REAL Options Paper

  • Upload
    cash82

  • View
    220

  • Download
    0

Embed Size (px)

Citation preview

  • 8/2/2019 REAL Options Paper

    1/6

    1. Introduction to project evaluationProject financial evaluation is used to analyse and represent the financial attractiveness of a project

    (P2Pay, 2011). It looks at all the monetary factors involved in undertaking the project, including the

    estimates of the projects capital cost, expected output, along with annual revenues, expenses anddeductions. It also analyses important variables such as the time frame over which the capital outlays

    will be recouped and, ultimately, the profits that can be realised. There is a number methodology that

    can be used in the financial evaluation of a project. According to (Maybee 2010), evaluation

    methodologies have undergone numerous changes overtime in order to address specific the

    characteristics of each project under evaluation. It has been found that evaluation techniques can be

    divided into three main categories: cost approach, market approach and income approach (Lee and

    Strang 2003a). However, the cost approach fails to recognise the future earnings potential of the

    project being evaluated while the nature of the minerals industry violates the principle of the market

    approach. The market approach states that comparable properties must have comparable values but in

    reality construction projects are rarely alike as previously discussed. As a result, both the cost andmarket approaches are not applicable to the construction industry. Income approach to project

    evaluation is therefore widely used in this industry.

    The first of the income-based evaluation methodologies is Payback Period (PBP). PBP is often used

    as a sanity check on the evaluation of projects. Essentially PBP tells an investor how long their

    invested capital will be tied up in the project. However, this method does not provide a platform that

    is conducive to ranking multiple alternatives that are under evaluation (Lee and Strang 2003a).

    Another weakness of PBP is that it fails to recognise the time value of money. Finally, it has been

    observed that PBP provides ambiguous results in situations where the sign of the cash flows from a

    project switch between positive and negative more than once (Maybee 2010). Recently, there have

    been a number of improvements to PBP. The first of these is Discounted PBP (DPBP). DPBP is a

    reformulated evaluation technique that is NPV-compatible and capable of producing results that

    recognise the entire cash flow process of the project (Hajdasinski 2012). The advantage of DPBP over

    the traditional PBP method is its ability to convey informative facts for investment decision making

    purposes. Through this formulation, NPV calculation of the project is required to establish

    profitability and the existence of multiple payback periods exist is explicitly recognised. The

    reformulation also provides a means of ranking mutually exclusive alternatives through the evaluation

    of projects based on their differential cash flows (Maybee 2010). Referencing the work of (Alesii

    2006), (Maybee 2010) mentioned another method of computing an updated version of PBP. This

    method is combines PBP and IRR with real options to enhance value of project options. By studying

    an investment project in the shipping industry the paper showed that when a project is passivelymanaged (no real options taken into account), PBP and IRR are inconsistent with NPV since the use

    of such methods may lead to under or overinvestment as a result of misallocation of resources;

    however, when the same investment is actively managed (including the effects of real options), PBP

    and IRR provide results consistent with the NPV-based investment decisions.

    The second income-based evaluation approach commonly used in the construction industry is internal

    rate of return (IRR). IRR is defined as the rate at which the total present value of cash inflow is equal

    to the present value of cash outflow. It is used to measure and compare the profitability of

    investments. The higher the IRR of a project, the more desirable it is. In practice, IRR is often

    compared against the minimum acceptable rate of return (which is a minimum rate of return set by a

    company if it is to invest in a project) or the cost of capital; if IRR is higher than its proxy then the

  • 8/2/2019 REAL Options Paper

    2/6

    project is considered acceptable. IRR therefore offers valuable insight into the value that a project

    yields. However, it was found that IRR is conceptually flawed and cannot serve as a valid evaluation

    criterion by (Hajdasinski 2012). As a result, the true rate of return (TRR) should be used as an

    alternative rate of return. This method offers an NPV-compatible measure for project evaluation

    (Hajdasinski 2012).

    The third and the most widely used income-based evaluation technique is the NPV methodology.

    NPV enjoys wide acceptance in the construction industry, and has been used as the standard

    evaluation technique for decades. In this approach, all future cash flows are estimated and discounted

    to the present days value using an appropriate discount rate to calculate the net present value, which

    is essentially the sum of all discounted future cash flows. NPV is used for dual purposes: first, as a

    method to place a value on a project; and second, as a vehicle for managers and decision makers to

    use as a guide in choosing among different alternatives. For example: if presented by two projects, a

    company can choose the best option to invest in by comparing NPV of each individual project. The

    project that has higher NPV will be accepted.

