  • 1. It is important to identify and document the specific activities that must be

    performed to produce the deliverables and sub-deliverables identified in the Work

    Breakdown Structure. This is done as part of:

    A. Define Activities

    B. Decomposition

    C. Define Scope

    D. Sequence Activities

    2. Plan Procurements is the process of identifying which project needs can be best

    met by procuring products or services outside the project organization. All the

    following are tools and techniques for Plan Procurements EXCEPT:

    A. Make-or-buy analysis

    B. Expert Judgment

    C. Standard forms

    D. Contract type selection

    3. As a PMP Certified project manager, you are responsible to comply with all

    organizational rules and policies. In this context, you have the responsibility to do

    all the following EXCEPT:

    A. Provide accurate and truthful representations concerning all information

    directly or indirectly related to all aspects of the PMI Certification Program

    B. Report possible violations of the PMP Code of Professional Conduct by

    individuals in the field of project management.

    C. Cooperate with PMI concerning ethics violations and the collection of

    related information

    D. Disclose to PMI about significant circumstances that could be construed as

    a conflict of interest or an appearance of impropriety

  • 4. Perform Quality Assurance involves evaluating project performance on a regular

    basis to provide confidence that the project will satisfy the relevant quality

    standards. Which of the following is an output from Perform Quality Assurance

    Process?

    A. Plan Quality

    B. Operational Definitions

    C. Change Requests

    D. Quality Metrics

    5. Plan Communications is used for determining the information and

    communications needs of the stakeholders: who needs what information, when

    they will need it, and how it will be given. Which of the following is an output from

    Plan Communications?

    A. Communication Management Plan

    B. Project Records

    C. Project Reports

    D. Report Performance

    6. Conduct Procurements comprises of obtaining responses to bids and proposals

    from potential vendors, selecting a vendor and awarding contract. All the following

    is not an output from Conduct Procurements EXCEPT:

    A. Selected Sellers

    B. Make or Buy Decisions

    C. Change Requests

    D. Resource Calendars

  • 7. One of your team-member was late to a critical bidder conference, which caused

    a lot of confusion. In this context,

    A. You should talk with the team member to understand why he was late and

    how to prevent similar situations in the future

    B. You should raise this issue to your manager, and ask for ways to mitigate

    similar problems in the future

    C. You should raise this issue to the team-member`s manager and ensure that

    the team-member makes himself available for future meetings

    D. You should raise a risk-memo highlighting the problems caused because of

    non-availability of the team member

    8. All the following are tools and techniques for Plan Quality EXCEPT:

    A. Flow charting

    B. Benefit/Cost Analysis

    C. Design of Experiments

    D. Quality Audits

    9. Close Project or Phase is used for generating, gathering, and disseminating

    information to formalize a phase or project completion. All the following are

    outputs for Close Project or Phase EXCEPT:

    A. Final product

    B. Change Requests

    C. Organizational process assets updates

    D. Final Service

  • 10. Conduct Procurements involves the receipt of bids or proposals and the

    application of the evaluation criteria to select a provider. Which of the following is

    an input for Conduct Procurements :

    A. Qualified Seller List

    B. Claims Administration

    C. Bidder Conferences

    D. Audits

    11. As a PMP Certified project manager, you are responsible for all the following

    EXCEPT:

    A. Confidentiality of sensitive information which you have access to

    B. Managing conflict of interest situations in your project

    C. Integrity of your team-members

    D. Refraining from offering and accepting inappropriate payments, gifts and

    other forms of communication

    12. Perform Quality Control involves monitoring specific project results to

    determine if they comply with relevant quality standards, and identifying ways to

    eliminate causes of unsatisfactory results. It should be performed throughout the

    project. All the following can be inputs to Perform Quality Control EXCEPT

    A. Metrics

    B. Checklists

    C. Results of quality control measurements

    D. Deliverables

  • 13. Which of the following is an output from Report Performance process?

    A. Performance Reports

    B. Project Records

    C. Communications Management Plan

    D. Lessons Learned

    14. The process of ensuring that the seller`s performance meets contractual

    requirements is done as part of :

    A. Close Procurements

    B. Source Selection

    C. Plan Procurement

    D. Administer Procurements

    15. You are the project manager of a manufacturing firm that produces machine

    parts required in automobiles. While doing a review, you discover some design

    requirements that had earlier been missed. What should you do?

    A. Communicate to your team that they should incorporate the requirement,

    and do an analysis to figure out the potential impact

    B. Inform your project sponsor that the project may be delayed because of the

    missed requirement

    C. Go forward with production because incorporating the requirement may

    delay the schedule

    D. Communicate this issue to your senior management

  • 16. Planned and Systematic activities performed throughout the project, and

    implemented within the quality system to provide confidence that the project will

    satisfy the relevant quality standards is also referred to as:

    A. Perform Quality Control

    B. Perform Quality Assurances

    C. Plan Quality

    D. Project Quality Management

    17. As part of Project Communications Management, you are collecting and

    disseminating information to provide stakeholders with information about how

    resources are being used to achieve project objectives. This is done as part of:

    A. Plan Communications

    B. Distribute Information

    C. Report Performance

    D. Administer Procurements

    18. Plan Risk Management is the process of deciding how to approach and plan the

    risk management activities for a project. It is important to plan for the risk

    management processes that follow to ensure that the level, type, and visibility of

    risk management are commensurate with both the risk and importance of the

    project to the organization. The output of Plan Risk Management is:

    A. Identify Risks

    B. Risk Management Plan

    C. Project Risk Management

    D. Plan Meetings and risk analysis

  • 19. Project procurement management includes the processes required to acquire

    goods and services, to attain project scope, from outside the performing

    organization. Which of the following statements related to buyer-seller

    relationships in Project Procurement Management is not correct?

    A. Seller manages the work as a project; buyer becomes the customer and is

    thus a key stakeholder for the seller.

    B. Seller`s project management team must be concerned with all the

    processes of project management

    C. Terms and conditions of the contract become a key input to many of the

    seller`s processes.

    D. All the statements above are correct

    20. One of the techniques used to both integrate the various process groups and

    measure the performance of the project as it moves from initiation through to

    completion is Earned Value Management (EVM). It is used in all the following

    processes EXCEPT:

    A. Coordinating changes across the entire project

    B. Formalizing acceptance to project scope

    C. Controlling changes to project schedule

    D. Controlling changes to project budget

  • 21. You are the project manager for a manufacturing company involved with making

    components for Internal Combustion Engines required for the automobile industry.

    In the past couple of days, there have been too many defects, and you would like to

    find out whether unusual events are occurring in your manufacturing process whose

    causes must be identified and corrected? For this purpose, you should use:

    A. Inspection

    B. Pareto Charts

    C. Control Charts

    D. Statistical Sampling

    22. Comparing actual project results to planned or expected results is a part of:

    A. Performance review

    B. Variance Analysis

    C. Trend Analysis

    D. Earned Value Analysis

    23. Identify Risks helps in determining which risks might affect the project and

    documenting their characteristics. All the following are tools and techniques for

    Identify Risks EXCEPT:

    A. Documentation Reviews

    B. Checklists Analysis

    C. Risk Probability and Impact

    D. Assumptions Analysis

  • 24. You are in the process of determining what types of contracts will be used,

    whether standardized procurement documents will be needed and how multiple

    providers will be managed. You should record this information in the:

    A. Develop Project Management Plan

    B. Administer Procurements

    C. Procurement Management Plan

    D. Procurement Documents

    25. In a project management context, all the following are Constructive Roles

    EXCEPT:

    A. Information Seeker

    B. Recognition Seeker

    C. Consensus Taker

    D. Information Giver

    26. All the following are inputs to Direct and Manage Project Execution Except:

    A. Project Management Plan

    B. Report Performance

    C. Enterprise Environmental Factors

    D. Organization Process Assets

  • 27. All the following statements related to Perform Quality Control are correct

    EXCEPT:

    A. Preventions refers to keeping errors out of the process; Inspection refers to

    keeping errors out of hands of the customer

    B.

