239
H PTER N . LINING OF CANAL DESCRIPTION OF ITEM NO 1: Formation, dressing and preparing sub-grade. a) In Bed. Detail Qty Rate Per Unit (Rs.) Amount (Rs.) Labour Rate Analyses for 125 Sft  Dresser 0.33 No 85.00 P. Day 28.05  Unskilled Cooly 0.77 No 140.00 P. Day 107.80  Total 135.85  Sundries 10 Percent 13.59  Total 149.44  Contractor's Profit & Overheads 20 Percent 29.89  Total 179.32  Item Rates Labour Rate for 100 Sft Rs. 143.46 Say 143.45  Labour Rate for 1 Sqm Rs. 15.44 Say 15.45  1 Rates for all finished work include the removal of surplus debris, unused material and byproducts. 2 The rates include curing for specified period wherever necessary. 3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement & payments. Unit Rate (British System) per 100 Sft

Rate analsis Chapter No. 14 (Lining of Canal)

Embed Size (px)

Citation preview

Page 1: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 1/23

H PTER N .

LINING OF CANAL

DESCRIPTION OF ITEM NO 1: Formation, dressing and preparing sub-grade.

a) In Bed.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Labour

Rate Analyses for 125 Sft  

Dresser 0.33 No 85.00 P. Day 28.05 

Unskilled Cooly 0.77 No 140.00 P. Day 107.80 

Total 135.85 

Sundries 10 Percent 13.59 

Total 149.44 

Contractor's Profit & Overheads 20 Percent 29.89 

Total 179.32 

Item Rates

Labour Rate for 100 Sft Rs. 143.46 Say 143.45 

Labour Rate for 1 Sqm Rs. 15.44 Say 15.45 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 1

Page 2: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 2/23

Item No. 1 Formation, dressing and preparing sub-grade.

b) On Slope.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

LabourRate Analyses for 125 Sft

Dresser 0.50 No 85.00 P. Day 42.50 

Unskilled Cooly 1.00 No 140.00 P. Day 140.00 

Total 182.50 

Sundries 10 Percent 18.25 

Total 200.75 

Contractor's Profit & Overheads 20 Percent 40.15 

Total 240.90 

Item Rates

Labour Rate for 100 Sft Rs. 192.72 Say 192.70 

Labour Rate for 1 Sqm Rs. 20.74 Say 20.75 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 2

Page 3: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 3/23

DESCRIPTION OF ITEM NO 2: Stabilized layer of cement sand ratio 1:30 2"

(50mm) thick on slope.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.50 Bag 230.00 P. Bag 115.00 Sand 18.00 Cft 3.50 Cft 63.00 

Total 178.00 

Contractor's Profit & Overheads 20 Percent 35.60 

Total 213.60 

Labour

Rate Analyses for 125 Sft

Mason 0.50 No 300.00 P. Day 150.00 

Unskilled Cooly 1.50 No 140.00 P. Day 210.00 

Bahishti 0.50 No 160.00 P. Day 80.00 

Total 440.00 

Sundries 10 Percent 44.00 

Total 484.00 

Contractor's Profit & Overheads 20 Percent 96.80 

Total 580.80 

Item Rates

Labour Rate for 100 Sft Rs. 464.64 Say 464.65 Labour Rate for 1 Sqm Rs. 50.00 Say 50.00 

Composite Rate for 100 Sft Rs. 678.24 Say 678.25 

Composite Rate for 1 Sqm Rs. 72.98 Say 73.00 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 3

Page 4: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 4/23

DESCRIPTION OF ITEM NO 3: Cement plaster ½" (12mm) thick, ratio 1:10.

a) In Bed.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.34 Bag 230.00 P. Bag 78.20 

Sand 4.20 Cft 3.50 Cft 14.70 

Total 92.90 

Contractor's Profit & Overheads 20 Percent 18.58 

Total 111.48 

Labour

Rate Analyses for 125 Sft

Mason 0.33 No 300.00 P. Day 99.00 

Unskilled Cooly 1.00 No 140.00 P. Day 140.00 

Bahishti 0.50 No 160.00 P. Day 80.00 

Total 319.00 

Sundries 10 Percent 31.90 

Total 350.90 

Contractor's Profit & Overheads 20 Percent 70.18 

Total 421.08 

Item RatesLabour Rate for 100 Sft Rs. 336.86 Say 336.85 

Labour Rate for 1 Sqm Rs. 36.25 Say 36.25 

Composite Rate for 100 Sft Rs. 448.34 Say 448.35 

Composite Rate for 1 Sqm Rs. 48.24 Say 48.25 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 4

