183
Table of contents Contents Page Nos. Acknowledgement ................................... i Letter transmittal ................. ................... ii Objective of the report .............. ...................... iii Abstract ................................... . iv Introduction ........ ............................ v Part I – The Company ............... ..................... 1 Site Location .................................... 1 Mission and vision statement .................................... 2 Core values .................................... 2 PHILEX MINING CORPORATION 1

Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Embed Size (px)

Citation preview

Page 1: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Table of contents

 

Contents                                                                                                         Page Nos.

 Acknowledgement                               ...................................                            i

Letter transmittal                                   ....................................                            ii

Objective of the report                          ....................................                           iii

Abstract ....................................                             iv        

Introduction                                     ....................................  v

 

Part I – The Company                           ....................................                         1          

Site Location                                          .................................... 1

Mission and vision statement                .................................... 2

Core values                                             .................................... 2

Corporate structure                                 .................................... 3

Organizational structure                         .................................... 4

 

The Sto. Tomas II Ore Deposit             .................................... 5

Location   .................................... 5

 Geology                                                .................................... 6

Lithology                                               .................................... 10

History and production                          .................................... 12-20

Mining method                                       .................................... 21-32

 

Part II – Divisions and Departments .................................... 33

The administrative division                     .................................... 33

The human resource department .................................... 33

The safety department                              .................................... 33

The geology department                           .................................... 35

1

Page 2: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

 The Mine Division

                                    

A.   Planning department           .......................... 40

B.   Mine development department        .......................... 43

C.   Mine production department             .......................... 44

D.   Mechanical/Electrical services Group ......................... 45

 

The Mill Division      ........................... 46

A.   Mill maintenance                         ........................... 46

B.   Metallurgy department                      ............................. 46

C.   Metallurgy test and research section ............................ 48

D.   Mill Engineering section                   ............................. 48

E.   Assay department                             ............................ 48

F.    Tailings pond                                     ........................... 49

 

2

Page 3: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Environmental and Community Relation

A.   Environmental management            ....................................

B.   Labor relations                                  ....................................

C.   Community development                 ....................................

D.   The security department                   ....................................

E.   Major awards/citations                     ....................................

 

Part III-Appendix                                                   .......................................

A.     Pictorials                                                         .......................................

B.     Other documents                               ....................................

 

 

3

Page 4: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

ACKNOWLEDGEMENT

The worth remembering experiences, the breath taking challenges, the learning

adventures - these would be nothing without the presence of the following persons whom I

awe a lot my thanks in allowing me to experience all of those first time and unforgettable

remarks in my life. Allow me to acknowledge the names of the following persons who serve

as my inspiration in accomplishing this terminal report. Without your presence, I would not

have a great on-the-job-training and this report would not have been written.

To our Heavenly Father, I am very much thankful for the ever burning guidance and

protection. Your presence serves as our provider of light when we are in darkness, our best

guide when we are lost and our savior when I am at risk.

To my family, Daddy Kid, Mamang Bon, Joy, Jr, and Jalal for their never ending love

and untiring support both in moral and financial aspects. You serve as my strength especially

when challenges come.

To Engr. Osita L. Catipay, Chair-Mining Engineering Department for giving us the

privilege to undergone the said Mine and Mill Practice in Philex. Even you are in difficulties

emotionally, your still always there for us as our second mother.

To Engr. Armando L. Malicse, for imparting his knowledge in safety and structural

geology. The lessons we took up give us an early overview on the different conditions in

underground.

To Engr. Ramon G. Roña, for the dedication in teaching the principles and theories

inside underground mining, rock mechanics and mineral exploration. Your teachings were

never been wasted as we applied it in underground duties.

To Engr. Samuel O. Tagsip, for sharing his knowledge in all metallurgical subjects.

Our discussions give us an edge from our fellows.

To Engr.Pepito T. Echavez, for imparting his knowledge in underground surveying. It

helped us to easily understand the activity procedures in the surveys underground.

To all the managers, supervisors, coordinators, miners, for all the knowledge and

information shared to us. Your enthusiasm and generosity are worth recognizing.

4

Page 5: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

To Sir Cocoy and Ma’am Sherryl, for all the patience and in making this OJT

memorable.

To Mommy Julia, Mommy Julia, Mommy Louei, Mommy Weng, Mommy Marlyn

and Mommy Judith for the unconditional love and for the best effort you exerted just to meet

our wants.

To all my fellow OJTs, our bonding experiences, our cultural differences, our

exchange of laughter and unique individual characteristics made this whole training

unforgettable.

Especial mention to all my group mates whom I shared most of my time in my

underground duties, both in serious and funny moments. I will miss our stupid moments

underground. Thank you Joseph, Leomar, Vincent, Billy, Carol, Mark, and Earvin.

You will be always treasured and remembered.

5

Page 6: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

ABSTRACT

The Mine and Mill Practices accomplished in Philex Mining Corporation in Padcal,

Tuba , Benguet, which lasted for 45 days was chiefly the application of the theories and

lectures studied from school. This report discusses the history of Philex Mining Corporation

and its ore body, which is the Sto. Thomas II and three main divisions of operation were

tackled.

In Mine Divisions, the paper focuses on the mine planning and design, development

and production of the mine with some figures, tables and plans.

In Geology Division, the district and regional setting of the ore body were presented

with the help of cross-sections, figures and maps. It also comprises of lectures regarding the

exploration, mineralogy and petrography, ore reserve, underground sampling and mapping,

diamond drilling and core logging and engineering geology.

In Metallurgical Division, the milling process undergone by the proper run of mine ore

from the primary crusher up to its concentrate and how the valuable metal contained in the ore

were treated to be able to separate from its gangue.

6

Page 7: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

HIGHLIGHTS OF THE TRAINING

To become green and responsible mineral extraction company is a greatest challenge

to all mining companies here in the Philippines. This is to answer the challenge given by anti-

mining organizations. Today is the best time for everyone in the mining industry to stand and

open the mine of those one sided individuals.

MINING, as one of the basic industry responsible for the development of the modern

civilization, is also held as the prime mover that leads man to technology advancement.

Since minerals, the basic raw materials for technological manufacturing, are nowhere to

found, explorations and development have always been found.

The prime purpose of this report is to acquire knowledge, information and skills in

different aspects based on the actual observation on the daily activities in mining operation

during the forty five days of training at Philex Mining Corporation. Through this training, the

student trainee were exposed and became aware to all actual events that occur in the field and

became motivated in pursuing the chosen careers.

Having enough knowledge in mining operations and became exposed in one of the most

known responsible mining company of the country, the trainees are assumed to be prepared

on their role as one of the prime movers and good ambassador for green mining.

This report aims to impart knowledge to the interested readers especially the Mining

Engineering students who wish and plan to undergo their Summer Mine and Mill practice in

Philex Mining Corporation.

7

Page 8: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

INTRODUCTION

Mine and Mill Practice is a pre-requisite subject in compliance in the Bachelor of

Science in Mining Engineering course. This 6-unit subject undertaking is offered every

summer term intended to pre-senior student and served as the actual application of the

theories learned from school for it to be more effective. Its prime purpose is to expose the

students to the actual scenario of his/her profession.

And so this year, eight (8) of the Cebu Institute of Technology - University Mining

Engineering pre-senior students were sent to undergo their Mine and Mill practice at Philex

Mining Corporation in Padcal, Tuba, Benguet, Philippines.

Truly, Philex Mining Corporation is a “gift of God, a work of Man”, striving to

become a world-class mineral extracting company.

In order to share our experiences especially to the Mining Engineering students who

have not yet undergo their practice, the students consolidated all they had learned about the

company to generate this report. This is based on the students’ observations and evaluations

during the actual operation. This report will serve as guide to the succeeding trainees.

8

Page 9: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

GENERAL TRAINING SCHEDULE

Area / Activity Duration Schedule Date

Processing of Papers 7:30 AM – 4:00 PM April 10, 2012

Policy Orientation

a. Philex (History, VMG, etc)

b. Security

c. Camp Administration

d. Community Development

e. Environment

7:00 AM – 4:00 PM April 11, 2012

Safety Policies / Productivity 7:00 AM - 4:00 PM April 12, 2012

Community Development / Forestry and

Tailing Pond Tour7:00 AM - 4:00 PM April 13, 2012

Geology / Exploration Exposure 7:00 AM - 4:00 PM April 14, 2012

Rest Day April 15, 2012

MINE PLANNING AND DESIGN

SECTION(c/o BS PALMA)

8 hrs.x 2 days

=16hrs.April16-17, 2012

MINE SURVEYING SECTION(c/o R.S

FIDELLO)

8 hrs. x 2 days=16

hrs.

April 18-19,

2012

DRAW CONTROL SECTION (c/o BL

Tamargo)

8 hrs. x 2 days=16

hrs.

9

Page 10: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

April 20-21,

2012

April 22-23,

Rock Mechanics Section (c/o J.E AGUSTIN)8 hrs.x 2 days= 16

hrs.

Mine Development (c/o Shift Managers and

Development Supervisors)

Vertical Driving 3 daysApril 24 – 26,

2012

Horizontal Driving and Rock Bolting 3 daysApril 27 – 29,

2012

Rock Support Installation 3 daysApril 30-May02,

2012

Fanhole Drilling 4 daysMay 03 – May

06, 2012

Mine Production (c/o Shift Managers and

Production Supervisors)

Rock breaking 3 daysMay 07 – 09,

2012

Ore Extraction/Scooping/LHD 3 daysMay 10 – 12,

2012

Operation Ore Rehandling 4 daysMay 13 – 16,

2012

CHC and FBC Operation 3 daysMay 17 – 19,

2012

10

Page 11: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

ASSAY Lab (c/o E.A Aquino)2 days x 8 hrs. = 16

hrs.

May 20 – 21,

2012

Mill Plant 1 day May 22, 2012

Terminal Report Writing 1 day May 23, 2012

Evaluation 1 day May 24, 2012

Panel Interview 1 day May 25, 2012

Home Sweet Home May 26, 2012

I. The Company

Company Profile

Name of Company: Philex Mining Corporation

Address: Camp 3, Tuba, Padcal, Benguet

Telephone Number: (0919)24208126 or (074)4427278

Fax Number: (0973)729161

Company Classification: Mining Company

Year Incorporated: 1955

Location of Mill Plant: Ampucao, Itogon, Benguet

Location of Mine Camp: The Mine Camp is 17 aerial kilometers southeast of Baguio City

Name of Orebody: Sto. Tomas II Orebody

Type of Mineralization: Porphyry Copper

11

Page 12: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Products: Copper (main), Gold and Silver (by-products)

Mining Method: Underground Block Caving using Load-Haul-Dump

Market: Pasar, Leyte/Centrotrade, Japan

Year Operation Started: 1958

Initial Ore Reserve: 18.0 million metric tons with 0.90%Cu and 0.977gram Au/ton

Initial and Present Production Rate: 800 tons per day and 26,000 MT per day respectively

Vision Statement

To be highly respected word-class natural resource company committed to

deliver excellent value to its investors, employees and other stakeholders.

Mission Statement

We are a responsible mining corporation that discovers and processes minerals

and energy resources for the use of society.

Core Values

Work Excellence

Produces work results in a timely accurate and safe manner

Constantly learns, innovates, amends, and improves services and processes

Consistently delivers superior quality of work

12

Page 13: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Social and Environmental Responsibility

Shows genuine concern toward its host communities to improve quality of life

Supports and practices the environment, safety, and health guidelines of Philex Mining

Corporation

rkActively participates in the company’s community development and environment

programs

Integrity

Practices honesty and sincerity in word and deed

Honors commitments

Speaks up when situations warrant commendation or correction

Teamwork

Listens to and considers ideas or points of view of others

Extends help while respecting the roles of others in doing the job

Acknowledges team effort in success and collective responsibility over failure

Respect for Individuals

Practices gender and cultural sensitivity

Shows an authentic concern to promote individual welfare

Examines own biases and behavior to avoid judgmental reactions

13

Page 14: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Corporate Responsibility

Advocates Philex as a responsible mining company

Manifests core values in both professional and personal circumstances

Upholds the Philex Code of Conduct

HISTORY OF THE MINE

Philex Mining Corporation was incorporated in 1955. It is one of ther elatively new

large-scale mining companies in Benguet. Lepanto Mining Corporation operating in the

Municipality of Mankayan, for example, has been in Benguet since 1936 while Benguet

Corporation (known as Benguet Consolidated Mining Company in 1906 and Benguet Gold

Mines in 1903) has been in Benguet for more than 100 years.

14

Page 15: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 1. Incorporation and ownership of Philex Mining Corporation

From incorporation of Philex Mining Corporation in 1955, mill and mineconstruction

commenced. Mineral production started in 1958 at 800 tons per day.However, mill capacity

was at 2,000 tons per day. Company data reported to theSecurities and Exchange Commission

say that ore extracted and processed from1958 was 332.2 million tons by 2008 and produced

897.4 million kilograms ofcopper, 162.2 million grams of gold, and 177.9 million grams of

silver.

Company data say that, as of 31 December 2006, total ore milled reached311 million

metric tons and generated US$2.7 billion through exports. A 26February 2005 report of The

SunsStar says that from a deposit of 18 million tonsand after mine and mill expansion, Philex

Mines mined and milled a total of293.6 million tons of ore over 47 years, from 1958 to 2005.

Philex generated atotal of US2.6 billion through exports during the period. Further, during the

47years, SunStar also say that the company produced 3.248 million dry metric tonsof

concentrate consisting of 824 million kilograms of copper, 146.9 millionkilogram of gold, and

163 million kilograms of silver.

15

Page 16: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

The main site of Philex mining operations, from its establishment until today, is the

Sto. Tomas II ore body in Pacdal, Tuba, Benguet. Pacdal Mine, as the mining site is also

known, used to be a completely logged-out old sawmill.

Figure 2. Production in 1958 started at 800 tons per day

16

Page 17: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 3. Philex Pacdal area In 1958

Philex Mines is proud to be the first mining company in the Philippines to have earned

the International Standard Organization (ISO) 14001 certification, making Philex the first

Philippine mining company to earn the certification. Philex claims to have successfully

reforested watershed, open, denuded, and poorly stacked forestlands with an area of 1,540

hectares as of 2005.

SITE LOCATION

Philex Mining Corporation’s mine site is located at the southern tip of the central

Cordillera, straddling the municipalities of Tuba and Itogon, Benguet. It is about seventeen

(17) aerial kilometres south – southeast of Baguio City and lies at an elevation of 1500 meters

above sea level. Access from Baguio City is via thirty two (32) kilometers well – paved road

with a travel time of one hour. Philex Mining Corporation was incorporated in the Philippines

in 1955 to engage in mining activities. Its shares are listed in the Philippine Stock Exchange

while shares of its 81% - owned gold subsidiary, Philex Gold, Inc., are listed in the TSX

Venture Exchange.

