Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

Embed Size (px)

Citation preview

  • 8/13/2019 Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

    1/12

    Quarterly Journal of Engineering Geology and Hydrogeology

    doi: 10.1144/1470-9236/08-0032010, v.43; p321-331.Quarterly Journal of Engineering Geology and Hydrogeology

    F.J. BaynesSources of geotechnical risk

    serviceEmail alerting to receive free e-mail alerts when new articles cite this articlehereclick

    requestPermission to seek permission to re-use all or part of this articlehereclick

    Subscribe

    Hydrogeology or the Lyell Collection

    to subscribe to Quarterly Journal of Engineering Geology andhereclick

    Notes

    The Geological Society of London 2014

    by Rodney Xerri on January 15, 2014http://qjegh.lyellcollection.org/Downloaded from by Rodney Xerri on January 15, 2014http://qjegh.lyellcollection.org/Downloaded from

    http://www.lyellcollection.org/cgi/alertshttp://www.lyellcollection.org/cgi/alertshttp://www.geolsoc.org.uk/permissionshttp://www.geolsoc.org.uk/permissionshttp://www.lyellcollection.org/site/subscriptionshttp://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://www.lyellcollection.org/site/subscriptionshttp://www.geolsoc.org.uk/permissionshttp://www.lyellcollection.org/cgi/alerts
  • 8/13/2019 Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

    2/12

    Sources of geotechnical risk

    F.J. BaynesBaynes Geologic Pty. Ltd., 9 Chester Street, Subiaco, WA 6008, Australia

    (e-mail: [email protected])

    Abstract: The geotechnical risks that can affect projects result from a range of hazards associated

    with geological conditions and geological processes, but also from hazards associated with the

    geo-engineering process. For example, active faults identified during pre-feasibility studies will pose

    one type of hazard, whereas a management decision to limit the extent of a site investigation to save

    money will pose another type of hazard. A systematic assessment of the nature and the source of the

    various hazards may be used to differentiate the types of geotechnical risk. Examples from projects are

    provided and some statistics are presented, to indicate the rates of occurrence of the various types of

    geotechnical risks in projects. Some established approaches to managing geotechnical risks in projects

    are noted.

    Effective management of geotechnical risks is supremely

    important in many projects. In an authoritative publica-

    tion, geotechnical risk has been described as the risk tobuilding and construction work created by the site

    ground conditions (Clayton 2001). At first reading, this

    might suggest that the ground conditions are the only

    source of geotechnical risk. However, the publication

    went on to describe how geotechnical risk is created by

    both the ground conditions and the geo-engineering

    process. This is an important distinction, because the

    management of geotechnical risks created by the site

    ground conditions (essentially the geological conditions)

    may require a very different approach compared with the

    management of geotechnical risks created by the geo-

    engineering process (essentially a human endeavour).

    The terms geotechnical risk and geotechnical hazard

    are used in different ways by different researchers and it

    is difficult to find an unequivocal definition. In this

    paper the terms are used with the following meanings. A

    geotechnical risk is something associated with the

    ground that might happen and that would have adverse

    consequences for the project. The something . . . that

    might happen may also be called a geotechnical hazard.

    The geotechnical risk may be measured as the product of

    the likelihood of the geotechnical hazard occurring and

    the consequences to the project. The sources of geotech-

    nical risks are thus geotechnical hazards, in the broader

    sense of the word. It should be noted that an identifiedgeotechnical risk, like all risks, is not an inherent prop-

    erty of the ground or of an engineering process, rather it

    represents a subjective belief of the probability of a

    hazard with given consequences occurring, on the part

    of those charged with assessing the risks (Harr 1987).

    The premise of this paper is that to effectively manage

    geotechnical risks, those involved in geo-engineering

    must both appreciate the subtleties of the various types

    of geotechnical risks and understand how, where and

    why these types of geotechnical risks occur within

    projects; that is, they must understand the sources of

    geotechnical risks. This knowledge is particularlyimportant to practitioners of engineering geology, as

    they are responsible for developing the geological model

    (Fookes 1997) and they are increasingly charged with a

    responsibility for using the geological model as a funda-mental tool to assist in geotechnical risk management

    (Morgenstern 2000; Knill 2003).

    Types of geotechnical risk

    Various types of geotechnical risk have been described in

    the prolific and ever-increasing literature on the subject.

    The matter has been discussed for many years by many

    experts and the intent of this paper is not to attempt to

    review these studies but instead to provide a brief

    glimpse of three of the more incisive contributions.

    McMahon (1985) identified three main types of geo-technical uncertainty associated with geotechnical

    design, which he described as the risk of encountering

    an unknown geological condition, the risk of using the

    wrong geotechnical design criteria, and the risk of bias

    and/or variation in the design parameters being greater

    than estimated. He also identified other uncertainties

    that can affect projects, including human error, design

    changes and over-conservatism.

    Clayton (2001) noted that geotechnical risks have

    three components or impacts, which he divided into

    technical, contractual and project management. Techni-

    cal risks arise from the particular problems on the site

    such as soft ground or contaminated land, contract riskis associated with the type of contract that the developer

    adopts, and project management risks are determined by

    the way the project manager or his advisors elect to

    manage the project.

