GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA UNSTARRED QUESTION NO.1691 ANSWERED ON 12.03.2013 GAS-BASED POWER PROJECTS IN THE COUNTRY 1691. SHRI N. BALAGANGA: SHRI P. BHATTACHARYA: Will the Minister of POWER be pleased to state: (a) the details of the gas-based power projects currently operational in the country, State- wise; (b) the details of the generation capacity of each such plants, during the last two years, year- wise, plant-wise and State-wise; (c) the steps being taken by Government to augment electricity generation from the gas based power plants; (d) whether Government considers to set up more gas-based power projects in the country; and (e) if so, the details thereof, including those planned to be set up in Tamil Nadu and West Bengal? A N S W E R THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a) : Details of gas based power projects currently operational in the country, State- wise are given at Annex-I. (b) : The details of the generation capacity of each plant, during the last two years, State-wise is at Annex–II. (c) : Government is trying to augment gas for existing stations by taking steps to increase domestic production of gas in the country and facilitating import of Re-Gasified Liquefied Natural Gas (RLNG) in the country. (d) : Government of India does not set up power plants. (e) : In view of (d) above does not arise. ********

RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

  • Upload
    buinhu

  • View
    223

  • Download
    5

Embed Size (px)

Citation preview

Page 1: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA

UNSTARRED QUESTION NO.1691 ANSWERED ON 12.03.2013

GAS-BASED POWER PROJECTS IN THE COUNTRY

1691. SHRI N. BALAGANGA:

SHRI P. BHATTACHARYA: Will the Minister of POWER be pleased to state: (a) the details of the gas-based power projects currently operational in the country, State-wise; (b) the details of the generation capacity of each such plants, during the last two years, year-wise, plant-wise and State-wise; (c) the steps being taken by Government to augment electricity generation from the gas based power plants; (d) whether Government considers to set up more gas-based power projects in the country; and (e) if so, the details thereof, including those planned to be set up in Tamil Nadu and West Bengal?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA )

(a) : Details of gas based power projects currently operational in the country, State-wise are given at Annex-I. (b) : The details of the generation capacity of each plant, during the last two years, State-wise is at Annex–II. (c) : Government is trying to augment gas for existing stations by taking steps to increase domestic production of gas in the country and facilitating import of Re-Gasified Liquefied Natural Gas (RLNG) in the country.

(d) : Government of India does not set up power plants.

(e) : In view of (d) above does not arise.

********

Page 2: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

ANNEX-I

ANNEX REFERRED TO IN REPLY TO PART (a) OF UNSTARRED QUESTION NO. 1691 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

*********** Gas based power plants in Country

Sl. No. Name of Power Stations Installed Capacity (in MW)

Located in State

Existing Stations Central Sector

1 Faridabad CCPP 431.59 Haryana 2 Auraiya CCPP 663.36 Uttar Pradesh 3 Dadri CCPP 829.78 Uttar Pradesh 4 Ratnagiri CCPP 1967 Maharashtra 5 Uran CCPP 672 Maharashtra 6 Trombay CCPP 180 Maharashtra 7 I.P.CCPP 270 Delhi 8 Pragati CCGT-III 1000 Delhi 9 Rithala CCPP 108 Delhi

10 Pragati CCPP 330.4 Delhi 11 Dholpur CCPP 330 Rajasthan 12 Anta CCPP 419.33 Rajasthan 13 Ramgarh CCPP 113.8 Rajasthan 14 Dhuvaran CCPP 218.62 Gujarat 15 Hazira CCPP Ext. 156.1 Gujarat 16 Gandhar CCPP 657.39 Gujarat 17 Kawas CCPP 656.2 Gujarat 18 Hazira CCPP Ext. 351 Gujarat 19 Utran CCPP 518 Gujarat 20 Vatwa CCPP 100 Gujarat 21 Baroda CCPP 160 Gujarat 22 Essar CCPP 515 Gujarat 23 Peguhtan CCPP 655 Gujarat 24 Sugen CCPP 1147.5 Gujarat 25 Karaikal CCPP 32.5 Puducherry 26 Kovikalpal CCPP 107 Tamil Nadu 27 Kuttalam CCPP 100 Tamil Nadu 28 Karuppur CCPP 119.8 Tamil Nadu 29 P.Nallur CCPP 330.5 Tamil Nadu 30 Valantarvy CCPP 52.8 Tamil Nadu 31 Valuthur CCPP 186.2 Tamil Nadu 32 Kathalguri CCPP 291 Assam 33 Lakwa GT 157.2 Assam 34 Namrup CCPP 95 Assam 35 Namrup ST 24 Assam 36 DLF Assam GT 24.5 Assam 37 Baramura GT 58.5 Tripura

 

………..2.

Page 3: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

- 2 -

38 Agartala GT 84 Tripura 39 Rokhia GT 90 Tripura 40 Gautami CCPP 464 Andhra Pradesh 41 GMR Energy Ltd 220 Andhra Pradesh 42 Godavari CCPP 208 Andhra Pradesh 43 Jegurupadu CCPP 455.4 Andhra Pradesh 44 Konaseema CCPP 445 Andhra Pradesh 45 Kondapalli Ext. CCPP 366 Andhra Pradesh 46 Kondapalli CCPP 350 Andhra Pradesh 47 Peddapuram CCPP 220 Andhra Pradesh 48 Vemagiri CCPP 370 Andhra Pradesh 49 Vijeswaran CCPP 272 Andhra Pradesh 50 Sriba Industries 30 Andhra Pradesh 51 RVK Energy 28 Andhra Pradesh 52 Silk Road Sugar 35 Andhra Pradesh 53 LVS Power 55 Andhra Pradesh

Grand Total 17721.47 MW- Mega Watt CCPP- Combined Cycle Power Plant NR-Northern Region WR-Western Region GT-Gas Turbine NER-North East Region CCGT-Combine Cycle Gas Turbine MU- Million Units  

*********** 

Page 4: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

ANNEX-II

ANNEX REFERRED TO IN REPLY TO PART (b) OF UNSTARRED QUESTION NO. 1691 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********

Gas based power plants in Country Sl. No.

Name of Power Stations

Installed Capacity (in MW)

Located in State Gen (MU) in 2010-11

Gen (MU) in 2011-12

Existing Stations Central Sector

1 Faridabad CCPP 431.59 Haryana 3155.4 3067.72 2 Auraiya CCPP 663.36 Uttar Pradesh 4369.34 3878.62 3 Dadri CCPP 829.78 Uttar Pradesh 5399.88 5376.07 4 Ratnagiri CCPP 1967 Maharashtra 11876.85 11619.08 5 Uran CCPP 672 Maharashtra 5587.39 4668.78 6 Trombay CCPP 180 Maharashtra 1568.79 1567.9 7 I.P.CCPP 270 Delhi 1368.32 1243.72 8 Pragati CCGT-III 1000 Delhi 6.09 331.38 9 Rithala CCPP 108 Delhi 88.8 241.83

10 Pragati CCPP 330.4 Delhi 2335.78 2560.05 11 Dholpur CCPP 330 Rajasthan 1994.87 2253.77 12 Anta CCPP 419.33 Rajasthan 2487.9 2694.6 13 Ramgarh CCPP 113.8 Rajasthan 301.13 536.79 14 Dhuvaran CCPP 218.62 Gujarat 891.38 1008.7 15 Hazira CCPP Ext. 156.1 Gujarat 1022.81 907.62 16 Gandhar CCPP 657.39 Gujarat 4058.06 3684.07 17 Kawas CCPP 656.2 Gujarat 3882.14 3638.4 18 Hazira CCPP Ext. 351 Gujarat 0 0 19 Utran CCPP 518 Gujarat 2947.22 2987.98 20 Vatwa CCPP 100 Gujarat 670.53 459.26 21 Baroda CCPP 160 Gujarat 843.55 668.74 22 Essar CCPP 515 Gujarat 1443.7 135.89 23 Peguhtan CCPP 655 Gujarat 3667.45 3067.07 24 Sugen CCPP 1147.5 Gujarat 8216.99 7592.16 25 Karaikal CCPP 32.5 Puducherry 195.45 251.46 26 Kovikalpal CCPP 107 Tamil Nadu 663.76 705.75 27 Kuttalam CCPP 100 Tamil Nadu 172.58 413.29 28 Karuppur CCPP 119.8 Tamil Nadu 820.38 797.1 29 P.Nallur CCPP 330.5 Tamil Nadu 2494.06 1526.19 30 Valantarvy CCPP 52.8 Tamil Nadu 370.17 377.51 31 Valuthur CCPP 186.2 Tamil Nadu 547.67 1114.56 32 Kathalguri CCPP 291 Assam 1833.87 1765.17 33 Lakwa GT 157.2 Assam 766.25 771.99 34 Namrup CCPP 95 Assam 508.73 565.73 35 Namrup ST 24 Assam 21.08 0 36 DLF Assam GT 24.5 Assam 67.42 0 37 Baramura GT 58.5 Tripura 225.82 357.62

 

………2.

Page 5: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

 

- 2 -

 

38 Agartala GT 84 Tripura 644.1 666.1239 Rokhia GT 90 Tripura 443.5 419.140 Gautami CCPP 464 Andhra Pradesh 3331.07 2898.6741 GMR Energy Ltd 220 Andhra Pradesh 960.49 1200.0342 Godavari CCPP 208 Andhra Pradesh 1464.36 1282.4643 Jegurupadu CCPP 455.4 Andhra Pradesh 3094.23 2833.4944 Konaseema CCPP 445 Andhra Pradesh 2350.49 2266.2245 Kondapalli Ext. CCPP 366 Andhra Pradesh 2043.68 2203.5446 Kondapalli CCPP 350 Andhra Pradesh 2133.77 2030.9447 Peddapuram CCPP 220 Andhra Pradesh 1427.37 1318.8248 Vemagiri CCPP 370 Andhra Pradesh 2815.56 2066.8149 Vijeswaran CCPP 272 Andhra Pradesh 0 050 Sriba Industries 30 Andhra Pradesh 0 051 RVK Energy 28 Andhra Pradesh 0 052 Silk Road Sugar 35 Andhra Pradesh 0 053 LVS Power 55 Andhra Pradesh 0 0

Grand Total 17721.47 97580.23 92022.77 MW- Mega Watt CCPP- Combined Cycle Power Plant NR-Northern Region WR-Western Region GT-Gas Turbine NER-North East Region CCGT-Combine Cycle Gas Turbine MU- Million Units  

********** 

Page 6: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA

UNSTARRED QUESTION NO.1692 ANSWERED ON 12.03.2013

ONGOING POWER PROJECTS IN THE COUNTRY

†1692. SHRI BHUPENDER YADAV: Will the Minister of POWER be pleased to state: (a) the details of ongoing power projects in the country; (b) whether these power projects are constantly lingering behind the schedule; (c) whether the expenditure on these projects is continuously increasing owing to delay; and (d) the efforts being made by Government to complete the said projects in a time-bound manner?

A N S W E R THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a) to (c): 107 thermal projects and 50 hydro-electric projects are under construction in the country and details of these projects are enclosed at Annex-I and Annex-II, respectively.

The details of under construction thermal & hydro power projects lagging behind

their scheduled time of commissioning along with the cost overrun are enclosed at Annex- III & IV, respectively.

(d) : Several steps have been taken by the Government to speed up the commissioning of power projects in a timely manner to prevent cost escalation and meet shortage of power. These, inter alia, include constitution of a Task Force on Hydro Project Development to look into all issues relating to development of hydro-power including issues of rehabilitation and resettlement of project affected persons, constitution of an Inter-Ministerial Group (IMG) to evolve a suitable framework to guide and accelerate the development of hydropower in the North-East, setting up of a Power Project Monitoring Panel by the Ministry of Power to independently follow up and monitor the progress of the hydro/thermal projects to ensure that projects are executed in time and setting up of an Advisory Group under the Chairmanship of Hon’ble Minister of State for Power (Independent Charge) to discuss and deliberate periodically issues pertaining to the Power Sector and suggest reform in different areas related to the sector.

**********

Page 7: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

ANNEX-I

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (c) OF UNSTARRED QUESTION NO. 1692 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

*********** LIST OF THERMAL PROJECTS UNDER CONSTRUCTION IN THE COUNTRY AS ON 07-Mar-2013

Sl.No. Sector/State Project Name Unit Cap (MW). Anticipated Comm.Date

CENTRAL SECTOR 1 Assam Bongaigaon TPP U-1 250 Jun-14 U-2 250 May-15 U-3 250 Oct-15 2 Bihar Barh STPP- I U-1 660 Jun-15 U-2 660 Apr-16 U-3 660 Feb-17 3 Bihar Barh STPP-II U-4 660 Oct-13 U-5 660 Sep-14 4 Bihar Muzaffarpur TPP Exp U-3 195 Jun-14 U-4 195 Sep-14 5 Bihar Nabi Nagar TPP U-1 250 Jul-14 U-2 250 Jan-15 U-3 250 Jul-15 U-4 250 Jan-16 6 Jharkhand BokaroTPS "A"Exp. U-1 500 Aug-14 7 Karnataka Kudgi STPP Ph-I U-1 800 Aug-16 U-2 800 Oct-16 U-3 800 Mar-17 8 Maharashtra Mouda STPP-II U-3 660 Jul-16 U-4 660 Jan-17 9 Maharashtra Mouda TPP U-2 500 Mar-13

10 Maharashtra Solapur STPP U-1 660 Jul-16 U-2 660 Jan-17

11 MP Vindhyachal TPP-IV U-12 500 Mar-13 12 MP Vindhyachal TPP-V U-13 500 May-14 13 TN Neyveli TPS-II Exp. U-2 250 Mar-14 14 TN Tuticorin JV U-1 500 Dec-13 U-2 500 Mar-14

15 TN Vallur TPP-II U-3 500 Sep-13 16 Tripura Monarchak CCPP GT+ST 101 May-14 17 Tripura Tripura Gas Module- 363.3 Jul-13 18 UP Meja STPP U-1 660 Aug-16 U-2 660 Feb-17

19 UP Rihand TPP- III U-6 500 Nov-13 20 WB Raghunathpur TPP, Ph-I U-1 600 Jul-13 U-2 600 Mar-14 STATE SECTOR

21 AP Damodaram Sanjeevaiah U-1 800 May-14 TPS U-2 800 Nov-14

22 AP Kakatiya TPP Extn U-1 600 May-14 23 AP Rayalseema St-III U-6 U-6 600 Dec-15 24 Assam Namrup CCGT GT 70 Sep-13 ST 30 Dec-13

25 Chhattisgarh Korba West St-III. U-5 500 Mar-13 26 Chhattisgarh Marwa TPP U-1 500 Jun-13 U-2 500 Oct-13

Page 8: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

27 Delhi Pragati CCGT - III GT-4 250 Apr-13 28 Delhi Pragati CCGT - III ST-2 250 Jul-13 29 Gujarat Bhavnagar CFBC TPP U-1 250 Oct-14 U-2 250 Feb-15

30 Gujarat Pipavav CCPP Block-1 351 Jul-13 Block-2 351 Mar-13

31 Gujarat Sikka TPP Extn. U-3 250 Nov-13 U-4 250 Feb-14

32 Maharashtra Chandrapur TPS U-8 500 Sep-13 U-9 500 Dec-13

33 Maharashtra Koradi TPP Expn. U-10 660 Mar-15 U-8 660 May-14 U-9 660 Oct-14

34 Maharashtra Parli TPP Expn. U-8 250 Dec-13 35 MP Malwa TPP ( Shree Singaji TPP U-1 600 Jun-13 U-2 600 Dec-13

36 MP Satpura TPP Extn U-10 250 Mar-13 U-11 250 Jul-13

37 Rajasthan Chhabra TPP Extn. U-3 250 May-13 U-4 250 Sep-13

38 Rajasthan Kalisindh TPS U-1 600 Aug-13 U-2 600 Dec-13

39 Rajasthan Ramgarh CCPP Extn. -III GT 110 Mar-13 ST 50 Aug-13

40 TN North Chennai Extn, U-1 U-1 600 Jul-13 41 TN North Chennai Extn, U-2 U-2 600 Mar-13 42 UP Anpara-D U- 6 500 Feb-14 U-7 500 Jun-14

