PART 1- Project objectives and overall research approach - (1000 words) 1.1. Reasons for choosing the project topic area and the particular organisation that is the focus of the research work My project topic is “An organization’s budgetary control system and its links with performance management and decision making” and my project title is “An evaluation of the budgetary control system of Sur Construction Plc (Sur) and its support to the company’s performance management and decision making processes”. I selected this topic for the following reasons which make me feel more comfortable with and confident to successfully complete this research compared to the other ones. A subject matter, concerning my company, in which I wanted to see improvement It is within my area of expertise I found sufficient amount of relevant literature My employer found the topic relevant and promised to provide all the necessary support including access to relevant data and use of office facilities for this purpose It gives me the opportunity to demonstrate IT skill Besides I have observed that in Sur this issue is not given due attention. I believe that by conducting the research I may come out with relevant findings that might help my company improve its budgetary practices. Similar companies in my country (Ethiopia) may also find the work useful. The focus organisation: 1

RAP ... combined

Embed Size (px)

Citation preview

Page 1: RAP ... combined

PART 1- Project objectives and overall research approach - (1000 words)

1.1. Reasons for choosing the project topic area and the particular organisation that is the focus of the research work

My project topic is “An organization’s budgetary control system and its links with performance management and decision making” and my project title is “An evaluation of the budgetary control system of Sur Construction Plc (Sur) and its support to the company’s performance management and decision making processes”.

I selected this topic for the following reasons which make me feel more comfortable with and confident to successfully complete this research compared to the other ones.

A subject matter, concerning my company, in which I wanted to see improvement

It is within my area of expertise I found sufficient amount of relevant literature My employer found the topic relevant and promised to provide all the

necessary support including access to relevant data and use of office facilities for this purpose

It gives me the opportunity to demonstrate IT skill

Besides I have observed that in Sur this issue is not given due attention. I believe that by conducting the research I may come out with relevant findings that might help my company improve its budgetary practices. Similar companies in my country (Ethiopia) may also find the work useful.

The focus organisation:

The focus organisation is “Sur Construction Plc”. I selected Sur because:

I have secured permission of access to relevant information and full support in material, financial and moral from my employer to undertake the research

I could save time and cost of securing relevant information from other companies and allow me devote more time on analysis of data collected

It would help me demonstrate my capability of doing research relevant to my company and thus promote myself

1.2. Project objectives and research questions

The objectives of the research are: To evaluate the budgetary control system of Sur for adequacy in its design

and implementation

1

Page 2: RAP ... combined

To identify the links of the budgetary control system with performance management and decision making processes within Sur.

To give recommendation on the system based on findings of the study.

To achieve the objectives stated I would evaluate the budgetary control system by dividing it in to its components i.e.

Administration Preparation Control

Research questionsThis study tries to address the following basic questions: How good was the budget administration in Sur? How good was the budget preparation in Sur? How good was the budget control in Sur?

Assessment variables The following variables which are believed to be indicators of existence of good budgetary control system and its links with the company’s performance management and decision making process were considered:

Does Sur have a budget committee, set a budget year, appoint a budget officer, and conduct follow up?

Does Sur communicate policies, determine key budget factor, prepare budgets based on key budget factor, coordinate individual budgets, use approved master budget as a benchmark? What type of budget does Sur prepare?

Does Sur produce performance reports, perform variance analysis, and how frequent? Does Sur use feedback for performance evaluation and decision making?

1.3. Overall research approachPlace of the researchAn author (Oliver, 2004, p. 126) has discussed on the necessity of indicating ‘location for the research’. The research is being conducted within the organisation in my office and for this I have already obtained the necessary permission from the relevant authority.

Structure of the research ProjectThe structure followed for the Research Project is the one recommended by the Oxford Brooks University as it is devised to enable students ‘demonstrate all of the required technical and professional skills, and graduate skills in sufficient depth’ (OBU Information Pack, 2008, p. 26); so I do not want to risk this opportunity by developing another different structure which may or may not demonstrate the stated quality.

2

Page 3: RAP ... combined

Scope The project is limited to Sur Construction plc, covered 2007/2008 budget year, and only the variables identified above were used to evaluate the budgetary control system and its contribution to company performance management and decision making. Capital budgeting and cash budget were not covered.

