“By working with Invensys, RasGas is setting the pace for the LNG industry globally, supplying more efficient and more environmentally friendly energy for export to the world.” RasGas Pumps Up Production Goals • Implement cost-saving measures to extend business efficiencies • Expand production while maximizing existing technologies Challenges • Communication from on-shore control room to off-shore well is 130 km away • Multiple operating platforms and hardware versions Solutions and Products • Foxboro Distributed Control System - I/A Series® • Triconex Safety Instrumented Systems Results • World’s largest LNG supplier with expected total production of 77 million tons per year • World’s longest safety system peer-to-peer network allows the onshore LNG system to shut-down the remote offshore wellheads from a distance of 130 km • Provided lowest risk level and with the highest life cycle value INDUSTRY: UPSTREAM OIL & GAS RasGas www.rasgas.com

RasGas . Doha, Qatar – Exploration engineers discovered ever natural gas off the Northeast handlecoast of Qatar in 1971. At the time, the magnitude vendorsof the discovery could

  • Upload
    others

  • View
    41

  • Download
    0

Embed Size (px)

Citation preview

Page 1: RasGas . Doha, Qatar – Exploration engineers discovered ever natural gas off the Northeast handlecoast of Qatar in 1971. At the time, the magnitude vendorsof the discovery could

“By working with Invensys, RasGas is setting the pace for the LNG industry globally, supplying more efficient and more environmentally friendly energy for export to the world.”

RasGas Pumps Up Production

Goals• Implementcost-savingmeasurestoextend

businessefficiencies• Expandproductionwhilemaximizingexisting

technologies

Challenges• Communicationfromon-shorecontrolroomto

off-shorewellis130kmaway• Multipleoperatingplatformsandhardware

versions

Solutions and Products• FoxboroDistributedControlSystem-I/ASeries®• TriconexSafetyInstrumentedSystems

Results• World’slargestLNGsupplierwithexpectedtotal

productionof77milliontonsperyear• World’slongestsafetysystempeer-to-peer

networkallowstheonshoreLNGsystemtoshut-downtheremoteoffshorewellheadsfromadistanceof130km

• Providedlowestrisklevelandwiththehighestlifecyclevalue

INDUSTRY:UPSTREAMOIL&GAS

RasGaswww.rasgas.com

Page 2: RasGas . Doha, Qatar – Exploration engineers discovered ever natural gas off the Northeast handlecoast of Qatar in 1971. At the time, the magnitude vendorsof the discovery could

Doha, Qatar–ExplorationengineersdiscoverednaturalgasofftheNortheastcoastofQatarin1971.Atthetime,themagnitudeofthediscoverycouldnothavebeenimagined.Sincethen,theNorthField(asitisnowknown)hasbeenconfirmedasthelargest,non-associatednaturalgasfieldintheworld.Withmorethan900trillionstandardcubicfeetofreserves,NorthFieldrepresents10percentoftheworld’snaturalgasreserves.

Drillingforgasisonlypartofthestory.ThoughQatar’snaturalgasislocatedinthisgiant,offshorefield,itstillneedstobesuperchilledasliquefiednaturalgas(LNG)forexport.Thissuperchillingoperationtakesplaceonshore130kmawayinagasprocessingplantcalleda“train”.RasGas,oneoftheworld’spremierintegratedLNGenterprises,hasseventrains,includingtwooftheworld’slargest.

TocapitalizeonthegasdiscoveryinNorthField,RasGasneededtodevelopnew,world-classfacilitiesfortheextraction,storage,processingandexportofLNG.Long-termagreementstosupplycustomersaroundtheglobe,includingKorea,India,Italy,Spain,Taiwan,BelgiumandtheUnitedStateshavepositionedRasGastobecomethelargestsupplierofLNGworldwide.

RasGasneededacompanytoprovidetimelydesigninformationintheengineeringphaseandaconsistentdesignthroughoutprojectdevelopment,despitethesheersizeoftheproject.Inaddition,allworkwasbeinghandledfromacombinationofdifferentengineeringlocations.