The Company has operated the Sto. Tomas II copper-gold-silver deposit at Padcal,

Tuba, Province of Benguet for about 49 years. The Padcal mine was the first block cave

operation in the Far East. Total ore mined to year-end 2007 was 314.05 million tonnes, with a

metal production of 858.16 million kilograms (1,895.24 million pounds) of copper

concentrate, 153.05 million grams (4,923.80 thousand ounces) of gold and 169.26 million

grams (5,453.50 thousand ounces) of silver in concentrate and bullion form. The Padcal mine

is the only remaining copper-gold operation in the Philippines.

17

Page 18: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

The total land area applied of Mineral Production Sharing Agreement (MPSA) was

14,256 hectares, area covered by mining claims was 14,085 hectares, and an area lease

contract was 342.85 hectares. The developed areas affected by operations which include

subsidence, ore body, tailings pond, residential area, school, recreational and industrial areas

covered a total area of 580 hectares. The Philex Management is totally committed to the

protection of its environment and showed deep concern to the welfare of its employees and

dependents as well.

Physiography and Climate

The locale is very rugged, where the mine site lies at an elevation of 1,500 meters

above sea level and depicted by steep and gentle slopes varying in different parts. The climate

is cool and invigorating with the rains coming mostly between the rainy seasons of June and

October. Occasional typhoons occur in the area annually with 500 mm average rainfall.

Several tributaries of Agno River (Albian Creek) occurred. Bued River and Toboy River were

drained to the eastern, western, and southern areas respectively. Vegetation is mostly pine

trees.

Mining Claims

The total land area applied in Mineral Production Sharing Agreement (MPSA) was

14,256 hectares, area covered by mining claims is 14,085 hectares and an area lease contract

is 342.85 hectares. Developed areas affected by operations which include the subsidence, ore

body area, tailings pond, residential area, school and recreation and industrial areas cover a

total area of 580 hectares.

18

Page 19: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

ORGANIZATIONAL STRUCTURE

DIRECTORS, OFFICERS AND STAFF

(As of February 15, 2012)

BOARD OF DIRECTORS

Manuel V. Pangilinan

Chairman

Juan B. Santos

Vice Chairman

Eliza R. Antonino

Eulalio B. Austin, Jr.

Emilio S. De Quiros, Jr.

Oscar J. Hilado (Independent)

Robert C. Nicholson

Wilfredo A. Paras (Independent)

Edward A. Tortorici

Marilyn A. Victorio-Aquino

19

Page 20: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

OFFICERS

(As of February 15, 2012)

20

Manuel V. Pangilinan Chairman of the Board

and Chief Executive

Juan B. SantosVice Chairman

Eulalio B. Austin, Jr. President and Chief

Operating Officer

Barbara Anne C.

MigallosCorporate Secretary

Guadaflor C. Malonzo Assistant Corporate

Secretary

CONSULTANT 

Rogelio G. Laraya, PhDSenior Adviser

Renato N. MigriñoTreasurer

Chief Finance OfficerSenior Vice President

Denis Ricardo G. LucindoVice President for Business

Development

Enrique C. Rodriguez, Jr. Vice President for Legal

Libby R. Ricafort Vice President Resident Manager , Padcal Operations

Redempta P. Baluda Vice President for

Exploration

Edgardo C. CrisostomoVice President for

Administrationand Materials Management

Victor A. FranciscoVice President for Environment and

Community Relations

Page 21: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

PASIG HEAD OFFICE AND PADCAL OPERATIONSSTAFF

21

PADCAL OPERATIONS

Vergel T. AgatepGroup Manager - Mine Mechanical

Eduardo M. AratasDivision Manager - Legal

Anselmo T. RangesGroup Manager - Central Mechanical 

& Electrical Services

Jocelyn B. GalaponGroup Manager - Geology &

Exploration

Roy P. MangaliDivision Manager - Mine

Joel S. Son Group Manager - Safety

Geraldine B. Ateo-an

Group Manager – Internal Audit

Noel C. Oliveros

Division Manager - Exploration

Victor B. MaglambayanDivision Manager - Exploration

PASIG HEAD OFFICE

Paraluman M. Navarro

Division Manager - Corporate FinanceEdgar L. Prangan

Division Manager - Safety/Loss Control

Elisa R. DungcaDivision Manager - InformationTechnology & Investor Relations

Vicente L. Servidad

Group Manager-Corporate

Environment & Community Relations

Reynold V. YabesGroup Manager - Mill Operations &

Maintenance

Andres C. Zabala(11) Group Manager - Human Resources

Roselyn M. Dahilan Group Manager – Padcal Finance

Eileen C. Rodriguez

Group Manager – Corporate Treasury

Page 22: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

CORPORATE STRUCTURE

As of May 25, 2010

22

Page 23: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

PHILEX CORPORATE STRUCTURE (As of May 23, 2011)

100%

100%

10.31%

18.46%

51.24%

38.82%

25.63%

23

PHILEX MINING CORPORATION

SILANAGAN MINDANAO MINING CO., INC

(Philippines)

PHILEX GOLD HOLDINGS, INC.

(Philippines)

PHILEX GOLD PHILIPPINES

(Philippines)

SILANGAN MINDANAO EXPLORATION CO., INC.

(Philippines)

FORUM ENERGY PLC

(United Kingdom)

PHILEX PETROLEUM CORPORATION

(Philippines)

PETROENERGY RESOURCES CORP.

(Philippines)

BRIXTON ENERGY & MINING CORP.

(Philippines)

FEC RESOURCES, INC.

(Canada)

PITKIN PETROLEUM PLC

(United Kingdom)

40%

100%

100%

60%

83.33%

16.67%

Page 24: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Corporate Structure

According to the 2009 report of independent auditors (SGV & Co/Ernst &Young) and

other documents of the Philex Mining Corporation:

Philex Mining Corporation (see www.philexmining.com.ph) was incorporated in the

Philippines in 1958. It is a parent company with thefollowing direct subsidiaries (the parent

company and its direct subsidiary are oftentimes referred to as the Philex Group):

1) Philex Gold Philippines, Inc.: PGPI is an 81%-owned subsidiary of theparent company

through holding companies and incorporated in thePhilippines. However, PGPI was

incorporated under the laws of Alberta,Canada and is primarily engaged in the exploration

and development ofoil, gas, and minerals.

2) Brixton Energy & Mining Corporation: BEMC is a wholly ownedsubsidiary of the parent

company and incorporated in the Philippines

3) Philex Petroleum Corporation: Philex Petroleum is a 51%-ownedsubsidiary of the parent

company and was incorporated in thePhilippines

4) FECR (formerly Forum Energy Corporation, see www.fecresources.comand

www.sedar.com): FECR is a 50.67%-owned subsidiary of the parentcompany and

incorporated under the laws of Alberta, Canada.

24

Page 25: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

The parent company or Philex Mining Corporation, Philex GoldPhilippines, Inc. (PGPI) and

its subsidiaries, and Brixton Energy & MiningCorporation are primarily in large-scale

exploration, development, andutilization of mineral resources.

The parent company (Philex Mining Corporation) operates the Padcal Mine in Benguet.

Philex Mining Corporation and subsidiaries derived their income mainly from the Padcal

Mine. Income from petroleum operations and other sources are insignificant to Philex Mining

Company and subsidiaries asof March 2009. Padcal Mine is on its 51st year of operation

producing copper,gold, and silver as its principal products.

PGPI operated the Bulawan Mine in Negros Occidental until the second quarter of 2002.

PGPI appears to have its own subsidiaries and this is asubject for further inquiry. PGPI has a

number of mineral properties throughout the Philippines at various stages of exploration. Its

focus since2001, however, has been on its “North property” where the Boyongan deposit, a

major copper-gold porphyry in Surigao del Norte, was discovered in August 2000 through a

joint venture with Anglo American Exploration Philippines B.V. (Anglo). PGPI owns the

Boyongan deposit.

BEMC has a coal property under pre-development in Zamboanga del Norte.ATM/LGI a.

boquiren May 2009 [email protected]

Philex Petroleum Corporation and FECR are engaged in oil and gasoperation and

exploration activities. Both participate in oil and gasproduction and exploration activities

through investee companies.

FECR owns 29.78% of Forum Energy Plc or FEP (FEP can be searched in Google Finance

and http://investing.businessweek.com. FEP is a United Kingdom company incorporated in

April 2005 through the consolidation of the Philippine assets of Forum Energy Corporation

and Sterling Energy Plc(“SEY”) of the UK. FEP has just closed a US$6.2 million pre-IPO

financing

25

Page 26: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

and a US$19.35 million IPO financing and is listed on the AIM market of the London stock

exchange. FEP has a portfolio of oil and gas exploration projects in the Philippines. The

portfolio includes contracts with existing infrastructure, production, and proven hydrocarbon

potential. FEP also holds coal operation contracts in Central and Southern Cebu.

Lascogon Mining Corporation (LMC) was incorporated in 2005 to engage inthe

exploration, development, and utilization of mineral resources.

Philippine Gold Mining Company B.V. (PGMC-BV): incorporated in Netherlands. This

company has been the intermediary holding company ofPhilex Gold Inc (source: page 5 of the

SGV & Co/Ernst and Young Independent Auditors Report to stockholders).ATM/LGI a.

boquiren May 2009 [email protected] other subsidiaries of Philex Mining

Corporation are:

Philex Land, Inc. (PLI): engaged in the business of owning, using,developing, subdividing,

selling, exchanging, leasing, and holding real estateof all kinds covering buildings, houses,

apartments, and other structure

Fidelity Stock Transfer, Inc. (FSTI): agency firm for stock transfers.

Philex Insurance Agency, Inc. (PIAI): general agent for domestic and foreign companies in

the non-life insurance business. However, this company was reported to be dormant. In its

report to the stockholders of Philex Mining Corporation (the report was also forwarded to the

Securities and Exchange Commission in 2009), SGV & Co and Ernst and Young in early

2009 reported that the following constitutes the ownership of firms of the Philex group.

26

Page 27: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

STO. TOMAS II ORE DEPOSIT

LOCATION

The Sto. Tomas II ore body of Philex Mining Corporation is deposited at the southern

tip of the Luzon Central Cordilleras about 17 aerial kilometres south-southeast of Baguio

City. It is located at Brgy. Padcal, Tuba, Benguet. Access to the mine site is a 32-km company

road of about an hour to drive. Within the Mine site is a private own community and it is free

in water and electric supply as one of the community development programs of the company.

27

Page 28: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

GEOLOGY

The mountain ranges of Northern Luzon, of which the site of Philex mining operation

is part, belongs to a volcanic arc terrain. Gold and copper mineralization is often associated

with volcanic rocks as well as with faults in the earth’s crust. In fact, the location of the ore

body that is the main subject of mining operations by Philex is actually crissed-crossed by

fault lines. The most not able of the fault lines are the Albian and Sta. Fe faults.

Thus, it is not be surprising for Philex gold and/or copper production to be associated

with geo-hazard risks vis-à-vis volcanic or earthquake activity.

Figure 16. Site of Philex mining operations and fault lines

28

Page 29: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 14 below gives us a close-up of the Sto. Tomas Ore body that is the main site

of Philex mining operation.

Figure 17. Philex Mining company illustration of Phlox ore body: Sto. Tomas ore

body is directly along the Albian and Sta. Fe faults

As indicated by the figure above, the Sto. Tomas Ore Body of Philex Mines lies

directly along the path of the Albian and Sta. Fe fault lines. A sharp movement along the fault

line can result to a geological disaster.

In the future, we will analyze Figure 14 further as we compare the map with ground

data. We will also analyze deeper all the figures in this work as they are probably indicative

of the risks to the environment posed by the Philex mining operations. The figures in this

work probably contain information more than what are obvious.

29

Page 30: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 18 indicate the proximity of the Philex milling plant to the Sto. Tomas II ore

body. The ore body is actually the site of the old open pit mining of Philex. Underneath the

site of the old open pit mine, Philex underground mining continues.

Figure 18. Vertical section of Sto. Tomas II ore body and milling plant: blue blocks

are mined-out, red blocks are producing, and green block is virgin.

30

Page 31: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 19. Location of Philex ore body: Philex Mines’ PowerPoint above suggest s

that the Sto. Tomas ore body is approximately at N16º16’ E120º32’. However, adiscussed in

Chapter 5, the ore body is likely at 16º15’45.62” North 120º37’18.87” East

31

Page 32: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

LITHOLOGY

A. Rock Types

Host Rocks Age Radiometric Dating

Zircon Fission Track

Dating

(Dr. J.F. Lovering)

K-Ar Dating

(Teledyne Isotope

Ltd.)

Meta-andesite and Meta-

sediments

Paleogene - -

Intrusive

Andesite Porphyry Early

Pleistocene

1.4 + 0.4 Myrs

1.4 – 0.4 Myrs

1.9 + 0.5 Myrs

1.9 – 0.5 Myrs

Clear Diorite Late Pliocene 2.0 + 0.5 Myrs

2.0 – 0.5 Myrs

-

Dark Diorite Late Miocene - 3.8 + 1.1 Myrs

Description of Lithology

1. Andesite Porphyry: located within the center of the orebody and represents the “low grade”

ore. It is porphyritic in texture with diagnostic subrounded plagioclase phenocrysts, light gray

in color and weak mineralized.

2. Clear Diorite: light gray in color, fine to medium grained in texture with quartz, plagioclase

and as primary minerals. This rock unit is less mineralized as compared to dark diorite.

3. Dark Diorite: this is the oldest of the intrusive complex and the most mineralized and altered.

It is usually dark-colored, fine grained quartz diorite porphyry. The primary minerals are

quartz, plagioclase, hornblende and magnetite and secondary biotite disseminations.

32

Page 33: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

4. Meta-sediments: this is the country rock unit belonging to the Zigzag-Pugo formations of the

Baguio District. It consists of regionally metamorphosed andesite and tuffaceous rocks with

intercalated sediments. The texture is variable ranging from aphanitic to porphyritic and

hornfelsic. It is usually dark in color. Mineralization near to a maximum radius of about 200

meters from the contract.

B. Geologic Structures

The orebody is pipe-like and almost vertical with lateral dimension of 500 meters and by

550 meters and a vertical column of 730 meters. At the top of the deposit had its outcrop at

the headwaters of Toboy River and Albian Creek with an elevation of 1,500 meters above sea

level.

The complex stocks of quartz diorite porphyries (1 – 2 million years by Fission Track

Dating) intruded into the Zigzag-Pugo Formation along the northeast trending steeply dipping

Albian Fault in four episodes of intrusion and associated mineralization. These intrusions are

classified from the oldest to youngest as dark diorite, clear diorite, andesite porphyry, and

hornblende andesite porphyry.