    Attribute Sampling determines if the result confirms or not; in variable

    sampling the result is rated on a continuous scale that measures degree of

    conformity

    C. Random causes are unusual events; special causes are normal process

    variations

    D.

    Using tolerance, the result is acceptable if it lies within range specified by

    tolerance; using control limits, the process is in control if the result falls

    within control limits

    28. You are the project manager of an IT company. You are in the process of

    creating a collection and filing structure that details what methods will be used to

    gather and store various types of information. Procedures should also cover

    collecting and disseminating updates and corrections to previously distributed

    material. Where will you include this information?

    A. Information Retrieval System

    B. Information Distribution tools

    C. Communication Management Plan

    D. Project Records

  • 29. Plan Risk Responses helps in developing procedures and techniques to enhance

    opportunities and reduce threats to the project`s objectives. All the following tools

    help in Plan Risk Responses EXCEPT:

    A. Strategies for negative risks

    B. Work breakdown structure(WBS)

    C. Expert Judgement

    D. Strategies for positive risks

    30. Which of the following statements related to managing different types of

    Procurement contracts is not accurate?

    A. In Fixed Price Incentive Fee, there is no incentive for the seller to decrease

    costs.

    B. In Fixed Price or Lumpsum contract, there is highest risk to seller and lowest

    risk to buyer

    C. In fixed price with redetermination, retroactive contracts allow for adjusting

    of contract price after performance has been completed.

    D. Fixed price with economic price adjustment allows for price increases if the

    contract is for multiple years

    31. In a project management context, which of the following is a Destructive Roles :

    A. Withdrawer

    B. Information Seeker

    C. Gate Keeper

    D. Initiator

  • 32. Which process is not an output from Monitor and Control Project Work?

    A. Change Requests

    B. Project Management Plan Updates

    C. Project Documents Update

    D. Project Plan

    33. Quality improvement involves taking action to increase the effectiveness and

    efficiency of the project to provide added benefits to stakeholders. In most cases,

    implementing quality improvements will require preparation of change requests or

    taking of corrective action, and will be handled according to procedures for :

    A. Quality Management Plan

    B. Integrated Change Control

    C. Quality Control Measurements

    D. Plan Quality and Perform Quality

    34. Organizational planning deals with identifying, documenting, and assigning

    project roles, responsibilities and reporting relationships. All the following are tools

    and techniques for Organizational Planning EXCEPT:

    A. Templates

    B. Organization Theory

    C. Reward and Recognition Systems

    D. Stakeholder Analysis

  • 35. As part of Distribute Information, you are involved with creation of an

    information retrieval systems which helps in sharing information by team members

    and stakeholders. What will you be doing next?

    A. Create a communications management plan

    B. Do stakeholder analysis to develop a methodical and logical view of

    information needs

    C. Determine methods for accessing information between scheduled

    communications

    D. Conduct performance reviews to assess project status and/or progress

    36. The process of keeping track of identified risks, ensuring the execution of risk

    plans, and evaluating their effectiveness in reducing risk is done as part of which

    process?

    A. Monitor and Control Risks

    B. Risk Management Plan

    C. Plan Risk Responses

    D. Perform Quantitative Risk Analysis

  • 37. You are a project manager in an Information Technology (software) company,

    but you recently got an offer as a project manager in a construction company with

    25% salary hike. You have excellent technical knowledge in software field, but do

    not have much exposure to the Construction Industry. In this context,

    A. You should attend training classes related to construction industry to get

    more technical expertise in the field

    B. You should not take up the assignment because you will lose out on the

    experience and skills gained in Information Technology field

    C.

    You should take up the assignment because similar project management

    skills will be required in the Construction company, as was required in the

    software company

    D.

    You should try to get more information about project management in the

    Construction Industry and then make an informed decision about whether

    to take up the new opportunity

    38. All the following statements related to Fixed Price, Cost Reimbursable and Time

    and Material contract are correct EXCEPT:

    A. In a Fixed Price contract, the product is well defined

    B. In a Cost reimbursable contract, the risk of seller is low

    C. In a time and material contract, the risk of buyer is low

    D.

    In a time and material contract, the type of payment is unit rates for work

    done. The unit rate for work done is fixed but the total cost increases with

    time

  • 39. A conflict resolution technique that emphasizes areas of agreement is also

    called:

    A. Confrontation

    B. Problem Solving

    C. Compromising

    D. Smoothing

    40. Which of the following are Tools and Techniques to Perform Integrated Change

    Control :

    A. Work Authorization System

    B. Accepted Deliverables

    C. Project Management Information System

    D. Expert Judgements

    41. You recently joined as a project manager for an existing project which is being

    implemented (the previous project manager had to take 2 months personal time-

    off). You are happy that the project is under budget and ahead of schedule. You also

    notice that some features have been included which are not explicitly mentioned in

    the project scope. While discussing with team-members, you were informed that

    they thought the added features would be appreciated by the customer and were

    hence included as part of the project. In this situation, you are:

    A. concerned because the project team is gold-plating

    B. happy because the project will "Exceed Customer Expectations"

    C. going to increase the sizing for the project, because it is delivering more

    than what the customer had asked for

    D. increase the quality metrics for the project, since you are delivering better

    quality

  • 42. Which of the following is an output from Staff Acquisition process?

    A. Project Staff Assigned

    B. Performance Measurement

    C. Staffing Management plan

    D. Role and Responsibility Assignments

    43. You are the project manager for a project where there are 7 team-

    members. One more team member will be joining after 1 week. What is

    the number of communication channels once the new person joins your

    team?

    A. 28

    B. 21

    C. 18

    D. 36

    44. As a project manager, you understand that risk ratings and prioritization may

    change during the life of the project. So, you make project risk an agenda at all team

    meetings and schedule regular:

    A. Project risk response audits

    B. Project risk reviews

    C. Earned value analysis

    D. Additional risk response planning

  • 45. All the following statements related to Progressive Elaboration of projects are

    true except:

    A.

    Scope of the project can change when product characteristics are

    progressively elaborated, and project manager must plan for such scope

    changes.

    B. Because the product of each project is unique, characteristics that

    distinguish the product or service must be progressively elaborated.

    C. Requirements are made more explicit as the project team develops a better

    and more complete understanding of the project

    D. Progressive Elaboration is a characteristic of projects that integrates the

    concept of temporary and unique.

    46. In your company, you are in the process of deciding whether to buy a product or

    make it in-house. All the following statements related to make-or-buy analysis are

    correct EXCEPT:

    A.

    Make-or-buy analysis is part of initial scope planning process that can be

    used to determine whether a particular product can be produced cost

    effectively by the performing organization.

    B. Make-or-buy analysis must take in account the perspective of the

    performing organization, as well as immediate needs of the project.

    C.

    If the performing organization has an ongoing need for the item, the

    portion of the purchase cost allocated to the project may be less than the

    cost of the rental.

    D.

