Upload
ngotuyen
View
217
Download
0
Embed Size (px)
Citation preview
Recommendations on SHP Seminar
1. Most of the Small Hydro Projects (SHP) sites are located far away from the
road side. In case cost of infrastructure development is also loaded to SHP,
the project may become commercially unviable. State Government shall take
comprehensive program for development of roads to these sites under
various schemes like PGGY or State sponsored rural road schemes in a time
bound manner.
2. Single Window Clearance shall be available to the hydro developer to
facilitate all clearances in a time bound manner. Forest & Revenue Clearances
should also be part of single window clearance.
3. Hydrology & Toposheets should be collected by State Government in advance
and should be handed over to the hydro site developer at a time of signing of
Implementation agreement.
4. Central Water Commission (CWC) / Irrigation department of the State/ other
agencies are measuring hydrology in different streams. It is seen that
generally SHP sites are not having reliable hydrological data and are required
to depend upon computation methodology which may not be correct
approach. It is seen that many SHP are suffering due to inaccurate hydrology
considered while preparing the DPR. Guidelines /manuals of small hydro
needs to be updated/revised considering the practical considerations.
In view of the above, CWC/ Irrigation Department/State Government should
take up program for installation of G&D sites on tributaries/sub-tributaries of
river where SHPs are possible and keep record so that the data can be made
available to the prospective developers.
5. Monitoring of implementation work of hydro sites shall be done by State
through a dedicated monitoring cell. Any problem beyond the control of the
developer may be resolved by state government.
6. To gain cooperation of local’s, it is necessary that money collected under
LADA scheme should be utilized for the area for which money has been
collected. For the purpose of monitoring, a committee comprising of
representative from local’s, developer and local administrative official should
be constituted.
7. It has been seen that Forest Department is collecting huge amount of money
for CAT Plan but rarely work has been carried out on ground. There is a need
to fairly work out cost of CAT plan depending on the project U/S & D/S of a
particular stream. Due to non-implementation of CAT Plans, future hydro
projects as well as present hydro projects suffer due to landslide, erosion and
silt problem. Hence a committee comprising of Forest Department, State
officials, concerned developer and local Panchayat representatives should be
constituted and a completion report of the work as conceived should be
prepared and submitted to State Government/Developer alongwith the
expenditure carried out in various works.
8. It has been seen that due to some reasons the hydro sites allocated to some
developing agency are transferred to another developing agency. It shall be
obligatory on the part of earlier agency to hand over the data collected to the
new developer at a reasonable cost. A suitable provision in the agreement is
recommended to be made.
9. Central Water Commission/ Central Electricity Authority (CEA) are expert
organization in the field. They may be requested to provide guidance to the
small hydro developer on request.
10. A Regional PMP Atlas is one of the important input. CWC has been
maintaining PMP Atlas and continue to do so in future and may be requested
to disseminate information which can be available on website.
11. Power evacuation is one of the bottlenecks in the commercial viability of the
SHP. Power shall be purchased at generating bus. Since construction of
evacuation line if constructed by the state agency may not match with the
commissioning of the hydro units, hence construction of evacuation line may
be entrusted to hydro developers at an approved cost which can be
reimbursed to the hydro developer suitably. Cluster of hydro sites in a
particular valley can be clubbed to optimize the cost of evacuation.
12. It has been seen that 11kV line are running in some area as long as 20 kms
resulting in heavy power loss and voltage drop. These existing lines may be
utilized by providing LILO arrangement to the extent possible which will not
only result in reduction in the transmission losses but would also improve the
voltage of that area.
13. Uttarakhand Electricity Regulatory Commission (UERC) has come out with
positive upward revision of tariff and metering of power at generating bus.
Different Regulatory Commission has to be approached so they also carried
out suitable exercise so that rules are amended to encourage development of
SHP.
14. Indian Meteorological Department (IMD) has installed Rain Gauges, but they
are not available in sufficient number. State Government as well as CWC
may carry out installation of Rain Gauges with or without IMD, so that
sufficient date is available basin-wise.
15. It has been observed that in many cases developers before taking the hydro
sites have not carried out proper due-diligence of the site. All the developer
may be advised that before considering any site for allotment they should
carry out techno-commercial due- diligence. The small amount spent at initial
stage will save huge losses to the small developers.
16. States are allocating the hydro sites without carrying out the initial work like
Head available, Hydrology and Geology studies etc. It should be
recommended to the State that for all possible sites, atleast PFR should be
made covering Topology, Hydrology and Geological aspects. The risk
anticipated shall be elaborated in the PFR. In case of any Wild Life
Sanctuary/ Bio-sphere falls in project area etc which may result refusal of
approval/delay in approval should be highlighted in PFR.
17. Most important aspect is optimization of valley which will reduce the cost of
infrastructure/evacuation system and would result in optimum exploitation
of small hydro potential, so State Govt. should adopt the optimization
approach of valley.