Upload
moeshfieq-williams
View
212
Download
0
Embed Size (px)
Citation preview
5 Written Questions5 Written Questions5 Written Questions5 Written Questions
1. Involves comparing actual or planned project practices to those of comparable projects
best practices, generate ideas for improvement, and provide a basis for measuring performance.
These other projects can be within the performing organization or outside of it and can be within
the same or in another application area
INCORRECT:INCORRECT:INCORRECT:INCORRECT: You gave no answer
ANSWER:ANSWER:ANSWER:ANSWER: Benchmarking
2. the values of repeated measurements are clustered and have little scatter
INCORRECT:INCORRECT:INCORRECT:INCORRECT: You gave no answer
ANSWER:ANSWER:ANSWER:ANSWER: Precision
3. which include two, three, or four groups of information and show relationships between factors,
causes, and objectives. Data in a matrix is organized in rows and columns with intersecting cells
that can be filled with information that describes the demonstrated relationship between the items
located in the row and column
INCORRECT:INCORRECT:INCORRECT:INCORRECT: You gave no answer
ANSWER:ANSWER:ANSWER:ANSWER: Matrix Diagrams
4. Costs of poor quality
INCORRECT:INCORRECT:INCORRECT:INCORRECT: You gave no answer
ANSWER:ANSWER:ANSWER:ANSWER: Failure Costs
5. • Organizational quality policies, procedures and guidelines
• Historical databases
• Lessons learned from previous projects
• Quality policy, as endorsed by senior management, which sets the intended direction of a
performing organization with regard to quality.
INCORRECT:INCORRECT:INCORRECT:INCORRECT: You gave no answer
ANSWER:ANSWER:ANSWER:ANSWER: Plan Quality: Organizational Process Assets
PMP 8: Project Quality Manageme...NAME: ________________________
Page 1 of 4Test: PMP 8: Project Quality Management | Quizlet
2014/05/19http://quizlet.com/22353760/test?written=on&matching=on&mult_choice=on&tf=on...
a
d
b
c
e
1. Quality vs GradeQuality vs GradeQuality vs GradeQuality vs Grade
INCORRECT:INCORRECT:INCORRECT:INCORRECT: No answer given
ANSWER:ANSWER:ANSWER:ANSWER: • While a quality level that
fails to meet quality requirements is
always a problem, low grade may not
be.
• The project manager and the project
management team are responsible for
managing the tradeoffs involved to
deliver the required levels of both
quality and grade
2. InspectionInspectionInspectionInspection
INCORRECT:INCORRECT:INCORRECT:INCORRECT: No answer given
ANSWER:ANSWER:ANSWER:ANSWER: Is the examination of a
work product to determine whether
it conforms to documented standards.
3. Standard Standard Standard Standard deviationdeviationdeviationdeviation
INCORRECT:INCORRECT:INCORRECT:INCORRECT: No answer given
ANSWER:ANSWER:ANSWER:ANSWER: Is a distance of
measurement from the mean or,
the square root of the average of the
squares of deviations (about) the mean
of a set of data. Standard deviation is a
statistical measure of spread or
variability
4. Failure Costs Failure Costs Failure Costs Failure Costs includeincludeincludeinclude
INCORRECT:INCORRECT:INCORRECT:INCORRECT: No answer given
ANSWER:ANSWER:ANSWER:ANSWER: • costs to rework
products, components, or
processes that are non-compliant;
• costs of warranty work and waste; and
• costs due to loss of reputation
5. Control Control Control Control LimitsLimitsLimitsLimits
INCORRECT:INCORRECT:INCORRECT:INCORRECT: No answer given
ANSWER:ANSWER:ANSWER:ANSWER: thresholds, which can
indicate whether the process is out
of control
5 Matching Questions5 Matching Questions5 Matching Questions5 Matching Questions
a • While a quality level that fails to meet
quality requirements is always a problem,
low grade may not be.
• The project manager and the project
management team are responsible for
managing the tradeoffs involved to deliver
the required levels of both quality and
grade
b Is a distance of measurement from the
mean or, the square root of the average of
the squares of deviations (about) the mean
of a set of data. Standard deviation is a
statistical measure of spread or variability
c • costs to rework products, components,
or processes that are non-compliant;
• costs of warranty work and waste; and
• costs due to loss of reputation
d Is the examination of a work product to
determine whether it conforms to
documented standards.
e thresholds, which can indicate whether the
process is out of control
Page 2 of 4Test: PMP 8: Project Quality Management | Quizlet
2014/05/19http://quizlet.com/22353760/test?written=on&matching=on&mult_choice=on&tf=on...