Information GatheringType of Data usedOnly secondary data were collected for my research project and both external and internal sources of secondary information were used to evaluate the budgetary control system for its design and implementation and also for its links with the company’s performance management and decision making activities.

In case secondary data is not available on certain areas of the system discussion and even oral or written interview with appropriate officials would be conducted.It is also necessary to mind that reliance on secondary data is wholly acceptable by the Oxford Brookes University, so why spend more time in collecting and evaluating primary data.

Sources of Data(See Part 2 section 2.1)

Method of collecting (See Part 2 section 2.2)

Analysis:Data analysis will be made based on whether: Standard costing, i.e. forecasted resource price and usage, and cost

prediction methods were used Key budget factor was defined All employees participated in preparing the budget Activities were coordinated Master budget was agreed and authorised The budget was used as a benchmark Regular performance reports and variance analysis made Influence in enhancing performance management and decision making Purposes of the system were achieved.

Finally Conclusion and Recommendation will follow based on results of the analysis made above.

3

Page 4: RAP ... combined

PART 2 - Information gathering and accounting/business techniques-1500 words

2.1. The sources of information from which relevant data obtained

The research mainly requires demonstration of skills of evaluating and analysing of data collected. Besides, use of secondary data for the research is acceptable by the Oxford Brookes University. As a result secondary data were obtained from: literature reading materials i.e. books, articles and relevant resources in the

internet listed in the “references” section of this paper. These would be sufficient enough to set criteria on which to base the evaluation

internal information on the administration, preparation and control aspects of the company’s budgetary control system would be sufficient enough to understand the overall picture of the system and reach conclusion.

In case when secondary data were found to be inadequate or unavailable, discussions were made with the cost and budget officer, the planning and monitoring officer, with commercial and construction department heads, and the general manager.

External Sources of information Relevant Literature books, articles and internet resources

Internal sources of information Company organizational Chart (See Appendix A) Formal letters of instruction to establish budget committee, letters of

appointment issued to individual members of the budget committee and budget officer

Company budget manual, budget policies, strategic or long-term plan, and approved master budget for the year 2007/2008

Periodic performance reports (monthly, quarterly and annually) Variance analysis on performance reports Minutes of meetings made to follow up budget implementation, to evaluate

performance and to make corrective and review decisions Documented decisions taken by management (minutes and letter of

instructions)

2.2. A description of the methods used to collect information, including online access In collecting information I followed the following steps:1. Identify locations of sources of information2. Reach locations to collect the information 3. Arrange appropriate safe custody for information collected

4

Page 5: RAP ... combined

4. Return on completion of the research those sources of information back to their location.

Location for external sources of informationMost of the Literature Books were collected from the British Council Library. Books from friends and my own texts were also used for the research. The ACCA Student Accountant was also an important source of published articles on subjects that provide guidance on how to pass the RAP and on subjects related to budgetary control and variance analysis techniques.The internet particularly the www.accaglobal.com and www.google.com websites were also very helpful locations for sources of relevant information. I have downloaded The RAP information PACK , an important document that guides how to approach the research, from the www.accaglobal.com and other internet resources related to research methods were collected from the www.google.com

Location for internal sources of informationThe following were among the most important internal sources of information for the study:

The commercial department is responsible for getting business for the company and facilitates the planning and monitoring processes within the company. Standard prices and usage of resources and total revenue for the year were determined by this department.

The planning and monitoring division which is under the direct supervision

of the Construction Department, maintained records related to planning and control information on project contracts, was another major source of information in relation to project plans and periodic performance reports.

The cost and budget division which is under the direct supervision of the Finance Department Manager produced financial reports in relation to cost of construction of each project contracts. The annual action plan for 2007/2008 was obtained from the finance department manager.

The Human resources department is also an important location of information sources such as the appointments of the budget committee and the budget officer. Also sources of information in relation to performance related pay is located in this department.

Reach locations to collect informationAs I am a member of the British Council Library I borrow books for my research. I have access to broadband internet service in my office.

In order to reach the locations of internally produced information I have formally obtained permission from the general manager to have access to relevant information of the company. I personally discussed with the personnel in charge

5

Page 6: RAP ... combined

of the locations I have identified above and therefore collected information I needed for my project. Arrangements were made to meet these individuals to discuss how and when they could supply me the information I needed. I gave them a note of list of data that I needed.