Page 5: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 5/23

Item No. 3 Cement plaster ½" (12mm) thick, ratio 1:10.

b) On Slope.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.34 Bag 230.00 P. Bag 78.20 

Sand 4.20 Cft 3.50 Cft 14.70 

Total 92.90 

Contractor's Profit & Overheads 20 Percent 18.58 

Total 111.48 

Labour

Rate Analyses for 125 Sft

Mason 0.50 No 300.00 P. Day 150.00 

Unskilled Cooly 1.25 No 140.00 P. Day 175.00 

Bahishti 0.50 No 160.00 P. Day 80.00 

Total 405.00 

Sundries 10 Percent 40.50 

Total 445.50 

Contractor's Profit & Overheads 20 Percent 89.10 

Total 534.61 

Item RatesLabour Rate for 100 Sft Rs. 427.68 Say 427.70 

Labour Rate for 1 Sqm Rs. 46.02 Say 46.00 

Composite Rate for 100 Sft Rs. 539.16 Say 539.15 

Composite Rate for 1 Sqm Rs. 58.01 Say 58.00 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 5

Page 6: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 6/23

DESCRIPTION OF ITEM NO 4: Cement plaster 3/8"(10mm) thick, ratio 1:3

a) In Bed.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.70 Bag 230.00 P. Bag 161.00 

Sand 2.50 Cft 3.50 Cft 8.75 

Total 169.75 

Contractor's Profit & Overheads 20 Percent 33.95 

Total 203.70 

Labour

Rate Analyses for 125 Sft

Mason 0.33 No 300.00 P. Day 99.00 

Unskilled Cooly 1.00 No 140.00 P. Day 140.00 

Bahishti 0.50 No 160.00 P. Day 80.00 

Total 319.00 

Sundries 10 Percent 31.90 

Total 350.90 

Contractor's Profit & Overheads 20 Percent 70.18 

Total 421.08 

Item RatesLabour Rate for 100 Sft Rs. 336.86 Say 336.85 

Labour Rate for 1 Sqm Rs. 36.25 Say 36.25 

Composite Rate for 100 Sft Rs. 540.56 Say 540.55 

Composite Rate for 1 Sqm Rs. 58.16 Say 58.15 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 6

Page 7: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 7/23

Item No. 4 Cement plaster 3/8"(10mm) thick, ratio 1:3.

b) On Slope.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.70 Bag 230.00 Each 161.00 

Sand 2.50 Cft 3.50 Cft 8.75 

Total 169.75 

Contractor's Profit & Overheads 20 Percent 33.95 

Total 203.70 

Labour

Rate Analyses for 125 Sft

Mason 0.50 No 300.00 P. Day 150.00 

Unskilled Cooly 1.25 No 140.00 P. Day 175.00 

Bahishti 0.50 No 160.00 P. Day 80.00 

Total 405.00 

Sundries 10 Percent 40.50 

Total 445.50 

Contractor's Profit & Overheads 20 Percent 89.10 

Total 534.61 

Item RatesLabour Rate for 100 Sft Rs. 427.68 Say 427.70 

Labour Rate for 1 Sqm Rs. 46.02 Say 46.00 

Composite Rate for 100 Sft Rs. 631.38 Say 631.40 

Composite Rate for 1 Sqm Rs. 67.94 Say 67.95 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 7

Page 8: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 8/23

DESCRIPTION OF ITEM NO 5: Cement plaster 1½" (40mm) thick, ratio 1:6.

a) In Bed.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 1.56 Bag 230.00 P. Bag 358.80 

