Unit
1 2 3 4 5 6 7 8
1
Over slab 1 x 1 54.00 12.00 0.08 48.60
48.60 cum
2
Pavillion complex
Ceiling 1 x 5 4.60 1.35 ----- 31.05
----do---- 1 x 4 3.80 1.85 ----- 28.12
Galleries top
Seating slabs of galleries--I 2 x 9 31.66 1.35 ----- 769.34
-----do----- II 2 x 1 31.66 1.85 ----- 117.14
Parapet wall 2 x 1 31.66 0.75 ----- 47.49
993.14 sqm
3
Inner Compound wall both sides 1 x 2 65.00 ---- 4.35 565.50
565.50 sqm
4
Galleries top:-
Seating slabs of galleries--I 2 x 9 31.66 1.35 ----- 769.34
-----do----- II 2 x 1 31.66 1.85 ----- 117.14
Parapet wall 2 x 1 31.66 0.75 ----- 47.49Galleries bottom:-Stairs bottom 2 x 9 31.66 1.35 ----- 769.34
----do---- 2 x 1 31.66 1.85 ----- 117.14
Gallery main beams 2 x 7 11.14 ---- 1.50 233.94
Gallery secondary beams 2 x 66 5.00 ---- 0.58 382.80
Compound walls:-
Inner Compound wall both sides 1 x 2 65.00 ---- 4.35 565.50
3002.69 sqm
Patch Plasteringwith CM (1:3), 12 mm thick including cost and conveyance of all
materials and all labour charges etc.complete
Painting to new walls with 2 coats of plastic emulsion paint of approved brand and
shade over a primary coat white cement paint after thoroughly brushing the surface to
remove all dirt and remains of loose powdered materials, including cost and
conveyance of all materials to work site and all operational, incidental, labour charges
etc. complete for finished item of work as per SS 911 for external walls
Plastering 12mmthick in CM(1:5) including cost and conveyance of all materials and
all labour charges etc.complete for existing compound wall
Plain Cement Concrete (1:1.5:3)prop using 6mm size HBG (SS5) metal for finished
item of work for wearing coat over pavillion complex
SUB ESTIMATE
Name of the Sub Work : Repairs to Pavillion complex& Galleries
No
8/12/2019 Reconstruction of A.S.R Stadium
25/27
5 Provision for repairs to electrical
wiring&Dummy columns
6 Provision for repairs to
plumbing&Sanitary lines andfittings and rain water pipes
Deputy Executive Engineer, Assistant Executi
PRI Sub-Division, Eluru PRI, Eluru
8/12/2019 Reconstruction of A.S.R Stadium
26/27
Rate Amount
9 10
6545.00 318087
106.49 105759
90.65 51263
87.39 262417
8/12/2019 Reconstruction of A.S.R Stadium
27/27
150000
250000
Total 1137526
ve Engineer,