95
i QUANTIFYING INCREMENTAL OIL PRODUCTION AND ECONOMICS OF USING INTELLIGENT COMPLETION AS A TOOL FOR RESERVOIR MANAGEMENT BY BENTIL NANA ESI BENYIWA A THESIS SUBMITTED TO THE AFRICAN UNIVERSITY OF SCIENCE AND TECHNOLOGY ABUJA - NIGERIA IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE AWARD OF MASTER OF SCIENCE IN PETROLEUM ENGINEERING SUPERVISOR: PROF. DAVID O. OGBE MAY 2013

QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

i

QUANTIFYING INCREMENTAL OIL PRODUCTION AND ECONOMICS OF USING

INTELLIGENT COMPLETION AS A TOOL FOR RESERVOIR MANAGEMENT

BY

BENTIL NANA ESI BENYIWA

A THESIS

SUBMITTED TO THE AFRICAN UNIVERSITY OF SCIENCE AND TECHNOLOGY

ABUJA - NIGERIA

IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE AWARD OF MASTER

OF SCIENCE IN PETROLEUM ENGINEERING

SUPERVISOR: PROF. DAVID O. OGBE

MAY 2013

Page 2: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

ii

QUANTIFYING INCREMENTAL OIL PRODUCTION AND ECONOMICS OF USING

INTELLIGENT COMPLETION AS A TOOL FOR RESERVOIR MANAGEMENT

By

Bentil Nana Esi Benyiwa

RECOMMENDED:

Prof. David O. Ogbe – Committee Chair

Prof. Wumi Iledare – Committee Member

Dr. Alpheus Igbokoyi – Committee Member

APPROVED:

Prof. Godwin Chukwu

Chair, Department of Petroleum Engineering

Prof. Wole Soboyejo

Provost, African University of Science and Technology

Date

Page 3: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

iii

DEDICATION

To my Mum and Dad, Madame Grace Abassah and Mr. Joseph Bentil

Page 4: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

iv

ACKNOWLEDGEMENT

Firstly, I am grateful to the Almighty God for the blessings throughout my program at the

African University of Science and Technology (AUST).

I acknowledge and appreciate the effort of my supervisor, Prof. David O. Ogbe for his assistance

and guidance throughout this thesis. My gratitude also goes to my thesis committee members,

Prof. Wumi Iledare and Prof. Alpheus Igbokoyi for their contributions to this work.

I am grateful to my mum, Madame Grace Abassah and my Dad, Mr Joseph Bentil for their

support throughout my program.

Finally, I would acknowledge all the distinguished lecturers that I encountered during my

program and friends who contributed to the success of this work.

Page 5: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

v

ABSTRACT

Huge amount of hydrocarbon in place is left unrecovered. Integrated reservoir management, in

addition to the use of new technologies improves hydrocarbon recovery. Intelligent completion is

one of the technologies which enhance reservoir management thereby improving the

hydrocarbon recovery.

This work presents a review of intelligent completion technology, guidelines to evaluate the

decision whether or not to implement intelligent completion and evaluates field cases of

intelligent completion installation.

The case studies were derived from four fields where intelligent completions have been

implemented. Comparison of intelligent completion with non-intelligent completion was based

on ease of data acquisition for reservoir management, incremental oil production and

profitability criteria. The yard sticks used for economic analysis include the net present value,

discounted payout period, profitability index and growth rate of return.

The results from the study show that reliable intelligent completion improves reservoir

management by enabling data acquisition and well monitoring. Employing intelligent well

completions in reservoir management can lead to 21% to 38% increase in oil recovery and 17%

to 41% increase in NPV compared to non-intelligent completion. It must be pointed out that

intelligent system failure may render intelligent completion projects economically unattractive.

The results of this study can be used to evaluate the feasibility of executing an intelligent

completion project; especially in fields were intelligent completion is yet to be implemented as a

tool for reservoir management.

Page 6: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

vi

TABLE OF CONTENT

DEDICATION ............................................................................................................................... iii

ACKNOWLEDGEMENT ............................................................................................................. iv

ABSTRACT .................................................................................................................................... v

TABLE OF CONTENT ................................................................................................................. vi

LIST OF FIGURES ....................................................................................................................... ix

LIST OF TABLES ......................................................................................................................... xi

CHAPTER 1 ................................................................................................................................... 1

INTRODUCTION .......................................................................................................................... 1

1.1 INTRODUCTION ................................................................................................................. 1

1.2 STATEMENT OF THE PROBLEM .................................................................................... 3

1.3 OBJECTIVES OF THE STUDY .......................................................................................... 4

1.4 SCOPE OF STUDY .............................................................................................................. 4

1.5 ORGANIZATION OF THESIS ............................................................................................ 5

CHAPTER 2 ................................................................................................................................... 6

2.1 LITERATURE REVIEW ...................................................................................................... 6

2.2 RESERVOIR MANAGEMENT ......................................................................................... 11

2.3 INTELLIGENT WELL COMPLETION ............................................................................ 14

2.4 CLASSIFICATION OF MONITORING SYSTEMS ........................................................ 17

2.5 COMPONENTS OF IWC ................................................................................................... 18

2.6 APPLICATIONS AND BENEFITS OF IWC .................................................................... 19

Page 7: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

vii

CHAPTER 3 ................................................................................................................................. 24

METHODOLOGY ....................................................................................................................... 24

3.1 INTRODUCTION ............................................................................................................... 24

3.2 RESERVOIR DATA ACQUISITION AND MANAGEMENT ........................................ 26

3.3 WELL PERFORMANCE ................................................................................................... 27

3.4 TIME VALUE OF MONEY AND ECONOMIC ANALYSIS .......................................... 32

CHAPTER 4 ................................................................................................................................. 37

RESULTS AND DISCUSSION OF CASE STUDIES IN RESERVOIR MANAGEMENT........ 37

4.0 INTRODUCTION .............................................................................................................. 37

4.1 ASSUMPTIONS COMMON TO ALL FOUR CASE STUDIES ..................................... 37

4.2 CASE STUDY 1: COMMINGLED PRODUCTION FROM A TWO-LAYER

OFFSHORE FIELD ................................................................................................................. 38

4.3 CASE STUDY 2: MULTI-LATERAL PRODUCER-INJECTOR PATTERN OFFSHORE

FIELD ....................................................................................................................................... 45

4.4 CASE STUDY 3: TRIPLE COMINGLED PRODUCTION – USARI FIELD OFFSHORE

NIGERIA .................................................................................................................................. 52

4.5 CASE STUDY 4: HORIZONTAL WELL PRODUCTION – OSEBERG FIELD

OFFSHORE NORWAY ........................................................................................................... 59

CHAPTER 5 ................................................................................................................................. 67

CONCLUSIONS AND RECOMMENDATIONS ........................................................................ 67

5.1 SUMMARY AND CONCLUSIONS.................................................................................. 67

5.2 RECOMMENDATIONS .................................................................................................... 68

Page 8: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

viii

NOMENCLATURE ..................................................................................................................... 69

REFERENCES ............................................................................................................................. 71

APPENDIX ................................................................................................................................... 76

Page 9: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

ix

LIST OF FIGURES

Figure 2.1: Reservoir management (Adapted from Satter et al., 1994) ........................................ 12

Figure 2.2: Reservoir management process (Fowler et al., 1996) ................................................ 13

Figure 2.3: Schematics of IWC (adopted from Sakowski, 2005) ................................................. 15

Figure 2.4: Intelligent wells installation trend from all providers (Eni Group, 2006) .................. 16

Figure 3.1: Workflow used for reservoir and economic analysis of IWC .................................... 25

Figure 3.2: Detailed Step-by-Step Procedure for Reservoir and Economic analysis of IWC

application (Adapted from Sakowski, Anderson and Furui, 2005) .............................................. 26

Figure 4.1: Production performance from the IWC and the conventional well............................ 40

Figure 4.2: NPV sensitivity analysis for both IWC and conventional well .................................. 42

Figure 4.3: Tornado charts of the NPV for the IWC and the conventional well .......................... 43

Figure 4.4: Cumulative discounted net cash flow versus time ..................................................... 43

Figure 4.5: Oil production history from both completions (Ajayi et. al, 2006) ............................ 46

Figure 4.6: Oil production performance for the two scenarios ..................................................... 48

Figure 4.7: NPV sensitivity analysis for both completions .......................................................... 50

Figure 4.8: Tornado chart of the NPV for both wells ................................................................... 50

Figure 4.9: Cumulative discounted net cash flow versus time ..................................................... 51

Figure 4.10: Development well path (Brock et al., 2006) ............................................................ 53

Figure 4.11: Production history from the IWC for Case Study 3 (Brock et al., 2006) ................. 53

Page 10: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

x

Figure 4.12: Oil production forecast for Case Study 3 ................................................................. 55

Figure 4.13: Spider and Tornado charts of the NPV .................................................................... 56

Figure 4.14: Sensitivity analysis of the NPV ................................................................................ 57

Figure 4.15: Cumulative discounted net cash flow versus time ................................................... 57

Figure 4.16: Production performance in both wells...................................................................... 62

Figure 4.17: Tornado charts of the NPV for both wells ............................................................... 64

Figure 4.18: Sensitivity on NPV for both completions................................................................. 64

Figure 4.19: Cumulative discounted net cash flow versus time for both wells ............................ 65

Figure B1: NPV certainty analysis for IWC ................................................................................. 78

Figure B2: NPV uncertainty analysis for Conventional Completion ........................................... 79

Figure B3: Spider Chart for both completions .............................................................................. 80

Figure C1: NPV uncertainty analysis for IWC ............................................................................. 80

Figure C2: NPV uncertainty analysis for NON -IWC .................................................................. 81

Figure D1: NPV uncertainty analysis for IWC ............................................................................. 82

Figure E1: NPV uncertainty analysis for IWC ............................................................................. 83

Figure E2: NPV uncertainty analysis for NON -IWC .................................................................. 83

Figure E3: Spider Chart for both completions .............................................................................. 84

Page 11: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

xi

LIST OF TABLES

Table 3.1: Some correlations used in the industry ........................................................................ 30

Table 3.2: Arp’s equations ............................................................................................................ 30

Table 4.1: Variable distribution input ........................................................................................... 38

Table 4.2: Stochastic variable input parameter distribution for Case Study 1 .............................. 39

Table 4.3: Summary of results for Case Study 1 .......................................................................... 44

Table 4.4: Stochastic variable distribution of input parameters for Case Study 2 ........................ 47

Table 4.5: Summary of results for Case Study 2 .......................................................................... 51

Table 4.6: Summary of results obtained for Case Study 3 ........................................................... 58

Table 4.7: Stochastic variable distribution of input parameters of Case Study 4 ......................... 60

Table 4.8: Summary of the results for Well B-21B ...................................................................... 65

Table A1: NPV calculation for IWC ............................................................................................ 76

Table A2: NPV calculation for Conventional Completion ........................................................... 77

Page 12: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 1

CHAPTER 1

INTRODUCTION

1.1 INTRODUCTION

Reserves are the main asset of the exploration and production (E&P) industry. Every E&P firm

aims at maximizing its total profit in the long run, hence the industry aims at enhancing ultimate

recovery of a field, cost efficiently. However, most of the hydrocarbons in place are not

recovered; about 35% of hydrocarbons in place are recovered leaving behind the remaining 65%.

The need to improve recovery from the huge amount of remaining hydrocarbons in place around

the world requires sound reservoir management practices.

