Put Title Here
Put date or other info here
December 20, 2018
Owner and Design Team
Grinnell College HSSC Project
Leadership Team:
Mike Latham
Jim Swartz
Erik Simpson
Keith Brouhle
Rick Whitney
Dave Robinson
Larry Gleason
Keith Archer
Nancy Combs
Christi Baker
Jane Taylor
EYP Architects
Jennifer Amster
Eric Kern
Eric Petersen
Alison Ledwith
OPN Architects
Bill Catrenich
Pylar Eaton
McGough Project Team
Dustin Schwake – Project Executive
Matt Schroeder – Senior Project Manager
Josh Miltenberger – Senior Project Manager
Ryan Drew – Senior Project Manager
Jennifer Radniecki – Project Manager
Alex Maass – Assistant Project Manager
Amy Robinson – Project Coordinator
Chuck Carpenter – Senior Superintendent
Patrick Woodson – Assistant Superintendent
Subcontractors
1st Interiors
Advance Equipment Co.
All-American Scaffold
American Fence Co.
American Structural Metals
Architectural Wall Systems
Baker Electric
Baker Group
Bartley Sales
Bolander
CGA
DA Bunch
Danny’s Construction
Des Moines Marble
Floors by Beckers
Forman Ford
Heartland Finishes
J&M Roofing
Johnson Specialty Sales
KONE Elevator
Navetta
PAC-VAN
Pella Tree Service
Peterson Contractors, Inc.
Premier Edge
Pro-Bel
S&F Underground
Seedorff Masonry
Skold Companies
Soil-Tek
Summit Fire Protection
Superior Painting
Swanson & Youngdale
Waldinger Mechanical
Walsh Door & Security
Wilkie Sanderson
Wynn O. Jones
Current Highlights
Exterior:
Detail work on canopies, granite, exterior doors installed
South pavilion:
Final clean, A/V, furniture and finishes continue
Elevator inspection passed 12/13
Test and balance continues
North pavilion:
Flooring nearly complete, A/V, furniture and finishes continue
Elevator inspection passed 12/14
Test and balance continues
Atrium:
Glass handrail and WVP-1 assembly in progress
Finishes on hanger rods, columns continue
View from commencement
View of main courtyard / atrium
Loading dock entrance – south side
Sun dial set in courtyard
Dasil – lighting install – ceiling to wall fixture
1st floor south – anthropology lab
2nd floor south pavilion – main corridor looking south
2nd floor south – admin offices
2nd floor south – interior classroom
Tiered classroom – 3rd floor south pavilion
A/V progress – 3rd floor south
3rd floor north pavilion – ready for carpet
3rd floor south pavilion – main corridor looking south
Fire shutter – closed (for test)
1st floor atrium – note the light refraction (RAINBOW!)
View of ARH / halo
Finished acoustical plaster / GFRG column finish progress
Substrate in place for wood handrail slats – 3rd floor
View of courtyard
Glass handrail / exterior column progress
Upcoming Highlights
Smoke evacuation test scheduled for December 20th
AHJ / State Fire Marshall final inspection scheduled for December 27th
Finishes continue in atrium and select areas in each pavilion
Test and balance / Commissioning continues
Owner activities continue – A/V, furniture, furnishings
Owner move-in – scheduled to commence January 2nd