Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
1
Quarter 4: 2016
Environment and Community
Terramin Australia Ltd
October - December: 2016
Quarterly Environment Report
2
EXECUTIVE SUMMARY
This Quarterly Environment Report (QER) for the Angas Zinc Mine (AZM) summarises the results of the
environmental monitoring program between October and December 2016, undertaken as part of the Mine’s
Programme for Environmental Protection and Rehabilitation (PEPR).
Terramin Australia Ltd ceased mining operations at AZM on September 30th
, 2013, with the site placed into a
Care and Maintenance phase.
This QER reflects the environmental monitoring requirements outlined in the Mine Care and Maintenance Plan
(MCMP), which has been approved by the Department for State Development (DSD) on the 23rd
March 2015.
Whilst the reduced level of the TSF decant pond surface is no longer a compliance limit, the level was surveyed
at 68.56m RL, as of the 24th
December. The surface area of the TSF decant pond was surveyed at 13,952m2 on
the 24th
December an in compliance. During December, the site experienced an unseasonal amount of rainfall
(93.7mm vs average of 25.6mm) this resulted in an increase in the water surface area. Additional pumps were
switched on to expand the sprinkler system and increase evaporation capacity. The surface area reduced
within seven days to under 15,000m2, as outlined by the outcome and measurable criteria tables. Overall,
2016 has been the wettest year, as well as the wettest December on record in Strathalbyn since 1992,
receiving 76.9mm over the month (BOM, 2017).
There are no non-compliances against Lease Condition Outcomes for Quarter 4, 2016.
During the quarter the DSD, EPA and DEWNR reviewed the closure Outcome Measureable Criteria tables and
provided feedback for finalisation of the Angas Mine Closure Plan. The company undertook the final drafting,
editing and internal management review of the document and incorporated it into the approved Program for
Environmental Protection and Rehabilitation (PEPR).
DSD regulators Kyle Rice, Antonia Scrase and Assessment Officer Paul Thompson conducted a quarterly
compliance visit on 24th
November and observed the site to be compliant. An SCCC meeting was held on
Thursday, 24th
November at Angas Zinc Mine and reported on the site’s compliance over quarter 3. This
feedback was incorporated into a review for the extension of ML6229 requested by Terramin in May 2016
prior to the original term expiring.
The Terramin management review of the Angas Zinc Mine Closure Plan has been completed and was
submitted to the DSD for review on 20th
January 2017.
Cover photo: Western Paddock SEB vegetation with Lignum in the foreground
3
TABLE OF CONTENTS
Executive Summary ................................................................................................................................................ 2
Background ............................................................................................................................................................. 5
1. Mining and Mine Void Acid and Metalliferous Drainage ................................................................................ 5
2. Surface Water ................................................................................................................................................. 6
3. Groundwater .................................................................................................................................................. 7
4. Noise ............................................................................................................................................................... 8
5. Public Health and Nuisance ............................................................................................................................ 8
High Volume Sampler – Compliance Criteria ..................................................................................................... 8
Dust Deposition Gauges – Leading Indicator Criteria......................................................................................... 9
Total Insoluble Matter .................................................................................................................................... 9
Lead .............................................................................................................................................................. 10
6. Waste Disposal and Hazardous Substances ................................................................................................. 12
7. TSF Water / Acid Mine Drainage .................................................................................................................. 12
TSF Decant Pond Reduced Level ...................................................................................................................... 12
TSF Seepage Drain Flows .................................................................................................................................. 12
TSF Surface Area .............................................................................................................................................. 12
TSF Groundwater Monitoring Bores ................................................................................................................ 13
TSF PAF testwork results .................................................................................................................................. 14
8. Community Engagement .............................................................................................................................. 16
Strathalbyn Community Consultation Committee (SCCC) ............................................................................... 16
Complaints Register ......................................................................................................................................... 16
9. Miscellaneous News ..................................................................................................................................... 16
10. Summary.................................................................................................................................................. 16
11. References ............................................................................................................................................... 17
12. Appendix A – Angas Zinc Mine – Filled and unfilled voids ...................................................................... 18
13. Appendix B – Water Monitoring Locations ............................................................................................. 19
14. Appendix C – Surface Water Monitoring Data ........................................................................................ 20
15. Appendix D – Groundwater Monitoring Data ......................................................................................... 21
4
Groundwater Quality Raw Data ....................................................................................................................... 21
Groundwater Quality Graphs ........................................................................................................................... 22
16. Appendix E – Groundwater Standing Water Levels ................................................................................. 25
17. Appendix F – Dust Monitoring Locations ................................................................................................ 26
18. Appendix G – Dust Leading Indicator Data – Dust Deposition Gauges ................................................... 27
Total Insoluble Matter...................................................................................................................................... 27
Offsite Lead Measurements ............................................................................................................................. 28
Onsite Lead Measurements ............................................................................................................................. 29
19. Appendix H – Compliance Criteria – HiVol .............................................................................................. 31
Total SolId Particulate Measurements ............................................................................................................. 31
PM10 measurements ....................................................................................................................................... 32
Lead measurements ......................................................................................................................................... 32
20. Appendix I – TSF ...................................................................................................................................... 34
Decant Pond reduced level throughout Care and Maintenance ..................................................................... 34
Seepage Drain Flows ........................................................................................................................................ 35
21. Appendix J – TSF Monitoring Bores ......................................................................................................... 36
22. Appendix K – TSF Seepage Drains ............................................................................................................ 40
5
BACKGROUND
This is the final QER for 2016 and represents the period from October to December 2016 (Quarter 4). This
report is prepared for the Strathalbyn Community Consultative Committee (SCCC), the Department of State
Development (DSD) and the Terramin Board of Directors. This document reports on Terramin’s status against
the measurable criteria outlined in the approved Mine Care and Maintenance Plan (23rd
March 2015)
submitted as an addendum to the PEPR in July 2014.