    Trenter (2003) also divided geotechnical risk into

    three interrelated categories, which are equivalent to

    Claytons three components:

    (1) design risk (equivalent to Claytons technical risk),

    which was further divided into three areas of

    uncertainty (which are somewhat equivalent to

    McMahons three main types of geotechnical

    uncertainty): uncertainty associated with the geo-logical framework (taken to be equivalent to the

    Quarterly Journal of Engineering Geology and Hydrogeology, 43, 321331 1470-9236/10 $15.00 2010 Geological Society of LondonDOI 10.1144/1470-9236/08-003

    by Rodney Xerri on January 15, 2014http://qjegh.lyellcollection.org/Downloaded from

    http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/
  • 8/13/2019 Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

    3/12

    geological model); the appropriateness of the engi-

    neering analysis; the reliability and representabilityof the engineering properties used in design;

    (2) the below-ground contract risk, because contracts

    fundamentally involve transfer of risk.

    (3) project management risk, because project managers

    are ultimately responsible for the successful man-

    agement of all of the geotechnical risks in a project.

    The basic types of geotechnical risk outlined by these

    researchers are clearly a well-accepted and useful frame-

    work and have been adopted in this paper. This frame-

    work is used to consider the relationships between the

    various types of geotechnical risk and the most likely

    sources of these types of geotechnical risk. By under-standing the sources of geotechnical risks it is possible to

    appreciate the reasons why these geotechnical risks arise.

    Discussion of types of geotechnicalrisk

    A suggested schematic relationship between the basic

    types of geotechnical risk that form the accepted frame-

    work identified in the literature is portrayed in Figure 1,

    which could be thought of as a project organizational

    structure that indicates responsibility for the manage-

    ment of the various types of geotechnical risk.In Figure 1 specific geotechnical risks form one

    obvious category of project risks and may be divided

    into technical and contractual. The term technical is

    preferred to design because some of the geotechnical

    risks in this category are associated with activities other

    than design. Technical risks can be subdivided into those

    associated with the geological model, those associated

    with the engineering analysis and those associated with

    the engineering properties used in the analysis. Each of

    these subcategories could be the responsibility of some-

    one within an organization. There are usually many

    other project risks and line management usually carriesthe responsibility for them. However, some types of

    more general geotechnical risks that relate to overall

    project implementation are the sole responsibility of

    project management, and have been indicated as such in

    Figure 1. The types of geotechnical risk portrayed in

    Figure 1 and the geotechnical hazards that are the

    sources of the risks are discussed in more detail below.

    Project management

    Identifying and managing geotechnical risks, in a general-

    ized way, is a fundamental project management activity in

    any project with a geo-engineering content. Project staff

    are responsible during both the pre-project planning phase

    and the main works construction stage for managing

    specific types of geotechnical risks, but also for managing

    the broader aspects of the project that can incur or

    mitigate geotechnical risk (e.g. overall project planning,

    construction planning, the choice of project procurement

    model, information acquisition for decision making, the

    preparation of a risk register and the responses to any

    risks that happen). Potent geotechnical risks often develop

    at a very early stage if appropriate project-wide geotech-

    nical risk mitigation measures are not implemented.

    When these risks develop it is usually because high-level

    decisions have been made by people who are over-

    worked and under-resourced and/or who do not appre-

    ciate the importance of geotechnical risks, through a

    lack of experience, education or training; those people,

    unwittingly, become the source of the geotechnical risk.

    Contractual

    Geotechnical risks are associated with contracts that

    relate to the ground conditions. Contracts involve the

    transfer of risk and, in many projects, geotechnical risks

    are transferred against some form of site investigation

    report on the basis of the information presented therein.

    Thus the quality of the site investigation report, and how

    it is communicated, plays a pivotal role in the way

    contractual geotechnical risks can develop in projects,

    particularly in respect of claims based on unforeseen

    ground conditions. Contracts usually refer to designs,

    quantities and specifications, and can also include

    measures to allocate risk and resolve disputes, so the

    quality of these aspects of the geo-engineering, and howthey are communicated, is often equally important. The

    contract will also reflect the risk allocation model for

    project procurement that has been chosen by project

    management (Eddlestonet al. 1995) (e.g. lump sum, bill

    of quantities, cost plus, etc.). When the contract and

    accompanying documentation is inadequate, the source

    of the risk must be the project staff responsible for

    managing the procurement and production of the docu-

    mentation. The reason that this occurs is usually an

    inadequate understanding of the importance of the

    geo-engineering aspects of the contract on the part of the

    project staff, or a limitation placed on those staffby ahigher-level project management decision.

    Fig 1. The relationship between the types of geotechnical riskidentified in the literature.

    F.J. BAYNES322

    by Rodney Xerri on January 15, 2014http://qjegh.lyellcollection.org/Downloaded from

    http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/
  • 8/13/2019 Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

    4/12

    Analytical

    The engineering analysis that is adopted may not reflect

    the actual failure mechanisms that occur or may be

    based on unreasonable assumptions about the system

    being analysed. If the engineering analysis is not appro-

    priate, then the source of this risk is usually the projectstaff, who are responsible for electing to use the par-

    ticular analytical method. It may be that they have

    an inadequate understanding of what would constitute

    an appropriate engineering analysis for the particu-

    lar project and ground conditions. Of course, it is

    also possible that the project staff are acting under

    instructions from project management.

