1
Tender No. : PEDA/2019-20/05
E-BIDDING DOCUMENTS
For
APPROVAL OF RATES FOR DESIGN, MANUFACTURE, SUPPLY, ERECTION,
TESTING AND COMMISSIONING INCLUDING WARRANTY AND MAINTENANCE
FOR 5 YEARS OF DIFFERENT CAPACITY GRID INTERACTIVE SPV POWER PLANTS
AT ANYWHERE IN PUNJAB
by
PUNJAB ENERGY DEVELOPMENT AGENCY PLOT NO. 1&2 SECTOR 33-D, CHANDIGARH 160 034, PB., INDIA
TELEPHONES: (91) 0172 - 2663382, 2663328, FAX : (91) 0172 – 2664502
2
CONTENTS
I. INVITATION FOR BIDS : 3-5
II. INSTRUCTIONS TO BIDDERS : 6-21
III. SCHEDULE OF REQUIREMENTS : 22-24
IV. TECHNICAL SPECIFICATIONS : 25-41
V. FORMATS : 42-56
VI. SCOPE OF OPERATION & MAINTENANCE OF
POWER PLANT
: 57-61
3
SECTION - I
1. INVITATION FOR BIDS
4
PUNJAB ENERGY DEVELOPMENT AGENCY Solar Passive Complex Plot No. 1 & 2, Sector 33-D, Chandigarh
Notice Inviting E-Tender
E-tender notice no. PEDA/2019-20/05 Punjab Energy Development Agency (PEDA), invites e-tender for different capacity SPV Rooftop Power Plants anywhere in Punjab:.
Sr. No
Name of work EMD (Rs.) Date of start of
downloading e-tender
document
Date of Pre -Bid
meeting
Last Date & time for submission
of e-bids
Date & time of opening of
Techno-commercial e-
bids
1. Approval of Rates for Design, Engineering, Supply, installation, commissioning and testing of different capacity SPV Rooftop Power Plants anywhere in Punjab as per DNIT
2,00,000 22.06.2019 at 11:00 AM
03.07.2019 at 11.00 AM
25.07.2019 upto 4:00 PM
26.07.2019 at 11:30 AM
Cost of Tender Document Non-refundable Tender Document fee Rs. 5,000/- through online Mode only
E-Processing Fee Non-refundable e-processing fee as applicable through online mode only
Earnest Money Deposit Earnest Money as mentioned above shall be deposited through online mode only.
1. Eligibility criteria and other terms & conditions for the works are given in the Tender
Document which can be downloaded from www.eproc.punjab.gov.in.
2. Bidders shall have to get themselves registered with eproc.punjab.gov.in and get user
ID and Password. Class- 2/3 Digital Signature, mandatory to participate in the e-
tendering process. For any clarification on the tender document clauses, please contact
at 0172-2663328, 0172-2663382. For any clarification/difficulty regarding e-tendering
process flow, please contact at 0172-2791326, 2791226.
3. Corrigendum / Addendum / Corrections, if any will be published on the e-tender website
and no separate notices shall be issued
4. PEDA reserve the right to accept or reject any or all the tenders without assigning any
reason thereof.
Chief Executive
5
SCOPE OF WORK
BID-SUBJECT- Approval of rates for Design, manufacture, supply, erection, testing and commissioning along with maintenance for 5 years for different capacity Grid Interactive SPV power plants any where in Punjab as per following categories:
Sr. No. Category of systems
I. 1 KWp to 10 KWp
II. More than 10 KWp to 20 KWp
III. More than 20 KWp to 50 KWp
IV. More than 50 KWp to 100 KWp
V. More than 100 KWp to 500 KWp
1. A complete set of bidding documents in English may be purchased from
www.eproc.punjab.gov.in through IPG Mode payment of a non-refundable fee of Rs.5000/-.
2. Bids must be submitted through e-tender upto 4.00 PM. on dt 25.7.2019 . All bids must be accompanied by a Earnest Money Deposit of Rs. 2,00,000/- . Conditional bids will be rejected. Bids will be opened in the presence of bidders representative who choose to attend at the address below on dated 26.07.2019 at 11:30 AM. The details are given below: (a) Name of office : Punjab Energy Development Agency
(b) Name of person : General Manager, PEDA
(c) Postal Address : Plot no. 1 & 2 Sector 33D
Chandigarh 160 022, India
(d) Telephone nos. : (91) 0172 , 2663328, 2663382
(e) Fax No. Tele FAX : (91) 0172 – 2662865
(f)
(g)
Date of commencement of sale of
bidding document
Date of pre bid meeting
:
:
22.06.2019 at 11:00 AM
03.07.2019 at 11:00 AM
(h) Last date & time for receipt of bids : 25.07.2019 upto 4.00 pm
(i) Time and date of opening of
technical Bids
: 26.07.2019 at 11.30 AM
(j) Time and date opening of price bid : Inform after evaluation of Techno
Commercial E-Bids
3. The bidding shall be in two parts pattern. Technical Bid and Financial Bid:
Technical bid will contain the qualifying requirement and the financial offer will contain the offered prices.
6
SECTION II
2. INSTRUCTIONS TO BIDDERS
(ITB)
7
A. INTRODUCTION
Scope of work : Approval of Rates for Design, Supply, Installation, Testing &
Commissioning of different capacity Grid Connected Rooftop Solar Power Plants at various
locations in the state of Punjab along with the operation & maintenance of Rooftop Solar
Photovoltaic Power Plant include wear, tear, overhauling, machine breakdown, and
replacement of defective modules, invertors / Power Conditioning Unit (PCU), spares,
consumables & other parts for a period of 5 years .
B. Source of Funds
Punjab Govt. has accorded sanction for installation of grid-
connected solar roof top power plants in Punjab. The generated solar power may be
utilized for captive application and the surplus power may be fed to the grid as per
State Net Metering policy .The scheme aims to reduce the fossil fuel based electricity
and make buildings self-sustainable from the point of electricity, to the extent
possible.
1. TERMS & CONDITIONS:
1.1 E-tenders shall be submitted on www.eproc.punjab.gov.in. Conditional tenders and
tenders without EMD shall be rejected.
1.2 The Rates to be quoted in Financial Bid form should be FOR at site inclusive of all
applicable taxes/ octoroi, installation, commissioning, maintaining & warrantee for 5
years. The rates shall be valid for one year from the date of opening of Financial Bid.
1.3 Supply, installation and commissioning of the project should be completed within 120
days from the date of placement of the work order.
1.4 The supporting documents to be submitted as proof with the bid should be in sequence
order and page marked. The bids found not in order and conditional bids with addition/
omission to original DNIT are liable to be rejected.
1.5 No additional documents will be accepted after opening of the technical bid on
due date. The sole criteria of qualification / disqualification will depend on the
documents uploaded by the bidders. However the Evaluation committee of PEDA
can sought any information regarding the papers/installation of the plant.
1.6 The bidder shall upload the bids as per formats on or before the date and time notified
in this document/ NIT .
1.7 Chief Executive PEDA reserves the right to accept or reject any or all the tenders
without assigning any reason in the interest of user and Punjab Energy Development
Agency.
1.8 Correspondence for enquiries and clarifications:
8
All correspondence, clarifications in respect of the bid document shall be
addressed to:
General Manger,
Punjab Energy Development Agency,
Plot No. 1 & 2, Sector 33-D, Chandigarh,
Tel: 0172 - 2663328 / 2663382
Fax: 0172 –2662865
and should reach one day prior to pre bid meeting in PEDA office or
through Email: [email protected]
2. Eligible Bidders
Bidder must meet the eligibility criteria independently as a Bidding
Company
Bidder will be declared as a Qualified Bidder based on meeting the
eligibility criteria and as demonstrated based on documentary evidence
submitted by the Bidder in the Bid.
The Successful Bidder shall be required to establish at least one Service
Centre in Punjab.
3. ELIGIBILITY CRITERIA
3.1 GENERAL
(a) The Bidder should be either a body incorporated in India under the Companies
Act, 1956 or 2013 including any amendment thereto . The EPC companies,
manufacturers, suppliers & system integrators of Solar PV Power Projects who
have not been debarred/black listed by any Govt. organization for design,
manufacture, supply, installation and commissioning of different capacity Roof
Top Solar Power Projects are eligible for this tender.
b) A copy of certificate of incorporation shall be furnished along with the bid in
support of above.
3..2 TECHNICAL ELIGIBILITY CRITERIA:
The bidder should have installed & commissioned the plants during last three years i.e from 1.4.2015 onwards as under:-
Sr. No. Category of systems Minimum Capacity of single system or
cumulative systems installed during last
three years years i.e 1.4.2015 onwards
i 1 kWp to 10 kWp 10 KWp single plant or 30 KWp Cumulative.
ii > 10 kWp to 20 kWp 20 kWp Single plant or 60 KWp Cumulative.
9
iii > 20 kWp to 50 kWp 50 KWp single plant or 150 kWp Cumulative.
iv > 50 kWp to 100 kWp 100 KWp Single plant or 300 kWp Cumulative
v > 101 kWp to 500 kWp 250 KWp Single plant or 500 kWp Cumulative
The plant should have been commissioned at least three months prior to date of publishing of NIT. The list of project commissioned at least 3 months prior to date of publishing of NIT, indicating whether the project is grid connected, along with a copy of the Commissioning certificate and Work order / Contract / Agreement/ from the Client/Owner shall be submitted. The plant should be in successful operation prior to 3 month on the date of publishing of NIT and certificate duly issued by SNA/ Govt. Department shall be submitted along with bid. The performance certificate issued by SNA/Govt. Deptt. should not be older then one month from the date of publishing of NIT.
3.3 FINANCIAL ELIGIBILITY CRITERIA:
(a) The Bidder should have an Annual Turnover as under in the any one
of last three years of operations of the bidder :-
Sr. No.
