Questionaires to MEA

  • Upload
    mrhom

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

  • 7/30/2019 Questionaires to MEA

    1/8

    Questionnaires to MEA

    1.1Distribution supply areaAREA 3,194.81 km

    2

    LOAD DEMAND 8,382.83 MW

    LOAD DENSITY 2.40 MW/km2

    Number of customer 3,158,131 Customers

    1.2Distribution facilities ( for example transformer, optical fiber, system and so on )TRANSFORMERS

    - TERMINAL STATION 230/69-115 kV ( 17 STATIONS) 18,205.88 MVA

    - SUBSTATION 69-115/12-24 kV ( 149 STATIONS ) 18,405.00 MVA

    - DISTRIBUTION 12-24 kV/230-380 V 14,148.68 MVA

    TRANSMISSION LINES

    - 230 kV ( 6 LINES ) 49.54 cct-km

    - 115 kV ( 38 LINES ) 722.75 cct-km

    - 69 kV ( 77 LINES ) 897.88 cct-km

    DISTRIBUTION LINES

    - 24 kV ( 1,156 LINES ) 12,829.52 cct-km

    - 12 kV ( 464 LINES ) 4,279.18 cct-km

    - Low voltage 27,211.83 cct-km

    OPTICAL FIBER

    - ADSS Structure Cable 10,000.00 cct-km

    Update : 08/2012

  • 7/30/2019 Questionaires to MEA

    2/8

    1.5 Quality of Power Supply (Restriction for Frequency fluctuation of power supply and voltage drop)

    MEA Quality of Electricity Supply for 69, 115 and 230 kV System

    Item Value Note

    Frequency 50 0.5 Hz (normal operation) Data from EGAT

    Voltage supply

    230 kV218.0 - 237.0 kV (normal)

    218.0 - 242.0 kV (emergency)

    115 kV106.4 - 117.6 kV (normal)

    96.0 - 123.0 kV (emergency)

    69 kV63.6 - 70.4 kV (normal)

    57.3 - 72.5 kV (emergency)

    Harmonic

    voltageTHDv less than 3.0 %

    Refer to planning level in Engineering

    Recommendation G5/4 table 4 and 5

    which also include individual harmonic

    Voltage

    flicker

    Pst less than 0.8 Refer to planning level in IEC 61000-3-

    7Plt less than 0.6

    Voltage

    unbalanceLess than 1.4 %

    Refer to planning level in IEC 61000-3-

    13

    Temp. powerfrequency

    overvoltage

    Less than 173.2 % of nominal voltage Refer to EN 50160

    Note: The specified value of harmonics, flicker and unbalance are planning level. MEA try to control

    these disturbances in power system which generated from the operation of customer load to be within

    the planning level. But due to the diversification of customer load and some uncontrolled circumstance,

    the levels of these disturbances maybe exceed the specified value above in some duration or some area.

    So customers should design their equipment to operate in environment that disturbances can be up to

    compatibility level which generally higher than planning level. Compatibility levels for harmonics, flicker

    and unbalance are shown in above reference standards.

  • 7/30/2019 Questionaires to MEA

    3/8

    MEA Connection Regulation for 69, 115 and 230 kV System

    Item Condition or Limit Note

    Load size

    230 kV not available

    Depend on specific area115 kV larger than 15 MVA

    69 kV larger than 15 MVA

    Maximum step

    voltage change

    Max. step voltage change at PCC due to

    customer load variation must less than 3.0 %

    of nominal voltage

    Power factor Between 0.9 - 1.0 lagging

    Harmonic

    current

    Limit individual harmonic current up to order

    50th

    . The limits depend on load size, systemcapacity and fault level at PCC.

    Refer to planning level from

    Engineering Recommendation G5/4

    and assessment method from IEC

    61000-3-6

    Voltage

    flicker

    Limit Pst and Plt created by customer at PCC.

    The limits depend on load size and system

    capacity.

    Refer to assessment method from IEC

    61000-3-7

    Unbalanced

    current

    Limit negative sequence current. The limit

    depends on load size, system capacity and

    fault level at PCC.

    Refer to assessment method from IEC

    61000-3-13

    Note: For traction load, the design criteria of the traction system shall be concern about EMC and safety

    related to public vicinity by referring to the international standard.

  • 7/30/2019 Questionaires to MEA

    4/8

    MEA Quality of Electricity Supply for 12 and 24 kV System

    Item Value Note

    Frequency 50 0.5 Hz (normal operation) Data from EGAT

    Voltage supply

    12 kV10.9 - 11.8 kV (normal)

    10.8 - 12.0 kV (emergency)

    24 kV21.8 - 23.6 kV (normal)

    21.6 - 24.0 kV (emergency)

    Harmonic

    voltageTHDv less than 4.0 %

    Refer to planning level in Engineering

    Recommendation G5/4 table 3 which

    also include individual harmonic

    Voltage flicker Pst less than 0.9 Refer to planning level in IEC 61000-3-

    7Plt less than 0.7

    Voltage

    unbalanceLess than 1.8 %

    Refer to planning level in IEC 61000-3-

    13

    Temp. power

    frequency

    overvoltage

    Less than 173.2 % of nominal voltage Refer to EN 50160

    Note: The specified value of harmonics, flicker and unbalance are planning level. MEA try to controlthese disturbances in power system which generated from the operation of customer load to be within

    the planning level. But due to the diversification of customer load and some uncontrolled circumstance,

    the levels of these disturbances maybe exceed the specified value above in some duration or some area.

