Purple Line ExtensionSection 2 Construction Community Meeting August 23, 2018
Agenda
• Wilshire/Rodeo Station
• Advance Utility Relocation
• Demo of former Ace Gallery
• N. Canon Demolition
• MOA City Council final Review
• N. Canon Drive Closure
• Century City/Constellation Station
• Advance Utility Relocation (AUR)
• Demo
• Constellation Bl Launch Box Closure
• #EatShopPlay #Century City
• Business Interruption Fund (BIF)
2
Purple Line ExtensionProject Alignment
3
> 2.56 miles
Sections 1, 2 & 3 Status
4
Forecasted Schedule
Section Section 1 Section 2 Section 3
Length 3.92 Miles 2.59 Miles 2.56 Miles
New Stations Wilshire/La Brea
Wilshire/Fairfax
Wilshire/La Cienega
Wilshire/Rodeo
Century City/
Constellation
Westwood/UCLA
Westwood/VA
Hospital
Pre-Construction
Activities
2014 – 2015 2016 – 2018 2018 – 2020
Construction 2015 – 2023 2018 – 2025 2019 – 2026
Operations 2023 2025 2026
*Subject to change. The PLE project team is working to deliver the project consistent with Measure M
Purple Line ExtensionSection 2 Alignment
5
Wilshire/Rodeo Station
Wilshire/Rodeo StationStation Box
Rendering shows length of the underground station box on Wilshire Bl from Canon Dr to Beverly Dr
7
Wilshire/Rodeo Station Schedule*As of August 2018, subject to change. Pending Council approval.
8
Advance Utility RelocationOrange = AT&T Yellow= Gas
SCG and AT&T Utility RelocationCombined Traffic Control * Dates subject to change
• Stage 6 behind K-rail• K-rail to remain 24/7 and work will take place behind it during approved
working hours• North side set up took place on August 15, 2018
10
• Wilshire, two lanes each direction, from west of Beverly to east of Canon
• Medians and parking removed from work zone
• Buses have been relocated outside of work zone
SCG Utility RelocationStage 6: 12 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
11
SCG Utility RelocationStage 7: 6 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
12
K-Rail 24/7
No Left Turns: EB Wilshire to NB Beverly
SCG and AT&T Utility RelocationStage 8: 6 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
K-Rail 24/7
13
Advance Utility RelocationBehind K-rail
14
Advance Utility RelocationBehind K-rail
15
Advance Utility RelocationBehind K-rail
16
Demolition of 9430 Wilshire BlFormer Ace Gallery, future Construction Staging Yard
17
Partial Closure of Reeves Park
Reeves Mini Park
• Metro is required to pay the City’s park rental fee for the closure of the park
• Required 30-day notification of the park closure
Wilshire Blvd
Bev
erl
y D
rive
Re
eve
s D
rive
9430 Wilshire Blvd
Reeves Mini Park
Proposed temporary closure area
Demolition of 9430 Wilshire BlFormer Ace Gallery
Site Address: 9430 Wilshire Bl
Schedule
• Preparation started on July 16, 2018
• Estimated duration of demolition activities: 8-10 weeks
• Work hours: 8am - 6pm
• Portion of park may be closed temporarily
Traffic Impacts
• Sidewalk/partial lane closure along Reeves Dr and Wilshire Bl(intermittently throughout duration of demolition)
• Pedestrian protection to be installed
• Partial closure of the alley
•19
• Work Hours: 8am – 6pm
• Start Date: Immediately following demolition. Anticipate September
• Sound wall installed using soldier piles and prefabricated noise panels
• Sound Wall: 20 feet
• Soundwall will have Public Information Graphics
20
Soundwall Installation
Example of prefab noise panels
Draft Staging Yard layout
21
Wilshire/RodeoPublic Information Graphics
To be implemented on soundwall, Fall 2018
22
Noise Control
• Independent Compliance Monitor (ICM)
• All construction personnel will attend Noise Awareness Training provided by Metro
• Moveable noise barriers
• Noise control curtains
• Noise muffling enclosures on stationary equipment
• No idling of heavy equipment when not in use
• No slamming tailgates
• Configure operations to eliminate backing movements
• Maintain equipment to avoid rattling and banging of parts
• Keep noise levels relatively uniform, avoid excessive and impulse noises
• Truck Manager will be onsite to ensure that trucks idle in and out of site to reduce noise levels at the site
Mitigation Measures: Noise
23
Vibration
• Vibration Monitoring will be implemented
• If vibration approaches FEIS/R threshold, then operations causing higher levels of vibrationwill be minimized
• Vibration exceedance will cause all work activities to stop until corrective measures can beimplemented
Dust
• During demo, water will be used to control fugitive dust
• Use tarped trucks / covered loads