    Buy side of make-or-buy analysis should include both the actual out-of-

    pocket cost to purchase the product as well as the indirect costs of

    managing the purchasing process

  • 47. In your organization, you are the project manager of the engineering

    department. But if questions related to manufacturing arise, they are passed up to

    the engineering department head, who consults with the head of the manufacturing

    department. Once the manufacturing head gets the answers, he passes it the

    engineering department head, who in turn passes answer back down to you. The

    organization structure you are working on is

    A. Weak Matrix

    B. Matrix

    C. Strong Matrix

    D. Functional

    48. A customer informed you that it is preferable to make a change to a certain

    aspect of the project. What should you do first?

    A. Talk with team members to understand implication of the change

    B. Communicate the change to Management to get their inputs

    C. Open up a Change Control

    D. Do sizing for the change and communicate to customer

    49. According to Maslow`s hierarchy of needs, Economic security is a:

    A. Physiological Need

    B. Safety Need

    C. Social Need

    D. Esteem Need

  • 50. As a project manager, you realize the importance of developing project team for

    Project human resource management. Develop Project Team helps in developing

    individual and group competencies to enhance project performance. All the

    following are inputs to Develop Project Team EXCEPT:

    A. Project plan

    B. Project staff Assignments

    C. Project interfaces

    D. Resource Calendars

    51. Email and notes are examples are which type of communication?

    A. Written Formal

    B. Written Informal

    C. Oral Formal

    D. Oral Informal

    52. In your project, you did extensive risk planning to ensure that all issues were

    taken care of. But, some technical problems related to networking problems have

    recently emerged as potential risks which could delay your project substantially.

    You had not anticipated this in your risk response plan. What should you do?

    A. Do additional risk response planning

    B. Conduct a project risk response audit

    C. Do a technical performance measurement to determine how to solve the

    technical problem

    D. Issue a change request

    53. Selection of an organization to prosecute a project depends upon three key

    items - degree of advanced technology in the project, percentage of project

    personnel in the professional category, and the ________ for the project."

    A. Size of the budget

    B. Level of uncertainty

    C. Location of implementation

    D. Type of scheduling system

  • 54. All the following are examples of projects EXCEPT:

    A. Developing a new product or service

    B. Running a campaign for political office

    C. Changing the password of one user used for logging into a bank

    web-site

    D. Running a marketing campaign for product launch

    55. You are in the process of preparing a document with "sufficient detail" which

    allows prospective sellers to determine if they are capable of providing an item. This

    is an example of a(an) :

    A. Plan Procurements

    B. Statement of Work

    C. Evaluation Criteria

    D. Proposals

    56. Managing conflicts is essential for successful implementation of the project. The

    conflict resolution techniques most used in projects are:

    A. Withdrawal, Forcing, Compromising

    B. Withdrawal, Authoritative, Forcing

    C. Confrontation, Directing, Smoothing

    D. Withdrawal, Confronting, Legitimate

  • 57. You are the project manager for a project which is being done under contract.

    You are informed by the buyer that government regulations will necessitate some

    changes in the project. What should you do first?

    A. Talk with team members to understand implication of the change

    B. Communicate the change to Management to get their inputs

    C. Open up a Change Control

    D. Do sizing for the change and communicate to customer

    58. Immediate corrective or preventive action as a result of quality control

    measurements is also referred to as:

    A. Process Adjustments

    B. Rework

    C. Rebaselining

    D. Quality Improvement

    59. Amongst the conflict resolution modes (Confrontation, Compromise,

    Withdrawal, Forcing and Smoothing), which conflict resolution mode is Most

    Preferred and Least Preferred by Project Managers?

    (answer format: Most Preferred, Least Preferred)

    A. Compromise, Withdrawal

    B. Confrontation, Withdrawal

    C. Confrontation, Forcing

    D. Smoothing, Withdrawal

  • 60. A conflict resolution technique that results in a win-lose situation i.e. one party

    wins at the expense of another is :

    A. Confronting

    B. Compromising

    C. Forcing

    D. Accomodating

    61. In your new project, you objective is to develop a new pharmaceutical drug.

    After doing a financial analysis, your finance manager provided you with these

    statistics:

    30% probability of success with benefits of $ 700,000

    70% probability of failure with loss of $ 300,000

    Based on this information, you :

    A. Suggest that the project to proceed ahead

    B. Suggest that the project to be stopped

    C. Communicate to your senior management that you cannot make a decision

    about whether to proceed with the project

    D. Start working on the project and ask your finance manager for additional

    information.

  • 62. Some planning processes have dependencies that require them to be performed

    in the same order and iterated several times during any phase of the project. These

    processes are also called:

    A. Project Management Processes

    B. Process Groups

    C. Facilitating Processes

    D. Core Processes

    63. In a bidder conference that you just attended, you tried to provide a clear,

    common understanding of the procurement (technical requirements, contract

    requirements etc.) Responses to questions posed by sellers were incorporated into

    the procurement documents as amendments. What will you do next?

    A. Use Standard forms required for solicitation planning

    B. Use a make-or-buy analysis to determine whether the product can be

    produced cost-effectively by performing organization

    C. Determine what type of contract should be used (i.e. fixed price, cost

    reimbursable or time and material contract)

    D. Use a screening system to determine minimum requirements of

    performance for one or more of the evaluation criteria

    64. Amongst the conflict resolution techniques, which of the following is a lose-lose

    situation?

    A. Smoothing

    B. Forcing

    C. Compromising

    D. Confronting

    Correct Choice: 3

  • 65. As a project manager, you must coordinate and direct the various technical and

    organizational interfaces that exist in the project. For this, it will be beneficial if you

    have as an input:

    A. Project Management Plan

    B. Change Results

    C. Project Charter

    D. Performance Reports

    66. Your project has been selected for a Quality Audit. Several of your team

    members are nervous because they do not have exposure to audits and do not

    understand what is expected from them. You explain to your team members that

    the primary objective of a quality audit is to:

    A. Identify how well the project compares with other projects in the

    organization

    B. Determine if the project is following all the requirements of the quality

    management plan

    C. Identify lessons learned that can improve performance of this project or of

    other projects within the performing organization

    D. Record quality control testing and measurements in a format for

    comparison and analysis

  • 67. As a project manager, you are involved in launching a new software product

    across several markets around the world and interacting with different units in your

    company. This requires a thorough knowledge of:

    A. Technical interfaces

    B. Organizational interfaces

    C. Interpersonal interfaces

    D. Staffing requirements

    68. Performance reports organize and summarize the information gathered and

    present the results of any analysis. All the following are common formats of

    Performance reports EXCEPT:

    A. S-curves

    B. Gantt Charts

    C. Earned Value Charts

    D. Tables

  • 69. As a project manager, you put a lot of emphasis on Risk Management. You just

    completed risk categorization. What could be a next step?

    A. Perform a structured review of project plans and assumptions, both at the

    total project and detailed scope levels

    B. Develop checklists for identifying risks based on historical information and

    knowledge that has been accumulated from previous similar projects

    C. Conduct planning meetings to develop the risk management plan

    D. Update Risk Registers

    70. As a project manager, you understand the importance of socio-economical

    influences on your organization. Some categories of socio-economic influences

    which you should be aware of include all the following EXCEPT:

    A. Standards and Regulations

    B. Organization Structure

    C. Cultural Influences

    D. Internationalization

    71. A procurement audit is a structured review of the procurement process from

    plan procurements through administer procurements. What is the primary objective

    of a procurement audit?

    A.