    Properties

    The engineering properties used in design may not be

    reliable and may not be representative. For example,

    they may be chosen from test results which may beaffected by sample disturbance, a limited sampling pro-

    gramme, sampling or testing bias, etc. If the engineering

    properties chosen for use in design are not reliable or not

    representative, then the source of this risk is usually the

    project staff, who are responsible for the choice, and

    who probably have an inadequate understanding of

    what would constitute reliable or representative engi-

    neering properties for the particular analytical approach

    and ground conditions. Again, it is also possible that the

    project staffare acting under instructions from project

    management.

    Geological

    Geotechnical risks associated with the geological and

    geomorphological conditions are somewhat different

    from those associated with the geo-engineering process,

    as the latter is essentially a human endeavour. Uncer-

    tainty is part of geological knowledge and is best con-

    sidered relative to the concept of the geological model

    (Fookes 1997; Fookes et al. 2000; Knill 2003). It is

    suggested that within any geological model three sources

    of uncertainty can be identified. These create different

    types of geotechnical hazard that could lead to adverse

    project consequences and hence are the source of differ-ent types of geotechnical risk. The three sources of

    geotechnical risk are as follows.

    (1) Variability in the 3D distribution of geological

    units and variability in the geological characteris-

    tics of each of the units, which could be caused by

    facies changes, unconformities, folds and faults,

    weathering profiles, soil fabric, rock structure, the

    groundwater regime, etc. The potential geotechni-

    cal hazard to the project results from shortcomings

    in knowledge of what each and every part of the

    ground consists of; boreholes, test pits, mapping,

    etc. can only ever acquire information about a verysmall proportion of the total volume of ground

    being investigated. The hazard results from the

    presence of geological detail that is unforeseeable

    within the practical limits of an investigation, and

    differences between the scale of the project, the

    scale of the investigation and the scale of the

    geological features will have a profound influence

    on the extent to which this source of risk is allowed

    to develop.

    (2) The occurrence of actual hazardous geological

    conditions or processes within the ground. There

    may be uncertainty about the spatial distribution

    of some hazards; for example, a seam of asbesti-

    form mineral may be known to exist on a site and

    to be a significant health hazard if it is comminuted

    and the dust inhaled, but the exact location of that

    seam may not be known. Alternatively, there may

    be uncertainty about the temporal occurrence of

    some hazards; for example, a landslide may be

    known to exist at a certain location or an activefault might have been identified but the precise

    timing of the next movement of the landslide or the

    fault will not be known. Of course, there can be

    both spatial and temporal uncertainty with some

    hazards.

    (3) When there is an absence of knowledge of what

    might be in the ground in which the project is

    being built (and this happens regularly on major

    projects around the world), a hazard to the project

    is created because of the possibility of encounter-

    ing an unforeseen ground condition that might

    adversely aff

    ect the project.

    Unforeseen versus unforeseeable

    An important distinction exists between unforeseen

    conditions and unforeseeable ground conditions.

    Fookes (1997) and Fookes et al. (2000) have argued as

    follows.

    (1) There is very little geology or geomorphology that

    will be unforeseen on a site if the investigation is

    carried out properly. This means that if a project is

    managed in a way that implements all of the

    established techniques developed to mitigate geo-

    technical risk, and the work that is carried out is ofhigh quality, then the probability of an unforeseen

    condition being encountered during construction

    should be reduced to negligible proportions.

    (2) Nevertheless, there are some geological conditions

    that are unforeseeable, and when those con-

    ditions are encountered (they will have been antici-

    pated) there will inevitably be some undetectable

    variations in the geology that can never be com-

    pletely investigated within practical limits; for

    example, cavernous ground as a result of karst

    may be recognized but it may be impractical to

    attempt to investigate the details of every singlecavity; the details are unforeseeable.

    SOURCES OF GEOTECHNICAL RISK 323

    by Rodney Xerri on January 15, 2014http://qjegh.lyellcollection.org/Downloaded from

    http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/
  • 8/13/2019 Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

    5/12

    Types of unforeseen ground conditions

    The concept of unforeseen ground conditions is associ-

    ated with two types of geotechnical risk, as follows.

    (1) Technical risk. A truly technically unforeseen

    ground condition would be a ground condition

    encountered during construction that was not rec-ognized or anticipated at all during site investi-

    gation. An example might be if the presence of

    faulting was not anticipated and then an adversely

    oriented fault that was not identified during the

    site investigation was unexpectedly encountered in

    an excavation and caused instability, which in turn

    gave rise to cost and time over-runs. It should be

    noted that this is not the same as an unforeseeable

    condition, where the condition is anticipated but

    the detail can never be investigated.

    (2) Contractual risk. Unforeseen ground conditions

    can be those ground conditions that one party to a

    contractual dispute claim to have encountered

    when contractual geotechnical risks happen; for

    example, an adversely oriented fault may be

    encountered in an excavation and lead to instabil-

    ity, which in turn gives rise to cost and time

    over-runs, which are then the subject of a contrac-

    tual dispute. Typically in such a dispute one party

    will argue that the instability was caused by a

    ground condition that could not have been fore-

    seen and the other party will argue that it could

    have been foreseen. It would be naive to think that

    such disputes are settled solely on the basis of

    scientific facts, as a range of commercial, legal andpersonal factors will come into play. Thus, where

    unforeseen ground conditions are claimed within a

    contractual setting, they should be thought of as a

    special case of unforeseen ground conditions that

    may or may not have a basis in scientific facts.

