QNU
Earned Value Management They Say I
have to Do It,But Why???
By Ursula Kuehn, PMP, EVPUQN and Associates
QNU History of EVMS
• 1962-1965 PERT/Cost on Minuteman Missile• 1965 USAF created CSPCS (35 criteria)• 1967-1996 DOD issued C/SCSC (35 same
criteria)• 1996 DOD EVMS (NDIA initiative) (32 criteria)
• 1998 ANSI/EIA-Standard 748 (32 same criteria)
QNU
What Size of Project Requires EVMS?
• DoD requires on projects > $20M• DoT requires on projects > $6M• Dept. of Ed. requires on projects > $2M,
with a lighter version for projects < $2M
Do we see a trend?
QNU
10 Easy Steps for EVMS on all Projects
1. Define the project scope via a WBS2. Determine who will perform the work and
what it might cost3. Plan & schedule the defined work for the
agreed upon scope4. Determine points of management control5. Authorize budgets for the baselined plan
Adapted from Earned Value Management Project Management, Third Edition, Fleming and Koppelmen
QNU
10 Easy Steps for EVMS on all Projects (continued)
6. Define metrics to measure performance of work within each control point
7. Record actual costs of the work8. Measure control point performance and
determine project performance9. Forecast future performance10.Manage changes to the agreed upon
baseline
QNU The WBS
Ursula’s Pond
Hole Liner Water Livestock Plants Test Pond
Design Pond
Project Management
QNU
Hole
Move Earth
Trees PlantsDisposal Equipment
Earth
Removal Equipment
Environmental Study
Earth Removal Earth Disposal
Garden
Take the Requirements Analysis to the Hole of the
Pond
QNU
Water
Water In Water Removal
Water Circulates
Take the Requirements Analysis to the Water of the
Pond
QNU $113.85
$71.35
$2.50$68.85
$93.45
$23.45$45.00$25.00
$50.00
$42.50
$2.50
$140.45
$40.00$7.50$107.95$25.00
$102.50
$17.50$60.00$25.00
$531.00
$30.00$90.00$411.00
$35.00
$136.95
$17.50$2.50$91.95$25.00
$240.20
$109.35$64.35$25.00
$41.50
$2.50$106.85$2.50$61.85$2.50$39.00
Pond
1234
Plants
1234.5
Livestock
1234.6
Water
1234.4
Rock Border
1234.7
Liner
1234.3
Pump
1234.8
Hole
1234.2
Inspect Pond
1234.9
Design Pond
1234.1
Design Hole
1234.2.1
Dig Hole
1234.2.2
Inspect Hole
1234.2.3
Design Liner
1234.3.1Buy Liner
1234.3.2
Install Liner
1234.3.3
Fill Pond
1234.4.2
Test Water
1234.4.3
Design Water
1234.4.1
Bog Plants
1234.5.3
Floating Plants
1234.5.4Oxygenating Plants
1234.5.2
Design Plants
1234.5.1
Install Oxy. Plants
1234.5.2.2
Buy Oxy. Plants
1234.5.2.1
Buy Bog Plants
1234.5.3.1
Install Bog Plants
1234.5.3.2
Buy Floating Plants
1234.5.4.1
Install Floating Plants
1234.5.4.2
Fish
1234.6.1
Snails
1234.6.2
Buy Fish
1234.6.1.1
Install Fish
1234.6.1.2
Install Snails
1234.6.2.2
Buy Snails
1234.6.2.1
Build Waterfall
1234.7.3
Buy Rock
1234.7.1
Install Border
1234.7.2
Buy Pump
1234.8.2