C. Orebody Geometry

Length : 550 meters

Width : 500 meters

Height : 730 meters

Shape : pipe-like

Altitude : Vertical, Tapers to the North

D. Ore Characteristics

Above 110 ML or Gypsum Line Fragmentation: RQD < 50

33

Page 34: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Below Gypsum Line Massive with RMR: 55 RQD > 75

E. Ore Reserve

Total since 1957 Remaining as of Jan. 1, 2001

MillionDMT 367.612 125,483

% Cu 0.310 0.282

gAu/DMT 0.626 0.674

F. Ore Distribution

Level M DMT % Cu gAu/ton Meta-volcanics Intrusive

975 ML 5.508 0.245 0.718 75% 25%

908 ML 29.869 0.284 0.593 65% 35%

863 ML 51.933 0.280 0.591 60% 30%

773 ML 38.173 0.290 0.843 75% 25%

745 ML 125.483 0.282 0.674

G. Dominant Alteration Minerals

Ore Zone Quartz, Secondary Biotite, Anhydrite,

34

Page 35: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Serecite, Magnetite

Fringe Zone Quartz, Chlorite, Epidote, Magnetite,

Pyrite

The host of mineralization is mainly the hornblende quartz diorite porphyry, the

Metavolcanics and, to a lesser degree, the other intrusive rocks. The K-Ar age of the

hydrothermal alteration and mineralization was estimated to be 1.5 ± 0.4 Ma. The orebody is

cylindrical/ pipe like and almost vertical with lateral dimensions of 400 meters by 500 meters

and vertical extent of 700 meters (Imai, 2001). Alteration is typical of porphyry copper

deposits. Main alteration assemblage associated with copper-sulfide mineralization is quartz -

biotite-chlorite. Hydrothermal alterations observed are silicification, biotization, sericitization,

propylitization, pyritization and sulfatization. Silicification, generally observed in the quartz

diorite porphyry and metavolcanics, occurs in the form of stockwork and fissure-filling

veinlets, and vug-filling quartz crystals.

H. Mineralogy and Petrography

Primary ore minerals are chalcopyrite and bornite (1 – 2%) with associated gold and silver

and trace of palladium-bearing carried by quartz and anhydrite stock works. Native gold

occurs mainly with copper sulfides either locked or along grain boundaries and also interstitial

to gangue minerals like quartz and anhydrite.

Alteration is typical to porphyry copper deposits. Main alteration assemblage associated

with copper-sulfide mineralization is quartz-biotite-chlorite. Orthoclase that is characteristic

of potassic zone is absent. Sericite is weak and actinolite is also noted.

5. Hypogene Copper Minerals – chalcopyrite and bornite

6. Sulfide Mode Occurrence – fracture fillings and stockworks associated with quartz and

anhydrite as disseminations.

35

Page 36: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

7. Gold Occurrence – free gold associated with chalcopyrite and bornite; 80% recovered with Cu

concentrate; 20% from gravity.Altitude: vertical, tapers to the north

MINING METHOD/PROCESSING

The mining method applied in Philex Mining Corporation is Block Caving System.

Slusher’s winches and recently load-haul-dump (LHD) units are used for ore extraction and

feeder and conveyor belts for ore transport. This method is used to partly cut off thick block

of ore from surrounding blocks by series of drills, as one above the other, or by boundary

shrinkage stopes. It is then undercut by removing a slice of ore or a series of slices separated

by small pillars underneath the block. The isolated, unsupported portion of the block of ore

breaks and caves under its own weight. Gravity forces in the order of millions of tons act on

the rock masses, and successive fracturing occurs, affecting the entire block. As the rock

pressure increases at the bottom of the block, the ore crushes to a fragmentation that allows

removal through draw points. Philex adapted the block caving for it is suitable for the geology

of the site.

The mine operated for the first two years a small open pit and shifted to underground

block caving using slusher and LHD extraction system respectively.

1. Slusher System (1963 – 1996)

The method generally consists of driving a series of spaced openings called the slusher

lines and are laid out in a north-south orientation. At the upper level of 1020 ML, ore is drawn

by full gravity and slushed by 0.90 metric tons capacity buckets which are pulled by a 36 Hp

slusher winches through short transfer raises to 1015 ML. These are loaded into 0.80 cubic

meters bottom-dump mine cars and transported by 25-ton diesel locomotives along the 3 km

stretch to the dump bin. However, the railroad hauling system was placed out last February

1997 as all the slusher blocks at 1020 ML have been depleted. Ore from the slusher blocks at

908 ML is slushed through long transfer raises and loaded into the feeder belts and eventually

to the dump bin via CHC system

2. Load-Haul-Dump (LHD) System (1996 – present)

36

Page 37: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Due to the increasing hardness of the ore at depth and water-related problems that

adversely affected the operation, the company has emerged in terms of mechanization. With

this, hydraulic jumbo drills for development activities and LHD units for ore extraction

replaced the conventional rock drills. This method can draw coarsely fragmented ore at high

production rate. The ore is drawn from draw points with wider openings by LHD equipment.

The lower levels particularly at 908 ML are laid out in an east-west orientation. These are

driven at an interval distance of 26 meters center to center.

The fallen ore is extracted from the draw crosscuts by the LHD’s and dump into the

grizzlies equipped with mechanical breakers. The sized ore travels into a long transfer raises

and conveyed to cabled belt conveyors through feeder belts.

Figure 21. Characteristics of Philex ore body: massive

37

Page 38: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 22. Overview on mining and milling method at Philex-Pacdal

Figure 23. Philex mining method 1958-1963: open pit mining

38

Page 39: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 24. Philex mining 1963-1996: block caving-slusher method

39

Page 40: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 25. Philex mining 1996-present: block caving with load-haul-dump

Sun Star (2 February 2005) describes the LHD or load, haul, and dump of the Philex

mining method this way: ore is drawn by the load haul-dump or LHD units then transported to

the mill through cable belt conveyor system, 2.7 kilometers away from the ore body. Sun Star

reports further that the milling process of Banguet Concentrator utilizes three stages of

crushing that creates a final product of copper concentrate described as “73% minus 10 mm.”

Developing mines from which ores can be gathered involves the following processes:

horizontal and vertical driving, installation of rock support, drilling of fan holes, excavation of

trenches, and undercutting. Figures 26-31 are illustrative

Figure 26. Overview on Philex mine development

40

Page 41: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 27. Horizontal driving in Philex mine development

41

Page 42: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 28. Vertical driving in Philex mine development

42

Page 43: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 29. Installing rock support in Philex mine development

43

Page 44: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 30. Drilling of fan holes in Philex mine development

44

Page 45: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 31. Drawpoints for ore in mine development

After a mine has been developed, production commences. Production involves

scooping, breaking rocks to get the ore, handling the ore, crushing the ore, and conveying the

ore. Figures 32-34 are illustrative.

45

Page 46: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

46

Page 47: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 33. Ore extraction method

47

Page 48: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

48

Page 49: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

49

Page 50: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 35. Subsidence at the ore body in mine operation

Figure 36. Backfilling operations on subsidence

50

Page 51: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

As discussed earlier, Figure 17 indicate that the Sto.Tomas II ore body is along the

Albian and Sta. Fe faults. Based on Figures35 and 36 above and Figure 37, it is clear that the

block caving-LHD mining method currently used by Philex mines involve the backfilling of

subsidence areas. An important question to ask, therefore, is: what are the risks and how can

we monetize the value of the risks involved in Philex mining given that the country lie along

the Pacific ring of fire that is vulnerable to frequent earthquakes and given that the Philex ore

body are crisscrossed by two fault lines?

Figure 37. Backfilling above active mining area

51

Page 52: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Figure 38. Milling flow sheet and transport to Poro Point for Japan or Leyte

52

Page 53: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

COMPANY DIVISIONS AND DEPARTMENTS

THE ADMINISTRATION DIVISION

The Administrative Division support the company’s operations by maintaining

harmonious labor and management relation through effective and efficient personnel

administration, man power training and development, health management, industrial relation

and public system.

THE HUMAN RESOURCE DEPARTMENT

The department of Human Resource and Development was created to be responsible

for implementing further the training and the evaluation program of the company.

The program was fashioned to train employees to SOP’s which the company hopes to

push and maintain. It uses functional, personal and environmental standards as the mode for

judging the performance of an employee.

Special training sessions and seminars were conducted for further I’m ensure the prove

and develop overall performance of individual workers in the company. Thru training and

learning, Philex Mining Corporation had develop the Human Resource Development Center

to ensure the employees of all levels and be able to acquire all skills old or near for the

betterment of not only the company but also the individual growth of the worker.

THE SAFETY DEPARTMENT

S- ound judgement

A-lways

F- oresight

E- xtreme caution

T- hink

Y- ou

53

Page 54: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Function of the department of safety as:

1. Maintenance of good working environment on the job site.

2. Monitoring through the establishment of accident rate reports, accident case analysis and use

of standards statistic system.

3. Training of supervisors and workers with the safety practices and procedures (first aid, mine

rescue, fire prevention and others).

4. Promotion of safety through contents, printing of papers or handouts, production of posters

and road signs and others.

5. Preparation of accident records of employees with accompanying analysis.

The frequency rate remarkably improve from 3.42 in 2005 to 2.89 in 2006; however

incidence rate per million man hours slightly increase from 5.06 in 2005 to 5.30 in 2006. The

company-wide safety audit system is continuously implemented in pursuit to an accident free

operation.

Top Ten Basic Safety Rules

1. Follow instructions; don’t take chances, if you don’t know..ask.

2. Correct on report unsafe condition.

3. Help keep everything clean and orderly.

4. Use the right tools and equipment for the right job; use them safely.

5. Report all injuries; get first aid promptly.

6. Use, adjust and repair equipment only when authorized.

7. Uses prescribe protective equipment; wear safe clothing; keep them in good condition.

8. Don’t horseplay; avoid distracting others.

9. When lifting, bend your knees; get help for heavy loads.

10. Comply with all safety rules and signs.

54

Page 55: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

25 General Safety Policies:

1. An employee shall report to work well rested and not under the influence of any intoxicating

liquor or prohibited drugs.

2 The employees should work using proper clothing, shoes or boots, and skull guards whenever

it is required.

3 An employee shall qualified and/or experienced or have general knowledge to perform the

particular work he was assigned.

4 An employee shall study the job carefully to determine all the hazards present and see that all

necessary safeguards and safety devices are provided to protect his self and other workmen.

5 He shall examine safety devices before they are used to make sure that they are in good

condition and that the proper device shall be used.

6 He shall faithfully observe all rules and regulations pertaining to safety and sanitation.

7 An employee shall submit himself to physical examination as the employer may require.

8 He shall follow instructions given by the operating staff and the safety department.

9 He shall not enter areas known to be dangerous or pass through danger signs without proper

authority.

10 An employee is not allowed to linger in any part of the plant or any working area after the end

of the shift.

11 He shall be forbidden to interfere with, remove, displace, damage or destroy any safety device

or other personal protective equipment furnished for his protection or for the protection of

others.

12 He shall promptly report all unsafe and unsanitary conditions to his supervisor.

13 He shall assist his fellow workmen in the prevention of accidents and warn them on

dangerous conditions.

55

Page 56: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

14 He shall attend safety meetings conducted by the management.

15 An employee shall not be allowed to ride on any company vehicle unless he is authorized to

use it.

16 He shall immediately administer first aid if qualified, to an injured workman or get in touch

with the nearest first aid station.

17 He shall take care of inflammable materials in such a way as to minimize fire hazards.

18 He shall report to his supervisor in any injury sustained while performing his regular duty in

the company no matter how slight it is. This must be done twenty-four hours.

19 He shall not be permitted to enter with or carry intoxicated liquor, drugs or deadly weapons

into any working area.

20 An employee is not allowed to sleep in any working area either on or off duty.

21 He shall watch out for any moving machines while in the performance of his work.

22 He shall pass or work under power shovels and other parts of the machines.

23 He shall not horseplay so as to prevent from accident and not to distract others from doing

their work.

24 An employee shall lift with his knees bend in carrying heavy loads.

25 An employee shall comply with all safety rules and regulations mentioned.

Safety Performance Analysis

1. Accidents happened commonly from the Mine Division, VP/RM Group, Mill Division and

Contract Group.

2. Injuries are commonly cause by truck by, Pinning, Rock fall and Structure against.

3. Accident are commonly caused by:

a. Failure to secure due to poor judgement.

b. Improper position for task due to overconfidence.

c. Failure to assess hazard due to violation by SOP/SSP.

56

Page 57: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

4. Accident commonly occur during the following work activities;

a. Working/handling on suspended load.

b. Grougnd support particularly on timbering and rock bolting.

THE GEOLOGY DEPARTMENT

The Geology Department of Philex Mining Corporation is the primary life of the

mine. Without its existence, the mine would not probably survive for long. The Geology

Department engages in the pursuit of finding ore and affirming the presence of such ores.

Because it is a fact that the ore being mined out is irreplaceable, the Geology Department

exerts its utmost effort in knowing the geological characteristic off Philex ore body. Another

significant function of this department is to find new minable deposits in other parts of the

country.

General Objectives:

The primary objective of the Geology Department is:

1. The increase of the ore reserve by finding the possible extension of present ore body and by

finding new ore bodies in the immediate vicinity.

2. The availability of accurate geological data such as:

a. Mineralogy and grade of ore

b. Rock mechanics or geotechnical descriptions

c. Structural and hydrological information.

These are needed in the improvement of mining and milling operations, in the

optimization of extraction and recovery and in the promotion of safety in the underground and

surface development.

3. Prompt warning and advice to the operation of potential geologic problems or effect of the

geological activity and legality of existing mining claims.

4. Maintenance of the validity and legality of existing mining claims.

5. Research studies on matters affecting operations.

57

Page 58: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

SIX SECTIONS WITH STATEGIES THAT MEET THE OBJECTIVES:

EXPLORATION GEOLGY SECTION – its objectives are the proper evaluation of the

mineralization and economic potential of the various known prospects within the vicinity of

Sto. Thomas II and Baguio District and the location of other exploration targets not yet

Known at present within the vicinity of Sto. Thomas II and Baguio District.

PETROGRAPHIC SECTION – it i responsible for the accurate determination of its

mineralogical characteristics, occurrence and association that are needed in the improvement

of metallurgical operations and in the evaluation of exploration targets and it also serves as

the custodian of the drilling core and geochem samples and the log sheets and assay records

of these samples.

ORE RESERVE AND DOCUMENTATION – the concern of these sections are:

a. The accuracy in the evaluation in the Sto. Thomas II ore reserve and proper inventory of the

ore extraction and recovery;

b. Custodian of geological and mining claim maps and documents;

c. Proper control of company issued supplies, tools, equipment, and facilities (office, core house

and DD shop) and the proper recording of personal attendance and records;

d. Proper budget preparation and proper charging of department expenses;

e. Maintenance of the validity of mining claims.

