    Rebate in MM

    REBATE PROCESS IN PURCHASE

    Rebate agreement is contract that is made between the vendor & the buyer for giving certain percentage ofdiscounts on supplying over a particular value of material.

    The below mentioned is the step for the same

    Step 1: Creation of a Rebate Agreement.

    Vendor Used:100023

    Rebate Agreement Created: 37

    1. T-codeMEB1

    Select Agreement Type -1000(Vendor Based Rebate).

    -2000(Material Based Rebate)

    Then select

    .

    http://scn.sap.com/servlet/JiveServlet/showImage/102-33000-1-153334/2.jpghttp://scn.sap.com/servlet/JiveServlet/showImage/102-33000-1-153333/1.jpg
  • 7/24/2019 Rebate in MM

    2/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    2

    Enter the required Purchasing.Org & Purchasing Group

    Enter the Condition Granter ( i.e. Vendor),Currency, validity start & end of the agreement.

    Select the .

    http://scn.sap.com/servlet/JiveServlet/showImage/102-33000-1-153346/5.jpghttp://scn.sap.com/servlet/JiveServlet/showImage/102-33000-1-153344/3.jpg
  • 7/24/2019 Rebate in MM

    3/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    3

    Maintain the rate of rebate.

    Select

    Maintain Scales according to the value & discounts.

    http://scn.sap.com/servlet/JiveServlet/showImage/102-33000-1-153352/8.jpg
  • 7/24/2019 Rebate in MM

    4/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    4

    1. Goto-->Material for settlement.

    Enter the material code. This material will be used at the time of settlement through credit memo. We can

    create a dummy material for this purpose.

    Save the agreement.

  • 7/24/2019 Rebate in MM

    5/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    5

    Step 2: Setting up the vendor master.

    T-code: XK02

    Select the Purchasing Data Field & select the mentioned fields in Control data.

    1. 1. Subsequent Settlement

    2. 2. Subseq.sett.index.

    3. 3. B.vol comp./ag.nec

  • 7/24/2019 Rebate in MM

    6/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    6

    Step 3: Partner function

    The partner function Invoicing Party need to be maintained as to vendor.

    Step 4:Define Business Volume Comparison type

    1. SPRO-->MM-->Purchasing-->Subsequent Settlement-->Agreements

    http://scn.sap.com/servlet/JiveServlet/showImage/102-33000-1-153364/b.jpg
  • 7/24/2019 Rebate in MM

    7/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    7

    Step 5: Define Rebate Arrangement Types for Subsequent Settlement

    SPRO-->MM-->Purchasing-->Subsequent Settlement-->Agreements

  • 7/24/2019 Rebate in MM

    8/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    8

    Here you can assign the BV Comp/agree.type

    The time of update of the Settlement ie PO/GR/IV

    I have used IV as the control parameter & hence did the complete process to update agreement.

    STEP 6: Creation of PO

    T-Code: ME21N

    Create a fresh PO for the vendor 100023; maintain the Material, Plant, Quantity etc.

    http://scn.sap.com/servlet/JiveServlet/showImage/102-33000-1-153367/d.jpg
  • 7/24/2019 Rebate in MM

    9/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    9

    1.

    In Conditions tab, check the Rebate Condition -->A001.Select Details .

    Details Screen: Rebate Agreement 37 Active for the Vendor.

    Rebate Agreement -37 picked automatically for the Vendor as created.

    http://scn.sap.com/servlet/JiveServlet/showImage/102-33000-1-153369/f.jpg
  • 7/24/2019 Rebate in MM

    10/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    10

    Step 7: Goods Receipt

    Step 8: Invoice VerificationT-code: MIRO

  • 7/24/2019 Rebate in MM

    11/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    11

    Step 9: Running Rebate Settlement

    T-code: MEB4

    Enter the Vendor as Condition Granter, Settlement date as the agreement end date mentioned &

    simulate.

    http://scn.sap.com/servlet/JiveServlet/showImage/102-33000-1-153373/j.jpg
  • 7/24/2019 Rebate in MM

    12/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    12

    As the PO value is less than 50000, as mentioned in rebate agreement the rebate % is 0.

    Created another PO with value 45000; done GR & IV.

    After the 2nd

    Invoice Done for Rs.45000 (Total PO Value=5000+45000) Hence Rebate of 6%

    Created another PO with value 50100; done GR & IV.

    After the 3rd

    Invoice Done for Rs.50100 (Total Value=50000+50100) Hence Rebate of 7%

  • 7/24/2019 Rebate in MM

    13/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    13

    Simulating Finally

    Settlement Done

    Here the material we had mentioned in the agreement 37 as material for settlement is used to post the rebate.

    -Arun Yesodharan

  • 7/24/2019 Rebate in MM

    14/14

    Rebate in MM

    Generated by Jive on 2016-01-18+01:00

    Associate Consultant

    HCL Infosystems