Category of systems
Minimum financial turn over during any one of last three years i .e from 2015-16 onwards
i 1 kWp to 10 kWp Rs. 30.00 Lac.
ii > 10 kWp to 20 kWp Rs. 50.00 Lac.
iii > 20 kWp to 50 kWp Rs. 100.00 Lac.
iv > 50 kWp to 100 kWp
Rs. 200.00 Lac.
v > 101 kWp to 500 kWp
Rs. 500.00 Lac.
b) Bidders shall furnish documentary evidence as per the Performa-2, duly
certified by Authorized Signatory and the Statutory Auditor / Practicing
Chattered Accountant of the Bidding Company in support of their
financial capability. Bidder is also required to submit the documentary
proof like Balance sheet along with CA certificate of Turnover.
Unaudited balance sheet should not be accepted. Turnover of bidder
company will be accepted only..
4. SUBMISSION OF BIDS
4.1 The bidder shall upload the bids as per formats on or before the date and time
notified in this document/ NIT.
4.2 Bids shall be uploaded in two parts.
Part – I Techno Commercial Bid
Part – II Price Bid.
4.3 It should be clearly noted that Part –I should not contain any price bid.
4.4 Part-I containing of those bidders who satisfy the requirement of bid security
deposit will only be opened at the time & date notified for opening. If any bidder
10
indicates the price in Part-I i.e techno commercial bid , the bid will not be read out
and bid would stand rejected. Part II containing will not be opened at the time of
opening Part-I. The bidders who do not qualify in Part –I, their bid of Part –II (Price
Bid) shall not be opened.
4.5 The Bidder shall submit complete e-bid through e-tender at website
www.eproc.punjab.gov.in
4.6 Bids shall remain valid for the period 90 days after the date of bid opening
prescribed by the Purchaser for the purpose of evaluation. A bid valid for a shorter
period shall be rejected by the Purchaser as non-responsive
4.7 Annual maintenance charges for 5 years should have minimum 10% of the total
cost of each power plant otherwise bid shall be rejected.
5. Earnest Money Deposit
The Earnest Money Deposit is required to protect the Purchaser against risk of
Bidder's conduct which would warrant the security's forfeiture.
The Earnest Money Deposit of Rs.2,00,000/- ( Rs. Two Lacs only) shall be
deposited through IPG mode only (Internet Payment Gateway)
Any bid not secured in accordance with above EMD will be rejected by the Purchaser
as non responsive.
Unsuccessful Bidder's Earnest Money Deposit will be discharged/returned as
promptly as possible but not later than thirty (30) days after the expiration of the
period of bid validity prescribed by the purchaser.
The successful Bidder's will be discharged upon the Bidders executing the Contract
and furnishing the performance security.
The Earnest Money Deposit may be forfeited:
a) if a Bidder:
I. withdraws its bid during the period of bid validity specified by the Bidder
II. does not accept the correction of errors
b) in case of a successful Bidder, if the Bidder fails
i. to sign the Contract in accordance or
ii. to furnish performance security.
6. . Deadline for Submission of Bids
Bids must be submitted through e-tendering process in time and date as mentioned
in NIT.
The Purchaser may, at its discretion, extend this deadline for submission of bids by
amending the Bid Documents, in which case all rights and obligations of the
Purchaser and Bidders previously subject to the deadline will thereafter be subject
to the deadline as extended.
7. Late Bids
After the deadline for submission of bids as mentioned in NIT, any bid shall not be
received by the e-tender system and no physical bids will be accepted.
8. Modification and Withdrawal of Bids
No bid can be modified subsequent to the deadline for submission of bids.
No bid may be withdrawn in the interval between the deadline for submission of
bids and the expiration of the period of bid validity specified by the Bidder on the
Bid Form. Withdrawal of a bid during this interval may result in the Bidder's
forfeiture of its EMD.
9. Opening of Bids by Purchaser
9.1 The Purchaser will open e-Technical bids, in the presence of Bidders' representatives
who choose to attend, at the time, on the date, and at the place specified in DNIT.
11
9.2 Bids that are not opened and read out at bid opening shall not be considered further
for evaluation, irrespective of the circumstances.
9.3 The technical e-bids shall be evaluated by the purchaser for assessing
responsiveness, bidders qualification and technical confirmation.
9.4 The bidders whose technical bids are declared as technically responsive and qualified
shall be informed accordingly and their Price Bids shall be opened.
9.5 The bidders whose technical bids do not qualify, there Price Bids shall not be opened.
9.6 Price Bids opening date shall be conveyed subsequently on e tendering website.
10. Evaluation of Financial Bids
The evaluation of Price Bid shall be carried out based on the information furnished in
the uploaded E-Price Bid. The Price Bid submitted by the Bidders shall be scrutinized
to ensure conformity with the DNIT. Any Bid not meeting any of the requirements of
this DNIT may cause the Bid to be considered “Non-responsive” at the sole decision
of the PEDA. The Price bids for the each category shall be evaluated separately.
11. Award of Contract
a) Post qualification
11.1 In the absence of pre qualification, the Purchaser will determine to its satisfaction
whether the Bidder selected as having submitted the lowest evaluated responsive bid
is qualified to perform the contract satisfactorily.
11.2 The determination will take into account the Bidder's financial, technical and
production capabilities. It will be based upon an examination of the documentary
evidence of the Bidder's qualifications submitted by the Bidder, as well as such other
information as the Purchaser deems necessary and appropriate.
11.3 An affirmative determination will be a prerequisite for award of the contract to the
bidder. A negative determination will result in rejection of the bidder’s bid, in which
event the purchaser will proceed to the next lowest evaluated bid to make a similar
determination of that bidder’s capabilities to perform satisfactorily.
11.4 The Rates quoted should be on the basis of FOR destinations anywhere in the State
of Punjab. Prices along with all applicable taxes/GST, octroi etc. to be indicated in
Financial Bid Format. Quoted rates shall be valid upto one year from the date of
opening of Financial Bid.
12. Selection of Bidder
The Project Cost quoted in Price Bids of Qualified Bidders for different categories
shall be ranked from the lowest to the highest for each location.
For all the categories , lowest bidder will be declared as the successful
bidder i.e L1. The other bidder will be asked to match the price quoted by the L1
bidder. The bidder who matches the L1 price will also be declared Successful bidder.
All the qualified bidders except the L1 bidder will be given 10 days from the date of
notification of L1 price on PEDA website and through email to bidder to give their
consent to execute the work at L1 price failing which it will be assumed that they are
not interested to match L1 price.
14 . Purchaser's Right to Accept Any Bid and to Reject Any or All Bids
12
The Purchaser reserves the right to accept or reject any bid, and to annul the bidding
process and reject all bids at any time prior to award of Contract, without thereby
incurring any liability to the affected Bidder or Bidders or any obligation to inform the
affected Bidder or Bidders.
15 . Notification of Award
15.1 Prior to the expiration of the period of bid validity, the Purchaser will notify the
successful Bidder in writing by registered letter of Intent, that its bid has been
accepted.
15.2 The notification of award will constitute the formation of the Contract
16. ISSUE OF WORK ORDER
16.1 The work order/ orders shall be placed depending upon the requirement of the
agency from time to time within the validity period of rates and work shall be allotted
on L1 rates during the validity of bid subject to discretion of PEDA. However PEDA
shall have no financially liability in any case if no work is allotted during rate validity
period.
16.2 PEDA reserves the right to split the work order on the lowest quoted rates to one or
more than one technically qualified bidders other than L1 for meeting with early
completion of supply or any other reasons. The decision of PEDA regarding quantity
will be final and binding on selected bidders in this case.
17 . Performance Bank Guarantee (PBG)
17.1 Within fifteen (15) days from the date of issue of notification of award for approval of
rates from the Purchaser, the successful Bidder shall furnish the PBG for an amount
of Rs. 5 lakhs valid for 15 months from the date of issue of notification of Award .
17 .2 Failure of the successful Bidder to comply with the above within the stated time
periods shall constitute sufficient grounds for the annulment of the award and
forfeiture of the EMD.
17.3 The PBG shall be denominated in the currency of the Contract, and shall be in one of
the following forms:
(a) A Bank guarantee, issued by a reputed bank located in the purchaser’s
country , acceptable to the Purchaser, in the form provided in the Bidding
Documents; or
(b) A Demand draft favoring Punjab Energy Development Agency.
17.4 The PBG shall be forfeited without prejudice to the Bidder being liable for any further
consequential loss or damage incurred to PEDA :-
If the Bidder/Company is not able to commission the projects to the
satisfaction of PEDA,
If the bidder company not accepted the work order during rate approval
period.
17.4 The performance security will be discharged by the Purchaser and returned to the
Supplier not later than thirty (30) days following the date of completion of the
Supplier's performance obligations, under the Contract, including any warranty
obligations
18 . Signing of Contract
18.1 At the same time as the Purchaser notifies the successful Bidder that its bid has been
accepted, the Purchaser will send to Bidder the work order/orders and the Contract
Form provided in the Bidding Documents, incorporating all agreements between the
parties.
13
18.2 Within fifteen (15) days from the date of issue of the Contract Form, the successful
Bidder shall sign the Contract and return it to the Purchaser. The signing of the work
order cum contract agreement shall evidence the final acceptance of all terms and
conditions and their due compliance by the successful bidder.
19. INSPECTIONS AND TESTS
19.1 The Purchaser or its representative shall have the right to inspect and/or to test the
Goods to confirm their conformity to the Contract specification at no extra cost to the
purchaser. Technical Specifications shall specify what inspections and tests the
Purchaser requires and where they are to be conducted. The Purchaser shall notify
the Supplier in writing of the identity of any representatives retained for these
purposes.
19.2 The inspection and tests of the plant above 10 KW capacity may be conducted on
the premises of the Supplier and its subcontractor(s) at point of delivery and/or at the
Goods final destination. If conducted on the premises of the supplier or its
subcontractor(s) all reasonable facilities and assistance, including access to drawing
and production data - shall be furnished to the inspectors at no charge to the
Purchaser.
19.3 Should any inspected or tested Goods fail to conform to the specifications, the
Specifications, the Purchaser may reject the Goods, and the Supplier shall either
replace the rejected Goods or make all alterations necessary to meet specification
requirements free of cost to the Purchaser.