Install Pump
1234.8.3
Design Pump
1234.8.1
Test Waterfall
1234.8.4
$1,743.55
QNU
Planning and Scheduling the Defined Work
END
Work Package G
24
22
0
16 21
15 20
14 21
14 21
22 24
18 20
21
21 24
6
14
6 14
6 10
10 14
7 16
6 15
6
6
0
15 18
19
Work Package I
Work Package H
Work Package E
Work Package F
Work Package B
Work Package C
Work Package D
Work Package A
QNU $113.85
$71.35
$2.50$68.85
$93.45
$23.45$45.00$25.00
$50.00
$42.50
$2.50
$140.45
$40.00$7.50$107.95$25.00
$102.50
$17.50$60.00$25.00
$531.00
$30.00$90.00$411.00
$35.00
$136.95
$17.50$2.50$91.95$25.00
$240.20
$109.35$64.35$25.00
$41.50
$2.50$106.85$2.50$61.85$2.50$39.00
Pond
1234
Plants
1234.5
Livestock
1234.6
Water
1234.4
Rock Border
1234.7
Liner
1234.3
Pump
1234.8
Hole
1234.2
Inspect Pond
1234.9
Design Pond
1234.1
Design Hole
1234.2.1
Dig Hole
1234.2.2
Inspect Hole
1234.2.3
Design Liner
1234.3.1Buy Liner
1234.3.2
Install Liner
1234.3.3
Fill Pond
1234.4.2
Test Water
1234.4.3
Design Water
1234.4.1
Bog Plants
1234.5.3
Floating Plants
1234.5.4Oxygenating Plants
1234.5.2
Design Plants
1234.5.1
Install Oxy. Plants
1234.5.2.2
Buy Oxy. Plants
1234.5.2.1
Buy Bog Plants
1234.5.3.1
Install Bog Plants
1234.5.3.2
Buy Floating Plants
1234.5.4.1
Install Floating Plants
1234.5.4.2
Fish
1234.6.1
Snails
1234.6.2
Buy Fish
1234.6.1.1
Install Fish
1234.6.1.2
Install Snails
1234.6.2.2
Buy Snails
1234.6.2.1
Build Waterfall
1234.7.3
Buy Rock
1234.7.1
Install Border
1234.7.2
Buy Pump
1234.8.2
Install Pump
1234.8.3
Design Pump
1234.8.1
Test Waterfall
1234.8.4
$1,743.55
QNU
Allocating the Budget
Work Package G
$3,000
24
22
END0
16 21
15 20
14 21
14 21
22 24
18 20
21
21 24
6
14
6 14
6 10
10 14
7 16
6 15
6
6
0
15 18
19
Work Package I$2,000
Work Package H
$3,000
Work Package E
$7,000
Work Package F
$5,000
Work Package B
$8,000
Work Package C
$4,000
Work Package D$9,000
Work Package A
$6,000
QNU Baseline the Plan
Performance Measurement Baseline (PMB)
$0
$10,000
$20,000
$30,000
$40,000
$50,000
1 2 3 4 5 6 7 8 9 1011 121314 151617 181920 212223 2425
Day
QNU How to Measure Progress
• Effort/(Effort + Remaining)• Physical % Complete• Weighted Milestones or
Inchstones• 50/50 Rule, 20/80 Rule, 0/100
Rule• Others, all used to determine a
% Complete
QNU The Planned Value (PV)
24
22
END0
16 21
15 20
14 21
14 21
22 24
18 20
21
21 24
6
14
6 14
6 10
10 14
7 16
6 15
6
6
0
15 18
19
Task I$2,000
Task H$3,000
Task E$7,000
Task F$5,000
Task G$3,000
Task B$8,000
Task C$4,000
Task D$9,000
Task A$6,000
QNU The PV Continued
Task Total Task Budget Planned Value (PV)As of Day 10
A $6,000.00 $6,000.00
B $8,000.00 $4,000.00
C $4,000.00 $4,000.00
D $9,000.00 $4,000.00
Project $47,000.00 $18,000.00
QNU The PV Continued
Performance Measurement Baseline (PMB)
$0
$10,000
$20,000
$30,000
$40,000