    Advances in modern finance theory in recent times, together with major developments in decision

    science, have brought some significant benefits to the management and planning field. Companies in

    various industries have begun embracing and utilising applications of finance theory more

    systematically (Walls, 2004; Hall & Nicholls, 2006; Samis et al, 2006; Hoare, 2007; Topal, 2008).

    Planning groups and business units in companies, especially those in the oil & gas and mining

    industries, increasingly use innovative techniques such as decision analysis, simulation, portfolio

    management, and real options analysis to improve the overall decision making and capital allocation

    process (Smith & McCardle, 1996; Walls, 2004; Dimitrakopoulos & Sabour, 2007; Xie, 2010). With

    significant improvements in computing power and widespread availability of high performance

    computers, simulation-based evaluation tools such as Monte Carlo Simulation (MCS) have been

    widely used in the construction industry. With MCS models, a user can model multiple key variablesand evaluate their impact on the value and risk of the project. In addition, correlations between the

    key variables can be included in a simulation analysis to provide an added level of uncertainty

    recognition. However, since these simulations are usually built on the NPV valuation technique, they

    inherit its inflexibility (Maybee 2010).

    Decision Tree (DT) analysis has its origin from operations research. DT is essentially a flowchart

    presented by a tree-like graph representing a classification of a system (Topal, 2008). DT models

    contain all information about projects under investigation. This information can be probabilities of

    occurrence and possible outcomes for each event, resource required and costs. The eventual utility

    (often in NPV terms) is presented at the end of each branch. DT method is usually employed in the

    probabilistic analysis process of complex projects, especially those in the construction or resources

    sectors, to identify the most appropriate strategy to undertake due its ability to break down large,

    complicated problems into a series of smaller, simpler ones (Topal, 2008). This allows the decision

    maker to see the whole project and its possible NPV outcomes. For example, decision trees were used

    to incorporate the heterogeneous nature of a mineral deposit into an evaluation model (Samis and

    Poulin (1996) (1998)). The authors considered a project with two zones: one high-grade and one low-

    grade, and modelled the development of the high-grade zone. In this study, management was given

    the option to extend production and develop the satellite low-grade zone when the high-grade had

    been exhausted. It was shown that managements ability to replace exhausted zones with auxiliary

    reserves has the potential to add great value to a mine extraction project (Samis and Poulin (1996)

    (1998); Maybee 2010). However, overall the use of decision analysis (DA) is still built on the NPV

  • 8/2/2019 REAL Options Paper

    3/6

    model, and will only evaluate the project cash flows in a static environment, alleviating one shortfall

    of the NPV model, only to be confined by another.

    Real option (RO) is often considered as the final stage in the development of evaluation tools (Lee

    and Strang 2003c). Essentially, RO is an extension and adaptation of corporate finance to real -life

    decision-making situations. This methodology builds upon, and can integrate with, decision tree andsimulation analyses. However, where assessments for future events and occurrences in DT or MCS

    rely heavily upon the managements preferences, RO uses market data to quantify probability

    distributions and incorporates learning into the model (Topal 2008). The benefits of RO over

    previously mention evaluation techniques is in its ability to value the managerial flexibility in a

    project. It has been found that in many instances, value of well-managed companies exceeds the value

    of their underlying assets (Macmillan 2000; Lee and Strang 2003c).

    2. NPV versus RO2.1.NPV method

    Despite its popularity, it is often found that NPV calculations undervalue projects (Moyen et al, 1996;

    Samis et al, 2006; Dimitrakopoulos & Sabour, 2007). This is due to a number of factors: first, there is

    a lack of adjustments for different types of uncertainty and risk involved in construction projects; and

    second, NPV fails to account for the flexibility inherently exists in the management of risky assets.

    The lack of adjustment in the NPV methodology is mainly due to the choice of a discount rate used in

    calculating the value of an investment (Topal 2008). The estimation of a suitable discount rate is often

    the most difficult and uncertain part of NPV method. It is exacerbated by the fact that the final result

    of a NPV calculation is very sensitive to the choice of discount rate, i.e. a small change in the discount

    rate can cause a large change in the NPV value. In practice, when evaluating projects, companies

    often use a hurdle rate to account for the uncertainty and possible risks that it faces (Dowd 2005). A

    hurdle rate is an upwardly adjusted single discount rate consisting of a risk-free rate and a risk

    premium. By using a hurdle rate, future cash flows of construction investments are discounted by both