19.4 The Purchaser's right to inspect, test and, where necessary, reject the Goods after the
Goods' arrival in the purchaser’s country shall in no way be limited or waived by reason
of the Goods having previously been inspected, tested and passed by the Purchaser or
its representative prior to the Goods shipment from the country of origin.
19.5 The complete charges for inspection & tests including equipment simulation at the works Supplier and its subcontractor(s) including to & fro airfare, boarding & lodging for purchasers engineers shall be borne by the supplier.
20. a) Inspection at Works:
The Purchaser, his duly authorized representative and/or outside inspection agency
acting on behalf of the Purchaser shall have at all reasonable times access to the
Contractor's premises or works and shall have the power at all reasonable times in
inspect and examine the materials and workmanship of the works during its
manufacture or erection and if part of the works is being manufactured at the sub-
contractor's works or assembled in their premises or works, the contractor shall obtain
for the Purchaser and for his duly authorized representative, permission to inspect as
if the works were manufactured or assembled in the Contractor's own premises or
works.
The Contractor shall give the Purchaser/Inspector 10 days written notice of any
material being ready for testing. Such test shall be to the Contractor's account. The
Purchaser/Inspector, unless witnessing of the test is virtually waived, will attend such
test within 7(seven) days of the date on which the equipment is notified as being ready
for test/inspection, failing which the Contractor may proceed with the test which shall
be deemed to have been made in the Inspector's presence and he shall forthwith
forward to the Inspector duly certified copies of tests in triplicate.
14
The Purchaser or Inspector shall within 7(seven) days from the date of inspection as
defined herein give notice in writing to the Contractor, or any objection to any
drawings and all or any equipment and workmanship which in his opinion is not in
accordance with the Contract. The Contractor shall give due consideration to such
objections and shall either make the modifications that may necessary to meet the
said objections or shall confirm in writing that no modifications are necessary to
comply with Completion of these tests or the issue of the certificate shall not bind the
Purchaser to accept the equipment should it, on further tests after erection be found
not to comply with the Contract.
In all cases where the contract provide for tests whether at the premises or works of
the Contractor or of any Sub-contractor, the contractor, except where otherwise
specified, shall provide free of charge such items as labour, materials, electricity,
apparatus and instruments as may be reasonably demanded by the
Purchaser/Inspector or his authorized representative to carry out effectively such tests
of the equipment in accordance with the contract and shall give facilities to the
Purchaser/Inspector or to his authorized representative to accomplish testing.
The inspection by Purchaser/Inspector and issue of Inspection Certificate thereon shall
in no way limit the liabilities and responsibilities of the Contractor in respect of the
agreed quality assurance programme forming a part of the Contract.
(b) Pre-Commissioning test
On completion of erection of the equipment and before start up, each item of the
equipment shall be thoroughly cleaned and then inspected jointly by the purchaser or
his authorized representative and the Contractor for correctness and completeness of
installation and acceptability for start-up, leading to initial pre-commissioning tests at
site.
The Contractor's commissioning/start-up engineers specifically identified as far as
possible shall be responsible for carrying out all the pre-commissioning tests. On
completion of inspection, checking and after the pre commissioning tests are
satisfactorily over, the complete equipment shall be ready for trial operation.
During the trial run the operator shall be under the supervision of the Contractor but
the schedule of operations shall be agreed to be the Purchaser and the Contractor
During the pre-commissioning, commissioning and performance guarantee tests the
operator will be under the supervision of the Contractor if the tests are being carried
out by him. In case the tests are being carried out by a third party the operator will be
under the control of the Purchaser. In both cases all aspects of the tests shall be
agreed to by the Purchaser and the contractor and the safety of the equipment shall
be the responsibility of the Contractor.
(c) Trial Operation
The Plant shall then be on Trial Operation during which period all necessary
adjustments shall be made while operating over the full load-range enabling the plant
to be made ready for performance and guarantee tests.
15
The Trial run shall have to be performed with grid synchronization. In the absence of
grid availability necessary load and set up to be required for trial operation shall have
to be arranged by the supplier.
A Trial Operation report comprising of observations and recording of various
parameters to be measured in respect of the above Trial Operation shall be prepared
by the Contractor. This report, besides recording the details of the various
observations during trial run, shall also include the dates of start and finish of the Trial
Operations and shall be signed by the representatives of both the parties. The report
shall have sheet, recording all the details of interruptions occurred, adjustments made
and any minor repairs done during the Trial Operation. Based on the observations,
necessary modifications, repairs to the plant shall be carried out by the Contractor to
the full performance and guarantee tests on the Plant. However, minor defects which
do not endanger the safe operation of the equipment, shall not be considered as
reasons for with holding the aforesaid permission.
(d) Performance and guarantee test
The final test as to the performance and guarantees shall be conducted at site, by the
purchaser. Such tests will be commenced after successful completion of Trial
Operations.
These tests shall be binding on both the parties of the Contract to determine
compliance of the equipment with the performance guarantees.
Any special equipment, load, tool and tackles required for the successful completion of
the performance and guarantee tests shall be provided by the Contractor.
The guaranteed performance figures of the equipment, shall be proved by the
Contractor during these performance and guarantees tests. Should the results of
these tests show any decrease from the guaranteed values, the Contractor shall
modify the equipment as required to enable it to meet the guarantees. In such case,
performance and guarantee tests shall be repeated within one month, from the date
the equipment is ready for retest and all cost for modification including labour,
materials and the cost of additional testing to prove that the equipment meet the
guarantees, shall be borne by the Contractor
21. For the System & Other Software the following will apply :
The Supplier shall provide complete and legal documentation of hardware, all
subsystems, operating systems, compiler, system software and the other software. The Supplier shall also provide licensed software for all software products, whether developed by it or acquired from others. The supplier shall also indemnify the purchaser against any levies/penalties on account of any default in this regard.
22. Acceptance Certificates cum Commissioning Certificate:
On successful completion of acceptability test, receipt of deliverables etc, and after
the purchaser is satisfied with the working on the plant, the commissioning certificate/Joint commissioning report signed by the supplier and the representative of the purchaser will be issued.
16
23 WARRANTY
23.1 The Supplier warrants that the Goods supplied under this Contract are new, unused,
of the most recent or current models and incorporate all recent improvements in
design and materials unless provided otherwise in the Contract. The Supplier further
warrants that the Goods supplied under this Contract shall have no defect arising
from design, materials or workmanship (except when the design and/or is required by
the Purchaser's Specifications) or from any act or omission of the Supplier, that may
develop under normal use of the supplied Goods in conditions prevailing in the
country of final destination.
23.2 This warranty shall remain valid for Sixty Months 60 months after the Goods or any
portion thereof as the case may be, have been delivered and installed to and
accepted at the final destination indicated in the Contract, or for 72 seventy two
months after the date of shipment from the port of loading in the source country,
whichever period concluded earlier.
23.3 The Purchaser shall promptly notify the Supplier in writing of any claims arising under
this warranty.
23.4 Upon receipt of such notice, the Supplier shall, within the period 3 days and with all
reasonable speed, repair or replace the defective Goods or parts thereof, without cost
to the Purchaser other than, where applicable, the cost of inland delivery of the
repaired or replaced Goods or parts from the port of entry to the final destination.
23.5 If the Supplier, having been notified, fails to remedy the defect(s) within the period
specified above , the Purchaser may proceed to take such remedial action as may be
necessary, at the Supplier's risk and expense and without prejudice to any other
rights which the Purchaser may have against the Supplier under the Contract.
24. Payments Payment shall be made in the following manner:
(a) Payment for Goods and Services (excluding Annual Maintenance Charges)
(i) Advance Payment : Ten (10) percent of the contract price shall be paid within thirty
(30) days of signing of the contract and upon submission of claim against a simple
receipt and a bank guarantee for the 110% amount valid until the goods are
delivered and in the form provided in the bidding documents or another form
acceptable to be purchaser.
(ii) On delivery : Sixty (60) percent of the contract price shall be paid within 30
days upon submission of required documents and conditions of the contract have
been complied with
(iii) On Final Acceptance: the remaining twenty (20)% of the contract price of the
goods shall be paid within thirty (30) days after the date of the Acceptance cum
commissioning Certificate issued by the Purchaser’s representative in the Performa
given in Performa- 7.
(iv) Balance 10% payment of work order value shall be released after the five year
maintenance period, however this amount can be released against equal amount of
Bank Guarantee valid for five years from the actual date of commissioning. On
17
receipt of Bank guarantee in the favour of PEDA Chandigarh for 10% equivalent
value of the contract (excluding annual maintenance costs) in the Performa-12
provided in the bidding document.
(b) Payment for Annual maintenance charges:
The annual maintenance charges shall be
paid in equal yearly installments within thirty days of receipt of claim at the end of
each year subject to satisfaction of PEDA/ User Agency.
(c) (i) For all the payments to be made, against Bank guarantees, the bank
guarantee shall be issued by a Scheduled Indian Bank located in India in the format enclosed at Section VIII. the guarantees issued by other banks should be confirmed by a scheduled Indian Bank operating in India.
(ii) Bank guarantees for advance payment shall be released not later than 30 days after the date of completion of installation of the of the goods at their final destination.
25. Prices
Prices payable to the Supplier as stated in the Contract shall be firm and not subject
to adjustment during performance of the Contract.
26. MAINTENANCE SERVICE
26.1 Maintenance services shall be provided by the supplier during the period of warranty. Annual maintenance and repairs of the entire system including supply of spares etc. for next 60 months will be done by the supplier from the date of commissioning of the plant at their own cost.
26.2 The maximum response time for a maintenance complaint from any of the
destination specified in the schedule of requirements (i.e. time required for suppliers maintenance engineers to report to the installations after a request call/telegram/fax is made or letter is written) shall not exceed 48 hours .