Arrange appropriate safe custody for information collected I arranged a shelf with a locker and safely stored notes of discussions made with different officials of the company and copies and original documents obtained many of which I had to return to the providers after completion of the research. The discussion notes and other documents collected were classified by nature and location and filed in a box file.

Return of secondary information back to their location on completion of the researchAfter completion of the study, I returned all documents and books collected from the company, the British Council and other sources as promised. I kept some copies of the aforementioned sources which are not restricted by copyright for further references.

2.3. A discussion of the limitations of the information gathering Listed below are some of the major limitations I observed and faced in connection with the information gathering process i.e. use of secondary data as source of information: Accuracy of information collected from the company itself cannot be

guaranteed as they are originally gathered by other people. Finance and construction departments produced separate profit and lose

statements for 9 months and their reports have differences. There were two different copies of budget manuals. None of the two

manuals were stamped as final. After a discussion with the finance department manager this problem was solved.

Differences in figures were also observed on planned project revenues reported in the three year business plan compared with the annual action plan.

Annual financial reports were not finalised. Information gathering from the internet was easy but difficult to determine

the most relevant resource out of bulk of resources. Sometimes it was of time taking activity compared to its benefit.

Information collecting encountered me with different officials within the company. Not all were comfortable with providing data to me as many of the data were prepared by themselves.

Another problem was that there was no formally documented students’ previous work on RAP which could have helped in assessing the overall effort required and could have helped raise confidence.

6

Page 7: RAP ... combined

Also there was problem with some staff members in keeping the appointment date to provide me necessary document. For example, the planning and division officer was out of office for training.

2.4. Identification of any ethical issues that arose during information gathering and how they were resolved

The ethical issues involved with my research project were mainly in relation to integrity and confidentiality of information of the company.

Ethical issues related to integrity Conducting the research on Sur Construction plc Using company facilities such as personal computer, stationeries and my

officeEthical issues related to confidentiality Disclosing information of Sur in my Research Project which can be accessed

by my examiners at Oxford Brookes University. Presenting my research to my mentor, an outsider. Keeping confidentiality of information

These were the ethical issues I tried to properly deal with. I obtained proper permission from my employer in dealing with disclosure of information with in my research project and uses of my employer’s resources.

2.5. An explanation of the accounting and / or business techniques you have used, including a discussion of their limitations.

The accounting techniques and models the company will apply are: Standard costing: used to set standard costs and usage of resource to

enable prepare plan and evaluate performance against these standards. Their limitation is that they are subject to changes caused by external and internal factors.

Responsibility Accounting: help assign tasks to a manager and make the manager accountable for the task. It is however difficult to accurately separate one activity of a manager from the other particularly in relation to overhead costs.

Percentage Completion Method: it is a method of calculating revenue for the year based on actual costs incurred in relation to contract revenue. But it has failures in accurately calculating revenue earned for the period because actual costs incurred may not be equal to plan.

Flexible budget and Variance analysis: help identify causes of deviations and make accountability easier. Involve complex calculations and may be are very costly to operate.

I expect the company uses these techniques in preparing budget and evaluating actual performances. My job in this case is to investigate whether these

7

Page 8: RAP ... combined

techniques were adequately applied to support the preparation of budget and its evaluation against actual results. In doing so I use analytical procedures, comparison and examination methods.

8

Page 9: RAP ... combined

PART 3 - Results, analysis conclusions and recommendations-4000 words

Background of Sur Construction plc

Sur Construction is a private limited company established in January 1992 G.C. and engaged in construction industry. The company’s current business involves road, building and airfield construction. Sur is one of the biggest construction companies in Ethiopia.

Sur is owned by EFFORT (Endowment Fund for the Rehabilitation of Tigray) a rehabilitation local institution. At present, the company’s annual turnover is approximately US$ 35million. It owned nearly US$ 30 million worth of medium and large size civil construction and earth moving equipment.

Currently the company has 1600 permanent employees and about 6700 workers hired on daily basis. Currently it ran 15 projects, and 3 projects located within Addis Ababa, the location of the company’s head office. 12 of the projects are located in different parts of the country out of Addis Ababa.

