Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Purple Line Extension Construction Community Meeting November 3, 2016
1
Agenda
2
Project Construction Updates: Western, La Brea, Fairfax and La Cienega La Brea Station Street Configuration Update Fairfax Decking: Phase I,II, III, Detours, outreach and communication Holiday Moratorium Eat Shop Play Wilshire Business Interruption Fund Measure M Question & Answer
Purple Line Extension Project Alignment
3 3
Sections 2 and 3 Status
4
Under Construction Forecasted Schedule
Section 1 Section 2 Section 3
Length 3.92 Miles 2.59 Miles 2.48 Miles
New Stations Wilshire/La Brea
Wilshire/Fairfax
Wilshire/La Cienega
Wilshire/Rodeo
Century City/
Constellation
Westwood/UCLA
Westwood/VA
Hospital
Pre-Construction Activities Current - 2016 2016 - 2018 2025 - 2027
Construction 2015 - 2023 2018 - 2026 2027 - 2035
Operations 2024 2026 2035
PLE Section 1 Alignment
5 5
Purple Line Maintenance Facility
Butterfield Property
590 S Santa Fe Avenue
• Located in Arts District downtown, near 6th St Bridge
• Continuation of Abatement Work – Monday thru Saturday
– Work Hours: 7am to 4:30pm
• Design Advisory Group – Advisory group is made up of local
leaders and artists from the Arts District.
– Goal is to review and provide input on exterior design of building.
– Next Meeting: November 9, 2016
• 3:00pm at SCI-Arc, Room 160
6 Installation of piles along west side to support excavation
Tie-in at Western Station
7
Western Staging Yard • Northeast corner of Wilshire and Manhattan Place one block west of Western
• Sound wall construction substantially completed.
• Remaining work includes gate installation, artwork on walls and widening of driveways
• Currently used intermittently for storage
Median Removal • No schedule for this work yet
Western Staging Yard
Example of Banner Art Design for Staging Yard
Crenshaw Yard Staging Site Wilshire/Crenshaw
• Used throughout Section 1 design-build construction
• Mitigation efforts and maintenance:
– Crenshaw Gate Entrance re-worked and improvements made
– Lorraine Gate temporarily closed until further notice
– Maintenance inside and outside of yard
Signage at the Crenshaw Yard
Signage and blankets at the Crenshaw Yard Entrance
8
La Brea Station
Rendering shows length of the La Brea underground station box
on Wilshire Blvd from Orange Dr. to Detroit St. 9
Purple Line Extension Wilshire/La Brea Schedule
10
*As of October 2016. Subject to Change
Tunneling
Station
Testing
La Brea Station La Brea Staging Yards
11
Contractor finishes concrete slab adjacent to much shaft at South La Brea Yard
Staging Yard Activities and Equipment
• Yard usage: 7am to 11pm, (11pm to 7am as needed).
• Sound wall is 20-24 feet high
• Maintenance of equipment
• Deliveries
• Excavation
Mitigations
• Must comply with City of Los Angeles noise requirements
• Noise Control Signage
• Low Impact Back up alarms
• Acoustical Insulation
• Metro 5 Step Noise Plan
S La Brea Staging Yard Mitigation signage and cleaning truck wheels to reduce track out of dirt
La Brea Station Decking Completed
Decking • On Wilshire, between Orange Dr. and Detroit
St.
• Constructed a concrete deck, curb to curb
• 593 deck panels installed
• Decking will serve as the temporary street surface
• Traffic will travel on the installed deck panels while the station is constructed underground
• La Brea Station:
– Approx. 1,000 feet long
– Approx. 70 feet wide
– Approx. 60 feet deep
12
Contractor has finished deck panels at La Brea/Wilshire
Wilshire/La Brea Work Zone, Traffic Control
13
Work to support excavation from the closure on Wilshire in progress
The current work zone on the south side of Wilshire from Detroit to Orange Dr is anticipated to be in place through January 2017. This work zone advances: • La Brea station excavation. • Utility hanging from the deck. • Dewatering system installation • Maintenance of geotechnical
instruments and dewatering wells.
• Restoration of street and sidewalk.
Deck Openings What: • Deck openings are openings of the street-deck for
the purpose of delivering materials for underground construction.