26.3 It is expected that the average downtime of an item will be less than half the
maximum downtime (i.e. defined as number of days for which an item of equipment is not usable because of inability of the supplier to repair it) as mentioned by the bidder in the form of technical details. In case an item is not usable beyond the stipulated maximum downtime the supplier will be required to arrange for an immediate replacement of the same till it is repaired. Failure to arrange for the immediate repair/replacement will be liable for penalty of 0.5% of the item/items cost per day per item. The amount of penalty will be recovered from bank guarantee during warranty or annual maintenance period as the case may be. If the supplier failed to maintain/repair the plant during 5 years maintenance period within stipulated time period then PEDA shall have every right to encash their 10% amount or forfeit the BG lying with PEDA .
27. Liquidated Damages
(i) Failure to complete work order in time shall attract penalty @ 0.5% of the
delayed goods for every week of delay or part thereof subject to a maximum
of 10% value of delayed goods and services including project commissioning.
However on reaching of Maximum penalty the work order cum contract
18
agreement may be cancelled and performance security may also be forfeited
by PEDA.
(ii) Relaxation in completion period for the purpose of penalty can be allowed if
the delay is beyond the control of contractor or due to force majeure
conditions. The proper documentation establishing the reasons for delay in
this regard will be required to be given by the supplier to PEDA. The decision
in this regard shall be given by Chief Executive, PEDA.
28. Resolution of Disputes
The dispute resolution shall be as follows:
(a) In case of Dispute or difference arising between the Purchaser and a domestic
supplier relating to any matter arising out of or connected with this agreement,
such disputes or difference shall be settled in accordance with the Arbitration and
Conciliation Act, 1996. The arbitral tribunal shall consist of 3 arbitrators one each
to be appointed by the Purchaser and the Supplier. The third Arbitrator shall be
chosen by the two Arbitrators so appointed by the Parties and shall act as
Presiding arbitrator. In case of failure of the two arbitrators appointed by the
parties to reach upon a consensus within a period of 30 days from the
appointment of the arbitrator appointed subsequently, the Presiding Arbitrator shall
be appointed by the *Indian Council of Arbitration/President of the Institution of
Engineers (India)/The International Centre for Alternative Dispute Resolution
(India).
(b) In the case of a dispute with a Foreign Supplier, the dispute shall be settled in
accordance with provisions of UNCITRAL (United Nations Commission on
International Trade Law) Arbitration Rules. The Arbitral Tribunal shall consist of
three Arbitrators one each to be appointed by the Purchaser and the Supplier. The
third Arbitrator shall be chosen by the two Arbitrators so appointed by the Parties,
and shall act as presiding arbitrator. In case of failure of the two arbitrators
appointed by the parties to reach upon a consensus within a period of 30 days
from the appointment of the arbitrator appointed subsequently, the Presiding
Arbitrator shall be appointed by the *Indian Council of Arbitration/President of the
Institution of Engineers (India)/The International Centre of Alternative Dispute
Resolution (India).
(c) If one of the parties fails to appoint its arbitrator in pursuance of sub-clause (a) and
(b) above, within 30 days after receipt of the notice of the appointment of its
arbitrator by the other party, then the *Indian Council of Arbitration/President of the
Institution of Engineers (India)/The International Centre for Alternative dispute
Resolution (India), both in cases of the Foreign supplier as well as Indian supplier,
shall appoint the arbitrator. A certified copy of the order of the *Indian Council of
Arbitration/President of the Institution of Engineers (India)/The International Centre
for Alternative Disputes Resolution (India), making such an appointment shall be
furnished to each of the parties.
(d) Arbitration proceedings shall be held at Chandigarh , India, and the language of
the arbitration proceedings and that of all documents and communications
between the parties shall be English.
19
(e) The decision of the majority of arbitrators shall be final and binding upon both
parties. The cost and expenses of Arbitration proceedings will be paid as
determined by the arbitral tribunal. However, the expenses incurred by each party
in connection with the preparation, presentation etc. of its proceedings as also the
fees and expenses paid to the arbitrator appointed by such party or on its behalf
shall be borne by each party itself.
(f) Where the value of the contract is Rs. 10 million and below, the disputes or
differences arising shall be referred to the Sole Arbitrator. The Sole Arbitrator
should be appointed by agreement between the parties; failing such agreement,
by the appointing authority namely the *Indian Council of Arbitration/President of
the Institution of Engineers (India)/The International Centre for Alternative Dispute
Resolution (India).
29. PLANT INSTALLATION:
The Supplier is responsible for all unpacking, assemblies, wiring, installations,
cabling between solar modules and connecting to power supplies & INVERTER .
The Supplier will test all equipment operations and accomplish all adjustments
necessary for successful and continues operation of the plant at the installation
site.
30. TERMINATION FOR DEFAULT
30.1 The Purchaser may, without prejudice to any other remedy for breach of
contract, by written notice of default sent to the Supplier, terminate the
Contract in whole or in part:
a. if the Supplier fails to deliver any or all of the Goods within the
period(s) specified in the Contract, or within any extension thereof
granted by the Purchaser or
b. if the Supplier fails to perform any other obligation(s) under the
Contract.
c. If the supplier, in the judgment of the purchaser, has engaged in
corrupt or fraudulent practices in competing for or in executing the
contract.
For the purpose of this clause :
“corrupt practice” means the offering, giving, receiving, or soliciting of
anything of value to influence the action of a public official in the
procurement process or in contract execution.
“fraudulent practice” means a misrepresentation of facts in order to
influence a procurement process or the execution or a contract to the
detriment of the borrower, and includes collusive practice among
bidders (prior to or after bid submission) designed to establish bid
prices at artificial non-competitive levels and to deprive the borrower of
the benefits of free and open competition.
30.2 In the event the Purchaser terminates the Contract in whole or in part,
pursuant to, the Purchaser may procure, upon such terms and in such
manner as it deems appropriate, Goods or services similar to those
undelivered, and the Supplier shall be liable to the Purchaser for any excess
costs for such similar Goods or services. However, the Supplier shall continue
the performance of the Contract to the extent not terminated.
20
31. FORCE MAJEURE
31.1 The Supplier shall not be liable for forfeiture of its performance security, liquidated
damages or termination for default, if and to the extent that, its delay in performance
or other failure to perform its obligations under the Contract is the result of an event
of Force Majeure.
31.2 For purposes of this Clause, "Force Majeure" means an event beyond the control of
the Supplier and not involving the Supplier's fault or negligence and not foreseeable.
Such events may include, but are not restricted to, acts of the Purchaser in its
sovereign capacity, wars or revolutions, fires, floods, epidemics, quarantine
restrictions and freight embargoes.
31.3 If a Force Majeure situation arises, the Supplier shall promptly notify the Purchaser in
writing of such conditions and the cause thereof. Unless otherwise directed by the
Purchaser in writing, the Supplier shall continue to perform its obligations under the
Contract as far as is reasonably practical, and shall seek all reasonable alternative
means for performance not prevented by the Force Majeure event.
32. TERMINATION FOR INSOLVENCY
32.1 The Purchaser may at any time terminate the Contract by giving written notice to the
Supplier, if the Supplier becomes bankrupt or otherwise insolvent. In this event,
termination will be without compensation to the supplier, provided that such
termination will not prejudice or affect any right of action or remedy which has
accrued or will accrue thereafter to the Purchaser.
33. TERMINATION FOR CONVENIENCE
33.1 The Purchaser, may by written notice sent to the Supplier, may terminate the
Contract, in whole or in part, at any time for its convenience. The notice of
termination shall specify that termination is for the Purchaser's convenience, the
extent to which performance of the supplier under the Contract is terminated, and the
date upon which such termination becomes effective.
33.2 The Goods that are complete and ready for shipment within 30 days after the
Supplier's receipt of notice of termination shall be accepted by the Purchaser at the
Contract terms and prices. For the remaining Goods, the Purchaser may elect:
a) to have any portion completed and delivered at the Contract terms and prices;
and/or
b) to cancel the remainder and pay to the Supplier an agreed amount for partially
completed Goods and services for materials and parts previously procured by
the Supplier.
34. SETTLEMENT OF DISPUTES
34.1 If any dispute or difference of any kind whatsoever shall arise between the Purchaser
and the supplier in connection with or arising out of the contract, the parties shall
make every effort to resolve amicably such dispute or difference by mutual
consultation.
34.2. If, after thirty (30) days the parties have failed to resolve their dispute or difference by
such mutual consultation, then either the purchaser of the supplier may give notice to
the other party of its intention to commence arbitration, as hereinafter provided, as to
the matter in dispute, and no arbitration in respect of this matter may be commenced
unless such notice is given.
21
34.2.1 Any dispute or difference in respect of which a notice of intention to commence
arbitration has been given in accordance with this clause shall be finally settled by
arbitration. Arbitration may be commenced prior to or after delivery of the Goods
under the contract.
34.2.2 Arbitration proceedings shall be conducted in accordance with the rules of procedure
specified above.
34.3 Notwithstanding any reference to arbitration herein,
(a) the parties shall continue to perform their respective obligations under the
contract unless they otherwise agree ; and
(b) the purchaser shall pay the supplier any monies due the supplier.
35. LIMITATION OF LIABILITY
35.1 Except in cases of criminal negligence or willful misconduct, and in the case of
infringement pursuant to Clause ,
(a) the supplier shall not be liable to the purchaser, whether in contract, tort, or
otherwise, for any indirect or consequential loss or damage, loss of use, loss of
production, or loss of profits or interest costs, provided that this exclusion shall
not apply to any obligation of the supplier to pay liquidated damages to the
purchaser and
(b) the aggregate liability of the supplier to the purchaser, whether under the
contract, in tort or otherwise, shall not exceed the total contract price, provided
that this limitation shall not apply to the cost of repairing or replacing defective
equipment.
36. PLANT PERFORMANCE EVALUATION
The successful bidder shall be required to meet minimum guaranteed generation
with Performance Ratio (PR) at the time of commissioning and related Capacity
Utilization Factor (CUF) as per the GHI levels of the location during the O&M
period. PR should be shown minimum of 75% at the time of inspection. Minimum
CUF of 15% should be maintained for a period of 5 years. The bidder should send
the periodic plant output details to PEDA for ensuring the CUF. The PR will be
measured at Inverter output level during peak radiation conditions.