1. MINING AND MINE VOID ACID AND METALLIFEROUS DRAINAGE
Production ceased at the Angas Zinc Mine (AZM) on the 30th
of September 2013.
As part of the ongoing Acid and Metalliferous Drainage management strategy the mine void has been allowed
to refill with groundwater seep. In order to speed up the process of filling the void and mitigate potential
oxidisation, additional water, sourced from onsite bores was pumped into the mine void.
During this time the water has been monitored for level and pH. The water level of the mine void measured
61.3m AHD on the 24th
December 2016. An increased from 59.57m AHD on the 27th
September 2016.
Figure 1 Mine Void Recharge against STEDS wells (LG1/LG2), DH2 and PF140
The STEDS wetland is currently full, locally recharging the tertiary aquifer and providing a potential pressure
difference of approximately 7.5 metres, between the wetland and the mine void pond, thus water is still being
drawn towards the mine void. Water has been detected in the screened levels of the STEDS wetland bores LG1
and LG2 for the first time since June 2009. Water levels in LG1 and LG2 will be added to the level monitoring
programme and used to monitor the groundwater conditions. Monitoring water levels of bores both near the
mine void, DH2, DH3 and the Pastefill line (which targets the 140m RL decline void), as well as the regional
groundwater bores continues.
01
/01
/20
16
22
/01
/20
16
12
/02
/20
16
04
/03
/20
16
25
/03
/20
16
15
/04
/20
16
06
/05
/20
16
27
/05
/20
16
17
/06
/20
16
08
/07
/20
16
29
/07
/20
16
19
/08
/20
16
09
/09
/20
16
30
/09
/20
16
21
/10
/20
16
11
/11
/20
16
02
/12
/20
16
23
/12
/20
16
13
/01
/20
17
50
52
54
56
58
60
62
64
66
68
70
m A
HD
Rainfall DH2 PF140 Mine Void LG1 - Tertiary LG2 - Cambrian
LG1/LG2 Water
Level
6
Figure 2 Matt Daniel dipping the water level of LG1 and LG2 in the STEDS wetland
2. SURFACE WATER
Surface water sampling was undertaken at Hogben and Croser in October 2016. Statistical paired t-testing for
means revealed no significant difference between upstream (Hogben) and downstream (Croser).