$50,000
1 2 3 4 5 6 7 8 9 1011 121314 151617 181920 212223 2425
Day
Data Date
QNU The EV Continued
Task Total Task Budget Planned Value (PV)As of Day 10
% Comp
Earned Value (EV)As of Day 10
A $6,000.00 $6,000.00 100% $6,000.00
B $8,000.00 $4,000.00 25% $2,000.00
C $4,000.00 $4,000.00 75% $3,000.00
D $9,000.00 $4,000.00 50% $4,500.00
Project $47,000.00 $18,000.00 $15,500.00
QNU EV Analysis
Performance Measurement Baseline (PMB)
$0
$10,000
$20,000
$30,000
$40,000
$50,000
1 3 5 7 9 11 13 15 17 19 21 23 25Day
PMB
EVAC
QNU Variances
PVEV(SV) Variance Schedule
ACEV(CV) VarianceCost
Positive Negative
SV Ahead of schedule Behind schedule
CV Under budget Over budget
QNU Cost Variance
Performance Measurement Baseline (PMB)
$0
$10,000
$20,000
$30,000
$40,000
$50,000
1 3 5 7 9 11 13 15 17 19 21 23 25Day
PMB
EVAC
CV
QNU EVA Examples
PV = $45,000
EV = $35,000
AC = $40,000
SV = -$10,000
CV = -$5,000
SPI = 0.78
CPI = 0.86
PV = $145,000
EV = $135,000
AC = $140,000
SV = -$10,000
CV = -$5,000
SPI = 0.93
CPI = 0.96
QNU
.79.94.83
.92
.96
1.00
.87
.92
.99
.921.03.98
.98Pond
1234
Plants
1234.5
Livestock
1234.6
Water
1234.4
Rock Border
1234.7
Liner
1234.3
Pump
1234.8
Hole
1234.2
Inspect Pond
1234.9
Design Pond
1234.1
Design Hole
1234.2.1
Dig Hole
1234.2.2
Inspect Hole
1234.2.3
Design Liner
1234.3.1Buy Liner
1234.3.2
Install Liner
1234.3.3
Fill Pond
1234.4.2
Test Water
1234.4.3
Design Water
1234.4.1
Bog Plants
1234.5.3
Floating Plants
1234.5.4Oxygenating Plants
1234.5.2
Design Plants
1234.5.1
Install Oxy. Plants
1234.5.2.2
Buy Oxy. Plants
1234.5.2.1
Buy Bog Plants
1234.5.3.1
Install Bog Plants
1234.5.3.2
Buy Floating Plants
1234.5.4.1
Install Floating Plants
1234.5.4.2
Fish
1234.6.1
Snails
1234.6.2
Buy Fish
1234.6.1.1
Install Fish
1234.6.1.2
Install Snails
1234.6.2.2
Buy Snails
1234.6.2.1
Build Waterfall
1234.7.3
Buy Rock
1234.7.1
Install Border
1234.7.2
Buy Pump
1234.8.2
Install Pump
1234.8.3
Design Pump
1234.8.1
Test Waterfall
1234.8.4
QNU
Project Control Chart
0.800.850.900.951.001.051.101.151.20
1 3 5 7 9 11 13 15 17 19 21 23
Day
CPI
SPI
Basing Your Stoplight on Your CPI
QNU
The Estimate At Completion (EAC)
• Forecasts possible project outcome based on past performance
– Calculating the EAC with just the CPI
– Calculating the EAC with both the CPI and SPI
CPI
BACEAC
SPICPI
)EVBAC(ACEAC
Note: EAC always has the caveat “…if things do not change…”
QNU
Other Forecasting Formulas
• The estimate to complete (ETC)
• The variance at completion (VAC)
• The to-complete performance index (TCPI)
EACBACVAC
ACEACETC
ACBAC
EVBACTCPI
QNU
The Change Control Process
• Establish a change control board (CCB)
• Require the use of change request forms
• Keep a change control log
• For each approved change, a new PMB is established