37. Bidder should furnish performance Statement in Performa-6, Service Centre
Detail in Performa-8, technical details of its offer in Performa 9,
38. GOVERNING LANGUAGE
The governing language shall be English
22
SECTION III
3. SCHEDULE OF REQUIREMENTS
23
Part 1
The general scope under this contract includes design, manufacture, shop testing, inspection, packing & forwarding, transportation upto project site loading & unloading, storage in safe custody, erection, carrying out preliminary tests at site, commissioning, performance testing & handing over to the purchaser all the equipment installed including the insurance coverage for the concept to commissioning period including 5 years maintenance as under :- The illustrative Schedule of requirements is in accordance with the specifications contained in this document
Sl. No.
Brief Description Units Make
1. SPV modules for a total capacity as per specifications.
1 Set Compliant to bid document spec’s As per IEC 61215 2nd edition and MNRE, GOI latest specifications /standards
2. SPV module roof top mounting structure suitable for accommodating SPV modules including foundation as per specifications on rooftop.
1 Set As per specification
3. Inverter as per specifications As per spec. Compliant to bid document spec’s. As per IEC 61683/IS 61683 and IEC 60068-2(1,2,14,30) /Equivalent BIS Std
4. Array Junction Boxes 1 Set Tyco / Hensel
5. Main Junction Boxes 1 Set Tyco / Hensel
6. DC Distribution Switchgear units as per specifications
1 set ABB / SIEMENS / Schnieder Electric
7. AC Distribution Switchgear units as per specifications
1 Set L&T / ABB / Schnieder Electric
8. DC Cable requirement as per design
Meters As required at site for full plant commissioning
Havells/ Finolex / CCI/ Seichem/ Polycab/Leoni/KEI
9. AC Cable requirement as per design
Meters As required at site for full plant commissioning
Havells/ Finolex / CCI/ Seichem/ Polycab/Leoni/ Kei
10. Lightning arrester complete set as per specification 1 Set
24
11. Earthing complete 3 numbers as per specification 1 Set 3 Numbers
12. Spares, tools and plant for 5years operation and maintenance
As per list
13. Maintenance of the SPV Power Plant for a period of 5 years from date of commissioning of the power plant as per scope.
14. Engineering, electrical drawings and installations and O&M manuals
3 Sets
15. Any other equipment required to complete the installation
16. Civil work and array structures: complete design, construction of array support structures on the roof top.
As per design submitted by supplier and approved by purchaser
Note : 1. The requirements for the plant and machinery are indicated in the schedule of requirements. The items indicated in the schedules are only indicative and the suppliers are required to include and quote for any other item left out in the schedule. Complete details and quantity of mandatory spare parts shall be furnished by the supplier in their bid. Suppliers shall offer their complete design along with drawings for the plant in their bids. 2. The user agency will be installed three phase transformer and breaker as per PSPCL regulations for 100KW and above SPV Power Plants, if required. The transformer and breaker is not part of the scope of work of this tender. Delivery Schedule
Sr. No. Description Time Required
1. Award of contract Say X date
2. Signing of Contract Agreement & submission of
Performance Guarantee
X + 15 days
3. Submission of Bank Guarantee for release of Advance
amount and submission of PERT Chart
X + 20 days
4. Submission of all documents related to procurement of all
Bought-out items delivery schedule, etc.
X + 30 days
5. Submission of site survey, engineering & design documents
for approval of PEDA
X + 50 days
6. Activities like inspection by PEDA, supply of complete
material at site, commencement of civil works at site and
other activities
X + 100 days*
7. Installation and Complete commissioning X+120 days
* indicative purpose
25
SECTION IV
4. TECHNICAL SPECIFICATIONS
26
General Description
The power plant shall provide a reliable and independent power supply to the critical
AC loads in the Building. The power plant shall have a provision to export the excess
power generated to the grid and shall have a provision to import power from grid for
localized use in case of load exceeding the PV generation. The Inverter shall be
designed to convert DC power produced by SPV modules, in to AC power and adjust
the voltage & frequency levels to suit the grid voltage & frequency.
A Grid Tied Solar Rooftop Photo Voltaic (SPV) power plant consists
of SPV array, Module Mounting Structure, Power Conditioning Unit (PCU) consisting
of Maximum Power Point Tracker (MPPT), Inverter, and Controls & Protections,
interconnect cables and switches. PV Array is mounted on a suitable structure. Grid
tied SPV system is without battery and should be designed with necessary features to
supplement the grid power during day time. Components and parts used in the SPV
power plants including the PV modules, metallic structures, cables, junction box,
switches, PCUs etc., should conform to the BIS or IEC or international specifications,
wherever such specifications are available and applicable.
Solar PV system shall consist of following equipments/components.
Solar PV modules consisting of required number of Crystalline PV modules.
Grid interactive Power Conditioning Unit with Remote Monitoring System
Mounting structures
Junction Boxes.
Earthing and lightening protections.
IR/UV protected PVC Cables, pipes and accessories
1. Solar Photovoltaic Modules
(A) Indigenous make only
1.1. The PV modules and its cells used should be made in India.
1.2. The PV modules used must qualify to the latest edition of IEC PV module qualification
test or equivalent BIS standards Crystalline Silicon Solar Cell Modules IEC
61215/IS14286. In addition, the modules must conform to IEC 61730 Part-2-
requirements for construction & Part 2 – requirements for testing, for safety
qualification or equivalent IS.
a) For the PV modules to be used in a highly corrosive atmosphere throughout their
lifetime, they must qualify to IEC 61701/IS 61701
b) The total solar PV array capacity should not be less than allocated capacity (kWp)
and should comprise of solar crystalline modules of minimum 250 Wp and above
wattage. Module capacity less than minimum 250 watts should not be accepted. The
efficiency of the modules should not be less than 16%.
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
27
c) Protective devices against surges at the PV module shall be provided. Low voltage
drop bypass diodes shall be provided.
d) PV modules must be tested and approved by one of the IEC authorized test centers.
e) The module frame shall be made of corrosion resistant materials, preferably having
anodized aluminum.
f) The bidder shall carefully design & accommodate requisite numbers of the modules to
achieve the rated power in his work order.
g) Other general requirement for the PV modules and subsystems shall be the Following:
I. The rated output power of any supplied module shall have tolerance of +/-3%.
II. The peak-power point voltage and the peak-power point current of any supplied
module and/or any module string (series connected modules) shall not vary by more
than 2 (two) per cent from the respective arithmetic means for all modules and/or for
all module strings, as the case may be.
III. The module shall be provided with a junction box with either provision of external
screw terminal connection or sealed type and with arrangement for provision of by-
pass diode. The box shall have hinged, weather proof lid with captive screws and
cable gland entry points or may be of sealed type and IP-65 rated.
IV. IV curves at STC should be provided by bidder.
14.1.3. Modules deployed must use a RF identification tag. The following information must be
mentioned in the RFID used on each modules (This can be inside or outside the
laminate, but must be able to withstand harsh environmental conditions).
a) Name of the manufacturer of the PV module
b) Name of the manufacturer of Solar Cells.
c) Month & year of the manufacture (separate for solar cells and modules)
d) Country of origin (separately for solar cells and module)
e) I-V curve for the module Wattage, Im, Vm and FF for the module
f) Unique Serial No and Model No of the module
g) Date and year of obtaining IEC PV module qualification certificate.
h) Name of the test lab issuing IEC certificate.
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
28
i) Other relevant information on traceability of solar cells and module as per ISO 9001
and ISO 14001
14.1.4. Warranties:
a) Material Warranty:
i. Material Warranty is defined as: The manufacturer should warrant the Solar Module(s)
to be free from the defects and/or failures specified below for a period not less than five
(05) years from the date of sale .
ii. Defects and/or failures due to manufacturing
iii. Defects and/or failures due to quality of materials
iv. Non conformity to specifications due to faulty manufacturing and/or inspection
processes. If the solar Module(s) fails to conform to this warranty, the manufacturer will
repair or replace the solar module(s), at the Owners sole option
b) Performance Warranty:
i. The predicted electrical degradation of power generated not exceeding 20% of the
minimum rated power over the 25 year period and not more than 10% after ten years
period of the full rated original output.
2. ARRAY STRUCTURE
a) Hot dip galvanized MS mounting structures may be used for mounting the modules/
panels/arrays. Each structure should have angle of inclination as per the site conditions
to take maximum insolation. However to accommodate more capacity the angle
inclination may be reduced until the plant meets the specified performance ratio
requirements.
b) The Mounting structure shall be so designed to withstand the speed for the wind zone
of the location where a PV system is proposed to be installed (like Delhi-wind speed of
150 KM/ hour). It may be ensured that the design has been certified by a recognized
Lab/ Institution in this regard and submit wind loading calculation sheet to PEDA.
Suitable fastening arrangement such as grouting and calming should be provided to
secure the installation against the specific wind speed.
c) The mounting structure steel shall be as per latest IS 2062: 1992 and galvanization of
the mounting structure shall be in compliance of latest IS 4759.
d) Structural material shall be corrosion resistant and electrolytically compatible with the
materials used in the module frame, its fasteners, nuts and bolts. Aluminium structures
also can be used which can withstand the wind speed of respective wind zone.
Necessary protection towards rusting need to be provided either by coating or
anodization.
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
29
e) The fasteners used should be made up of stainless steel. The structures shall be
designed to allow easy replacement of any module. The array structure shall be so
designed that it will occupy minimum space without sacrificing the output from the SPV
panels
f) Regarding civil structures the bidder need to take care of the load baring capacity of the
roof and need arrange suitable structures based on the quality of roof.
g) The total load of the structure (when installed with PV modules) on the terrace should
be less than 60 kg/m2.
h) The minimum clearance of the structure from the roof level should be 300 mm.
i) No damage in any way should be caused to the roof of the building while
installation of SPV Power Plant. If any damage done it will wholly be the
responsibility of the bidder and cost shall be recovered from the bidder. To
avoid any problem the system of fixing of panel structure shall be got approved.
