2
PIPING REINSTATEMENT CHECKLIST Form TP-09 YES N / A 1 Check Hydrostatic Testing has been satisfactorily Completed and recorded 2 Flushing Drainage of Lines completed and accepted 3 Check that Correct Bolts and Gaskets installed at all Mechanical Joints. 4 Check that All Vents and Drains are correctly installed. 5 Check that all temporaru Vents and drains comply with Piping Specification. 6 Check that All Process Blinds and Spades have been correctly installed as indicated on the P & ID 7 Check that Spectacle Blinds are in the correct 'Flow' position. 8 Check that all Pipe cleaning, and Pickling has been satisfactorily completed and recorded. 9 Check that Control Valves have been installed in the correct 'Flow' position. 10 Check that specified Block valves have locking devices correctly installed. 11 Check that all Valves are functioning properly and that spindles have been coated with 'Copa-Slip' or equivalent where specified. 12 Check that chain wheels for specified Valves have been correctly installed 13 Check that extended spindles required for specified Valves have been installed 14 Check that Relief Valves have been correctly installed 15 Check that all Thermowells have been correctly installed. 16 Check that Restriction and Orifice plates have been correctly installed 17 Check that all Pump Suction Strainers have been correctly installed. 18 Check for correct Flow through Filters& Strainers, Traps, Check Valves, and Globe Valves. 19 Check that all Gags have been removed from Spring loaded Pipe supports, and Expansion Bellows. 20 Check that all Pipe Seals have been correctly fitted. 21 Lines Released for Painting 22 Heat Tracing Superintendent informed Lines released for painting 23 Insulation Superintendent informed Lines released for painting For Items Marked 'No' Punch List has to be raised Remarks. COMPLETED BY Subcontractor TPC DQR / PMC NAME SIGNATURE DATE

QCF301 TP11 Reinstatement Checklist

  • Upload
    minhnn

  • View
    299

  • Download
    16

Embed Size (px)

DESCRIPTION

form

Citation preview

Page 1: QCF301 TP11 Reinstatement Checklist

PIPING REINSTATEMENT CHECKLIST Form TP-09

YES N / A NO1 Check Hydrostatic Testing has been satisfactorily Completed and recorded

2 Flushing Drainage of Lines completed and accepted

3 Check that Correct Bolts and Gaskets installed at all Mechanical Joints.

4 Check that All Vents and Drains are correctly installed.

5 Check that all temporaru Vents and drains comply with Piping Specification.

6 Check that All Process Blinds and Spades have been correctly installed

as indicated on the P & ID

7 Check that Spectacle Blinds are in the correct 'Flow' position.

8 Check that all Pipe cleaning, and Pickling has been satisfactorily completed

and recorded.

9 Check that Control Valves have been installed in the correct 'Flow' position.

10 Check that specified Block valves have locking devices correctly installed.

11 Check that all Valves are functioning properly and that spindles have been

coated with 'Copa-Slip' or equivalent where specified.

12 Check that chain wheels for specified Valves have been correctly installed

13 Check that extended spindles required for specified Valves have been installed

14 Check that Relief Valves have been correctly installed

15 Check that all Thermowells have been correctly installed.

16 Check that Restriction and Orifice plates have been correctly installed

17 Check that all Pump Suction Strainers have been correctly installed.

18 Check for correct Flow through Filters& Strainers, Traps, Check Valves,

and Globe Valves.

19 Check that all Gags have been removed from Spring loaded Pipe supports,

and Expansion Bellows.

20 Check that all Pipe Seals have been correctly fitted.

21 Lines Released for Painting

22 Heat Tracing Superintendent informed Lines released for painting

23 Insulation Superintendent informed Lines released for painting

For Items Marked 'No' Punch List has to be raised

Remarks.

COMPLETED BY Subcontractor TPC DQR / PMC

NAME

SIGNATURE

DATE