    Identify successes and failures that warrant transfer to other procurement

    items on this project or to other projects within the performing

    organization

    B. Determine the issues with your present contract so that the contract terms

    can be modified or improved

    C. To ensure that the seller is following all the terms listed in the contract

    D. To ensure that the buyer is following all the terms listed in the contract

    Correct Choice: 1

  • 72. Quality Audits, Reward and Recognition Systems and Information Retrieval

    Systems are tools for :

    A. Project Execution

    B. Project Control

    C. Project Initiation

    D. Project Planning

    73. As a Project Manager, Project Plan Development is an important element for

    managing projects. Which phase of the project management life-cycle does Project

    Plan Development belong to?

    A. Facilitating Planning Process

    B. Initiation Process

    C. Core Planning Process

    D. Execution Process

  • 74. All the following are tools and techniques of Control Costs Except:

    A. Forecasting

    B. Earned Value Management

    C. Computerized tools

    D. Expert Judgment

    75. Cost of quality is the total cost of all efforts to achieve product/service quality,

    and includes all work to ensure conformance to requirements. All the following are

    costs that are incurred EXCEPT:

    A. Internal Failure costs

    B. Prevention costs

    C. Opportunity Costs

    D. Appraisal Costs

  • 76. Identifying, documenting, and assigning project roles, responsibilities, and

    reporting relationships is done as part of:

    A. Staff Acquisition

    B. Organizational Planning

    C. Team Development

    D. Project interfaces

    77. Plan Communications involves determining the information and

    communications needs of the stakeholders: who needs what information, when

    they will need it, and how it will be given. For this, you will need all the following

    inputs EXCEPT:

    A. Stakeholders Register

    B. Factors that will limit the project management team`s options

    C. Methods used to transfer information back and forth among project

    stakeholders

    D. Tools for distributing information between stakeholders

    78. You are evaluating the probabilities of risks and costs or rewards of each logical

    path of events and future decisions. You create a diagram that describes a decision

    under consideration and implications of choosing one or another of the available

    alternatives. The diagram you are creating can also be referred to as:

    A. Simulation Diagram

    B. Decision tree

    C. Fishbone Diagram

    D. Probability/Impact risk rating matrix

  • 79. In a Balanced Matrix Organization,

    A. Project Manager reports to Functional Manager

    B. Project Manager position does not exist

    C. Project Manager reports to Manager of Project Managers

    D. Project Manager reports to Program Manager

    80. You just signed the contract with a seller, and are ready to start Contract

    Administration. But because of funding issues, your management decides to

    terminate the contract. What should you do?

    A. Go back to procurement planning to determine what to procure and when

    B. Choose from other potential sellers

    C. Follow procedures as listed in close procurements

    D. Initiate procedures listed in contract change control system to define the

    process by which the contract may be identified.

    81. Two fundamental objectives of project control are to

    A. Ensure that the required input of material, personnel, and equipment is available

    when needed and that budgeting is adequate

    B. Eliminate unexpected technical problems and technical difficulties that require

    more resources

    C. Ensure that resources are available when needed and that the scope of work does

    not increase

    D. Ensure that the required input of material, personnel, and equipment is available

    when needed and that budgeting is adequate Achieve results by altering activities and

    managing organizational assets

  • 82. The causes of variances and the reasoning behind the corrective action chosen

    should be documented so that they become part of the historical database of the

    performing organization. This is documented as part of:

    A. Project plan updates

    B. Corrective Action

    C. Lessons Learned

    D. Performance Measurement

    83. Determine Budget involves allocating the overall cost estimate to individual

    work activities or work packages. One output from Determine Budget process is:

    A. Cost Performance Baseline

    B. Basis of Estimates

    C. Resource Calendars

    D. Budget Forecasts

    84. You are trying to determine what cost and schedule trade-off will be most

    appropriate for your project. You have the option to select either a more

    experienced person at $ 120 per hour who can do the task in 45 days or a less

    experienced person at $ 80 per hour who can do the same task in 65 days. A tool

    you can use to facilitate making the decision is:

    A. Cost of Quality

    B. Cause-and-effect diagram

    C. Design of Experiments

    D. Network diagrams

  • 85. You are the project manager in a Matrix organization. So, all your team

    members report to you and the functional manager of their respective

    departments. Managing this dual relationship is always a challenge and should

    generally be the responsibility of :

    A. Project Manager

    B. Functional Manager

    C. Project Manager and Functional Manager

    D. Program Manager

    86. In your project, you are presently involved with collecting project records;

    ensuring that they reflect final specifications; analyzing project success,

    effectiveness, and lessons learned; and archiving such information for future use.

    This is done as part of :

    A. Close Project or Phase

    B. Administer Procurements

    C. Contract

    D. Project Document Updates

    87. You are identifying risk owners and assigned responsibilities; results from

    qualitative and quantitative risk analysis processes; level of residual risk;

    contingency plans and fallback plans. You will write down all this information in the:

    A. Risk Management Plan

    B. Risk Register Updates

    C. Data Gathering and Representation Techniques

    D. Plan Projects

  • 88. All the following are features of projectized organization EXCEPT:

    A. Team members are often collocated

    B. There is a "home" for project team members after a project is completed

    C. Project managers have great deal of authority and independence

    D. Organizational units (or departments) either report directly to the project

    manager or provide support services to the various projects

    89. You are in the process of documenting project requirements and identifying

    potential sources for Plan Procurements. You understand the benefits of PMP

    Certification, and as part of Plan Procurements, you specify having a "PMP

    Certified" project manager will be an advantage for the seller. This is an example of

    :

    A. Procurement Documentation

    B. Subjective Evaluation Criteria

    C. Objective Evaluation Criteria

    D. Statement of Work

    90. As a project manager, achieving customer satisfaction is an important objective

    for you. Which of the following will best help you in getting customer satisfaction?

    A. Defining Requirements

    B. Providing more features than what customer has asked for

    C. Identifying project related risks

    D. Providing project justification

  • 91. You are managing a small project with 5 team-members working part-time. In

    the beginning of every week, you verbally allocate work to all the team-members.

    This is an example of:

    A. Verbal Work Authorization System

    B. Improper Planning because team-members do not know what needs to be

    done at appropriate times.

    C. Project Plan Execution

    D. Project Plan Development

    92. The cost of corrective action taken by the purchaser and chargeable to the

    supplier under the terms of the contract is

    A. Payment authorization

    B. Bid cost considerations

    C. Back Charge

    D. Release payment

    93. All the following statements about "Quality" and "Grade" are true EXCEPT:

    A. Grade is a rank given to entities having the same functional use but

    different technical characteristics

    B. Low quality project may be having a high grade

    C. Low Grade product may be having high quality

    D. It is a problem if either the product is low grade or low quality

  • 94. As part of your project, you were involved in negotiating with functional

    managers and other project management teams for staff assignments. What should

    you be doing next?