• Hand sweep work area prior to opening work area to traffic
• Implementation of the Mitigation Monitoring Reporting Program (MMRP)
• Dust control during transport, no idling of heavy equipment, maintenance of construction equipment
• Metro’s Green Construction Policy sets rigorous standards for equipment emissions
• Implementation of Best Management Practices (BMPs)
• Street watering, street sweeping, truck wheel track outs, wheel wash
Mitigation Measures: Vibration and Dust
Air Quality Control Measures
Construction Air Quality Compliance
• Activities must comply with South Coast Air Quality Management District (SCAQMD) Rule 403, the reduction and control of fugitive dust
• Construction equipment is required to be registered with the California Air Resource Board (CARB)
• Use of Tier 4 equipment is required, which reduces emissions by over 95%
• Inspectors and Monitors actively observe daily activities and track compliance
• Report dust concerns to SCAQMD via 800-288-7664
24
Abatement of N. Canon Properties
Site Address: 9383-9393 and 9395-9399 Wilshire Bl
Schedule
• Abatement - Completed
• Estimated duration of demolition activities: 5 weeks
• Work hours Monday - Friday 8am to 6pm
• Demolition anticipated in September 2018*
25
*Pending City Council Approval
Memorandum of Agreement (MOA)
26
• Establish conditions and procedures for construction
• Minimize impact to the community
• Establish independent compliance monitor and enforcement process
• Key Elements:
• Work Hours
• Holiday Moratorium
• Business Mitigation Assistance
• Penalties and Fines
MOA Holiday Moratorium*Pending City of Beverly Hills Council Approval
27
• Each year, Metro will request from COBH the right to workfrom Thanksgiving to New Years
• Requests will be required by each August (annually)
MOA – Design-BuildBusiness Mitigation Assistance (BMA)
28
• 24/7 Hotline with live-person
• Advertising
• Eat Shop Play Beverly Hills
• Parking Replacement program
• Banners and signage (Aesthetic Treatment)
• Communications, Outreach and Engagement
• Traffic Control Officers
• Marketing
• Lighting
• Public Information Graphics
Next StepsWilshire/Rodeo Station
29
City Council Approvals*
• MOA Design-Build Consideration – August 21 2018
*Subject to change
Century City/Constellation Station
30
Century City/ConstellationStation Box
Rendering shows length of the underground station box on Constellation Bl from Century Park East to Avenue of the Stars
31
Century City/Constellation Station Schedule
32
*As of August 2018, subject to change.
Century City/Constellation AUR Schedule
33
*As of August 2018, subject to change
Advance Utility Relocation
34
Advanced Utility Relocation
Advance Utility Relocation Schedule and Work Hours AT&T/DWP
AT&T: thru September, 2018
Work hours: Sunday through Thursday, 8pm to 6am
• Work will occur on Constellation Blvd west of Avenue of the Stars
DWP (Power): Continuous through 2019
• Work hours: Monday through Friday
12am-6am and 12am through 3pm
• Weekends: Friday, 12am through Monday, 8am
• Work will occur east and west of Avenue of the Stars
35
*Dates subject to change
AUR, Constellation Bl west of Avenue of the Stars (before)
Resurfaced (after)
Century City/Constellation StationConstruction Staging Areas
36
• Construction of sound wall• Sound Wall: 20 feet• Acceptable Noise Limits:
• Mon-Fri: 7am - 10pm = 75dBA• 10pm - 7am and Weekends:
No more than 5dBA over ambient/background
Construction Staging Areas1940, 1950 & 2040 Century Park East
Construction Staging AreasProgress
Completed soundwall adjacent to Beverly Hills High School
39
Site Address: 1940 & 1950 Century Park East
• 1940 Century Park East (formerly the California Bank building)
• 4-story structure with parking garage (3 stories and a basement)
• 1950 Century Park East (parking structure of former AAA building)
• 3 story parking structure
All Demolition activities completed!
Ongoing Activities:
• Backfill of basement at 1940 Century Park East
• Site grading
• Installation of sound wall around perimeter
1940 & 1950 Century Park EastDemolition = COMPLETED
1940 & 1950 Century Park EastDemolition
40
41
Full Closure of Constellation Blvd.at Century Park East
*Dates subject to change
Pre-Construction Activities
•Potholing – Completed this week
•Survey – Ongoing
Implementing Traffic Control for Full Closure:
• All traffic control measures will be in place by Monday, Sept. 24 at 6 AM
• Re-striping to begin on Friday, Sept. 21 at 8 PM.
• Implementation of traffic control measures & signal work will be completed throughout weekend.