5 5 5 5 Multiple Choice QuestionsMultiple Choice QuestionsMultiple Choice QuestionsMultiple Choice Questions
1. • It implements the quality management system through policy and procedures with continuous
process improvement activities conducted throughout, as appropriate.
• Addresses the management of the project and the product of the project.
• It applies to all projects, regardless of the nature of their product.
(No Answer)
a. Characteristics of Flowcharting
b. Characteristics of a Run Chart
c. Characteristics of the Quality Management Plan
d. CORRECT:CORRECT:CORRECT:CORRECT: Characteristics of Project Quality Management
2. • Is a line graph that shows data points plotted in the order in which they occur.
• Show trends in a process over time, variation over time, or declines or improvements in a
process over time.
• Trend analysis is performed using run charts and involves mathematical techniques to forecast
future outcomes based on historical results
(No Answer)
a. Characteristics of Inspection
b. CORRECT:CORRECT:CORRECT:CORRECT: Characteristics of a Run Chart
c. Characteristics of Histograms
d. Control Charts
3. accurate data
(No Answer)
a. CORRECT:CORRECT:CORRECT:CORRECT: Survey of the entire population yields
b. Approved Change Requests Reviews
c. Prevention Costs
d. Prioritization Matrices
4. Used to produce project activity metrics to evaluate actual progress as compared to planned
progress. These metrics include:
• Planned s. Actual technical performance
• Planned s. Actual schedule performance
• Planned s. Actual cost performance
(No Answer)
a. Control Charts Use in Perform Quality Control
b. Project Management Plan Use in Perform Quality Control
c. CORRECT:CORRECT:CORRECT:CORRECT: Work Performance Measurements Use in Perform Quality Control
d. Flowcharting Use in Perform Quality Control
Page 3 of 4Test: PMP 8: Project Quality Management | Quizlet
2014/05/19http://quizlet.com/22353760/test?written=on&matching=on&mult_choice=on&tf=on...
5. • Rank ordering is used to focus corrective action.
• The project team should address the causes creating the greatest number of defects first.
• Pareto diagrams are conceptually related to Pareto's Law
• Pareto diagrams can also be used to summarize various types of data for 80/20 analyses.
(No Answer)
a. CORRECT:CORRECT:CORRECT:CORRECT: Characteristics of Pareto Charts
b. Prioritization Matrices
c. Characteristics of Project Quality Management
d. Process Metrics
5 5 5 5 True/False QuestionsTrue/False QuestionsTrue/False QuestionsTrue/False Questions
1. Tolerance → that the measured value is very close to the true value
This is false. You gave no answer.
It should be ToleranceToleranceToleranceTolerance → defines the allowable variations on the metrics. For example, a metric
related to the quality objective of staying within the approved budget by ± 10% could be to
measure the cost of every deliverable and determine the percent variance from the approved
budget for that deliverable.
2. Attribute Sampling → the result either conforms or does not conform
This is true. You gave no answer.
3. Approved Change Requests → All approved change requests should be reviewed to verify that
they were implemented as approved
This is false. You gave no answer.
It should be Approved Change Approved Change Approved Change Approved Change RequestsRequestsRequestsRequests → Include modifications such as defect repairs, revised
work methods and revised schedule..
4. Technical Performance: Trend Analysis → which are diagrams of the forces for and against
change
This is false. You gave no answer.
It should be Technical Performance: Trend AnalysisTechnical Performance: Trend AnalysisTechnical Performance: Trend AnalysisTechnical Performance: Trend Analysis → How many errors or defects have been
identified, and how many remain uncorrected.
5. Stakeholder Register Use in Plan Quality → Identifies stakeholders with a particular interest in , or
impact on, quality
This is true. You gave no answer.
Page 4 of 4Test: PMP 8: Project Quality Management | Quizlet
2014/05/19http://quizlet.com/22353760/test?written=on&matching=on&mult_choice=on&tf=on...