    A. Using role and responsibility definitions or reporting relationships of a

    similar project to expedite organizational planning

    B. Identifying all stakeholders and their needs so that their needs are satisfied

    C. Creating Roles and Responsibility Assignment Matrix

    D. Deciding on which team building activities will help in improving team

    performance

    95. As part of Close Procurements, you document project results to formalize

    acceptance of the:

    A. Project

    B. Product of the project

    C. Contract

    D. Product of the contract

    96. Risk Acceptance is a strategy that indicates that the project team has decided

    not to change the project plan to deal with a risk or is unable to identify any other

    suitable response strategy. The most usual risk acceptance response is to :

    A. Establish a contingency reserve

    B. Create a fallback plan

    C. Develop alternative options

    D. Change project scope

  • 97. You are working as a Project Manager in an organization where your

    responsibility is to coordinate activities, but decisions are primarily made by

    Management. The organization structure you are working in is:

    A. Weak Matrix

    B. Balanced Matrix

    C. Functional

    D. Strong Matrix

  • 98. Conduct Procurements involves obtaining responses(bids and proposals) from

    prospective sellers on how project needs can be met. Most of the cost for the

    Conduct Procurements is usually paid for by the:

    A. Project

    B. performing organization

    C. Buyer

    D. Seller

    99. Your previous project manager made most decisions by himself without

    consulting subordinates. So, he believed in a leadership style that was:

    A. Laissez Faire

    B. Assertive

    C. Autocratic

    D. Coaching

    100. You are the project manager for a pharmaceutical company, which will be

    launching a new product in the market. It is essential that you follow Integrated

    change control to ensure that all changes are properly coordinated across the entire

    project. In this context, you should do all the following EXCEPT:

    A. Influence the factors that create changes

    B. Determine that a change has occurred

    C. Make changes to the integrated performance baseline to reflect the

    changes

    D. Manage actual changes as and when they occur

  • 101. You are the project manager for a software company, and are in the process of

    developing an approximation of the costs of the resources needed to complete

    project activities. In approximating the cost, you are considering the causes of

    variation of the final estimate for purpose of better managing the project. This is

    done as part of:

    A. Administer Procurements

    B. Estimate Costs

    C. Determine Budget

    D. Control Costs

    102. As a quality-conscious project manager, you realize that it is not just enough to

    say that meeting the planned schedule dates is a measure of management quality;

    the project management team must also indicate whether every activity must start

    on time or only finish on time; whether individual activities will be measure or only

    certain deliverables, and if so which ones. These definitions, in very specific terms,

    what something is and how it is measured in the perform quality control process are

    also called:

    A. Checklists

    B. Benchmarks

    C. Quality Policies

    D. Quality Metrics

  • 103. In your project, you have designated a "war room" where your team

    congregates and posts schedules, updates etc. This is an example of:

    A. Collocation

    B. Team-building activity

    C. Training

    D. Solving critical problems

    104. Analysis of project performance often generates a request for a change to

    some aspect of the project. Such change requests, which are an output of Report

    Performance, are managed through which of the following process/processes

    (Select the Best Answer):

    A. Integrated Change Control

    B. Control Scope

    C. Control Schedule

    D. All of the above

    105. Workarounds are unplanned responses to emerging risks that were previously

    unidentified or accepted. If you have to perform a workaround during Monitor and

    Control Risks, it will be done through:

    A. Project change requests

    B. Updates to risk response plan

    C. Corrective Action

    D. Project risk response audits

  • 106. Two technical resources in your team have been arguing consistently, and you

    would like to ensure that personality clashes do not endanger your project. To

    resolve this issue, you should use:

    A. Leading and Influencing Skills

    B. Communication Skills

    C. Negotiation Skills

    D. Problem Solving skills

    107. Conduct Procurements involves the receipt of bids or proposals and the

    application of the evaluation criteria to select a provider. Which of the following are

    tools and techniques can be used for Source Selection:

    A. Procurement Negotiation, Screening System, Independent Estimates

    B. Procurement Negotiation, Screening System, Bidder Conferences

    C. Procurement Negotiation, Make-or-buy analysis, Independent Estimates

    D. Bidder Conferences, Expert Judgements, Advertising, Internet search

    108. _________ is a written order directing the contractor to make changes according to the

    provisions of the contract documents.

    A. Change order/purchase order Amendment

    B. Contract order Modifications.

    C. Contractor claim

    D. Owner Directive

  • 109. If you would like to find out who will be approving changes in your project, you

    can refer to the:

    A. Change Control system

    B. Project plan

    C. Organization Chart

    D. Resource Assignment Matrix

    110. In your project, you are using Project files, commercial cost-estimating

    databases and project team knowledge to determine the cost of many categories of

    resources. This will help you in determining estimate of the costs of the resources

    needed to complete project activities. This information is available to you as part of

    A. activity duration estimates

    B. estimating publications

    C. historical information

    D. chart of accounts

    111. A flow chart is any diagram which shows how various elements of a system

    relate and includes techniques like "Cause and Effect Diagrams" and "System or

    Process Flowcharts." As a project manager, you find flow-charting as an useful tool

    for :

    A. Plan Quality

    B. Perform Quality Assurance

    C. Perform Quality Control

    D. A and C

  • 112. What are Maslow's three highest levels of human needs?

    A. Physiological, safety, and social

    B. Recognition, responsibility, and reward

    C. Happiness, health, and prosperity

    D. Self-actualization, esteem, and social

    113. Project communication management includes the processes required to ensure

    timely and appropriate generation, collection, dissemination, storage, and ultimate

    disposition of project information. The Major processes for Project Communication

    Management are as follows:

    A. Communications Planning, Information Distribution and Performance

    Reporting

    B. Communications Planning, Performance Reporting and Integrated Change

    Control

    C. Plan Communications, Report Performance, Distribution Information,

    Manage Stakeholders Expectations

    D. Performance Reporting, Information Distribution, Administrative Closure

    114. Risk management plan describes how risk identification, qualitative and

    quantitative analysis, response planning, monitoring, and control will be structured

    and performed during project life cycle. The risk management plan includes all the

    following EXCEPT:

    A. Approaches, tools and data sources that may be used to perform risk

    management on the project

    B. Budget for risk management in the project

    C. Risk Triggers to indicate when a risk may occur

    D. Scoring and interpretation methods appropriate for the type and timing of

    qualitative and quantitative risk analysis

  • 115. Project Monitoring occurs:-

    A. On a continual basis throughout the executing process and as needed in the other

    processes

    B. At the end of each phase of the project life cycle to assess its success in meeting

    project objectives

    C. At the end of each planning process

    D. On a continual basis throughout the project

    116. During plan procurements, you identify which project needs can be best met by

    procuring products or services outside the project organization. In this context,

    which of the statements relating to Product Description and Statement of Work is

    correct?

    A.

    Product Description describes the ultimate end product of the project; a

    statement of work describes the portion of the product to be provided by a

    seller to the project

    B. Product Description is generally broader than a statement of work

    C. If the performing organization procures the entire product, Product

    Description and Statement of Work refer to the same thing.

    D. All Statements above are true

  • 117. You are in the build phase of your project, when you realize that because of a

    design error, the product will not meet the performance parameters specified by

    the customer. In this context, what should you do first:

    A. Decrease the performance parameters so that the product developed will

    satisfy those parameters.