• Intermittent lane closures will be utilized to assist with installation throughout the weekend
42
Full Closure of Constellation Blvd.at Century Park East
*Dates subject to change
• No Public Access for Tenants through Driveway• Limited Access for:
• Large Trucks, Deliveries, Construction, Trash, Fedex/UPS (Flaggers will be present for access)
15 Month ClosureAnticipated to begin September 2018
43
Full Closure of Constellation BlGeneral Detour/Circulation
Anticipated: October 2018*
• Pile installation includes:
• Rig to drill holes
• Crane to lift piles into holes
• All work occurs behind k-rail (concrete barriers)
• Street will be reduced during operation
• Weekend closures may be needed to install piles across intersections
44
Pile Drilling InstallationStart Date *Dates subject to change
Example of piling work at Wilshire/La Brea
45
Pile Drilling InstallationExample from Wilshire/La Cienega
Anticipated: November 2018*• Construction of a concrete deck, curb-to-curb
• Sidewalks will be maintained or pedestrian detours created
• Decking will serve as the temporary street surface
• Traffic will travel on the installed deck panels while the station is constructed underground
• Typical station:
– Approximately 1000 feet long
– Approximately 70 feet wide
– Approximately 75 - 90 feet deep
• Metro will work closely with first responders on emergency access and safety
• Additional activities under decking closures: ground improvements, piling, temporary civil improvements
46
Decking InstallationOverview *Dates subject to change
Asphalt removal on Wilshire Bl near Detroit St
Steel beams welding prior to concrete deck panel installation
47
Decking example from Wilshire/Fairfax, aerial view of decking progress from roof of the Petersen Automotive Museum
47
4848
Decking InstallationSet-Up
Monitoring and Coordination
• COLA/Metro/ TPOG will monitor traffic
• Turn lanes will remain open for use (except for full street closure on weekends)
• Access to driveways & entrances will be maintained (except for weekends)
• Access for Emergency Vehicles & First Responders will be maintained
49
• Work primarily occurs underground beneath concrete decking
• Surface activities include:• Deliveries• Soil removal• Concrete pumping
• Material delivery and hauling occurs day/night
50
Station Construction24/7 Underground
Example of underground station construction
Santa Monica Bus Layover
51
Scheduled to start early Fall 2018
Tree Removal and Replacement• Estimate 15 trees need to be removed in public Right-
of-Way• 8 at Constellation Bl- removed• 7 at Santa Monica Bl
• Trees evaluated for relocation potential• Potential tree relocations
• 9 at Constellation Bl• 21at Santa Monica Bl
Platanus x acerfolia – London planetree, along south side of Constellation Bl
Ficus rubiginosa – Rusty leaf fig, at NE corner of Constellation Bl and Avenue of the Stars
Tree Removal and ReplacementLandscape Plan Overview
• Metro will replace all trees 2:1
• Design-Builder responsible for landscape plan• Reviewed existing plan to ensure all trees
need to be removed
• Landscape palette dictated by existing palette and City requirements
• Workshops will be hosted by Design-Builder for community input
• City of Los Angeles has agreed to 36” box trees
• New irrigation, controllers and lighting for affected areas (Santa Monica Bl) Quercus agrifolia – Coastal live oak,
Santa Monica Bl
53
Tree Removal and Replacement Constellation Bl
Note: To satisfy 2:1 ratio, additional tree replacements for Constellation Bl tree removals will be located at Santa Monica Bl
54
Tree Removal and Replacement Santa Monica Bl
Landscape Exhibit: Tree Replacement at Avenue of the Stars/Constellation Bl
Platanus x acerfolia –London planetree1
56
1TYP
57
Lunch Pop-Up When: September 20, 11:30 am-1:30 pmWhere: Century Park
Come by the Eat Shop Play Pop-Up for information on the Constellation Blvd, closure
and to receive special prizes! Free TAP card giveaway at participating business.
Ask for yours today!
Helping local businesses as we build.Update as of 8/10/18
BIF Information and Eligibility
> Financial assistance to small “mom & pop” businesses with 25 or fewer employees directly impacted by Metro Rail construction along three project areas
> Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements
> Grant amount determined by loss of business revenue related to period of construction disruption
> To date, 730 grants have been awarded with a total value of more than $16.4 million along all three projects
BIF Grant Award Update
> Purple Line Extension, Section 1
> BIF Grants Awarded: 176
> BIF Grant Amount Awarded: $4,394,161.83
> Number of small businesses awarded: 69
> BIF Business Advisor: Brian Lazo
> Pacific Coast Regional Small Business Development Corporation (PCR)
> Phone: 213.739.2999
BIF Grant Award Update
> Purple Line Extension, Section 2
> BIF Grants Awarded: 14
> BIF Grant Amount Awarded: $395,024.90
> Number of small businesses awarded: 13
> BIF Business Advisor: Darrell Smith
> Pacific Coast Regional Small Business Development Corporation (PCR)
> Phone: 213.739.2999
Update on La Cienega and Rodeo Stations
Wednesday, September 5, 2018
6:30pm – 8pm
Beverly Hills City HallMunicipal Gallery
455 N. Rexford Drive
Beverly Hills, CA 90210
62
Next Community MeetingBeverly Hills
Section 2: Construction Community Meeting
Thursday, November 13, 2018
6:30pm – 8pm
Century Park Towers2029 Century Park EastLos Angeles, CA 90067
*Parking will be validated
63
Next Community MeetingSection 2
Stay in Touch
64