Detailed design and Drawing shall have to submit to PEDA for
acceptance and approval before execution of work.
NOTE: The structural design of the complete system should be compatible with the
structural strength and load bearing capacity of the roof, design calculations and
certificate to this effect shall be provided by a qualified chartered structural
engineer.
3. JUNCTION BOXES (JBs)
a) The junction boxes are to be provided in the PV array for termination of connecting
cables. The J. Boxes (JBs) shall be made of GRP/FRP/Powder Coated Aluminum /cast
aluminum alloy with full dust, water & vermin proof arrangement. All wires/cables must
be terminated through cable lugs. The JBs shall be such that input & output termination
can be made through suitable cable glands.
b) Copper bus bars/terminal blocks housed in the junction box with suitable termination
threads Conforming to IP65 standard and IEC 62208 Hinged door with EPDM rubber
gasket to prevent water entry. Single / double compression cable glands. Provision of
earthings. It should be placed at 5 feet height or above for ease of accessibility.
c) Each Junction Box shall have High quality Suitable capacity Metal Oxide Varistors
(MOVs) / SPDs, suitable Reverse Blocking Diodes. The Junction Boxes shall have
suitable arrangement monitoring and disconnection for each of the groups.
d) Suitable markings shall be provided on the bus bar for easy identification and the
cable ferrules must be fitted at the cable termination points for identification
4. DC DISTRIBUTION BOARD:
e) DC Distribution panel to receive the DC output from the array field.
f) DC DPBs shall have sheet from enclosure of dust & vermin proof conform to IP 65
protection. The bus bars are made of copper of desired size. Suitable capacity
MCBs/MCCB shall be provided for controlling the DC power output to the PCU along
with necessary surge arrestors.
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
30
5. AC DISTRIBUTION PANEL BOARD:
g) AC Distribution Panel Board (DPB) shall control the AC power from PCU/ inverter, and
should have necessary surge arrestors. Interconnection from ACDB to mains at LT Bus
bar while in grid tied mode.
h) All switches and the circuit breakers, connectors should conform to IEC 60947, part I, II
and III/ IS60947 part I, II and III.
i) The changeover switches, cabling work should be undertaken by the bidder as part of
the project.
j) All the Panel’s shall be metal clad, totally enclosed, rigid, floor mounted, air - insulated,
cubical type suitable for operation on three phase / single phase, 415 or 230 volts, 50 Hz .
e) The panels shall be designed for minimum expected ambient temperature of 45 degree
Celsius, 80 percent humidity and dusty weather.
f) All indoor panels will have protection of IP54 or better. All outdoor panels will have
protection of IP65 or better.
g) Should conform to Indian Electricity Act and rules (till last amendment).
h) All the 415 AC or 230 volts devices / equipment like bus support insulators, circuit
breakers, SPDs, VTs etc., mounted inside the switchgear shall be suitable for
continuous operation and satisfactory performance under the following supply
conditions
Variation in supply +/- 10 %
voltage
Variation in supply +/- 3 Hz
frequency
6. PCU/ARRAY SIZE RATIO:
a) The combined wattage of all inverters should not be less than rated capacity of
power plant under STC.
b) Maximum power point tracker shall be integrated in the PCU/inverter to
maximize energy drawn from the array.
7. PCU/ Inverter:
As SPV array produce direct current electricity, it is necessary to convert this direct
current into alternating current and adjust the voltage levels to match the grid voltage.
Conversion shall be achieved using an electronic Inverter and the associated control
and protection devices. All these components of the system are termed the “Power
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
31
Conditioning Unit (PCU)”. In addition, the PCU shall also house MPPT (Maximum
Power Point Tracker), an interface between Solar PV array & the Inverter, to the power
conditioning unit/inverter should also be DG set interactive, If necessary. Inverter output
should be compatible with the grid frequency. Typical technical features of the inverter
shall be as under:-
Switching devices IGBT
Control Microprocessor / DSP
Nominal AC output voltage and frequency 415V, 3 phase, 50 Hz
Output Frequency Synchronization range + 3 Hz or more
Ambient temperature considered - 20 Co to 50 Co
Humidity 95% Non-condensing
Protection of Enclosure IP-20 (minimum) for indoor
IP-65(minimum) for outdoor
Grid Frequency Tolerance range + 3 or more
Grid Voltage Tolerance - 20% & + 15%
No-load losses Less than 1% of rated power
Inverter efficiency (minimum) >95% ( in case of 10kW or above)
Inverter efficiency (minimum) >93% ( in case of less than 10kW )
THD < 3%
PF >0.9
a) Three phase PCU/ inverter shall be used with each power plant system (5 kW and/or
above) but In case of less than 5 kW single phase inverter can be used.
b) PCU/inverter shall be capable of complete automatic operation including wake-up,
synchronization & shutdown.
c) The output of power factor of PCU inverter is suitable for all voltage ranges or sink of
reactive power, inverter should have internal protection arrangement against any
sustainable fault in feeder line and against the lightning on feeder.
d) Built-in meter and data logger to monitor plant performance through external computer
shall be provided.
e) The power conditioning units / inverters should comply with applicable IEC/ equivalent
BIS standard for efficiency measurements and environmental tests as per standard
codes IEC 61683/IS 61683 and IEC 60068-2(1,2,14,30) /Equivalent BIS Std.
f) The charge controller (if any) / MPPT units environmental testing should qualify IEC
60068-2(1, 2, 14, 30)/Equivalent BIS std. The junction boxes/ enclosures should be IP
65(for outdoor)/ IP 54 (indoor) and as per IEC 529 specifications.
g) The PCU/ inverters should be tested from the MNRE approved test centres / NABL
/BIS /IEC accredited testing- calibration laboratories. In case of imported power
conditioning units, these should be approved by international test houses.
8. INTEGRATION OF PV POWER WITH GRID:
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
32
The output power from SPV would be fed to the inverters which converts DC produced
by SPV array to AC and feeds it into the main electricity grid after synchronization. In
case of grid failure, or low or high voltage, solar PV system shall be out of
synchronization and shall be disconnected from the grid. Once the DG set comes into
service PV system shall again be synchronized with DG supply and load requirement
would be met to the extent of availability of power. 4 pole isolation of inverter output
with respect to the grid/ DG power connection need to be provided.
8.1 Technical and interconnection requirements
Overall conditions of
service
State Distribution/Supply Code State Distribution/Supply Code
Overall Grid Central Electricity Authority
(Grid
Central Electricity Authority (Grid
Standard)
Standards Standard) Regulations 2010 Regulations 2010
Equipment BIS / IEC / IEEE BIS / IEC / IEEE
Meters Central Electricity authority
(Installation & operation of
meters) Regulation 2006 as
amended time to time
Central Electricity authority
(Installation & operation of meters)
Regulation 2006 as amended time
to time
Safety and supply Central Electricity
Authority(measures of safety
and electricity supply)
Regulations, 2010
Central Electricity
Authority(measures of safety and
electricity supply) Regulations, 2010
Harmonic IEEE 519 CEA (Technical IEEE 519 CEA (Technical
Standards for
Requirements Standards for Connectivity of
the
Connectivity of the Distributed
Generation
Harmonic Current Distributed Generation
Resources) Regulations 2013
Resources) Regulations 2013
Synchronization IEEE 519 CEA (Technical
Standards for Connectivity of
the Distributed Generation
Resources) Regulations 2013
Photovoltaic system must be
equipped with a grid frequency
synchronization device. Every time
the generating station is
synchronized to the electricity
system. It shall not cause voltage
fluctuation greater than +/- 5% at
point of connection.
Voltage IEEE 519 CEA (Technical
Standards for Connectivity of
the Distributed Generation
Resources) Regulations 2013
The voltage-operating window
should minimize nuisance tripping
and should be under operating
range of 80% to 110% of the
nominal connected voltage. Beyond
a clearing time of 2 second, the
photovoltaic system must isolate
itself from the grid.
Flicker IEEE 519 CEA (Technical
Standards for Connectivity of
the Distributed Generation
Operation of Photovoltaic system
should not cause
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
33
Resources) Regulations 2013
Frequency IEEE 519 CEA (Technical
Standards for Connectivity of
the Distributed Generation
Resources) Regulations 2013
When the Distribution system
frequency deviates outside the
specified conditions (50.5 Hz on
upper side and 47.5 Hz on lower
side), There should be over and
under frequency trip functions with a
clearing time of 0.2 seconds.
DC injection IEEE 519 CEA (Technical
Standards for Connectivity of
the Distributed Generation
Resources) Regulations 2013
Photovoltaic system should not
inject DC power more than 0.5% of
full rated output at the
interconnection point or 1% of rated
inverter output current into
distribution system under any
operating conditions.
Power Factor IEEE 519 CEA (Technical
Standards for Connectivity of
the Distributed Generation
Resources) Regulations 2013
While the output of the inverter is
greater than50%, a lagging power
factor of greater than 0.9 should
operate.
Islanding and IEEE 519 CEA (Technical The photovoltaic system in the
event of fault,
Disconnection Standards for Connectivity of
the Distributed Generation
Resources) Regulations 2013
voltage or frequency variations must
island/disconnect itself within IEC
standard on stipulated period.
Overload and Overheat IEEE 519 CEA (Technical
Standards for Connectivity of
the Distributed Generation
Resources) Regulations 2013.
The inverter should have the facility
to automatically switch off in case of
overload or overheating and should
restart when normal conditions are
restored.
Paralleling Device IEEE 519 CEA (Technical
Standards for Connectivity of
the Distributed Generation
Resources) Regulations 2013.
Paralleling device of photovoltaic
system shall be capable of
withstanding 220% of the normal
voltage at the interconnection point.
9. DATA ACQUISITION SYSTEM / PLANT MONITORING
i. Data Acquisition System shall be provided for each of the solar PV plant.
ii. Data Logging Provision for plant control and monitoring, time and date stamped system
data logs for analysis with the high quality, suitable PC. Metering and Instrumentation
for display of systems parameters and status indication to be provided. The PC is the
part of BOM of plant capacity for 25 KW or above. A
iii. Solar Irradiance: An integrating Pyranometer / Solar cell based irradiation sensor
(along with calibration certificate) provided, with the sensor mounted in the plane of the
array. Readout integrated with data logging system.