Sand 11.70 Cft 3.50 Cft 40.95 

Total 399.75 

Contractor's Profit & Overheads 20 Percent 79.95 

Total 479.70 

Labour for 125 Sft

Mason 0.50 No 300.00 P. Day 150.00 

Unskilled Cooly 1.25 No 140.00 P. Day 175.00 

Bahishti 0.50 No 160.00 P. Day 80.00 

Total 405.00 

Sundries 10 Percent 40.50 

Total 445.50 

Contractor's Profit & Overheads 20 Percent 89.10 

Total 534.61 

Item RatesLabour Rate for 100 Sft Rs. 427.68 Say 427.70 

Labour Rate for 1 Sqm Rs. 46.02 Say 46.00 

Composite Rate for 100 Sft Rs. 907.38 Say 907.40 

Composite Rate for 1 Sqm Rs. 97.63 Say 97.65 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 8

Page 9: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 9/23

Item No. 5 Cement plaster 1½" (40mm) thick, ratio 1:6.

b) On Slope.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 1.56 Bag 230.00 P. Bag 358.80 

Sand 11.70 Cft 3.50 Cft 40.95 

Total 399.75 

Contractor's Profit & Overheads 20 Percent 79.95 

Total 479.70 

Labour for 125 Sft

Mason 0.75 No 300.00 P. Day 225.00 

Unskilled Cooly 1.50 No 140.00 P. Day 210.00 

Bahishti 0.50 No 160.00 P. Day 80.00 

Total 515.00 

Sundries 10 Percent 51.50 

Total 566.50 

Contractor's Profit & Overheads 20 Percent 113.30 

Total 679.80 

Item RatesLabour Rate for 100 Sft Rs. 543.84 Say 543.85 

Labour Rate for 1 Sqm Rs. 58.52 Say 58.50 

Composite Rate for 100 Sft Rs. 1023.54 Say 1,023.55 

Composite Rate for 1 Sqm Rs. 110.13 Say 110.15 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 9

Page 10: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 10/23

DESCRIPTION OF ITEM NO 6: Tile lining (12"x6"x2") (300x150x50mm) in 1:6

cement sand mortar.

a) In Bed.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

er Brick Tiles 1200.00 Nos 1250.00 1000 Nos 1,500.00 

Cement 3.44 Bag 230.00 P. Bag 791.20 

Sand 25.70 Cft 3.50 Cft 89.95 

Total 2,381.15 

Contractor's Profit & Overheads 20 Percent 476.23 

Total 2,857.38 

Labour

Mason 2.50 No 300.00 750.00 Unskilled Cooly 5.00 No 140.00 700.00 

Bahishti 0.75 No 160.00 120.00 

Total 1,570.00 

Sundries 10 Percent 157.00 

Total 1,727.00 

Contractor's Profit & Overheads 20 Percent 345.40 

Total 2,072.40 

Item RatesLabour Rate for 100 Cft Rs. 2,072.40  Say 2,072.40 

Labour Rate for 1 Cum Rs. 731.97  Say 731.95 

Composite Rate for 100 Cft Rs. 4,929.78  Say 4,929.80 

Composite Rate for 1 Cum Rs. 1,741.20  Say 1,741.20 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

The rates are only for laying tiles over 1/8" Ø (6mm) thick layer of 1:6 mortar items 1 to 5

above are payable separately.

Unit Rate (British System) per 100 Sft

Page 10

Page 11: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 11/23

Item No. 6 Tile lining (12"x6"x2") (300x150x50mm) in 1:6

cement sand mortar.

b) On Slope.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Brick Tiles 1200.00 Nos 1250.00 1000 Nos 1,500.00 

Cement 3.44 Bag 230.00 P. Bag 791.20 

Sand 25.70 Cft 3.50 Cft 89.95 

Total 2,381.15 

Contractor's Profit & Overheads 20 Percent 476.23 

Total 2,857.38 

Labour

Mason 2.75 No 300.00 P. Day 825.00 

Unskilled Cooly 6.00 No 140.00 P. Day 840.00 

Bahishti 0.75 No 160.00 P. Day 120.00 

Total 1,785.00 

Sundries 10 Percent 178.50 

Total 1,963.50 

Contractor's Profit & Overheads 20 Percent 392.70 

Total 1,187.32 

Item Rates

Labour Rate for 100 Cft Rs. 1,187.32  Say 1,187.30 

Labour Rate for 1 Cum Rs. 419.36  Say 419.35 

Composite Rate for 100 Cft Rs. 4,044.70  Say 4,044.70 

Composite Rate for 1 Cum Rs. 1,428.59  Say 1,428.60 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

The rates are only for laying tiles over 1/8" Ø (6mm) thick layer of 1:6 mortar items 1 to 5

above are payable separately.