On 26 March 2008, Sur Construction plc was awarded ISO: 1900:2000 by Deutsche Gesellschaft fur Technische Zusammenarbeit (GTZ) GmBH, which certifies quality system to conduct Road, Building, Airfield, Hydro Power, Irrigation and Water Supply.

In 2007/2008 the company was running 15 different projects comprising of 9 road projects, 5 building projects and an airfield project.

Company mission To perform its construction activities efficiently and effectively To understand customers’ need and ensure their satisfaction To ensure profitability for the owners

3.1. A description of the results you have obtained and any limitations

Information has been gathered in relation to the assessment variables identified in PART I and the findings are presented in the following sections.

Administration of the budgeting process

The budget period of Sur Construction plc is 1st July to 30th of June. The company has developed a budget manual through consultants known as Tradesmen Engineering (pvt) LTD, an international company.

With in the manual a number of policies and procedures concerning administration and preparation of a budget are adopted. This manual also indicated the necessity of forming a budget committee, a budget controller and

9

Page 10: RAP ... combined

developing and reviewing a budget manual to help proper execution of budgetary control within the company. However no budget committee as well as budget controller were formed so far by the company.

Annual Action Plan Preparation

The company did not prepare a budget in 2007/2008 budget year. It rather prepared company wide annual action plan which included detailed activities that should be undertaken by each department without expressing the resources requirement for departments other than the construction department and the plan was not expressed in terms of money. The preparation process should have been made following manner as the budget manual has indicated:

10

1. Communication of planning policy

2. Key budget factor

3. Planned sales budget

4. Construction Plan

5. Preparation of individual annual plan

6. Review of individual annual plan

7. Acceptance of the agreed annual plan

8. Submitting the action plan to EFFORT for final approval

Page 11: RAP ... combined

1. Communication of planning guidelines

The commercial department of the company conducted industry analysis and gathered and recorded information on the market demand for construction, level of competition, costs of materials, etc which was important for determining contract cost when tendering for new incoming project contracts and for setting target revenue and costs for existing projects.

The department organised the preparation of the company annual action plan. In doing so the department had communicated to all responsible centres:

- the company three year business plan, - cost targets for each construction activity of both building and road

contract projects. (See Appendix B)

2. Determining the principal budget factor (Key constraint)

Traditionally Sur started its action plan from forecasting the level of revenue to be generated in the budget period. Therefore sales revenue was considered as key budget factor. No limiting factor analysis was undertaken.

3. Planned Revenue TargetIn its three year business plan the company determined the level of revenue to be generated for the year 2007/2008. The plan considered:

the information gathered in relation to the industry, the volume of work at hand, time of completion of existing project contracts and expectations of new contracts completion period of projects

Accordingly the revenue for the year 2007/2008 was forecasted to be Br.650million which is Br.50million less than the forecast made in the three year business plan. The decrease in planned revenue was because one project contract was excluded from the annual plan.

An extract from the business Plan

11

Page 12: RAP ... combined

Table 1: Three Years Company Goals on Yearly Basis (Amounts are In Ethiopian Birr)Figures are in millions (Birr 000,000)

Serial No. DESCRIPTION

BUDGET YEARTOTAL2007/08 2008/09 2009/10

1PLANNED SALES FOR EXISTING CONTRACTS 629.63 338.39 0.48 968.51

2PLANNED SALES FOR NEW CONTRACTS 70.37 461.61 999.52 1,531.49

TOTAL PLANNED SALES 700.00 800.00 1,000.00 2,500.00

YEARLY SALES GROWTH (%)

- 14.29 25.00

3PLANNED COST FOR EXISTING CONTRACTS 614.47 318.55 0.44 933.46

4PLANNED COST FOR NEW CONTRACTS 63.33 415.45 899.56 1,378.34

TOTAL PLANNED COSTS 677.80 734.00 900.00 2,311.80

5PLANNED PROFIT FOR EXISTING CONTRACTS 15.16 19.84 .05 35.05

6PLANNED PROFIT FOR NEW CONTRACTS 7.04 46.16 99.95 153.15

TOTAL PLANNED PROFIT 22.20 66.00 100.00 188.20PROFIT MARGIN (%) 3.17 8.25 10.00 7.53

7FORECASTED NEW CONTRACT ENTRIES 500.00 800.00 800.00 2,100.00

Amounts are in Ethiopian Birr

4. Construction PlanThe construction department ran 15 project contracts (9 road, 5 building and one airfield projects) which were considered as a sub-responsibility centres and each were accountable to the construction department manager. Managers of the project contracts had produced and submitted their own action plan to the construction department manager to be integrated into the department’s plan.