    the risk-free and risk premium rates (Moyen et al. 1996). Consequently, future cash flows are

    discounted by both the risk-free rate and the risk premium. This effect is compounded by each

    subsequent cash flow, which ultimately results in a much lower NPV than which might be otherwise

    calculated. Moreover, due to the integration of the time-value-of-money and risk discounting into a

    single discount rate, the traditional single-rate NPV approach is inherently biased. Of particular

    concern and relevance in construction is an inherent bias against high-margin, long-life assets with

    large capital requirements and a bias towards low-margin, short-life assets with low capital

    investment (Lai & Stange, 2009). To overcome this issue, the certainty equivalent concept can be

    used to account for the risk premium without compounding its effect on the present values (Pietersz,

    2011). Along with the discount rate issue, another important drawback of NPV is in its implicit

    assumption regarding the certainty of future cash flow over the life of the project (Fox 2008). It is

    often assumed during the early stages of a project that all cash flow streams are constant throughout

    the whole project. The reality is that OPEX and CAPEX changes at different stages of the project life.

    As a consequent, effects of cyclical fluctuation in materials, labour, capital and operating costs are

    ignored. Even though smoothing these series makes it easy for calculation in the evaluation process,

    one has to be aware that these factors will change over time and therefore they will affect the value of

    the project. One possible solution is to calculate a range of NPV values by using different discount

    rates and forecasts, so that a range of options available to the company can be generated. Options

    considered often consist of the best, median and worst cases of NPV values. In some instances, MonteCarlo simulations are used to generate a probability distribution of NPVs. These ranges give the

  • 8/2/2019 REAL Options Paper

    4/6

    decision makers indications of possible project outcomes. Moreover, they allow project planners to set

    appropriate contingency plans accordingly.

    The final pitfall of NPV is the built-in assumption that manager is passive in managing their projects.

    The NPV method assumes that if a project is undertaken today, it will continue to perform until it is

    completed. In contrast, the reality is that managers have considerable flexibility in choosing the timeto invest in a project (Maybee 2010). Moreover, once the project has commenced, managers have

    discretions concerning equipment, material and labour. Often, in making investment decisions using

    NPV, the consensus is to undertake the investments with positive net present values and reject those

    with negative net present values (Sabour and Poulin 2006). By this immediate accept/reject decision,

    NPV ignores the value of options such as deference/abandonment or expansion/contraction of the

    investment. Since the market conditions for construction products are highly uncertain, these

    flexibility options can add a significant value to the underlying project (Sabour & Poulin, 2006,

    Sabour & Dimitrakopoulos, 2010; Dimitrakopoulos, 2010). Failures to address the management

    responses to the supply and demand cycle will result in inaccurate estimates and consequently will

    lead to wrong decisions (Moyen et al, 1996; Sabour & Poulin, 2006).

    It must be noted that since NPV was originally designed for evaluating bonds in the financial markets,

    where future cash flows are relatively easy to identify and quantify, it does have constraints when

    applied to the minerals industry, where cash flows are less certain (Dowd 2005; Maybee et al. 2010;

    Maybee 2010). Therefore, one must be careful in using and interpreting results obtained from a NPV-

    based evaluation method (Fox 2008; Pietersz 2011). To overcome the shortcomings presented by the

    traditional static NPV method, stochastic methods and multiple scenarios can be used to deal with

    uncertain variables in the NPV. However, this methodology still possesses the same dilemma as the

    traditional method in that it focuses on whether or not to invest the project but does not inform the

    investors of the timing of investment (Yang & Blyth, 2007).

    2.2.Real Options

    RO has been viewed as a promising technique of valuing investments under uncertainty that is

    induced by the constant changes in the market place (Dimitrakopoulos & Sabour 2007). Further, such

    uncertainty can have significant effects on the value of a project, due to the competitive interactions of

    firms in the market. As a consequence, the expected returns on a project may be drastically different

    to the actual return that can be realised from the investment itself. It has been observed that under

    these conditions, RO tends to perform better than the conventional NPV method due to the inclusion

    of management flexibility (Dimitrakopoulos & Sabour, 2007). Managerial flexibility here arises from

    the fact that as new information arrives, uncertainty about market conditions and future cash flows is

    gradually resolved and management has valuable flexibility to alter the companys operating strategyin order to capitalise on favourable future opportunities or mitigate losses by deferring, expanding,

    contracting, abandoning or otherwise altering the project at different stages of its operating life

    accordingly (Trigeorgis, 2001). This flexibility allows the managers to modify the project according

    to changes. Ultimately, the management flexibility inherent in real options provides the company

    opportunities to maximise the upside potential while limiting the downside losses (Dimitrakopoulos &

    Sabour, 2007).