    They can be distinguished by referring to them as

    contractually unforeseen ground conditions and

    represent a link between technical geotechnical

    risks and contractual geotechnical risks.

    Sources of geotechnical riskLike all risks, the various types of geotechnical risks are

    the product of hazard and consequence. The consequences

    to projects are similar for each type of geotechnical risk

    and consist of significant cost or time over-runs and/or

    physical failure of the facility. The hazards are any con-

    dition or process that is associated with the geology and

    geomorphology that may have adverse consequences for

    the project, and are different for each type of geotechnical

    risk. Each hazard has a primary source, which may relate

    to the geological conditions and geological processes, or

    to various aspects of the geo-engineering process.

    The types of geotechnical risks that have been dis-cussed above, the hazards that they are associated with,

    and the primary source of these hazards, are summa-

    rized in Table 1. It should be noted that because the

    various risks are interrelated, the sources are also inter-

    related. Table 1 suggests that within the three types of

    geotechnical risk identified by Clayton (2001) and

    Trenter (2003) there are only two ultimate sources of

    geotechnical risk, as follows.

    (1) Project staff responsible for the geo-engineering

    process who have an inadequate understanding of

    the ground conditions and/or who do not appreci-

    ate the importance of ground conditions. Often

    this deficit of knowledge is compounded by that of

    high-level decision makers: politicians, financiers

    and promoters who determine funding and timing

    and who probably have never even heard of geo-

    technical risk.

    (2) Geological conditions or geological processes

    that are difficult to investigate or inherently

    hazardous.

    Examples of geotechnical risks inprojects

    Examples are presented below of projects from the last

    two decades that the author has been involved in and

    that have been affected by many of the types of geotech-

    nical risks that are identified in Table 1. The authors

    role varied from project to project and the examples are

    presented anonymously, and have been modified to

    make them difficult to identify, for reasons that are fairly

    obvious.

    Project management

    A major industrial facility was being designed and built

    by a contractor. The site had been investigated by over

    300 boreholes but the work had been carried out with a

    tick the box when the geotechnical work is done

    mentality; there was no geological map or sections, no

    understanding of the geology, no awareness of the active

    geological processes and no appreciation of the geotech-

    nical risks that the project faced. Consequently, despite

    the huge amounts of information available, the follow-

    ing problems developed during construction.(1) Granular construction materials that could have

    been used in wet weather were neither identified

    nor preserved, and consequently construction

    ground to a halt during the rainy season as the

    haul roads had no pavement; construction plan-

    ning did not take into account the ground con-

    ditions.

    (2) Although noted in early investigations, the pres-

    ence of acid sulphate generating soils was not

    anticipated during design and late-stage changes

    had to be made, including protecting footings and

    treating runoff; an unreasonable analytical modelwas chosen for footing design.

    F.J. BAYNES324

    by Rodney Xerri on January 15, 2014http://qjegh.lyellcollection.org/Downloaded from

    http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/
  • 8/13/2019 Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

    6/12

    (3) Landslides were present in many parts of the site,

    reducing soil strengths to residual values and lead-

    ing to unstable cuts and fills; optimistic strength

    values were initially chosen for slope design.

    (4) Faulting affected parts of the site, resulting in deep

    weathering and low strengths requiring over-

    excavation and replacement of foundation soils;

    optimistic strength values were initially chosen for

    foundation design.

    (5) Coastal erosion occurring at rates that would

    affect facilities within their design life required

    changes to the design of port facilities; inherently

    hazardous ground conditions existed and were notrecognized.

    All of these problems affected the construction pro-

    gramme, leading to significant cost and time over-runs,

    although the facility was eventually successfully con-

    structed. Many specific geotechnical risks were encoun-

    tered on this project, but the fundamental source of the

    risk was poor project management: the significance of

    the specific geotechnical risks was not appreciated until

    too late.

    Contractual

    A contractor tendered for work that involved road cuts,a tunnel and embankment construction using clean,

    strong, durable angular rockfill won from the excava-

    tion. The total amount of rockfill available from exca-

    vation was enough to build the embankments but

    because of the complex sequencing of the construction

    and restricted access, the rockfill required double han-

    dling and longer than anticipated haul distances, and a

    claim resulted. Upon independent review of the tender

    documents, the following conclusion was drawn. The

    limited availability of rockfill from excavations could

    have been anticipated from consideration of the docu-

    mentation, site inspection and the viewing of the cores.

    However, the precise extent to which rockfill availability

    would be limited was difficult to evaluate as thedocumentation did not include geological sections or

    maps relating the proposed structure to the observed

    and interpreted geology on a chainage basis. The

    as-encountered limitations on the availability of rockfill

    could have been anticipated only with great difficulty by

    the contractor during the tender period. The claim was

    partially successful and the contractor obtained some

    financial relief.