Therefore construction department prepared the annual action plan that showed detailed activities to be conducted and the physical resources required to generate the forecasted revenue based on the revenue and cost targets determined by the commercial department.The department had listed all sorts of resources (Machineries of different types and capacities, materials and manpower) required to execute the construction work but not planned as to the timing of delivery and not expressed in terms of money (See Appendix C).

Following is a brief explanation of how the remaining major departments prepared their annual plan.

12

Page 13: RAP ... combined

5. Prepare initial annual action plan In preparing the annual action plan all managers including lower level managers participated in the planning process, the process followed was bottom-up approach. The company applied responsibility accounting to evaluate each department and service manager’s performance.Each department and service within the company was considered as a responsibility centre. Therefore each department and service was responsible for the preparation of their own annual action plan and submitted their annual plan to the commercial department. The commercial department combining the individual annual plans together presented to the general manager for review in the management meeting.

Equipment Management DepartmentThis department established targets such as available hours of machineries, serviceability of machineries, hourly maintenance cost of machineries, maximum number of accidents for machineries, and labour costs of involved. But the plan did not indicate the total number of machineries in different capacities needed for the year including the resources required in terms of manpower, spare parts, fuel, etc to operate and maintain the Machineries.

Logistics Department The action plan of this department focused on setting the purchase and distribution cycle of local and foreign procurement of materials and services. That is the days that will be taken to purchase the materials or services requested and distribute them to user departments. However, program of purchases and distribution was not made at all. (See Appendix D)

Finance DepartmentThis department had indicated in its annual action plan that Ethiopian Birr 182 million cash deficit for the year 2007/2008 and identified possible sources of finance. Out of which EFFORT (the owners) were expected to raise Birr 100million and sister companies (other companies owned by EFFORT) were expected to raise Birr 47.5 million in the form of credit supply and services. Birr 32 million was expected to be obtained from external credit suppliers. The plan however didn’t show in detail how it arrived at such cash deficit. The plan also detailed the ongoing accounting activities to be done in the year without preparing financial statements (See Appendix E)

Table 2. Working Capital Financing for 2007/2008 (Millions of Birr)

13

Page 14: RAP ... combined

No. Type of finance Sources Amount1 Capital injection EFFORT 100.002 Cement Credit Facility Messebo* 30.003 Iron-Bar Credit Facility Guna Trading* 15.004 Tyre Credit Facility Pirelli-Trans* 1.505 Transport credit TEPLCO* 1.00

6 machinery rent credit External Supplier 10.007 Other credit supplies External Supplier 10.00

8 Advance lease purchase agreement External Supplier 12.00

Total 179.50Note: * Other Companies owned by EFFORT  

The above table presented in a pie chart below:

Source of Working Capital Financing for the year 2007/2008 Amount in Birr (000,000)

147.50

32.00

1 Internal 2 External

Human Resource DepartmentThis department had set targets for manpower recruitment and turnover. Recruitment duration in days was determined for different levels of positions and the minimum rate of labour turnover was set.

6. Annual action plan submission, acceptance and approval (steps 5 to 8)Finally after all departments and services delivered their annual plan, an agreed and approved company annual action plan was produced and it was sent on 20th of June 2007 to the management of EFFORT, the owner of Sur. EFFORT approved the plan as final action plan for the year on August 2007.

14

Page 15: RAP ... combined

ControlPerformance reports were produced monthly, quarterly, semi-annually and annually by all responsibility centres. Construction works were the core tasks of the company. Project managers were responsible to conduct daily monitoring in all aspects of their project activities, and reported to each respective department at head office.Projects’ construction work execution related performance reports were directly submitted to the planning and monitoring division. Cost and accounting related reports from projects were submitted to cost and budget division. The divisions produced separate reports of profit and lose statement of all 15 projects and presented the combined reports to their respective department managers. The reports produced by cost and budget division did not show comparison of budget with actual results. It only reported what is actually incurred cost against revenue calculated based on percentage completion method.