• Deck openings will be done at locations of the deck that are designed to open and close.
• Deck openings will occur periodically, as needed • Deck panels are 8-ft by 14-ft
When: • Following La Brea decking, late 2016 • Throughout the duration of the project
How: • Off-peak hours, (M-F, 9am-3:30pm, 7pm-6am) and
Saturdays and Sundays. • Traffic reduced to one lane each direction
Example of a deck opening from underneath the deck
14
15
La Brea Station Construction Opportunity
• Center Opening Concept
La Brea Station Center Opening Construction Concept
14
Rendering of center opening.
Cross-section of center opening being used
for excavation.
What: • Establish a material handling shaft in the
Wilshire Blvd. center median between Sycamore Ave. and Orange Dr., just east of La Brea in lieu of multiple intermittent closures and panel openings during excavation
• Wilshire remains two lanes in each direction between La Brea and Mansfield
• Left turns open on Wilshire at La Brea and Detroit in both directions
When: • Proposed January 2017 thru December 2017 How: • The work zone would be established using k-
rail, fencing and sound blankets • Seeking community input
La Brea Station Center Opening Construction Concept
15
Proposed Benefits : • For handling material in and out of the
1,000 ft. station during construction. • Safest method to accomplish work under
deck from the street. • Limits lane reductions for deck openings,
leaving a more consistent traffic pattern. • More robust noise mitigation for this
method rather than for lane closures. • Assists traffic flow of hauling and
decentralizes hauling from the La Brea staging yards.
• Expedites station excavation and concrete
work if in place.
Center opening work zone on Wilshire between Sycamore and Mansfield. Wilshire two lanes in each direction.
La Brea Station Excavation
• Now thru the Fall of 2017
• Work hours are 7am-11pm, 11pm-7am as needed
• Excavation will occur under the concrete deck, with intrinsically safe equipment that’s been certified by the State of California
• Excavation material will be removed from the staging yards at Wilshire/La Brea, loaded into trucks, and hauled using approved haul routes (SB La Brea to I-10)
• Street level excavation has started as a part of decking – excavation and utility hanging under the deck will continue behind the closure on Wilshire through the Fall of 2016
Examples of the excavation and utility hanging underway for the Wilshire/La Brea station
18
Jet Grouting
Overview • Jet grouting is a construction process that uses high-pressure air and
grout to create a deep soil-concrete block • The purpose of jet grouting is to reinforce and strengthen the soil with
concrete to support tunneling and cross-passage construction
Locations • Jet Grouting will occur at 16 locations along Wilshire between La
Cienega and Western • There will be no more than two jet-grouting operations being
performed at one time • Approximately 6 weeks at each location • Work hours M-F 7am-9pm, Sat 8am-6pm
Schedule • Wilshire between Orange and Mansfield-Completed • Wilshire between Rossmore and Lucerne- Underway • Wilshire between Arden and Muirfield – anticipated start Nov. 2016 • Wilshire between Plymouth and Windsor – anticipated start
December 2016 • Construction notices will be sent and outreach will be conducted for
each location
19
*Dates and work activities subject to change
Workers begin jet grouting at Wilshire Blvd near Rossmore
Jet Grouting Activities and Layout
Work Activities • Potholing, street level excavation ,
vertical drilling , trucking, cement silos, pumps, generators
Layout • Concrete Barriers placed on the
middle lanes of Wilshire Blvd • Lanes reduced to two lanes each
direction at jet grouting locations • Bus stops will be temporarily
relocated as required • Wilshire BRT lane not enforced in
these areas during jet grouting • Intermittent material deliveries
during off peak hours.
20
Fairfax Station
Rendering shows length of the Fairfax underground station box
on Wilshire Blvd from west of Fairfax to just west of Ogden Dr. 21
Purple Line Extension Wilshire/Fairfax Station Schedule
*Schedule is subject to change. Updated as of October 2016.