THE CORE LOGGING SECTION – it is where samples were collected and analyzed. The

core samples were collected, cut by half; one for the stockpile, and the other half for the

laboratory analysis. Then the specific weight, the compressive strength and the core recovery

were determined.

DIAMOND DRILLING SECTION – its prime objective it to attain proper diamond drilling

procedures and collection of required samples from drill holes that the geologist will propose

58

Page 59: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

either for exploration, development, water source and structural stability of foundation

purposes.

THE MINE DIVISION

If the Geology Department serves as the life of the mine by finding ore and affirming the

presence of such ores, the Mine Division is the center and heart of the company’s operation. It

is principally responsible in all the mining activity from mine planning, and designs, mine

underground development works, are extraction and quality.

The Mine Division also involved in electrical operation, supply delivers and mechanical

operations in the maintenance of all mine equipment such drilling equipments ( Jumbo Drills,

Air-Leg ). Loading and hauling equipments ( LHD, Volvo and LPT ) and including the

operation in Batching Plant.

The Mine Division is composed of four major departments namely: Mine Engineering and

Draw Department, Mine Development Department, Mine Production Department, and Mine

Mechanical and Electrical Department.

MINE ENGINEERING DEPARTMENT

Mine Planning and Design Section

Plan – a map showing features such as mine working of geological structures and projecting

its objectives and strategies.

Planning – a method of pre-designing different detailed work to be undertaken.

The Planning section has the following objectives and functions:

59

Page 60: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

1. Prepares the plan and layouts/programs and budget based on annual production schedules and

monitor these against actual for appropriate adjustments and action

2. Coordinates with the Mine Logistics/Mine Engineering and Materials Management

Department for the delivery or requisitioning of supplies/materials and equipment in

underground.

3. Responsible for the training and motivation of production mines/operators in coordination with

HRD/PID and Safety.

4. Prepares all necessary reports and documents together with the mine information technology

crews for discrimination and appropriate action of all concerned.

Factors to be considered in planning:

1. Layout or design of a certain project

2. Feasibility study

3. Cost estimate at development stage

4. Project duration/completion at development stage

5. ROI (Return of Investment) at production stage

6. Life span

7. Schedule

Importance of Proper Planning:

To determine if your feasibility study is acceptable

To determine if the design is acceptable

To determine the development and production costs

To determine the life span of the project

60

Page 61: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Project Scheduling – is a form of planning strategy indicating various detailed work activities

and time frame of a certain project to be undertaken.

Two Kinds of Project Schedule:

Gantt Chart Schedule

PERT/CPM-Project Evaluation Review Technique/Critical Path Method

Importance of Project Scheduling:

To determine the manpower to be utilized in the project

To determine the duration or date of completion

Factor to consider in Project Scheduling:

1. Different work activities to be undertaken

2. Resources involved in the project (manpower to be included)

3. Availability of the materials

4. Arrangement of the activities

5. Determination of the parameters to be considered in each activity

6. Determination of the duration of each work activity

7. Determination of the activities that proceed, succeed or those that that can be simultaneously

done

Survey Section

The main function is to provide data/information needed by the Engineering

Department for feasibility study preparation. Also provide assistance to planning/design

section. Undertake survey works both underground/surface and other survey activity outside

the mine, monitor excavation and progress of backfilling activities and the subsidence area.

61

Page 62: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Surveying is a work of:

1. Measuring horizontal and vertical distances

2. Measuring angle between lines

3. Determine the direction of mines

4. Establishing points by pre-determined angular and linear measurements

5. Mathematical calculations of elevations, areas and volumes from the data surveyed

Underground work activities in Philex:

1. Establishing centerline of a tunnel

2. Establishing grade lines of a tunnel

3. Offsetting of a tunnel

4. Setting the Alimak anchor guide

5. Monitoring ITH/CUBEX, drilling, concreting activities

6. Measuring daily development advance

7. Office work:

8. Complete of field survey

9. Updating of plan maps, developing advance report

10. Blueprinting of maps, etc.

Surface work activities in Philex:

1. Pit subsidence survey – 4% required slope stability

2. Tailings pond survey – 60% dikes slope stability

3. Hydrographic survey – pore point

62

Page 63: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

4. Chain survey

5. Ore stockpile survey

Surface survey includes topographic survey in subsidence area and other sites, location

and relocation survey, progress survey, and volume survey of stockpile.

Surveyed Data as Of October 2009

Area: Pit Floor Subsidence Rate for the Month

Buffer Zone: 288 has. As of October 2009: -1.58m

Crest Line: 136 has. Subsidence Rate Year-to-Date: -1.45m

Pit Floor: 37 has. Dam # 3

Subsiding Area: 13.50 has. Water Elevation: 601.033m

Subsidence Gradient: Free Board

Radial: - 4.28% Main: 7.230m

Water Way: - 2.43% Offset: 5.188

Rock Mechanics Section

Rock mechanics is a combined responsibility of the geology and the mine engineering

staffs, with the geology providing the vital information to the mine engineering to include in

mine planning the following:

1. The ground characterization through rock mass classification

2. Determination of the cavability of the ore column

3. Undercutting sequence

4. Fragmentation of the rock mass in the ore column

63

Page 64: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

5. Drawzone spacing

6. Proper draw control procedure

7. Layout of openings

8. Design of ground supports based on the rock mass condition

9. General geology of the orebody

For the proper interpretation of the rock mass that would cater to the diverse mining

situations, Philex adopted the modified geomechanics rockmass classification (Mining

Rockmass Rating, MRMR) as this system is recognized and used by most of the block cave

mine worldwide. Dr. DH Laubscher introduced the concept of MRMR to fine-tune the Rock

Mass Rating (RMR) for the diverse mining environments. The RMR is subjected to a series of

adjustments so that the final ratings (MRMR) could be used for mine design.

Basic parameters of the RMR are the following:

8. Intact Rock Strength (IRS) which is the unconfined uniaxial compressive strength of the rock

between fractures and joints. The intact strength of a rock can be estimated using Table 1 and

the ratings for the different IRS values can be found in Table 2.

Table 1

Estimation of intact rock strength (after Laubscher 1990)

Descriptive rock strength Equivalent

stress

MPa psi

Easily molded in fingers; shows distinct heel marks 0.05 5

Molds in fingers with strong pressure; faint heel marks 0.07 10

Very difficult to mold in fingers; difficult to cut with hand spade 0.15 20

64

Page 65: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Cannot be molded in fingers; cannot be cut with hand spade and

requires hand-picking to dig out

0.5 70

Very tough and difficult to move with hand-pick; requires pneumatic

spade for digging

0.7 100

Crumbles under firm blows with sharp end of geological pick and can

be peeled off with a knife; too hard to cut out a test specimen by hand

3 450

Can just be scraped and peeled with a knife; indentations up to 3 mm

show in the specimen with a firm blow of the geological pick point

7 1000

Cannot be scraped or peeled with a knife; hand-held specimen can be

broken with one firm blow of hammer end of geological pick

20 3000

Hand-held specimen breaks under more than one blow with hammer

end of geological pick

70 10000

Many blows with geological pick required to break through intact

specimen

200 30000

Table 2

Intact rock strength rating (after Laubscher 1990)

Intact Rock Strength (IRS)

MPa % Rating

185 20

165 – 185 18

145 – 164 16

125 – 144 14

105 – 124 12

65

Page 66: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

85 – 104 10

65 – 84 8

45 – 64 6

35 – 44 5

25 – 34 4

12 – 24 3

5 – 11 2

1 – 4 1

9. Fracture Frequency per Meter (FF/m) is the number of naturally occurring discontinuities in a

specified length of core or sidewall (refer to Table 3).

Table 3

Fracture frequency per meter rating (after Laubscher 1990)

Fracture Frequency per Meter (FF/m)

Average per meter Rating

1 Set 2 Sets 3 Sets

0.10 40 40 40

0.15 40 40 40

0.20 40 40 38

0.25 40 38 36

0.30 38 36 34

66

Page 67: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

0.50 36 34 31

0.80 34 31 28

1.00 31 28 26

1.50 29 26 24

2.00 26 24 21

3.00 24 21 18

5.00 21 18 15

7.00 18 15 12

10.00 15 12 10

15.00 12 10 7

20.00 10 7 5

30.00 7 5 2

40.00 5 2 0

10. Joint Condition which is the assessment of the frictional properties of the joints (not fractures)

and is based on expression, surface properties, alteration zones, filling and water. The

procedure for the determination of joint condition is shown in Table 4, which divides the joint

assessment sections into subsections A, B, C, D, and E.

Table 4

Joint condition rating (after Laubscher 1990)

Parameter Accumulative % adjustment of a possible rating of 40

Description Dr Adjustment (%)

67

Page 68: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

y Mois

t

Moderate

Pressure

25 – 125

li/min

High

Pressure

>125

li/min

A

Large Scale Joint

Expression

Wavy/multi-directional 100 100 95 90

Uni-directional 95 92 90 87

Curved 90 87 85 82

Slight undulation 85 82 80 77

Straight 80 74 70 72

B

Small Scale Joint

Expression

Very rough 95 90 85 80

Striated/rough 90 85 80 75

Smooth 85 80 75 70

Polished 80 75 70 65

C

Joint Wall

Alteration

Weaker than wall rock 75 70 65 60

D

Joint Filling

Non softening and sheared

material

Coarse

Medium

Fine

95 90 70 70

90 80 70 60

80 70 60 50

D Soft sheared material

68

Page 69: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Joint Filling Coarse

Medium

Fine

70 60 50 40

60 50 40 30

50 40 30 20

Gough

Thickness<Amplitude of

irregularities

40 30 20 10

Gough

Thickness>Amplitude of

irregularities

20 10 Flowing

material

E

Cement

Hardness

Anhydrite (5+) 95

Calcite, Fluoride (3 – 4) 90

Gypsum (1 – 2) 85

Table 5

Meaning of the ratings (after Laubscher 1990)

1 2 3 4 5

Class A B A B A B A B A B

Rating 100 - 81 80 – 61 60 – 41 40 - 21 20 – 0

Description Very good Good Fair Poor Very poor

Table 6

Parameters/adjustments to arrive at MRMR (after Laubscher 1990)

Parameter Possible adjustment, %

69

Page 70: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Weathering 30 – 100

Joint Orientation 63 – 100

Induced Stresses 60 – 120

Blasting 80 – 100

Factors affecting Mining- Induce Stresses

Drift – induced stresses

Interaction of closely spaced drifts

Location of drifts or tunnels close to large stopes abutment stresses, particularly with respect

to the direction of advance and orientation of the field stresses

Uplift

Point loads from caved ground caused by poor fragmentation

Removal of restraint to sidewalls and apices

Increase in size of mining area causing changes in the geometry

Massive wedge failures

Influence of major structure not exposed in the excavation but creating the probability of high

toe stresses or failures in the back of the stope

Presence of intrusive that may retain high stress or shed stress into surrounding, more

competent rock.

MRMR = RMR × { ( % weathering )(% joint orientation) (% mining induced stresses) (%

blasting effects) }

The resulting MRMR after applying corresponding adjustments factors to the RMR is

21 to 30 or poor ground conditions.

70

Page 71: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

The evaluation of the following geomechanical issues shows the importance wage of rock

mechanics in the design of Philex mechanize block cave operations.

Cavability

Aside from the after asked question of, “Will it cave or will not cave? , the reql question is

“Can we afford to make it cave?, carry the rock away and extract the mineral?

Laubscher (1994) stated that the cavability of an ore deposit is based on many aspects, but

clearly, if a large enough area is undermined (hydraulic radius), any rockmass will cave. The

manner of their caving and the resulting fragmentation size distribution need to be predicted if

cave mining is to be successfully implemented. Controlling the draw as the cave can only

propagate if there is space into which rock can move, can slow the rate of caving. Advancing

cut more rapidly can increase the rate of caving but problems can arise if this allows an air

gap to structures, heavy blasting and the influx of water can result in damaging an air blasts.

Rapid, uncontrolled caving can result in an early influx of waste dilution. The rate of

undercutting should be controlled so that the deterioration of the undercut and is extraction

openings is avoided. Stagnant cave front should be avoided.

Fragmentation

Primary fragmentation is the particle distribution that separates from the cave back and enters

the clean column. It is generally finer that from subsidence caving owing to the rapid

propagation of caving in the latter case with disintegration of the rockmass, primarily along

favourably oriented joint sets and little shearing of interaction of rock. Secondary

fragmentation is the reduction in size of the original particles that enters the draw column, as

it moves through the draw column.

Draw Zone Spacing

It should always be determined using the results of the secondary fragmentation study and

interaction of adjacent draw points. The spacing should also be carefully chosen so that the

three-dimensional flow ellipsoids from adjacent overlap slightly. This produces almost

complete extraction and minimizes dilution.

71

Page 72: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Draw Control

In order to improve fragmentation, the height of cave should be maximized and a slow initial

rate of draw should be used. The rate of draw should be such that the volume of ore removed

during causing is equal to the volume increase or bilking of the caving rockmass.

Basic Concepts in Block Cave Mining

Draw rate is dictated by caving rate. The more fragmented the ore, the greater the draw rate.

Block should be developed and mineral in a systematic fashion, favouring one or two general

retreat directions.

Blocks should be developed to ensure retreat towards service areas.

Convergent re-entrant or air step caving fronts should be avoided.

Stagnant caving fronts should be avoided.

The cave line should be configured perpendicular to production workings.

The larger the drifts directly beneath and adjacent to caving areas the incidence of ground

control problems.

The larger the density of drifts, the higher the incidence of ground control problems.

Efforts should be undertaken to ensure that an undercut is created.

1.3 Ventilation Section

It is the objective of this section to ensure the good working condition of exhaust

system and to ensure the good air to the mine. At the same time, disposal of contaminated air

in the underground work area is undertaken.

A major concern in the underground is the availability of good air. Existences of large

amount of dust, trapped toxic gases, are some of the concerns which may cause health

problems to the mines. With proper ventilation not only is health safeguarded but also

improves and offers a health working condition.

Philex undertaken this task by taking in air thru intake airways and expels used and

contaminated air thru exhaust airway. But then again, some areas where fumes and dust are at

extreme, breathing and protective devices are provided.

72

Page 73: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

In order to maintain a standard of good ‛atmosphere’, a ventilation survey is done to

check the efficiency of the ventilation system. Air volume intake and exhaust are checked

regularly. Pressure, dust survey, and gas are also conducted as part of the ventilation survey

program.

e Ventilation System – an arrangement of airway networks in a mine together with pressure sources and control, which

produce and govern airflow.

