Pure Water North City Phase 1 Construction Projects Community Working Group Meeting 3 – Bay Park/Morena Date: Aug. 1, 2018, 4:30 p.m. – 8 p.m. Location: South Clairemont Recreation Center Meeting Agenda 4:30 Welcome J. Helminski 4:35 Agenda Introductions N. Hentschel 4:45 5:15 Follow-up Items Construction Topics Staging areas/parking Construction site housekeeping Environmental monitoring A. Shapiro/S. Lindsay/S. McCarty S. Lindsay/S. McCarty 6:00 DINNER 6:30 Pure Water Website Resources S. McCarty 6:40 Construction Topics Outreach, communication and notifications Construction monitoring Future participation of the group S. Lindsay/S. McCarty/J. Helminski 7:45 Public Comment N. Hentschel 7:55 Closing and Next Steps N. Hentschel

Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

Pure Water North City Phase 1 Construction Projects Community Working Group Meeting 3 – Bay Park/Morena

Date: Aug. 1, 2018, 4:30 p.m. – 8 p.m.

Location: South Clairemont Recreation Center

Meeting Agenda

4:30 Welcome J. Helminski

4:35 Agenda Introductions

N. Hentschel

4:45 5:15

Follow-up Items Construction Topics

• Staging areas/parking

• Construction site housekeeping

• Environmental monitoring

A. Shapiro/S. Lindsay/S. McCarty S. Lindsay/S. McCarty

6:00 DINNER

6:30 Pure Water Website Resources S. McCarty

6:40 Construction Topics

• Outreach, communication and notifications

• Construction monitoring

• Future participation of the group

S. Lindsay/S. McCarty/J. Helminski

7:45 Public Comment N. Hentschel

7:55 Closing and Next Steps N. Hentschel

Page 2: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

August 1, 2018

Pure Water San Diego Phase 1

Bay Park/Morena Working Group: Meeting 3

Page 3: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

Agenda

30% design rendering60 percent design rendering of North City Pure Water Facility

▪ Welcome▪ Agenda Review

▪ Follow-up Items from Meeting 2▪ Construction Topics Overview and Discussion

▪ Staging Areas/Parking▪ Construction Site Housekeeping▪ Environmental Monitoring

▪ DINNER

▪ Pure Water Website Resources▪ Construction Topics Overview and Discussion

▪ Outreach Communications and Notifications▪ Construction Monitoring▪ Future Participation

▪ Public Comment

▪ Closing and Next Steps

2

Page 4: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

1. Multiple disruptions and project coordination

2. Street restoration

3. Air quality/noise

4. Staging areas/parking

5. Environmental monitoring

6. Traffic control/signage

7. Special stakeholder access needs

8. Outreach, communication and notifications

9. Work restrictions and construction phasing

10. Working days and hours

11. Construction monitoring

30% design rendering60 percent design rendering of North City Pure Water Facility

Working Group Topics

15

Page 5: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

Construction Staging Areas

▪ Staging areas are utilized to temporarily store pipe, bedding, backfill material, and construction equipment▪ Located adjacent to construction work area, typically within

City right-of-way▪ Contractor is responsible for identifying staging locations▪ Requires approval by the City’s construction management

staff▪ Must all be located on paved or cleared surfaces

Page 6: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

Storage Yards

▪ Storage yards are locations where a contractor may choose to store surplus materials, larger equipment, office trailers, etc.▪ May be located on private property and require exclusive

agreements between the contractor and that private property owner

▪ All storage areas must be located on paved or cleared surfaces

Page 7: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

No Parking

▪ Notifications▪ Types

▪ Timing

▪ Impacted Area

Selection

Page 8: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

▪ Environmental Management Plan▪ Oversight

▪ Mitigation Monitoring and Reporting Program (MMRP)

▪ Mitigation Monitoring Coordination (MMC) section of the City Development Services Department (DSD)

▪ Biological Resources Monitoring▪ Adjacent sensitive biological habitat

will be fenced off

▪ Cultural Resources Monitoring

▪ Paleontological Resources Monitoring

7

Environmental Monitoring

Page 9: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

▪ Storm Water Pollution Prevention Plan (SWPPP)

▪ Dust abatement measures▪ Street sweeping▪ Use of covers/tarps

▪ Other Best Management Practices (BMPs)

Construction Site Housekeeping

Page 10: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

▪ www.purewatersd.org

▪ Informational materials

▪ Phase 1 interactive map

9

Pure Water Website Resources

Page 11: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

▪ Construction Communication Plan

▪ Community Liaison

▪ Notifications▪ Types▪ Timing

▪ Other Outreach

Discussion: What forms of outreach, communication and notifications are preferred and proven effective in your community?

10

Outreach, Communication and Notifications

Page 12: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

▪ Bid release starting end of 2018 ▪ Proposed Working Group Update

Meeting

▪ Contract award and Notice to Proceed Spring 2019▪ Proposed Working Group Update

Meeting

11

Construction Monitoring

Discussion: What form of community involvement do you envision? What would work best for your community?

Page 13: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

Public Comment

Page 14: Pure Water North City Phase 1 Construction Projects ...Agenda 60 percent design rendering 30% design rendering of North City Pure Water Facility Welcome Agenda Review Follow-up Items

Next Meeting

Meeting Date and Time Meeting Location

4 Thursday, Aug. 23, 20184:30 – 8 p.m.

South Clairemont Recreation Center