5
December, 2016 Quaid-e-Azam Thermal Power (Private) Limited Invitation For Pre-Qualification (IFP) For Supply Of High Speed Diesel (HSD) To 1180 MW Combined Cycle Power Plant Bhikki, Sheikhupura, Punjab, Pakistan IFP NO. 4-RLNG-POWER PLANT (HSD) Prequalification Documents

Quaid-e-Azam Thermal Power (Private) Limited

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

December, 2016

Quaid-e-Azam Thermal Power (Private) Limited

Invitation For Pre-Qualification (IFP)

For Supply Of High Speed Diesel (HSD)

To 1180 MW Combined Cycle Power Plant Bhikki, Sheikhupura, Punjab, Pakistan

IFP NO. 4-RLNG-POWER PLANT (HSD)

Prequalification Documents

(1)

1. Project Background and Scope of Application

In connection with the Invitation for Prequalification (IFP) No. 4-RLNG-POWER PLANT (HSD), Quaid-e-Azam Thermal Power (Pvt.) Limited (QATPL), the Company, issues this Prequalification Document to Applicants interested and capable in bidding for the Supply of High Speed Diesel (HSD) to 1180 MW Combined Cycle Power Plant Bhikki (the Project).

QATPL is a private limited company, wholly owned by Government of Punjab and incorporated under the Companies Ordinance 1984. QATPL is setting up a 1180 MW (Gross) Combined Cycle Power Plant at Bhikki, Sheikhupura, 18km from Sheikhupura under the IPP (Independent Power Producer) regime. RLNG will be the primary fuel for the Plant whereas High Speed Diesel (HSD) will be used as a backup fuel. Configuration of the Plant comprises of two (02) GE Frame 9HA.01 Gas Turbines, two (02) Heat Recovery Steam Generators and one (01) Alstom Steam Turbine.

The Project is scheduled to be commissioned in phases; with both gas turbines expected to achieve commerical operation in simple cycle mode during the first quarter of 2017 whereas the plant will be commissioned in combined cycle mode in the last quarter of 2017.

In this regard, QATPL intends to procure High Speed Diesel (HSD) primarily for Testing & Commissioning of the Gas Turbines in December, 2016 – January, 2017 from established and reputable Oil Marketing Companies (OMCs).

The requisite quantity of High Speed Diesel (HSD) will be appoximately ten to fifteen million (10,000,000 –

15,000,000) liters, which may be increased or decreased at the time of sharing of Bidding Documents.

2. Qualification Criteria An Applicant shall fulfull the following criteria for prequalification;

(a) The Applicant must not have been declared ineligible / blacklisted by any Governmental / Semi-

Governmental agency / department. (b) The Applicant must submit audited Financial Statements for the last three (03) years to

demonstrate the current soundness of the Applicants financial position. (c) The Applicant must demonstrate a minimum average annual turnover of Fifty Billion Pakistani

Rupees (PKR 50,000,000,000) as reported in the financial statements, within the last three (03) years or a cumulative turnover of One Hundred and Fifty Billion Pakistani Rupees (PKR 150,000,000,000) over the last three (03) years.

(d) The Applicant must hold a valid NTN and Sales Tax Number. (e) The Applicant must hold a valid license from Oil & Gas Regulatory Authority (OGRA)

establishing the Oil Marketing Company (OMC) status of the Applicant for a minimum of the last seven (07) years.

(f) The Applicant must have an Oil Storage Depot in the District of Sheikhupura. 3. Documents to be Attached with the Applications

(a) Application Submission Sheet [As attached]. (b) Applicant Information Sheet [Form-1]. (c) Average Annual Turnover Sheet [Form-2]. (d) Valid NTN and STN Certificate. (e) Valid OGRA License establishing the OMC status of the Applicant. (f) Audited Financial Statements for the last three (03) years as mentioned above. (g) Original affidavit duly authenticated by the relevant government agency on non-judicial stamp

paper that the Applicant hasn’t been declared ineligible / blacklisted as per Clause 2.(a) above. (h) Any other documentary evidence required as per the abovementioned requirements.