Table 1: Surface water assay results and t-test values
Site Units Croser 1
Croser 2
Croser 3
Mean Croser
Hogben 1
Hogben 2
Hogben 3
Mean Hogben p-value t-value
pH pH 8.09 7.87 7.98 7.98 7.83 8.02 8.02 7.95666
7 0.867 4.303
EC us/c
m 1530 1460 1430 1473.33
3 1350 1350 1350 1350 0.053 4.303
TDS mg/L 853 810 827 830 786 791 813 796.666
7 0.187 4.303
Turbidity NTU 8 8 7 7
Under detection limits
SO4-D mg/L 51 43 43 45.6666
7 43 41 43 42.3333
3 0.300 4.303
As-T mg/L 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 Under detection
limits
Cd-T mg/L 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 Under detection
limits
Cu-T mg/L 0.002 0.002 0.002 0.002 0.011 0.002 0.002 0.005 0.423 4.303
Pb-T mg/L 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 Under detection
limits
Mn-T mg/L 0.028 0.028 0.028 0.028 0.023 0.025 0.026 0.02466
7 0.063 4.303
Se-T mg/L 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 Under detection
limits
Zn-T mg/L 0.005 0.005 0.009 0.00633
3 0.005 0.006 0.005 0.00533
3 0.580 4.303
Fe-T mg/L 0.57 0.6 0.59 0.58666
7 0.52 0.56 0.6 0.56 0.287 4.303
7
Site Units Croser 1
Croser 2
Croser 3
Mean Croser
Hogben 1
Hogben 2
Hogben 3
Mean Hogben p-value t-value
NOX-N mg/L 0.04 0.04 0.04 0.04 0.04 0.05 0.05 0.04666
7 0.184 4.303
TKN-N mg/L 0.8 0.9 0.6 0.76666
7 0.8 0.7 0.8 0.76666
7 1.000 4.303
N-T mg/L 0.8 0.9 0.6 0.76666
7 0.8 0.8 0.8 0.8 0.742 4.303
P-T mg/L 0.06 0.09 0.15 0.1 0.07 0.07 0.07 0.07 0.374 4.303
3. GROUNDWATER
The environmental monitoring plan outlined in the Care and Maintenance Plan for Angas Zinc Mine requires,
where access is possible, quarterly monitoring of RG1, RG2, RG3, RG4, RG5, RG7 and RG8. The weekly water
level monitoring of DH2 for three months after water has been detected in the well has been completed,
however, regular monitoring of DH2, DH3 and the 140 RL Pastefill line has continued throughout the quarter.
RG1, RG4 and RG8 did not exceed the drawdown beyond a one-metre band of 2006 levels, which is shown in
Figure 3, Figure 4 and Figure 5 below. Water levels in RGs 1, 4 and 8 in October have all risen, in response to
the rainfall received throughout the catchment during the preceding quarter (see graph against rainfall in
Appendix E). Regional groundwater recharge has occurred in the district, with a nearby private bore also
recording an increase in recharge compared to previous years (SWL of 68.33m AHD in March 2016 to 68.87m
AHD in January 2017, an increase of 0.54m over the year.
Water quality measurements undertaken in October for the quarter demonstrate a continuity of the patterns
of most parameters from previous quarters in RG1, RG4 and RG8, and are all significantly within leading
indicator limits and thus also PEPR compliance limits.
Land access was not available for RG2 and RG3. RGs 5 and 7 remain dry.
Figure 3 Standing Water Level for RG1
0
2
4
6
8
10
12
Jan-16 Apr-16 Jul-16 Oct-16
Me
tre
s b
elo
w g
rou
nd
leve
l
RG1 Baseline SWL Criteria
Under detection limits
8
Figure 4 Standing Water Level for RG4
Figure 5 Standing Water Level for RG8
4. NOISE
As outlined in the Care and Maintenance addendum to the PEPR (approved March 2015), noise monitoring has
ceased through the Care and Maintenance phase. There were no noise related complaints received
throughout the quarter.
5. PUBLIC HEALTH AND NUISANCE
The HVS measures lead, TSP and PM10 levels over a 24 hour period every three days. In addition to the HVS,
twelve Dust Deposition Gauges (DDGs) remain installed both onsite and offsite and sampled monthly for Total
Insoluble Matter (TIM) and lead. Locations of all dust monitors can be seen in Appendix F.
Compliance criteria remains as per the PEPR criteria. Leading indicators require an investigation as to the
source of the dust and remain as per the PEPR requirements.
Throughout the quarter there has been no public health or nuisance PEPR non-compliances (Appendix H).
HIGH VOLUME SAMPLER – COMPLIANCE CRITERIA
26.5
27
27.5
28
28.5
29
29.5
Jan-16 Apr-16 Jul-16 Oct-16M
etr
es
be
low
gro
un
d le
vel
RG4 Baseline SWL Criteria
4
5
6
7
8
9
Jan-16 Apr-16 Jul-16 Oct-16
Me
tre
s b
elo
w g
rou
nd
leve
l
RG8 Baseline SWL Criteria
9
Throughout the quarter there has been no instance of particulate lead, PM10 or TSP levels above the PEPR
compliance criteria (Appendix H).
DUST DEPOSITION GAUGES – LEADING INDICATOR CRITERIA
Acknowledging that the dust deposition gauges are not a compliance measure, results are reported for
completeness.