43 UP Parichha Extn U-6 250 Mar-13 44 WB Durgapur TPS Extn U-8 250 Dec-13 45 WB Sagardighi TPP-II U-3 500 Jul-14 U-4 500 Oct-14 PRIVATE SECTOR

46 AP Bhavanpadu TPP U-1 660 Oct-15 U-2 660 Mar-16

47 AP NCC TPP U-1 660 Mar-16 U-2 660 Sep-16

48 AP Painampuram TPP Cc U-1 660 Sep-14 U-2 660 Dec-14

49 AP Simhapuri Energy Pvt Ltd Ph.II U-3 150 Jun-13

U-4 150 Sep-13 50 AP Thamminapatnam TPP-I U-2 150 Mar-13 51 AP Thamminapatnam TPP-II U-3 350 Oct-14 U-4 350 Jan-15

52 AP Vizag TPP U-1 525 Feb-14 U-2 525 Jun-14

53 Chhattisgarh Akaltara (Naiyara) TPP U-1 600 Jun-13 U-2 600 Oct-13 U-3 600 Jun-14 U-4 600 Aug-14

54 Chhattisgarh Avantha Bhandar TPS, U-1 U-1 600 Sep-13 55 Chhattisgarh Balco TPP U-1 300 Mar-14 U-2 300 Jan-14

56 Chhattisgarh Bandakhar TPP Ltd U-1 300 Aug-14 57 Chhattisgarh Baradarha TPP U-1 600 Aug-13 U-2 600 Feb-14

58 Chhattisgarh Binjkote TPP U-1 300 Sep-14 U-2 300 Dec-14 U-3 300 Sep-15

Page 9: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

U-4 300 Jan-16 59 Chhattisgarh Chakabura TPP U-1 30 Sep-13 60 Chhattisgarh Lanco Amarkantak TPS-II U-3 660 May-14 U-4 660 Sep-14

61 Chhattisgarh Raigarh TPP (Visa) U-1 600 Mar-14 62 Chhattisgarh Raikheda TPP U-1 685 May-14 U-2 685 Nov-14

63 Chhattisgarh Singhitarai TPP U-1 600 Feb-15 U-2 600 May-15

64 Chhattisgarh Swastic TPP U-1 25 May-13 65 Chhattisgarh Tamnar TPP ( Raigarh) U-1 600 Feb-14 U-2 600 Jun-14 U-3 600 Mar-15 U-4 600 Aug-15

66 Chhattisgarh TRN Energy TPP U-1 300 Aug-14 U-2 300 Dec-14

67 Chhattisgarh Uchpinda TPP U-1 360 Oct-13 U-2 360 Jan-14 U-3 360 Apr-14 U-4 360 Jul-14

68 Chhattisgarh Vandana Vidyut TPP- U-1 135 Mar-13 U-2 135 Aug-13

69 Gujarat Mundra UMTPP U-5 800 Mar-13 70 Jharkhand MahadevPrasas STPP Ph- U-2 270 Jul-13 71 Jharkhand Maitrishi Usha TPP-Ph-I U-1 270 Dec-13 U-2 270 Mar-14

72 Jharkhand Maitrishi Usha TPP-Ph-II U-3 270 Aug-14 U-4 270 Dec-14

73 Jharkhand Tori TPP U-1 600 Apr-15 U-2 600 Aug-15

74 Maharashtra Amravati TPP Ph-I U-1 270 Mar-13 U-2 270 Jun-13 U-3 270 Sep-13 U-4 270 Dec-13 U-5 270 May-14

75 Maharashtra Amravati TPP Ph-II U-1 270 $ U-2 270 $ U-3 270 $ U-4 270 $ U-5 270 $

76 Maharashtra Bela TPP-I U-1 270 Mar-13 77 Maharashtra Dhariwal Infracture TPP U-1 300 Apr-13 U-2 300 Aug-13

78 Maharashtra EMCO Warora TPP U-2 300 Jun-13 79 Maharashtra Lanco Vidarbha TPP U-1 660 Dec-14 U-2 660 Mar-15

80 Maharashtra Nasik TPP Ph-I U-1 270 May-13 U-2 270 Aug-13 U-3 270 Nov-14 U-4 270 Jan-15 U-5 270 Mar-15

81 Maharashtra Nasik TPP Ph-II U-1 270 $ U-2 270 $ U-3 270 $ U-4 270 $ U-5 270 $

82 Maharashtra Tirora TPP Ph-I U-2 660 Mar-13 83 Maharashtra Tirora TPP Ph-II U-1 660 May-13 U-2 660 Aug-13 U-3 660 Nov-13

Page 10: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

84 MP Anuppur TPP Ph-I U-1 600 Jul-14 U-2 600 Feb-15

85 MP Bina TPP U-2 250 Mar-13 86 MP Gorgi TPP U-1 660 Jun-16 87 MP Mahan TPP U-2 600 Jul-13 88 MP Nigri TPP U-1 660 Mar-14 U-2 660 Sep-14

89 MP Sasan UMPP U-1 660 Mar-14 U-2 660 Sep-13 U-3 660 Apr-13 U-4 660 Jul-14 U-5 660 Dec-14 U-6 660 May-15

90 MP Seioni TPP Ph-I U-1 600 Jan-14 91 Orissa Derang TPP U-1 600 Nov-13 U-2 600 Feb-14

92 Orissa Ind Bharat TPP ( Orissa) U-1 350 Sep-13 U-2 350 Dec-13

93 Orissa Kamalanga TPP U-1 350 Mar-13 U-2 350 Jun-13 U-3 350 Sep-13

94 Orissa KVK Nilanchal TPP U-1 350 Jan-14 U-2 350 Aug-15 U-3 350 Dec-15

95 Orissa Lanco Babandh TPP U-1 660 Jul-14 U-2 660 Dec-14

96 Orissa Malibrahmani TPP U-1 525 May-14 97 Punjab Goindwal Sahib U-1 270 Jun-13 U-2 270 Oct-13

98 Punjab Rajpura TPP ( Nabha) U-1 700 Jan-14 U-2 700 Mar-14

99 Punjab Talwandi Sabo TPP U-1 660 Dec-13 U-2 660 Apr-14 U-3 660 Jul-14

100 Rajasthan Jallipa-Kapurdi TPP U-6 135 # U-7 135 # U-8 135 #

101 Rajasthan Kawai TPP 660 Apr-13 102 Rajasthan Kawai TPP U-2 660 Jul-13 103 TN Melamaruthur TPP U-1 600 Jul-13

U-2 600 Nov-13 104 TN Tuticorin TPP (Ind- Barath U-1 660 Mar-16

TPP) 105 UP Lalitpur TPP U-1 660 Oct-14

U-2 660 Feb-15 U-3 660 Jun-15

106 UP Prayagraj (Bara ) TPP U-1 660 Jul-14 U-2 660 Nov-14 U-3 660 Mar-15

107 WB Haldia TPP-I U-1 300 Aug-14 U-2 300 Nov-14

$: Work is at stand still. Commissioning schedule shall be worked out after restart of work. #: Commissioning schedule shall be work out after getting permission to enhance production from existing mines or development of Jallipa mines.  

Page 11: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

*********** 

ANNEX-II

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (c) OF UNSTARRED QUESTION NO. 1692 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********

List of Hydro-electric projects under execution (Excluding projects under Ministry of New & Renewable Energy)

As on 28.02.2013 Sl. No.

Sector/Name of Project State Capacity (MW)

Central Sector 1 Uri-II Jammu & Kashmir 240 2 Nimoo Bazgo Jammu & Kashmir 45 3 Kishanganga Jammu & Kashmir 330 4 Parbati St. II Himachal Pradesh 800 5 Parabati-III Himachal Pradesh 520 6 Kol Dam Himachal Pradesh 800 7 Rampur Himachal Pradesh 412 8 Tapovan Vishnugad Uttarakhand 520 9 Tehri PSS Uttarakhand 1000 10 Lata Tapovan Uttarakhand 171 11 Teesta Low Dam-III West Bengal 33 12 Teesta Low Dam-IV West Bengal 160 13 Subansiri Lower Arunachal Pradesh 2000 14 Kameng Arunachal Pradesh 600 15 Pare Arunachal Pradesh 110 16 Tuirial Mizoram 60 State Sector 17 Baglihar-II J&K/ 450 18 Uhl-III Himachal Pradesh 100 19 Kashang-I Himachal Pradesh 65 20 Kashang-II & III Himachal Pradesh 130 21 Sainj Himachal Pradesh 100 22 Swara Kuddu Himachal Pradesh 111 23 Shongtong Karcham Himachal Pradesh 450 24 Koyna Left Bank PSS Maharashtra 80 25 Nagarujana Sagar TR Andhra Pradesh 50 26 Lower Jurala Andhra Pradesh 240 27 Pulichintala Andhra Pradesh 120 28 Pallivasal Kerala 60 29 Thottiyar Kerala 40 30 Bhawani Barrage II Tamil Nadu 15 31 Bhawani Barrage III Tamil Nadu 30 32 Myntdu Unit-3 Meghalaya 42 33 New Umtru Meghalaya 40 Private Sector 34 Sorang Himachal Pradesh 100 35 Tangnu Romai- I Himachal Pradesh 44 36 Shrinagar Uttarakhand 330 37 Phata Byung Uttarakhand 76 38 Singoli Bhatwari Uttarakhand 99

Page 12: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

 

 

39 Maheshwar Madhya Pradesh 400 40 Chujachen Sikkim 99 41 Teesta- III Sikkim 1200 42 Tidong-I Himachal Pradesh 100 43 Teesta- VI Sikkim 500 44 Rangit-IV Sikkim 120 45 Jorethang Loop Sikkim 96 46 Bhasmey Sikkim 51 47 Tashiding Sikkim 97 48 Dikchu Sikkim 96 49 Rangit-II Sikkim. 66 50 Rongnichu Sikkim 96  

 

*********** 

Page 13: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

ANNEX-III

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (c) OF UNSTARRED QUESTION NO. 1692 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********

Details of Under Construction Thermal Power Projects Lagging behind schedule time of Commissioning State Project Name Unit No Capacity

(MW) Original Comm. Sched.

Anticipated Comm. Sched.

Org. Cost (Rs. Crs)

Latest Cost (Rs. Crs)

Cost Overrun Rs. Crs.

CENTRAL SECTOR Assam Bongaigaon TPP U-1 250 Jan-11 Jun-14

U-2 250 May-11 May-15 U-3 250 Sep-11 Oct-15

4375.35 4375.35 0

Bihar Barh STPP- I U-1 660 Oct-13 Jun-15 U-2 660 Apr-14 Apr-16 U-3 660 Oct-14 Feb-17

8693 8693 0

Bihar Barh STPP-II U-4 660 Dec-12 Oct-13 U-5 660 Oct-13 Sep-14

7341.04 7341.04 0

Bihar Muzaffarpur TPP Exp (Kanti TPP St-II)

U-3 195 Oct-12 Jun-14

U-4 195 Jan-13 Sep-14

3154.33 3154.33 0

Bihar Nabi Nagar TPP U-1 250 May-13 Jul-14 U-2 250 Sep-13 Jan-15 U-3 250 Jan-14 Jul-15 U-4 250 May-14 Jan-16

5352.51 5352.51 0

Jharkhand BokaroTPS "A"Exp. U-1 500 Dec-11 Aug-14 2313 3552.18 1239.18 Maharashtra Mouda TPP U-2 500 Oct-12 Mar-13 5459.28

( 2 Units) 6010.89

( 2 Units) 551.61

MP Vindhyachal TPP-IV U-12 500 Dec-12 Mar-13 5915 (2 Units)

5915 (2 Units)

0

TN Neyveli TPS-II Exp. U-2 250 Jun-09 Mar-14 2030.78 (2 Units)

3027.59 ( 2 Units)

996.81

TN Tuticorin JV TPP U-1 500 Mar-12 Dec-13 U-2 500 Aug-12 Mar-14

4909.54 6478.92 0

TN Vallur TPP Ph-II U-3 500 Dec-12 Sep-13 3086.78 3086.78 0 Tripura Monarchak CCPP GT+ST 101 Jul-13 May-14 623.44 623.44 0 Tripura Tripura Gas Module-1 363.3 Dec-11 03.01.13(A)

Module-2

363.3 Mar-12 Jul-13 3429 3429 0

UP Rihand TPS- III U-6 500 Dec-12 Nov-13 6230.81 (2 Units)

6230.81 (2 Units)

0

U-1 600 Feb-11 Jul-13 WB Raghunathpur TPP, Ph-I U-2 600 May-11 Apr-14

4122 6745 2623

STATE SECTOR AP Damodaram

Sanjeevaiah TPP U-1 800 Jul-12 May-14

U-2 800 Jan-13 Nov-14 8432 8654 222

AP Kakatiya TPP Extn U-1 600 Jul-12 May-14 2968.64 3466 497.36 AP Rayalseema Stage-III U-6 600 Jul-14 Dec-15 3028.86 3525 496.14

Assam Namrup CCGT GT 70 Sep-11 Sep-13 ST 30 Jan-12 Dec-13

411 693.73 282.73

Chhattisgarh Korba West St-III. U-5 500 May-12 Mar-13 2309.34 3156 846.66 Chhattisgarh Marwa TPP U-1 500 May-12 Jun-13

U-2 500 Jul-12 Oct-13 4735 6318 1583

Delhi Pragati CCGT - III GT-4 250 Sep-10 Apr-13 5195.81 5195.81 0

Page 14: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

ST-2 250 Nov-10 Jul-13 (for 4 GT + 2 ST)

(for 4 GT + 2 ST)

Page 15: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

Gujarat Pipavav CCPP Block-1 351 Sep-10 Jul-13 Block-2 351 Nov-10 Mar-13

2354.29 4296 1941.71

Gujarat Sikka TPP Extn. U-3 250 Oct-13 Nov-13 U-4 250 Jan-14 Feb-14

2004 2356 352

Gujarat Ukai TPP Extn. U-6 500 Jan-11 Mar-13 1950 2135 185 U-1 250 Oct-13 Oct-14 Gujarat Bhavnagar

CFBC TPP U-2 250 Dec-13 Feb-15 3742.08 3742.08 0

Maharashtra Chandrapur TPS U-8 500 Jun-12 Sep-13 U-9 500 Sep-12 Dec-13

5500 5500 0

Maharashtra Koradi TPP Exp U-8 660 Dec-13 May-14 U-9 660 Jun-14 Oct-14 U-10 660 Dec-14 Mar-15

11880 11880 0

Maharashtra Parli TPP Expn. U-8 250 Jan-12 Dec-13 1375 1696.24 321.24 MP Malwa TPP

(Shree Singaji TPP) U-1 600 Jun-12 Jun-13

U-2 600 Oct-12 Dec-13 4053 6750 2697

MP Satpura TPP Extn U-10 250 Feb-12 Mar-13 U-11 250 Apr-12 Jul-13

2350 3032.34 682.34

Rajasthan Chhabra TPP Extn. U-3 250 May-11 May-13 U-4 250 Jul-11 Sep-13

2200 2200 0

Rajasthan Kalisindh TPS U-1 600 Aug-11 Aug-13 Rajasthan Kalisindh TPS U-2 600 Mar-12 Dec-13

