Upload
hoangliem
View
214
Download
0
Embed Size (px)
Citation preview
Purpose and Need
EASTBOUND WIDENING
The purpose of the project is to increase capacity in order to improve traffic operations and reduce congestion issues, as well as address safety needs between the Dulles Connector Road and Fairfax Drive.
TRANSFORM 66
Environmental Assessment Findings
EASTBOUND WIDENING
ENVIRONMENTAL RESOURCE RESOURCE SUMMARY
Property Impacts No relocations or displacements are anticipated. Minor permanent right of way acquisition (0.1 acre) and temporary/permanent easements (4.73 acres) associated with the Build Alternative would occur.
Community Facilities Impacts include enhancements to the Washington and Old Dominion Trail, Custis Trail and Bon Air Park.
Environmental Justice (Minority/Low-income)
No disproportionate impacts.
Historic Properties No adverse effect.
Section 4(f) Protected Properties* De minimis impacts to Washington and Old Dominion Trail, Custis Trail and Bon Air Park.
Noise Under the No Build Alternative, 236 receptors are predicted to be impacted, under the Build Alternative an additional 113 receptors are impacted (349 total). Approximately 3.7 miles (19,490 linear feet) of noise walls have been preliminarily identified to mitigate noise. This includes the replacement of existing noise walls.
Air Quality No adverse impacts to ambient air quality and no violation of the National Ambient Air Quality Standards.
Wetlands and Streams Impacts to 137.5 linear feet of stream and 0.6 acre of wetlands are expected.
Floodplains Impacts to 0.39 acre of the 100-year floodplain are anticipated.
Wooded Areas Permanent conversion of wooded areas within the proposed right of way for the Build Alternative is 0.05 acre. Impacts to 11.49 acres of wooded and semi-wooded areas within the existing VDOT right of way and 0.84 acre within areas of temporary easements.
Wildlife and Habitat Minimal impacts.
Threatened and Endangered Species
The federally listed species, the northern long-eared bat (NLEB), may be affected by the project. However, the project is within a highly-developed urban area, which the USFWS indicates is extremely unlikely to be suitable NLEB habitat.
*Public comment is invited on proposed de minimis impact findings for the Build Alternative on Section 4(f) resources, which include parks, trails and historic properties under the provisions of 23 CFR §774 (Section 4(f) of the U.S. Department of Transportation Act).
TRANSFORM 66
Schedule
EASTBOUND WIDENING
MILESTONE 2016 2017 2018 2019 2020
Revised Environmental Assessment and Federal Highway Administration Decision
Early
Begin Tolling and Implement Initial Multimodal Projects
Mid
Award Design-Build Contract Late
Construction Early Late
Open New Eastbound Lane Late
Timeline
PROGRAM OF IMPROVEMENTS
I-66 Transit/TDMStudy Final Report
December 2009
Secretary Layne Announced Inside the Beltway Plans
March 2015
Public Information Meetings on Tolling and MultimodalImprovements Project
June 2015
Public Information Meetings on Tolling and MultimodalImprovements Project
October 2015
CTB Public Meetingand Approval ofInside the Beltway Proposal
December 2015
Governor McAuliffeAnnounced BipartisanCompromise on Eastbound Widening February 10, 2016
Design Public Hearingson Tolling Gantries andSignage
March – April 2016
Public Availability of Tolling Environmental Document (Categorical Exclusion)
NVTC Open Houses and Public Hearings onMultimodal Components
May 2016
CTB Decision onMultimodal Projects
July 2016
Start TollingConstruction
August 2016
Release Environmental Assessment andPublic Hearings on Eastbound Widening
Late 2016
Revised Environmental Assessment and FHWA Decision on Eastbound Widening
Early 2017
Begin Tolling andImplement InitialMultimodal Projects
Mid 2017
Award Design-Build Contract for Eastbound Widening
Late 2017
Begin EastboundWidening Construction
Early 2018
Open NewEastbound Lane
Late 2020
K E Y
CTB: Commonwealth Transportation BoardFHWA: Federal Highway AdministrationNVTC: Northern Virginia Transportation CommissionTDM: Transportation Demand Management
2 0 0 9 2 0 1 2 2 0 1 3 2 0 1 5 2 0 1 6 2 0 1 7 2 0 1 8 2 0 2 0
I-66 Multimodal Study Inside theBeltway Final Report
June 2012
I-66 MultimodalStudy Inside the BeltwaySupplemental Report
August 2013
Public InformationMeetings onEastbound Widening May - June 2016
Transform 66 Inside the Beltway Program Improvements:
• Tolling during weekdays, peak hours, peak directions – Eastbound: 5:30 AM – 9:30 AM – Westbound: 3:00 PM – 7:00 PM – HOV 2+ toll free in 2017, HOV 3+ toll free when express lanes on I-66 outside the
Beltway open – All vehicles using the lanes during tolling periods must have an E-ZPass or E-ZPass
Flex, if they are HOV
• Multimodal improvements funded by toll revenue to support transit, transportation demand management (TDM) strategies, and other multimodal improvements benefitting the I-66 Corridor (selected by NVTC)
• Widening of I-66 eastbound from two to three lanes from the Dulles Connector Road to Fairfax Drive-Exit 71 (approximately 4 miles)
Noise Analysis Process
EASTBOUND WIDENING
Fin
al D
esig
nN
EPA
an
d P
relim
inar
y D
esig
n
MAY–JUNE 2016
NOV-DEC. 2016
JUNE–SEPT. 2016
2018
Identify noise receptors• Identify Common Noise Environments (CNE) (typically within 500 feet of the highway)• Identify noise sensitive receptors within each CNE (such as residences, parks, and schools)
Perform noise modeling• Develop noise models of existing and future roadway conditions using computer modeling
(incorporates roadway design, traffic volumes and speed, receptors, topography, and ground type)• Validate model with noise measurements data• Compute existing, no-build and build design-year sound level
Identify impacts (is noise mitigation warranted?)• Approach or exceed Federal Highway Administration (FHWA) noise abatement criteria (e.g., 67 dB(A)
for residences, parks, or schools) or• 10 decibel increase above existing noise levels
Design and assess mitigation (typically noise walls)
Is the wall feasible?• Does it work acoustically (do 50% or more of
the impacted receptors receive a 5 dB(A) or more noise reduction)?
• Can it be constructed (e.g., are there safety, drainage, utilities, maintenance, or other issues)?
Is the wall reasonable?• Cost-effectiveness (1,600 maximum square
feet or less per benefited receptor)• Design goal (7 decibels of noise reduction at 1
impacted receptor)
Perform noise measurements at representative receptors along the corridor
Post noise study results and preliminary noise wall locations on project website and present at public hearings
Finalize noise barrier designs once the project has received design approval
Obtain VDOT Chief Engineer approval
Obtain FHWA concurrence
Solicit public input from benefited property owners and renters (voting process)
Incorporate approved noise wall(s) into the final road design construction plans