TOTAL INSOLUBLE MATTER
Throughout the quarter there were 9 instances of Total Insoluble Matter (TIM) exceeding the leading indicator
criteria. 6 of these instances are located alongside paddocks which have been harvested in the recent season
(DDGs 3, 12, 10 and 9), with November being a particularly busy month for agricultural activities.
During the quarter, earthworks in neighbouring properties to the east & south of the ML provided additional
potential dust sources, which is the likely cause of DDG 7 data in October.
With no active mining activities onsite through the quarter, it is likely these TIM increases are linked to
neighbouring agricultural and landfill activities on neighbouring properties surrounding the ML.
Average wind direction was 226 degrees at 15km/hr for October, 207 degrees at 13km/hr for November and
194 degrees at 12km/hr in December. Of the ten wettest days during the quarter included six of the windiest
days on average. See Figure 6.
All DDG dust data is located in Appendix G.
Table 2 Rainfall and wind speed/direction for windiest AZM days
Date Average of Degrees Average of km/hr Rainfall - mm
28/12/2016 227.5521 17.86125 64.43
27/12/2016 87.70833 9.94125 14.59
3/10/2016 282.0625 25.9875 11.46
21/10/2016 225.8958 16.5 10.5
11/11/2016 187.875 8.59875 9
4/10/2016 267.3646 23.38125 8.11
30/10/2016 265.5833 25.26 5.91
2/10/2016 270.1875 24.64875 5.06
9/10/2016 206.8854 22.59375 4.94
8/12/2016 237.5417 25.665 4.56
Table 3 Wind speed/direction and rainfall averages for Q3
Month Average of wind degrees Average wind speed of km/hr Sum of Rainfall - mm
October 225.8040995 15.12689516 62.81
November 207.2881615 12.72454605 17.36
December 194.281922 11.73931818 93.73
Total 209.1446904 13.17093225 173.9
10
Figure 6 Total Insoluble Matter for Q3 diagram
LEAD
There were no instances of lead deposition exceeding the leading indicator criteria onsite during quarter 4.
Offsite, there continued to be instances of lead deposition exceeding the leading indicator criteria to the north
of the former AZM operating area. As can be seen in Figure 7 below, the ML is surrounded by agriculture,
which is predominantly cropping. Gauges which are returning a higher than the leading indicator criteria lead
deposition are located next to agricultural fields which were reaped during quarter 4 and within the vicinity of
a recorded highly mineralised zone with an average of around 400mg/kg lead in the upper Tertiary soils – see
Figure 8. Overview of the historic offsite lead deposition rates in Appendix G shows no material change in lead
deposition over the life of the project to date.
There were no instances of lead deposition above the compliance limit of 0.5ug/m3.month, measured by the
high volume dust sampler.
All DDG dust data is located in Appendix G.
11
Figure 7 Landuse and Dust Deposition Gauges 2016
12
Figure 8 Lead concentrations in soil surrounding the ML overlain with local geology
6. WASTE DISPOSAL AND HAZARDOUS SUBSTANCES
There was no waste removed from site throughout the quarter outside of normal roadside council collection
bins.
7. TSF WATER / ACID MINE DRAINAGE
TSF DECANT POND REDUCED LEVEL
The reduced water level of the decant pond was surveyed to be 68.56m RL, equating to a surface area of
13,952m2, on the 24
th December 2016, within the compliance limit of 15,000m
2. Graph for the quarter is
included in Appendix I.
TSF SURFACE AREA
The surface area of the TSF decant pond was surveyed at 13,952m2 on the 24
th December.
Overall, 2016 has been the wettest year, as well as the wettest December on record since 1992 (BOM, 2017).
After the rainfall received in between Christmas and New Year, Terramin started a secondary pump with its
own evaporation sprinkler line to increase evaporation volume. This was in place is to manage the predicted
increasing occurrence of low pressure bands and associated rainfall events. The Bureau of Meteorology
13
Climate Outlooks tool predicts a 75% chance of Strathalbyn receiving between 25 and 50mm of rain between
February and April and this pump will assist in managing this forecasted rainfall.
TSF SEEPAGE DRAIN FLOWS
The seepage drain flows in the TSF have remained significantly lower when compared to the operational phase
of the mine. This pattern can be expected to continue while AZM remains in Care and Maintenance and the
TSF water volumes are low. As seen in Figure 9 below, flows have decreased as the pressure head from the TSF
decant pond has reduced due to evaporation and the reduced depth of the decant pond due to the tailings
disposition from the sprinkler system. On the 16th
December, seepage flows were approximately 2L/minute –
see Figure 9.
Seepage drain flows since the TSF was commissioned are located in Appendix I.
