Frequent Problems encounteredFrequent Problems encountered
by QS in Building Services Worksby QS in Building Services Works
The Hong Kong Institute of SurveyorsThe Hong Kong Institute of Surveyors
CPD EventCPD Event
19 October 200519 October 2005
7/30/2019 QS in BS
2/19
What is Building ServicesWhat is Building ServicesWorks ?Works ?
Electrical Installations
Mechanical Ventilation Installations Air Conditioning Installations
Fire Services Installations Extra Low Voltage Installations
7/30/2019 QS in BS
3/19
Electrical Installations
Mains Installations
Sub-mains Installations
Standby Power Supply
Cable Containment
Lighting Installations Power Installations
Busbar / Busduct Lightning Installations
Earthing and Bonding
General Works (Sundries)
7/30/2019 QS in BS
4/19
Mechanical Ventilation &
Air Conditioning Installations
Condenser Water System
Chilled Water Installations Condensate Drainage Installation
Air Conditioning Installation Mechanical Ventilation Installation
Smoke Extraction System
Staircase Pressurization System
Automatic Temperature Control System
General Works (Sundries)
7/30/2019 QS in BS
5/19
Fire Services Installations
Incoming Water Supply Main
Fire Hydrant and Hose reel System
Automatic Sprinkler System
Drencher System FM200 System / CO2 System
Automatic Fire Alarm System Portable Fire Extinguishers
General Works (Sundries)
7/30/2019 QS in BS
6/19
Extra Low Voltage Installations
CCTV System
CABD Installation PABX Installation
BGM System Door Access Control System
Patrol Guard System
Cable TV Installation
Satellite TV System
Broadband Installation
7/30/2019 QS in BS
7/19
What are the problems frequentlyencountered by QS in building servicesworks ?
An understanding of the nature of the various buildingservices works
Cost estimating of building services works
Measurement of building services works Packaging of works
Tender documentation
Contractual arrangement
Design liability
Valuation of interim payment
Assessment of variation works
Assessment of unit rates Evaluation of variation works
7/30/2019 QS in BS
8/19
What are the problems frequentlyencountered by QS in building servicesworks
Procurement of equipment and materials Cash flow forecast
Payment methodology
Subletting Interfacing with builders works
Evaluation of abortive works / redundant works
Programming of works Extension of time claims
Assessment of additional loss and expenses
Completion criteria
Defects liability scope, frequency, methods
7/30/2019 QS in BS
9/19
Understanding of Building Services Installations
1. Design
1.1 Fan coil system vs VAV system
1.2 Air cooled chiller vs water cooled chiller1.3 T5 vs T8 florescent fittings
1.4 Ambient atmosphere indirect lighting
2. Functions2.1 Building management system EBI / Metasys
2.2 Busbar vs cabling
2.3 Digital recording vs VHS recording3. Interfacing characteristics
3.1 Acoustic treatment
3.2 Fire rated protection TG pipework thru othercompartments
7/30/2019 QS in BS
10/19
Measurement of Building Services Installations
1. Hong Kong Standard Method of Measurement for
Building Services Works (First Edition May 1993)
2. Sec. C - Electrical InstallationsSec. D - Mechanical Installations
Sec. E - Building Management, Security and Communication
Installations2.1 system classification
2.2 works coverage (e.g. FE, cladding to air duct)
2.3 application (final circuit / wiring & conduits)3. Things to note:
3.1 interfacing related with building works
3.2 phasing of works3.3 packaging of works
7/30/2019 QS in BS
11/19
Contractual Arrangement
1. Works packaging separate packages or all-in-one
package1.1 technical complexity
1.2 specialization1.3 value of works1.4 coordination complexity
1.5 programming of works2. Lump Sum or Re-measurement
2.1 nature of the works2.2 basis of tender information
2.3 basis of final approved information2.4 basis of measurement
7/30/2019 QS in BS
12/19
Things to note in preparing the Building
Services Tender / Contract Document1. commencement of works - conditions
2. completion of works - criteria
3. phase completion may affect
- programming of works
- system handover- defects liability period
- release of retention money
- temporary installations prior to full completionof a particular system
- maintenance works for partial running prior to
the full completion of a particular system
7/30/2019 QS in BS
13/19
Programming of Works
1. drawings submission2. materials / equipment submission
3. equipment & materials ordering / manufacture /delivery
4. associated builders works requirements
5. works installation- 1stfix
- 2nd fix
- final fix6. testing and commissioning7. critical path
7/30/2019 QS in BS
14/19
Payment for Building Services Works
1. Progress / Stage / Milestone interim payment
2. Payment for engineering works
3. Payment for materials on site and off site4. Payment assessment
- 1stfix
- 2nd fix- final fix
- T&C
5. Payment withheld for submission of T&C records,
as-built drawings / records, O&M manual
6. Back to Back / Pay when Paid
7/30/2019 QS in BS
15/19
Variation Works for Building Services
Works
1. Entitlements
1.1 change in builders works1.2 change in level of suspended ceiling
1.3 change in door opening direction
1.4 re-partitioning1.5 change in room function (e.g. from pantry to
kitchen)
1.6 addition of metal framework at external wall
1.7 revision in fire compartmentation
1.8 as required in statutory inspections
7/30/2019 QS in BS
16/19
2. Quantum Assessment- basis of measurement
- change in one item may lead to corresponding changes
in other items (e.g. addition of lighting circuits will leadto addition of lighting switches; omission of false ceiling
may lead to addition of slim duct to insulated refrigerant
pipe work or cladding to chilled water pipe work)
3. Rates Assessment
- contract rates- pro-rata rates
- star rates
Variation Works for M&E Works (Contd)
7/30/2019 QS in BS
17/19
4. Abortive Works
- entitlement
- evaluation
5. Miscellaneous Works
- draining and refilling- testing and commissioning
- cleaning of works (e.g. air purging, chemical
treatment)- refueling works
- spare parts and tools
Variation Works for M&E Works (Contd)
7/30/2019 QS in BS
18/19
Extension of Time Claim
1. Shop Drawings Submission & Approval
2. Sample / Materials Submission & Approval
3. Statutory Submission for Consent & Approval (e.g.
necessary for licensing)
4. Delivery of materials and equipment
5. Pre-requisite builders works
6. Testing and Commissioning
7/30/2019 QS in BS
19/19
~ END ~