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
34
iv. Temperature: Temperature probes for recording the Solar panel temperature and/or
ambient temperature to be provided complete with readouts integrated with the data
logging system
v. The following parameters are accessible via the operating interface display in real time
separately for solar power plant:
a. AC Voltage.
b. AC Output current.
c. Output Power
d. Power factor.
e. DC Input Voltage.
f. DC Input Current.
g. Time Active.
h. Time disabled.
i. Time Idle.
j. Power produced
k. Protective function limits (Viz-AC Over voltage, AC Under voltage, Over frequency,
Under frequency ground fault, PV starting voltage, PV stopping voltage.
vi. All major parameters available on the digital bus and logging facility for energy auditing
through the internal microprocessor and logging facility (the current values, previous
values for up to a month and the average values) should be made available for energy
auditing .
vii. PV array energy production: Digital Energy Meters to log the actual value of AC/ DC
voltage, Current & Energy generated by the PV system provided. Energy meter along
with CT/PT should be of 0.5 accuracy class.
viii. Computerized DC String/Array monitoring and AC output monitoring shall be provided
as part of the inverter and/or string/array combiner box or separately.
ix. String and array DC Voltage, Current and Power, Inverter AC output voltage and
current (All 3 phases and lines), AC power (Active, Reactive and Apparent), Power
Factor and AC energy (All 3 phases and cumulative) and frequency shall be monitored.
x. Computerized AC energy monitoring shall be in addition to the digital AC energy meter.
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
35
xi. The data shall be recorded in a common work sheet chronologically date wise. The
data file shall be MS Excel compatible. The data shall be represented in both tabular
and graphical form.
xii. All instantaneous data shall be shown on the computer screen.
xiii. Software shall be provided for USB download and analysis of DC and AC parametric
data for individual plant.
xiv. Provision for Internet monitoring and download of data shall be also incorporated.
xv. Remote Server and Software for centralized Internet monitoring system shall be also
provided for download and analysis of cumulative data of all the plants and the data of
the solar radiation and temperature monitoring system.
xvi. Ambient / Solar PV module back surface temperature shall be also monitored on
continuous basis.
xvii. Simultaneous monitoring of DC and AC electrical voltage, current, power, energy and
other data of the plant for correlation with solar and environment data shall be provided.
xviii. Remote Monitoring and data acquisition through Remote Monitoring System software
location with latest software/hardware configuration and service connectivity for online /
real time data monitoring/control complete to be supplied and operation and
maintenance/control to be ensured by the supplier.
xix. Energy Meter: The solar generation meter and Bi-directional meter along with
CT/PT (if required) with Surge Protection Device (SPD) should be of as per PSPCL
guidelines and is in the scope of bidder.
10. POWER CONSUMPTION:
a) Regarding the generated power consumption, priority need to give for internal
consumption first and thereafter any excess power can be exported to grid..
11. PROTECTIONS
The system should be provided with all necessary protections like earthing,
Lightning, and grid islanding as follows:-
11.1. LIGHTNING PROTECTION
The SPV power plants shall be provided with lightning & over voltage protection. The
main aim in this protection shall be to reduce the over voltage to a tolerable value
before it reaches the PV or other sub system components. The source of over voltage
can be lightning, atmosphere disturbances etc The entire space occupying the SPV
array shall be suitably protected against Lightning by deploying required number of
Lightning Arrestors. Lightning protection should be provided as per IEC 62305
standard. The protection against induced high-voltages shall be provided by the use
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
36
of metal oxide varistors (MOVs) and suitable earthing such that induced transients
find an alternate route to earth.
11.2. SURGE PROTECTION
Internal surge protection shall consist of three MOV type surge-arrestors connected
from +ve and –ve terminals to earth (via Y arrangement)
11.3. EARTHING PROTECTION
i. Each array structure of the PV yard should be grounded/ earthed properly as per
IS:3043-1987. In addition the lighting arrester/masts should also be earthed inside the
array field. Earth Resistance shall be tested in presence of the representative of PEDA
as and when required after earthing by calibrated earth tester. PCU, ACDB and DCDB
should also be earthed properly.
ii. Earth resistance shall not be more than 5 ohms. It shall be ensured that all the earthing
points are bonded together to make them at the same potential.
11.4. GRID ISLANDING:
i. In the event of a power failure on the electric grid, it is required that any independent
power-producing inverters attached to the grid turn off in a short period of time. This
prevents the DC-to-AC inverters from continuing to feed power into small sections of
the grid, known as “islands.” Powered islands present a risk to workers who may expect
the area to be unpowered, and they may also damage grid-tied equipment. The
Rooftop PV system shall be equipped with islanding protection. In addition to
disconnection from the grid (due to islanding protection) disconnection due to under
and over voltage conditions shall also be provided.
ii. A manual disconnect 4 pole isolation switch beside automatic disconnection to grid
would have to be provided at utility end to isolate the grid connection by the utility
personnel to carry out any maintenance. This switch shall be locked by the utility
personnel
12. CABLES
Cables of appropriate size to be used in the system shall have the following
characteristics:
i. Shall meet IEC 60227/IS 694, IEC 60502/IS1554 standards
ii. Temp. Range: –10oC to +80oC.
iii. Voltage rating 660/1000V
iv. Excellent resistance to heat, cold, water, oil, abrasion, UV radiation
v. Flexible
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
37
vi. Sizes of cables between array interconnections, array to junction boxes, junction boxes to
Inverter etc. shall be so selected to keep the voltage drop (power loss) of the entire solar
system to the minimum. The cables (as per IS) should be insulated with a special grade
PVC compound formulated for outdoor use.
vii. Cable Routing/ Marking: All cable/wires are to be routed in a GI cable tray and suitably
tagged and marked with proper manner by good quality ferule or by other means so that
the cable easily identified.
viii. The Cable should be so selected that it should be compatible up to the life of the solar PV
panels i.e. 25years.
ix. The ratings given are approximate. Bidder to indicate size and length as per system
design requirement. All the cables required for the plant provided by the bidder. Any
change in cabling sizes if desired by the bidder/approved after citing appropriate reasons.
All cable schedules/layout drawings approved prior to installation.
x. Multi Strand, Annealed high conductivity copper conductor PVC type ‘A’ pressure
extruded insulation or XLPE insulation. Overall PVC/XLPE insulation for UV protection
Armoured cable for underground laying. All cable trays including covers to be provided.
All cables conform to latest edition of IEC/ equivalent BIS Standards as specified below:
BoS item / component Standard.
Description Standard Number Cables General Test and Measuring Methods, PVC/XLPE
insulated cables for working Voltage up to and including 1100 V ,UV resistant for outdoor
installation IS /IEC 69947.
xi. The size of each type of DC cable selected shall be based on minimum voltage drop
however; the maximum drop shall be limited to 1%.
xii. The size of each type of AC cable selected shall be based on minimum voltage drop
however; the maximum drop shall be limited to 2 %.
13. DANGER BOARDS AND SIGNAGES:
Danger boards should be provided as and where necessary as per IE Act. /IE rules as
amended up to date. Three signage shall be provided one each at battery –cum- control
room, solar array area and main entry from administrative block.
14. FIRE EXTINGUISHERS:
The firefighting system for the proposed power plant of capacity above than 25 kw for
fire protection shall be consisting of:
a) Portable fire extinguishers in the control room for fire caused by electrical short
circuits
b) Sand buckets in the control room
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
38
c) The installation of Fire Extinguishers should confirm to TAC regulations and BIS
standards. The fire extinguishers shall be provided in the control room housing
PCUs as well as on the Roof or site where the PV arrays have been installed.
15. DRAWINGS & MANUALS:
i. Two sets of Engineering, electrical drawings and Installation and O&M manuals are to
be supplied. Bidders shall provide complete technical data sheets for each equipment
giving details of the specifications along with make/makes in their bid along with basic
design of the power plant and power evacuation, synchronization along with
protection equipment.
ii. Approved ISI and reputed makes for equipment be used.
iii. For complete electro-mechanical works, bidders shall supply complete design, details
and drawings for approval to PEDA before progressing with the installation work
16. DRAWINGS TO BE FURNISHED BY BIDDER AFTER AWARD OF CONTRACT
i. The Contractor shall furnish the following drawings Award/Intent and obtain approval
ii. General arrangement and dimensioned layout
iii. Schematic drawing showing the requirement of SV panel, Power conditioning Unit(s)/
inverter, Junction Boxes, AC and DC Distribution Boards, meters etc.
iv. Structural drawing along with foundation details for the structure.
v. Itemized bill of material for complete SV plant covering all the components and
associated accessories.
vi. Layout of solar Power Array
vii. Shadow analysis of the roof
17. SAFETY MEASURES:
The bidder shall take entire responsibility for electrical safety of the installation(s) including
connectivity with the grid and follow all the safety rules & regulations applicable as per
Electricity Act, 2003 and CEA guidelines etc.
18. TOOLS & TACKLES AND SPARES :
After completion of installation & commissioning of the power plant, necessary tools &
tackles are to be provided free of cost by the contractor for maintenance purpose. List of
tools and tackles to be supplied by the contractor for approval of specifications and make
from PEDA.
A list of requisite spares in case of INVERTER comprising of a set of control logic cards,
IGBT driver cards etc, Junction Boxes, Fuses, MCCBs etc. along with spare set of PV
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
39
modules and batteries be indicated, which shall be supplied along with the equipment. A
minimum set of spares shall be maintained in the plant itself for the entire period of
warranty and Operation & Maintenance which upon its use shall be replenished. A
minimum spare parts list is enclosed at Annexure 1 in Section IX.
19. CIVIL STRUCTURE
Civil Works and piping, Water pump
General Specification of Work.
Scope : The scope of work includes :
1. Full painting of the control room provided in the building along with necessary
partition with glass and aluminum frame structure works.