Figure 9 Seepage drain flows for TSF through the Care and Maintenance phase to date
TSF GROUNDWATER MONITORING BORES
TSF bores were sampled and analysed monthly through quarter 3.
Standing water levels of TSF A, B and D have risen over the preceding 6 months (June to December) in line with
the increased rainfall received in the Strathalbyn region, as shown in Figure 10.
All bores (TSF A, B and D) reported concentrations at levels all below the leading indicator criteria for the
quarter.
0
1
2
3
4
5
6
7
Oct
-13
De
c-1
3
Feb
-14
Ap
r-1
4
Jun
-14
Au
g-1
4
Oct
-14
De
c-1
4
Feb
-15
Ap
r-1
5
Jun
-15
Au
g-1
5
Oct
-15
De
c-1
5
Feb
-16
Ap
r-1
6
Jun
-16
Au
g-1
6
Oct
-16
De
c-1
6
Litr
es/
min
ute
Drain 1 Drain 2 Drain 3 Drain 4 Drain 5 Total Flow (L/min)
14
Figure 10 Standing Water Level of TSF bores against rainfall
TSF PAF TESTWORK RESULTS
The acid testwork on the tailings dam surface advised by O’Kane Consultants (Review of Terramin’s AZM
MCMP, 2013) was undertaken in December 2016. O’Kane advised quarterly testwork for the initial 12 months,
and on the basis of the results have now revised the testwork regularity to be undertaken biannually. The next
round of test work will be completed in June 2017.
The International Framework for Acid Prevention (INAP) Global Acid Rock Drainage Guide (“GARD Guide”)
provides the following commentary regarding the evolution of AMD:
The chemical reaction representing pyrite oxidation requires three basic ingredients: pyrite, oxygen, and
water. The overall pyrite oxidation reaction generally is written as:
FeS2 + 7/2O2 + H2O = Fe2+ + 2SO4
2- + 2H
+
However, oxygen dissolved in water can also result in pyrite oxidation but due to its limited solubility in water,
this process is much less prominent. Aqueous ferric iron can oxidize pyrite as well according to the following
reaction:
FeS2 + 14Fe3+ + 8H2O = 15Fe
2+ + 2SO4
2- + 16H
+
The December testwork demonstrated a continuing of trends towards more acidic, both at surface and at
depth. This is to be expected, as oxidation of pyrite (FeS2) occurs naturally when exposed to atmospheric
conditions, such as air or water. With the increased percolation in the top section of the tailings due to rainfall
events and the sprinkler evaporation system operating on the TSF, this has resulted in a slightly accelerated
acidification of the tailings at the surface within the TSF, as can be seen in Figure 12. The material sampled at
depth (400-700mm), is more neutral in pH, than at the TSF surface. This is because pore space is reduced as
compared to the shallower samples which can be more easily disturbed by meteorological and anthropogenic
conditions (typically to a depth of 100mm) and are hence more compressed. Pore space, O2, H2O and AMD is
conceptualised in Figure 11, as taken from Figure 2-11 of the GARD Guide.
0
20
40
60
80
100
120
140
160
1800
1
2
3
4
5
6
7
8
9
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Sep
-15
Oct
-15
No
v-1
5
Dec
-15
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
Dec
-16
Met
ers
bel
ow
su
rfac
e
Rainfall TSF A TSF B TSF D
15
Figure 11 Pore space and AMD
Figure 12 TSF PAF Testwork results overtime
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
pH
(fie
ld)
1 - 100 1 - 700 2 - 100 2 - 700 3 - 100
3 - 700 4 - 100 4 - 700 5 - 100 5 - 700
6 - 100 6 - 700 7 - 100 7 - 700 8 - 100
8 - 700 9 - 100 9 - 700 10 - 100 10 - 700
11 - 100 11 - 700 12 - 100 12 - 700 13 - 100
13 - 700 16 - 100 16 - 700 Average Linear (Average)
16
8. COMMUNITY ENGAGEMENT
STRATHALBYN COMMUNITY CONSULTATION COMMITTEE (SCCC)
An SCCC meeting was held on the 24th
November 2016 and reported to the SCCC AZM’s status against
Outcome Measurable Criteria, derived from lease conditions for ML6229.
The meeting was held at the Angas Zinc Mine and included a site tour. Members of the committee reviewed
the condition of the TSF, revegetation success in the Western Significant Environmental Benefit area and the
low lying evaporation - silt retention area that has the potential for growing native basket weaving reeds which
is an interest for local historians.