4600 5500 900

GT 110 May-11 Mar-13 Rajasthan Ramgarh CCPP Extn.-III ST 50 Oct-11 Aug-13

640 640 0

U-1 600 Apr-11 Jul-13 3398 3552 154 TN North Chennai TPP Extn, U-2 600 Nov-11 Mar-13 2718.75 2813.58 94.83

UP Anpara-D U- 6 500 Mar-11 Feb-14 U-7 500 Jun-11 Jun-14

5358.79 5358.79 0

UP Parichha Extn U-6 250 Nov-09 Mar-13 1900 (2 Units)

2356 (2 Units)

456

PRIVATE SECTOR U-1 660 Oct-13 Oct-15 AP Bhavanpadu TPP U-2 660 Mar-14 Mar-16

6571.94 6571.94 0

U-1 660 Mar-15 Mar-16 AP NCC TPP U-2 660 Jun-15 Sep-16

7046 7046 0

U-1 660 May-14 Sep-14 AP Painampuram TPP U-2 660 Aug-14 Dec-14

6869 6869 0

U-3 150 Dec-11 Jun-13 AP Simhapuri Energy Pvt Ltd Ph-II U-4 150 Feb-12 Sep-15

1605.9 1605.9 0

AP Thamminapatnam TPP-I

U-2 150 Nov-11 Mar-13 1420 (2 Units)

1428 (2units)

8

U-3 350 May-12 Oct-14 AP Thamminapatnam TPP-II U-4 350 Aug-12 Jan-14

3120 3700 580

Vizag TPP U-1 520 Jun-13 Feb-14 AP U-2 520 Sep-13 Jun-14

5545 5545 0

U-1 600 Apr-12 Jun-13 U-2 600 Aug-12 Oct-13 U-3 600 Dec-12 Jun-14

Chhattisgarh Akaltara (Naiyara) TPP

U-4 600 Apr-13 Aug-14

16190 (6 units)

16190 (6 units)

0

Chhattisgarh Avantha Bhandar TPS, U-1

U-1 600 Jul-12 Sep-13 2872 3850 978

U-1 600 Mar-13 Aug-13 Chhattisgarh Baradarha TPP (DB Power TPP) U-2 600 Jul-13 Jan-14

6533 6640 107

U-1 300 Feb-11 Mar-14 Chhattisgarh Balco TPP U-2 300 Nov-10 Jan-14

4650 (4 units)

4650 (4 units)

0

Chhattisgarh Bandakhar TPP U-1 300 Dec-12 Aug-14 1456 1456 0 U-1 300 Aug-14 Sep-14 Chhattisgarh Binjkote TPP U-2 300 Nov-14 Dec-14

5058 6848.1 1790.1

Page 16: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

U-3 300 Feb-14 Mar-15 U-4 300 May-14 Jun-15 U-3 660 Jan-13 May-14 Chhattisgarh Lanco Amarkantak

TPS-II U-4 660 Mar-13 Sep-14 6886 7700 814

U-1 685 Sep-13 May-14 Chhattisgarh Raikheda TPP U-2 685 Jan-14 Nov-14

8290 8290 0

U-1 600 Jun-14 Feb-15 Chhattisgarh Singhitarai TPP U-2 600 Sep-14 May-15

4650 6200 1550

Chhattisgarh Swastic TPP U-1 25 Jun-12 May-13 136 142 6 U-1 600 Jan-14 Feb-14 U-2 600 Apr-14 Jun-14 U-3 600 Sep-14 Mar-15

Chhattisgarh Tamnar TPP (O.P.Jindal)

U-4 600 Nov-14 Oct-15

12800 (4 Units)

12800 (4 Units)

0

U-1 300 Dec-13 Aug-14 Chhattisgarh TRN Energy TPP U-2 300 Apr-14 Dec-14

2844 2844 0

U-1 360 May-12 Oct-13 U-2 360 Nov-12 Jan-14 U-3 360 Feb-13 Apr-14

Chhattisgarh Uchpinda TPP

U-4 360 Jul-13 Jul-14

6653.61 6653.61 0

U-1 135 Jun-11 Mar-13 Chhattisgarh Vandana Vidyut TPP- Chhattisgarh U-2 135 Sep-11 Aug-13

1458.44 1458.44 0

Jharkhand Mahadev Prasad STPP Ph.I

U-2 270 Mar-12 Jul-13 3151 (2 Units)

3151 (2 Units)

0

U-1 270 May-12 Jul-13 Jharkhand Maitrishi Usha TPP-Ph-I U-2 270 Jun-12 Nov-13

2900 2900 0

U-3 270 Feb-13 Jan-14 Jharkhand Maitrishi Usha TPP-Ph-II U-4 270 Mar-13 Mar-14

3182 3182

Jharkhand Tori TPP U-1 600 Jun-13 Apr-15 U-2 600 Jan-14 Aug-15

5700 5700 0

Maharashtra Amravati TPP Ph-I U-1 270 Dec-11 Mar-13 U-2 270 Dec-11 Jun-13 U-3 270 Jan-12 Sep-13 U-4 270 Feb-12 Dec-13 U-5 270 Mar-12 Mar-14

6889 6889 0

Maharashtra Amravati TPP Ph-II U-1 270 Jul-14 * U-2 270 Sep-14 * U-3 270 Nov-14 * U-4 270 Jan-15 * U-5 270 Mar-15 *

6646 6646 0

Maharashtra Bela TPP-I U-1 270 Dec-11 Mar-13 1477 1768 291 U-1 300 Feb-12 Apr-13 Maharashtra Dhariwal

infracture TPP U-2 300 May-12 Aug-13 2850 2878 28

Maharashtra EMCO Warora TPP U-2 300 Feb-12 Jun-13 3480 (2 Units)

3480 (2 Units)

0

Maharashtra Lanco Vidarbha TPP U-1 660 Jan-14 Sep-14 U-2 660 May-14 Jan-15

6936 6936 0

Maharashtra Nasik TPP Ph-I U-1 270 Feb-12 May-13 U-2 270 Apr-12 Aug-13 U-3 270 Jun-12 Nov-14 U-4 270 Aug-12 Jan-15 U-5 270 Oct-12 Mar-15

6789 6789 0

Maharashtra Nasik TPP Ph-II U-1 270 Apr-13 * U-2 270 Jun-13 * U-3 270 Aug-13 * U-4 270 Oct-13 * U-5 270 Dec-13 *

6789 6789 0

Maharashtra Tirora TPP Ph-I U-2 660 Jul-11 Mar-13 6560 (2units)

7309 (2 Units)

749

Maharashtra Tirora TPP Ph-II U-1 660 Oct-11 Apr-13 U-2 660 Jul-12 Aug-13

8993 9635 642

Page 17: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

U-3 660 Oct-12 Nov-13  

MP Anuppur TPP Ph-I U-1 600 Apr-13 Jul-13 U-2 600 Aug-13 Feb-15

6240 6240 0

MP Bina TPP U-2 250 Nov-11 Mar-13 2750 (2 Units)

2750 (2 Units)

0

MP Gorgi TPP (DB Power)

U-1 660 Jun-13 Jun-16 6640 (for 2units)

6640 (for 2 units)

0

MP Mahan TPP U-2 600 Sep-11 May-13 4860 (2 Units)

4860 (2 Units)

0

U-1 660 Jun-13 Mar-14 MP Nigri TPP U-2 660 Dec-13 Jun-14

8100 8100 0

MP Seioni TPP Ph-I U-1 600 Mar-13 Jan-14 2910 2910 0 Orissa Derang TPP U-1 600 Mar-12 Nov-13

U-2 600 Jun-12 Feb-14 5961 5961 0

Orissa Ind Bharat TPP (Orissa)

U-1 350 Sep-11 Sep-13

U-2 350 Dec-11 Dec-13 3185 3185 0

Orissa Kamalanga TPP U-1 350 Nov-11 Mar-13 U-2 350 Dec-11 Jun-13 U-3 350 Feb-12 Sep-13

4540 5268 728

Orissa KVK Nilanchal TPP U-1 350 Dec-11 Jan-14 U-2 350 Jan-12 Aug-15 U-3 350 Mar-12 Oct-15

4990 4990 0

U-1 660 Apr-13 Mar-14 Orissa Lanco Babandh TPP U-2 660 Aug-13 Jul-14

6930 6930 0

Orissa Malibrahmani TPP (Monnet Ispat)

U-1 525 Dec-12 May-14 5093 (2 units)

5093 (2 units)

0

Punjab Talwandi Sabo TPP U-1 660 Oct-12 Dec-13 U-2 660 Jan-13 Apr-14 U-3 660 May-13 Jul-14

10250 10250 0

U-6 135 Aug-10 ** U-7 135 Sep-10 **

Rajasthan Jallipa-Kapurdi TPP

U-8 135 Mar-11 **

5075 (8 Units)

6085 (8 Units)

1010

U-1 660 Dec-12 Mar-13 Rajasthan Kawai TPP U-2 660 Mar-13 Jun-13

7020 7020 0

U-1 660 Feb-14 Jul-14 U-2 660 Jul-14 Nov-14

UP Prayagraj TPP

U-3 660 Dec-14 Mar-15 11622.3 11622.3 0

TN Melamaruthur TPP U-1 600 Feb-12 Jul-13 U-2 600 Mar-12 Sep-13

4800 5158 358

TN Tuticorin TPP (Ind- Barath TPP)

U-1 660 May-12 Mar-16 3595 3595 0

* No Work is going on at site. Date of commissioning would be assessed after restart of work at site. **Due to delay in development of Jalipa Mines. Date of commissioning would be assessed after development of Jalipa mines or after getting permission to enhance production from existing mines.

 

*********** 

Page 18: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

ANNEX-IV

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (c) OF UNSTARRED QUESTION NO. 1692 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

*********** HYDRO ELECTRIC PROJECTS HAVING COST OVER RUN

Sr. No.

Name of Project Capacity

State

Commissioning Schedule

Project Cost Rupees in Crores

Price Level

Cost over run

Original mm/yy

Latest mm/yy

Original Latest Rs. Crs

CENTRAL SECTOR 1 Kol Dam

(4x200 MW)/H.P. Apr-09 2008-10

2014-15 4527.15 (12/01)

6358.91 (12/01)

1831.76

2 Tapovan Vishnughad (4x130 MW) Uttarakhand

Mar-13 2012-13

2015-16 2978.48

2978.48

Nil

3 Pare (2x55MW)/Ar.Pd

Aug-12 2012-13

2014-15 573.99 (06/07)

573.99 (06/07)

Nil

4 Tuirial (2x30 MW)/Mizoram

Jul-06 2006-07

2016-17 368.72 (06/97)

913.63 (03/10)

544.91

5 Kameng (4x150 MW)/ Ar. Pd

Dec 09 2009-10

2016-17 2496.90 (03/04)

5139.00

2643.90

6 Tehri PSS (4x250 MW)/Uttarakhand

Jul- 10 2010-11

2017-18 1657.60 (12/05)

2978.86 (04/10)

1321.26

7 Rampur (6x68.67 MW)/ HP

Jan-12 2011-12

2013-15 2047.03

2047.03

Nil

8 Parbati-III (4x130 MW)/HP

Nov-10 2010-11

2012-14 2304.56 (05/05)

2716.00

411.44

9 Nimoo Bazgo (3x15 MW)/ J&K

Aug-10 2010-11

2013-14 611.01 (12/2005)

936.10 (Anticipated)

325.09

10 Teesta Low Dam-III (4x33 MW)/W B

Mar-07 2006-07

2012-14

768.92 (12/02)

1628 (anticipated)

859.08

11 Teesta Low Dam– IV (4x40 MW)/ WB

Sep-09 2009-10

2014-15

1061.38 (03/05)

1502.0

440..62

12 Parbati - II (4x200 MW)/H.P

Sep-09 2009-10

2016-17

3919.59 (12/01)

5366 (Anticipated)

1446.41

13 Subansiri Lower (8x250 MW)/ Ar. Pd./Assam

Sep-10 2010-11

2016-18 6285.33 (12/02)

10667 (anticipated

4381.67

14 Uri-II (4x60 MW)/J&K

Nov-09 2009-10

2012-13 1724.79 (02/05)

2081 (anticipated

356.21

15 Kishanganga (3x110 MW)/J&K

Jan-16 2015-16

2016-17 3642.04 (11/07)

3642.04 (11/07)

Nil

STATE SECTOR JAMMU & KASHMIR 16 Baglihar-II

(3x150 MW)/ 2014-15 2016-17 2113.09

2113.09

Nil

 

Page 19: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

 

 

HIMACHAL PRADESH 17 Kashang-I

(1x65MW) 2013-14 2014-15

18 Kashang-II & III (1x65 + 1x65 MW)

2013-14 2015-16 1078.00 1078.00 Nil

19 Uhl-III (3x33.33MW)

Mar-07 2006-07

2014-15 431.56 (09/02)

940.84 (03/08)

509.28

20 Sawra Kuddu (3x37MW)

Dec-10 2010-11

2014-15 558.53 1181.90 (03/12)

623.37

21 Sainj (100 MW)

2013-14 2014-15 725.24

725.24

Nil

ANDHRA PRADESH 22 Lower Jurala

(6x40 MW) 2011-12 2014-16 908.34

(2007) 1474.83 566.49

23 Pulichintala (4x30MW)

2011-12 2015-17 380.00 (2006-07)

396.00

16.00

24 Nagarjuna Sagar Tail Pool Dam (2x25 MW)

Nov-08 2008-09

2014-15 464.63 (2002-03)

958.67 494.04

TAMIL NADU 25 Bhavani Kattalai H.E.

Project Barrage II (2x15 MW)

Mar-06 2005-06

2012-13

99.15 (95-96)

497.46

301.44

26 Bhavani Kattalai H.E. Project Barrage III (2x15 MW)

Mar-06 2005-06

2012-14

99.75 (99-00)

442.73

342.98

KERALA 27 Pallivasal

2x30MW Oct-10

2010-11 2014-15 222.00

(1999) 268.02

46.02

28 Thottiyar (1x30+1x10)MW

2012-13 2015-16 136.79 (2007)

144.58

5.7

MEGHALAYA 29 New Umtru

(2x20MW 2011-12 2014-15 226.40

226.40

Nil

30 Myntdu (2x42MW + (1x42 MW)

2006-07 2011-13 363.08 (01/99)

Incl. IDC & FC

1173.13 (2010)

Incl. IDC

810.05

PRIVATE SECTOR HIMACHAL PRADESH 31 Tidong-I

2x50MW 2013-14 2015-16 543.15

543.15

Nil

32 Tangnu Romai-I (2x22 MW)

2014-15 2015-16 255.00

255..0

Nil

33 Sorang (2x50 MW),

2012-13 2013-14 586.00 586.00 Nil

 

Page 20: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

 

 

UTTARAKHAND 34 Srinagar

(4x82.5 MW) 2005-06 2013-15 1699.12

(3/99) 2069.00

369.88

35 Singoli Bhatwari (3x33MW)

2014-15 2015-16 666.47

666.47 Nil

MADHYA PRADESH 36 Maheshwar

(10x40 MW) 2001-02 2013-15 1569.27

(96-97) 2760.00 (2010)

1190.73

SIKKIM 37 Chujachen

(2x49.5 MW) Sept-09 2009-10

2013-14 448.76 (2004)

1044.50 595.74

38 Teesta Stage III (6X200 MW)

Oct-11 2011-12

2014-15 5705.55

5705.55 Nil

39 Teesta Stage VI (4X125 MW)

2012-13 2015-16 3283.08

3283.08 Nil

40 Rangit-IV HE Project (3X40 MW)

2012-13 2014-15 726.16

726.16 Nil

41 Jorenthang Loop (2x28MW)

Dec 12 2012-13

2014-15 543.15

543.15 Nil

42 Bhasmey (2x25.5 MW)

2012-13 2015-16 408.50

408.50 Nil

 

 

***********

Page 21: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA

UNSTARRED QUESTION NO.1693 ANSWERED ON 12.03.2013

CAPACITY UTILIZATION OF POWER PLANTS

1693. SHRI RAJEEV CHANDRASEKHAR: Will the Minister of POWER be pleased to state: (a) whether Government has reviewed the capacity utilization of power plants in Karnataka and other parts of the country; (b) if so, the details and the outcome thereof; and (c) the action Government proposes to take to ensure that the power plants achieve their full capacity utilization?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a) to (c) : The Central Electricity Authority (CEA) under the Central Government periodically inter-alia monitors the capacity utilization of power plants of the country including for Karnataka. The performance of power plants in Karnataka and other parts of the country depend upon many factors like forced and planned outages, technological obsolescence of some of the vintage units, schedule from beneficiary states, transmission constraints and availability and quality of fuel for thermal plants and availability of water for hydel power plants.