UG Main Intake UG Main Exhaust

1.1425 ML GCH Shaft 1. 1170 ML

2. CHC Portal 2. Bumolo Portal 1

3. 745 ML Tunnel 3. Bumolo Portal 2

4. Banget Batching Plant

Monthly Air Volume Survey

Summary of May 2010 Air Volume Intake Requirement, Main Air Intake, Main Booster

Exhaust and Final Main Exhaust Air

1. Air Volume Intake Requirement

Area – ML Required,

cfm

Actual, cfm Difference

1015 ML –

Batching Plant

10,600 16,642 6,042

908 ML/890

ML/UCL

192,800 197,770 4,970

840 ML 91,220 106,420 15,200

782 ML/UCL 188,810 194,568.81 5,759

773 ML/745 ML 242,060 243,450 1,390

Total 725,490 758,851 33,361

73

Page 74: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

2. Underground Air Intake, Booster Exhaust, and Final Exhaust

2.1 Table for Main Intake Air

Location (Source) Area,

ft2

Air Velocity,

ft/min

Air Volume, cfm

1.1020 ML GCH Shaft Access 72 928 66,816.00

2. 1020 ML Ring Drift (to 1015

Batching Plant)

53.00 314 16,642.00

3. Fringe Drift #1, 908 ML 172.00 567.00 97,524.00

4. Fringe Drift #2, 908 ML 87.35 372.00 32,494.20

5. South Block Access Bypass, 908

ML

295.86 229.00 67,751.94

6. Fringe Drift #1, 840 ML 187.00 211 39,457.00

7. Fringe Drift #2, 840 ML 221.00 303 66,963

8. Main Access to PL5, 782 ML from

791 ML Ramp

242.49 341 82,689.09

9. Ramp up to PL6, 782 ML from

773 ML

212.37 0 0

10. 2-4 Ramp from 773 ML 206.04 543 111,879.72

11. Thompson Shaft Station, 791 ML 64.00 147 9,408.00

12. CHC Tunnel 200.00 992 198,400.00

745 ML Tunnel after GCH Shaft 73.33 1,433 105,081.89

2.2 Table for Main Booster Exhaust Air

Location/Level Unit/HpProjected

Vol., cfm

Area,

ft2

Air Velocity,

ft/min

Air Volume,

cfm

1.CPR, 890 ML 1x200 172,000 248.52 703.00 174,709.56

2. NE, 890 ML 2x200 172,000 193.65 1,106.00 214,176.90

74

Page 75: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

3. 4-7 Exhaust, 840

ML2x200 86,000 131.79 298.00 39,273.42

4. 4-4B Exhaust,

840 ML2x75 50,000 221.00 118.00 26,078.00

5. 4-7 Exhaust, 773

ML2x200 172,000 166.54 1,396.00 232,489.84

Total 686,727.72

2.3 Table for Final Main Exhaust Air

Location/Level Unit/HpProjected

Vol., cfm

Area,

ft2

Air Velocity,

ft/min

Air Volume,

cfm

1.Bumolo #1 1x200 86,000 88 1,073 94.424.00

2. Bumolo #2 2x200 172,000 238 976 232,288.00

3. 1170 ML 1x200 86,000 72 1,388 99,936.00

4. CH-Drift #1,

1015 ML1x200 86,000 102 614.00 62,5853.02

5. CH-Drift #2,

1015 ML1x200 86,000 95 1,038 99,097.86

Total 516,000 588,330.88

U/G Air Requirement Computation

1015 ML

As of March 2010

Projected

QT

Y

Air Req’t. (cfm) Util.

Factor

Final Air Req’t.

Personnel 7 150 1.00 1,050.00

Trucks 2 8,500.00 0.20 3.400.00

75

Page 76: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Batching Plant 1 10,250.00 0.60 6,150.00

908/890/UCL

Sub-total 10,600

ST 7.5/TORO

45D/TORO 1250

6 27,700 0.60 99,720

ST 1030 1 30,000 0.50 15,000

TORO 301 1 18,800 0.50 9,400

Rock Breaker 7 5,000 0.60 21,000

FH/FD/RB 8 5,500 0.50 22,000

Normet 3 8,500 0.40 10,200

Personnel 100 150 1.00 15,000

Ore 80 10 0.60 480

840 ML

Sub-total 192,800

Personnel 30 150.00 1.00 4,500

Volvo/LPT Trucks 2 47,500.00 0.40 38,000

ST 6C/TORO 007 3 23,100.00 0.40 27,720

FH/FD/RB/Cubex 5 5,500.00 0.50 13,750

4-6 A/F 1 4,000.00 0.60 2,400

Ore 100 10.00 0.60 600

76

Page 77: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Trucking 1 8,500 0.50 4,250

782 ML/UCL

Sub-total 91,220

ST 6C/TORO

007/LH 410

6 23,100 0.60 83,160

ST 1030 1 30,000 0.60 18,000

ST 7.5Z/TORO

450D/TORO 1250

3 27,500 0.60 49,500

Rock Breaker 7 5,000 0.60 21,000

FH/FD/RB 2 5,000 0.50 5,000

Personnel 75 150 1.00 11,250

Ore 150 10 0.60 900

773/745 ML

Sub-total 188,810

Cleaning LHD ST

6C

3 23,100 0.40 27,720

ST 7.5Z/TORO

450D/TORO 1250

3 27,500 0.50 41.250

Rock Breaker 7 5,000 0.50 17,500

Personnel 100 150 1.00 15,000

2-4/4-4 Crusher 2 38,300 0.40 30,640

FBC’s 1 197,500 0.50 98,750

Ore 200 10 0.60 1,200

77

Page 78: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

CHC Loading

Area

4 5,000 0.50 10,000

Sub-total 242,060

Total Air Requirement 725,490.00

NOTE: 150.00 cfm per person

100.00 cfm per Horsepower of any UG equipment

10 cfm per ton of ore

Use utilization factor per unit

Draw Control / Loss control Section

This section controls and predetermines the required draw rate. Its objective is

to check that draw-out of the ore is informed as possible. Maximum tonnage with minimum

dilution is maintained in order to protect the block from damage and prevent the occurrence of

“pipe-outs”.

Functions of Draw Control:

1. Ore Extraction by Drawing

*Draw Rate – quantity that must be pulled out in draw point.

*Caving Rate – ability of the ore to be caved and crushed. It is directly proportional to draw

rate. If slow draw occurs, there will have pack-up and it will build pressure. To prevent this

from occurring, maximize ore recovery and minimize dilution, and check the draw order.

Here are some parameters needed:

78

Page 79: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

2. 1.1 grade – PCBC and GEMCOM

3. 1.2% extraction or age of draw

4. Condition of draw point

5. Ore Accounting (Tonnage Accounting)

6. Sampling/Grab sampling is done per draw point.

7. Draw Points Survey

8. Subsidence Area Operation

9. Backfilling of subsidence at the ratio of 1:5

10. Gradient of – 4% to – 7% towards the drainage outlet

11. Construction of benches to support wall

12. Maintenance of silt pond

13. Reforestation

1.5. Contract Management and Cost Control

UG Contract Activities:

1. Horizontal Driving

2. Jumbo Drill Machine

3. LHD

4. Pilot Raise Driving

5. Vertical (for short hole)

6. RDM (Rock Drill Machine)

7. Jackleg

79

Page 80: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

8. LHD

9. Alimak Driving (for long hole)

10. Concreting for draw crosscuts

11. Rock bolting/cable bolting

12. Steel set installation

13. Timbering

14. Shotcreting

Tire Budgeting and Cost Control

18”x12” Tire

Model No. of Units

TORO 007 6

ST 6C 4

LH 410M 6

ST 1030 3

Total 19

26.50”x25” Tire

TORO 1250 5

TORO 450D 5

ST 7.5Z 3

Total 15

17.5”x25” Tire

80

Page 81: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

TORO 301DL 3

*Annual Tire Budget of the Company: P68 million/year

Common Injuries of Tires:

1. Tread cut/punctured tread

2. Tread cut, IOL (injury over limit)

3. Tread separation

4. Side cut (4”)

5. Side cut, IOL (injury over limit)

6. Side cut separation

7. Shoulder cut (4”)

8. Shoulder cut, IOL (injury over limit)

9. Shoulder separation

10. Inner liner

11. Exposed ply

Scrap Tire Analysis

*Total Utilization Cost (TUC) = unit cost + repair cost x Trade Utilization Rate (TUR)

*Unrecovered cost = unit cost + repair cost – TUC

MINE DEVELOPMENT DEPARTMENT

81

Page 82: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Development is one of the stages in mining which continues throughout the life of a mine. It

refers to the works made for openings of a mineral deposit for exploration.

In underground mining, mine cannot suddenly start to produce ore and without making a

necessary development work. The major purpose of development is to provide access to the

ore deposits, permitting to have an entry for miners, equipments, supplies, power,water and

ventilation.

The following activities are done in preparing blocks, for ore extraction:

Production Lines – these are horizontal mainline pening/excavations that are parallel to each

other, which serve as main access of mobile equipments and supplies.

Draw Cross-cuts – these are horizontal excavations or heading driven across the production

lines sometimes called as Draw drift or drilling cross – cuts.

Undercut Lines – these are horizontal excavations driven above the production lines from

which fan holes drilling and undercutting takes place to

Induce the block to cave.

Pilot Raises – these are vertical opening driven to serves as free face for the fan hole blasting

at the trenches. These openings could be driven either vertical or inclined.

Fan Hole Drilling – long hole drilling at the trenches and for undercut where in this hole are

blasted to create a draw hole or the trench or to induce caving at the undercut.

82

Page 83: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Rock Supports – these are accessories being applied on the rock for stabilization purposes.

Include herewith are, rockbolts, cablebolts, wire mesh, shotcrete, steel set, concrete, cable

strap and tendon straps.

Undercutting – this activity refers to the blasting of rings of long holes designed to induce the

caving of a certain block. It includes trench and ITH blasting.

2.1. Sizes of the Main Headings:

Headings Standard Size

Production Lines 3.5m x 4.0m

Draw Crosscuts 3.0m x 3.5m

Access Ramps 4.0m x 4.0m

Long Transfer Raises 2.0m x 2.0m

Undercut Lines 3.5m x 3.5m

Drainage Drifts 3.5m x 3.5m

Pilot Raises 2.5m x 2.0m

UNDERGROUND DEVELOPMENT ACTIVITIES

Horizontal and Vertical Driving

Methods in Driving Vertical Headings:

83

Page 84: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

1.Conventional Raise Driving – It consists of utilizing timber and wooden ladders as

platforms for short raise while in the long raise, the chute and manway system of advancing is

employed.

2. Alimak Raise Driving – It is mostly used in long and vertical or inclined raising. The

Alimak which is commonly called “the raise climber”, consists of hoist with working

platform having a rack or pinion drive. It travels along a monorail with pin rack and integrated

pipes for air/water and is bolted to the wall of the raise.

Rock Support Installation

Rock Support Installation Sequence and Development Headings:

1. Openings within Fault Zones

2. Initial shotcrete (with synthetic fibers or install 4” mesh)

3. Rock bolt (1.0m x 4.0m spacing)

4. Steel set (15m advance for PL’s and 10m for DXC’s)

5. Construct concrete support by following the steps:

6. Steel set installation

7. Dowel installation

8. Steel reinforcing/matting

9. Forming/pouring

10. Dismantling of forms

11. Openings outside Fault Zones

12. Rock bolt (1.0m x 2.0m spacing)

13. Initial shotcrete (2” thick)

84

Page 85: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

14. Wire mesh/cyclone wire

15. Final rock bolt (place in between initial rock bolts)

16. Cable bolt (2.0m x 2.0m spacing)

17. Final shotcrete (2” thick)

Note: In addition for areas that shotrcrete with synthetic fibers will be used in lieu of wire

mesh, the following will the sequences:

1. Rock bolt (1.0m x 1.0m spacing)

2. Initial shotcrete using synthetic fibers (3” thick)

3. Cable bolt

4. Final shotcrete

Fan Hole Drilling

It is a long hole drilling at the trenches and for undercut where the holes are blasted to create a

draw hole or the trench or to induce caving at the undercut.

Trench Excavation

Trenches must only be opened up after steel set and concreting of draw points or additional

supports during the development of the draw post.

Undercutting

This is the last activity in the development wherein the rings of long holes are being blasted to

induce the caving of a certain block. It includes trench and ITH blasting.

2.3. Activities Performed by the Trainee in the Development

1. Rock bolting

The support specifications are as follows:

85

Page 86: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Equipment used: Rock Bolter (Robolt)

Size of rod used: 8’ x 38mm

Size of button bit: 4” x 38mm

Size of rock bolt: 7’

Size of base plate: 6” x 6”/8” x 8”

Size of screw: 2 ½”

Cemextra capsule: 1” diameter; 1’ length; 8pcs/hole

Length of drill hole: 2.4m

Pattern: 9 holes per set-up (5 pcs. for roof and 4 pcs. for wall)

Spacing: 2m per set-up

2. Timbering

Sizes of log used: 6” x 8” x 10’; 6” x 8” x 12’; 3” x 8” x 10’

3. Vertical Driving/Pilot Raising

Equipment used: Alimak/Jackleg

4. Horizontal Driving

Equipment used: Jumbo Drill Machine

Size of rod: 12ft.

Size of bit: 15mm.

Penetration rate: 2 minutes per hole

5. Shotcreting

Equipment used: Variomec (concrete mixer); Spraymec (shotcrete machine)

86

Page 87: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Wet mix: accelerator (MEYCO SA160)(4 – 5 L/mix), cement, plastic fibers

6. Fan Hole Drilling

Equipment used: SOLO – B#9 Fanhole drill

Size of rod: 1.22m

No. of holes per fan: 17

Spacing: 2m

7. Concreting (Batching Plant)

Mix

Purpose Crushed Sand

(kg)

Cement

(kg)

Gravel

(kg)

Water

(kg)

Grouting (for cable bolting) 1,500 480 - 175

Pouring with gravel (for steel

setting)

1,200 480 380 175

Shotcreting with plasticizer

(Glenium)

1,350 400 - 120

8. Steel Setting

Advances: 15m for PL’s and 10m for DXC’s

9. Cable Bolting

Equipment used: Jackleg/Jumbo Drill/Axera/Robolt

Size of cable bolt: 6.2m (3 cables)

Size of polyethylene pipe: >6.2m

87

Page 88: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Size of dowel: 4ft. (2ft. standard)

Diameter of hole: 32mm

Distance between bolts: 2m

Mix: 1bag (40 kg) cement, 13 – 14 Lwater

10. Loading and Blasting

Explosive used: Senatel Magnum Dynamite (for pilot raising and face drilling)

Excel Detonator Firing Times

Delay No. MS Delay Time (MS) LP Delay Time (MS) J-Hook Color

0 0 25 Dark Green

1 25 200 Red

2 50 400 Pink

3 75 600 Tan

4 100 1000 Orange

5 125 1400 Cream

6 150 1800 Yellow

7 175 2400 Lime

8 200 3000 Light Green

9 250 3800 Green

10 300 4600 Aqua

11 350 5500 Light Blue

12 400 6400 Blue

88

Page 89: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

13 450 7400 Mauve

14 500 8500 Purple

15 600 9600 Hot Pink

Surface Delay Times

Delay J-Hook Color

9 Green

17 Yellow

25 Red

42 White

65 Blue

100 Orange

125 Cream

150 Mustard

175 Lime

200 Light Green

*EXEL MS Detonators use pink tubing.