Integrated reservoir management is a continuous process and the key to successful operation of

the reservoir throughout its entire life. It requires the use of both multi-disciplines and

technological resources for maximizing profit. A comprehensive reservoir management plan

involves depletion and development strategies, data acquisition and analyses, geological and

numerical model studies, production and reserves forecasts, knowledge of facilities requirement

and economic optimization. These can facilitate better reservoir management which will enhance

economic recovery of hydrocarbons (Satter et al., 1994). Intelligent well completion forms part

of the overall vision of reservoir management optimization.

An intelligent well completion (IWC) is completion system capable of measuring, transmitting

and analyzing wellbore production, reservoir and completion integrity data, and enabling remote

action; change valve chokes and optimize these parameters to better control reservoir, well and

production processes (Eni, 2006 ). The concept of intelligent completion does not generally refer

Page 13: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 2

to any capability for automated self-control but rather manual interface to initiate instructions to

the well (Robinson, 2007).

Reservoir parameters are continuously monitored for each zones with permanent pressure and

temperature gauges, base on which the valve chokes are reconfigured to allow simultaneous

production from more zones through a single string or well. Remote completion monitoring is

the ability of a system to provide data, obtained in or near the wellbore, without requiring access

and entry for conventional intervention to the well. Hence IWC technology provides great

flexibility in the operation of conventional wells and multilateral wells; as each branch of the

well can be controlled independently. (Yeten et al., 2004)

The basic element of IWC are acquisition and transmission system, flow control valves (FCV)

and actuation system. The acquisition and transmission system is a set of equipment used to

transmit and acquire reservoir data, while the FCVs control flow rate from a zone or in a level.

And the actuation system is a set of equipment that supplies power to the valves (Eni, 2006)

Compared to conventional completions, IWC offers great benefits. The primary objectives of

IWC are normally to maximize or optimize and anticipate oil recovery, control gas and water

breakthrough, reduce cost and improve safety. Zero intervention especially subsea or remote

location wells and production optimization for multi zones reservoir (simultaneous production),

horizontal wells, complex reservoir structure, auto gas lift, etc. justifies the installation of

intelligent completions (Eni, 2006).

Full benefits of IWCs are reservoir specific; it depends on reservoir quality, production rates,

fluid contacts, gas and water coning. The control lines, cables and sensors represent the nervous

Page 14: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 3

and circulatory system of an IWC and damage to these elements may result in partial or total loss

of its function. There could be the risk of system failure, for instance with sand control, there

could be erosion of choke elements, seal surfaces, control lines and interference with device

movement. High reliability of intelligent completion is necessary for avoiding workover

operations whereas monitoring and measuring of downhole reservoir data and choking ability are

important to reach production optimization throughout the entire life of a reservoir. (Robinson,

2007)

This work compares conventional completions with intelligent well completions by analyzing

case studies of some reservoirs where intelligent completions have been installed.

1.2 STATEMENT OF THE PROBLEM

This study is designed to answer the following questions:

For the reservoir under consideration,

What extent does IWC improve data acquisition in reservoir management?

What extent does IWC improve reservoir performance, in terms of oil production/,

recovery, water and gas production control?

Is the use of IWC economically viable?

Page 15: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 4

1.3 OBJECTIVES OF THE STUDY

The objectives of this study are:

To quantify the incremental oil production from the application of IWC as a reservoir

management tool

To ascertain the economic viability of IWC compared to non-intelligent completion

To guide reservoir management team in the decision to use intelligent completion or not

1.4 SCOPE OF STUDY

The case studies presented in this work described the analyisis of four (4) reservoirs where IWC

has been employed. The analysis considered reservoir performance - production and recovery,

water/gas production control and economics or cost implication – OPEX, CAPEX and

profitability indicators such as Net Present Value (NPV), Payout period (PO), Growth Rate of

Return (GRR) and Profitability Index (PI).

Monte-Carlo simulation and sensitivity analysis are carried out using Crystal Ball (Oracle, 2012)

to account for the project risks in the economic analysis.

Page 16: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 5

1.5 ORGANIZATION OF THESIS

This thesis is divided into five chapters. Chapter 1 introduces the problem of this study, the

objectives and the scope of the study. Chapter 2 discusses literature review of related studies

previously done on this problem and reviews the concept of reservoir management and

intelligent well systems. Chapter 3 discusses the methodology, which describes how the selected

reservoirs are analyzed for the justification of the use of intelligent well completion. Chapter 4

focuses on the results and discussion of the results of the study. And finally, the conclusion and

recommendations are covered in Chapter 5.

Page 17: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 6

CHAPTER 2

2.1 LITERATURE REVIEW

Since 1997, when the first intelligent well (IW) was installed in Saga Snorre TLP North Sea-

Norway, intelligent well technology has been used in many kinds of production wells all over the

world, including off-shore wells, vertical conventional wells, horizontal wells and multilateral

wells. Before 1997, all wells were completed with a common completion including hydraulically

sliding sleeves and tubing. The evolution of downhole gauges, sliding sleeves and surface

controlled subsurface safety valves resulted in the development of intelligent wells. (Dekui et al.,

2012)

From 1997, several studies have been published to demonstrate the importance of the application

and benefits of intelligent well completion (IWC), especially for multiple reservoirs where

commingled production is the main production strategy (Jalali et al., 1998; Lucas et al., 2001).

The application and potential benefits of IWC for production from a single reservoir have been

demonstrated in several studies (Yu et al., 2000; Yeten and Jalali, 2001; Jansen et al., 2002;

Valvatne et al., 2003).

Sharma (2002) presented a method to apply real options theory to quantify the value of

intelligent well applications, including the value of reducing project volatility and risk. He

described how mathematical model can be incorporated into a larger workflow process to assess

entire asset portfolios which can be used as a tool for screening reservoir assets for potential

IWC applications and also help optimize the design of the completion.

Yeten et al. (2004) determined the optimal performance of IWs using gradient based

optimization technique in conjunction with a reservoir simulator. They considered the effect of

Page 18: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 7

uncertainty in reservoir description and equipment reliability and noted that downhole control

can compensate to some extent for geological uncertainty, even when there is the possibility of

equipment failure. They also noted that, the impact of equipment reliability was related to both

the timing and type of failure; generally the earlier the valves failed the larger the negative

impact.

Vachon and Furui (2005) illustrated how IWC can enhance the electrical submersible pump

(ESP) performance and add flexibility by using downhole chokes to optimize ESP performance.

Their study focused on single ESP wells producing from multiple pay zones. It was established

that the intelligent completion systems with remotely controlled chokes allow for optimal

production rates, maintain the optimum ESP operating range and reduce risk of pump failure.

Thus, IWC eliminates the expense of intervention and the associated loss in production, due to

extended ESP life, reduction of cost of replacing damaged pumps and pump down time.

Sakowski (2005) looked at the impact of intelligent well completions on total economics of field

development. Reservoir performance analysis and economic evaluation tools were used to

quantify the value of IWC. IWC projects performed better in relatively cost sensitive

environments since they can maintain oil production while reducing the capital and operating

costs. He noted that the ability to respond to expected changes in reservoir performance is also a

valued benefit and the technology has advanced rapidly from more high-cost, offshore

application environment to more revenue-sensitive operating environment due to the ability to

clearly demonstrate economic value of IWC over alternate conventional completions.

Aggrey et al. (2006) employed a synthetic reservoir to explore and compare the value of

extensive, accurate measurements with a higher chance of system failure with the deployment of

Page 19: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 8

lower resolution sensors of greater reliability. A methodology to calculate the value of

information and expected opportunity loss parameters for IWC of different capabilities was

developed. It was shown that value creation from IWC and real time optimization is strongly

dependent on the ability of the system to function properly throughout the equipment’s specified

lifetime.

Aggrey and Davies (2007) presented an enabler for IWC decision making process where

stochastic coupling of the reliability profile and reservoir performance is employed. The

proposed workflow allows the inclusion of conventional stochastic analysis for economic and

geologic risks. The evaluated scenarios showed increased value potential for IWC

implementation.

Addiego-Guevara et al. (2008) investigated whether simple reactive control strategies based on a

feedback loop between inflow control valve (ICV) settings and surface or downhole

measurements can enhance production and mitigate reservoir uncertainty if they are designed to

work across a range of production scenarios. The implementation of an intelligent horizontal

well in a thin oil rim reservoir in the presence of reservoir uncertainty was assessed. They

evaluated the benefit of using two completions in conjunction with surface and downhole

monitoring. It was found that reactive control strategy can insure against reservoir uncertainty.

However, a simple reactive control strategy using variable ICVs adjusted in response to

downhole measurements of phase flow rates yielded a neutral or positive return regardless of

reservoir behavior. They suggested that downhole reservoir imaging techniques which can

monitor fluid flow and saturation changes at a distance from the well may be used in a proactive

feedback loop.

Page 20: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 9

Pari et al. (2009) presented a comprehensive review of state-of-the-art intelligent well

technology considering the benefits, types of sensors, challenges, economics and application in

fractured reservoir. They concluded that IWC aids reservoir management although there could be

the risk of system failure. To mitigate the risk of system failure, the use of cable-less power and

communication system in IWC was recommended.

Grebenkin and Davies (2010) conducted a study on the impact of geological uncertainty and

uncertainty in the dynamic parameters such as fluid contacts, relative permeability, aquifer

strength and zonal skin on the flow control ability of an IW to reduce the production uncertainty.

The results emphasized the importance of the probabilistic approach for production prediction

and illustrated its use as a tool to justify the installation of IW technology in a particular well. It

was found that the uncertainty of the dynamic parameters had a higher impact on the total oil

production than uncertainty associated with reservoir geology.

Rodriguez and Figueroa (2010) evaluated the applicability of multi-purpose intelligent

completions for high productive oil reservoir from both the productivity and the operational

standpoints. They noted that IWC in naturally fractured mature fields tends to increase oil

production and reduce the field decline. As water production increases, the producing zones can

be shut off as needed to reduce the overall production of water. Hence IWC will improve the life

cycle value of mature field.

Hudson et al. (2011) reviewed case studies of about thirty (30) oil and gas production fields

containing IWs to consider the work process that was used to justify the incremental investment

in hardware and installation cost. The study outlined key findings from the review,

recommended a project-stage-base modeling workflow and presented opportunities for

Page 21: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 10

improvements to support more rigorous and efficient design decisions. They noted that IWC

justification is typically attributed to reduction of lifecycle costs, accessing marginal reserves and

certain reservoir management concerns and suggested that IWC modeling workflow requires

multi-disciplinary collaboration and sometimes require simulation experts to handle reservoir

uncertainties.

Dekui et al. (2012) considered some advanced downhole devices and the prospects for IW

application in the Daqing oil field. It was concluded that IWs improves oil recovery and reservoir

management. IW technology was effective in Daqing oil field, average water cut decreased from

89% to 70% and average oil production increased by 40%.

Gulyaev et al. (2012) noted that IW is an important part of production technology from low and

extremely low permeable reservoirs. IW equipment with remote downhole control significantly

increased well construction cost but with tax reduction the oil production from such reservoirs

become economical.

Griffith et al. (2012) evaluated IW system at the Saramacca oil fields. Well performance was

monitored monthly based on the volume flow test and flowing bottomhole pressure (BHP)

measurements. Downhole pressure data was also collected for build up tests and other reservoir

studies. It was concluded that IWC offers several advantages over the conventional well.