Based on the review, some of the generating stations with low performance are considered for R&M work and life Extension from time to time by respective power utilities.

The action plan to ensure that the power plants achieve their full capacity

utilization are as under:

1. Better availability of coal and gas to power sector.

2. Adopting better Operation & Maintenance practices by power plants.

3. Renovation and Modernization of existing old Thermal and hydro power plants by respective power utilities.

Page 22: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

***********

GOVERNMENT OF INDIA

MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.1694

ANSWERED ON 12.03.2013

INVESTMENTS IN POWER SECTOR BY DIFFERENT AGENCIES

1694. DR. BHALCHANDRA MUNGEKAR: Will the Minister of POWER be pleased to state: (a) the details of investment made in the power sector by the Central Government, private sector and through the PPP mode during the last three years; (b) the quantum of power generated through different sources and by above mentioned agencies during the last three years; and (c) the gap between requirement and availability of power in the country and the details of the short, medium and long term plans to fill up this gap?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a) : As per reports available in Central Electricity Authority, figures of investment in Power Sector from 2009-10 to 2011-12 are as follows:

All India Investment in power (Rs. crore)

2009-10 2010-11 2011-12 Central Sector 38461.81 36772.44 39931.56State Sector 52037.16 55528.23 51669.37Private Sector 43335.15 72334.32 69356.88Total 133834.12 164634.99 160957.81

Note: (i) Data is provisional; (ii) Expenditure in captive power plants is not included; (iii) Private investment data is incomplete.

(b) : The year-wise, source-wise details of gross electricity generation are given below:

Source Gross Energy Generation (BU) 2009-10 2010-11 2011-12 2012-13* # Thermal 640.877 665.008 708.806 631.436 Hydro 106.680 114.257 130.510 99.071 Nuclear 18.636 26.266 32.287 27.450

Page 23: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

……..2.

- 2 -

Bhutan Import 5.358 5.611 5.284 4.710 Total 771.551 811.143 876.887 762.667 * up to January, 2013 # Includes provisional figures for the month of January, 2013

(c) : The details of power supply position in the country including shortage during the years 2009-10, 2010-11, 2011-12 and 2012-13 (Up to January,2013) are given below: Year Peak (MW) Energy (MU)

Shortage Shortage Peak Demand

Peak Met MW %

Require-ment

AvailabilityMU %

2009-10 119116 104009 15157 12.7 830594 746644 83950 10.1 2010-11 122287 110256 12031 9.8 861591 788355 73236 8.5 2011-12 130006 116191 13815 10.6 937199 857886 79313 8.5 2012-13 (Up to January,2013)*

135453 123294 12159 9.0 833230 759849 73381 8.8

* Provisional

The steps being taken by the Government to bridge the gap between demand and supply of power in the country include inter-alia the following:

(i) Capacity addition of 88,537 MW during 12th Plan period (2012-2017). (ii) Rigorous monitoring of capacity addition of the on-going generation projects. (iii) Augmentation of domestic manufacturing capacity of power equipment through Joint

Ventures. (iv) Development of Ultra Mega Power Projects of 4,000 MW each and coordinated

operation and maintenance of hydro, thermal, nuclear and gas based power stations to optimally utilize the existing generation capacity.

(v) Thrust to import of coal by the power utilities to meet the shortfall in coal supplies to

thermal power stations from indigenous sources. (vi) Renovation, modernization and life extension of old and inefficient generation units. (vii) Strengthening of inter-state and inter-regional transmission capacity for optimum

utilization of available power.  

************ 

Page 24: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA

UNSTARRED QUESTION NO.1695 ANSWERED ON 12.03.2013

RECOMMENDATIONS OF THE WORKING GROUPS ON DULHASTI HEP

1695. SHRI G. N. RATANPURI: Will the Minister of POWER be pleased to state: (a) whether Hon'ble Prime Minister has made a public announcement of intended transfer of Dulhasti Hydroelectric Project (HEP) to J&K in pursuance of the recommendations of working groups constituted by the Prime Minister; (b) the extent of recommendations of the working groups that have been implemented by Government; and (c) the other recommendations of the working groups under consideration of Government?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA )

(a) : A Task Force on development of Jammu & Kashmir constituted by the Hon’ble

Prime Minister on 29.05.2005 under the Chairmanship of Dr. C. Rangarajan has recommended

inter-alia transfer of certain Power Projects of NHPC including Dulhasti Hydro-electric Project

(HEP) to State Government.

(b) & (c): As regards the status of implementation of these recommendations, the status is at

Annex.

************

Page 25: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

ANNEX

ANNEX REFERRED TO IN REPLY TO PARTS (b) & (c) OF UNSTARRED QUESTION NO. 1695 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********

i) Transfer of Dul Hasti Project.

The Central Government has decided that the transfer of Dulhasti HEP may not be possible due to likely financial, legal implications etc.

ii) Transfer of Bursar

The Bursar HEP is presently under Survey & Investigation by NHPC.

iii) Long Term Measures

The present status of implementation of other Projects recommended by the Task Force is as under:

Name of the Project

I.C. (MW) Status

Kiru 660 Detailed Project Report (DPR)has been submitted to CEA.

Kwar 560 CEA has returned the DPR.

Ratle 850 DPR was concurred by CEA on 19.12.2012

Shamnot 370 PFR prepared.

Sawalkot 1350 + 56 DPR returned by CEA.

iv) Policy Framework for development of hydro power potential in J&K.

As per recommendations, Draft Revised State Hydel Policy of Jammu & Kashmir has been

formulated by JKSPDC in June, 2010.

***********

 

Page 26: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

GOVERNMENT OF INDIA

MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.1696

ANSWERED ON 12.03.2013

ELECTRIC CONNECTIONS TO SCS AND STS FAMILIES

†1696. SHRI RAM VILAS PASWAN: Will the Minister of POWER be pleased to state the number of families in the country belonging to Scheduled Castes (SCs) and Scheduled Tribes (STs) and out of these the number of families which have the facility of electricity connection, State-wise?

A N S W E R THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA )

As per Census 2011, there are 442.27 lakh Scheduled Caste and 233.29 lakh Scheduled

Tribes households in the country and out of these 261.05 lakh Scheduled Caste and 120.60 lakh

Scheduled Tribes used electricity as main source of lighting for major part of the last 12 months. The

State wise detail is at Annex-I.

The Government of India launched ‘Rajiv Gandhi Grameen Vidyutikaran Yojana

(RGGVY)– Programme for creation of Rural Electricity Infrastructure & Household Electrification, in

April 2005 for providing access to electricity to rural households. Under the scheme, out of 7,80,90,874

number of rural households, 2,29,39,511 BPL households including Scheduled Castes and Scheduled

Tribes households have been covered for release of free electricity connections. Cumulatively, as on

31.01.2013, free electricity connections to 2,05,15,472 BPL households including Scheduled Castes and

Scheduled Tribes households have been provided. The State wise details are at Annex-II.

************

 

Page 27: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

ANNEX-I

ANNEX REFERRED TO IN REPLY TO UNSTARRED QUESTION NO. 1696 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********

State wise total number of SC & ST households and electricity as main source of lighting(as per 2011 )

Figures in lakhs Sl. NO.

STATES/Uts Total Number of SC households

SC households using electricity as

main source of light

Total Number of ST households

ST households using electricity as main source

of light 1 Andhra Pradesh 36.72 32.48 15.6 12.49 2 Arunachal Pradesh 1.73 1.15 3 Assam 6.73 2.66 8.87 2.48 4 Bihar 32.31 3.16 4.24 0.49 5 Jharkhand 7.94 3.08 17.18 5.04 6 Goa 0.13 0.12 0.33 0.32 7 Gujarat 9.95 9.21 18.37 14.7 8 Haryana 10.51 8.83 9 Himachal Pradesh 3.69 3.53 0.92 0.87

10 Jammu & Kashmir 1.98 1.8 2.62 1.57 11 Karnataka 21.4 18.21 9.37 7.83 12 Kerala 7.51 6.48 1.36 0.85 13 Madhya Pradesh 24.6 16.04 32.14 17.35 14 Chhattisgarh 7.88 6.49 17.48 9.92 15 Maharashtra 33.11 26.41 24.46 14.62 16 Manipur 0.28 0.18 1.74 1 17 Meghalaya 0.16 0.11 4.57 2.7 18 Mizoram 0.04 0.03 2.12 1.78 19 Nagaland 3.49 2.83 20 Odisha 17.8 6.2 22.4 3.5 21 Punjab 18.67 17.56 22 Rajasthan 23.18 13.96 18.36 7.28 23 Sikkim 0.08 0.07 0.46 0.42 24 Tamil Nadu 37.59 33.92 3.85 3.25 25 Tripura 1.65 1.21 2.59 1.22 26 Uttar Pradesh 76.49 18.41 5.13 1.88 27 Uttarakhand 3.77 3.01 0.63 0.53 28 West Bengal 51.4 21.32 12.73 4.03 29 Chandigarh 0.44 0.43 30 Delhi 5.7 5.61 31 Daman & Diu 0.02 0.02 0.03 0.03 32 D&NH 0.03 0.03 0.33 0.3 33 Lakshadweep 0.1 0.1 34 Puducherry 0.48 0.45 35 A&N 0.08 0.07

Total(All India) in Lakhs

442.27 261.05 233.29 120.6

 

Page 28: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

************ 

ANNEX-II

ANNEX REFERRED TO IN REPLY TO UNSTARRED QUESTION NO. 1696 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********   

State-wise details of coverage and release of free electricity connections to BPL households including Scheduled Caste and Scheduled Tribes under RGGVY

Release of free electricity connections to BPL households

Sr. No.

State Coverage

Cumulative Achievement as on 31.01.2013

1 Andhra Pradesh 2484665 2783390 2 Arunachal Pradesh 40726 24615 3 Assam 1150597 882554 4 Bihar 2761010 2305704 5 Chhattisgarh 903500 944103 6 Gujarat 742094 827788 7 Haryana 235841 194461 8 Himachal Pradesh 13196 14753 9 Jammu & Kashmir 81217 51012

10 Jharkhand 1803377 1283770 11 Karnataka 950437 856401 12 Kerala 55732 52993 13 Madhya Pradesh 1320184 942734 14 Maharashtra 1183603 1180284 15 Manipur 107369 28814 16 Meghalaya 109696 83067 17 Mizoram 27417 15144 18 Nagaland 69899 36062 19 Odisha 3045979 2802221 20 Punjab 148860 79104 21 Rajasthan 1224417 1120242 22 Sikkim 11458 9695 23 Tamil Nadu 502865 501202 24 Tripura 107506 97625 25 Uttar Pradesh 963778 1042593 26 Uttarakhand 238522 234593 27 West Bengal 2655566 2120548 Total 22939511 20515472

 

************

Page 29: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA

UNSTARRED QUESTION NO.1697 ANSWERED ON 12.03.2013

STATUS OF MOUs AND JVPS SIGNED BY POWER PSUs

1697. SHRI BALWINDER SINGH BHUNDER: Will the Minister of POWER be pleased to state: (a) the number of Memorandum of Understandings (MoUs) Joint Venture Projects (JVPs) which have been signed by the Public Sector Undertakings (PSUs) under the Ministry with the foreign or domestic partners; (b) the date of signing of each of these MoUs/JVPs and the purposes of signing; (c) the status of each of the MoU/JVPs; and (d) by when the MoUs/JVPs will be realized/completed?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a) to (d) : The number of Memorandum of Understanding (MoUs) Joint Venture Projects (JVPs) signed by various Public Sector Undertakings (PSUs) under Ministry of Power is given below and details of each of the MOUs/JVPs for each of Power Sector PSU are annexed. Sl. No.

Name of PSUs No. of MoUs/JVPs

Remarks

1. NTPC Limited 10 8 MoUs/JVPs were signed with domestic partners and 2 with foreign partners. Details at Annex-I.

2. NHPC 6 Details at Annex-II. 3. PGCIL 24 12 MoUs ( 7 with foreign partners and 5 with domestic

partner) and 12 JVPs (11 with domestic partners and 1 with foreign partner). Details at Annex-III .

4. PFC 2 2 MoUs have been signed by PFC/PFCCL. PFC does not have any Joint Venture (JVP). Details at Annex-IV.

5. REC 2 Details at Annex-V 6. SJVNL 13 Details at Annex-VI. 7. THDC 12 Details at Annex-VII. 8. NEEPCO No MoUs/JVPs has been signed by NEEPCO with any

foreign or domestic partners.

Page 30: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

***********

ANNEX-I

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (d) OF UNSTARRED QUESTION NO. 1697 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********

Details of MoU/JVPs of NTPC (For development of power projects)

Sl. No.

Name of the JV Date of JV/ MOU Agreement

Purpose Status

With Domestic Partners 1. Aravali Power

Company Private Ltd., (NTPC, HPGCL & IPGCL)

14.12.2006 To set up thermal power plants in Haryana

Three units of 500 MW have been commissioned at Jhajjar.

2. Meja Urja Nigam Private Ltd. (NTPC & UPRVUNL)

28.02.2008 To set up thermal power plants in Uttar Pradesh

Main Plant for Stage-I (2x660 MW) coal based power plant at Meja Tehsil in Allahabad District has been awarded in May, 2012.

3. Nabinagar Power Generating Company Private Ltd. (NTPC & BSEB)

14.02.2008 To set up thermal power plants in Bihar.

A 1980 MW (3x660 MW) coal based power project in Nabinagar has been awarded in January 2013.

4. * Kanti Bijlee Utpadan Nigam Ltd. (NTPC & BSEB)

26.12.2005 To take up and operate Muzaffarpur Thermal Power Station in Bihar.

Stage-I (2x110 MW under R&M). Main Plant for expansion project 2X195 MW awarded in March, 2010.

5. *Bhartiya Rail Bijlee Company Ltd. (NTPC & Railways)

06.11.2007 To set up thermal power plants to meet requirement of Railways.

Main Plant for 1000 MW Coal based thermal power project (4X250 MW) at Nabinagar Aurangabad Dist. awarded in January, 2008.

6. NTPC Tamil Nadu Energy Company Ltd. (NTPC & TNEB)

23.01.2006 To set up thermal power plants in Tamil Nadu.

2 X 500 MW (Unit#1 & Unit # 2) commissioned. Main Plant for Unit #3(1X500 MW) awarded in July, 2009.

7. Ratnagiri Gas and Power Pvt. Ltd. (NTPC, Gail, IFIs & MSEB)

28.02.2007 To acquire assets of mothballed Dabhol Power Company.

RGPPL has taken over, revived and re-commissioned the power plant with installed capacity of 1967 MW. RGPPL has also commissioned the 5 MMTPA LNG Terminal in January, 2013.