    This is an example of contractual geotechnical risk

    caused by a well-planned and well-executed site investi-

    gation that was poorly documented and poorly pre-

    sented, and this deficiency led to difficulties in thecommunication of the ground conditions. It also

    Table 1. Sources of geotechnical risk

    !"#$ &' ($&)$*+,-*./ 0-12 3.4.56 7&85*$

    !"#$%&' )*+*,%)%+'

    !##" )*+*,%)%+' #-%+'."% ,%#/%+,.+%%".+,0"#&%11

    2+!"#$%&'#(% '"$%*+(#"$!", -. (/% !01-*(#"2% -. ,*-'"$2-"$!(!-"+"%134'.+, .+ 0##" )*+*,%)%+' #- '5% %+'."% ,%#/%+,.+%%".+, 0"#&%11 %6,6 * 7%&.1.#+ '# 138).' * '%+7%" 0".&%9.'5 +# ".1: 9%.,5'.+, -#" ,%#'%&5+.&*4 -*&'#"16

    ;#+'"*&'3*4!##" )*+*,%)%+' #- 1.'%.+ "%134'.+, .+ *+ 3+"%*1#+*84% &5#.&% #-*+*4A'.&*4 )#7%41

    !"#0%"'.%1B+"%*1#+*84% 7%1.,+ *,,"%11. #-'%+ 8%&*31% #- *+ .+*7%=3*'% 1.'%.+

  • 8/13/2019 Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

    7/12

    reflected poor project management, as the documenta-

    tion could have been better prepared if the project

    manager had appreciated the importance of getting it

    right and had allocated sufficient resources to the task.

    Analytical

    A tunnel was to be built by a design and construct

    contractor that involved excavation through rock

    beneath a palaeochannel containing permeable gravels.

    During bid preparation, the tunnel was designed to be

    drained; that is, flow of water into the tunnel was

    considered to be of no great consequence. However, softcompressible sediments occurred in the palaeochannel

    overlying the permeable gravels downstream of the

    tunnel (Fig. 2), and to prevent settlement damage occur-

    ring during construction the tunnel lining had to be

    redesigned to be less permeable and the dewatering

    effects of the tunnel had to be compensated for by

    injection wells, and large delays and costs were incurred.

    In this case an unreasonable engineering analysis was

    initially adopted that did not allow for the potential

    settlement problems associated with the geological con-

    ditions along the palaeochannel. The other type of

    geotechnical risk that occurred was associated with

    project management: the significance of the geotechnical

    risk to the project was not recognized and was not

    allowed for in the bid, and consequently the construction

    cost was underestimated. The matter ended in litigation.

    Properties

    A road involving a large amount of earthworks was

    being designed and built by a contractor. Very stiff,

    low-plasticity clays and silts had been identified and

    characterized by laboratory testing along the route, and

    earthworks with cut batters at 2h:1v were designed,

    based on average measured properties. When construc-tion started it was realized that the clays and silts were

    deeply weathered, more plastic and had softened over

    the top several metres, and that the lower shear strengths

    exhibited by only a small proportion of the tested

    samples would have to be adopted for cut batter design.

    The cut batters were flattened to 4h:1v, resulting in a

    larger volume of excavation, increased spoil requiring

    disposal and increased construction time.

    Prior to construction all of the information was avail-

    able to make the correct choice of parameters but the

    significance of the range of measured strengths was not

    appreciated and unreasonable design values were chosen.

    The unreasonable design values were chosen because the

    understanding of the ground conditions contained in the

    simple geological model illustrated by Figure 3 was not

    communicated amongst the project staff.

    Unforeseeable geological details

    A dam was being built by a government utility with

    well-developed in-house design and construction capa-

    bility. The dam was to be founded on karstic limestone

    and extensive investigations were carried out in four

    phases that involved regional mapping, aerial photo-

    graph interpretation, detailed geological mapping, hun-

    dreds of boreholes and test pits, seismic refraction

    survey, an extensive laboratory testing programme,

    grouting trials, and external review. The last phase of the

    investigation was carried out after construction was

    temporarily halted, to relocate the dam to a less hazard-

    ous position.

    Despite the amount of investigation, and the late-

    stage relocation, the utility was of the view that thereremained too many unforeseeable details of the ground

    conditions, and that this presented a significant geotech-

    nical risk (Fig. 4). A very conservative belt and braces

    design was adopted, the observational method was used

    when construction recommenced, and an extensive pro-

    gramme of monitoring and maintenance was put in

    place and continues to this day. The dam functions

    acceptably. However, there were significant cost and

    time over-runs when compared with the original cost

    estimate and schedule.

    Other types of geotechnical risks also affected the

    project. The dam was founded on an inherently hazard-ous geological condition consisting of karst limestone,

    and project management risks occurred because design

    and construction of the dam commenced before the

    investigation had been completed and before the opti-

    mum dam location had been identified.

    Inherently hazardous geological conditions

    A pipeline being built under a design and construct

    contract was located within a route corridor determined

    largely by the availability of land that could be pur-

    chased. Route options past a village included some

    poorly drained ground to the west and some gravel hillsforming a series of low linear escarpments to the east.

    Fig. 2. Block model of geological conditions in thepalaeochannel.

    F.J. BAYNES326

    by Rodney Xerri on January 15, 2014http://qjegh.lyellcollection.org/Downloaded from

    http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/
  • 8/13/2019 Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

    8/12

    After the pipeline corridor was fixed within the east-

    ern option, a site investigation was carried out and

    major active regional thrust faults were identified (Fig.

    5). Five fault crossings had to be designed and built, and

    this caused significant delays to construction.

    This geotechnical risk was an inherently hazardousground condition that was ultimately catered for in

    design. However, other types of geotechnical risks affected

    this part of the project: the lack of timely site investigation

    resulted from poor project management and led to an

    unforeseen ground condition being encountered.