4. Deadline for Submission of Applications

Applications shall be submitted by the Applicants through courier / express mail or by hand at the following address no later than 1500 hours [PST] on December 16, 2016; Attention: Mr. Khalid Parvaiz, (General Manager Admin & HR), Address: Quaid-e-Azam Thermal Power (Private) Limited, First Floor, 7-C-1 Gulberg III, Lahore, Pakistan Telephone: +92-42-35750936-8, Cell: +92-300-8824147

(2)

Application Submission Sheet

Date: ................................................... IFP No.: 4-RLNG-POWER PLANT (HSD)

Invitation for Prequalification for Supply of High Speed Diesel (HSD) for 1180 MW Combined Cycle Power Plant Bhikki, Bhikki, Punjab, Pakistan.

To: Mr. Khalid Parvaiz (General Manager HR & Admin), Quaid-e-Azam Thermal Power (Pvt.) Limited Address: Quaid-e-Azam, Thermal Power (Pvt.) Limited, 1st Floor,

7-C-1, Gulberg-III, Lahore, Pakistan Telephone: +92-42-35750936-8 Cell: +92-300-8824174

Facsimile number: +92-42-35750939, Email: [email protected] We, the undersigned, apply to be prequalified for the referenced IFP and declare the following: (a) We have examined and have no reservations to the Prequalification Documents.. (b) We have not been declared ineligible / blacklisted in accordance with Clause 2.(a). (c) We understand that you may cancel the prequalification process at any time and that you are not bound either to

accept any Application that you may receive or to invite the prequalified Applicants to bid for the subject contract of this prequalification, without incurring any liability to the Applicants.

(d) We agree to permit the Company or its representative to inspect our accounts and records and other documents

relating to the Application for prequalification and to have them audited by auditors appointed by the Company.

(e) All of the Forms accompanying the Application have duly been signed by the undersigned and stamped. Name ...................................................................................................................................................... In the capacity of .................................................................................................................................... Signed .................................................................................................................................................... ……………………………………..(Seal)… Duly authorized to sign the Application for and on behalf of ................................... (Name of Applicant) Date ........................................................................................................................................................ Witness # 1: Witness # 2:

Signature: ____________________ Signature: ____________________

Signed by: ____________________ Signed by: ____________________

Designation: __________________ Designation: __________________

Date: _________________________ Date: _________________________

Seal: _________________________ Seal: _________________________

(3)

Form – 1

Applicant Information Sheet

Date: ......................................... IFP No.: 4-RLNG-POWER PLANT (HSD) Page .............. of ............. pages

Applicant Information

Applicant’s legal name

Applicant’s year of constitution

Applicant’s legal address

Applicant’s authorized representative (name, address, telephone numbers, fax numbers, e-mail address)

OGRA OMC License No.

OGRA OMC Licesne Issuance Date

Oil Storage Depot Location in District Sheikhupura

Attached are copies of the following original documents.

q 1. Articles of incorporation or constitution of the legal entity named above.

q 2. Authorization to represent the firm named in above.

q 3. License issued by Oil & Gas Regulatory Authority (OGRA) establishing the Oil Marketing Company (OMC) status of the Applicant.

q 4. Documentary evidence to support OMCs’ Oil Storage Depot location; such as certificates / NOCs from Depratment of Explosives or any other competent Government Agency, and OCAC Oil Report.

(4)

Form – 2 Average Annual Turnover Sheet

Applicant’s Legal Name: .............................................. Date: ............................................... IFP No.: 4-RLNG-POWER PLANT (HSD)

Page .............. of ............. pages

Each Applicant must fill in this form

Annual Turnover Data for the Last Three (03)- Years

Year Amount (Pakistani Rupees, in words) Amount (Pakistani Rupees, in figures)

Average Annual Turnover

The information supplied should be the Annual Turnover of the Applicant in terms of the amounts recognized for each year in Pakistani Rupees (PKR). This should be consistent with the amounts reported in the audited accounts.