 

Page 31: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

8. NTPC – SAIL Power Company PVT. Ltd. (NTPC & SAIL)

06.03.2001 To own and operate SAIL's captive power plants

NTPC-SAIL Power Company Pvt. Ltd. owns and operates 814 MW located at Durgapur, Bhilai and Rourkela.

With Foreign Partners 1. Bangladesh- India

Friendship Power Co. (Pvt.) Ltd. (NTPC & Bangladesh Power Development Board)

29.01.2012 To develop 1320 MW coal based power project(s) in Bangladesh.

Feasibility report for (2X660 MW) Project has been prepared and the project agreements are under finalization.

2. Trincomalee Power Co. Ltd., SHRI LANKA (NTPC, PGCIL, PFC & Ceylon Electricity Board)

06.09.2011 Setting up 2X500 MW coal based power plants in Trincomalee, Sri Lanka.

Project agreement is under finalization.

* Subsidiaries of NTPC with NTPC as a major partner.

Additional Information

Besides above, NTPC has signed MOUs and formed JV companies with other domestic and foreign partners for following purposes:

1. Services - Energy Efficiency Services Ltd., National High Power Test Laboratory Pvt. Ltd., Utility Powertech Limited, NTPC Alstom Power Services Pvt. Ltd. (with foreign partner).

2. Backward integration – CIL NTPC Urja Pvt. Ltd., NTPC SCCL Global Venture Power Limited, International Coal Ventures Pvt. Ltd.

3. Power Equipment manufacturing - NTPC BHEL Power Projects Pvt. Ltd., BF-NTPC Energy Systems Limited, Transformers and Electricals Kerala Limited.

4. Diversification – Anushakti Vidyut Nigam Limited, National Power Exchange Limited, Pan Asian Renewables Pvt. Ltd. (with foreign partner).

 

************

Page 32: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

ANNEX-II

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (d) OF UNSTARRED QUESTION NO. 1697 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

*********** Details of Joint Venture Projects of NHPC are as under:-

* Both these projects have been commissioned by NHDC ahead of schedule.

MOU/JOINT VENTURE PROJECT IN MYANMAR NHPC has also signed one agreement each for taking up Additional Investigations and Preparation of Updated Detailed Project Report for 1200 MW Tamanthi and 880 MW Shwezaye HE Projects on Chindwin River in Myanmar, as consultancy assignment, with Ministry of External Affairs (MEA), Government of India. on 16.09.2008 Earlier, an MOU was also signed between NHPC Limited and Department of Hydro Power Implementation (DHPI), Ministry of Electric Power (1)- (MOEP-I), Govt. of Union of Myanmar (GoUM) for appraisal of Detailed Project Reports (DPRs) of 1200 MW Tamanthi HE Project. The Agreements with MEA, Govt. of India was signed on 8th January, 2010. The Agreements were signed with a purpose of carrying out additional investigations and preparation of updated DPRs of both the projects to take up implementation based on methodology to be decided by Govt. of India and Govt. of Union of Myanmar subject to the projects being techno-commercially viable and environmentally sustainable. MOU was signed with DHPI, MOEP-I, GoUM on 16.09.2008 for appraisal of Detailed Project Reports (DPRs) of 1200 MW Tamanthi HE Project (prepared by M/s Colenco Power Engg., Switzerland) and 642 MW Shwezaye HE Project (prepared by M/s Kansai Electric Power Company Inc. Japan) viz-a-viz the master plan of Chindwin River Basin and suggest modifications and additional studies which are required for establishing the techno commercial viability of these projects within a period of 3 months.

S. No.

Joint Venture

JV Partners/ Date of signing of MoU

Purpose

1 NHDC* NHPC & Govt. of M.P. (51:49), 01.08.2000

For development of hydropower Projects and other renewal energy potential in the state of Madhya Pradesh. NHDC was entrusted with the construction of Indira Sagar Project (1000 MW) and Omkareshwar Project (520 MW) in Narmada basin.

2 CVPP NHPC, JKPDC & PTC (49:49:2), 10.10.2008

For execution of Pakal Dul, Kiru & Kwar (2120 MW) Hydro-Electric projects in J&K state.

3 LDHCL NHPC & Govt. of Manipur (74:26), 14.9.2007

For implementation of the Loktak Downstream HE project (66MW) in Manipur state.

4 TIPAIMUKH NHPC, Govt. of Manipur & NEEPCO (69:5:26), 28.04.2010

For implementation of the Tipaimukh HE (M) Project (1500 MW) in Manipur state.

5 NPEX NHPC, NTPC, PFC & TCS (16.67:16.67:16.66:50), 03.9.2008

To set up & operate a Power Exchange at National Level. The company has the main objective of carrying on the business of Power Exchange to facilitate, promote, assist, regulate and manage trading in Power.

6 NHPTLPL NHPC, NTPC, PGCIL & DVC (25:25:25:25), May,09

The mission of the company is to establish a state of art On-Line High Power Short Circuit Test Facility

Page 33: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

Implementation Agreements with Govt. of Uttarakhand for 210 MW Dhauliganga Intermediate and 120 MW Goriganga-IIIA HE Projects in Pithoragarh Distt., Uttarakhand Further, NHPC has signed two Implementation Agreements with Govt. of Uttarakhand for 210 MW Dhauliganga Intermediate and 120 MW Goriganga-IIIA HE Projects in Pithoragarh Distt., Uttarakhand. The Implementation Agreements have been signed with Govt. of Uttarakhand on 23.01.2013 for taking up implementation of the projects and subsequent operation & maintenance upon their commissioning. c) Status of JVPs are as following: NHDC NHPC signed an MOU with Govt. of MP in August 2000 for formation of Joint venture company i.e. Narmada Hydroelectric Development Corporation Ltd. (now NHDC Limited) for implementation of Indira Sagar (1000 MW) and Omkareshwar (520 MW) Projects in M.P with NHPC being major share holder (51%). Both these projects have been commissioned by NHDC ahead of schedule. LDHCL- Loktak Downstream Hydroelectric Corporation Limited NHPC signed an MOU with Government of Manipur in Sept-07 for development of the 66 MW Loktak downstream project under Joint Venture with share of NHPC as 74%. The JVC has been registered as “Loktak Downstream Hydroelectric Corporation Limited” on 23.10.2009 and the project is presently under process of getting various clearances. Tipaimukh HE Project MoU for formation of JVC for implementation of the project has been signed between the JVC Partners at New Delhi on 28.04.2010 Promoter’s Agreement for setting up a Joint Venture Company amongst NHPC Limited , SJVN Limited and Government of Manipur for implementation of the project was also signed on 22.10.2011. However, MoP vide letter dated 10.12.2012 has intimated the approval of competent Authority to induct NEEPCO in the proposed Joint Venture as JV partner with 26% share in lieu of SJVN Ltd. Draft M&AoA has been forwarded to NEEPCO on 27.12.2012, for its views/comments. Draft Promoters Agreement also forwarded to NEEPCO & Govt. of Manipur on 09.01.2013, for views and comments. Joint Venture with Govt. of J&K, CVPPPL In October 2008, a MOU was signed among JKSPDC, NHPC and PTC for development of Pakal Dul and other Chenab Basin Projects under joint venture aggregating to 2100 MW in J&K. The Joint Venture Company has been registered as “Chenab Valley Power Projects Pvt. Ltd.” on 13.6.2011 with shareholding of 49% of each for NHPC & JKSPDC and 2% for PTC. The projects under CVPPPL are presently under various stage of clearances. National Power Exchange The National Power Exchange (NPEX) has been incorporated as a Joint Venture Company amongst NHPC (16.67%), NTPC (16.67%), PFC (16.67%) & TCS (50%) under the provisions of the Companies Act 1956 to set up & operate a Power Exchange at National Level. CERC has granted in principle approval to NPEX. The company has the main objective of carrying on the business of Power Exchange to facilitate, promote, assist, regulate and manage trading in Power. National High Power Test Lab A Joint Venture has been formed in May-09 amongst NTPC, NHPC, PGCIL & DVC having shareholding of 25% each. The mission of the company is to establish a state of art On-Line High Power Short Circuit Test Facility . This facility will be fully independent and professionally managed standalone testing facility in India to provide a full range of Short Circuit testing for the electrical equipment manufacturing industry and power supply utilities in conformance to Indian (BIS-Bureau of Indian Standards) and International Standards

Deleted: ,

Deleted:

Deleted:

Page 34: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

(IEC- International Electro-technical Comm.). Tamanthi & Shwezaye HE Project The updated DPR of Tamanthi HE Project has been submitted by NHPC in Oct’2011 and for Shwezaye HE Project in April 2012 to MEA/ MoP, GoI and DHPP/ DHPI, GoUM. The appraisal of the updated DPR of 1200 MW Tamanthi HE Project, Myanmar has been approved by CEA on 13th Sept’2012 and conveyed vide CEA letter No.2/Myanmar/1/CEA/PAC-2011/6312-15 dt. 12.10.12. Further measures for reduction of cost for making power saleable in India and implementation methodology of the project is to be finalized based on discussions between Government of India and Govt of Union of Myanmar. The updated DPR of Shwezaye HE Project is under examination by CEA / CWC / GSI / CSMRS.

Dhauliganga Intermediate, 210 MW and Goriganga-IIIA, 120 MW HE Projects in Pithoragarh Distt., Uttarakhand As per the Implementation Agreements, the projects have been taken on BOOT (Build, Own, Operate & Transfer) basis with an agreement period of 45 years. Application for approval of TOR (Terms of Reference) for EIA / EMP studies and balance field investigations for updating the DPR has been submitted to Ministry of Environment & Forest, Govt. of India. The projects are proposed to be implemented as per schedule to be approved by CEA and CCEA clearance by Govt. of India after accord of all other statutory clearances.  

***********

Page 35: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

ANNEX-III

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (d) OF UNSTARRED QUESTION NO. 1697 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

*********** MoUs/Agreement signed by POWERGRID/POSOCO (subsidiary of POWERGRID) with Foreign

Partners:

S. N.

MoU/ Agreement signed and

presently in vogue

Date of Signing

Purpose

Present Status

MoUs/ Agreement signed by POWERGRID 1. MOU signed between

POWERGRID and Sigma Power Engineering Consultants (SPEC), UAE, Dubai

26.06.2007 For submission of proposal for engineering consultancy services for 2 nos. 400kV GIS stations including associated OHL works for Dubai Electricity & Water Authority (DEWA). Sigma Power is a lead partner providing logistics support whereas POWERGRID is providing technical support services for the consultancy contract.

Consultancy services contract is expected to be completed during FY 2013-14.

2. MOU signed between Govt. of India, Govt. of Sri Lanka, POWERGRID and Ceylone Electricity Board (CEB)

09.06.2010 Feasibility study for Interconnection of India and Sri Lanka electricity Grids.

Draft Feasibility Report has been submitted to CEB in December, 2012.

3. MoU signed with KETRACO, Kenya

12.04.2011 For providing assistance to KETRACO for development of Power Transmission network in Kenya.

Based on MoU, POWERGRID has successfully completed three consultancy assignments for KETRACO. MoU is valid up to 11th April 2013.

4. A General Cooperation Agreement signed with Gulf Cooperation Council Interconnection Authority (GCCIA)

21.09.2011 For providing technical services in areas of Operation and Maintenance of HVDC, Telecom, Grid Operations, Technical services, system planning and operation, etc.

Opportunities are being explored in Gulf Region. MoU is valid up to September, 2013.

5. MoU signed with Ethiopian Electric Power Corporation (EEPCo), Ethiopia

21.11.2011 For providing assistance to EEPCo for development of Power Transmission network in Ethiopia.

Based on MoU, POWERGRID is executing consultancy assignment pertaining to Strategic Voltage in Ethiopia. MoU is valid up to 20th November, 2013.

Page 36: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

 

MoUs signed by POWERGRID with Domestic Partners Sl. No.

MoU signed Date of Signing

Purpose

Present Status

1. IL&FS Energy Development Company Limited, India

06.06.2012 To explore opportunities in selected territories outside India inter-alia in countries in Asia, Middle East and Africa and other emerging economies in the transmission, sub-transmission and distribution sector and any other related projects in the energy sector.

Opportunities are being explored. MoU is valid up to 5th June, 2014.

2. Telecommunications Consultants India Ltd., India

16.10.2012 To jointly pursue the business opportunities in various fields of Power Transmission, Consultancy Services, Inspection, Third Party Audit, Monitoring & Supervision of Power Projects, etc.

Opportunities are being explored. MoU is valid up to October, 2013.

3. National Aluminum Company Ltd.

19.10.2011

Manufacturing of Conductors (Aluminum and Aluminum Alloy) including research and development

Feasibility study is underway.

4. Rastriya Ispat Nigam Ltd. 16.12.2011

Manufacturing of Tower parts including research and development.

Feasibility study is underway.

5. Rastriya Ispat Nigam Ltd. 27.07.2012

Manufacturing of Electrical Grade CRGO / CRNO steel.

Feasibility study not commenced in view of initiative taken by Ministry of Steel for setting up Pilot

6. MoU signed with International Finance Corporation (IFC), an extended arm of the World Bank

15.03.2012 For extending co-operation between POWERGRID and IFC to identify and evaluate transmission projects for development and/or Own/ Co-own transmission Projects in Asian and African Continents by providing financial and technical services to Project’s client.

Exploring the opportunity to jointly implement transmission projects under BOOT (build, own, operate & transfer) basis in Bangladesh. MoU is valid up to 14th March, 2014.

MoU signed by POSOCO 1. MoU signed with Lawrence

Berkeley National Laboratory (LBNL), University of California, USA

12.12.2012 Regarding cooperation on exploration of future collaborations relating to Power System Operation, Electricity Markets, and Integration of Renewable Energy Resources between POSOCO and LBNL.

MoU is operational and knowledge sharing is taking place between POSOCO and LBNL.

Page 37: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

Project in a Joint Venture.

Joint Venture Projects of POWERGRID with Domestic Partners Sl. No.

Name of JVC [JV Partners)

Date of Signing of SHA/ JV

Agreement/ MOU

Purpose

Present Status

1. Powerlinks Transmission Ltd. [POWERGRID (49%) & TATA Power (51%)]

04.07.2003 Implementation of 400kV Transmission Lines associated with Tala HEP (1020 MW), Bhutan.

Project commissioned progressively by August 2006.

2. Torrent Powergrid Ltd. [POWERGRID (26%) & Torrent Power Ltd (74%)]

15.06.2006 Implementation of 400kV D/C Sugen – Pirana Transmission System associated with 1100 MW Gas Based Power Project at Sugen in Surat, Gujarat.

Project commissioned progressively by March, 2011.

3. Jaypee Powergrid Ltd. [POWERGRID (26%) & Jaypee Power Ventures Ltd (74%)]

22.02.2007 Implementation of 400kV D/C Karcham Wangtoo – Abdullapur transmission line associated with 1000 MW Karcham Wangtoo HEP in Kannaur District, Himachal Pradesh.

Project commissioned progressively by April, 2012.

4. Teestavalley Power Transmission Ltd. [POWERGRID (26%) & Teesta Urja Ltd. (74%)]

06.08.2008 Implementation of Teesta-III - Kishanganj 400kV D/C line associated with 1200 MW Teesta –III HEP in Sikkim.

Project under implementation and expected to be completed by December, 2013.

5. North-East Transmission Company Ltd. [POWERGRID (26%) & OPTCL (a JV between ONGC, IL&FS and Government of Tripura) (30%), Govt. of Assam (13%), Govt. of Tripura (10%), Govt .of Manipur (6%), Govt.of.Meghalaya (5%) Govt of Mizoram (10%)]

03.02.2009 Implementation of 400kV D/C Pallatana – Silchar – Bongaigaon transmission line to evacuate power from 726 MW Pallatana Gas based Power Project in the State of Tripura.