Unit Rate (British System) per 100 Sft

Page 11

Page 12: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 12/23

DESCRIPTION OF ITEM NO 7: Tile lining (12"x6"x2") (300x150x50mm) in 1:3

cement sand mortar.

a) In Bed.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Brick Tiles 1200.00 Nos 1250.00 1000 Nos 1,500.00 

Cement 6.00 Bag 230.00 P. Bag 1,380.00 

Sand 22.50 Cft 3.50 Cft 78.75 

Total 2,958.75 

Contractor's Profit & Overheads 20 Percent 591.75 

Total 3,550.50 

Labour

Mason 2.50 No 300.00 P. Day 750.00 

Unskilled Cooly 5.00 No 140.00 P. Day 700.00 

Bahishti 0.75 No 160.00 P. Day 120.00 

Total 1,570.00 

Sundries 10 Percent 157.00 

Total 1,727.00 

Contractor's Profit & Overheads 20 Percent 345.40 

Total 2,072.40 

Item Rates

Labour Rate for 100 Cft Rs. 2,072.40  Say 2,072.40 

Labour Rate for 1 Cum Rs. 731.97  Say 731.95 

Composite Rate for 100 Cft Rs. 5,622.90  Say 5,622.90 

Composite Rate for 1 Cum Rs. 1,986.01  Say 1,986.00 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

The rates are only for laying tiles over 1/8" (6mm) thick layer of 1:3 mortar items

1 to 5 above are payable separately.

Unit Rate (British System) per 100 Sft

Page 12

Page 13: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 13/23

Item No. 7 Tile lining (12"x6"x2") (300x150x50mm) in 1:3

cement sand mortar.

b) On Slope.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Brick Tiles 1200.00 Nos 1250.00 1000 Nos 1,500.00 

Cement 6.00 Bag 230.00 P. Bag 1,380.00 

Sand 22.50 Cft 3.50 Cft 78.75 

Total 2,958.75 

Contractor's Profit & Overheads 20 Percent 591.75 

Total 3,550.50 

Labour

Mason 2.75 No 300.00 P. Day 825.00 

Unskilled Cooly 6.00 No 140.00 P. Day 840.00 

Bahishti 0.75 No 160.00 P. Day 120.00 

Total 1,785.00 

Sundries 10 Percent 178.50 

Total 1,963.50 

Contractor's Profit & Overheads 20 Percent 392.70 

Total 1,187.32 

Item Rates

Labour Rate for 100 Cft Rs. 1,187.32  Say 1,187.30 

Labour Rate for 1 Cum Rs. 419.36  Say 419.35 

Composite Rate for 100 Cft Rs. 4,737.82  Say 4,737.80 

Composite Rate for 1 Cum Rs. 1,673.40  Say 1,673.40 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

The rates are only for laying tiles over 1/8" (6mm) thick layer of 1:3 mortar items

1 to 5 above are payable separately.

Unit Rate (British System) per 100 Sft

Page 13

Page 14: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 14/23

DESCRIPTION OF ITEM 8: Brick lining (9"x4½"x3") (225x114x75mm) in

1:6 cement sand mortar.

a) In Bed.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Bricks 1350.00 Nos 1200.00 1000 Nos 1,620.00 

Cement 3.44 Bags 230.00 P. Bag 791.20 

Sand 25.70 Cft 3.50 Cft 89.95 

Total 2,501.15 

Contractor's Profit & Overheads 20 Percent 500.23 

Total 3,001.38 

Labour

Mason 2.50 No 300.00 P. Day 750.00 

Unskilled Cooly 5.00 No 140.00 P. Day 700.00 

Bahishti 0.75 No 160.00 P. Day 120.00 

Total 1,570.00 

Sundries 10 Percent 157.00 

Total 1,727.00 

Contractor's Profit & Overheads 20 Percent 345.40 

Total 2,072.40 

Item Rates

Labour Rate for 100 Cft Rs. 2,072.40  Say 2,072.40 

Labour Rate for 1 Cum Rs. 731.97  Say 731.95 

Composite Rate for 100 Cft Rs. 5,073.78  Say 5,073.80 

Composite Rate for 1 Cum Rs. 1,792.06  Say 1,792.05 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:6 mortar items

1 to 5 above are payable separately.