35
Ogden Staging Yard Activities and Safety Measures/Mitigations
24
Street sweeper for the staging
yards at La Brea and Fairfax
Grading the surface in Ogden yard Vault installation for electrical power in the Ogden yard
Fairfax Station Pile Installation Overview
47
• Pile installation includes:
– Rig to construct 95ft (L) deep
– Crane lifting 95Ft (L) , 24 Inch H-piles into holes
– Approx. 490 piles
– Drilling, pile installation and backfilled concrete completed same day
• Piling started in August 2016 on the north side of Wilshire
• Operation anticipated to take approximately 4-6 months on each side of the street
• Typical work hours 7am-11pm with potential nighttime work hours from 11pm to 7am
• Wilshire is reduced to two lanes in each direction.
• Directional closures on Fairfax and Wilshire will take place on weekends
PHOTO
24 Piling on N. side of Wilshire Blvd.
Fairfax Station Piling Flip to South Side
• Traffic switch to south side of Wilshire anticipated over the weekend of November, 18th - 20th 2016
• Traffic reconfiguration will be installed over a single weekend using intermittent lane reductions
• Wilshire will be reduced to two lanes in each direction for approximately 4-6 months
• Potential off-peak lane reductions to one lane in each direction • Left turn pockets eliminated on Wilshire at Fairfax
Left: Wilshire/Fairfax work zone for piles on the north side of Wilshire.
25
26
Station Decking
Fairfax Station Decking Overview
Decking • On Wilshire, between Ogden Dr. and the 99 Cents Store.
• Construction of a concrete deck, curb to curb
• Sidewalks be maintained, or pedestrian detours created.
• Decking will serve as the temporary street surface. Traffic will travel on the installed deck panels while the station is constructed underground
• Fairfax Station:
– Approx. 800 feet long
– Approx. 70 feet wide
– Approx. 60 feet deep
• Will follow pile operations; anticipated to begin January 2017
• Additional activities under decking closures: piling, temporary civil improvements.
• Will work closely with First Responders on emergency access and safety
27
27
Fairfax Station Decking Schedule
January 2017 through Spring 2017 • Approximately 18 weekend closures, scheduled in three phases beginning east and moving
west on Wilshire Blvd Phase 1: Ogden-Fairfax – 10 weekends Phase 2: Fairfax intersection – 4 weekends Phase 3: West of Fairfax – 4 weekends • Friday 8pm: Full closure of Wilshire or Wilshire/Fairfax intersection (Phase 2) • Monday 6am: streets open • Work occurs continuously throughout weekend • Working with DOT on early lane reductions to start Fridays 10am (similar to La Brea). Wilshire
would reduce to one lane each direction to allow for the loudest work (breaking of concrete) to be completed during day time hours.
28
*Dates and work activities subject to change
Fairfax Station Decking Traffic Action Plan
• Detour for 3 Phases have been submitted to DOT for review Phase 1: Ogden-Fairfax – 10 weekends Phase 2: Fairfax intersection – 4 weekends Phase 3: West of Fairfax – 4 weekends • This work requires close coordination and approval from City agencies • Board of Public Works approval anticipated in December 2016 • Traffic Action Plan:
• Detour routes • Proposed Mitigations • Signage • Signal timing adjustment • Traffic Control Officer locations • Maintains local access • Bus Detours
29
*Dates and work activities subject to change
Fairfax Decking Phase 1 Wilshire, Ogden to Fairfax
Essentials: • Wilshire reduced to one lane
in each direction from Spaulding to Fairfax on Fridays from 10am -8pm
• Full closure of Wilshire Blvd, from Spaulding to Fairfax starting at 8pm on Fridays until Mondays at 6am
• Lane reductions on Fairfax for west end work.