    B. Discuss with your team to try to find out alternatives means to solve the

    issue

    C. Escalate to your leadership team

    D. Ask for additional funding from your business sponsors to accommodate

    the new requirement

    118. According to the expectancy theory of motivation

    A. Poor performance is the natural outcome of poor training

    B. Managers should not expect too much of workers

    C. Managers should expect that employees who are paid more will work harder

    D. Motivation to act is linked to an outcome that is expected to have value

    119. Rolling wave planning provides information on the work to be done

    A. For successful completion of the current phase and subsequent phases of the

    project

    B. Throughout all phases of the project

    C. For successful completion of the current phase of the project

    D. In the next phase of the project

  • 120. Description of how a project management team should implement the overall

    intentions and direction of an organization with regards to quality (as expressed by

    top management) is available in:

    A. Operational Definitions

    B. Quality Management Plan

    C. Checklists

    D. Quality Policy

    121. Getting the needed human resources (individuals or groups) assigned to and

    working on your project is done as part of:

    A. Procurement Management

    B. Acquire Project Team

    C. Organizational Planning

    D. Resource Planning

    122. To examine project results over time to determine if performance is improving

    or deteriorating, you would use:

    A. Performance reviews

    B. Trend Analysis

    C. Earned Value Analysis

    D. Variance Analysis

  • 123. All the following are examples of techniques that can be used for Identify Risks

    EXCEPT:

    A. Brainstorming

    B. SWOT Analysis

    C. Checklist Analysis

    D. Assumption Analysis

    124. A tangible verifiable work product to ensure proper definition of product of the

    project is also called:

    A. Work Breakdown Structure

    B. Work Breakdown Structure Dictionary

    C. Deliverable

    D. Phase end review

    125. The statement of work (SOW) describes the procurement item in sufficient

    detail to allow prospective sellers to determine if they are capable of providing the

    item. In this case, "sufficient detail"

    A. May vary, based on nature of the item or needs of the buyer

    B. Should be at the level of Work Breakdown Structures

    C. Should be at the activity level

    D. Should be at the level required in proposal

  • 126. In your project, you have historical information about costs, and the given

    parameters for cost estimating are quantifiable and scalable. Your manager wants

    to use project characteristics in a mathematical model to predict project costs. But

    you believe that parametric modeling is the best solution. What is the best course

    of action for this situation:

    A. Agree with your manager`s opinion

    B. Make an analysis for your manager`s proposal and create a case for why

    your solution is better

    C. Ask for Expert Judgment from a Subject Matter Expert in cost estimation

    D. None of the above

    127. Plan Quality involves identifying which quality standards are relevant to the

    project and determining how to satisfy them. For this, you use "cost of quality" as a

    tool. In this context, cost of quality refers to:

    A. Prevention, appraisal and failure costs

    B. Work required to ensure conformance to requirements

    C. Work resulting from nonconformance to requirements

    D. All the statements above are true

  • 128. Risk management helps in maximizing the probability and consequences of

    positive events and minimizing the probability and consequences of adverse events

    to project objectives. Plan Risk Responses helps in this context because it:

    A. helps in deciding how to approach and plan the risk management activities

    B. determines which risks might affect the project and documenting their

    characteristics

    C. develops procedures and techniques to enhance opportunities and reduce

    threats to project objectives

    D. monitors residual risks, identifies new risks and executes risk reduction

    plans

    129. Project Portfolio Management refers to:

    A. Selection and support of projects or program investments

    B. Group of projects managed in a coordinated way

    C. Creating unique product, service or result

    D. Progressive Elaboration of projects to ensure customer requirements are

    satisfied

    130. Your project is in Execution phase. NPV of your project is -200,000 and IRR is

    5%. CPI is 1.2 and SPI is 0.8 - what is the recommended action?

    A. Cancel the project since NPV is negative

    B. Cancel the project since IRR is very low

    C. Crash your project

    D. Try to improve the NPV by highlighting benefits which were not included in

    the CBA

  • 131. All the following statements about Risk Management processes in real-life

    project situations are correct EXCEPT:

    A. Processes interact with each other

    B. Processes always have discrete elements with well-defined interfaces

    C. Risk management processes interact with processes in other knowledge

    areas

    D. Each process generally occurs at least once in every project

    132. While managing projects, negotiating helps in conferring with others to come

    to terms with them or reach an agreement. A form of Assisted Negotiation is

    A. Arbitration

    B. Problem Solving

    C. Regulation

    D. Compromising

    133. Project A had an initial investment of $ 3 million, out of which $ 1.5 million has

    already been spent. Another competing project, Project B will require $ 1.6 million

    now for completion and will meet the same objectives as project A. Which project

    should you select?

    A. Project A

    B. Project B

    C. Neither Project A nor Project B

    D. Cannot be determined by the information available

  • 134. Graphic display of cumulative costs or labor hours plotted against time is also

    called a(an):

    A. Histogram

    B. S-curve

    C. Control Chart

    D. Pareto Diagram

    135. Factors like Probability of successfully completing the project, Cost of changes,

    Cost of error correction etc. are highest:

    A. At beginning of the project

    B. At end of the project

    C. During project implementation

    D. Cannot be determined as they are specific to the project

    136. All the following are inputs for Control Scope EXCEPT:

    A. Project Management Plan

    B. Work Performance Information

    C. Inspection

    D. Organizational Process Assets

  • 137. During Sequence Activities, you identify and document interactivity

    dependencies. Which of the following is an output from Sequence Activities

    Process?

    A. Project Network Diagrams

    B. Activity Duration Estimates

    C. Project Schedule

    D. Activity List

    138. Please refer to the following diagram:

    What is the Earned Value(EV)?

    A. $ 5,000

    B. $ 10,000

    C. $ 11,000

    D. $ 12,500

  • 139. Utility function is a commonly used technique to find out the tolerance of a

    project manager towards risk. Some project managers are more averse towards risk

    than others. All the following are different classifications of tolerance for risk

    EXCEPT:

    A. Risk Averter

    B. Risk Seeker

    C. Risk Mitigator

    D. Risk Neutral

    140. A project manager is responsible for managing project costs and human

    resources. Factors like Cost and Staffing level for a project :

    A. Increase with duration of the project

    B. Decrease with duration of the project

    C. Are low at the start, higher toward the end, and decrease rapidly as project

    draws to a conclusion.

    D. Cannot be determined as they are specific to the project

    141. Which of the following is an output of Define Scope Process?

    A. Scope Statement

    B. Work Breakdown Structure

    C. Project Charter

    D. Lessons Learned

  • 142. All the following are Tools and Techniques for Develop Schedule EXCEPT:

    A. Critical Path Method

    B. Duration Compression

    C. Analogous Estimating

    D. Resource Leveling heuristics

    143. Please refer to the following diagram:

    What is the status of the project?

    A. Behind Schedule, Under Budget

    B. Ahead of Schedule, Under Budget

    C. Ahead of Schedule, Over Budget

    D. Behind of Schedule, Over Budget

  • 144. You did proper risk management to systematically identify, analyze and discuss

    response strategy to minimize probability and consequences of adverse events to

    the project objectives. But there were minor risks for which you created a small

    contingency budget. These minor risks are examples of:

    A. Secondary risks

    B. Residual Risks

    C. Remaining Risks

    D. None of the above

    145. Planning is of major importance for a project because project involves doing

    something that has not been done before. What of the following is the final core

    process in Planning phase?

    A. Scope Planning

    B. Estimate Costs

    C. Define Scope

    D. Develop Project Management Plan

    146. All the following are Inputs to Define Scope EXCEPT:

    A. Requirements Documentation

    B. Project Charter

    C. Organizational process assets

    D. Project Deliverables

  • 147. As part of Define Activities, you identify the specific activities that must be

    performed to produce the various project deliverables. All the following are inputs

    to this process EXCEPT:

    A. Enterprise Environmental Factors

    B. Organizational Process Assets

    C. Scope Baseline

    D. Mandatory and Discretionary Dependencies

    148. Please refer to the following diagram:

    You know that Current Variances are atypical i.e. similar variances will not occur in the

    future. What is the Estimate at Completion(EAC)?