    Unforeseen ground conditions

    A hydroelectric project being built using a traditional

    ownerengineercontractor approach was designed with

    an unlined pressure tunnel that required sufficient in situ

    stress to ensure high-pressure water containment(Fig. 6). It was assumed that the in situ stress at depth

    would include both a gravity and a compressive tectonic

    component. The site investigation included a range of

    boreholes and pressure tests that suggested that the

    tunnel configuration would achieve the design objective.

    However, because of the depth of the tunnel and the

    remote location, drilling did not extend down to the levelof the proposed downstream limit of the unlined tunnel

    (the upstream limit of the steel liner). During construc-

    tion, confirmatory testing in the vicinity of the power

    station indicated that the in situstresses were a lot lower

    than expected and the power station was moved several

    hundred metres further into the hillside, where the

    stresses were marginally higher. Even after the move, the

    as-constructed tunnel configuration required further

    remedial treatment to prevent leakage because the in situ

    stresses clearly did not include a sufficient compressive

    tectonic component.

    This unforeseen ground condition resulted in signifi-cant delays and increased costs to the project. With

    Fig. 3. A simple geological model illustrating the distribution of weathered and softened clays.

    Fig. 4. Dam on karstic foundations resulting in unforeseeable geological details. MFL, . . .; NMOL, . . .

    SOURCES OF GEOTECHNICAL RISK 327

    by Rodney Xerri on January 15, 2014http://qjegh.lyellcollection.org/Downloaded from

    http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/
  • 8/13/2019 Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

    9/12

    hindsight, the geological model for the area should

    have placed greater emphasis on the regional faulting

    pattern, which included normal faults, suggesting tensile

    regional tectonic stresses. Other types of geotechnical

    risks associated with project management affected the

    project. The design of the underground works was based

    on a poor understanding of the geological condition,

    and recognition of the criticality of this aspect of thedesign and the significance of the risk at an early stage

    might have alerted the project manager to the need to

    carry out more thorough investigations, and create a

    more flexible contract arrangement that allowed changes

    to the power station location.

    Rates of occurrence of geotechnicalrisk

    It is instructive to consider the rates of occurrence of

    geotechnical risks, but there is very little publishedinformation available, presumably because of a natural

    disinclination to discuss failures. Projects involving a

    significant proportion of geo-engineering can be divided

    into those where there were no significant geotechnical

    risks involved, those where significant geotechnical haz-

    ards were present but where the risks were effectively

    managed and consequences such as significant cost and

    time over-runs and physical failures did not happen, and

    those that were affected by significant cost and time

    over-runs and/or physical failures.

    Stapledon (1983) quoted studies by the International

    Commission on Large Dams that indicated that 1% of

    all major dams built between 1900 and 1965 failed

    during operation. Stapledon also estimated, based on his

    personal experience, that 20% of recently built dams had

    significant cost and time over-runs during construction

    (Stapledon 1983). Whitman (1984) indicated an annual

    probability of failure of about 220% for mine pit

    slopes and about 0.11% for foundations; presumably

    this meant physical failure, as opposed to cost and timeover-runs. McMahon (1985) collected information on

    130 major civil and mining projects developed between

    1955 and 1985 in the Australasian region and concluded

    that 36% of the projects were affected by significant

    geotechnical problems and 5% were affected by failure

    during operation. Hoek & Palmieri (1998) presented a

    review of 64 thermal and 71 hydroelectric plants and

    concluded that actual construction costs were, on aver-

    age, 27% above estimated costs and schedules were 28%

    longer than estimated. A large proportion, but not all of

    these time and cost over-runs, were attributed to geo-

    technical factors. Clayton (2001) presented a survey ofroad construction that suggested that of 49 road

    projects, 55% had a greater than 20% cost over-run. This

    author reviewed 70 geo-engineering projects that he

    was involved in and concluded that 31% had involved

    some form of significant time or cost over-run and that

    about 1% had been affected by physical failure during

    operation.

    This information suggests that geotechnical risks

    might occur at the following rates.

    (1) Physical failures of geo-engineering projects might

    occur in around 0.11% of civil projects and up to

    20% of mining projects. Presumably this illustrates

    a greater appetite for risk on the part of themanagers of mining projects.

    (2) Significant cost and time over-runs might occur in

    2050% of all projects.

    There is even less information regarding the rates of

    occurrence of specific types of geotechnical risk.

    McMahon (1985) differentiated the 47 projects that

    had been affected by significant geotechnical problems

    into his three types of technical risk and another cat-

    egory, which is taken to be akin to project management

    risk. Stapledon (1983) described 13 failures of water-

    works and Duncan (1988) described 13 personal lessons

    in what not to do from the perspective of a designengineer. The information provided by Duncan (1988)

    Fig. 5. Pipeline route options and fault trace.

    F.J. BAYNES328

    by Rodney Xerri on January 15, 2014http://qjegh.lyellcollection.org/Downloaded from

    http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/
  • 8/13/2019 Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

    10/12

    mainly concerned engineering design because he was a

    geotechnical engineer. Fookes et al. (2000) described 31

    case histories of geo-engineering failures that illustrated

    how understanding the geological model could have

    helped anticipate the cause of the failure. This author

    reviewed 70 geo-engineering projects that he was

    involved in and attempted to identify the specific type ofgeotechnical risks involved in the 22 that had had some

    form of significant time or cost over-run or physical

    failure. In the case of Fookes et al. (2000) and this

    author, a large proportion of the projects that were

    categorized involved inherently hazardous ground con-

    ditions, because they are the source of many commis-

    sions for consultant engineering geologists.

