For a project using heavy wood section 250 x 350mm
Citation preview
Rate Analysis
1 Fixing of Door and window size (1175x2775)Considering 1 Nos
S.No. Item Unit Qty. Rate Amount
i
brick cutting labour (6 nos. hole 300x230x300) and shifting of door/window frame Nos. 2.000 350 700
ii Fixing of frameForman Nos. 1.000 500 500Labour Nos. 1.000 350 350mason Nos. 0.500 1000 500
iii CC work holfast grouting (6 nos) Cuft 4.500 212 954iv Shuttering Sqft 12.000 42 504
3508.00
v Add T & P 2% 70.16vi Add Sundries 1% 35.08
3613.24Add Over head & profit (5+15) = 20% 722.65
4335.89Say Rs 4335/- per Frame