    A. $ 15,000

    B. $ 20,000

    C. $ 20,500

    D. $ 22,000

  • 149. Plan Risk Responses helps the project manager develop options and determine

    actions to enhance opportunities and reduce threats to the project`s objectives. The

    output from plan risk responses is a risk response plan which should be:-

    A. At the level of detail of work packages in WBS

    B. At the level of detail where actions will be taken

    C. Able to identify and document residual risks and secondary risks

    D. Used for periodic risk reviews to identify risk ratings and prioritization

    150. As part of controlling, project performance must be monitored and measured

    regularly to identify variances from the plan. All the following are processes

    involved with controlling process group EXCEPT:

    A. Verify Scope

    B. Monitor and Control Risks

    C. Report Performance

    D. Perform Quality Assurance

    151. Your Management is evaluating a project which requires an investment of $

    500,000. The expected inflow is $ 100,000 for 1st year, and $ 300,000 for every year

    after that. What is the payback period?

    A. 2 years

    B. 2 years, 4 months

    C. 3 years

    D. Cannot be determined because Discount Rate is not specified

  • 152. Please refer to this diagram:

    What is the effect on the project if duration of task J is increased to 9 weeks?

    A. No effect since task J is not on the critical path

    B. Risk of the project will increase

    C. The overall time-frame required to complete the project will increase by 1

    week

    D. None of the above

  • 153. Please refer to the following diagram:

    You know that Current Variances are atypical i.e. similar variances will not occur in the

    future. What is Cost Performance Index (CPI) for the project?

    A. 0.96

    B. 1.04

    C. 1.00

    D. 1.20

  • 154. All the following statements about IRR (Internal Rate of Return) and NPV (Net

    Present Value) are correct EXCEPT:

    A. Net Present Value is difference between all present value of all inflows and

    present value of all outflows

    B. The prevailing market rate is used for Net Present Value Calculations

    C. Internal Rate of Return is the discount rate when Net Present Value = 0

    D. While selecting projects, it is preferable to select projects with a higher IRR

    155. Please refer to this diagram:

    What is the slack of task G?

    A. 0 weeks

    B. 1 week

    C. -1 week

    D. Cannot be determined

  • 156. Estimating the cost of individual activities or work packages, then rolling up the

    individual estimates to get a project total is done as part of :

    A. Bottom up Estimating

    B. Analogous Estimating

    C. Parametric Modeling

    D. Top-down Estimating

    157. A project charter has all the following (Select the best option):

    A. Project Justification, Product, Deliverables and Objectives

    B. Business Need, Product Description

    C. Business Need, Project Justification

    D. Project Deliverables, Product Description

  • 158. Please refer to this diagram:

    What is the impact to critical path if management wants you to complete the project in

    20 weeks ?

    A. Duration of Critical path increases by 3 weeks

    B. Duration of Critical path decreases by 3 weeks

    C. Duration of Critical path remains same

    D. Duration of Critical path cannot be determined

    159. Your project is being cancelled, and you are following the Statement of

    Position (developed by American Institute of Certified Public Accountants - AICPA)

    which requires that all the costs for failed information technology project should be

    written off in the quarter that the project is cancelled. These processes are part of:

    A. Lessons Learned

    B. Revised Cost Estimates

    C. Close Project

    D. Earned Value Management

  • 160. A well-constructed Scope Statement can provide all the following benefits

    EXCEPT:

    A. Provide a documented basis for making future project decisions

    B. Develop common understanding of project scope among stakeholders

    C. Provide knowledge of project justification, deliverables and objectives

    D. Provide a basis for time and cost estimates

    161. In your project, you realize the importance of determining the start and finish

    dates for project activities. If the project start or end dates are not realistic, then the

    project may not be completed on time. This is done as part of :

    A. Sequence Activities

    B. Estimate Activity Durations

    C. Develop Schedule

    D. Define Activities

    162. According to Herzberg's motivator-hygiene Theory of Motivation, if

    achievement, recognition, responsibility, advance or promotion, and positive

    supervisor attitude are not present, employees will:-

    A. Become alienated with the organization and leave

    B. Lack motivation and become dissatisfied with their work

    C. Lack motivation but will not be dissatisfied with their work

    D. Become dissatisfied only if they do not receive salary increases

  • 163. A work authorization system is a:-

    A. Work breakdown structure showing individual work elements

    B. Formal procedures for sanctioning work so that it is done at the right time and in

    the proper sequence

    C. Method to ensure that each person on the project team knows the work elements

    that are his or her responsibility

    D. System to help measure performance in terms of work completed versus work

    planned

    164. Measuring project performance regularly is necessary to identify variances

    from the project plan. A variance is considered to be significant if it:-

    A. Is considered a project risk

    B. Becomes a lesson learned as a result of the corrective action selected

    C. Jeopardizes project objectives

    D. Requires corrective action

    165. You are the project manager responsible for delivering a project which is being

    done under contract. From a financial perspective, you know that all the cost

    estimates must be assigned to the correct accounting category. For this, you use:

    A. Chart of Accounts

    B. Project Files

    C. Estimating Publications

    D. Work Breakdown Structures

  • 166. Change requests occur in all the following forms except

    A. Oral or written

    B. Formal or Informal

    C. Legally mandated or optional

    D. Externally or internally initiated

    167. Following information is available about a particular task in your project plan:

    Early Start(ES) : 25 days

    Late Start(LS) : 30 days

    Early Finish(EF) : 50 days

    Late Finish(LF) : 55 days

    Based on this information, you can deduce that:

    A. The task is on critical path

    B. The project may get delayed

    C. Project Float is 5 days

    D. None of the above

    168. Which of the following includes all the processes required for Project Cost

    Management? (select the best answer)

    A. Estimate Costs, Determine Budget, Control Costs

    B. Cost Aggregation , Budget Forecasts, Cost Control

    C. Define Cost, Cost Aggregation , Budget Forecasts, Control Costs

    D. Resource Calendars , Cost Aggregation , Budget Forecasts

  • 169. You are managing a complicated software development project with several

    deliverables. To be effective, and to be alert of potential future problems, you

    monitor interim deliverables i.e. which deliverables have been completed and

    which have not. This information is available to you through:

    A. Revisions to Work Breakdown Structure

    B. Project Baseline changes

    C. Performance Reports

    D. None of the above

    170. The process of conferring with others to come to terms or reach an agreement

    is called

    A. Win-win

    B. Negotiation

    C. Getting to yes

    D. Arbitration

    171. When communicating with a people-oriented person, a project manager

    should

    A. Stress the uniqueness of the idea or topic at hand

    B. Stress the relationships between his/her proposals and the people concerned

    C. Be precise about the value of the ideas to overall organizational goals

    D. Focus on personnel performance issues first

  • 172. A work breakdown structure is most useful for ...

    A. Identifying individual tasks for a project

    B. Scheduling the start of tasks

    C. Both A and D

    D. Developing a cost estimate

    173. Fast-tracking is also known as

    A. Overtime and contracting

    B. Utilizing additional resources

    C. Concurrent Engineering

    D. Crashing

    174. In dealing with the customer, the project manager should:-

    A. Disclose information only at regular intervals to maintain consistency

    B. Strive to develop a friendly, honest, and open relationship

    C. Be honest to the extent that the project organization is protected from litigation

    D. Try to maximize profits by encouraging scope creep

  • 175. Your project is very critical for the company and must be completed within 6

    months. The project charter has been signed, but Scope Statement is not yet

    prepared. Management asks you to go ahead with the project without the scope

    statement being approved. What should you do?

