SEQ Rail Stabling Program - Robina Construction update As part of a scheduled track closure of the Gold Coast line, Queensland Rail and Leighton Contractors will be undertaking vital construction activities along the rail corridor between Robina Station and Cbus Stadium as part of the SEQ Rail Stabling Program. The work will be undertaken around the clock from 3.00am Saturday, 12 September through until midnight Sunday, 14 September 2015 and will include: Delivery trucks and workers vehicles entering the site via Bayberry Lane, Robina Use of machinery such as an excavator, vacuum excavation truck and generators Mobile lighting towers to light the work areas Re-routing and terminations of signaling cables Concrete works for the foundations of overhead line equipment masts Use of small power tools such as drills, saws and minor vibratory equipment Delivery and unloading of materials. Robina Hospital Work Cbus LEGEND Access into Robina Station

Queensland Rail | We aim to be Australia's best …€¦ · Web viewUse of machinery such as an excavator, vacuum excavation truck and generators Mobile lighting towers to light the

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Queensland Rail | We aim to be Australia's best …€¦ · Web viewUse of machinery such as an excavator, vacuum excavation truck and generators Mobile lighting towers to light the

SEQ Rail Stabling Program - RobinaConstruction update

As part of a scheduled track closure of the Gold Coast line, Queensland Rail and Leighton Contractors will be undertaking vital construction activities along the rail corridor between Robina Station and Cbus Stadium as part of the SEQ Rail Stabling Program.

The work will be undertaken around the clock from 3.00am Saturday, 12 September through until midnight Sunday, 14 September 2015 and will include:

Delivery trucks and workers vehicles entering the site via Bayberry Lane, Robina Use of machinery such as an excavator, vacuum excavation truck and generators Mobile lighting towers to light the work areas Re-routing and terminations of signaling cables Concrete works for the foundations of overhead line equipment masts Use of small power tools such as drills, saws and minor vibratory equipment Delivery and unloading of materials.

Trains will be affected from the first train Saturday 12 September until the last train Sunday 14 September. Freight services will not operate during this time. For information about passenger train replacement services, please contact Translink on 13 12 30 or via the website at www.translink.com.au

Work area

Cbus Stadium

Robina Station

Robina Hospital

LEGEND Access into work area

Page 2: Queensland Rail | We aim to be Australia's best …€¦ · Web viewUse of machinery such as an excavator, vacuum excavation truck and generators Mobile lighting towers to light the

SEQ Rail Stabling Program - RobinaConstruction update

From early September until late October 2015, various construction activities will be undertaken to build the stabling facility at Robina. Activities will include:

Minor earthworks to grade and level the construction area Placement of a laydown facility adjacent to the Robina Raptors club house Excavation and installation of stormwater drainage Placement of buildings for new crew facilities and connection of utilities Transporting fill material using haulage trucks.

You will notice some changes around your local area and the car parks on both sides of the rail line including: Increased truck and vehicle movements on Robina Town Centre Drive, Robina Station Road and

Bayberry Lane Construction work will be carried out between 6.30am and 5.00pm Monday to Saturday. Workers may

arrive onsite between 5.30am and 6.30am to prepare for the day’s activities Truck and construction vehicle movements in the car parks around Robina Station Establishment of storage and lay down areas for construction materials Placement of temporary fencing around construction areas.

Every effort will be made to keep disruption to a minimum. We appreciate your patience during the construction period and will continue to update you as work progresses.

Where can I find out more information?If you have any questions or would like to register for more information, please contact the Project Team on 1800 783 334 (free call) or [email protected]. Visit www.queenslandrail.com.au/stabling anytime for more information and updates.

Project information

The South East Queensland (SEQ) Stabling Program involves the design and construction of new or additional train stabling facilities in four locations: Robina, Banyo, Elimbah and Woombye.

The $116 million project was announced on Wednesday, 6 May 2015. The SEQ Stabling Program is part of the broader New Generation Rollingstock project that will see 75 new suburban six-car trains added to the South East Queensland City network, a 30 per cent increase of the current fleet.

Leighton Contractors will design and construct the new stabling facilities to help house the 75 new six-car trains which will commence services in mid-2016.