Barreto et al. (2012) presented a methodology to optimize production using water cut as a

parameter to shut down wells and IWC as a variable of the optimization process and as an

economic indicator to evaluate well completion efficiency. The results show the importance of a

Page 22: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 11

good estimation of the time to shut down wells and completions to reach the optimum production

potential of the reservoir.

2.2 RESERVOIR MANAGEMENT

The need to enhance recovery from the huge amount of remaining hydrocarbon around the world

requires a sound reservoir management practice which is a continuous process throughout the

entire life of a reservoir.

In the past, non-integrated reservoir management was practiced only when a major expenditure is

planned, but during the last 20 years emphasis has been put on integrated reservoir management

where there is full coordination of geologists, geophysicists and petroleum engineers to advance

petroleum exploration, development and production (Satter et al., 1994).

There are many papers with different definitions of reservoir management. Satter, describe

reservoir management as the use of available human, technological and financial resources to

maximize profits from a reservoir by optimizing recovery while minimizing capital investments

and operating expenses. Reservoir management is carried out purposefully to control operations

in order to obtain the maximum possible economic recovery from a reservoir on the basis of

facts, information and knowledge (Thakur, 1996). Technological advances and computer power

provide tools for better reservoir management. A team approach based on integration of

geosciences and engineering personnel, tools, technology and data are essential for sound

reservoir management practice (Satter et al., 1994). Figure 2.1 illustrates schematics of reservoir

management.

Page 23: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 12

Figure 2.1: Reservoir management (Adapted from Satter et al., 1994)

Reservoir management does not refer to a high-tech approach to improving production in large

reservoirs and it is not an optional activity because every reservoir has to be managed. Reservoir

management practices involve goal setting, planning, implementing, monitoring, evaluating and

revising initial plans throughout the entire life of a reservoir from exploration to abandonment

(Fowler et al., 1996). Figure 2.2 presents a schematic illustration of reservoir management

process.

TECHNOLOGY

DATA

TOOLS

PEOPLE

Page 24: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 13

Figure 2.2: Reservoir management process (Fowler et al., 1996)

No

Yes

No

Yes

Monitor Reservoir

Management Plan Predictions

Monitor Business and

Technology Environment

End Points or

Anomalies

Encountered?

New

Developments

Applicable?

Implement Reservoir

Management Plan

Reservoir

knowledge

Business

Environment

Knowledge

Technologies

Knowledge

Construct (or Revise) Reservoir Management Plan

of Appropriate Scale and Scope

Page 25: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 14

Intelligent well completion (IWC) forms part of the overall vision of reservoir management and

automation system. Reservoir management using intelligent completions enables better

understanding of the reservoir, resulting in improved reserves recovery. For a complex reservoir,

completion design in terms of monitoring and control are better handled with intelligent

completions compared to conventional completions. Intelligent wells implementation in a major

project requires the joint effort of many disciplines, an integrated workflow that systematically

integrates the contributions from various disciplines throughout the lifecycle of the project which

is the key to success (Lau, 2008).

2.3 INTELLIGENT WELL COMPLETION

Intelligent wells completion (IWC) can provide reservoir control through continuous monitoring

and valve actuation in real-time, capable for transmitting, collection and analyzing wellbore,

production, reservoir and completion integrity data allowing remote control of reservoir, well

and production processes without requiring access and entry for conventional intervention to the

well (Robinson,2007). Downhole sensors and control devices are combined with a surface or

subsurface unit for production optimization; the systems are programmed to optimize a given

parameter such as net production by varying for example the inflow profile from various zones.

(Robinson, 2007)

IWC consists of packers, hydraulic and/or electrical control lines, inflow control valves, and a

surface control unit. The packers isolate the individual zones along the well path. The inflow

control valve (ICV) enables choking or shutting different zones according to performance like

drawdown, water cut, gas-oil-ratio, etc. The control lines are used for power transmission to the

ICV and transfer of monitored downhole data like pressure and temperature. The surface control

Page 26: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 15

unit is used for handling all the monitored data and for remote operation of the downhole inflow

control valves. There are IWC with infinitely variable chokes and extensive monitoring like

pressure, temperature, sand detectors, multi-phase metering, and resistivity and seismic sensors

for tracking near well fluid contacts (Erlandsen, 2000). Figure 2.3 illustrates schematic of IWC.

Figure 2.3: Schematics of IWC (adopted from Sakowski, 2005)

Robinson (2007) reported that until the late 1980s, remote monitoring was generally limited to

surface pressure transducers around the tree and surface choke, with remote completion control

Page 27: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 16

restricted to the hydraulic control of safety valves and (electro-) hydraulic control of tree valves.

Data are now transmitted to remote offices and interpreted from the well site. Recent and

developing remote monitoring and control capabilities include: multiphase flow measurement;

chemical composition and sand detection; multiple sensors and flow monitoring; remote-control

gas-lift valves, flow-control sleeves, valves, and packers; along-hole profile detectors for

pressure and distributed temperature; and seismic geophones and resistivity sensors. There is an

increasingly adoption of IWC due to the identifiable practical and economical advantages of its

application. Installation of IWC systems multiplied from 2000 to 2002, running at 50 well

systems per year (Robinson, 2007). Figure 2.4 shows IWC installation increasing trend globally.

Figure 2.4: Intelligent wells installation trend from all providers (Eni Group, 2006)

Page 28: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 17

There is an increasing variety of real-time, downhole, monitoring and measurement systems

which are now available for deployment ranging from simple system with sliding sleeves open or

shut, to high end hydraulic/electric systems with infinitely variable chokes and extensive

monitoring of pressure and temperature, sand detectors, multi-phase metering, resistivity and

seismic sensors for tracking near well fluid contacts. There are sensors for high resolution

pressure and temperature, high frequency pressure (acoustic), multiphase flow rate, phase-cut,

electric potential (electro-kinetic), seismic (accelerometers) and casing condition monitoring

(strain). A thorough understanding of what data is actually needed, the most suitable sensor types

and interfaces together with availability of the necessary data reconciliation and validation

methodology are key factors for the success of an integrated IW project (Silva et al., 2012).

2.4 CLASSIFICATION OF MONITORING SYSTEMS

Permanent well monitoring is divided into two classes of systems; deep reservoir and near

wellbore monitoring systems. Deep reservoir sensing is related to 4D seismic (time-lapse

seismic), dynamic 3D resistivity and streaming potential (electro-kinetic) – monitoring

techniques which capture the dynamics of the entire reservoir. Near wellbore sensing includes

the classical downhole measurements such as pressure and temperature (Silva et al., 2012).

Permanent sensors may also be classified by technology as electronic or optical and by the

number of monitored points as single point, quasi-distributed and distributed. Single point

sensors read the physical quantity to be monitored at a point; example is the permanent

downhole gauge (PDG); pressure is often monitored close to the reservoir depth or at the top of

the interval of interest. Quasi-distributed sensors allow the monitoring of the physical quantities

Page 29: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 18

at a distinct number of locations across the reservoir or interval of interest, it requires at least

three sensors measuring the same physical quantity to be installed at various points across each

interval. Distributed sensors monitor physical quantity at a spatial resolution as small as 0.5m;

example is the distributed temperature sensor (DTS). The distributed sensing network requires

understanding of all errors and limitations in the signal path besides the sensor itself (Silva et al.,

2012).

2.5 COMPONENTS OF IWC

The basic elements of IWC are as follows (Eni Group, 2006):

Acquisition and transmission system

Flow control valves (FCV) and

Actuation system

The acquisition and transmission system is a set of equipment usually electric or fiber optic, used

to transmit and acquire reservoir data.

Two types of flow control valves are available; binary control (on/off valve) and choke valve.

The on/off valve is used to open or close the flow rate in a level, hence has only two positions;

fully open or fully close and does not have the possibility to choke the flow. Internal control

valve (choke valve) has the capacity to choke the flow rate. There are two types available;

multistep and infinity variable choke. Multistep valve can have only a limited number of discrete

positions to choke the flow while the infinite variable valve can have a continuous regulation of

flow area from 0% to 100%. The selection of the right flow control is critical, as it may have an

Page 30: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 19

impact on the number of zones or intervals that can be effectively controlled in one well (Silva et

al., 2012).

The actuation system is a set of equipment that supplies power to the valves. There are three (3)

systems available, hydraulic, hybrid and electric system. The hydraulic system usually for on/off

and multistep valves, is the simplest system in the market and it is less expensive. The hybrid

system usually for on/off, multistep and infinity variable valves, is an electro-hydraulic system

and provides a higher level of control than the hydraulic system. Controls consist of hydraulic

power, electric distribution of the pressure and monitoring or control of the flow control valve

(FCV) positions. The hydraulic control moves the FCVs while the electric control communicates

signals (move solenoid valves). Compared to the hydraulic system, the hybrid system has a high

level of control and steers around failure but it is complex and expensive. For the electric system,

FCV can assume infinity positions to choke the flow rate. This system need only one electric

permanent downhole cable for multiple valves, the same cable transmits the signal from the

PDGs and the electrical power to the FCVs. The valve has inside pressure, temperature and

diagnostic measurements. Advantages of the electric system include high level of control and

number of control lines. Its disadvantages include no redundancy, high cost and level of

complexity (Eni Group, 2006).

2.6 APPLICATIONS AND BENEFITS OF IWC

Installation details or data acquisition issues need to be fully analyzed to design a robust,

integrated, monitoring architecture that delivers the full added value. Instrumentation and other

hardware advances have allowed more flexibility at the design and installation stage while

Page 31: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 20

enabling the systems use for a variety of new applications. For example, developments in

pressure and temperature gauges, allow control of the sample rate for capturing fast events

without causing data overload. Cableless technology for example allows access to data from

gauges installed within the laterals of a multilateral well. New hybrid (electric/hydraulic) IWC

systems are becoming available, enabling the flow control system and the sensor to share the

same system architecture. This represents a reduced number of control lines and allows

interchangeable modules for actuators and sensors, increasing the installation’s flexibility while

simplifying the installation procedure (Silva et al., 2012). IWC has been employed in many areas

to maximize recovery.

Areas of IWC application include the following:

Commingle production

Managing drawdown

Distribution of injectant (water and gas injection)

Water and gas coning

Sand control

Gas lift

Control WAG injection

Miscible flood

Minimal intervention

Page 32: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 21

The value of the IWC comes from the ability to actively modify the well zonal completions and

performance through flow control and to monitor the response and performance of the zones

through real-time downhole data acquisition. The benefits of IWCs will vary from different

fields and is a function of reservoir quality, production rates, fluid contacts, gas and water

coning, etc. The cost of a conventional intervention is also an important parameter. For each

reservoir installation of IWC, there are objectives for its installation hence the value of IWC

must meet the objectives as well as other benefits.

The primary objectives of IWs are generally to maximize or optimize production/recovery,

minimize operating costs, and improve safety (Robinson, 2007).

The most important benefit of a smart well system is improved reservoir management or

monitoring; ability to remotely choke or shut zones with poor performance will give an

immediate response on the well performance without any expensive well interventions. With

downhole sensors data will be collected for every zone along the well path continuously which

will be helpful for reservoir models and also give input for optimal openings of the inflow

control valves.

IW also reduces intervention costs, well intervention in horizontal wells is far more complex and

expensive both in terms of reservoir monitoring (production logging) and zonal isolation

(plugging or patching). Without any zonal control, the production potential from a long

horizontal well may be restricted by small thief zones.

In additional to their main application, they can also identify and classify failures in downhole

equipment (Hudson et al., 2011).