Unit Rate (British System) per 100 Sft

Page 14

Page 15: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 15/23

Item No. 8 Brick lining (9"x4½"x3") (225x114x75mm) in

1:6 cement sand mortar.

b) On Slope.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Bricks 1350.00 Nos 1200.00 1000 Nos 1,620.00 

Cement 3.44 Bags 230.00 P. Bag 791.20 

Sand 25.70 Cft 3.50 Cft 89.95 

Total 2,501.15 

Contractor's Profit & Overheads 20 Percent 500.23 

Total 3,001.38 

Labour

Mason 2.75 No 300.00 P. Day 825.00 

Unskilled Cooly 6.00 No 140.00 P. Day 840.00 

Bahishti 0.75 No 160.00 P. Day 120.00 

Total 1,785.00 

Sundries 10 Percent 178.50 

Total 1,963.50 

Contractor's Profit & Overheads 20 Percent 392.70 

Total 2,356.20 

Item Rates

Labour Rate for 100 Cft Rs. 2,356.20  Say 2,356.20 

Labour Rate for 1 Cum Rs. 832.21  Say 832.20 

Composite Rate for 100 Cft Rs. 5,357.58  Say 5,357.60 

Composite Rate for 1 Cum Rs. 1,892.30  Say 1,892.30 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:6 mortar items

1 to 5 above are payable separately.

Unit Rate (British System) per 100 Sft

Page 15

Page 16: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 16/23

DESCRIPTION OF ITEM No 9: Brick lining (9"x4½"x3") (225x114x75mm) in

1:3 cement sand mortar.

a) In Bed.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Bricks 1350.00 Nos 1200.00 1000 Nos 1,620.00 

Cement 6.00 Bags 230.00 P. Bag 1,380.00 

Sand 22.50 Cft 3.50 Cft 78.75 

Total 3,078.75 

Contractor's Profit & Overheads 20 Percent 615.75 

Total 3,694.50 

Labour

Mason 2.50 No 300.00 P. Day 750.00 

Unskilled Cooly 5.00 No 140.00 P. Day 700.00 

Bahishti 0.75 No 160.00 P. Day 120.00 

Total 1,570.00 

Sundries 10 Percent 157.00 

Total 1,727.00 

Contractor's Profit & Overheads 20 Percent 345.40 

Total 2,072.40 

Item Rates

Labour Rate for 100 Cft Rs. 2,072.40  Say 2,072.40 

Labour Rate for 1 Cum Rs. 731.97  Say 731.95 

Composite Rate for 100 Cft Rs. 5,766.90  Say 5,766.90 

Composite Rate for 1 Cum Rs. 2,036.87  Say 2,036.85 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:3 mortar items

1 to 5 above are payable separately.

Unit Rate (British System) per 100 Sft

Page 16

Page 17: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 17/23

Item No. 9 Brick lining (9"x4½"x3") (225x114x75mm) in

1:3 cement sand mortar.

b) On Slope.

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Bricks 1350.00 Nos 1200.00 1000 Nos 1,620.00 

Cement 6.00 Bags 230.00 P. Bag 1,380.00 

Sand 22.50 Cft 3.50 Cft 78.75 

Total 3,078.75 

Contractor's Profit & Overheads 20 Percent 615.75 

Total 3,694.50 

Labour

Mason 2.75 No 300.00 P. Day 825.00 

Unskilled Cooly 6.00 No 140.00 P. Day 840.00 

Bahishti 0.75 No 160.00 P. Day 120.00 

Total 1,785.00 

Sundries 10 Percent 178.50 

Total 1,963.50 

Contractor's Profit & Overheads 20 Percent 392.70 

Total 2,356.20 

Item Rates

Labour Rate for 100 Cft Rs. 2,356.20  Say 2,356.20 

Labour Rate for 1 Cum Rs. 832.21  Say 832.20 

Composite Rate for 100 Cft Rs. 6,050.70  Say 6,050.70 

Composite Rate for 1 Cum Rs. 2,137.11  Say 2,137.10 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

The rates are only for laying bricks over 1/8" (6mm) thick layer of 1:3 mortar items

1 to 5 above are payable separately.