Theclearchoicewastheproducts,servicesandsolutionsprovidedbyInvensysOperationsManagement.Invensysoffersthemostholisticandcost-effectivewaytooptimizeoperationperformanceandoverallprofitability.Invensyshelpsimprovetheperformanceofkeyresources(people,equipment,energyandmaterials)inrealtime—withdramatic,measurableresults—usingacollaborativeandopenapproach.

OneofthemainreasonsInvensyswasselectedwastheirstrongprojectexecutioncapabilitywithdeepknowledgeofLNGapplicationsandtheexistinginstallationatRasGas.Operatinginan

everchangingenvironment,Invensys’abilitytohandlelatedesigninformationfrompackagevendorshelpedminimizeimpacttotheprojectschedule.

RigorousFactoryAcceptanceTesting(FAT)helpedtointegrateFoxboroI/ADistributedControlSystem,TriconexCriticalandSafetySystemsandotherapplicationsystems–alltestedwithinanintegratedenvironment.Withitswealthofexperience,Invensyswasabletoidentifycriticaltie-insearlyintheproject,whichhelpedtomitigatetherisksassociatedwithworkinginaliveplant.

Duetothelargescaleoftheprojectandextendedtestingperiod,theInvensysteamhadbeverydetailedintheFAT,takingintoconsiderationmanydiverseconcerns,includingshipmentconstraints.Invensys’world-classprocessautomationbroughttechnologicallyadvancedattributestoensureaseamlessimplementationinthislargescaleLNGproject.

Bigger and Better

RasGas’hugeinvestmentintoLNGplacesQatarontheworld-mapasaleadingglobalnaturalgasproducer.In1999,thefirstyearofproduction,RasGasproduced6.6milliontonsperannum(MTA)withitsfirst2trains.Asmoretrainscameonline,productionincreasedtoalevelwhere

Page 3: RasGas . Doha, Qatar – Exploration engineers discovered ever natural gas off the Northeast handlecoast of Qatar in 1971. At the time, the magnitude vendorsof the discovery could

industryexpertsestimatethatsoonQatarwillsupply30%oftheworld’sLNG.WithTrains6and7online,eachproducing7.8MTA,thesetwoprojectsrepresentabigsteptowardsQatarbecomingtheworld’slargestsupplierofLNGwithexpectedtotalproductionof77MTA.

The Invensys Solution

Theexistingcontrolsystemhadmultipleoperatingplatformsandhardwareversions.Invensyshadtostrikeadelicatebalancebetweenexistingandnewtechnology.Systemlimitsondatatrafficintheexistingsystemcoupledwiththenumberofcontrolstationsalsoimpactedtheadditionofnewstationsandapplications.

Toachievethesegoals,Invensysdeliveredthebest-in-classtechnologiesincontrolandsafetysystems,providingexpertiseinserialdatacommunications(HART,Modbus,ProfiBus,OPCandHighSpeedEthernet),insinglesystemintegration,providingmissioncriticalinformationandcontrolfortheoperationoftheLNGPlant.

Becausetheoffshorewellheadsrequirereal-timecommunicationwiththeonshoreoperations,Invensysdeliveredtheworld’slongestsafetysystempeer-to-peernetwork,whichallowstheonshoreLNGsystemtoshut-downtheremoteoffshorewellheadsfromadistanceof130km.

Invensys’uniquesolutionallowsforinteroperabilityonasolidintegratedplatform,byutilizingFoxboroI/ASeriesConfigurationComponent(IACC)EngineeringSuite,imbeddingFieldDeviceTool(FDT)technologyandFieldDeviceManagement(FDM)intooneconsistentsingleengineeringenvironment.AllFieldBusstandardsinteroperatewithinthesystemutilizingonecoherentprojectdatabaseforthesystemandfielddevices.