    So customers should design their equipment to operate in environment that disturbances can be up to

    compatibility level which generally higher than planning level. Compatibility levels for harmonics, flicker

    and unbalance are shown in above reference standards.

  • 7/30/2019 Questionaires to MEA

    5/8

    MEA Connection Regulation for 12 and 24 kV System

    Item Condition or Limit Note

    Load sizeLarger than 300 kVA

    but smaller than 15 MVADepend on specific area

    Power factor Between 0.9 - 1.0 lagging

    Maximum step

    voltage change

    Max. step voltage change at PCC due to

    customer load variation must less than 3.0 %

    of nominal voltage

    Harmonic

    current

    Limit individual harmonic current up to order

    50th. The limits depend on load size, system

    capacity and fault level at PCC.

    Refer to planning level from

    Engineering Recommendation G5/4

    and assessment method from IEC

    61000-3-6

    Voltage flicker

    Limit Pst and Plt created by customer at PCC.

    The limits depend on load size and system

    capacity.

    Refer to assessment method from IEC

    61000-3-7

    Unbalanced

    current

    Limit negative sequence current. The limit

    depends on load size, system capacity and

    fault level at PCC.

    Refer to assessment method from IEC

    61000-3-13

    Note: For traction load, the design criteria of the traction system shall be concern about EMC and safety

    related to public vicinity by referring to the international standard.

  • 7/30/2019 Questionaires to MEA

    6/8

    2.3 Current situation for Adder

    FuelAdder

    (Bath/kWh)

    Years

    effective

    (Years)

    1. Biomass

    - Installation Capacity 1 MW 0.50 7

    - Installation Capacity 1 > MW 0.30 7

    2. Biogas

    - Installation Capacity 1 MW 0.50 7

    - Installation Capacity 1 > MW 0.30 7

    3. Waste (Waste from communityor Waste from industry which is not both

    dangeroussubstances and organic matters.)

    - Fermentation or Landfill system 2.50 7

    - Heat Energy 3.50 7

    4. Wind Energy

    - Installation Capacity 50 kW 4.50 10

    - Installation Capacity 50 > kW 3.50 10

    5. Very Small Hydropower

    - 50 kW Installation Capacity 200kW 0.80 7

    - Installation Capacity < 50kW 1.50 7

    6. Solar Energy 8.00 or6.50 10

  • 7/30/2019 Questionaires to MEA

    7/8

    4.1 Overview of the Very Small Power Producer

    VSPP or Very Small Power Producer is a power generator of a private sector , state agency , state

    owned enterprise or individual who generate and sell electrical power less than 10 MW to MEA or PEA.

    Fuels which are used in a power generation process are solar energy , biogas and biomass energy ,

    hydropower , natural gas and etc. The objectives for purchasing electrical power from VSPP are to support

    an efficient use of resources and reduce pollution effect to the environment.

    4.2 The number of VSPP

    VSPP in MEA Area Fuel

    Number Power(kW)

    (project)Installation

    Offer for

    sale

    (1) Projects that have been turned on the power

    to MEA system. 43 11,677.58 8,419.58

    Solar Energy 39 237.58 219.58

    Waste 1 1,040.00 1,000.00

    Very Small

    Hydropower 2 800.00 800.00

    Natural gas 1 9,600.00 6,400.00

    (2)Projects that have already been signed but are

    been setting the date of COD. 3 1,644.00 832.00

    Solar Energy 2 44.00 32.00

    Waste 1 1,600.00 800.00

    (3) Projects that have already been admitted but

    have not been signed yet. 2 10,200.00 10,200.00

    Solar Energy 1 3,000.00 3,000.00

    Natural gas 1 7,200.00 7,200.00

    (4) Projects that are been considering. 2 7,000.00 4,200.00

    Solar Energy 1 3,000.00 3,000.00

    Natural gas 1 4,000.00 1,200.00

    TOTAL 50 30,521.58 23,651.58

    Update : 29/11/2012

  • 7/30/2019 Questionaires to MEA

    8/8

    4.3 Condition or regulations to be authorized as VSPP

    - Power Generation Using Renewable Energy ( attached 1 )

    - Power Generation Using Cogeneration Energy ( attached 2 )

    4.4 The procedure to be authorized as VSPP

    According to regulations 2006 for the purchase of electrical power from VSPPs who sell electrical

    power into MEA distribution grid less than 10 MW, there are 4 main issues required to consider ;

    1. Procedures and criteria for consideration of power purchase from VSPPs.

    2. Conditions for purchasing electrical power from VSPPs.

    3. Power purchasing point and connection point.

    4. Costs incurred for VSPPs.

    4.5 Example of VSPP business

    No. Company /

    Person

    Type of

    fuel

    Linking

    voltage

    Installation

    capacity

    ( kW )

    Offer

    for sale

    ( kW )

    Started

    date

    Adder

    Rate

    (Bath/kWh)

    Duration

    1Charoensompong

    Ltd.Waste 24 kV 1,040.00 1,000.00 08/2007 2.50 08/07 07/14

    2PTT Public

    Co.,Ltd.

    Solar

    Energy400/230 V 43.73 43.73 10/2007 8.00 10/07 09/17

    3Lard prao Water

    Work

    Very Small

    Hydropower69 kV 480.00 480.00 12/2008 Not apply -

    4

    Combined Heat

    & Power

    Producing Ltd.

    Natural gas 24 kV 9,600.00 6,400.00 11/2010 - -

    5 Mr. Pirom JamsaiSolar

    Energy400/230 V 2.50 2.50 08/2012 6.50 08/12 07/22