Page 33: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 22

General benefits of remote completion monitoring and control are as follows:

Provide quality reservoir data for support of total field development.

Improve zonal or areal recovery monitoring (locate remaining oil and define infill

development targets)

GOR and water-cut can be controlled by changing the position setting of the choke,

optimizing oil production from the different layers.

Water and gas injection rates can be regulated for individual sections of injection wells,

thereby optimizing the sweep efficiency.

Minimize or eliminate the need for well intervention (reduce intervention costs)

Target stimulation treatments from surface

Reduce water handling (reduce cost of surface facilities)

2.7 LIMITATIONS OF IWC

High reliability of IWC is necessary for avoiding workover operations; whereas monitoring and

measuring of downhole reservoir data and choking ability are also important to reach optimal

production.

Certain risks are common to any application of a downhole control system. Common risks

include cable or line failure particularly during installation, longer-term system failures may be

caused by erosion, temperature effects on electronics, wear and tear and seizure of moving

Page 34: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 23

components. The simpler the system and the fewer moving parts, the fewer components

available to fail.

Control lines, cables and sensors represent the nervous and circulatory system of an IWC and

damage to these elements may mean partial or total loss of the functionality of the IWC.

(Robinson, 2007)

Veneruso et al. (2000) in their study of reliability of permanent downhole equipment found that

the equipment reliability greatly depends on temperature; gauges in high temperature

environment have a shorter expected life time.

Page 35: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 24

CHAPTER 3

METHODOLOGY

3.1 INTRODUCTION

Oil and gas production operations involve risks as a result of uncertainties from reservoir

properties, equipment failure as well as unforeseen future events; hence evaluation and

justification of field development projects are extremely important, as projects incur huge sums

of money and once a field is developed, the whole architecture cannot be changed entirely.

This section describes the methodology used to compare the application of intelligent well

completions (IWC) vs. non-intelligent completions in reservoir management. In the presentation,

we consider data acquisition, oil recovery and the economics involved in both completions.

Case studies of reservoirs where intelligent completions have been employed were analyzed. The

tools used for this analysis include material balance software (MBAL) for production forecast

using decline curve analysis and Monte Carlo-Simulation-software (a spread sheet add-in, Oracle

Crystal Ball) for the uncertainty analysis of the economics of the two types of completions.

Figure 3.1 illustrates the major steps in the workflow which is patterned after the model proposed

by Sakowski et al, (2005); the detailed step-by-step procedure used in their work is illustrated by

Figure 3.2.

Page 36: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 25

Figure 3.1: Workflow used for reservoir and economic analysis of IWC

No Yes

Define possible application

and objectives of IWC

Estimate production profile

or performance

Carry out economic

analysis of project

Desired profitability

and objectives

achieved?

IWC project

justified

IWC project not

justified

Page 37: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 26

Figure 3.2: Detailed Step-by-Step Procedure for Reservoir and Economic analysis of IWC

application (Adapted from Sakowski, Anderson and Furui, 2005)

3.2 RESERVOIR DATA ACQUISITION AND MANAGEMENT

Reservoir management uses elements of geology, geophysics and petroleum engineering to

predict and manage oil recovery which requires a thorough knowledge of the reservoir through

an integrated efficient data management. So much data is collected and analyzed during the life

of a reservoir. Data acquisition and management is key to project success; hence must be

Yes

No

No

Yes

Identify a possible

application of IWC

Define architecture of basic and

IW completion

Simulate behavior of well

(Nodal analysis, Simulation)

Increase

production rate or

recovery factor?

Redefine architecture of

the IWC

Carry-out economic

analysis of project

Desire

profitability

achieved?

Execute the IWC

project

Consider other

alternatives

Page 38: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 27

carefully planned and guided by timeliness, quality and cost effectiveness. The need for the data

and associated cost or benefit analysis should be established.

The need and type of data obtained from IWC were compared to conventional or non-intelligent

wells, for the reservoirs studied in this work.

3.3 WELL PERFORMANCE

Well performance in various well configurations (vertical, horizontal wells, multi-lateral etc.)

was compared by analyzing oil production, water and gas production, for both intelligent and

conventional or non-intelligent completions.

3.3.1 INFLOW AND VERTICAL LIFT PERFORMACE

The ability of a well to produce fluids depends on the capacity of the piping system to carry these

fluids to the surface which is controlled by three flow processes; flow from reservoir to the well

bore (Inflow performance), flow from the well bore to the well head (Vertical lift) and flow

through chokes, flow lines and process facilities (Surface flow). Reservoir system analysis

relates pressure drop (ΔP) with flow rate and allows determination of the producing capacity for

any combination of components of the well by analyzing the inflow performance (IPR) and

outflow performance (VLP) relationships. The IPR curve describes the relationship between the

production rate across the reservoir-wellbore interface and the wellbore pressure across the

thickness of the producing zone. The tubing intake curve describes the relationship between the

bottomhole flowing pressure and the rate of flow through the production tubing, allows

evaluation of the friction losses developed through the production tubing as a function of the

fluid flow rates.

Page 39: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 28

From Darcy’s law, the flow equation for stabilized radial flow of a single phase liquid flow

through homogenous formation from an infinite reservoir is given by equation 3.1 and the

productivity index (PI), which is the ratio of flow rate to pressure drawdown is given by equation

3.2.

The simplest and most widely used IPR equation is the straight line IPR which is applicable for

undersaturated reservoirs but for two-phase flow or saturated reservoirs, Vogel’s equation given

by equation 3.3 and Standing equation which is a modification of Vogel’s equation, can be used

to describe the IPR.

For horizontal well, the inflow performance equations at steady-state have been proposed by

Borisov, Merkulov, Giger, Giger et al, Renard & Dupuy and Joshi. The most popularly used

model is the Joshi’s equation given by equation 3.4 for an anisotropic reservoir (kh is different

from kv) and equation 3.8 for an isotropic reservoir (kh=kv).

Page 40: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 29

where is given by equation 3.5

where c and b are the major and minor radii of a drainage ellipse. The PI is given by equation

3.7.

The pressure drop along the production tubing can be calculated by using charts or correlations.

Gradient or Transverse curves can be used to determine the wellbore flowing pressure at

different oil rates if the wellhead pressure is specified. Table 3.1 shows some correlations used in

the industry.

Page 41: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 30

Table 3.1: Some correlations used in the industry

Method Well Fluid Comments

Duns & Ros

(1972)

Oil, Water, Gas Optimistic, under predicts pressure drop

Beggs & Brill

(1973)

Oil, Water, Gas Use for deviated well greater than 45 degrees,

tends to over predict pressure drop, used for

horizontal wells

Gray Water, Gas Good for gas condensate wells

Cullender & Smith Water, Gas Used for dry gas wells

3.3.2 DECLINE CURVE ANALYSIS

Decline curve analysis is based on empirical relationship of production rate versus time given by

Arps in 1945. Arps presented three types of production rate-time decline, namely, exponential,

hyperbolic and harmonic decline equations (Table 3.2).

Table 3.2: Arp’s equations

In this work, exponential decline was used because it is known to give a more conservative

production rate forecast. For exponential decline the equation can be written as follows:

Page 42: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 31

where D is the exponential decline rate

In the above case, d is called the nominal decline rate and can be written as

The nominal and exponential decline rate can be related as;

The applicable decline for the purpose of reserves estimates is usually based on the historical

trend that is seen on the well or reservoir performance. It is assumed that the factors causing the

historical decline continue unchanged during the forecast period. These factors include both

reservoir and operating conditions. Operating conditions that influence the decline rate are;

separator pressure, tubing size, choke setting, workovers, artificial lift, operating hours,

compression etc. For instance the decline rate determined pre-workover will not be applicable to

the post-workover period.

3.3.3 PRODUCTION RATE FORECAST

The analysis of production rate versus time was carried out using MBAL. MBAL is a Petroleum

Experts software package which is made up of various tools such Material Balance, Reservoir

Allocation, Monte Carlo Volumetric Analysis, Decline Curve Analysis, 1-D Model and Multi-

Page 43: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 32

layer to perform prediction runs, but this work only employed Decline Curve analysis to forecast

well production rate versus time.

Daily oil production history from both intelligent and non-intelligent wells was history matched

using exponential decline and the future well production rates versus time were calculated from

MBAL performance prediction runs.

3.4 TIME VALUE OF MONEY AND ECONOMIC ANALYSIS

Decision-making in investment analysis requires anticipated revenues and cost of investment

alternatives to be placed on equivalent basis. As a result of interest rate, inflation and risk

investment today may not be of the same value tomorrow. Economic analysis of each scenario

was done based on the time value of money by comparing the after tax cash flow in each case;

considering the CAPEX, OPEX and some profitability indicators such as discounted payout

period, net present value, profitability index and growth rate of return. Also, uncertainty analysis

was performed to assess the project (IWC versus non-intelligent completion) risks. Net-present

value methods recognize the time value of money and are critical when assessing the profitability

of long-term investments (Main, 2002). After-tax Net cash-flow given by equation 3.13 is the

cash received less cash spent during a period. The cash inflow is basically from the revenue

generated from the sale of oil and gas. The gross revenue is given by equation 3.14.

Page 44: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 33

Inflation was considered in the cash flow analysis. Inflation decreases the purchasing power of

money. The price of a product increases by inflation rate at time t from present time and it is

given by:

where Ao, %ri and t in Equation 3.15 are the base price, the inflation rate, and the years measured

from the present time, respectively.

3.4.1 OPEX

Operating expenditure (OPEX) also called lease operating expenditure is the direct cost

associated with production or injection. OPEX includes fixed operating cost e.g., management

fees, and variable operating costs which include utilities, maintenance, production costs, etc.

3.4.2 CAPEX

Capital Investment (CAPEX) refers to as front-end cost is the capital invested in assets that will

generate benefits for more than one year. These include cost of drilling and developing wells,

surface equipment, completion, installing facilities for enhanced recovery, etc. CAPEX consists

of tangible such as surface equipment cost, etc and intangible CAPEX such as seismic

acquisition, etc.

Page 45: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 34

3.4.3 PROFITABILITY INDICATORS

The profitability indicators used in this work are described in the following section.

3.4.3.1 NET PRESENT VALUE (NPV)

Net present value is the most popular petroleum evaluation criterion. NPV is obtained by

subtracting the present value of periodic cash outflows from the present value of periodic cash

inflows. For end of year discounting, NPV is given by:

For mid-year discount factor, NPV is given by;

This study adopted the year end discounting method for the NPV calculations.

3.4.3.2 PROFITABILITY INDEX (PI)

PI measures the efficiency of an investment. It is a dimensionless ratio which is obtained by

dividing the present value of future operating cash flows by the present value of the investment.

Mathematically, the PI is given by the following equations.

Page 46: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 35

where

3.4.3.3 GROWTH RATE OF RETURN (GRR)

This is also called equity rate of return or modified internal rate of return (MIRR). A project is

desirable if the GRR is greater than the hurdle rate, rd.

For annual and continuous compounding, the GRR is given by equation 3.21 and 3.22

respectively.

3.4.3.4 PAYOUT PERIOD (PO)

Payout is the time required to recover the investment either before income tax or after income

tax. We have used after income tax payout time in this work. Cash receipts are exactly equal

investment at this point.

The payout period can be calculated by accumulating the negative net cash flow each year until it

turns positive or by plotting the cumulative net cash flow versus time, the intersection of the time

line at zero net cash flow is the payout period. The partial payback in the year when the NCF

turns positive can be calculated using equation 3.23.