The planning and monitoring division however produced comparison of actual against planned works though it did not include detailed variance analysis to identify causes of variances to support management decision making. Comparison was made between plan and actual results, and arrived at variance. The variance stated in both absolute and relative terms did not consider changes in volume, price and usage. Therefore it was so difficult to make managers accountable for failures in achieving plans as the reports were not detailed enough in identifying causes and responsible managers to specific variances. (See Appendix F)

Budget Review and corrective actionActions are taken on an ad hoc basis not based on proper variance analysis conducted by the company’s staffs. Also managers are not made accountable for their actions taken.

3.2. A critical analysis / evaluation of your results which includes an explanation of your significant findings

Budgetary Control

Budgetary control is concerned with ensuring that actual financial results are in line with targets. An important part of this feedback process is investigating variations between actual results and budgeted results and taking appropriate corrective action (Collier, 2003, p. 225).

A budget is a plan expressed in monetary terms covering a future time period (typically a year broken down into months). (Collier, 2003, p. 207)

15

Page 16: RAP ... combined

From this definition of a budget it can be concluded Sur didn’t prepare budget for the year 2007/2008. But prepared a plan of physical activities to be performed with in the year and divided into monthly action plans.

Budget Administration‘It is important that suitable administration procedures be introduced to ensure that the budget process works effectively’ (Drury, 2004, p. 596)

The Company budget manual has clearly stated the necessity of establishing budget committee and budget controller (officer). It defined the roles and types of officials that should be members of the committee and the budget officer. However both the budget committee and budget controller were not appointed to administer the budgeting process, as a result:

No body within the company considered responsibility to enforce the preparation and implementation of a budget

Adequate planning couldn’t be enforced and a budget expressed in monetary terms could have been prepared in the year.

Coordination and communication of activities of departments within the company could have been achieved

The company failed to set benchmark against which to evaluate actual performance

Budget Preparation It was made clear above that Sur did not prepare a budget for the year 2007/2008. However, it was necessary to evaluate the existing budgetary control system of the company based on literature. Sur had prepared an annual action plan for the year 2007/2008 and analysis is made on the information gathered to reach conclusion and give recommendation.

Policy Communication

The long-term plan is the starting point for the preparation of the annual budget. Managers responsible for preparing the budget must be aware of the way it is affected by the long-term plan so that it becomes part of the process of meeting the organisation’s objectives. (BPP Professional Education, 2006, p. 168)

Three year business plan and standard cost, an estimated unit cost built up of standards for each cost element and usage of resources were communicated to construction department and other departments to be used as a basis for the preparation of their annual plan.

Key budget factor and sales forecast‘In every organization there is some factor that restricts performance for a given period’ (Drury, 2004, p. 597)

16

Page 17: RAP ... combined

This factor is known as limiting factor or key budget factor. Sur had not conducted constraint resources analysis to identify the limiting factor before it started preparing its annual plan. It determined sales to be the limiting factor as a matter of traditional practice. However, during the budget year Sur faced serious cash shortage and could not buy essential asphalt machineries and construction materials as needed. This caused to the company both financial and reputation damage. Had proper limiting factor analysis been conducted and the limiting factor identified and the annual plan was based on the identified factor Sur would have been able to revise its forecasted revenue to a more realistic forecast reducing its commitments to the maximum level of cash resources Sur could have generated and also would spend the limited cash resource on activities that give highest contribution per unit of limited resource.

As a result the forecasted revenue of Birr 650 million for the year was much exaggerated compared to the actual revenue achieved Birr 425 million, which is only 65%, as reported by the construction department in the annual report (See Appendix G).

Construction plan

When the sales budget has been completed, the next stage is to prepare the production budget. This budget is expressed in quantities only and is the responsibility of the production manager. The objective is to ensure that production is sufficient to meet sales demand and that economic stock levels are maintained. (Drury, 2004, p. 604)

Normally units of construction works are measured by types of activities such as excavation and earth work, concrete ancillaries, masonry work etc relevant to building construction and clearing and grubbing, drainage, demolishing, removal etc relevant for road (see Appendix H) involved in each construction types- road, building and airfield. The construction department failed to prepare plan of total units of construction activities for 2007/2008. This hindered reasonably accurate determination of materials, machineries and labour usage for the year.