Unit Rate (British System) per 100 Sft

Page 17

Page 18: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 18/23

DESCRIPTION OF ITEM NO 10: Cement concrete lining, using washed screened

and graded stone aggregate.

a) In Bed.

i) Ratio 1:2:4

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 17.60 Bags 230.00 P. Bag 4,048.00 

Sand 44.00 Cft 3.50 Cft 154.00 

Aggregate 88.00 Cft 18.50 Cft 1,628.00 

Total 5,830.00 

Contractor's Profit & Overheads 20 Percent 1,166.00 

Total 6,996.00 

Labour

Mason 1.00 No 300.00 P. Day 300.00 

Unskilled Cooly 6.00 No 140.00 P. Day 840.00 

Bahishti 0.60 No 160.00 P. Day 96.00 

Total 1,236.00 

Sundries 10 Percent 123.60 

Total 1,359.60 

Contractor's Profit & Overheads 20 Percent 271.92 Total 1,631.52 

Item Rates

Labour Rate for 100 Cft Rs. 1,631.52  Say 1,631.50 

Labour Rate for 1 Cum Rs. 576.25  Say 576.25 

Composite Rate for 100 Cft Rs. 8,627.52  Say 8,627.50 

Composite Rate for 1 Cum Rs. 3,047.24  Say 3,047.25 

1 Rates for all finished work include the removal of surplus debris, unused materialand byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 18

Page 19: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 19/23

Item No. 10 Cement concrete lining, using washed screened

and graded stone aggregate.

a) In Bed.

ii) Ratio 1:3:6

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 13.00 Bags 230.00 P. Bag 2,990.00 

Sand 46.00 Cft 3.50 Cft 161.00 

Aggregate 92.00 Cft 18.50 Cft 1,702.00 

Total 4,853.00 

Contractor's Profit & Overheads 20 Percent 970.60 

Total 5,823.60 

Labour

Mason 1.00 No 300.00 P. Day 300.00 

Unskilled Cooly 6.00 No 140.00 P. Day 840.00 

Bahishti 0.60 No 160.00 P. Day 96.00 

Total 1,236.00 

Sundries 10 Percent 123.60 

Total 1,359.60 

Contractor's Profit & Overheads 20 Percent 271.92 Total 1,631.52 

Item Rates

Labour Rate for 100 Cft Rs. 1,631.52  Say 1,631.50 

Labour Rate for 1 Cum Rs. 576.25  Say 576.25 

Composite Rate for 100 Cft Rs. 7,455.12  Say 7,455.10 

Composite Rate for 1 Cum Rs. 2,633.15  Say 2,633.15 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 19

Page 20: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 20/23

Item No. 10 Cement concrete lining, using washed screened

and graded stone aggregate.

a) In Bed.

iii) Ratio 1:4:8

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 9.60 Bags 230.00 P. Bag 2,208.00 

Sand 48.00 Cft 3.50 Cft 168.00 

Aggregate 96.00 Cft 18.50 Cft 1,776.00 

Total 4,152.00 

Contractor's Profit & Overheads 20 Percent 830.40 

Total 4,982.40 

Labour

Mason 1.00 No 300.00 P. Day 300.00 

Unskilled Cooly 6.00 No 140.00 P. Day 840.00 

Bahishti 0.60 No 160.00 P. Day 96.00 

Total 1,236.00 

Sundries 10 Percent 123.60 

Total 1,359.60 

Contractor's Profit & Overheads 20 Percent 271.92 Total 1,631.52 

Item Rates

Labour Rate for 100 Cft Rs. 1,631.52  Say 1,631.50 

Labour Rate for 1 Cum Rs. 576.25  Say 576.25 

Composite Rate for 100 Cft Rs. 6,613.92  Say 6,613.90 

Composite Rate for 1 Cum Rs. 2,336.04  Say 2,336.05 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 20

Page 21: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 21/23

Item No. 10 Cement concrete lining, using washed screened

and graded stone aggregate.

b) On Slope.