Page 47: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 36

3.4.4 MONTE-CARLO SIMULATION

Sensitivity is the amount of uncertainty in a forecast caused by model assumptions and input data

uncertainties. Monte Carlo simulation aids in making predictions by accounting for randomness

and future uncertainties through investigation of different input data scenarios. Sensitivity

analysis was performed on variables considered to be estimates with high uncertainties such as

oil price, oil price inflation rate, discount rate, etc. Oracle Crystal Ball software was used to

determine the impact of variations in the input variables on the base case value of profitability.

Page 48: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 37

CHAPTER 4

RESULTS AND DISCUSSION OF CASE STUDIES IN RESERVOIR MANAGEMENT

4.0 INTRODUCTION

The results obtained from the analysis are presented and discussed in this Chapter. Sample

worked examples are presented in the Appendix.

Actual field cases where IWC has been proposed and implemented as solution to the challenges

in reservoir management in the field were evaluated and compared with non-intelligent

completions.

4.1 ASSUMPTIONS COMMON TO ALL FOUR CASE STUDIES

In this work, the following assumptions were common to all the four case studies considered.

Periodic year-end funds flow

Royalty

o Cumulative oil production less than 1MMSTB – 5%

o Cumulative oil production greater than 1MMSTB – 12.5%

Depreciation method - Double declining depreciation

Oil price inflation - 2.5%

Income Tax – 45%

Discount rate – 12.5%

Page 49: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 38

20% of CAPEX is expensed

Table 4.1 shows the input variable stochastic distributions common to all four case studies.

Table 4.1: Variable distribution input

Parameter Distribution Minimum Most

likely

Maximum Mean Standard

deviation

Oil price inflation, % Normal 2.5 1.6

Income Tax, % Uniform 25 50

Discount rate, % Triangular 10 12.5 15

4.2 CASE STUDY 1: COMMINGLED PRODUCTION FROM A TWO-LAYER

OFFSHORE FIELD

The first case study is the application of IWC in an offshore field presented by Behrouz et. al.

(2010). The structure of the reservoir is anticline, with two-layer sand stone formation separated

by an impermeable shale layer. The reservoir has no gas cap but has a strong aquifer with edge

water drive mechanism. Out of seven wells, three wells were proposed for intelligent completion

with commingled production. (Behrouz et. al, 2010)

The total oil production from the intelligent and conventional wells for six years was compared,

and the economics of the project analyzed.

Assumptions made in the analysis of Case Study 1 include the following:

Page 50: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 39

Drilling and completion cost for each well is $7MM

Equipment and installation cost of IWC without ICV is $1MM

ICV unit cost is $0.5M

Period considered is six years

Workover cost per year is $1.0MM

No workover was carried out in the IWC over the six years

Operating cost is $4/bbl without workover

Additional input data used in the analysis for this case study are listed in Table 4.1.

Table 4.2: Stochastic variable input parameter distribution for Case Study 1

Parameter Distribution Minimum Most likely Maximum

Capex IWC, MM$ Triangular 8 9 11

Capex CW MM$ Triangular 6 7 9

Workover cost per year, MM$ Uniform 0.5 2.5

Reservoir management

The intelligent completion (IWC) allowed reservoir monitoring of pressure drawdown and

individual layer productivity test. Layer 2 was shut in as a result of high water cut confirmed by

Page 51: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 40

the reservoir monitoring. It was observed that the oil production from Layer 1 increased due to

elimination of back pressure exerted by the high water production rate from the Layer 2. Figure

4.1 shows the total oil production from the conventional and intelligent wells for six years.

The use of IWC increased oil production by 23.9% compared to the convention well (CW),

which can be seen in Table 4.3. This oil production increment can be attributed to the

optimization of oil production in the IWC by the use of downhole flow control valves.

Figure 4.1: Production performance from the IWC and the conventional well

0

500

1000

1500

2000

2500

0

50

100

150

200

250

300

350

400

450

500

0 2 4 6

Cu

mu

lati

ve o

il p

rod

uct

ion

, Mb

bl

An

nu

al o

il p

rod

uct

ion

, Mb

bl

Time, year

Oil production versus time

CW oil production IWC oil production

IWC Cumulative oil production CW Cumulative oil production

Page 52: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 41

Economic analysis

The NPV in both completions was positive which means that both projects are acceptable but the

IWC gave a higher NPV compared to the conventional well. From the certainty analysis, the

NPV of the IWC at P90, P50 and P10 compared to that of the conventional completion gave an

increment of 25.6%, 27.5% and 30.1% respectively (Table 4.3). Hence the IWC improved the

economic outcome of the well and these results can be attributed to the accelerated oil

production and reduced well intervention costs from the IWC. This makes the IWC preferable to

conventional completion

Figure 4.2 shows the sensitivity analysis on the NPV in both completions. From Figure 4.2, it

can be observed that oil price and oil price inflation have a positive impact on the NPV whiles

Income Tax, workover cost per year and CAPEX have a negative impact on the NPV. Therefore,

increase in oil price and oil price inflation will increase the NPV whiles an increase in Income

Tax, workover cost per year and CAPEX will lower the NPV. The Tornado chart in Figure 4.3

ranks the most sensitive parameter to the least sensitive. From Figure 4.3, the oil price is the

most sensitive to the NPV in both completions. Hence, the decision to implement IWC or not

will depend on the prevailing oil price because the economic performance relies greatly on the

revenue generated from the oil sale.

Although the CAPEX in IWC was higher, the operating cost was less than that of the

conventional completion by 29%.

The payout period illustrated by Figure 4.4 was less than seven (7) months in both completions.

This shows that investment in both completions is recovered early enough, considering the

economic life of six years. The conventional completion payout period was slightly earlier

Page 53: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 42

compared to that of the IWC. This means that IWC project is riskier compared to the

conventional completion project, especially for a politically unstable country.

The PI and the GRR was almost the same for both completions, a difference of less than 1%. The

PI was more than one and the GRR greater than the hurdle rate of 12.5% in both completions.

This shows that both projects are acceptable. Summary of results obtained from this analysis is

presented in Table 4.3.

Since the PI, GRR and PO are almost the same for both completions, IWC installation can be

justified based on incremental oil recovery and NPV. IWC installation is justifiable, since it

improved recovery and the economic outcome of the well.

Figure 4.2: NPV sensitivity analysis for both IWC and conventional well

Page 54: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 43

Figure 4.3: Tornado charts of the NPV for the IWC and the conventional well

Figure 4.4: Cumulative discounted net cash flow versus time

64

27%

0.45%

11.12%

8.55

96

47%

4.55%

13.88%

10.23

30 40 50 60 70 80

Oil price

Income Tax

Oil price Inflation

Discount rate

CAPEX

NPV - IWC Downside

Upside

64

27%

0.45%

0.7

11.12%

6.55

96

47%

4.55%

2.3

13.88%

8.23

20 30 40 50 60 70

Oil price

Income Tax

Oil price Inflation

Workover cost per year

Discount rate

CAPEX

NPV - NON IWC Downside

Upside

-10

0

10

20

30

40

0 1 2 3 4 5 6 7

Cu

mu

lati

ve

Dis

cou

nte

d N

CF

,

MM

$

Time, year

Payout period for both completions

IWC

CW

Page 55: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 44

Table 4.3: Summary of results for Case Study 1

Parameter IWC CW Difference (%)

Cumulative Oil produced, MMbbl 1.992 1.607 +23.9

Deterministic Economic Results

NPV, MM$ 36.83 29.58 +25.9%

Operating cost, $/bbl produced 8 11 -27.2%

OPEX, MM$ 5.98 10.82 -44.8%

CAPEX, MM$ 9.00 7.00 +28.6%

DPO, months 7.20 6.00 +1.20 months

PI 2.01 2.03 -0.99%

GRR, % 26.38% 26.60% -0.22%

Stochastic Results of NPV, MM$

P90 43.15 33.16 +30.1%

P50 58.06 45.54 +27.5%

P10 76.28 60.75 +25.6%

Page 56: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 45

4.3 CASE STUDY 2: MULTI-LATERAL PRODUCER-INJECTOR PATTERN

OFFSHORE FIELD

The second case study is a mature field located in a low permeability limestone environment.

This case study is taken from the study of Ajayi et al. (2006). Multi-lateral wells, producer-

injector pattern were employed to enhance oil production and maintain reservoir pressure, but

this lead to high water production. Some of the multi-lateral producers recorded as high as 99%

water-cut with a field average water-cut of 75% which drastically reduced oil production rate.

One multi-lateral oil producer with four branches was selected for a trial to evaluate the use of

IW technology to restore field oil production, decrease water production, improve water flood

efficiency and to increase reservoir knowledge. The well was shut in after three and half (3.5)

years of production to install the IWC. The intelligent completion design was made up of four

inflow control valves (ICV) attached to each lateral. Each lateral was separated by isolation

packers to ensure monitoring of the individual layers. (Ajayi et. al, 2006)

In this study two scenarios were considered for this case. Evaluation of performance of the well

for a period of 10 years if;

1. No well control system was installed

2. Well control (intelligent system) was installed after three years of production

Production history from the non-intelligent completion and the IWC were history matched using

exponential decline non-linear regression with medium data point weighting and production

forecasted for 10 years. The production history from the IWC and non-intelligent completion are

shown in Figure 4.5.

Page 57: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 46

Figure 4.5: Oil production history from both completions (Ajayi et. al, 2006)

Assumptions used in the analysis of Case Study 2 are listed below and Table 4.4 contains the

distribution of the stochastic input variables.

Drilling and completion cost is $3.5MM

Well equipment cost is $4.0MM

ICV unit cost is $0.5MM

Intelligent system installation cost is $1MM

Operating cost without workover is $3/bbl

Workover cost per year is $1.0MM

0

1000

2000

3000

4000

5000

6000

7000

0 2 4 6 8

Oil

Rat

e, b

bl/

day

Time, year

Oil production history from both completions

IWC

Non-IW

Page 58: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 47

Table 4.4: Stochastic variable distribution of input parameters for Case Study 2

Parameter Distribution Minimum Most likely Maximum

CAPEX IWC, MM$ Triangular 9 10.5 12

CAPEX NON-IWC, MM$ Triangular 6 7.5 9

Workover cost per year, MM$ Uniform 0.5 2.5

Reservoir management

Downhole sensors in the IWC allowed real time monitoring of pressure drawdown and

production from each lateral; the observed data was used to optimize the inflow from each

lateral. The productivity index for each lateral was established without extra cost. Zones 1 and 4

were found to produce a larger fraction of total water produced, hence the ICV for zones 1and 4

were set to fully closed and the well was produced only from branches 2 and 3.

Oil production increased by 21% (Table 4.5) in the IWC compared to the non-intelligent

completion. This is due to the optimization of oil production in the IWC by the use of downhole

control valves. Figure 4.6 shows the oil production performance for 10 years in both

completions.

Page 59: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 48

Figure 4.6: Oil production performance for the two scenarios

Economics Analysis

For both completions, the NPV was positive, the PI was greater than one, the GRR was greater

than the hurdle rate and the payout period was desirable. This shows that both projects are

acceptable but the economic outcome from the IWC was more attractive compared to that of the

non-intelligent completion.