Chairperson Kelvin Trimper has requested the CCC submit suggestions to Terramin as to how best to present a
summary of the Closure Plan. To date, no suggestions have been received. Terramin will submit a summary of
the Closure Plan to the CCC prior to the CCC meeting scheduled for the 16th
February.
Chairperson Kelvin Trimper tabled a written Chairperson’s report for SCCC members, reporting on his quarterly
activities for Q2. Terramin confirmed the validity of the existing waivers put in place under ML6229, as
requested at the previous CCC meeting held in May 2016. The Committee also agreed to view the Closure Plan
after the plan has been reviewed by DSD experts and approved by the DSD. Terramin will provide a summary
document upon completion and provide this to the SCCC, media and wider public.
COMPLAINTS REGISTER
No complaints were received through Terramin’s hotline or lodged with the Environmental and Community
Superintendent throughout Q4 of 2016.
9. MISCELLANEOUS NEWS
DSD conducted a quarterly compliance visit on 24th
November and observed the site to be compliant. The
compliance visit was accompanied by members of DSD, including Mine Closure Regulator Antonia Scrase, Site
Regulator Kyle Rice, and Site Assessment Officer Paul Thompson. The review incorporated the inspection for
recommendation for the extension of ML6229. Terramin submitted the request for extension of the lease as
per Mining Act 1971 – Parts 6, 6A and 8 in May 2016 in the 3 months prior to the end of the lease term.
Hillgrove continued to clean-up and maintenance the area which they have been leasing over the preceding 24
months. This work is envisaged to continue throughout Q1:2017.
10. SUMMARY
Angas Zinc Mine continued to be maintained through the Care and Maintenance period:
The continuation of the Care and Maintenance Environmental Monitoring Plan;
The process plant, including crusher, mill and floatation areas, received regular maintenance;
Onsite water management, plant upkeep, rehabilitation vegetation and SEB areas maintained.
Hillgrove staff remained onsite 1-2 days per week to clean and repair the concentrate shed;
There were no non-compliances against Lease Condition Outcomes for Quarter 4, 2016.
The SCCC continue to meet quarterly.
17
11. REFERENCES
INAP. (2014). The International Network for Acid Prevention Global Acid Rock Drainage Guide, Revision 1.
Bureau of Meteorology. (2017). Climate Data Online for Strathalbyn, 023747. www.bom.gov.au.
18
12. APPENDIX A – ANGAS ZINC MINE – FILLED AND UNFILLED VOIDS
19
13. APPENDIX B – WATER MONITORING LOCATIONS
20
14. APPENDIX C – SURFACE WATER MONITORING DATA
Date Oct-16
Site Units
Croser 1
Croser 2
Croser 3
Mean Croser
Hogben 1
Hogben 2
Hogben 3
Mean Hogben p-value t-value
pH pH 8.09 7.87 7.98 7.98 7.83 8.02 8.02 7.956667 0.867 4.303
EC-L us/cm 1530 1460 1430 1473.333 1350 1350 1350 1350 0.053 4.303
TDS-180 mg/L 853 810 827 830 786 791 813 796.6667 0.187 4.303
Turbidity NTU 8 8 7 7 Under detection
limits
SO4-D mg/L 51 43 43 45.66667 43 41 43 42.33333 0.300 4.303
As-T mg/L 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 Under detection
limits
Cd-T mg/L 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 Under detection
limits
Cu-T mg/L 0.002 0.002 0.002 0.002 0.011 0.002 0.002 0.005 0.423 4.303
Pb-T mg/L 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 Under detection
limits
Mn-T mg/L 0.028 0.028 0.028 0.028 0.023 0.025 0.026 0.024667 0.063 4.303
Se-T mg/L 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 Under detection
limits
Zn-T mg/L 0.005 0.005 0.009 0.006333 0.005 0.006 0.005 0.005333 0.580 4.303
Fe-T mg/L 0.57 0.6 0.59 0.586667 0.52 0.56 0.6 0.56 0.287 4.303
NOX-N mg/L 0.04 0.04 0.04 0.04 0.04 0.05 0.05 0.046667 0.184 4.303