i) Ratio 1:2:4

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 17.60 Bags 230.00 P. Bag 4,048.00 

Sand 44.00 Cft 3.50 Cft 154.00 

Aggregate 88.00 Cft 18.50 Cft 1,628.00 

Total 5,830.00 

Contractor's Profit & Overheads 20 Percent 1,166.00 

Total 6,996.00 

Labour

Mason 1.25 No 300.00 P. Day 375.00 

Unskilled Cooly 7.00 No 140.00 P. Day 980.00 

Bahishti 0.50 No 160.00 P. Day 80.00 

Total 1,435.00 

Sundries 10 Percent 143.50 

Total 1,578.50 

Contractor's Profit & Overheads 20 Percent 315.70 Total 1,894.20 

Item Rates

Labour Rate for 100 Cft Rs. 1,894.20  Say 1,894.20 

Labour Rate for 1 Cum Rs. 669.03  Say 669.05 

Composite Rate for 100 Cft Rs. 8,890.20  Say 8,890.20 

Composite Rate for 1 Cum Rs. 3,140.02  Say 3,140.00 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 21

Page 22: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 22/23

Item No. 10 Cement concrete lining, using washed screened

and graded stone aggregate.

b) On Slope.

ii) Ratio 1:3:6

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 13.00 Bags 230.00 P. Bag 2,990.00 

Sand 46.00 Cft 3.50 Cft 161.00 

Aggregate 92.00 Cft 18.50 Cft 1,702.00 

Total 4,853.00 

Contractor's Profit & Overheads 20 Percent 970.60 

Total 5,823.60 

Labour

Mason 1.25 No 300.00 P. Day 375.00 

Unskilled Cooly 7.00 No 140.00 P. Day 980.00 

Bahishti 0.50 No 160.00 P. Day 80.00 

Total 1,435.00 

Sundries 10 Percent 143.50 

Total 1,578.50 

Contractor's Profit & Overheads 20 Percent 315.70 Total 1,894.20 

Item Rates

Labour Rate for 100 Cft Rs. 1,894.20  Say 1,894.20 

Labour Rate for 1 Cum Rs. 669.03  Say 669.05 

Composite Rate for 100 Cft Rs. 7,717.80  Say 7,717.80 

Composite Rate for 1 Cum Rs. 2,725.93  Say 2,725.95 

1 Rates for all finished work include the removal of surplus debris, unused material

and byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft

Page 22

Page 23: Rate analsis Chapter No. 14 (Lining of Canal)

8/9/2019 Rate analsis Chapter No. 14 (Lining of Canal)

http://slidepdf.com/reader/full/rate-analsis-chapter-no-14-lining-of-canal 23/23

Item No. 10 Cement concrete lining, using washed screened

and graded stone aggregate.

b) On Slope.

iii) Ratio 1:4:8

Detail

Qty Rate

Per Unit (Rs.) Amount (Rs.)

Material

Cement 9.60 Bags 230.00 P. Bag 2,208.00 

Sand 48.00 Cft 3.50 Cft 168.00 

Aggregate 96.00 Cft 18.50 Cft 1,776.00 

Total 4,152.00 

Contractor's Profit & Overheads 20 Percent 830.40 

Total 4,982.40 

Labour

Mason 1.25 No 300.00 P. Day 375.00 

Unskilled Cooly 7.00 No 140.00 P. Day 980.00 

Bahishti 0.50 No 160.00 P. Day 80.00 

Total 1,435.00 

Sundries 10 Percent 143.50 

Total 1,578.50 

Contractor's Profit & Overheads 20 Percent 315.70 Total 1,894.20 

Item Rates

Labour Rate for 100 Cft Rs. 1,894.20  Say 1,894.20 

Labour Rate for 1 Cum Rs. 669.03  Say 669.05 

Composite Rate for 100 Cft Rs. 6,876.60  Say 6,876.60 

Composite Rate for 1 Cum Rs. 2,428.82  Say 2,428.80 

1 Rates for all finished work include the removal of surplus debris, unused materialand byproducts.

2 The rates include curing for specified period wherever necessary.

3  Nominal dimensions of tile or brick shall be taken for the purpose on measurement

& payments.

Unit Rate (British System) per 100 Sft