Pallatana – Silchar section already commissioned in August 2012 and Silchar – Byrnihat section commissioned in February 2013. Byrnihat – Bongaigaon section is expected to be completed in FY 2013-14.

6. Parbati Koldam Transmission Company Ltd. [POWERGRID (26%) & Reliance Infrastructures Ltd. (74%)]

23.11.2007 Implementation of Parbati II -Koldam and Koldam - Ludhiana 400kV lines associated with Parbati-II (800 MW) HEP and Koldam (800 MW) HEP in Himachal Pradesh.

Under implementation and expected to be completed by September 2013.

7. National High Power Test Laboratory Pvt. Ltd. [POWERGRID (20%) & NTPC Ltd. (20%), NHPC (20%), Damodar Valley Corporation (20%), Central Power Research Institute (20%)]

08.04.2009 Establishment of on-line high power short circuit test facility in India.

Under implementation and expected to be completed by December, 2013.

Page 38: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

************ 

 

 

ANNEX-IV

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (d) OF UNSTARRED QUESTION NO. 1697 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********

Details of MoUs signed by PFC are as follows:-

1. Power Finance Corporation Ltd. and Nuclear Power Corporation Ltd (NPCIL)

Date of signing - 28.10.2012. Purpose - To facilitate cooperation in financing of nuclear projects to be

setup. Status - PFC has considered the sanction of financial assistance of Rs. 8021

crore for setting up of Kakrapar Atomic Power station unit 3&4 (2x700 MW). The final sanction is subject to interest rate acceptance by NPCIL.

2. PFC Consulting Ltd (PFCCL), a wholly owned subsidiary of Power Finance Corporation Ltd. and Central Mine Planning and Design Institute Limited (CMPDIL) a wholly owned subsidiary of Coal India Limited Date of signing - 18.12.2012. Purpose - To combine their expertise and experience in order to offer

comprehensive consultancy services to power projects involving coal mine related activities on a commercial basis to various clients in the power sector. To facilitate cooperation in financing of nuclear projects to be setup.

Status - Consulting opportunities are being spotted by both PFCCL &

CMPDIL.  

 

***********

Page 39: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

ANNEX-V

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (d) OF UNSTARRED QUESTION NO. 1697 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********  

Details of MoUs signed by REC are as follows:-

Two Memorandum of Understanding has been signed with Andhra Pradesh Power Generation Corporation Limited (APGENCO), Andhra Pradesh and Karnataka Power Corporation Limited (KPCL), Karnataka, as per detailed below:

Sl. No.

Utility MOU signing date

Purpose Status

1 Andhra Pradesh Power Generation Corporation Limited (APGENCO), AP

16.08.2012 To provide financial assistance to APGENCO for their upcoming Generation projects

APGENCO has yet to submit loan proposal for their projects.

2. Karnataka Power Corporation Limited (KPCL), Karnataka

23.01.2013 To provide financial assistance to KPCL for their upcoming Generation Projects

KPCL has yet to submit loan proposal for their projects.

A Joint Venture Agreement was executed amongst REC, NTPC, PFC and PGCIL on 19.11.2009 for incorporation of a Company namely Energy Efficiency Services Ltd.

 

**********

Page 40: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

ANNEX-VI

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (d) OF UNSTARRED QUESTION NO. 1697 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

*********** Details of MoUs signed by SJVNL are as follows:-

Sl. No.

Name of the project

Date of signing of MOU/Agreement/JV

Agency Purpose Status

1 Nathpa Jhakri Hydro Power Station

July 23, 1991 (Agreement)

Government of Himachal Pradesh and Ministry of Power & NES, Government of India

Execution of Nathpa Jhakri Hydro Electric Project

Operational since 2004 with annual design energy generation capacity of 6,612 MU.

2 Rampur Hydro Electric Project

October 20, 2004 (Implementation Agreement)

MPP & Power, Government of Himachal Pradesh

Execution of Rampur Hydro Electric Project

Under advanced stage of construction, scheduled to be commissioned progressively from December 2013 onwards.

3 Luhri Hydro Electric Project

October 27, 2008 (MOU)

MPP & Power, Government of Himachal Pradesh

Execution of Luhri Hydro Electric Project

• FAC meeting held on 22.01.13 has recommended the proposal for Forest Clearance.

• EAC recommended for Environment Clearance in November, 2012.

• Because of increased environmental release, capacity has been reduced to 588 MW and DPR has been modified accordingly.

4 Dhaulasidh Hydro Electric Project

October 27, 2008 (MOU)

MPP & Power, Government of Himachal Pradesh

Execution of Dhaulasidh Hydro Electric Project

• TEC accorded by Govt. of HP on 25th June, 2011.

• Proposal for Investment approval submitted to Govt. of India.

• EAC recommended the case for environment clearance on 20.07.12.

• Stage-I Forest clearance accorded on March 06, 2012.

Page 41: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

5 Devsari Hydro Electric Project

November 21, 2005 (Implementation Agreement)

Irrigation and Power Department, Government of Uttarakhand

Execution of Devsari Hydro Electric Project

• TEC for the project accorded by CEA on 07.08.12.

• EAC meeting held on 27.12.11 recommended for Environment Clearance.

• In the 2nd meeting for Stage-I Forest Clearance, FAC of MoEF directed that NOC’s from Gram Sabha of affected village should be obtained, which is under progress.

6 Naitwar Mori Hydro Electric Project

November 21, 2005 (Implementation Agreement)

Irrigation and Power Department, Government of Uttarakhand

Execution of Naitwar Mori Hydro Electric Project

• TEC for the project accorded by GoUK on March 02, 2010.

• EAC recommended the project for environmental clearance on 27.12.2011.

• Diversion of Forest Land- Case forwarded by Nodal Officer to MoEF, RO, Lucknow on 19.01.13.

• The case is under consideration by the State Advisory Group, Dehradun.

7 Jakhol Sankri

Hydro Electric Project

November 21, 2005 (Implementation Agreement)

Irrigation and Power Department, Government of Uttarakhand

Execution of Jakhol Sankri Hydro Electric Project

• DPR submitted to Govt. of Uttarakhand on December 29, 2011 and is under examination.

• For forest clearance, State Board of Wild Life (SBWL) followed by National Board of Wild Life (NBWL) Clearance is required. Matter is being pursued with SBWL of GoUK.

• Environment and Forest clearance are dependent upon clearance from

Page 42: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

SBWL and NBWL.

8 Arun-III Hydro Electric Project

March 02, 2008 (MOU)

Government of Nepal Execution of Arun-III Hydro Electric Project

• DPR submitted to CEA and Govt. of Nepal on May 31, 2011 and is under examination.

• Signing of Detailed Project Agreement (DPA)- Awaited.

• The scoping documents/ToR regarding EIA/EMP approved on 27.12.12 by Ministry of Science Technology & Environment (MoSTE) of GoN.

9 Wangchhu Hydro Electric Project

October 12, 2010 (Agreement)

Department of Energy, Ministry of Economic Affairs, Royal Government of Bhutan

DPR preparation of Wangchhu Hydro Electric Project

• DPR submitted to CEA- Dec. 30, 2011.

• SJVN is mandated to execute this project in JV with Druk Green Power Company. JV Agreement is under finalization.

• Environment and Forest Clearances are under consideration of RGoB.

10 Kholongchhu Hydro Electric Project

December 22, 2009 (Agreement)

Department of Energy, Ministry of Economic Affairs, Royal Government of Bhutan

DPR preparation of Kholongchhu Hydro Electric Project

• DPR submitted to CEA and Royal Govt. of Bhutan (RGoB) on June 30, 2011.

• In-principle approval of DPR received.

• SJVN is mandated to execute this project in JV with Druk Green Power Company. JV Agreement is under finalization.

• Environment and Forest Clearances are under consideration of RGoB.

11 Buxar Thermal Power Project

January 17, 2013 (MOU)

Bihar State Power Holding Company Limited and Bihar Power Infrastructure Company

Implementation of 1320 MW Buxar Thermal Power Project

• NTPC and MECON have been approached for carrying out the consultancy work for review and updation of DPR of 1320 Buxar Thermal Power Project and other PMC activities.

Page 43: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

• PIB Note for making expenditure on pre construction activities submitted to MoP, GoI on February 13, 2013.

• Process for transfer of ownership of Buxar Bijlee Company Private Limited formed for this project to SJVN is under progress.

12 Renewable Energy Projects

May 29, 2012. (MOU)

Indian Renewable Energy Development Agency Ltd. (IREDA)

For mutual cooperation for development of Renewable Energy projects

No specific project proposal has been finalized till date.

13 Cross Border Power Transmission Company Limited (CPTC)

July 09, 2012(Share Holder Agreement)

PGCIL, IL&FSEDCL and Nepal Electricity Authority

For development of 400 KV D/C Muzaffarpur-Dhalkebar Transmission Line

Route, Detail survey

& the work of DPR completed.

Approval u/s 68 of EA 2003 & u/s 164 of EA 2003 received.

Transmission License received on 22.03.2011.

Implementation & Transmission Service Agreement (ITSA) has been signed on 13.12.2011 between CPTC and NEA.

Share Holder Agreement (SHA) has been signed on 09.07.2012 amongst PGCIL, IEDCL, SJVN Ltd & NEA .

PGCIL has been appointed as PMC on 10th Aug 2012.

Bid specification for EPC under finalization by PMC & NIT is scheduled during 2nd week of March, 2013.

Memorandum of Association for the same was signed on 25.06.2009.

Page 44: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

***********

Page 45: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

ANNEX-VII

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (d) OF UNSTARRED QUESTION NO. 1697 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********

MOUs signed by THDC India Limited with Government / Other PSUs

THDCIL have signed following MOUs with Government / Other PSUs:

1. MOUs with Government of Uttarakhand: (a) MOU regarding implementation of Vishnugad Pipalkoti HEP, signed on 08th April 2003.

(b) Implementation Agreement of Jhelam Tamak HEP, signed on 21st November 2005.

(c) Implementation Agreement of Malari Jhelam HEP, signed on 21st November 2005.

(d) Implementation Agreement of Karmoli HEP, signed on 21st November 2005.

(e) Implementation Agreement of Jadh Ganga HEP, signed on 21st November 2005.

(f) Implementation Agreement of Bokang Bailing HEP, signed on 21st November 2005.

(g) Implementation Agreement of Gohana Tal HEP, signed on 21st November 2005.

2. MOU with Government of Uttar Pradesh: (a) Implementation Agreement of Dhukwan Small Hydro Project, signed on 02nd September,

2009.

(b) MoU regarding implementation of Khurja STPP (1320 MW), signed on 31.12.2010

3. MOU with Royal Government of Bhutan: (a) MOU with Department of Energy, Royal Government of Bhutan for updation of DPR of

Sankosh MPP (4060 MW) signed on 23rd March, 2010.

(b) MOU with Department of Energy, Royal Government of Bhutan for updation of DPR of Bunakha HEP (180 MW) signed on 24th June, 2010.

4. MOU with Nuclear Power Corporation of India Limited (NPCIL): MOU has been signed between THDCIL and NPCIL on 27.02.2007 to identify hydroelectric projects as well as pumped storage schemes in India and abroad. To develop hydropower in Maharashtra, Government of Maharashtra has allotted two Pumped Storage Schemes in April’08 namely Malshej Ghat PSS (600 MW) and Humbrali PSS (400 MW) for updation of DPRs and identifying viability.

Page 46: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

***********

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA

UNSTARRED QUESTION NO.1698 ANSWERED ON 12.03.2013

SUPPLY OF SURPLUS POWER TO POWER DEFICIT STATES

1698. SHRI HUSAIN DALWAI: Will the Minister of POWER be pleased to state: (a) how many States are facing shortage of power and how many are producing surplus power; (b) whether there exist a system to provide power to power deficit States; (c) if so, the details thereof; (d) whether certain States are not in a position to provide their surplus power to power deficit States; and (e) if so, the reasons therefor?

A N S W E R THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a) : There is an overall shortage of power in all the States in the country. The shortage of power varies from State to State on month to month and day to day basis depending upon the demand and availability of power. Surplus power accrues in some of the States on seasonal basis or for a few days in a month or for certain hours in a day/year, depending upon the requirement and availability of power during the period. During the current year (April to December, 2012) the net export of energy was from the States of Himachal Pradesh, Jammu & Kashmir, Chhattisgarh, Madhya Pradesh, Odisha, Sikkim and DVC to other power deficit States. (b) & (c): The States generally dispose of the surplus power through power exchanges, trading licensees and bilateral agreements. (d) & (e) : Yes, Sir. The constraint in selling power may be in finding appropriate buyer at a particular cost of power or transmission constraints in certain corridors.

***************

Page 47: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

 

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA

UNSTARRED QUESTION NO.1699 ANSWERED ON 12.03.2013

ULTRA MEGA POWER PROJECTS IN THE COUNTRY

1699. SHRI P. BHATTACHARYA: Will the Minister of POWER be pleased to state: (a) the details of the existing Ultra Mega Power Projects (UMPPs) in the country; (b) whether Government proposes to construct more UMPPs during the current plan period; (c) if so, the details thereof, State-wise including West Bengal; and (d) the details of the amount allocated and utilized for this purpose during the last three years, year-wise and project-wise?

A N S W E R THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a) to (c): List of existing and proposed UMPPs along with details of location and status is

at Annex. The awarded UMPPs are expected in 12th Plan (except the last unit of Tilaiya UMPP,

which is likely to come in 13th Plan) as per schedule in the Power Purchase Agreement (PPA). At

present, there is no proposal for setting up of an UMPP in the State of West Bengal.

(d) : Under the Ultra Mega Power Projects (UMPPs) initiative launched by the

Ministry of Power, no financial allocation has been envisaged from the Government. The

projects are given to the bidder with the lowest levellized tariff. Further, the responsibility for

achieving financial closure and tying up of funds for meeting the requirement of the project rests

with the identified developers.

**********

Page 48: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

ANNEX

ANNEX REFERRED TO IN REPLY TO PARTS (a) TO (c) OF UNSTARRED QUESTION NO. 1699 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********

A. Awarded UMPPs.

Sl. No.

UMPP Location Status

Madhya Pradesh

1. Sasan (6x660MW)

Sasan in district Singrauli, Madhya Pradesh

Project awarded and transferred to M/s Reliance Power Ltd. on 07.08.2007. As per progress of the project,first Unit is expected to achieve Commercial operation Date (CoD) in March, 2013 and last unit in June, 2014.

Gujarat

2. Mundra (5x800MW)

Mundra in village Tundawand in district Kutch, Gujarat

Project awarded and transferred to M/s Tata power Ltd. on 24.4.2007. Four units have been commissioned so far in March, July, October, 2012 and January, 2013. Fifth unit has been synchronized and expected to achieve CoD in March, 2013.

Andhra Pradesh

3.Krishnapatnam (6x660MW)

Krishnapatnam in district Nellore, Andhra Pradesh

The Project awarded and transferred to M/s Reliance Power Ltd. on 29.1.2008. The developer has stopped work at site, citing new regulation of coal pricing in Indonesia. Procurers issued termination notice to Coastal Andhra Power Ltd. (CAPL), a Reliance Power Company on 15.3.12. CAPL approached Hon’ble High Court of Delhi. The Court has dismissed CAPL’s petition. CAPL has now approached the Division Bench, Delhi High Court and Indian Arbitrator Council. The Case is now subjudice. CAPL has also filed a petition before CERC in December, 2012 for revision of tariff. Jharkhand

4. Tilaiya (6x660MW)

Near Tilaiya village in Hazaribagh and Koderma Districts, Jharkhand

Project awarded and transferred on 7.8.2009 to M/s Reliance Power Ltd. Construction of the plant is held up as the land has not been handed over to the developer by Jharkhand Government.