    From this information an interpretation of the rates

    of occurrence of the various types of geotechnical risk in

    projects is provided in Table 2. The information in Table

    2 does not provide a clear picture of the distribution of

    the types of geotechnical risk but suggests that both the

    ground conditions and the project staff responsible forthe geo-engineering process are a significant source of

    geotechnical risk, and that the project staffmay actually

    be the largest source. The reason why project staffare a

    significant source of geotechnical risk has been explored

    by Stapledon (1983), who identified 15 factors that

    contributed to failures. Of the 15 factors, it is of interest

    to note that most relate to people management such as

    a lack of training or knowledge on the part of project

    staff, poor project management, communication prob-

    lems, not asking the right questions, excessive work

    loads and poor quality work, and only a few relate to the

    engineering design function. Sowers (1993) reviewedapproximately 500 geotechnical failures and concluded

    that 88% reflected human shortcomings, and that this

    was a factor that could be reduced by addressing people

    management issues.

    Management of geotechnical riskwithin projects

    The implementation of projects can generally be divided

    into the idealized stages illustrated in Figure 7. Depend-

    ing upon the method of project procurement, differentparties may be responsible for different stages and the

    stages might occur in a different order. For example, if

    the project is being implemented through a traditional

    ownerengineercontractor relationship, the responsi-

    bilities for the stages will be different from if project

    implementation is through a design and construct con-

    tractor. Probably more importantly, in the case of a

    design and construct tender, the contract stage and theall-important agreement of the price of the project often

    occurs after only a preliminary investigation and hence

    the bid price is fixed when only limited information is

    available, a classic way in which a project management

    decision can generate geotechnical risk.

    The idealized project stages can usually be identified

    even when different project procurement methods are

    employed, and the literature on geotechnical risk clearly

    describes the established techniques that are available to

    manage the risks during each of the idealized project

    stages. These include the following.

    (1) The use of risk registers for overall management of

    the geotechnical risks (Clayton 2001; Trenter 2003).

    (2) An adequate and comprehensive site investigation

    (Stapledon 1983; Fookes 1997).

    (3) A multistage approach to the site investigation and

    an experienced multidisciplinary team to carry out

    the work (Stapledon 1983; Fookes 1997; Fookes

    et al. 2000).

    (4) The use of different types of reports to systemati-

    cally convey the findings of the site investigation to

    the contractor (Knill 2003; van Staveren & Knoeff

    2004).

    (5) Peer review at critical hold points for the project

    (Stapledon 1983; Baynes et al. 2005).(6) The adoption of the observational method during

    construction (Fookes 1997; Fookes et al. 2000;

    Knill 2003).

    (7) Contract flexibility that allows the contractor to be

    paid for work that needs to be done (Fookes et al.

    2000; Clayton 2001).

    (8) The use of a contract that fairly allocates geotech-

    nical risk between the owner and the contractor

    (Eddlestonet al. 1995).

    (9) The use of residual risk registers to manage risks

    during operation (Clayton 2001; Knill 2003).

    (10) The adoption of a total engineering geologyapproach, where a lot of effort is applied to

    Fig. 6. Cross-section showing underground arrangement and topography; no vertical exaggeration; elevation in metres.

    SOURCES OF GEOTECHNICAL RISK 329

    by Rodney Xerri on January 15, 2014http://qjegh.lyellcollection.org/Downloaded from

    http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/
  • 8/13/2019 Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

    11/12

    understanding the geology and defining and docu-

    menting baseline or reference conditions at the

    earliest possible opportunity (Knill 2003; van

    Staveren & Knoeff, 2004; Baynes et al. 2005).

    The relationship in time between when these estab-

    lished techniques should be used and the idealized

    project stages is illustrated in Figure 7.

    Unfortunately, the established techniques are seldom

    fully adopted in practice, because of cost and time

    pressures and inept or inexperienced management. The

    consequence of not fully adopting the established tech-

    niques is the manifestation of uncontrolled geotechnical

    risk.

    Conclusions

    (1) If past performance can provide a guide to what

    will happen in the future, then the likelihood of

    experiencing a significant geotechnical risk in the

    form of a cost or time over-run on a major projectis somewhere between 20 and 50%.

    (2) Similarly, the likelihood of a physical failure is

    much less, maybe less than 1 or 2% for civil

    projects and up to 20% for mining projects.

    (3) Geotechnical risks can be divided into those

    associated with project management and those

    that relate to technical and contractual matters.

    Technical risks can be subdivided into those

    associated with the geological model, those associ-

    ated with the engineering analysis and those

    associated with the engineering properties used in

    analysis. The risks associated with the geologicalmodel can be divided into those associated with

    unforeseeable geological details, those associated

    with inherently hazardous ground conditions and

    those associated with unforeseen ground con-

    ditions.

    (4) Available information suggests that the ground

    conditions and the project staffresponsible for the

    geo-engineering process are both significant

    sources of geotechnical risk and that the project

    staffmay actually be the largest source.

    (5) Project staffcan be educated and trained to man-

    age and mitigate the geotechnical risks, rather than

    generate them.

    (6) The ground conditions cannot be changed, but

    competent engineering geologists can advise how

    projects can be engineered to overcome risks

    associated with the geological model.