From the stochastic analysis, the NPV for the IWC was higher that of the non-intelligent

completion. The IWC gave 17.5%, 18.5% and 20% increase in NPV at P10, P50 and P90

respectively (shown in Table 4.5). This shows that the IWC investment gave more value

compared to the non-intelligent completion. The increase in NPV in the IWC can be attributed to

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

0.0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

1.8

2.0

0 2 4 6 8 10 12

Cu

mu

lati

ve o

il p

rod

uce

d, M

MST

B

An

nu

al o

il p

rod

uct

ion

, MM

STB

Time, year

Oil production performance for both completions

IWC - Annual oil production NON-IWC - Annual oil production

NON-IWC - Cumulative oil produced IWC - Cumulative oil production

Page 60: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 49

the increase in oil recovery and less operating cost (decreased by 23.3%). The high workover

cost in the non-intelligent completion gives rise to the high operating cost.

Figure 4.7 shows the sensitivity of oil price, income tax, oil price inflation, workover cost per

year, discount rate and CAPEX on NPV in both completions. It can be observed that oil price

and oil price inflation have a positive impact on NPV whiles the income tax, workover cost per

year and discount rate have a negative impact on NPV. This shows that increase in oil price and

oil price inflation increases the NPV but increase in income tax, workover cost and discount rate

will decrease the NPV. Figure 4.8 illustrates the Tornado chart for both completions. The

Tornado chart ranks the most sensitive variable to the least. It can be observed that oil price is

the most sensitive and CAPEX the least sensitive in both the IWC and the non-intelligent

completion. Therefore a lower oil price may render both projects less attractive.

Figure 4.9 illustrates the payout period in both completions. The payout period was less than

three (3) months in both completions. This shows that investments in both projects for 10 years

of production are recovered early enough and have the same risk exposure.

The total return on investment dollars was $3.05 per dollar for the IWC whiles that of the non-

intelligent completion was $2.73 per dollar. This shows an increase in PI by 11.7% in the IWC

compared to the non-intelligent completion. This makes the IWC more preferable.

The project worth plus the reinvestment opportunities for the IWC was 25.78% whiles that of the

non-intelligent completion was 24.36%, giving a difference of 1.42%. This shows that the

investment in IWC was better than that of non-intelligent completion.

Page 61: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 50

Since the objectives of the IWC installation-to reduce water production, increase oil recovery

and ease acquisition of reservoir data were met in addition to improved economic outcome, IWC

implementation is justified.

Figure 4.7: NPV sensitivity analysis for both completions

Figure 4.8: Tornado chart of the NPV for both wells

64

27%

0.45%

11.1%

0.7

9.67

96

47%

4.55%

13.9%

2.3

11.33

80 100 120 140 160 180

oil price

Income Tax

Oil price Inflation

Discount rate

Workover cost per year

CAPEX

NPV IWC Downside

Upside

64

27%

0.45%

0.7

11.1%

6.67

96

47%

4.55%

2.3

13.9%

8.33

60 80 100 120 140 160

oil price

Income Tax

Oil price Inflation

Workover cost per year

Discount rate

CAPEX

NPV - NON IWC Downside

Upside

Page 62: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 51

Figure 4.9: Cumulative discounted net cash flow versus time

Table 4.5: Summary of results for Case Study 2

Parameter IWC Non-IWC Difference (%)

Cumulative Oil produced, MMbbl 4.224 3.475 +21.6%

Deterministic Economic Results

NPV, MM$ 85.21 71.63 +19.0%

OPEX, MM$ 15.67 20.42 -23.3%

CAPEX, MM$ 10.50 7.50 +40.0%

DPO, months 2.04 2.04 0

PI 3.05 2.73 +11.7%

GRR, % 25.78% 24.36% +1.42%

-10

10

30

50

70

90

0 2 4 6 8 10 12 Cu

mu

lati

ve D

isco

un

ted

NC

F, M

M$

Time, year

Payout period for both completions

IWC

NON-ICW

Page 63: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 52

Stochastic Results of NPV, MM$

P90 99.18 82.62 +20.0%

P50 131.07 110.65 +18.5%

P10 169.84 144.54 +17.5%

4.4 CASE STUDY 3: TRIPLE COMINGLED PRODUCTION – USARI FIELD

OFFSHORE NIGERIA

The third case study is taken from the Usari field located about 16 miles offshore Nigeria in

about 72 feet of water (Brock et al., 2006). The field has 35 reservoirs which are subdivided into

shallow (18 reservoirs), intermediate (15 reservoirs) and deep (2 reservoirs) based on the fluid

properties, pressure regimes and the geologic setting. The Usari shallow reservoirs are made up

of faults sealed within a graben. The graben has seven reservoirs which were discovered in 2001.

Development wells were planned to be completed across three (3) of the seven reservoirs (Figure

4.10), the 7-US1G which is the upper reservoir, the 8-US1G which is the middle reservoir and

the 9-US1G, the lower reservoir as a triple comingled producer using intelligent well completion.

The well in Figure 4.10 was made up of multi-position flow control valves for each of the three

9-5/8 inch gravel packed completion. The flow control valves can be activated at the surface and

had permanent downhole pressure and temperature gauges in front of the valves (Brock et al.,

2006).

Page 64: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 53

Figure 4.10: Development well path (Brock et al., 2006)

Daily production history from the IWC was history matched using exponential decline, non-

linear regression analysis with medium weighted data points and the oil production, forecasted

for six years. Figure 4.11 shows the daily production history from the IWC.

Figure 4.11: Production history from the IWC for Case Study 3 (Brock et al., 2006)

Page 65: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 54

Assumptions used in the analysis of Case Study Number 3 include the following:

Analysis period was six years and the life of the intelligent system equipment can last

over the six years period, hence no workover cost inquired.

Well equipment cost is $3.0MM

Rig cost is $95,000/day

Intelligent equipment and installation cost without ICV is $1.0MM

Unit cost of ICV is $0.5MM

Production and handling cost without workover cost is $5/bbl

Triangular distribution is assumed as the probability distribution for the CAPEX

Reservoir management

Real time pressure and temperature profiles are being recorded and monitored by use of the

intelligent system. Build up test and productivity test can be done simultaneously without

shutting in the well by the use of the FCV and the result is simulated to optimize production.

Geochemical analysis of oil sample from each zone was also made possible by use of the

intelligent system without additional cost. Figure 4.12 shows the production forecast for six (6)

years.

Page 66: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 55

Figure 4.12: Oil production forecast for Case Study 3

Economic analysis

A project can be acceptable if the payout period is desirable, the NPV is positive, the PI greater

than one and the GRR greater than the hurdle rate. From the stochastic analysis, the NPV at P90

for the IWC installation was 189.56MM$ which shows the value of the investment for six years.

This high NPV can be attributed to high production from the optimized flow and no intervention

cost incurred.

Figure 4.13 shows the Spider and Tornado charts of the NPV from the IWC. The Spider chart

shows the most sensitive variable to NPV with the steepest line and the Tornado chart ranks the

most sensitive variable to the least sensitive variable to NPV. From the charts, the NPV is most

sensitive to oil price and CAPEX is the least sensitive. The sensitivity analysis in Figure 4.13

shows that the oil price and oil price inflation have a positive impact on the NPV whiles the

income tax and discount rate have a negative impact on the NPV, as observed from previous case

0

2

4

6

8

10

0.0

0.5

1.0

1.5

2.0

0 2 4 6 8 Cu

mu

lati

ve o

il p

rod

uct

ion

, MM

bb

l

An

nu

al o

il p

rod

uct

ion

, MM

bb

l

Time, year

Oil production from the IWC

Annual oil production Cumulative oil production

Page 67: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 56

studies. Therefore increase in oil price will increase the NPV whiles increase in discount rate and

income tax will decrease the NPV.

The payback period illustrated by Figure 4.15 was less than four (4) months. This shows that for

six years of production, investment is recovered early, which reduce the risk exposure of the

investment.

The total return on the investment dollars was $4.92 per dollar which is acceptable. The GRR

was far greater than the hurdle rate of 12.5% which shows that the worth of the project plus the

reinvestment opportunities is also acceptable. Table 4.8 gives the summary of the results

obtained for this case study.

Since IWC installation is very economical and allows reservoir optimization, IWC

implementation is recommendable.

Figure 4.13: Spider and Tornado charts of the NPV

150

200

250

300

90% 70% 50% 30% 10%

Percentiles of the variables

NPV IWC

Oil price

Income Tax

Oil price Inflation

Discount Rate

CAPEX

64

27%

0.45%

11.1%

9.61

96

47%

4.55%

13.9%

11.28

150 200 250 300 350

Oil price

Income Tax

Oil price Inflation

Discount Rate

CAPEX

NPV IWC Downside

Upside

Page 68: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 57

Figure 4.14: Sensitivity analysis of the NPV

Figure 4.15: Cumulative discounted net cash flow versus time

-20

0

20

40

60

80

100

120

140

160

180

0 1 2 3 4 5 6 7

Cu

mu

lati

ve D

isco

un

ted

NC

F, M

M$

Time, year

Payout period for IWC implementation

Page 69: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 58

Table 4.6: Summary of results obtained for Case Study 3

Parameter IWC

Cumulative oil produced, MMbbl 8.770

Deterministic Economic Results

NPV, MM$ 162.75

OPEX, MM$ 43.85

CAPEX, MM$ 10.25

DPO, months 3.24

PI 4.92

GRR, % 46.70%

NPV stochastic results, MM$

P90 189.56

P50 252.30

P10 330.72

Page 70: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 59

4.5 CASE STUDY 4: HORIZONTAL WELL PRODUCTION – OSEBERG FIELD

OFFSHORE NORWAY

The fourth case study presented in this work is taken from the Oseberg field located offshore

Norway. The field is made up of three (3) main reservoir zones; the uppermost Tarbert

formation, the middle Ness formation and the base, the Oseberg/Rannoch/Etive (ORE) formation

(Erlandsen, 2000). As a result of the high gas-oil ratio in the deviated wells, the wells were

converted into horizontal well. The initial oil column of more than 200m has reduced to 20 –

40m oil rim; hence most of the production wells have experienced early gas break through and

reduction in the oil production rate. IWC was employed to control the gas production in order to

increase the oil rate (Erlandsen, 2000).

Intelligent system, electric-hydraulic control was installed in four wells; B-30B, B-21B, B-41A

and B-29B with the ICV in four (4) positions; 1/3 and 2/3 openings, fully opened and fully

closed, purposely to prevent early gas breakthrough. (Erlandsen, 2000)

Only two of the wells were analyzed in this study, B-30B and B-21B, to evaluate well

performance of IWC versus non-intelligent completion (Non-IWC).

Assumptions used in the analysis of the Oseberg Field include the following:

Drilling and completion cost is $8MM

Intelligent system equipment and installation cost without ICV is $1.5MM

ICV unit cost is $0.5MM

Workover cost is $1.0MM

Page 71: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 60

Production and handling cost without workover is $3/bbl

Table 4.7 lists additional input data used in the study of the Oseberg field.

Table 4.7: Stochastic variable distribution of input parameters of Case Study 4

Parameter Distribution Minimum Most likely Maximum

CAPEX IWC, MM$ Triangular 10 11 12

CAPEX NON-IWC, MM$ Triangular 7 8 9

The analyses of the data for the two wells are presented in the following section.

4.5.1 Well B-30B

Erlandsen reported that the position indicator of the IWC failed during installation; hence there

was no additional benefit other than zonal testing, temperature and pressure profile monitoring.