…….2.

Page 49: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

- 2 -

B. Other UMPPs

Odisha 5. Bedabahal Near Bedabahal in Sundergarh

district, Orissa Request for Qualification (RFQ) bids for selection of the Developer of the project have been received on 1st August, 2011. Request for Proposal to be issued after SBDs are revised.

6. 1st and 2nd additional UMPPs in Orissa

Sites at Bijoypatna in Chandbali Tehsil of Bhadrak district for coastal location and at Narla&Kasinga sub division of kalahandi district for inland location have been identified.

State Government’s final decision is awaited.

Chhattisgarh 7. Chhattisgarh Near Salka&Khameria villages in

District Surguja, Chhattisgarh The RfQ was issued on 11.6.2010. The date of submission of RfQ for Chhattisgarh UMPP is being extended from time to time as Ministry of Environment and Forests (MoEF) has categorized coal blocks of this UMPP in “No Go” area. The last date for submission of RfQ bids now is 3.4.2013.

Tamil Nadu 8. Tamil Nadu Village Cheyyur, District

Kancheepuram, Tamil Nadu The site has been finalized. RfQ to be issued after Standard Bidding Documents (SBDs) are revised.

9 2nd Tamil Nadu UMPP

Not finalized --

Andhra Pradesh 10. 2nd Andhra

Pradesh UMPP

Village Nayunipalli, District Prakasam, Andhra Pradesh

Pre-RfQ stage

Jharkhand 11. 2nd Jharkhand

UMPP Site at Husainabad, DeogharDistt has been identified.

--

Gujarat 12. 2nd Gujarat

UMPP Not finalized --

Karnataka 13. Karnataka State Govt. has identified a

suitable site in Niddodi village of Mangalore taluka Dakshina Kannada District.

--

Maharashtra 14. Maharashtra Not finalized --

Bihar 15. Bihar Site at Kakwara in Banka Distt has

been identified.

 

Page 50: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

*********

 

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA

UNSTARRED QUESTION NO.1700 ANSWERED ON 12.03.2013

PROMOTION OF RENEWABLE SOURCES OF ENERGY

1700. SHRIMATI KANIMOZHI: Will the Minister of POWER be pleased to state: (a) whether the Central Electricity Regulatory Commission (CERC) has notified guidelines to promote renewable sources of energy and the development of its market in the country; (b) if so, the details thereof, State-wise; (c) whether these guidelines are binding on various State Electricity Regulatory Commissions; and (d) if so, the details thereof?

A N S W E R THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a) & (b) : The Central Electricity Regulatory Commission (CERC) has notified the Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010 to promote development of renewable sources of energy in the country. The salient features of the CERC REC Regulations are at Annex-I. The CERC has also issued regulations for determination tariffs for different RE technologies. (c) & (d): The CERC REC Regulations supplement the efforts of States Electricity Regulatory Commission (SERCs)/ Joint Electricity Regulatory Commission (JERCs) in terms of issuing their State specific REC Regulations recognizing the REC issued under the CERC REC Regulations as a valid instrument for fulfillment of renewable purchase obligation by the obligated entities in their States. Twenty Eight States have issued State specific REC Regulations. The list of such States is enclosed as Annex-II.

As regards tariffs, as per Section 61 of the Electricity Act, 2003, the principles and methodologies of tariff for generation and transmission specified by CERC are the guiding principles for SERCs.

**********

Page 51: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208
Page 52: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

ANNEX-I

ANNEX REFERRED TO IN REPLY TO PARTS (a) & (b) OF UNSTARRED QUESTION NO. 1700 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********  

 Salient features of the REC framework are as under:- Renewable Energy Certificate (REC) mechanism is a market based instrument to

promote renewable energy and facilitate meeting the renewable purchase obligations (RPO).

REC mechanism is aimed at addressing the mismatch between availability of RE resources in State and the requirement of the obligated entities to meet the renewable purchase obligation.

RE generators have two options (i) either to sell the renewable energy at preferential tariff or (ii) to sell electricity generation and environmental attributes associated with RE generations separately.

The environmental attributes can be exchanged in the form of REC.

REC is issued to the RE generators for 1 MWh of electricity injected into the grid from renewable energy sources.

REC is purchased by the obligated entities to meet their RPO under section 86 (1) (e) of the Act. Purchase of REC would be deemed as purchase of RE for RPO compliance.

Grid connected RE Technologies approved by MNRE are eligible under this scheme.

Central Agency carries out functions of registration, issuance of RECs, repository, and other functions for implementation of REC framework at national level.

Only accredited project can register for REC at Central Agency.

REC is exchanged only in the CERC approved power exchanges.

REC is exchanged within the forbearance price and floor price determined by CERC.

*********

Page 53: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

ANNEX-II

ANNEX REFERRED TO IN REPLY TO PARTS (c) & (d) OF UNSTARRED QUESTION NO. 1700 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********

1. Andhra Pradesh

2. Arunachal Pradesh

3. Assam

4. Bihar

5. Chhattisgarh

6. Delhi

7. Gujarat

8. Haryana

9. Himachal Pradesh

10. Jammu & Kashmir

11. JERC (Goa & UT)

12. Jharkhand

13. Karnataka

14. Kerala

15. Madhya Pradesh

16. Maharashtra

17. Manipur

18. Mizoram

19. Meghalaya

20. Nagaland

21. Odisha

22. Punjab

23. Rajasthan

24. Tamil Nadu

25. Tripura

26. Uttar Pradesh

27. Uttarakhand

28. West Bengal(Draft)

Page 54: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

*********

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA

UNSTARRED QUESTION NO.1701 ANSWERED ON 12.03.2013

PEAK POWER SHORTAGE IN HARYANA

1701. DR. KANWAR DEEP SINGH: Will the Minister of POWER be pleased to state: (a) the levels of peak power shortage in Haryana recorded in 2012; (b) the corrective steps being taken by Government; (c) whether special emphasis is being laid on rural power supply in the State; (d) if so, the details thereof; and (e) if not, the reasons therefor?

A N S W E R THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a): Power Supply position is monitored on financial year basis. Haryana peak power

shortage for April to December, 2012 was 9%.

(b): Government has enhanced the unallocated power of Central Generating Stations

of Northern Region from 121 MW - 188 MW to 308 MW – 342 MW in June, 2012 to mitigate

the power shortage of Haryana.

(c) to (e): Electricity being a concurrent subject, responsibility for its supply and distribution

to different categories of consumers in a State lies with the concerned State Government / Power

Utilities in the State. The priorities for supply of power to various categories of consumers in a

State, including rural areas, are also administered by the State Government. Government of India

supplements the efforts of the State Governments by establishing power plants in Central Sector

through Central Public Sector Undertakings (CPSUs).

Page 55: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

**********

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA

UNSTARRED QUESTION NO.1702 ANSWERED ON 12.03.2013

RANGANADI PROJECT OF NEEPCO

1702. SHRI BIRENDRA PRASAD BAISHYA: Will the Minister of POWER be pleased to state: (a) whether the North Eastern Electric Power Corporation (NEEPCO) is committed to fund flood protection work of Dikrong river due to additional discharge of water into it from Ranganadi project; (b) if so, the details thereof; (c) whether Assam had approached NEEPCO for funding of flood protection work of Dikrong river from the downstream Bandardewa to Dikrong confluence; (d) if so, the details thereof; (e) the action taken thereon; and (f) the benefits to Assam on account of Ranganadi project of NEEPCO?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a) & (b) : The Central Water and Power Research Station (CWPRS) in its findings, as per study conducted, had stated that the discharge of 160 Cumec water from the tail race of Ranganadi HEP into the Dikrong river system, is insignificant in comparison to the observed flood discharge of the Dikrong River which is about 2500 Cumec. This discharge leads to an incremental rise to the range of only 7-12 cm in different stretches (between Bandardewa and Sissapather) along its course in Assam. Therefore, it was not contemplated to take up flood protection measures of Dikrong river as part of the total project. (c) : No, Sir. (d) & (e) : Do not arise. (f) : NEEPCO has informed that the State of Assam is entitled to a share of 43.33% of generated power from Ranganadi Project.

Page 56: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

************

GOVERNMENT OF INDIA

MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.1703

ANSWERED ON 12.03.2013

AUDIT OF POWER TRANSMISSION COMPANIES BY CAG

†1703. SHRIMATI MAYA SINGH: Will the Minister of POWER be pleased to state: (a) the number of companies that have been accorded approval for the transmission licences by the Central Electricity Regulatory Commission till date; (b) whether auditors are appointed by the Commission to audit the accounts of such companies; (c) whether provisions of mandatory audit by CAG has been made a precondition to ensure independent audit of these companies and also to ensure that information regarding over-recoveries from the consumers may also be tracked; and (d) if not, the reasons therefor and, if so, the number of companies whose accounts have been audited by the CAG?

A N S W E R THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a) : As per the information provided by the Central Electricity Regulatory

Commission (CERC), 17 companies have been granted inter-state transmission licences by the

CERC during the period from November, 2003 to October, 2011.

(b) : The CERC does not appoint auditors to audit the accounts of the transmission

companies.

(c) & (d) : As per Section 619 of the Companies Act, 1956, an auditor of a Government

company shall be appointed by the Comptroller & Auditor General (CAG) and the auditor shall

audit the accounts under the control and directions of CAG. The Government owned

transmission licensees are required to get their audit done by an auditor appointed by the CAG.

Page 57: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

The transmission licensees regulated by CERC recover charges on the basis of the tariffs

determined and the regulation specified by CERC.

*********** GOVERNMENT OF INDIA

MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.1704

ANSWERED ON 12.03.2013

INCREASE IN POWER TARIFFS BY STATE ELECTRICITY BOARDS

1704. SHRI SANJAY RAUT: Will the Minister of POWER be pleased to state: (a) whether State Electricity Boards (SEBs) across the country are increasing power tariffs regularly; (b) the impact of hike in power tariff on the consumers; (c) whether the Ministry has asked States to reduce the transmission losses; and (d) if so, the details of aggregate transmission and commercial (AT&C) losses?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a) & (b) : The Electricity Act, 2003 has entrusted the responsibility of tariff fixation on the Electricity Regulatory Commissions and it empowers the State/Joint Electricity Regulatory Commissions (SERCs/JERCs) to fix tariffs for consumers. In this regard, SERCs / JERCs notify the Terms and Conditions of tariff fixation from time to time. Section 61 of the Act provides for guiding principles which the Appropriate Commission is required to consider for specifying the terms and conditions of tariff. Any person aggrieved by an order made by the Appropriate Commission under this Act may prefer an appeal to the Appellate Tribunal for Electricity. (c): Electricity is a concurrent subject and the responsibility of sub-transmission and distribution segment and reduction of Aggregate Transmission and Commercial (AT&C) losses in distribution network rest with the State Government and Power Departments/Utilities. Government of India acts as a facilitator in supplementing the efforts of States to provide power to consumers in an improved manner. However, with the aim to reduce the AT&C losses in the country and to improve the power distribution sector of state utilities, Government of India has launched the Restructured-Accelerated Power Development and Reforms Programme (R-APDRP) during 11th Plan period. Projects under the scheme are taken up in two parts in towns having population more than 30,000 (10,000 for special category States) as per census 2001. Part-A of the scheme is for establishing IT enabled system for energy accounting / auditing and Supervisory Control and Data Acquisition (SCADA) for big cities (population:4 lacs and Annual Energy Input: 350MU) whereas Part-B is for up-gradation, augmentation & strengthening of electrical infrastructure in project towns. So far, under R-APDRP, projects worth Rs.32323.70 crores (Part-A: Rs 6638.79 crores covering 1402 towns and 63 SCADA projects in 63 towns; Part-B: Rs. 25684.91 crores in 1132 towns) have been sanctioned.

Page 58: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

(d): Aggregate Technical and Commercial (AT&C) Losses for the States and UTs, for the year 2008-09, 2009-10 & 2010-11 as per the Power Finance Corporation’s Report on Performance of State Power Utilities for the year 2008-09 to 2010-11are given at Annex.

*********

ANNEX

ANNEX REFERRED TO IN REPLY TO PART (d) OF UNSTARRED QUESTION NO. 1704 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

*********** AT&C losses(%) for utilities selling directly to the consumers

Region State Utility 2008-09 2009-10 2010-11Eastern Bihar BSEB 34.37 43.92 47.44 Jharkhand JSEB 54.16 10.21 46.79 Orissa CESCO 46.84 39.98 45.54 NESCO 38.90 36.70 38.47 SESCO 50.59 51.00 54.12 WESCO 37.55 37.58 43.84 Sikkim Sikkim PD 46.81 55.36 51.96 West Bengal WBSEDCL 25.81 33.24 27.40 North Eastern Arunachal Pradesh Arunachal PD 60.15 58.82 61.45 Assam CAEDCL 39.36 LAEDCL 29.23 UAEDCL 31.42 APDCL 29.31 29.19 Manipur Manipur PD 81.32 47.55 40.17 Meghalaya MeSEB 43.37 48.77 MeECL 51.63 Mizoram Mizoram PD 41.08 38.95 41.00 Nagaland Nagaland PD 44.12 46.16 50.07 Tripura TSECL 31.91 29.16 34.48 Northern Delhi BSES Rajdhani 20.59 19.83 15.80 BSES Yamuna 13.73 28.63 18.13 NDPL 17.64 15.68 13.75 Haryana DHBVNL 32.60 28.11 26.29 UHBVNL 34.00 30.58 29.85 Himachal Pradesh HPSEB 12.85 18.46 35.48 HPSEB Ltd. 12.22 Jammu & Kashmir J&K PDD 69.05 70.44 72.86 Punjab PSEB 18.51 17.73 PSPCL 17.47 Rajasthan AVVNL 31.28 33.04 26.80 JDVVNL 30.19 31.51 23.73 JVVNL 28.40 26.70 22.66 Uttar Pradesh DVVN 28.25 49.62 55.39 KESCO 53.44 51.66 44.11 MVVN 29.90 37.58 37.57 Pash VVN 29.38 27.68 31.61

Page 59: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

Poorv VVN 49.75 27.86 40.43 Uttarakhand Ut PCL 39.89 28.35 28.48 Southern Andhra Pradesh APCPDCL 14.24 17.93 20.56 APEPDCL 10.26 9.69 14.51 APNPDCL 14.37 18.52 16.07 APSPDCL 11.36 16.63 14.20 Karnataka BESCOM 19.17 21.10 22.75 CHESCOM 25.33 28.21 28.73 GESCOM 38.80 38.05 25.75 HESCOM 33.90 28.51 26.22 MESCOM 14.01 18.40 13.75 Kerala KSEB 21.61 14.90 14.09 Puducherry Puducherry PD 18.47 19.35 14.43 Tamil Nadu TNEB 14.39 18.87 19.90 Western Chhattisgarh CSEB 30.46 CSPDCL 38.29 36.28 28.64 Goa Goa PD 21.69 6.12 14.08 Gujarat DGVCL 16.11 15.23 13.08 MGVCL 14.98 15.27 14.83 PGVCL 31.78 32.35 26.75 UGVCL 16.31 18.89 7.20

Madhya Pradesh MP Madhya Kshetra VVCL 50.24 42.26 43.95

MP Paschim Kshetra VVCL 36.38 36.16 31.12

MP Purv Kshetra VVCL 55.84 46.11 37.99

Maharashtra MSEDCL 31.19 25.02 23.30 Note: AT&C Losses for Sikkim PD (for 2008-09 to 2010-11), APSPDCL (for 2009-10 and 2010-11) and BSES Rajdhani (for 2010-11) include transmission losses since the figure for transmission losses is not available Note: Collection efficiency for J&K PDD for 2008-09 to 2010-11 has been calculated based on figures for revenue realized available in Resource Plan submitted by them to Planning Commission.