*EXEL LP Detonators use yellow tubing.

It is important that the holes should be drilled at the right location. The drilling pattern

also includes information on the lookout angle needed at the different points on the face.

89

Page 90: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Follow then the usual procedure of charging. Here are some of the drilling and blasting

patterns gathered:

MINE PRODUCTION DEPARTMENT

Exploitation is the final stage of mining associated with the actual recovery of mineral

from the earth in quality. While development works is necessary continuous throughout the

life of a mine, exploitation emphasis in the mine extraction and production.

The mine production must be give a proper consideration in the mine planning and design

especially in the selection of mining method to be use to extract the ore body in economical

and profitable manner. And also the equipment to be use, drilling and blasting techniques,

mucking and ground support to be adopted, for the continues production and the target or

projected tonnage/volume will meet.

The major purpose of mine production department is to extract and recover quantity of

minerals from the ore body.

This department has the following objectives and functions

A. To extract ore and deliver it into the overpass according to production schedule in order to

meet the required tonnage and grade and sustain feed to the mill.

B. To implement block maintenance program at various ore sources in order to maintain the

required readily available draw points and safe working environment.

C. To coordinate with the mine mechanical and mine electrical group, regarding preventive or

repair maintenance of various production equipment and installations to see to this optimum

utilization.

90

Page 91: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

D. Responsible for the safety of mine in various production activities such as secondary blasting,

timbering, high packing, LHD operation.

3.1. Mine Ore Flow

PERFORMED UNDER PRODUCTION

Secondary Blasting or Bouldering

When properly initiated, commercial explosives are rapidly and violently converted into

gases at a very high temperature and pressures. The rapid conversion of solids and liquids into

gases is called “detonation”. The effectiveness of explosives in blasting is due to the speed

with which the gas pressure is developed. The company then provided the appropriate

explosives for the blasting of their ores. Here are of the explosives they use:

1. Powergel, 25mm x 300mm

2. Powergel, 32mm x 300mm

3. ANFO-Repacked (64:40 ratio)

91

Scooping

Rock Breaking

Ore Rehandling

Ore Crushing

Conveying

Page 92: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

4. Ordinary Blasting Cap (OBC) with safety fuse

5. Netex Detonator Fuse, 5g

6. Cordtex Detonator Fuse, 10g

Method Used in Secondary Blasting:

1. High Packing Method

It is employed in bringing down hang-up or clogged large or blocks at the undercut level

or within finger raise column. This method is used by providing a series of wooden ladders to

reach clogged fragments. The supported large blocks of ore are drilled and blasted. This

activity is undertaken by highly skilled miners and is supervised to strictly implement the

SOP’s.

2. Blasting Stick Method

The method is used to bring hang-up at the undercut level or above the brow of the

draw point. A considerable amount of ANFO in plastic cartridge and dynamite stick are tied

around the end of the stick or pole. It is then wedged in between the large blocks of ore.

Initiation is done at the slusher line through detonating cord. The strong shock which is

generated by the blast will either bring down or break the large boulders.

3. Pop-Hole Drilling or Bouldering

Clogged boulders are drilled by the pneumatic drills and the drill holes are charged

with explosives.

4. Mud Capping

Considerable amount of explosives are plastered over large boulders with mud/clay.

This amount is also done at the slusher lines to break the ore fragments into smaller sizes that

can pass through the grizzly.

Rock Breaking

92

Page 93: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Equipment used: Rock Breaker Machine

Basic parts: hoist, dipper, tilt, swing, breaker stick/fire

Ore Extraction/Scooping/LHD Operation

Equipment used: LHD’s

Cycle time: 165 seconds

Distance between grizzly and LHD: 1m

Contractor: BBF, Vanos

Bucket Factor of LHD Units

No. of

Bucket

Counts

LHD Units

TORO

450D/TORO

1250

ST

7.5

ST

1000/1010/1030

TORO

007/LH 410

TORO

300D/301D

Bucket Factor at 90% Fill Factor

8.33 7.50 7.20 5.99 4.51

MT MT MT MT MT

1 8 8 7 6 5

2 17 15 14 12 9

3 25 23 22 18 14

4 33 30 29 24 18

5 42 38 36 30 23

6 50 45 43 36 27

93

Page 94: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

7 58 53 50 42 32

8 67 60 58 48 36

9 75 68 65 54 41

10 83 75 72 60 45

11 92 83 79 66 50

12 100 90 86 72 54

13 108 98 94 78 59

14 117 105 101 84 63

15 125 113 108 90 68

16 133 120 115 96 72

17 142 128 122 102 77

18 150 135 130 108 81

19 158 143 137 114 86

20 167 150 144 120 90

21 175 158 151 126 95

22 183 165 158 132 99

23 192 173 166 138 104

24 200 180 173 144 108

25 208 188 180 150 113

26 217 195 187 156 117

27 225 203 194 162 122

28 233 210 202 168 126

94

Page 95: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

29 242 218 209 174 131

30 250 225 216 180 135

31 258 233 223 186 140

32 267 240 230 192 144

33 275 248 238 198 149

34 283 255 245 204 153

35 292 263 252 210 158

36 300 270 259 216 162

37 308 278 266 222 167

38 317 285 274 228 171

39 325 293 281 234 176

40 333 300 288 240 180

41 342 308 295 246 185

42 350 315 302 252 189

43 358 323 310 258 194

44 367 330 317 264 198

45 375 338 324 270 203

46 383 345 331 276 207

47 392 353 338 282 212

48 400 360 346 288 216

49 408 368 353 294 221

95

Page 96: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

50 417 375 360 300 226

Long Transfer Raise (LTR) and Feeder Belt Conveyor (FBC)

Gathered Data about Conveyors and Crushers in the Production

Conveyor/Crusher Length (m) Date

Established

Inclination

(degrees)

Rated Capacity

(TPH)

FBC #1 408 May 15,

1998

10.9 6,976

FBC #2 528 Sept. 5, 1998 8.78 8,268

FBC #4 320 Feb. 16, 2002 2.15 12,256

FBC #5 440 Feb. 18, 2007 5.46 12,256

FBC #6 175 Sept. 16,

1998

10.83 8,268

FBC #17 381 Nov. 14,

2005

Plane 6,532

FBC #18 132 Nov. 14,

2005

10.83 6,532

Short 8.1 August 2007 Plane 3,488

By-pass 22.17 May 14,

1998

10 3,488

Sacrificial 35 May 2009 6 27,500

4-4 Crusher C140

(previous

April 2001 10,348

96

Page 97: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

name)

2-4 Crusher C140 April 2001 2,962

*Tons per Hour (TPH) = (Average Amps – 70) x Operation Time x 0.90

Cable Hauled Conveyor (CHC) Operation

Length: 2.7 km (from production to mill primary crushing plant)

Rated Capacity: 27,500 tph

3.3. Production and Average Ore Grade

Philex Mining Corporation has a daily production of 26,000 MT per day with an

average grade of 0.28% Cu and 0.674g Au/ton. Sources of ore tonnage came from 908 ML.

The average concentrate produced is 24-27% Cu and 30-64g Au/ton. The ore is drawn by the

action of gravity at 908 ML and then using LHD equipment or scoop trams and transported

through transfer raises to 782 ML where CHC takes off towards the dump bin which is 2.7 km

away from the orebody.

4. Mechanical/Electrical Services Group

The Mechanical/Electrical Services Group is tasked to support the company operation

with utmost efficiency to enable the operation group attain their objectives.

The group particularly the mechanical services and electrical is primarily concerned in

the proper generations and distributions and maintaining the 36-MW Benguet Power Plant

and 500-kW Mini-Hydro. The Benguet Power Plant supplies of about 27% of the operation

total power needs. The two compressed air plants also supplies 100-psi compressed air to the

underground and mill. The Mobile Equipment Department on the other hand, transports

copper concentrate from the mine site to Poro. It also maintains all heavy equipments used in

surface operations and light vehicles of the company.

In doing so, the group exerts continuous effort toward underground planning,

installation, maintenance and cost operation.

97

Page 98: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

THE MILL DIVISION

The division is established to process the ore from the underground by

processing it systematically in every areas of the mill plant. It is also the responsibility of the

division to maintain the efficiency of the equipments they installed and monitor the daily

metallurgical operation of the plant by simply conducting sampling of the basic parameters to

control the quality of the final product. The samples are tested in advance to determine the

recovery. They also carefully dispose the mill tails in the proper containment.

MILL PROCESS DESCRIPTION

Primary Crushing Section

98

Page 99: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Coarse ore is delivered from the mine to the primary crushing plant via the cable

hauled conveyor system (CHC) at the rate of 28,000 tons a day. The ore drops to three units

of vibrating scalper each of which is atop a 2,438 mm x 6,096 mm dewatering screen with 9.5

mm opening. The minus 9.5 mm material is currently conveyed via a series of launders and

canals to the slimes screen while the plus 9.5 mm material drops to a 5,600-ton capacity dump

bin.

Underneath the dump bin are four units of apron feeders individually feeding four

units of 762 mm x 1,067 mm jaw crusher. These jaw crushers are set at 100 mm closed side

setting. The crushed product of each jaw crusher is fed onto four parallel conveyors each

feeding to a unit of 1,524 mm x 4,877 mm washing screen with 9.5 mm opening. The oversize

is conveyed to a 30,000 T capacity coarse ore stockpile (COS) while the undersize flows

through a series of canals to the slimes screens.

99

Page 100: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

There are four units of 1,524 mm x 4,877 mm slimes screens with 2 mm opening. The

last panel is however fitted with 12.7 mm screen. The minus 2 mm material, which is

considered as the primary slimes, flows and is fed to the ball mill discharge sump box for

cycloning. The minus 2.7 mm is conveyed to the fine ore bin while the oversize is brought to

the secondary/tertiary crushing section.

Part of the slime generated by the dewatering screen is fed to a bank of sieve bends (8

units) with 2 mm opening. The oversize of the sieve bends is conveyed to the fine ore bin

(FOB) while the minus 2 mm material is fed to two units of rake classifier. The classifier sand

is combined with the sieve bend oversize and is conveyed to the fine ore bin. The overflow of

the rake classifier is fed to a cluster of hydrocyclones. The cyclone overflow is fed to a 7 m

diameter x 9 m high slime surge or conditioning tank. These slimes are treated separately in a

Wemco 164 flotation bank. The cyclone underflow is piped to the ball mill discharge sump

box.

Secondary/Tertiary Crushing Section

100

Page 101: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

From the COS, the ore is withdrawn and conveyed to a 675 T capacity surge bin.

From this bin, the ore is then fed to three units of 1,676 mm standard cone crushers used for

secondary crushing. The secondary crushers are set at 38 mm closed side setting. The crusher

product is conveyed to a 2,800 T capacity surge bin.

From this bin, the ore is withdrawn and fed to 16 units of 1,524 mm x 3,657 mm

vibrating screen with 9.5 mm opening. The oversize of the screens is fed to seven units of

1,676 mm short head cone crushers. The tertiary crushers are set at 9.5 mm closed side

setting. The tertiary crusher product combines with that of the secondary crusher product for

screening. The setup is two vibrating screens in series with a tertiary crusher.

The undersize of the screens is considered as the final product of the crushing plant

and must be at least 73% passing 10 mm. This is conveyed to the FOB.

Grinding Section

101

Page 102: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

c

cc

c

c

c

cc

c c

c

2nd Cleaner 3rdCleaner

1st Cleaner

Wemco D

Wemco C Wemco ESmartcells

Main Flotation Feed Box Distributor

50 ft Thickener80 ft Thickener

75 ft Thickener

250 ft Thickener

Copper Lot

1

2

3

4

1

2

3

5

4

5

6

7

8

7

8

9

10

11

9 10 1112 13 14

15 16 17

18 19 20 21 22 23 24 25 26

1 2 3 4

56

Drum Filter(2 units)

27 28 29 30

FeedFeedFeedFeed

Conc Conc

Conc

Conc Conc

Conc

Conc

Conc

Booster Tank

Tails

TailsTailsConc

ConcTails

TailsTails

Conc

Tails TailsFFC

Filter Cake

Final Tails

Recycled process water

10 units Sluice

Launders

There nine FOB’s with an aggregate capacity of 17,000 T. From these bins the ore is

withdrawn and fed to ball mills. There are nine ball mills of varying sizes ranging from 3,510

mm x 4,270 mm to 5,030 mm x 8,230 mm. Two mills serve as spare to sustain milling

tonnage. All mills are charged with 32 – 35% steel ball loading at 45% 90mm and 55% 80

mm composition of cast steel balls. The circulating load average is around 300 – 450%.

The cyclone overflow or finished product of the grinding section is normally 60 –

65% passing 200-mesh (74 micrometers) at 1,260 – 1,320 g/l pulp density. This material

flows by gravity through four parallel trash screens before being fed to the flotation circuit.

Flotation Section

102

Page 103: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Copper, gold, silver and sulphide minerals are separated from the waste or gangue

portion of the ore by a rougher flotation circuit which comprises of six Wemco Smart Cells

and four Wemco 164 banks, having a total volume of 1,206 m3. The rougher concentrate

produced is upgraded in a three stage cleaning circuit. The first cleaning stage consists of 4

units of Wemco 164 with a volume of 113 m3 and the second and third cleaning stages

consist of two units Column Flotation with a total volume of 170 m3.

Tailings from the roughers are passed through parallel sluice launders to recover

mineral values in the tails before it is fed to the tailings thickeners. Recovery of the mineral

values is done daily. Rougher concentrate is piped to the first cleaner for upgrading. The first

cleaner tails is pumped back and combined with the rougher feed. The first cleaner

concentrate is pumped to the first Column Flotation serving as second cleaner. The first

Column Flotation tails drops back and combined with the rougher concentrate which is fed to

the first cleaner. The first Column Flotation concentrate is pumped to the second Column

Flotation for final upgrading and the second column tails is recirculated back to the first

column.

Chemical reagents used to recover the minerals are sodium isobutyl xanthate (SIBX)

added at a dosage rate of 25 to 30 g/t and frother added on a as-required basis. SIBX serves as

the collector for the values while frother is added to stabilize the froth.

The pH is also regulated at 10 to 10.5 in the roughers and 11.5 to 12 in the cleaners by

the addition of quicklime. A milk of lime production facility handles the addition of

quicklime. The table shows the capacity of the flotation bank.

Flotation Bank Capacity

At: Optimum Flotation Time = 25 mins.