    Like investments made in the electricity oil & gas or mining sectors, building projects has three

    important characteristics: first, the investment is partially or completely irreversible (once invested,

    the capital costs become totally or partially sunk); second, there is always uncertainty over the future

    return from the investment; and finally, both management of a company and investors have the

  • 8/2/2019 REAL Options Paper

    5/6

    flexibility in timing the investment (such as options to abandon, expand or contract the operation of

    the project). However, traditional NPV-based project evaluation methods cannot incorporate these

    three characteristics (Yang and Blyth 2007). These two methods differ on a fundamental level: RO

    adjusts for risk within the cash flow components while NPV discounts for risk at the aggregate net

    cash flow. This seemingly small difference allows RO to differentiate assets according to their unique

    risk characteristics, while the conventional NPV approach cannot (Samis et al. 2006; Samis et al.

    2007). Another advantage of RO over NPV is the way it handles the discount rates: while NPV uses

    risk-adjusted discount rate, RO utilises a risk-free rate to discount the cash flows in the evaluation of

    the project (Smith & McCardle, 1996; Walls, 2004; Martinez, 2009). Therefore, when applying

    discounting procedures, a project estimated by RO yields higher values than that estimated by the

    conventional NPV method. However, Trigeorgis (2001) and others recommended against crapping the

    traditional NPV method. Rather it should be seen as a crucial and necessary input to an option-based

    expanded NPV analysis. Using a case in the mining industry as an example, (Dimitrakopoulos and

    Sabour 2007) noted of the lack of procedures for testing the usefulness and advantages of RO over the

    static NPV method in practice. They therefore contend it is not yet clear whether the RO can deal

    with the complexity of mining projects and whether it can really be applied to making decisions thatcan improve project value (Dimitrakopoulos and Sabour 2007). Nonetheless, RO could become a

    useful tool for decision makers and investors to quantitatively analyse the impacts of uncertainty and

    price uncertainty on construction sector investment (Yang and Blyth 2007).

    It must be noted that the NPV and RO evaluation methods share many features. Both see assets as

    portfolios of uncertain cash flows received at a series of times in the future. In the absence of

    flexibility, the only difference between the two approaches is the manner of accounting for the effect

    of cash flow uncertainty on asset value. Although the difference in risk-adjustment between the NPV

    and RO evaluation methods appears to be nuanced but its consequences are potentially large because

    in the case of the latter, it allows senior management to use market information to determine the

    underlying structure of risk adjustments for uncertain variables (Sami et al, 2007).

    The real option valuation technique has been extensively studied in the context of natural resources

    industries. In mining, RO is widely used to evaluate projects under a wide range of uncertainty and

    risk. Risk in this industry arises from uncertainty in orebody estimations to operational uncertainty

    (mining and processing) to economic uncertainty (commodity prices and foreign exchange). For

    instance, despite recent advances in exploration and ore estimation techniques, the amount of resource

    within a deposit can never be known with certainty. Further, since the ore quality varies substantially

    throughout the deposit, the assumption of constant resource extraction rate throughout the lifetime of

    the mine is an extreme simplification. It has been found that by using RO, mining companies are able

    to capture the upside potentials while significantly reducing the downside risks in their positions bymeans of leveraging the managerial flexibility provided by this method (Martinez, 2007).

    Recently, there have been a number of attempts to apply the real option concept into the construction

    industry. Chiara et al (2007) studied a case concerning multiple exercise dates in a limited revenue

    guarantee venture in a Build-Operate-Transfer (BOT) toll road project with a fixed concession period.

    In this model, they consider a revenue guarantee as a particular type of real options, a discrete-

    exercise option. Discrete exercise options are ones that can be exercised at discrete points over a

    predetermined time period and generally take one of three forms: European, Bermudan, and simple

    multiple-exercise options. The decision process in this study is multi-stage with a return associated to

    each decision and the objective is to determine the optimal decision policy. Once the decision is

    made, the fair value guarantee, given by the expectation of the sum of the payoffs relative to the

    optimal stopping time set, is discounted back to the present. Along this line of research, Ford et al

  • 8/2/2019 REAL Options Paper

    6/6

    (2001) investigated the strategic flexibility involved in a complex civil project. They found that using

    a structured real option approach in construction management can increase returns through improved

    project planning and management.