However, the department had determined the total quantities of usage of materials, machineries and labour needed for the year without indicating how it arrived at such quantities of resources requirements. Also it did not indicate the level of ending inventories required during the year for each type of resources.

Direct Materials Purchase Plan‘The raw materials budget is necessary to ensure adequate materials are available to meet the production needs on a timely basis’ (Berry, 2006, p. 226)

17

Page 18: RAP ... combined

The logistics department did not prepare material purchase plan. The possible reason could be as the logistics manager explained the material requirements prepared by the construction department were not time scheduled and their accuracy was not reliable because there was no proper plan of the unit volume of construction works.It was also difficult to prepare direct labour and overhead budgets because unit volume of construction work was not determined. However, selling and administrative costs were planned based on past performance.

As a result the total material usage forecasted by the construction department remained unchanged into monetary requirements. Therefore sufficiently detailed and integrated company annual plan (master budget) could not be produced in the 2007/2008 budget year and financial performance indicators such as ROCE percentage, profit margin, and liquidity ratios could not be determined to evaluate the company’s financial performance.

Control At this point the budgetary control system would be evaluated for its links with the company’s performance management and decision making.

Existence of appropriate budgetary control system would have helped to provide benchmarks to be achieved in terms of financial and physical objectives with in the budget period; and helped financial objectives to be expressed in absolute terms as well as in relative terms. Amount of sales volume and profit level could have been determined and then a budget prepared. Relative measures such as financial ratios could have been set for that year to measure managements’ performance.

Budgetary control could have been helped to set measures in terms of physical targets such as kilometers of roads, materials and labour usages. Based on such measures the budgetary control system, supported by adequate cost accounting records, would have provided benchmark against which managers’ performances would be measured. In that the system would have served as part of the performance management system. By giving feedback on deviations it would have supported management to focus on problem areas (management by exception) rather than try to control all aspects of operations that went smooth. The feedback from a budgetary control system would have contributed a lot to management decision making either by enabling them to enhance or correct future performances.

The two separate main performance reports used for control were one produced by construction department and the other by finance department. Periodic revenue and cost performance reports produced by construction department were made based on engineers’ estimated executed construction works. The same report produced by finance department was based on

18

Page 19: RAP ... combined

percentage completion method. These reports for the same period had material differences in amounts. The construction department relied on its own records in producing information on revenue and cost, and produced its own profit and loss statement for each project contracts and never used the cost accounting records of finance department believing that it did not produce accurate information.

Flexible budget enable us make a more valid comparison between the budget (using the flexed figures) and the actual results. Key differences, or variances, between budgeted and actual results for each aspect of the business’s activities can then be calculated (Atrill and McLaney, 2007, p. 213).

However the comparisons of plan versus actual performance made by the construction department did not assume changes in volume and price. Therefore flexible budgeting was not applied by the company in comparing actual results with plan. Also variance analysis was not used at all. Therefore no valid comparison of actual against planned performance could be made and the planning process of the company failed to support performance management and decision making of the company.

The company’s finance department produced reports only on actual revenue and costs because there was no budget prepared for comparison.

3.3. Your conclusions about your research findings and how well you have met your project objectives and research questions

StrengthThe company developed a budget manual, which contains detailed policies and procedures on budget administration, preparation and implementation.

The company also obtained experience in developing a three year business plan for the budget years 2007/2008, 2008/2009 and 2009/2010. Standard costs and usage of resources were also established for the year 2007/2008 and communicated to all departments and services. Though the business plan and the standards set failed to serve their purpose in helping the planning and control process.

WeaknessThe budget manual was not implemented at all. And the annual plan was full of assumptions that never based on the company’s reality in terms of available resources in the short term; as it did not perform scarce resource (limiting factor) analysis to identify the company’s reality in terms of the limiting factor and make best use of scarce resources.