    A. Refuse to work on the project because management is not following

    standard Project Management Practices

    B. Since time is of essence, you should start the project with the inputs from

    project charter

    C. Meet the Management and mention the problems you will face without a

    Scope Statement

    D. Escalate the issue to the project sponsor and issue a Risk Memo

    176. A project manager who wants to create a receptive atmosphere for

    communicating should

    A. Speak or write as he/she would like to be spoken or written to

    B. Ensure that all communication is clear and understood

    C. Have the project team prepare a project communication plan

    D. Ensure that team members have the information needed to do their work

    E. Ensure that team members have the tools available to facilitate communication

  • 177. Earned Value Management is a properly used tool and technique to measure

    project performance. In Earned Value Management, BCWP refers to:

    A. Physical work actually accomplished, including the estimated value of this

    work

    B. Physical work scheduled to be performed, including the estimated value of

    this work

    C. Actual cost incurred to accomplish the earned value

    D. None of the above

    178. You are doing a project under contract, where you are supposed to create an

    anti-virus software product for the customer in 10 months. You follow the software

    development life-cycle which includes Analysis, high level design, low level design,

    coding, testing and rollout, with a deliverable at end of each phase. Your customer

    has defined the scope very well, and said that they would review your product after

    10 month period. In this case, you should:

    A. Insist that the customer verifies the deliverables at end of each phase

    B. Ask your Senior Management to review the deliverables at end of each

    phase to ensure it satisfies customer requirements

    C. Complete building the product as per specifications and provide completed

    product to customer as requested.

    D. Provide project deliverables to the customer at the end of each phase even

    if the customer may not review them

  • 179. Financial compensation is the primary motivational tool for which of the

    following management theories or programs?

    A. Zero Defects program

    B. Theory X management

    C. Theory Y management

    D. Quality Control Circles

    E. A and C

    180. A poured concrete footing has been tested to determine the compliance with

    applicable requirements. This is an example of

    A. Perform Quality control

    B. Perform Quality assurance

    C. Plan Quality

    D. Quality Audit

    A. - 0.3 Million

    B. - 1 Million

    C. 1 Million

    D. 0.7 Million

    181. Items at the lowest level of a Work Breakdown Structure are also called:

    A. Work Components

    B. Work Packages

    C. WBS Dictionaries

    D. WBS, Work Components, Work Packages or WBS Dictionaries - depending

    on the context in which the term is used

  • 182. You are using an Arrow Diagramming method to construct a project network

    diagram - you use arrows to represent the activities and connect them at nodes to

    show their dependencies. You can use all the following as Inputs for this process

    EXCEPT:

    A. List of All Activities that will be performed on the project

    B. Description of the product

    C. Mandatory and Discretionary Dependencies

    D. Schematic Display of project`s activities and logical relationships

    183. Inspection includes activities such as measuring, examining, and testing

    undertaken to determine whether results conform to requirements. Inspections can

    also be called all the following EXCEPT:

    A. Product Reviews

    B. Audits

    C. Stage-gates

    D. Walk-throughs

    184. The statistical control chart is a tool used primarily to help:-

    A. Monitor process variation over time

    B. Measure the degree of conformity

    C. Determine whether results conform

    D. Analyze how problems occur

    E. Determine whether results conform to requirements

  • 185. Project scope management includes the processes required to ensure that the

    project includes all the work required, and only the work required, to complete the

    project successfully. In this context, project charter plays a very important role

    because it:

    A. Provides list of project deliverables

    B. Authorizes the project

    C. Provides deliverable oriented grouping of work components

    D. Describes the project objectives i.e. quantifiable criteria that must be met

    for the project to be considered successful

    186. You are doing a what-if analysis to determine the impact of delaying a major

    component delivery, extending specific engineering durations etc. What-if analysis

    is an example of :

    A. Critical Path Method

    B. Simulation

    C. Conditional Programming

    D. Resource Leveling heuristic

    187. The "rule of seven" as applied to statistical process control charts means

    that:-

    A. Seven rejects typically occur per thousand inspections

    B. Seven consecutive points are ascending, descending, or the same

    C. At least seven inspectors should be in place for every thousand employees

    D. The quality control group should measure the process at least seven times to

    validate it

    E. A process is not out of control even though seven measurements fall outside the

    lower and upper control limits:

  • 188. The quality management plan describes all the following except the

    A. Organizational structure, responsibilities, procedures, processes, and resources

    needed to implement project quality management

    B. Method for implementing the quality policy

    C. Quality control, quality assurance, and quality improvement plans for the project

    D. Procedures used to conduct trade-off analyses among cost, schedule, and quality:

    189. Kaizen is an approach to continuous improvement that emphasizes:-

    A. Customer satisfaction over cost

    B. Major advances

    C. Incremental improvement

    D. Zero defects

    190. By using Project Risk management techniques project managers can develop

    strategies that do all but which of the following:-

    A. Significantly reduce project risks

    B. Provide a rational basis for better decision making

    C. Eliminate project risks

    D. Identify risks, their impact(s), and any appropriate responses

  • 191. Risks classified as unknown unknowns (i.e., those which cannot be identified

    or evaluated)

    A. Should be handled via contingency allowances

    B. Should be deflected to the contracting officer

    C. Should be ignored since they cannot be identified

    D. Should be ignored, since they are not covered in the Project Risk Assessment

    192. In the network diagram for a completely unrealistic schedule, you would likely

    find:-

    A. No slack available for critical tasks

    B. Late start dates earlier than early start dates

    C. Negative total float

    D. All of the above

    193. Assumptions generally involve some risk because:-

    A. Assumptions are based on lessons learned

    B. Assumptions involve factors that are considered true, real, or certain:

    C. Assumptions are based on constraints

    D. Historical information may not be available

  • 194. Which relationship dependency is indicative of concurrency?

    A. Finish-to-finish

    B. Start-to-finish

    C. Finish-to-start

    D. Start-to-start

    195. Lessons learned from projects are significant because they

    A. Must be collected to meet requirements of organizational policies and procedures

    B. Show why certain projects were selected by the organization over others

    C. Show the causes of variances and the reasons certain corrective actions were

    selected

    D. Show why certain people were selected as project manager and team members

    over others:

    196. Define Activities involves identifying and documenting the specific activities

    that must be performed to produce the deliverables and sub-deliverables identified

    in the work breakdown structure (WBS). All the following statements about the

    activity list produced as an Output from Define Activities are True EXCEPT:

    A. Activity list must include ALL activities that will be performed on the project

    B. Activity list may include some activities that are not required as part of the

    project

    C. Activity list should include descriptions of each activity to ensure that the

    project team members will understand how the work is to be done.

    D. Activity list should be organized as an extension to the WBS to ensure that

    it is complete

  • 197. Which of the following is an appropriate management style to use with the

    project manager wants to encourage the staff to pool its knowledge to make the

    best decision possible?

    A. Laissez-faire

    B. Autocratic

    C. Democratic

    D. Directive

    198. There is a Subject Matter Expert in your company who specializes in

    Information Security. You know that you will need her help for 3 days in your

    project. Since her availability is limited, you scheduled her in reverse from the

    project ending date. This is an example of:

    A. Critical Chain

    B. Resource based method

    C. Crashing

    D. Reverse resource allocation

    199. All the following are benefits of fast tracking a project EXCEPT:

    A. Facilitates Duration Compression

    B. Reduces risk

    C. Ensure activities are done in parallel which would normally be done in

    sequence

    D. Helps shorten the project schedule without changing the project scope

  • 200. Control Schedule process is concerned with influencing the factors that create

    schedule changes to ensure that changes are agreed upon, determining that the

    schedule has changed, and managing the actual changes when and as they occur.

    Which of the following tool is helpful to control schedule?

    A. Duration Compression

    B. Pareto Diagram

    C. Performance reviews

    D. Network Diagram