This shows that even when the downhole control valves in IWC fail, there are auxiliary benefits

from the use of IWC (data acquisition and monitoring). But when the well was close to dying

due to the increasing water-cut, the remotely operated zone was closed. This reduced water

production and increase oil production from the other zones.

Economic analysis

The additional capital expenditure of $2.0MM (25% increment in CAPEX) for the IWC

installation, it cannot be ascertain whether it significantly improved the NPV due to lack of

production data from this well.

Page 72: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 61

Although there was an increase in oil production at the later stage of the life of the well, the

objective of IWC installation was not achieved.

Since the IWC installation did not meet all the objectives for which it was installed as a result of

equipment failure, IWC installation in well B-30B cannot be justified.

4.5.2 Well B-21B

Reservoir management

From the analysis of this well, the total oil produced for five years was 4.416MMbbl from the

IWC whereas that of the non-intelligent well was 3.198MMbbl. This shows oil production

increment in the IWC by 38% compared with the production from the non-intelligent

completion. This can be attributed to the optimization of production based on the real time

productivity index, gas-oil ratio, water-cut, shut in pressure, flowing tubing pressures and

flowing annulus pressured for each zone obtained from the IWC. Figure 4.16 shows the oil

production in both completions.

Page 73: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 62

Figure 4.16: Production performance in both wells

Economic analysis

The NPV from both completions was positive, which shows that both projects are acceptable.

But the IWC gave a higher NPV compared to the non-intelligent completion. From the certainty

analysis, the NPV of the IWC at P90, P50 and P10 compared to that of the non-intelligent

completion gave an average increase of 39.9% (shown in Table 4.8). This is can be attributed to

the increase in oil production and reduced operating cost (reduced by 9.2%) from the IWC. With

reference to NPV, IWC is preferable to non-intelligent completion since IWC show a remarkable

increase.

Figure 4.17 shows the Tornado charts for both completions. From the Tornado chart, the oil price

is the most sensitive to the NPV and CAPEX is the least sensitive to the NPV as it has been

observed from all the previous cases analyzed. Therefore lower oil price reduces the NPV which

0

1

2

3

4

5

0

1

2

3

0 2 4 6

cum

ula

tive

oil

pro

du

ced

, MM

bb

l

An

nu

al o

il p

rod

uct

ion

, MM

bb

l

Time, year

Oil production versus Time

IWC Annual oil production NON-IWC Annual oil production

NON-IWC Cumulative oil produced IWC Cumulative oil produced

Page 74: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 63

may render the project economically unattractive because the economic performance relies

greatly on the revenue generated from the oil sale. The sensitivity chart in Figure 4.18 also shows

that oil price and oil price inflation have a positive effect on the NPV whiles the income tax and

discount rate negatively affect the NPV.

The payout period for both completions was less than two (2) months which is illustrated by

Figure 4.19. This shows that for five years of production, it takes less than two months to recover

the investment which is desirable. Thus both projects have a low risk exposure. The payout

period from the non-intelligent completion was slightly earlier compared to that of the IWC, but

because the payout in both projects is desirable, it does not make the non-intelligent completion

preferable to the IWC. The later payout period in the IWC can be attributed to the high cost of

IWC installation.

The PI from the IWC was 3.37 while that from the non-intelligent completion was 3.45. This

shows a decrease of 0.08 in PI using the IWC. IWC shows a slightly lesser PI due to the high

cost associated with it.

The GRR from the IWC was less than that from the non-intelligent completion by 0.7%. Base on

the difference of 0.7% in GRR, non-intelligent completion is preferable. But on the other hand,

the difference in GRR for both completions is less than 1%. The decision to implement IWC or

not cannot be based only on GRR, since both completion gave almost the same GRR. Summary

of the results obtained for Well B-21B analysis is given by Table 4.8.

Since IWC installation gave a higher oil recovery, increased the NPV within a desirable payout

period, IWC installation in Well B-21B is justifiable.

Page 75: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 64

Figure 4.17: Tornado charts of the NPV for both wells

Figure 4.18: Sensitivity on NPV for both completions

64

27%

0.45%

11.1%

10.67

96

47%

4.55%

13.9%

12.33

100 150 200 250

Oil price

Income Tax

Oil price Inflation

Discount rate

CAPEX

NPV - IWC Downside

Upside

64

27%

0.45%

0.7

11.1%

7.55

96

47%

4.55%

2.3

13.9%

9.23

60 80 100 120 140 160

Oil price

Income Tax

Oil price Inflation

Workover cost per year

Discount rate

CAPEX

NPV - NON IWC Downside

Upside

Page 76: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 65

Figure 4.19: Cumulative discounted net cash flow versus time for both wells

Table 4.8: Summary of the results for Well B-21B

Parameter IWC Non-IW Difference (%)

Cumulative oil produced, MMbbl 4.416 3.198 +38.0%

Deterministic Economic Results

NPV, MM$ 97.03 69.87 +38.9%

OPEX, MM$ 13.25 14.59 -9.2%

CAPEX, MM$ 11.50 8.00 +43.8%

-10

0

10

20

30

40

50

60

70

80

90

100

0 1 2 3 4 5 6 Cu

mu

lati

ve D

isco

un

ted

NC

F, M

M$

Time, year

Payout period for both completions

IWC

NON IWC

Page 77: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 66

DPO, months 1.92 1.68 +7.3days

PI 3.37 3.45 -2.3%

GRR, % 43.44% 44.14% -0.7%

Stochastic Results of NPV, MM$

P90 114.16 81.21 +40.57%

P50 151.03 107.9 +39.97%

P10 195.48 140.52 +39.11%

Page 78: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 67

CHAPTER 5

CONCLUSIONS AND RECOMMENDATIONS

5.1 SUMMARY AND CONCLUSIONS

This study compares the application of intelligent well completions versus non-intelligent or

conventional well completions for reservoir management. The objectives of this study is to

present a methodology which guides the planning and decision making process of implementing

IWC, as well as to present the benefits and limitations of IWC.

The case studies from four fields where IWC has been implemented were analyzed to examine

the applications of IWC. Daily production history from both IWC and non-intelligent completion

was history matched and prediction runs carried out. The criteria for judging the feasibility of

implementing IWC includes ease of data acquisition and well monitoring, incremental oil

recovery, NPV, Discounted payout period, Profitability Index and Growth Rate of Return.

Based on the results of the analysis of the case studies presented in this work the following

conclusions are drawn:

1. Incremental oil recovery from IWC vs. Non-IWC ranges from 21.6% to 38%.

2. IWC proves to be more economically viable compared to Non-IWC; NPV from IWC

exceeds that from Non-IWC by 17.5% to 40.6% for the case studies evaluated in this

work.

3. NPV is dependent on oil price.

4. Comparing field operating costs of IWC vs. Non-IWC shows that IWC OPEX can be

reduced from 9% to 45%.

Page 79: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 68

5. Payout time for IWC is a week to a month less than that of the Non-IWC but desirable.

6. IWC implementation is justifiable for the cases considered, except for IWC installation in

well B – 30B (Oseberg field) which did not yield the expected benefits due to the failure

of the surface-controlled downhole flow control valves. Failure of downhole control

devices would limit the profitability and justification for IWC projects.

5.2 RECOMMENDATIONS

Based on methodology and results of this study, the following recommendations are suggested:

1. Decline Curve Analysis was used for the oil production forecast in this work. It is

recommended that reservoir simulation be used for production forecast in similar

analysis.

2. Production period of five to six years after IWC implementation was considered in this

work. The entire life of the field, from IWC implementation to abandonment should be

considered in quantifying the benefits of IWC.

3. Statistics of all intelligent completions implemented, with their level of success, the risk

of failure, types of failure and the vendors should be compiled to guide the planning

process and actual field deployment of intelligent completion.

4. Pre-installation or pre-development test should be carried out to ascertain the reliability

of the intelligent system.

5. More research should be done on the intelligent system hardware to improve its

reliability.

Page 80: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 69

NOMENCLATURE

FCV Flow control valve

ICV Inflow control valve

S Skin factor

ko Effective permeability to oil, md

kv Effective permeability in the vertical direction, md

kh Effective permeability to oil in the horizontal direction, md

re External boundary radius, ft

rw Wellbore radius, ft

reh Effective or apparent wellbore radius, ft

Bo Oil formation volume factor, Bbl/Stb

h Pay thickness, ft

µo Oil viscosity, cp

ΔP Pressure change, psi

Pe External boundary pressure, psi

Pwf Flowing bottomhole pressure, psi

Average reservoir pressure, psi

Page 81: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 70

qo Oil production rate, bbl/day

qh Horizontal production rate, bbl/day

qmax Maximum production rate, bbl/day

Jh Horizontal productivity index, bbl/day/psi

L Length of horizontal section, ft

r Discount rate, percentage

I Interest payment on debt loan, percentage

Tc Corporate tax rate, percentage

NCFATAX Net cash flow after Income tax

NCFBTAX Net cash flow before Income tax

DD&A Depreciation expense

Page 82: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 71

REFERENCES

1. Addiego-Guevara E. A., Jackson M. D. and Giddins M. A.: “Insurance Value of

Intelligent Well Technology against Reservoir Uncertainty”, SPE 113918 presented at the

2008 SPE Improved Oil Recovery Symposium, Tulsa, Oklahoma, April 19-23, 2008.

2. Aggrey G. H. and Davies D. R.: “A Rigorous Stochastic Coupling of Reliability and

Reservoir Performance When Defining the Value of Intelligent Wells”, SPE 107197

presented at the Offshore Europe, Aberdeen, Scotland, September 4-7, 2007.

3. Aggrey G. H. et al.: “Data Richness and Reliability in Smart-Field Management – Is

There Value?”, SPE 102867 presented at SPE Annual Technical Conference and

Exhibition, San Antonio, Texas, September 24-27, 2006.

4. Ajayi, A. and Konopczynski, M. R.: “Intelligent-Well Technology Reduced Water

Production in a Multilateral Oil Producer”, SPE 102982 presented in the SPE Annual

Technical Conference and Exhibition, San Antonio, September 24-27 2006.

5. Barreto C. E. A. G. et al.: “Use of Water Cut to Optimize Conventional and Smart

Wells”, SPE 150908 presented at the North Africa Technical Conference and Exhibition,

Cairo, Egypt, February 20-22, 2012.

6. Behrouz* T., et al.: “Economic Evaluation of Smart Well Technology – A case Study”,

presented at the 14th

International Oil, Gas & Petrochemical Congress, Iran, 2010.

7. Brock W. R., et al.: “Application of Intelligent-Completion Technology in a Triple-Zone

Gravel Packed Commingled Producer”, SPE 101021 presented in the SPE Annual

Technical Conference and Exhibition, San Antonio, September 24-27, 2006.

Page 83: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 72

8. Dekui X. et al.: “Smart Well Technology in Daqing Oil Field”, SPE 161891 presented at

the Abu Dhabi International Petroleum Exhibition and Conference, Abu Dhabi, UAE,

November 11-14, 2012.

9. Elrandsen, S. M.: “Production Experience from Smart Wells in the Oseberg Field”, SPE

62953 presented in the SPE Annual Technical Conference and Exhibition, Dallas,

October 1-4, 2000.

10. Fowler M. L. et al.: “Some Practical Aspects Of Reservoir Management”, SPE 37333

presented at the 1996 SPE Eastern Regional Meeting, Columbus, Ohio, October 23-25,

1996.

