QS in BS

Embed Size (px)

Citation preview

  • 7/30/2019 QS in BS

    1/19

    Frequent Problems encounteredFrequent Problems encountered

    by QS in Building Services Worksby QS in Building Services Works

    The Hong Kong Institute of SurveyorsThe Hong Kong Institute of Surveyors

    CPD EventCPD Event

    19 October 200519 October 2005

  • 7/30/2019 QS in BS

    2/19

    What is Building ServicesWhat is Building ServicesWorks ?Works ?

    Electrical Installations

    Mechanical Ventilation Installations Air Conditioning Installations

    Fire Services Installations Extra Low Voltage Installations

  • 7/30/2019 QS in BS

    3/19

    Electrical Installations

    Mains Installations

    Sub-mains Installations

    Standby Power Supply

    Cable Containment

    Lighting Installations Power Installations

    Busbar / Busduct Lightning Installations

    Earthing and Bonding

    General Works (Sundries)

  • 7/30/2019 QS in BS

    4/19

    Mechanical Ventilation &

    Air Conditioning Installations

    Condenser Water System

    Chilled Water Installations Condensate Drainage Installation

    Air Conditioning Installation Mechanical Ventilation Installation

    Smoke Extraction System

    Staircase Pressurization System

    Automatic Temperature Control System

    General Works (Sundries)

  • 7/30/2019 QS in BS

    5/19

    Fire Services Installations

    Incoming Water Supply Main

    Fire Hydrant and Hose reel System

    Automatic Sprinkler System

    Drencher System FM200 System / CO2 System

    Automatic Fire Alarm System Portable Fire Extinguishers

    General Works (Sundries)

  • 7/30/2019 QS in BS

    6/19

    Extra Low Voltage Installations

    CCTV System

    CABD Installation PABX Installation

    BGM System Door Access Control System

    Patrol Guard System

    Cable TV Installation

    Satellite TV System

    Broadband Installation

  • 7/30/2019 QS in BS

    7/19

    What are the problems frequentlyencountered by QS in building servicesworks ?

    An understanding of the nature of the various buildingservices works

    Cost estimating of building services works

    Measurement of building services works Packaging of works

    Tender documentation

    Contractual arrangement

    Design liability

    Valuation of interim payment

    Assessment of variation works

    Assessment of unit rates Evaluation of variation works

  • 7/30/2019 QS in BS

    8/19

    What are the problems frequentlyencountered by QS in building servicesworks

    Procurement of equipment and materials Cash flow forecast

    Payment methodology

    Subletting Interfacing with builders works

    Evaluation of abortive works / redundant works

    Programming of works Extension of time claims

    Assessment of additional loss and expenses

    Completion criteria

    Defects liability scope, frequency, methods

  • 7/30/2019 QS in BS

    9/19

    Understanding of Building Services Installations

    1. Design

    1.1 Fan coil system vs VAV system

    1.2 Air cooled chiller vs water cooled chiller1.3 T5 vs T8 florescent fittings

    1.4 Ambient atmosphere indirect lighting

    2. Functions2.1 Building management system EBI / Metasys

    2.2 Busbar vs cabling

    2.3 Digital recording vs VHS recording3. Interfacing characteristics

    3.1 Acoustic treatment

    3.2 Fire rated protection TG pipework thru othercompartments

  • 7/30/2019 QS in BS

    10/19

    Measurement of Building Services Installations

    1. Hong Kong Standard Method of Measurement for

    Building Services Works (First Edition May 1993)

    2. Sec. C - Electrical InstallationsSec. D - Mechanical Installations

    Sec. E - Building Management, Security and Communication

    Installations2.1 system classification

    2.2 works coverage (e.g. FE, cladding to air duct)

    2.3 application (final circuit / wiring & conduits)3. Things to note:

    3.1 interfacing related with building works

    3.2 phasing of works3.3 packaging of works

  • 7/30/2019 QS in BS

    11/19

    Contractual Arrangement

    1. Works packaging separate packages or all-in-one

    package1.1 technical complexity

    1.2 specialization1.3 value of works1.4 coordination complexity

    1.5 programming of works2. Lump Sum or Re-measurement

    2.1 nature of the works2.2 basis of tender information

    2.3 basis of final approved information2.4 basis of measurement

  • 7/30/2019 QS in BS

    12/19

    Things to note in preparing the Building

    Services Tender / Contract Document1. commencement of works - conditions

    2. completion of works - criteria

    3. phase completion may affect

    - programming of works

    - system handover- defects liability period

    - release of retention money

    - temporary installations prior to full completionof a particular system

    - maintenance works for partial running prior to

    the full completion of a particular system

  • 7/30/2019 QS in BS

    13/19

    Programming of Works

    1. drawings submission2. materials / equipment submission

    3. equipment & materials ordering / manufacture /delivery

    4. associated builders works requirements

    5. works installation- 1stfix

    - 2nd fix

    - final fix6. testing and commissioning7. critical path

  • 7/30/2019 QS in BS

    14/19

    Payment for Building Services Works

    1. Progress / Stage / Milestone interim payment

    2. Payment for engineering works

    3. Payment for materials on site and off site4. Payment assessment

    - 1stfix

    - 2nd fix- final fix

    - T&C

    5. Payment withheld for submission of T&C records,

    as-built drawings / records, O&M manual

    6. Back to Back / Pay when Paid

  • 7/30/2019 QS in BS

    15/19

    Variation Works for Building Services

    Works

    1. Entitlements

    1.1 change in builders works1.2 change in level of suspended ceiling

    1.3 change in door opening direction

    1.4 re-partitioning1.5 change in room function (e.g. from pantry to

    kitchen)

    1.6 addition of metal framework at external wall

    1.7 revision in fire compartmentation

    1.8 as required in statutory inspections

  • 7/30/2019 QS in BS

    16/19

    2. Quantum Assessment- basis of measurement

    - change in one item may lead to corresponding changes

    in other items (e.g. addition of lighting circuits will leadto addition of lighting switches; omission of false ceiling

    may lead to addition of slim duct to insulated refrigerant

    pipe work or cladding to chilled water pipe work)

    3. Rates Assessment

    - contract rates- pro-rata rates

    - star rates

    Variation Works for M&E Works (Contd)

  • 7/30/2019 QS in BS

    17/19

    4. Abortive Works

    - entitlement

    - evaluation

    5. Miscellaneous Works

    - draining and refilling- testing and commissioning

    - cleaning of works (e.g. air purging, chemical

    treatment)- refueling works

    - spare parts and tools

    Variation Works for M&E Works (Contd)

  • 7/30/2019 QS in BS

    18/19

    Extension of Time Claim

    1. Shop Drawings Submission & Approval

    2. Sample / Materials Submission & Approval

    3. Statutory Submission for Consent & Approval (e.g.

    necessary for licensing)

    4. Delivery of materials and equipment

    5. Pre-requisite builders works

    6. Testing and Commissioning

  • 7/30/2019 QS in BS

    19/19

    ~ END ~

    Thank you for coming