• Anticipated duration: 10 weekends
30
Phase 1 Traffic Detour Wilshire, Ogden-Fairfax Full Closure DRAFT
31
Westbound: Northbound La Brea to Westbound 6th St. to Southbound Fairfax to Westbound Wilshire Eastbound: Northbound Fairfax to Eastbound 6th St. to Southbound La Brea to Eastbound Wilshire
Fairfax Decking Phase 2 Fairfax/Wilshire Intersection
32
Essentials: • Early start lane reductions on
Wilshire and Fairfax starting on Fridays from 10am until 8pm
• Full closure of Fairfax Ave. starting at 8pm on Fridays until Monday at 6am
• Full closure of Wilshire Blvd. starting at 8pm on Fridays until Monday at 6am
• Anticipated duration: 4 weekends
Phase 2 Wilshire Traffic Detour Fairfax/Wilshire Intersection Closure DRAFT
33
• Westbound Wilshire: Westbound Wilshire to southbound La Brea to westbound Olympic to northbound San Vicente to westbound Wilshire
• Eastbound Wilshire: Eastbound Wilshire to eastbound San Vicente to northbound La Brea to eastbound Wilshire
Local access on Wilshire for business and residents will be maintained. Lane reductions on Wilshire going eastbound will start: Wilshire/Hamilton. Lane reductions on Wilshire going westbound will start: Wilshire/Orange
Phase 2 Fairfax Traffic Detour Fairfax/Wilshire Intersection Closure DRAFT
34
Southbound Fairfax: Southbound Fairfax to eastbound 6th st. to southbound La Brea to westbound Olympic to southbound Fairfax. Northbound Fairfax: Northbound Fairfax to eastbound Olympic to northbound La Brea to westbound 6th to northbound Fairfax. Lane reductions on Fairfax will start in the blocks approaching the hard closures. **Note: Local access on Fairfax for business and residents will be maintained.
Fairfax Decking, Phase 3 Wilshire, West of Fairfax
Essentials: • Wilshire, from Fairfax to
Crescent Heights reduced to one lane in each direction on Fridays from 10am until 8pm
• Full closure of Wilshire Blvd. from 8pm on Friday until 6am on Monday
• Working with DOT to address access to buildings between Crescent Heights and Fairfax (zone shown in yellow). Work zone shown in purple
• Lane reductions on Fairfax to support work on the east end of the closure
• Anticipated Duration: 4 weekends
35
Phase 3 Wilshire Traffic Detour Wilshire, West of Fairfax DRAFT
36
• Eastbound: Eastbound San
Vicente to northbound La
Brea to eastbound
Wilshire
• Westbound: Southbound
Fairfax to westbound San
Vicente to westbound
Wilshire
Fairfax Station Decking Community Outreach
37
• Robust Marketing Campaign • Social Media: Facebook, Twitter, Nextdoor • Advertising: print, radio, online • Media Coverage: press release
• Business and resident outreach • Meetings with local groups, leaders • Elected Official Briefings • Safety Presentations • School Presentations • Community Partnerships
La Brea Decking postcard mailed to residents and businesses.
Holiday Moratorium Exemption Wilshire/La Brea and Wilshire/Fairfax
38
The holiday moratorium exemption is an approval from the City of LA to work in the public right of way outside of k-rail work zones between Thanksgiving and New Years. Specific work and locations include:
• La Brea Utility work • Fairfax Piling • Jet grouting locations
Construction notices will be provided prior to any work activity starting
La Cienega Station
Rendering shows length of the La Cienega underground station
box on Wilshire Blvd from La Cienega to Tower Dr. 38
Purple Line Extension La Cienega Schedule
40
*As of October 2016. Subject to Change
Tunneling
Station
Testing
• Major work complete
• Fiber, AT&T, Water, Sewer, Storm Drain, Power, Gas
• Punch list items remain- anticipate Metro completion September 2016
• Utilities self-performing cable pulling – anticipated completion January 2017
Advance Utility Relocation (AUR)
40 Completed AUR work at Wilshire/La Cienega
• City Council approved on July 19, 2016
• Work hours: 8am-5pm
• Hauling hours: 9am-3:30pm
• Anticipated 10 weeks
• Work activities include:
• Tree removal
• Protective sidewalk cover installation on Wilshire and Gale
• Building demo
• Hauling
• Intermittent sidewalk closures
• Intermittent curb lane closure on Wilshire during street frontage demo work.
Demolition Future Staging Yards
41
La Cienega Station Gale Yard
• Demolition of buildings on Gale and Wilshire - completed
• Future Gale Staging Yard
Need photo of green screened
property
42
Left: Photo of demo in progress at Wilshire/Gale
Right: Photo of demo completed at Wilshire/Gale
La Cienega Station La Cienega Demo
Future La Cienega Staging Yard
43
Demolition in progress at Wilshire/La Cienega
Potholing/Survey Traffic Reconfiguration
45
• Work will take place during off-peak hours, if approved
• Work hours under review with COBH.