11. Grebenkin I. M. and Davies D. R.: “Analysis of the Impact of an Intelligent Well

Completion on the Oil Production Uncertainty”, SPE 136335 presented at the 2010 SPE

Russian Oil & Gas Technical Conference and Exhibition, Moscow, Russia, October 26-

28, 2010.

12. Griffith C. R., Simon L. and Lien H. C. A.: “Evaluation of a Smart Well System at the

Saramacca Oil Fields – A Case Study”, SPE 157717 presented at the SPE 2012 Energy

Conference and Exhibition, Port of Spain, Trinidad, June 11-13, 2012.

13. Gulyaev D., Ipatov A. and Krichevskiy V.: “<<Smart wells>> is a key to production

enhancement from low permeable reservoirs”, SPE 159210 presented at the SPE Russian

Oil & Gas Exploration & Production Technical Conference and Exhibition, Moscow,

Russia, October 16-18, 2012.

14. Hudson J. D., Alves I. and Khoshkbarchi M.: “Formalization and Standardization of the

Smart Well Modeling Workflow”, SPE 145961 presented at the SPE Annual Technical

Conference and Exhibition, Denver, Colorado, October 30 – November 2, 2011.

Page 84: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 73

15. Jalali Y., Bussear T. and Sharma S.: “Intelligent Completions Systems – The Reservoir

Rationale”, SPE 50587 presented at the SPE European Petroleum Conference, The

Hague, Netherland, October 20-22, 1998.

16. Jansen J. D., et al.: “Smart Well Solutions for Thin Oil Rims: Inflow Switching and the

Smart Stinger Completion”, SPE 77942 presented at the SPE Asia Pacific Oil and Gas

Exhibition, Melbourne, Australia, October 8 -10, 2002.

17. Lau H. C.: “Good Practices in Progressing a Smart Well Portfolio”, IPTC 12255

presented at the International Petroleum Technology Conference, Kuala Lum pur,

Malaysia, December 3-5, 2008.

18. Lucas C., et al.: “Near – Wellbore Modeling to Assist Operation of an Intelligent

Multilateral Well in the Sherwood Formation”, SPE 71828 presented at the SPE Annual

Technical Conference and Exhibition, New Orleans, Louisiana, September 30 – October

3, 2001.

19. Main, M. A, Project Economics and Decision Analysis (Volume 1: Deterministic

Models), PennWell Corporation, Tulsa (2002), pp 262

20. Oracle, Crystall Ball User’s Manual, 2012.

21. Pari M. N., et al.: “Smart well Benefits, Type of Sensors, Challenges, Economic

Consideration, and Application in Fractured Reservoir”, SPE 126093 presented at the

SPE Saudi Arabia Section Technical Symposium, AlKhobar, Saudi Arabia, May 9-11,

2009.

22. Rodriguez J. C. and Figueroa A. R.: “Intelligent Completions and Horizontal Wells

Increase Production and Reduce Free-Gas and Water in Mature Fields”, SPE 139404

Page 85: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 74

presented at the SPE Latin American and Caribbean Petroleum Engineering Conference,

Lima, Peru, December 1-3, 2010.

23. Sakowski, S. A., Andersen, A. and Furui, K.: “Impact of Intelligent Well System on Total

Economics of Field Development”, SPE 94672 presented in the SPE Hydrocarbon

Economics and Evaluation Symposium, Society of Petroleum Engineers: Dallas, April 3-

5, 2005.

24. Satter A., Varnon J. E. and Hoang M. T.: “Integrated Reservoir Management”, SPE

22350 first presented at the SPE International Meeting on Petroleum Engineering,

Beijing, China, March 24-27, 1992.

25. Sharma A. K. et al.: “Quantifying Value Creation from Intelligent Completion

Technology Implementation”, SPE 78277 presented at the SPE 13th

European Petroleum

Conference, Aberdeen, Scotland, October 29-31, 2002.

26. Silva M. F. Jr., Muradov K. M. and Davies D. R.: “Review, Analysis and Comparison of

Intelligent Well Monitoring Systems”, SPE 150195 presented at the SPE Intelligent

Energy International, Utrecht, The Netherlands, March 27-29, 2012.

27. Vachon G. and Furui K.: “Production Optimization in ESP Completions with Intelligent

Well Technology by Using Downhole Chokes to Optimize ESP Performance”, SPE

93621 presented at the 14th

SPE Middle East Oil and Gas Show and Conference, Bahrain,

March 12-15, 2005.

28. Valvatne P. H., et al.: “Efficient Modeling of Nonconventional Wells with Downhole

Inflow Control Devices”, Journal of Petroleum Science and Engineering, Vol 39, pp. 99 –

116.

Page 86: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 75

29. Veneruso A. F., et al.: “Reliability Qualification Testing for Permanently Installed

Wellbore Equipment”, SPE 62955 presented at the SPE Annual Technical Conference

and Exhibition, Dallas, Texas, October 1- 4, 2000.

30. Verga F.: Intelligent Well Completion State of the Art and Trim Chokes Optimization

Lecture, Eni Corporate University, October 24-25, 2006.

31. Yeten B., et al.: “Decision Analysis under Uncertainty for Smart Well Deployment”,

Journal of Petroleum Science and Engineering. 43 (2004), pp. 183-199

32. Yeten B. and Jalali Y.: “Effectiveness of Intelligent Completions in a Multiwell

Development Context”, SPE 68077 presented at the SPE Middle East Oil Show, Bahrain,

March 17-20, 2001.

33. Yu S., Davies D. R., and Sherrard D. W.: “The Modeling of Advanced Intelligent Well,

An Application”, SPE 62950 presented at the SPE Annual Technical Conference and

Exhibition, Dallas, October 1-4, 2000.

34. http://petrowiki.spe.org/PEH%3AIntelligent_Well_Completions, Accessed January 2, 2013.

Page 87: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 76

APPENDIX

APPENDIX A: SAMPLE ECONOMIC ANALYSIS CALCULATION

For Case Study 1:

Table A1: NPV calculation for IWC

Time Annual Cum Oil Price Oil price Gross Royalty Net CAPEX OPEX Depreciation

(Year) Production Produced Deflator Revenue

Revenue

(bbl) (bbl) $/bbl MM$ MM$ MM$ MM$ MM$ MM$

0 0 0 1.00 60.0 0 0 0 9 0.00

1 470192 470192 1.03 61.5 28.92 1.45 27.47 1.41 3.60

2 286876 757068 1.05 63.0 18.08 0.90 17.18 0.86 2.16

3 291770 1048838 1.08 64.6 18.85 2.36 16.50 0.88 1.30

4 315587 1364425 1.10 66.2 20.90 2.61 18.29 0.95 0.78

5 314439 1678864 1.13 67.9 21.35 2.67 18.68 0.94 0.47

6 313533 1992397 1.16 69.6 21.82 2.73 19.09 0.94

TOTAL 1992397 5.98

Page 88: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 77

Table A1: NPV calculation for IWC (Continuation)

Total Tax Loss Taxable Income After Tax Cum. Discounted

Deduction Income Tax, MM$ NCF NCF NCF

MM$ MM$ MM$ 45% MM$ MM$ MM$

1.80 (1.80) (9.00) (9.00) (9.00)

5.01 (1.80) 20.66 9.30 16.76 7.76 14.90

3.02 14.16 6.37 9.95 17.71 7.86

2.17 14.32 6.45 9.17 26.89 6.44

1.72 16.56 7.45 9.89 36.77 6.17

1.41 17.27 7.77 9.96 46.74 5.53

0.94 18.15 8.17 9.98 56.72 4.92

Total 36.83

Table A2: NPV calculation for Conventional Completion

Annual Cum Oil Deflator Oil price Gross Royalty Net CAPEX OPEX Depreciation

Time Production Produced Revenue

Revenue

(Year) (bbl) (bbl) $/bbl MM$ MM$ MM$ MM$ MM$ MM$

0 0 0 1.00 60.0 0.0000 0.000 0.000 7

1 469658 469658 1.03 61.5 28.8840 1.444 27.440 2.41 2.80

2 269734 739392 1.05 63.0 17.0034 0.850 16.153 1.81 1.68

3 228100 967492 1.08 64.6 14.7383 0.737 14.001 1.68 1.01

4 225000 1192492 1.10 66.2 14.9015 1.863 13.039 1.68 0.60

5 215000 1407492 1.13 67.9 14.5952 1.824 12.771 1.65 0.36

6 200000 1607492 1.16 69.6 13.9163 1.740 12.177 1.60

TOTAL 1607492 10.82

Page 89: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 78

Table A2: NPV calculation for Conventional Completion (Continuation)

Total Tax Loss Taxable Income After Tax Cum. Discounted

Deduction Income Tax, MM$ NCF NCF NCF

MM$ MM$ MM$ 45% MM$ MM$ MM$

1.40 (1.40) (7.00) (7.00) (7.00)

5.21 (1.40) 20.83 9.37 15.66 8.66 13.92

3.49 12.66 5.70 8.65 17.30 6.83

2.69 11.31 5.09 7.23 24.53 5.08

2.28 10.76 4.84 6.52 31.05 4.07

2.01 10.76 4.84 6.28 37.33 3.49

1.60 10.58 4.76 5.82 43.15 2.87

Total 29.25

APPENDIX B: NPV PROBABILISTIC RESULTS FOR CASE STUDY 1

Figure B1: NPV uncertainty analysis for IWC

Page 90: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 79

Figure B2: NPV uncertainty analysis for Conventional Completion

Page 91: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 80

Figure B3: Spider Chart for both completions

APPENDIX C: NPV PROBABILISTIC RESULTS FOR CASE STUDY 2

Figure C1: NPV uncertainty analysis for IWC

40

50

60

70

80

0.9 0.7 0.5 0.3 0.1

Percentiles of the variables

NPV - IWC

Oil price

Income Tax

Oil price Inflation

Discount rate

CAPEX

30

35

40

45

50

55

60

0.9 0.7 0.5 0.3 0.1

Percentiles of the variables

NPV - NON IWC

Oil price

Income Tax

Oil price Inflation

Workover cost per year

Discount rate

Page 92: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 81

Figure C2: NPV uncertainty analysis for NON -IWC

Figure C3: Spider Chart for both completions

100

120

140

160

180

0.9 0.7 0.5 0.3 0.1

Percentiles of the variables

NPV IWC

oil price

Income Tax

Oil price Inflation

Discount rate

Workover cost per year

80

100

120

140

0.9 0.7 0.5 0.3 0.1

Percentiles of the variables

NPV - NON IWC

oil price

Income Tax

Oil price Inflation

Workover cost per year Discount rate

CAPEX

Page 93: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 82

APPENDIX D: NPV PROBABILISTIC RESULT FOR CASE STUDY 3

Figure D1: NPV uncertainty analysis for IWC

Page 94: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 83

APPENDIX E: NPV PROBABILISTIC RESULTS FOR CASE STUDY 4

For Well B-21B

Figure E1: NPV uncertainty analysis for IWC

Figure E2: NPV uncertainty analysis for NON -IWC

Page 95: QUANTIFYING INCREMENTAL OIL PRODUCTION AND …

Page 84

Figure E3: Spider Chart for both completions

100

120

140

160

180

200

0.9 0.7 0.5 0.3 0.1

Percentiles of the variables

NPV - IWC

Oil price

Income Tax

Oil price Inflation

Discount rate

CAPEX

80

90

100

110

120

130

140

0.9 0.7 0.5 0.3 0.1

Percentiles of the variables

NPV - NON IWC

Oil price

Income Tax

Oil price Inflation

Workover cost per year

Discount rate