Also unit volume of construction work for the year was not determined by the construction department. Even the haphazard forecast of total resources

19

Page 20: RAP ... combined

requirement included in the annul plan of the construction department was not planned as to their timing when they should be made available to the department causing other departments not to properly plan their support activities to the construction department. For example, the logistics department could not determine materials purchase plan (budget) and the finance department could not determine the level of financial resources to be made available at the right time and in the level of amount required.

The planning and control process was weak in that adequate benchmark could not be put in place. The support that would have been provided by the budgetary control system in enhancing the company’s performance management system and decision making process failed to be achieved.

EffectThe company failed to enforce adequate preparation and implementation of a budget by not giving due management attention to the issue and by not appointing budget committee and budget accountant who could have facilitated this. Therefore the company could not produce a budget in the year 2007/2008.

This in turn resulted in disintegration of the activities of the departments causing each department to mind only its own activities rather than coordinating to achieve common company goals. Also causes disputes among departments. For example, there were instances in which it was difficult to identify responsible manager for a delay in supply. Such an environment also created lack of motivation in many of the managers in the company.

Lack of scarce resource analysis also caused the company to forecast an exaggerated volume of sales compared to its available financial resource and skilled and capable manpower (e.g. poor planning). This was another source of less management motivation as the revenue target was unachievable.

Not exercising proper monitoring and control activities also caused management not to access proper feedback on performance resulting weak decision making and poor performance management. This was substantiated by the poor cost-revenue relationship. Conclusion In conclusion the company’s budgetary control system was weak in its design and implementation and failed to achieve the very purposes of the system such as compel planning, facilitate communication and coordination and managers’ motivation.

As a result the system as part of Sur’s performance management failed to enhance managers’ performances and decision making.

20

Page 21: RAP ... combined

The information gathered and analysed were sufficient enough to answer my research questions on the selected three main criteria i.e. administration, preparation and control. The conclusion reached also was based on the findings observed therefore I believe my research objectives were reasonably answered.

3.4. If appropriate, recommendations on specific courses of action to identified individuals within your chosen organisation.

Recommendations

To the company’s General Manager

Budget AdministrationAppropriate management attitude and attention would help design and implement adequate budgetary control system in the company. PreparationThe general manager has to make sure timely preparation of budgets, as chairman of the budget committee.

ControlEnhancement in the budget administration and preparation would improve control. Attention has to be given to improve the cost accounting records.

The improvement in the budgetary control system is to aid the general manger’s ability to manage performance and make informed decision. Therefore it is necessary for the general manager to emphasize in adopting adequate budgetary control system.

References

21

Page 22: RAP ... combined

Atrill, P. and McLaney, E. (2007) Management Accounting for Decision Making. Madrid: FT Prentice Hall –Financial Times.

Berry, Leonardo Eugene. (2006) Management Accounting DeMYSTiFied. USA: McGraw-Hill Companies.

BPP Professional Education. (2006) Financial Management and Control-2.4. Great Britain: BPP professional Education.

Collier, M. Paul. (2003) Accounting for Managers. Great Britain: John Wiley & Sons Ltd.

Drury, C. (2004) Management and Cost Accounting. China: Thomson Learning.

Oliver, P. (2004) Writing your thesis. Great Britain : SAGE Publications.

Bibliography

Charles T. Horngren, Srikant M. Datar and George Foster. (2003) Cost Accounting a Managerial Emphasis. New Jersey: Pearson Education International

Charles T. Horngren, Gary L. Sundem and William O. Stratton. (2002) Introduction to management Accounting. New Jersey: Pearson Education Inc.

Eddie McLaney and Peter Atrill. (2005) Accounting an Introduction. Madrid: Pearson Education Limited.

FTC Kaplan Limited. (2007) Advanced Performance Management (APM): Paper P5. Great Britain: KAPLAN Publishing.

Graham Holt. (2003) ‘Research and Analysis: a formula for success’, Student Accountant, October, pp. 24-26.

Shane Johnson. (2005) ‘Beyond Budgeting’, Student Accountant, March, pp. 68-71.

Shane Johnson. (2005) ‘how not to rap’, Student Accountant, June/July, pp.26-28.

Swetnam, Derek. (2004) Writing your Dissertation. Trowbridge, Wiltshire: How To Books Ltd.

Internet Sources Used