TKN-N mg/L 0.8 0.9 0.6 0.766667 0.8 0.7 0.8 0.766667 1.000 4.303
N-T mg/L 0.8 0.9 0.6 0.766667 0.8 0.8 0.8 0.8 0.742 4.303
P-T mg/L 0.06 0.09 0.15 0.1 0.07 0.07 0.07 0.07 0.374 4.303
____ Under detection limits
21
15. APPENDIX D – GROUNDWATER MONITORING DATA
GROUNDWATER QUALITY RAW DATA
Date Criteria Leading
Indicator
October 2016
Site Units RG1 RG4 RG8
pH pH 8.70 8.15 7.71 7.85 7.94
EC-L uS/cm 68500 53670 10800 11000 29300
TDS mg/L 25000 24843 6290 6170 19400
As-T mg/L 0.090 0.038 711 526 2050
Cd-T mg/L 0.0100 0.004 <0.001 0.001 <0.001
Pb-T mg/L 0.820 0.262 <0.0001 0.0002 0.0001
Zn-T mg/L 4.400 1.704 0.001 <0.001 <0.001
Se-T mg/L 0.130 0.088 0.019 0.013 0.017
Fe-T mg/L 232.00 69.02 0.02 0.02 <0.01
22
GROUNDWATER QUALITY GRAPHS
0.00
2.00
4.00
6.00
8.00
10.00
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16
pH
un
its
pH
RG1 RG4 RG8 PEPR Criteria
0
20000
40000
60000
80000
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16
us/
cm
EC
RG1 RG4 RG8 PEPR Criteria
0
5000
10000
15000
20000
25000
30000
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16
mg/
L
TDS
RG1 RG4 RG8 PEPR Criteria
23
0
0.02
0.04
0.06
0.08
0.1
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16
mg/
L As
RG1 RG4 RG8 PEPR Criteria
0
0.002
0.004
0.006
0.008
0.01
0.012
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16
mg/
L
Cd
RG1 RG4 RG8 PEPR Criteria
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16
mg/
L
Pb
RG1 RG4 RG8 PEPR Criteria
24
0
1
2
3
4
5
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16
mg/
L Zn
RG1 RG4 RG8 PEPR Criteria
0
50
100
150
200
250
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16
mg/
L
Fe
Fe Fe Fe Fe
0
0.02
0.04
0.06
0.08
0.1
0.12
0.14
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16
mg/
L
Se
RG1 RG4 RG8 PEPR Criteria
25
16. APPENDIX E – GROUNDWATER STANDING WATER LEVELS
PEPR criteria is no drawdown further than 1m from baseline data values obtained in 2006 (outlined below)
PEPR Criteria (m)
RG1 9.64 RG4 29.15 RG8 8.56
0
20
40
60
80
100
120
140
160
180
2000
5
10
15
20
25
30
35
Rai
nfa
ll/m
on
th (
mm
)
SWL
(m)
Rainfall RG1 RG1 PEPR criteria RG4 RG4 PEPR Criteria RG8 RG8 PEPR Criteria
26
17. APPENDIX F – DUST MONITORING LOCATIONS
27
18. APPENDIX G – DUST LEADING INDICATOR DATA – DUST DEPOSITION GAUGES
TOTAL INSOLUBLE MATTER
NB: High levels of insoluble matter picked up in gauges 6, 3, 12 and 10 in November and in gauge 12 in December are thought to be related to off-site agricultural
harvesting to the north of the site. November and December are typically harvesting months.
0
5
10
15
20
25
30
35
40
7 5 4 2 8 1 6 9 11 3 12 10
g/m
2.m
on
th
Gauge number
Total Insoluable Matter
Oct-16 Nov-16 Dec-16
28
OFFSITE LEAD MEASUREMENTS
Figure 13 Historic offsite lead deposition
NB: Gauges 2, 3, and 10 are off-site to the north, prevailing winds for the period were Westerly. Due to no activity on the mine site, elevated levels are due to agricultural
activity in the area and the natural levels of lead in the soils in the area. The leading indicator is 150mg/kg, Terramin and government records show natural soil levels are
often higher than 150mg/kg in these paddocks.
0
200
400
600
800
1000
1200
1400Ja
n-0
8
Ap
r-0
8
Jul-
08
Oct
-08
Jan
-09
Ap
r-0
9
Jul-
09
Oct
-09
Jan
-10
Ap
r-1
0
Jul-
10
Oct
-10
Jan
-11
Ap
r-1
1
Jul-
11
Oct
-11
Jan
-12
Ap
r-1
2
Jul-
12
Oct
-12
Jan
-13
Ap
r-1
3
Jul-
13
Oct
-13
Jan
-14
Ap
r-1
4
Jul-
14
Oct
-14
Jan
-15
Ap
r-1
5
Jul-
15
Oct
-15
Jan
-16
Ap
r-1
6
Jul-
16
Oct
-16
Lead
de
po
siti
on
(m
g/kg
)
Offsite Lead Measurements
2 3 10 11 12
29
ONSITE LEAD MEASUREMENTS
NB: Gauge 9 is situated on the southern boundary adjacent to a cropped field, additional dust levels are attributed to agricultural activity, Leading indicator is 750mg/kg.