103

Page 104: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Optimum Pulp Density = 1,300 gpl

Optimum % Solids = 37

Flotation Bank’s Factor for Aeration = 17%

Total

Flotation

Bank Volume

(m3)

Total Flotation

Bank Effective

Volume

(m3)

% Feed

Distribution

Total Feed Rate (tph)

Solids

(Total

BM +

Slime)

Slurr

y

Wate

r

Wemco A 198 164 16 189 512 323

Wemco B 198 164 16 189 512 323

Wemco C 255 212 21 245 662 417

Wemco D 255 212 21 245 662 417

Wemco

Smart

Cell

300 249 26 287 777 490

Total 1,206 1,001 100 1,155 3,125 1,970

1.5. Concentrate Handling Section

The final concentrate produced from the second column is first thickened in a 22.86 m

diameter thickener before being fed to two units of 3,048 mm x 3,048 mm drum filter. The

dewatered final concentrate filter cake having a moisture content of 10 to 11% is hauled by

trucks for shipment to contracted copper smelters in Japan.

1.6. Tailings Disposal and Water Handling

104

Page 105: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

The final tails coming out of the rougher flotation is piped to two units of 76.2 m

diameter thickeners for water reclamation. The thickener overflow is recirculated back to the

plant as process water while the underflow flows to the tailings pond for impoundment.

Additional fresh water is also pumped from Sal-angan creek. A system for flocculants

addition is provided in case the need arises.

2. Mill Maintenance

The department practices “area maintenance policy”, a policy supervised by a general

foreman and coordinated planner.

The mill is subdivided into four main areas namely:

14. Primary Crushing

15. Secondary Crushing

16. Grinding

17. Flotation and Thickening Plant

The gold recovery equipment is maintained in designated area where they are installed.

Metallurgy Department

The Metallurgy Department is composed of four sections:

Plant Metallurgy and ISA Section

This section is responsible in monitoring the day to day activities concerning

metallurgical operation of the plant, preparing the mill reagents and ensuring that the said

reagents are readily available for use in the milling operations, maintaining the reagent

mixers, feeders and pipelines, conducting screen analysis for mill samples and ensuring the

availability of the In-Stream Analysis equipment to monitor the copper analysis and density at

selected streams.

Quality Control and Sampling Section

105

Page 106: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

They are responsible in conducting sampling in the mill process streams, monitoring it

during mill reagents addition and also the ball mill cyclone overflow densities, pulp pH, pulp

density, pulp boxes, spillages, screen opening. They are also getting samples for the Quick

Assay Monitor and determining the moisture content of ball mill feed, filter cake and hauled

concentrate to Poro.

The following are metallurgical parameters that are closely minotored:

Metallurgical Parameters Productivity Indices for 2010

Steel ball, gpt 376

Lime, gpt 1,000

SIBX, gpt 30

Frother, gpt 16

Power, kwhr/ton 18.06

Work Index -

Ball mill product size, %+65 mesh 6 – 9

Final tailing, %-200 mesh 60 – 65

pH at rougher 10 – 10.5

pH at cleaner 11.5 – 12.0

Flotation pulp density, g/l 1,270 – 1,300

Sampling then is done every hour in most of the sampling points except in the final

flotation tails in which the automatic cutter is set at 15-minute interval and in copper lot in

which sample is taken in every bucket load of the front end loader. These samples are

analyzed in selected areas. Mill reagents additions are measured every hour. Points of addition

as well as the adjustments of the reagents are checked from time to time in order to maintain

106

Page 107: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

the exact recovery of gold and copper. The table shows the areas where it is regularly

controlled.

MET Quality Control Section Regular Samples

Sample Sampling Point Method Sample Purpose Analysis

Needed

1.Conveyor

#15

Discharge of

conveyor

Automatic cutter Met.Acctg./R&D Cu, Au,

CuO,

water,

screen, SG,

wl

2.Cyclone

overflow

Common

cyclone launder

of each mill

Manual cut Control parameter PD screen

3.Slimes 1 Canal at

secondary/tertia

ry crushing

plant

Manual cut Met.Acctg./R&D/

Geo.

Cu, Au,

CuO,

screen, SG,

PD

4.Slimes 2 Flowlip of slime

distribution box

Automatic cutter Met.Acctg./R&D/

Geo.

Cu, Au,

CuO,

screen, SG,

PD, pH

5.Main

flotation

feed

Main flotation

distribution box

Submersible

cutter

Met.Acctg./R&D/

Geo.

Cu, Au,

CuO,

screen, PD,

pH

6.Rougher

tailsDischarge tails

107

Page 108: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

6.1.Wemc

o A

6.2.Wemc

o B

6.3.Wemc

o C

6.4.Wemc

o D

6.5.AgitAir

pipeline

Discharge tails

box

Discharge tails

pipeline

Discharge tails

pipeline

Discharge tails

pipeline

Manual cut

Manual cut

Manual cut

Manual cut

Manual cut

Control Parameter

Control Parameter

Control Parameter

Control Parameter

Control Parameter

Cu, Au

Cu, Au

Cu, Au

Cu, Au

Cu, Au

7.Final

flotation

tails

Convergence

point of tailings

line

Automatic cutter Met.Acctg./R&D/

Geo.

Cu, Au,

CuO,

screen, PD

8.First

cleaner feed

Feed box of first

cleaner tank

Submersible

cutter

Control Parameter Cu, pH

9.First

cleaner

concentrate

Discharge end of

overflow

launder

Manual cut Control Parameter Cu, Au

10.First

cleaner tails

Discharge of

cleaner tails

pump #1

Manual cut R&D/Geo. Cu, Au

11.Second

cleaner

Feed box of

third cleaner cell

Submersible

cutter

Control Parameter Cu, Au

108

Page 109: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

concentrate

12.Second

cleaner tails

Not available - Control Parameter Cu

13.Third

cleaner

concentrate

Feedwell of 75-ft

thickener

Automatic cutter Control Parameter Cu, Au

14.Third

cleaner tails

Discharge end of

tails line

Manual cut Control Parameter Cu

15.Filter

cake

Discharge cake

of filter machine

Manual cut Met.Acctg./R&D/

Geo.

Cu, Au, Ag,

water,

screen

16.Copper

lot

Bucket of loader Manual cut Met.Acctg./R&D Cu, Au, Ag,

water,

screen

17.Special

samples

17.1.for

microscopicItems 1, 3, 4, 5,

10 and 15

Automatic/

manual cut

Geology For

petrographi

c analysis

Metallurgical Test and Research Section

They are responsible for all metallurgical tests in which findings are applied in the

milling operation. The results then are used as reference. The samples from mine underground

are tested in advance to determine their recoveries. They are also responsible for the

evaluation of new technologies needed in the operation.

109

Page 110: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Mill Engineering Section

It is responsible for all projects being undertaken in the mill plant. It is involved in the

studies being conducted from crushing through ball mill, flotation, filtering, and thickening.

They are also into procurement of mill equipment and spare parts; computes and monitors the

steel ball charges and the equipment and parts performance.

Assay Department

Assay Department is tasked in the metallurgical accounting of production, and the

mode of calculation and actual production. A daily calculation of both methods is done to

determine the variance. The resulted variance between the two methods is reconciled monthly

following the actual production of concentrate of copper. The actual gold bullion production

is also reconciled with estimated gold grams from amalgam. The variances are adjusted to the

copper and gold feed grade.

There is a future plan, however, to revise the computation of the daily production and

to reconcile the mine ore delivery with the tons milled.

Concentrate produced every shift are hauled to Poro to accumulate the required

tonnage for shipment. Daily deliveries are recorded and monitored. The weights and moisture

loss are submissive on the system loading. The inventory of concentrate is adjusted based on

the report of Poro regarding the concentrate leftover.

Productivity Indices for 2010

Particulars Unit Productivity Indices for 2010

Milling Tonnage,

monthly

DMT 700,000

Milling Tonnage, daily DMT 25,000

Heads, Cu % 0.220

110

Page 111: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Heads, Au g/t 0.550

Concentrate DMT 5,589

Grade, Cu % 25.00

Grade, Au g/t 58.14

Moisture % 11.50

Tails Grade, Cu % 0.040

Tails Grade, Au g/t 0.110

Metals Produced

Cu Kgs.

Lbs.

1,262,019

2,782,273

Au Grams

Oz.

308,555

9,920

Different Assay Analyses Conducted by the Department:

1. Sample Preparation

2. Primary Crusher (Jaw Crusher)

3. Roller Crusher

4. Pulverizer

5. Drying Oven

6. Fire Assay (Au and Ag Analysis)

7. Fusion Furnace

111

Page 112: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

8. Cupellation Furnace

9. Annealing Furnace

10. Pulp Balance (Top Loading)

11. MicroBalance

12. Chemical Laboratory (Metals in Ore Analysis)

13. Hot Plate Digester

14. Microwave Digester

15. Digital Burette

16. Analytical Balance

17. Atomic Absorption Spectrophotometer (AAS)

18. Magnetic Stirrer

19. Water Bath

20. Mechanical Shaker

21. Used Oil and Water Analysis Laboratory

22. Analytical Balance

23. Soxhlet Apparatus

24. Distilling Flask

25. Hot Plate

26. Viscometer

112

Page 113: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

TAILINGS POND

Padcal Mine Tailings Containment System

Before then, Pres. Marcos enacted a law known as Pollution Control Law in 1976, the

company started the construction of its first dam. It is composed of slurry materials of finely

ground materials of gangue minerals produced after the extraction of valuable minerals.

From the Banget mill which is 27 km long tailings tunnel and received by three

parallel 16 inches diameter pipelines of about 4 km long. Before discharging the containment

area or the main dam, the slurry passes through a cyclone to separate the coarse sands from

the fines or slimes. The coarse sand is conveyed downstream to build the dikes supporting the

main dam. The fines are deposited at the main dam where the process of decantation takes

place such that only clean water is released through the penstocks to join the receiving body

of water, in this case, the Balog River which is a tributary of the Agno River. The effluent is

monitored from its total suspended solids and heavy metals as prescribed in the DENR

AO#35 series 1990. The PMC has constructed three impounding dams.

The construction of Tailings Dam No.1 began on December 1967 at a cost of P8.633

million and was immediately put into operation in April 1971. This dam is longer operative

for tailings impounding but still is being maintained. The total metric ton tailings impounded

was about 85.2 million DMT.

Tailings Dam No.2, on the other hand, was started on July 1973 and completed

December 1981 at a cost of P37.137 million. Its operation started on the same year where it

was completed receiving an average of 50% of the mill tailings, while the other 50%

remained at Tailings Dam No.1 for the continuous build-up of its Toe Dam downstream.

Tailings impounded at Dam No.2 were about 76.4 million DMT.

The construction of Tailings Dam No.3 was started in September 1983 and became

operational in April 1992. As the impounding operation progresses crest of the main rock fill

dam, its downstream supporting benches and the penstocks are being raised to maintain the

113

Page 114: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

required free board. Total construction cost at dam no.3 as of January 31, 2010 was 331

million pesos. Its impounding capacity is 142.6 million DMT with a height of 160 meters.

The Tailings Pond

The company is very aware of its commitment to protect its environment from the

effects of pollution that it may cause due to its mining and milling operations. In this regard,

Philex has constructed three impounding dams.

The first pond as the tailings dam no.1 was completed in 1971 at a total cost of 8.8

million pesos, with a depth of 122 meters. It has ten years of its usage. Due to limited capacity

of this dam, the construction of the second dam was made. Tailings dam no. 2 was

constructed between the years 1971-1981 with the total cost of 37.3 million pesos. It had 11

years of usage from 1981-1992. The dams were being utilized continuously to contain the mill

114

Page 115: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

tailings from the Benguet Concentrator. With the average of milling capacity of 27,000 DMS

per day, the combine service life of the dams were only up to 1986 only. Tailings dam no.3

was designed and constructed from the year 1983 to 1995. It has the 6.6 DMT capacities that

it could accommodate. Until now. Dam no.3 is being utilized.

Table 1 indicates the expected useful life, area, capacity, and status of Philex Mines’

three tailings ponds.

Table 1 . Philex tailings pond, expected useful life, area, capacity, and status

Tailing Pond/

Dam

Expected

Years of

Useful Life

Surface

Area

(hectares

Designed

Impounding

Capacity (in

metric tons

Status

Tailing Pond #1 10 26.16 85,259.975 Closed in 1981

Tailing Pond #2 11 28.19 72,067,331 Closed in1992

Tailing Pond #3 18-20 63.08 142,000,000 Active

115

Page 116: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

MAJOR AWARDS/CITITIONS

PHILEX WINS NATIONAL OUTSTANDING VOLUNTEER AWARD

It's another feather added to Philex's cap!

Philex Mining Corporation was conferred with another distinction, this time, as

a NATIONAL OUTSTANDING VOLUNTEER AWARDEE – Organization (Corporate) 

category. The award, conferred by  the Philippine National Volunteer Service Coordinating

Agency under the National Economic and Development Authority (NEDA),  is in recognition

116

Page 117: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

of the Company’s exemplary volunteerism in the protection and preservation of life under

emergency circumstances. Over the years, Philex has taken on a very active role in civic 

volunteer work, most notably  in emergency  rescue and retrieval operations all over the

country. For this year alone,  the Company has extended assistance in at least four tragic 

incidents,   in Tinoc,  Ifugao, Mayantoc, Tarlac, Kias, Baguio City and  La Trinidad,

Benguet.    It has also assisted in the clearing operations along Kennon Road  and Naguilian

Road as a result of the devastation brought about by TyphoonPepeng.

On December 10, 2009, the Philex delegation headed by Engr. Joel S. Son personally

received the award in Malacañang from no less than the President of the Philippines, Gloria

Macapagal Arroyo.

Earlier, Philex Mining Corporation, Engr. Joel S. Son and Hilario R. Villanueva were

selected as   Regional Winners in the Search for Outstanding Volunteers in the organization

and individual categories respectively.  The awards were given by Benguet Governor Nestor

Fongwan and NEDA-CAR Regional Director, Juan B. Ngalob on the occasion of the Regional

Development Council En Banc meeting in La Trinidad, Benguet on November 13, 2009.

Once more, Philex stands proud! Mabuhay ang Philex!

117

Page 118: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

PHILEX HAILED “BEST MINING FOREST”

At  a  testimonial  dinner at the CAMP - John Hay  Convention Center in  Baguio City on

November 22, 2008, Philex took top honors as it received the Best Mining Forest award for

fiscal year 2007 –  2008  during the 55th Annual National Mine Safety &

EnvironmentConference.Started in 1989 pursuant to a Government directive, the Adopt-a-

Mountain, Adopt-a-Mining Forest mandates all mining companies to conduct reforestation /

afforestation within or outside their active mining operation areas.  The program was renamed

“The Mining Forest Program” on October 26, 2005, per NEC Resolution No. 2005-02, to

make it separate and distinct from other DENR Reforestation Programs.