TheFoxboroI/ASeriesistheworld’sfirstOpenControlSystem(OCS),whichallowsuserstocontinuouslydeploymoreadvancedcontrolstrategies,applicationandengineeringpackages.OCSallowsfortheabilitytomigratefromoldertechnologytothenewesttechnologyandprovidesaguaranteeofsystemsandhardwarebeingcontinuouslycurrent.

The Energy to Succeed

Invensysprovidedarobustandsustainablesolutionallowingforanalysis,measurementsandimprovementsinLNGplantperformance.AdvanceAlarmPackage,LoopPerformanceandInstrumentAssetManagementwereprovidedforTrain6&7.ThesolutionsuitewasalsoenhancedwithcontrolsystemsforPre-treatment,ProductionandThroughput,RefrigerantCompositionandLoad,MainHeatExchanger,LiquefiedPetroleumGas(LPG)recoveryandFractionationSystemQuality.

InvensysbroughtuniqueattributestotheRasGasoperation,whichensuredsuccessatthelowestrisklevelandwiththehighestlifecyclevalue.Invensysshowcasedextensiveandlong-termexperienceinQatar,andastrongtrackrecordindesignandimplementation.TheexpansionandretrofitofRasGas’LNGplantprocessautomationsystemsincorporatedbothlegacyandnewsystemsintooneintegratedsystem.

Asunanticipatedsituationsarose,Invensysprovedtobeveryflexibleandadaptableinhandlinglatechangesindesigndatawithoutimpactingprojectdeliverydates.ControlSystemswereengineered,installedandpre-commissionedtoachieverecord-breakingcompletiondates.

Thesefactorsresultedinthedeliveryofthelowestriskcontrolsystemandadvancedapplicationsystem,designedandimplementedbyengineerswhoweretechnicalexpertsandunderstoodthebusinesscontextofRasGas’market.

Page 4: RasGas . Doha, Qatar – Exploration engineers discovered ever natural gas off the Northeast handlecoast of Qatar in 1971. At the time, the magnitude vendorsof the discovery could

WhiletheInvensysteamworkedonthelivesystem,theyconsideredtheneedfortie-inpackageengineeringtofollowstrictqualitycontrolprocedures,makingsurethesystempassedthroughastringentreviewprocessandgainedapprovalfromRasGas.Invensysdidevenmorebyformulatingarisksandmitigationplan.Thiswasexecutedseamlesslywhilefacedwithscheduleconstraintsinshiploadingandplannedshutdownactivities.

With40%ofworldwideLNGproductioncontrolledbyInvensysandtheirbest-in-classLNGexecutionteam,RasGashaschosenaviablepartnerandsystemintegratorthathasensuredcosteffectivenessatthelowestrisk.Technologyisakeyenablerinachievingsuchascaleofproduction.ThesizeandcostefficienciesofeachtrainequippedwithInvensystechnologywilleventuallycontributetolowercostsofproducingLNG.

Withsuchexperience,InvensysismorethanqualifiedtoserviceRasGasfortheentire25-yearlifecycle.ByworkingwithInvensys,RasGasissettingthepacefortheLNGindustryglobally,supplyingmoreefficientandmoreenvironmentallyfriendlyenergyforexporttotheworld.

Invensys,theInvensyslogo,ArchestrA,Avantis,Eurotherm,Foxboro,IMServ,InFusion,SimSci-Esscor,Triconex,andWonderwarearetrademarksofInvensysplc,itssubsidiariesoraffiliates.Allotherbrandsandproductnamesmaybethetrademarksorservicemarksoftheirrepresentativeowners.

©2010InvensysSystems,Inc.Allrightsreserved.Nopartofthematerialprotectedbythiscopyrightmaybereproducedorutilizedinanyformorbyanymeans,electronicormechanical,includingphotocopying,recording,broadcasting,orbyanyinformationstorageandretrievalsystem,withoutpermissioninwritingfromInvensysSystems,Inc.

Invensys Operations Management • 5601 Granite Parkway III, #1000, Plano, TX 75024 • Tel: (469) 365-6400 • Fax: (469) 365-6401 • iom.invensys.com

Rev.06/10