    (7) Effective geotechnical risk management techniques

    for different project stages are clearly described in

    the literature. The single greatest challenge is to

    manage the project in a way that incorporates all

    of these established techniques and obtains the

    maximum benefit from their use.

    Acknowledgements.I am grateful to A. Moon and P. Fookesfor their many thoughtful comments and contributions to thisT

    ab

    le2.Ratesofoccurrence(givenasperc

    entages)oftypesofgeotechnicalriskinprojects

    Ultimatesource,andhazard

    McMahon(1985);47

    projectswith

    problems*

    Stapledon(1983);13

    failuresofwaterworks

    Duncan(1988);

    13

    personallesson

    s

    Fookesetal.(2000);

    31casehistories

    illustratinggeological

    models*

    Autho

    rsrecordsof22

    p

    rojectswith

    problems*

    Proj

    ectstaff

    Poormanagementofentiregroundengine

    ering

    process

    25

    38

    95

    Poormanagementofsiteinvestigationand

    co

    ntract

    n.a.

    46

    73

    Unr

    easonableanalyticalmodelchosen

    22

    62

    46

    64

    Unr

    easonabledesignvalueschosen

    58

    15

    46

    6

    32

    Groundconditions

    Unforeseeabledetailsofgroundconditions

    n.a.

    59

    Inherentlyhazardousgroundconditions

    n.a.

    7

    68

    73

    Unforeseengroundconditions

    33

    8

    29

    73

    n.a.,

    thiscategorywasnotusedbyMcMahon.

    *Th

    efrequenciesadduptomorethan100%becausesomeprojectsencounteredmoretha

    nonetypeofproblem.

    Itshouldbenotedthat18%oftheprojectsin

    volvedallofthetypesofrisk.

    F.J. BAYNES330

    by Rodney Xerri on January 15, 2014http://qjegh.lyellcollection.org/Downloaded from

    http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/
  • 8/13/2019 Quarterly Journal of Engineering Geology and Hydrogeology-2010-Baynes-321-31

    12/12

    paper, and also to two anonymous reviewers who took the

    time to comment on this paper so constructively. The views

    expressed here are my own.

    References

    B, F.J., F, P.G. & K,J.F. 2005. The totalengineering geology approach applied to railways in thePilbara, Western Australia. Bulletin of EngineeringGeology and the Environment, 64, 6794.

    C,C.R.I.2001.Managing Geotechnical Risk: ImprovingProductivity in UK Building and Construction. ThomasTelford, London.

    D, J.M. 1988. Prediction, design and performance ingeotechnical engineering.In: Fifth AustraliaNew ZealandConference on Geomechanics,Sydney. Institution of Engi-neers Australia, Canberra, 112.

    E,M., M, R.E.& W,S.1995. The roleof the engineering geologist in construction. In:E,M., W,S., C,J.C.& C,M.G.(eds)Engineering Geology of Construction. Geologi-cal Society, London, Engineering Geology Special Publi-

    cations, 10, 389401.F, P.G. 1997. The First Glossop Lecture, geology forengineers: the geological model, prediction and perform-ance. Quarterly Journal of Engineering Geology, 30, 293424.

    F, P.G., B, F.J. & H, J.N. 2000. Totalgeological history: a model approach to the anticipation,observation and understanding of site conditions. In:GeoEng 2000 Conference, Melbourne Australia, Vol. 1.Technomic, Lancaster, PA, 370460.

    H,M.E.1987.Reliability-based Design in Civil Engineering.Dover, New York.

    H,E.& P,A.1998. Geotechnical risks on large civilengineering projects.In: M,D.P.& H,O.(eds)Proceedings of the 8th Congress of the InternationalAssociation for Engineering Geology and the Environment,Vancouver, Vol. 1. Balkema, Rotterdam, 7988.

    K, J.L. 2003. Core values: the First Hans Cloos lecture.Bulletin of Engineering Geology and the Environment, 62,134.

    MM, B.K. 1985. Geotechnical design in the face ofuncertainty. Journal of the Australian GeomechanicsSociety, 10, 719.

    M,N.R.2000. Common ground.In: GeoEng 2000Conference, Melbourne Australia, Vol. 1. Technomic,Lancaster, PA, 120.

    S, D.H. 1983. Towards successful waterworks. In:Proceedings of the Symposium on Engineering for Damsand Canals. Institution of Professional Engineers, NewZealand, 1.31.15.

    S, G.F. 1993. Human factors in civil and geotechnicalfailures. ASCE Journal of Geotechnical Engineering, 119,238256.

    T,N.2003. Understanding and containing geotechnicalrisk.Proceedings of the Institution of Civil Engineers: CivilEngineering, 156, 4248, Paper 12706.

    S,M.T. & K, J.G. 2004. The geotechnicalbaseline report as a risk allocation tool. In: H, R.,A, R. & C, R. (eds) Engineering Geology

    for Infrastructure Planning in Europe. Springer, Berlin,777785.

    W, R.V. 1984. Evaluating calculated risk in geo-technical engineering. ASCE Journal of GeotechnicalEngineering, 110, 145188.

    Received 4 March 2008; accepted 3 March 2010.

    Fig. 7.The management of geotechnical risk at the various project stages (indicated at the top of the figure and progressing in timefrom left to right).

    SOURCES OF GEOTECHNICAL RISK 331

    by Rodney Xerri on January 15, 2014http://qjegh.lyellcollection.org/Downloaded from

    http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/http://qjegh.lyellcollection.org/