(Source: PFC’s Report on Performance of State Power Utilities for the year 2008-09 to 2010-11)  

************ 

 

Page 60: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA

UNSTARRED QUESTION NO.1705 ANSWERED ON 12.03.2013

SPEEDY DISPOSAL OF POWER THEFT CASES

1705. SHRI DHIRAJ PRASAD SAHU: Will the Minister of POWER be pleased to state: (a) whether power theft is a major impediment in the growth of power sector in the country; (b) if so, the number of cases of power theft registered during the last three years; (c) whether any special courts have been set up for speedy disposal of power theft cases; and (d) if so, the details thereof ?

A N S W E R THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA ) (a) : Bringing down the Aggregate Technical and Commercial (AT&C) losses in the

distribution segment of the power sector remains one of the important challenges before the

distribution companies. AT&C loss has two major components viz., technical loss and

commercial loss. Theft of electricity contributes to commercial loss and results in loss of revenue

to the distribution companies as the billable units of distribution companies go down due to theft

of electricity which puts an avoidable burden on the paying consumers.

(b) : Based on available information, the number of cases in power theft registered is at

Annex-I.

(c) & (d) : Special Courts have been constituted by the State Government in 27 States, the

list of which is at Annex-II.

**********

Page 61: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

Page 62: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

ANNEX-I

ANNEX REFERRED TO IN REPLY TO PART (b) OF UNSTARRED QUESTION NO. 1705 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

*********** The details of Theft Cases in various States / Uts ( (As on 5.3.2013)

Category of Consumer State/ UT

Power Utilities Number of theft cases Industrial

consumer Commercial Consumer

Agriculture consumer

Domestic Consumer

Number of Prosecution

Details of Penalty

(Rs.in lakhs)

Remarks

1 2 3 4 5 6 7 8 9 10 Andaman & Nicobar Electricity Deptt. Adm. 0 0 0 0 0 0 0.00 Assam

APDCL 1690 23 442 1225 1164

Mostly all cases have been compounded

Andhra Pradesh APSPDCL 2007-08 2723 771 1135 817 0 0.00 2008-09 1409 400 883 126 0 0.00 2009-10 1943 281 1077 585 0 0.00 2010-11 1414 351 767 296 0 0.00 Total 7489 1803 3862 1824 0 0.00 APNPDCL, Warangal 2007-08 157 4 152 1 157 0.00 2008-09 173 11 148 14 173 0.00 2009-10 139 8 118 13 139 0.00 2010-11 163 7 154 2 163 0.00 Total 632 30 572 30 0 632 0.00 APNPDCL,

Karimnagar

2007-08 94 3 90 1 94 0.00 2008-09 48 2 46 0 48 0.00 2009-10 154 17 128 9 154 0.00 2010-11 393 10 86 1 393 0.00 Total 689 32 350 11 689 0.00

Page 63: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

APNPDCL, Khammam 2007-08 223 2 192 29 223 0.00 2008-09 112 2 102 8 112 0.00 2009-10 72 0 72 0 72 0.00 2010-11 71 0 69 2 71 0.00 Total 478 4 435 39 478 0.00 APNPDCL, Nizamabad 2007-08 68 4 64 0 68 0.00 2008-09 63 2 60 1 63 0.00 2009-10 110 2 107 1 110 0.00 2010-11 323 12 304 7 323 0.00 Total 564 20 535 9 564 0.00 APNPDCL, Adilabad 2007-08 89 6 83 0 89 0.00 2008-09 110 3 106 1 110 0.00 2009-10 84 1 83 0 84 0.00 2010-11 83 1 82 0 83 0.00 Total 366 11 354 1 366 0.00 Total in APNPDCL 2729 97 2246 90 0 2729

APCDCL 9305 1708 7537 60

4 0.00

Year-wise details notfurnished. Penalty in 1 no.of case

APEPDCL 3414 375 2146 893

38

0.00

Year-wise details not furnished. Penalty in 5 no. of case

Total in AP 22937 3983 15791 2867 0 2771 0.00 Penalty in 6 no of cases Chandigarh Electricity Deptt. 2010-11 256 1 116 2 2 15.84 Delhi BSES Rajdhani

Ltd(BRPL) 44003 672 8075 50 35206 5240 725.00 Total no. of cases after the

enactment of Electricity

Page 64: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

(Amendment) Act, 2007 BSES Yamuna

Ltd(BYPL) 55470 2655 10197 0 42618 6123 582.16

 

 

 

Goa Dptt. Of Electricity

Details for 2008-09 & 2009-2010 not furnished.

2010-11 0 0 0 0 0 0 0.00 2011-2012 10 0 10 0 0 0 3.95 Total in Goa 10 0 10 0 0 0 3.95 Gujarat TPL-Ahemdabad 2007-08 11158 159 1987 4 2 4.55 +2yrs. R.I. & 1 year R.I. 2008-09 12879 522 2151 7 0 0.00 2009-10 12034 747 3841 1 1 0.00 + 3 years R.I. 2010-11 10526 1211 2824 2 2 2.44 +1 year R.I. & 1 year R.I. Total 46597 2639 10803 14 5 6.99 TPL-Surat 2007-08 3882 125 297 0 54 1.90 2008-09 3915 141 362 0 307 5.18 2009-10 3439 100 307 0 263 4.14 2010-11 2750 38 170 0 100 0.53 Total 13986 404 1136 0 724 11.75 Total in Gujarat 60583 3043 11939 14 729 18.74 Haryana DHBVN 2007-08 20700 419 3987 1040 492 3438.44 2008-09 22121 322 4070 592 888 4718.43 2009-10 23433 150 4571 697 873 4862.21 2010-11 18724 54 3708 596 29 4408.46 Total 84978 945 16336 2925 2282 17427.54 UHBVN 2007-08 13538 0 0 0 492 1669.09 2008-09 11885 0 0 0 232 1872.18

Page 65: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

2009-10 20935 0 0 0 84 3469.85 2010-11 33310 86 4518 872 67 5211.54 Total 79668 86 4518 872 875 12222.66 Total in Haryana 164646 1031 20854 3797 0 3157 29650.20

Page 66: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

 

Himachal Pradesh HPSEBL 2007-08 302 0 100.32 2008-09 553 2 237.84 2009-10 321 2 105.67 2010-11 194 0 36.58

*includes Industrial, Agriculture and Domestic consumers

2011-12 211

Category-wise details not furnished

1 120.40

Category-wise break-up not furnished.

2012-13 upto june 2012 255 255 Total in HP 1836 0 0 4 600.81 Jharkhand JSEB 2007-08 1118 0 1050.00 2008-09 3235 0 2669.00 2009-10 4238 0 2476.00 2010-11 6757

Category-wise details not furnished

0 2032.00 Total in Jharkhand 15348 0 0 0 0 8227

J&K

EM&RE 1619 195 650 0 774 0

39.96 Year-wise details not furnished

Karnataka BESCOM 2007 7071 129 216 0 6726 1542 321.21 2008 4754 223 213 1 4317 1251 721.04 2009 3346 336 330 8 2672 1009 797.29 2010 2334 167 157 8 2002 544 1155.69 Total 17505 855 916 17 15717 4346 2995.23 HESCOM 2007 3115 413 211 16 2475 219 642.62 2008 3775 376 198 5 3196 198 1519.90 2009 4004 500 231 11 3262 225 1237.98 2010 5175 390 159 7 4619 132 955.94 Total 16069 1679 799 39 13552 774 4356.44 GESCOM 2007 2350 114 187 1 2048 338 98.68

Page 67: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

2008 3188 145 222 2 2819 433 210.05 2009 4573 312 286 0 3975 913 364.96 2010 10309 492 597 0 9220 686 507.57 Total 20420 1063 1292 3 18062 2370 1181.26 MESCOM 2007 560 15 32 9 504 10 102.96 2008 667 26 37 26 578 34 122.45 2009 821 21 23 7 770 43 167.23 2010 549 19 22 24 484 13 103.92 Total 2597 81 114 66 2336 100 496.56 CESC 2007 1111 81 47 1 982 59 117.79 2008 1108 82 59 1 966 15 162.28 2009 934 78 48 2 806 57 151.30 2010 575 30 25 1 519 5 57.65 Total 3728 271 179 5 3273 136 489.02 HESCL(Hubli) 2007 3418 0 22 1263.15 2008 3614 0 26 1137.79 2009 4436 0 79 977.12 2010 4006 0

Category-wise details not furnished 110 867.36

Total 15474 0 0 0 237 4245.42 Total in Karnataka 75793 3949 3300 130 52940 7963 13763.93 Kerala

KSEB

Category-wise details not furnished

Details upto Feb 2011 1968 84 384 51 1 1534.44

2011-12 upto Sep 2011

189 0 0 0 0

179.62

Details furnished upto Sept 2011 & category-wise details not furnished

Total in Kerala 2157 84 384 51 0 1 1714.06 Madhya Pradesh MPMKVVCL,

Jabalpur 108539 2918 4028 26455 39001 3603.00

MPMKVVCL, 139993 1983 7676 50485 19126 92.00

Page 68: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

Bhopal MPMKVVCL, Indore 117225 762 4316 52256 11810 317.00 Total in MP 365757 5663 16020 129196 69937 4012.00

 

 

Maharashtra BES&T 2007-08 1018 29 589 Nil 400 Nil 2008-09 910 14 443 Nil 453 0 2009-10 868 2 356 Nil 510 0 2010-11- upto Dec,

2010 428 2 192 Nil 234 0

Total 3224 47 1580 0 1597 0 0.00 MSEDCL 2007-08 5252 193 526 226 4307 15 1.28 In 134 no of cases,

accused paid compounding charges amounting to Rs. 7.16 lakhs

2008-09 5044 234 509 323 3978 8 3.92 In 80 no of cases, accused paid compounding charges amounting to Rs. 1.84 lakhs

2009-10 12027 459 1335 717 9516 15 1.22 In 37 no of cases, accused paid compounding charges amounting to Rs. 0.88 lakhs

2010-11 9229 255 1027 349 7598 12 0.92

2011-12 13308 220 931

365 11792 10 10.90 In 3 no of cases, accused paid compounding charges amounting to Rs. 0.12 lakhs

2012-13 upto Sep 2012 11361 141 423

168 10946 107 137.91 In 107 no. of cases charge sheet filed, and sent to trial court.

Total 56221 1502 4751 2148 48137 167 156.15

Page 69: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

RIL 2007-08 104 12 80 0 12 27 101.99 Mostly all cases have

been compounded 2008-09 169 12 109 9 48 28 94.23 Six months imprisonment

and fine of Rs. 5000/- 2009-10 239 6 168 0 65 31 79.94 Mostly all cases have

been compounded 2010-11- upto Jan,

2011 209 1 159 0 49 28 36.28 Mostly all cases have

been compounded Total 721 31 516 0 174 114 312.44 Mostly all cases have

been compounded TATA Power 0 0 0 0 0 0 0.00 Total in Maharashtra 60166 1580 6847 2148 49908 281 468.59 Mizoram Power & Electricity Deptt.

0 0 0 0 0 0 0.00

Nagaland Deptt. of Power 0 0 0 0 0 0 0.00 Odisha NESCO Ltd. 2007-08 26 2 6 0 18 26 0.00 Prosecution Under trial 2008-09 39 2 8 1 28 39 0.00 Prosecution Under trial 2009-10 60 3 9 3 45 53 1.78 Prosecution Under trial 2010-11 85 4 14 1 66 77 6.90 Prosecution Under trial 2011-12 86 6 25 7 48 69 14.19 2012-13 upto Sep 12 63 4 7 0 52 21 7.11 Prosecution Under trial Total in Odisha 359 21 69 12 257 285 29.98 Puducherry Electricity Deptt 0 0 0 0 0 0 0.00 Punjab

PSPCL 23557 category-wise details not furnished 79

2216.69 category-wise details not furnished

Tamil Nadu TANGEDCO

(Upto Feb 2011) 20393 1062 7361 1829 0 28 5235.2 Year-wise details not

furnished.

Page 70: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

Tripura TSECL 2006-07 11610 358 44.50 84 persons prosecuted 2007-08 8863 106 31.28 72 persons prosecuted 2008-09 11353 213 58.95 127 persons prosecuted 2009-10 12320 22 55.92 15 persons prosecuted 2010-11 upto Dec,

2010 7231

Category-wise details not furnished

34 28.28 17 persons prosecuted

Total in Tripura 51377 0 0 0 0 733 218.93 315 persons prosecuted

 

 

Uttar Pradesh UPPCL 2008 48319 33439 28602.32 Assessment 2009 35062 21353 22966.63 Assessment 2010

39349 26714

2693.14 Only compounding charges

2011 upto Oct 2011 24892

Category-wise details not furnished

16025 2260.83 Only compounding charges

Total 147622 0 0 0 0 97531 56522.92

KESCL, Kanpur 1752 129 373 315 734 474.72 Year-wise details not

furnished. NPCL 0.00 * Figures include

Domestic &Temporary connections

2007-08 816* 0 21 44 2.69 2008-09 1067* 0 9 26 2.58 2009-10 1059* 0 17 18 4.89 2010-11 -upto Dec,

2010 1102* 0 15 22

4.73 Total 4044* 0 62 110 0 14.89 0 Total in UP 153418 129 435 425 98265 57012.53 West Bengal CESC Ltd. 20408* 793 1474 707 7219.00 * Includes theft by

domestic consumers & unauthorized thefts.

DPSC Ltd. 2 2 0 0 2 405.91 One case pending in court WBSEDCL

Page 71: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

2007-08 1127 418 437 272 772 1339.30 2008-09 1132 394 462 276 854 1369.10 2009-10 1398 257 753 388 816 1054.96 2010-11 414 264 740 410 546 1352.53 Total 4071 1333 2392 1346 0 2988 5115.89 Total in West Bengal 24481 2128 3866 1346 3697 12740.80

Total in the Country 1146112 26220 106472 143094 181703 200461 137292

***************

Page 72: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208
Page 73: RAJYA SABHA UNSTARRED QUESTION NO.1691 GAS …powermin.nic.in/sites/default/files/uploads/Raj_12032013_Eng.pdf · GAS-BASED POWER PROJECTS IN THE COUNTRY ... 42 Godavari CCPP 208

ANNEX-II

ANNEX REFERRED TO IN REPLY TO PARTS (c) & (d) OF UNSTARRED QUESTION NO. 1705 TO BE ANSWERED IN THE RAJYA SABHA ON 12.03.2013.

***********  

STATUS OF SPECIAL COURTS SET UP BY THE STATE GOVERNMENTS AS PER SECTION-153 THE ELECTRICITY ACT, 2003 (AS ON 04.03.2013) Sl. No. States Whether the Special Courts set-up or not

(Section 153 of the Act) 1. Andhra Pradesh Yes 2. Assam Yes 3. Bihar Yes 4. Chhattisgarh Yes 5. Delhi Yes 6. Gujarat Yes 7. Haryana Yes 8. Himachal Pradesh Yes 9. Jharkhand Yes 10. Karnataka Yes 11. Kerala Yes 12. Madhya Pradesh Yes 13. Maharashtra Yes 14. Meghalaya Yes 15. Odisha Yes 16. Punjab Yes 17. Rajasthan Yes 18. Tamil Nadu Yes 19. Uttar Pradesh Yes 20. Uttarakhand Yes 21. West Bengal Yes 22. Arunachal Pradesh No 23. Goa Yes 24. Jammu & Kashmir Yes 25. Manipur Yes 26. Mizoram No 27. Nagaland Yes 28. Sikkim Yes 29. Tripura Yes

Total 27

*******