• Use temporary lane closures similar to AUR
• Investigating utility conflicts with pile line
• Anything not labeled on existing plans
Add photo with
capion
Potholing work for vault installation at La Cienega
Piling at La Cienega Station
46
• Approximately 500 piles to be installed
• Station is approximately:
– 990 feet long
– 70 feet wide
– 60 feet deep
• Piling at La Cienega is projected to start in the first quarter of 2017 on the south side of Wilshire.
• The work zone and traffic control will reduce Wilshire to two lanes in each direction.
• Work hours under review with COBH.
Approximate location of south side pile work zones at Wilshire/La Cienega.
Eat, Shop, Play Wilshire Business Spotlight- East Segment
47 47
Whimsic Alley Fine Shops Short Description: Los Angeles’s largest fandom retail store
Long Description: Whimsic Alley is located a few blocks from the future La Brea station. They are the largest fandom retail store in Los Angeles. Many of the featured items you will find at the store include fan favorites: Harry Potter, Game of Thrones, Doctor Who, Supernatural, Sherlock Homes and Outlander
Go Metro: Whimsic Alley is located at 5464 Wilshire Blvd. Los Angeles, CA 90036. For your best route, use the Trip Planner More Information: Contact: 310-453-2370 Visit www.whimsicalley.com Facebook: www.facebook.com/whimsicalley/
Eat, Shop, Play Wilshire Business Spotlight- West Segment
48 46
Wadee Spa
Wadee Spa is a wonderful addition in the Fairfax area, providing a tranquil, calm environment for massage customers. More Information: www.wadeespa.com 637 S. Fairfax Avenue, Los Angeles 90048 Phone: 323-934-2020 Hours 10am-10pm Mon-Sat. Early Bird Specials before 4pm on Weekdays!
Purple Line Extension in the Community
49 48 Press event announcing early end of La
Brea decking
Project Taco-Eat Shop Play Taco Tuesdays
Tarfest 2016
50
Metro Business Interruption Fund
• Financial assistance to small “mom & pop” businesses impacted by Metro transit rail construction along three project areas:
– Purple Line Extension, Phase 1
– Crenshaw/LAX Transit Project
– Regional Connector, Little Tokyo area & 2nd/Broadway segment
• Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements
• Grant amount determined by demonstrated loss of business revenue directly related to the period of construction disruption
• Maximum annual grant amount per business is $50,000
Metro Business Interruption Fund
• BIF Fund Administrator: Pacific Coast Regional Small Business Development Corporation (PCR)
• To apply visit www.pcrcorp.org or call 213.739.2999, ext. 223
• Upcoming BIF workshops:
Monday, November 7th at 11:30am Purple Line Extension Field Office
5055 Wilshire Blvd., Suite 400 Los Angeles, CA 90036
Parking validation provided
• For more information, visit www.metro.net/bif
Measure M
Ballot Measure Overview
• In June, Metro Board approved placing a “No Sunset” measure on the November ballot
• New ½ cent sales tax starting in July 2017
• Increases to 1-cent in 2039 when current ½ cent Measure R expires
• Continues until voters decide to repeal it
– Through an initiative or Metro-sponsored measure
• Needs two-thirds approval by voters
Measure M
Elements of the Measure
• New rail and bus rapid transit projects
• New highway projects
• Enhanced bus and rail service
• Local street, signal, bike/pedestrian improvements
• Affordable fares for seniors, students and persons with disabilities
• Maintenance/replacement of aging system
• Bike and pedestrian connections to transit facilities
Measure M
Accountability Built in the Measure
• Establishes an independent oversight process to provide an enhanced level of accountability on the use of sales tax revenues
– Taxpayers Oversight Committee
• Establishes a comprehensive assessment of the plan every 10 years
• Reviews funding to each city and uses of those revenues
Want more information? Visit metro.net/theplan
Next Meeting
Section 1 Construction Community Meeting
Thursday, January 19, 2017 6:00-8:00pm
Los Angeles County Museum of Art Brown Auditorium 5905 Wilshire Blvd Los Angeles, 90036
56
Stay in Touch
www.metro.net/purplelineext
twitter.com/purplelineext
facebook.com/purplelineext
213.922.6934
57