0.000
100.000
200.000
300.000
400.000
500.000
600.000
700.000
800.000
900.000
1000.000
Oct-16 Nov-16 Dec-16
mg/
kg
Onsite Lead Deposition
1 4 5 6 7 8 9
30
31
19. APPENDIX H – COMPLIANCE CRITERIA – HIVOL
TOTAL SOLID PARTICULATE MEASUREMENTS
0
20
40
60
80
100
120
1402
/10
/20
16
8/1
0/2
01
6
14
/10
/20
16
20
/10
/20
16
26
/10
/20
16
1/1
1/2
01
6
7/1
1/2
01
6
13
/11
/20
16
19
/11
/20
16
25
/11
/20
16
1/1
2/2
01
6
7/1
2/2
01
6
13
/12
/20
16
19
/12
/20
16
25
/12
/20
16
31
/12
/20
16
ug/
m3
Western Unit PEPR Criteria
32
PM10 MEASUREMENTS
LEAD MEASUREMENTS
0
0.1
0.2
0.3
0.4
0.5
0.6
µg/
m³
PEPR criteria Northern Unit
33
0
0.1
0.2
0.3
0.4
0.5
0.6µ
g/m
³
PEPR criteria Northern Unit
34
20. APPENDIX I – TSF
DECANT POND REDUCED LEVEL THROUGHOUT CARE AND MAINTENANCE
10.0
20.0
30.0
40.0
50.0
60.0
60.00
62.00
64.00
66.00
68.00
70.00
72.00
74.00
76.00
78.00
1/1
1/2
013
1/1
2/2
013
1/0
1/2
014
1/0
2/2
014
1/0
3/2
014
1/0
4/2
014
1/0
5/2
014
1/0
6/2
014
1/0
7/2
014
1/0
8/2
014
1/0
9/2
014
1/1
0/2
014
1/1
1/2
014
1/1
2/2
014
1/0
1/2
015
1/0
2/2
015
1/0
3/2
015
1/0
4/2
015
1/0
5/2
015
1/0
6/2
015
1/0
7/2
015
1/0
8/2
015
1/0
9/2
015
1/1
0/2
015
1/1
1/2
015
1/1
2/2
015
1/0
1/2
016
1/0
2/2
016
1/0
3/2
016
1/0
4/2
016
1/0
5/2
016
1/0
6/2
016
1/0
7/2
016
1/0
8/2
016
1/0
9/2
016
Rain
fall (
mm
/day)
Red
uced
Lev
el (m
)
Angas Mine Rainfall Records
Rainfall Actual Water level RL(m) Spillway RL (m) Target RL
35
SEEPAGE DRAIN FLOWS
0
1
2
3
4
5
6
7O
ct-1
3
No
v-1
3
De
c-1
3
Jan
-14
Feb
-14
Mar
-14
Ap
r-1
4
May
-14
Jun
-14
Jul-
14
Au
g-1
4
Sep
-14
Oct
-14
No
v-1
4
De
c-1
4
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Sep
-15
Oct
-15
No
v-1
5
De
c-1
5
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Litr
es/
min
ute
Drain 1 Drain 2 Drain 3 Drain 4 Drain 5 Total Flow (L/min)
36
21. APPENDIX J – TSF MONITORING BORES
5.5
6
6.5
7
7.5
8
8.5
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
pH
pH
TSFA TSFB TSFD Leading indicator Leading indicator
0
5000
10000
15000
20000
25000
30000
35000
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
EC (
uS/
cm)
EC
TSFA TSFB TSFD Leading Indicator
37
TSF B has recorded cadmium under detection limits since January 2010
0
0.005
0.01
0.015
0.02
0.025
0.03
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
As
(mg/
L)
Arsenic
TSFA TSFB TSFD LeadingIndicator
0
0.001
0.002
0.003
0.004
0.005
0.006
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
Dec
-16
Cd
(m
g/L)
Cd
TSFA TSFB TSFD LeadingIndicator
38
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Pb
(m
g/L)
Lead
TSFA TSFB TSF D Leading Indicator
0
0.5
1
1.5
2
2.5
3
3.5
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Zinc
TSFA TSFB TSF D Leading Indicator
Zn (
mg/
L)
39
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Mn
(m
g/L)
Manganese
TSFA TSFB TSFD
0
20
40
60
80
100
120
140
160
180
200
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Fe (
mg/
L)
Iron
TSFA TSFB TSFD LeadingIndicator
40
22. APPENDIX K – TSF SEEPAGE DRAINS