The criteria in the selection for this recognition are:

·         Development Plans – long and short range plans

118

Page 119: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

·        Nursery operations

·         Extent of Planted Area -  new plantation, total planted area, ratio of planted over

disturbed area

·         Maintenance and protection – density, survival rate, no. of persons involved

·         Biodiversity consideration – specie diversity, tree endemicity, wildlife migration

·         Others – Research/studies on Reforestation, IEC on reforestation community

involvement

The first, second and third runners-up for distinction went to Apex Mining Co., Inc., Philex

Gold Phils., Inc. – Bulawan Operation and Philex Gold Phils., Inc. – Sibutad Project,

respectively. Last year, Philex – Padcal also won the top honors for the same recognition.

In the same event, Engr. Joel Son, Safety Department Manager, received an award of

distinction in relation to the rescue and recovery operations Philex has been extending through

the country, the latest of which was the Gold Field Mine, Antamok tragedy where 10 miners

survived and 6 perished.

The only metal mining company in the Philippines awarded with ISO 14001 Certification

(Certificate No.: CI/1097 issued on 10 September 2002) even before the promulgation and

implementation of DENR Administrative Order 14, Series 2003. This certification is based on

119

Page 120: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

the company’s self regulation toward Improved Environmental Performance.

Presidential Award for Heroism - The company’s commitment to help in the country’s

rebuilding after natural disaster has been recognized through a Presidential Award for Heroism

in the aftermath of the February 20, 2006 Ginsaugon, Leyte landslide and the July 16, 1990

earthquake in Baguio City. The photograph shows the Padcal Mine Safety Manager receiving

the award from Pres. Gloria Macapagal-Arroyo.

Reforestation/Environment Awards:

2008, 2007, 2004, 2000-2002, 1994, 1991 - Champion: "Best Mining Forest"

2008 - Platinum Award (Silangan Mindanao Mining Company, Inc.) given by the

Presidential Mineral Industry  Environmental Awards (PMIEA)

2007 - ASEAN Outstanding Engineering Achievement Award (ASEAN Federation of

Engineers Organization (AFEO)

2005 - 2006, 2003, 1996-1999, 1990 - First Runner-Up - "Adopt-A-Mountain, Adopt-A-

Mining Forest"

2002, 2003, 2004 - Presidential Mineral Industry Environmental Award, Boyongan

Exploration Project - DENR/PMSEA

120

Page 121: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

1998 - Presidential Mineral Industry Environmental Platinum Award - DENR/PMSEA

1995 - Likas Yaman Awardee - Department of Environment and Natural Resources (DENR)

1983 - Four Green Stars (Highest award given to a mining company in the Philippines)

          International Loss Control Institute

Community Development, Health, Labor, & Others:

2008 - Special Award of Recognition for unselfish service extended during time of crises

(PMSEA)

2003 - Kapatiran Award: Strategic Visioning - ECOP

2000 - 2001 - CHILD-FRIENDLY FIRM Award - ECOP  

1999 - Commendation to the Philex Rescuers who helped in the Lumban, Laguna Tragedy

(DILG)

1997 - HAMIS Silver Award - Integrated Community Development Programs in Health Care

Management

          DOH/German Agency for Technical Cooperation

1997 - CAR's Most Outstanding Firm with Family Welfare Program - DOLE

1997 - Hall of Fame Award - Outstanding Lupong Tagapamayapa (under the Katarungang

Pambarangay Program; first barangay in the country to achieve Hall of Fame status)

1996 - One of the Most Outstanding Workplace in the CAR - DOH-CAR

1995 - SPEC Employer of the Year Appreciation Award - DOLE

1995 - One of the 50 Model Communities in the World by the "We the Peoples'

Organization" of the United Nations

1995 - Recognition - Municipality of Itogon - Community development projects

1994 - HAMIS Bronze Award for Integrated Community Development Programs in Health

Care Management - DOH

1994 - Hall of Fame Award for Family Welfare Programs - DOLE

1993 - One of the Philippines' 10 Best Managed Firms - Asiamoney's Survey

1993 - Recognition for Family Welfare Programs - DOLE 

121

Page 122: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

1992 - 1994 - One of the Philippines' 20 Most Oustanding Firms With Family Welfare

Program - DOLE

1992 - Acknowledgement - Ligay Community PTA/Ligay Catholic Mission - Road and

community development programs.

1991 - KABISIG Award - DTI

Safety Awards:

1994, 1975-1993, 1969 - Safest Underground/Block Cave Mining Operation

          Philippine Mine Safety & Environmental Association (PMSEA)

1978-1979 - Safest Concentrator - Philippine Mine Safety and Environmental Association

(PMSEA)

1977 - Exemplary Performance and Contribution to Safety Movement in the Philippine

Mining IndustrySafety Organization of the Philippines (SOPI)

MAJOR AWARDS/CITITIONS

122

Page 123: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

PHILEX WINS NATIONAL OUTSTANDING VOLUNTEER AWARD

It's another feather added to Philex's cap!

Philex Mining Corporation was conferred with another distinction, this time, as

a NATIONAL OUTSTANDING VOLUNTEER AWARDEE – Organization (Corporate) 

category. The award, conferred by  the Philippine National Volunteer Service Coordinating

Agency under the National Economic and Development Authority (NEDA),  is in recognition

of the Company’s exemplary volunteerism in the protection and preservation of life under

emergency circumstances. Over the years, Philex has taken on a very active role in civic 

volunteer work, most notably  in emergency  rescue and retrieval operations all over the

country. For this year alone,  the Company has extended assistance in at least four tragic 

incidents,   in Tinoc,  Ifugao, Mayantoc, Tarlac, Kias, Baguio City and  La Trinidad,

Benguet.    It has also assisted in the clearing operations along Kennon Road  and Naguilian

123

Page 124: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Road as a result of the devastation brought about by TyphoonPepeng.

On December 10, 2009, the Philex delegation headed by Engr. Joel S. Son personally

received the award in Malacañang from no less than the President of the Philippines, Gloria

Macapagal Arroyo.

Earlier, Philex Mining Corporation, Engr. Joel S. Son and Hilario R. Villanueva were

selected as   Regional Winners in the Search for Outstanding Volunteers in the organization

and individual categories respectively.  The awards were given by Benguet Governor Nestor

Fongwan and NEDA-CAR Regional Director, Juan B. Ngalob on the occasion of the Regional

Development Council En Banc meeting in La Trinidad, Benguet on November 13, 2009.

Once more, Philex stands proud! Mabuhay ang Philex!

PHILEX HAILED “BEST MINING FOREST”

124

Page 125: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

At  a  testimonial  dinner at the CAMP - John Hay  Convention Center in  Baguio City on

November 22, 2008, Philex took top honors as it received the Best Mining Forest award for

fiscal year 2007 –  2008  during the 55th Annual National Mine Safety &

EnvironmentConference.Started in 1989 pursuant to a Government directive, the Adopt-a-

Mountain, Adopt-a-Mining Forest mandates all mining companies to conduct reforestation /

afforestation within or outside their active mining operation areas.  The program was renamed

“The Mining Forest Program” on October 26, 2005, per NEC Resolution No. 2005-02, to

make it separate and distinct from other DENR Reforestation Programs.

The criteria in the selection for this recognition are:

·         Development Plans – long and short range plans

·        Nursery operations

·         Extent of Planted Area -  new plantation, total planted area, ratio of planted over

disturbed area

·         Maintenance and protection – density, survival rate, no. of persons involved

·         Biodiversity consideration – specie diversity, tree endemicity, wildlife migration

·         Others – Research/studies on Reforestation, IEC on reforestation community

involvement

The first, second and third runners-up for distinction went to Apex Mining Co., Inc., Philex

Gold Phils., Inc. – Bulawan Operation and Philex Gold Phils., Inc. – Sibutad Project,

respectively. Last year, Philex – Padcal also won the top honors for the same recognition.

In the same event, Engr. Joel Son, Safety Department Manager, received an award of

distinction in relation to the rescue and recovery operations Philex has been extending through

the country, the latest of which was the Gold Field Mine, Antamok tragedy where 10 miners

survived and 6 perished.

125

Page 126: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

The only metal mining company in the Philippines awarded with ISO 14001 Certification

(Certificate No.: CI/1097 issued on 10 September 2002) even before the promulgation and

implementation of DENR Administrative Order 14, Series 2003. This certification is based on

the company’s self regulation toward Improved Environmental Performance.

Presidential Award for Heroism - The company’s commitment to help in the country’s

rebuilding after natural disaster has been recognized through a Presidential Award for Heroism

in the aftermath of the February 20, 2006 Ginsaugon, Leyte landslide and the July 16, 1990

earthquake in Baguio City. The photograph shows the Padcal Mine Safety Manager receiving

126

Page 127: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

the award from Pres. Gloria Macapagal-Arroyo.

Reforestation/Environment Awards:

2008, 2007, 2004, 2000-2002, 1994, 1991 - Champion: "Best Mining Forest"

2008 - Platinum Award (Silangan Mindanao Mining Company, Inc.) given by the

Presidential Mineral Industry  Environmental Awards (PMIEA)

2007 - ASEAN Outstanding Engineering Achievement Award (ASEAN Federation of

Engineers Organization (AFEO)

2005 - 2006, 2003, 1996-1999, 1990 - First Runner-Up - "Adopt-A-Mountain, Adopt-A-

Mining Forest"

2002, 2003, 2004 - Presidential Mineral Industry Environmental Award, Boyongan

Exploration Project - DENR/PMSEA

1998 - Presidential Mineral Industry Environmental Platinum Award - DENR/PMSEA

1995 - Likas Yaman Awardee - Department of Environment and Natural Resources (DENR)

1983 - Four Green Stars (Highest award given to a mining company in the Philippines)

          International Loss Control Institute

Community Development, Health, Labor, & Others:

2008 - Special Award of Recognition for unselfish service extended during time of crises

(PMSEA)

2003 - Kapatiran Award: Strategic Visioning - ECOP

2000 - 2001 - CHILD-FRIENDLY FIRM Award - ECOP  

1999 - Commendation to the Philex Rescuers who helped in the Lumban, Laguna Tragedy

(DILG)

1997 - HAMIS Silver Award - Integrated Community Development Programs in Health Care

Management

          DOH/German Agency for Technical Cooperation

127

Page 128: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

1997 - CAR's Most Outstanding Firm with Family Welfare Program - DOLE

1997 - Hall of Fame Award - Outstanding Lupong Tagapamayapa (under the Katarungang

Pambarangay Program; first barangay in the country to achieve Hall of Fame status)

1996 - One of the Most Outstanding Workplace in the CAR - DOH-CAR

1995 - SPEC Employer of the Year Appreciation Award - DOLE

1995 - One of the 50 Model Communities in the World by the "We the Peoples'

Organization" of the United Nations

1995 - Recognition - Municipality of Itogon - Community development projects

1994 - HAMIS Bronze Award for Integrated Community Development Programs in Health

Care Management - DOH

1994 - Hall of Fame Award for Family Welfare Programs - DOLE

1993 - One of the Philippines' 10 Best Managed Firms - Asiamoney's Survey

1993 - Recognition for Family Welfare Programs - DOLE 

1992 - 1994 - One of the Philippines' 20 Most Oustanding Firms With Family Welfare

Program - DOLE

1992 - Acknowledgement - Ligay Community PTA/Ligay Catholic Mission - Road and

community development programs.

1991 - KABISIG Award - DTI

Safety Awards:

1994, 1975-1993, 1969 - Safest Underground/Block Cave Mining Operation

          Philippine Mine Safety & Environmental Association (PMSEA)

1978-1979 - Safest Concentrator - Philippine Mine Safety and Environmental Association

(PMSEA)

1977 - Exemplary Performance and Contribution to Safety Movement in the Philippine

Mining IndustrySafety Organization of the Philippines (SOPI)

V. Summary of Weekly Activities

128

Page 129: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Activity Duration Schedule Date

OJT Orientation 6 days April 10 - 15,

2012

Subtotal 6 days x 8 hrs. =

48 hrs.

MINE PLANNING AND DESIGN

SECTION(c/o BS PALMA)

8 hrs.x 2 days

=16hrs.

April16-17,

2012

MINE SURVEYING SECTION(c/o R.S

FIDELLO)

8 hrs. x 2

days=16 hrs.

April 18-19,

2012

April 20-21,

2012

April 22-23,

2012

DRAW CONTROL SECTION (c/o BL

Tamargo)

8 hrs. x 2

days=16 hrs.

Rock Mechanics Section (c/o J.E AGUSTIN) 8 hrs.x 2 days=

16 hrs.

Subtotal 8 days x 8 hrs. =

64 hrs.

Mine Development (c/o Shift Managers and

Development Supervisors)

Horizontal Driving and Rock Bolting 3 days April 24 – 26,

2012

Rock Support Installation 3 days April 27 – 29,

2012

Fanhole Drilling 3 days April 30-

May02, 2012

Vertical Driving 4 days May 03 – May

06, 2012

129

Page 130: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Subtotal 13 days x 8 hrs.

= 106 hrs.

Mine Production (c/o Shift Managers and

Production Supervisors)

Ore Extraction/Scooping/LHD Operation 3 days May 07 – 09,

2012

Ore Rehandling 3 days May 10 – 12,

2012

CHC and FBC Operation 4 days May 13 – 16,

2012

Rock breaking 3 days May 17 – 19,

2012

Subtotal 13 days x 8 hrs.

= 106 hrs.

ASSAY Lab (c/o E.A Aquino) 2 days x 8 hrs. =

16 hrs.

May 20 – 21,

2012

Mill Plant 1 day May 22, 2012

Terminal Report Writing 1 day May 23, 2012

Evaluation 1 day May 24, 2012

Panel Interview 1 day May 25, 2012

Subtotal 6 days x 8 hrs. =

48 hrs.

Total 360 hrs.

130

Page 131: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Remarks and Recommendations

Learning Comments

Recommendations

131

Page 132: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

Based on the training which the trainee had experienced, he frankly recommends to

the company:

To give trainees the ensued assignments before they start their duties. Based on the

trainees’ observation, some managers, supervisors, and foremen seemed unprepared

on what to do. The students then tend to get bored and wait without any accomplished

work until the training is over.

To provide trainees the complete Personal Protective Equipments (PPE’s) for their

safety as they expose on the actual operation in underground working milieu.

To assign a well-informed personnel who will serve as a guide to student-trainees. The

working men should also be aware on what to teach to them. They should complement

from one another.

To effect the correct Standard Operating Procedures (SOP’s) in every activity within

the working area. Some of the “mineros” tend to disobey it as what the trainee

observed.

To be strict in the attendance of the trainees. It should be checked always to detect the

absentees.

ELCASMER G. ACEDO

Author

Appendix

PICTORAILS:

132

Page 133: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

133

Page 134: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

134

Page 135: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

135

Page 136: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

136

Page 137: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

137

Page 138: Raaaa a a Aaaaaaaaaaaaaaaaaaaaaaaaaa

138