2. Providing of pedestals if required for mounting of the INVERTER’s and control
panels
3. Water pump with shed along with full C class piping for water supply on the rooftop
with array level supply points for panels cleaning and washing along with water
discharge piping upto ground level.
4. RCC columns structures to support the structural steel / aluminium frame work /
depending on design approval.
5. Any other work urgently required as per site conditions.
6. Full water proofing of the building rooftop have to be carried out after installation of
structures if required.
7. All structural drawings to be got approved from PEDA.
A) Brick Work :
1. Unless otherwise specified, brick work shall consist of first class bricks laid in the
specified mortar strictly according to drawings and specifications.
2. Bricks required for brick work in cement mortars shall be thoroughly soaked in clean
water immediately before use for one hour or till complete causation of air bubbles
which ever is later, in brick lined or steel tanks of sufficient size. The soaked bricks
shall be kept on wooden planks or brick platforms to avoid earth being smeared on
them. Unless otherwise specified, bricks shall be laid in English bond, with frogs
upwards.
3. All horizontal joints shall be parallel and unless otherwise specified, truly level. All
vertical joint shall be truly vertical and they shall come directly over one another in
alternate courses.
4. The thickness of joints shall be as follows :
“ The thickness of joints shall be 1/4” and shall not exceed 3/8” The height of four
courses (and four joints) as laid, shall not exceed by more than 1” the height of four
bricks as piled dry one upon the other.
5. Protection & Cutting : Brick work laid in cement shall be protected from rain by
suitable covering while it is green. Later on it shall be kept moist on all the faces for a
period of two weeks.
B) Cement Plaster
1. Plastering shall be done in mortar of various ingredients mixed in the specified
proportion in the drawing and shall be specified thickness as per drawings.
2. Preparation of surface for the durability of the plaster is of the utmost importance to
obtain satisfactory bond between the background and the plaster coat and also
ensure that the bond is maintained subsequently.
3. The brick wall should be watered for 24 hours before the plaster is applied.
4. After completion, plaster shall be kept wet for 10 days and shall be protected during
that period from extreme of temperature and weather.
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
40
5. All the structures above ground level shall be plastered with C.M 1:4 both inside and
outside of thickness 12 mm and 20 mm as required.
C) Cement Concrete/RCC:
The cement concrete /RCC shall be laid (two coats) as per para 10.4/10.7 of Punjab
PWD specifications.
1. Cement : Cement used shall be ordinary portland cement or rapid hardening
portland cement in accordance with specification no 3.14 for portland cement and
shall confirm to the requirement of Indian Standard 269
2. Water : Water used for all construction work shall be clean from objectionable
quantities of suspended material, vegetable or organic impurities, alkali salt and
other deleterious substance likely cause efforescene
3. a) Sand: Sand is important constituent of mortars and for satisfactory
performance, its requirement for cleanliness, freedom will depend upon the
purpose for which the mortar is used. The sand shall consist of natural sand,
crushed stone sand or crushed graded sand or composite of any of these and
should be hard, durable chemically inert, clean and shall not contain any
appreciable amount of clay balls or pellets
b) For concrete /RCC works only sand should be used.
c) For brick works and plastering purposes fine sand shall be used. Fine
sand shall be such that it passes through BS Sieve no 16 (IS Sieve no 15) . For all
concrete /RCC mixes 1:1.5:3 – (M-20), only crushed bajri ½” graded and for
cement concrete 1:8:16 in foundation brick ballast of 50 MM gauge shall be used.
d) Stacking : Sand shall be stacked on wooden or bricks platform and shall
be so stored as to be adequately protected from any admixture or clay, dust.
D) CEMENT, SAND, MORTARS:
Cement and sand shall be spread on a clean dry platform in layers one over the
other in the proportions specified, and mixed dry three times over. The sand
used should be perfectly dry. Water should be added to the dry mix, only when
the mortar is required for use.
E) STEEL:
Mild steel cold twisted / thermo-mechanical twisted bars as per Indian Standard
shall be used as per drawings.
F) CEMENT:
The arrangement for storage of cement shall be done by the contractor and
stored to the satisfaction of PEDA in weather tight building or sheds, the floors of
which shall be damp proof and at least 18” above the natural surface of the
ground. Cement shall not be stored in contact with walls and should be stacked
not more than 10 layers high to prevent bursting of bags in the bottom layers and
formation of clods.
G) Structural steel work : The structural steel shall conform to the relevant Indian
Standards IS:226 and IS:2062. Fabrication and erection shall be done as per
approved drawings and in accordance with IS 800. Providing shop primer coat
and finish coats in approved color for steel structure. Grouting of holding down
bolt pocket and below base plates where required.
H) Wood : Sawn timber for various building works specified variety of timber
specified in design and drawing shall be used in work. The well seasoned timber
shall be sawn in the direction of grains and the sawing shall trully straight and
square. Wood work shall conform to IS:883.
I) Stones : The stones shall be of specified variety and shall be obtained only from
an approved quarry. These shall be hard, round, durable, free from any defects.
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
41
The percentage of water absorption shall not be more than 5% when tested as
per IS method of testing for water absorption for natural building stones. The
minimum crushing strength shall be 200Kg/Sq.Cm. unless higher minimum
strength is specified in any particular call.
J) Aluminum work : The aluminum sections as per Indian standard shall be used as
per drawings for door, windows, ventilators of any specified glazing work.
K) Jet pump 1 HP (only for 50Kwp and and above capacity SPV Power Plants) :
1nos. 1 HP, BIS approved pump shall be installed at the site if required . Suitable
nos. of water outlets shall be provided through C class GI pipes for cleaning of
the modules. The GI pipes shall be spread along the module arrays for dedicated
water spray for module cleaning on the roof top.
L) Tests : All material to be used for construction and fabrication should be tested
before use. All laboratory/Field tests should be conducted as per relevant Indian
standards and PWD specifications by taking minimum required samples.
20. QUALITY AND ADAPTABILITY OF THE EQUIPMENT:
Bidders must verify the grid behavior, solar insolation levels, general site conditions on
their own before bidding, the bidder shall accordingly ensure that the equipment and the
design submitted, shall be able to perform as per guaranteed performance levels in the
available site conditions. The design of the plant and the equipment offered by the
bidders shall be evaluated for its quality and adaptability to the site conditions based on
the purchasers past experience, projects earlier executed by the bidders and from other
sources. Bidders must submit detailed technical operational parameters and latest plant
performance indicators and status complete with the clients address and contact no’s.
with regard to projects of similar nature already executed.
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
42
SECTION V
5. Bid Form, Price Schedules and other Formats
C:\Program Files (x86)\PDF Tools AG\3-Heights(TM) Document Converter Service\Temp\9c98d64941c9bcb4803081e88dfd1fc537e4b8dc7320a50c864011bd754f512d.doc
43
Annexure-I
LIST OF DOCUMENTS TO BE ENCLOSED WITH THE BID.
i) Part-I-Techno-commercial Bid
The Techno-commercial bid Part-I of tender shall be furnished complete in all respects
and documents mentioned therein including the scanned copies of the following documents
should be submitted.
a) Forwarding letter
b) Power of attorney for authorized signatory to sign the documents.
c) Manufacturer’s authorization letter
d) Non debarring/black listing certificate.
e) Copies of IEC certification of Modules,inverter,cables etc
f) Bid document cost 5 000/-.
g) Bid processing fee 2247/-.
h) Earnest money deposit of Rs. 200000/-
i) Valid test report
(i) Test report of SPV module
(ii) Test report of PCU
j) Photocopies of satisfactory performance reports of systems supplied to state nodal
agencies/ Govt. departments and other organizations/beneficiaries along with the
copies of purchase orders
k) Annual turnover along with CA certificate
l) Balance Sheet of last three years from 1.4.2015 onwards.
m) performance statement form
(other documents required as per bid document)
44
PERFORMA-I
Format for forwarding letter
(To be submitted /uploaded by bidders on the official letter head of the company)
No. Dated:-
To
The General Manger
Punjab Energy Development Agency
Plot No 1 &2, Sector 33D, Chandigarh
Bid Submitted for Category :......................
Subject:- Offer in response to Notice inviting Tender for Approval of rates for
Design, manufacture, supply, erection, testing and commissioning along with maintenance
for 5 years for different capacities Grid Interactive SPV power plants any where in Punjab
given in the bid document at PEDA Office Chandigarh.
Sir,
We here by submit our offer in compliance with terms and conditions of the e-
tender Notice PEDA/2019-20/05 dated as specified, the offer has been submitted
a) That we are submitting this offer under the above mentioned notice after having fully
read and understood the nature of the work and having carefully noted all the specifications,
terms and conditions laid down in the tender document and submitting the bid for
category..................
b) That we have never been debarred from executing similar type of work by any
central/state/public sector undertaking/department.
c) That we shall execute the work as per specifications, terms and conditions of the
tender document.
d) That our offer shall remain valid for placement of purchase order/ orders for 90 days
after the bid opening date.
e) We are not involved in any major litigation that may have an impact on the delivery
installation & commissioning of the project under this contract
f) I have read and accepted all the terms and conditions of DNIT.
Yours faithfully,
(………..)
Name, Seal &Signature
(Authorized Signatory)
45
PERFORMA 2. CONTRACT FORM
THIS AGREEMENT made the .......day of.................................., 20... Between ..........................
(Name of purchaser) of .............. (Country of Purchaser) (hereinafter "the Purchaser") of the one part
and ..................... (Name of Supplier) of ......................... (City and Country of Supplier) (hereinafter
called "the Supplier") of the other part :
WHEREAS the Purchaser invited bids for certain Goods and ancillary services viz.,
..................................... (Brief Description of Goods and Services) and has accepted a bid by the
Supplier for the supply of those goods and services in the sum of .............................. (Contract Price
in Words and Figures) (hereinafter called "the Contract Price").
NOW THIS AGREEMENT WITNESSETH AS FOLLOWS:
1. In this Agreement words and expressions shall have the same meanings as are respectively
assigned to them in the Conditions of Contract referred to.
2. The following documents shall be deemed to form and be read and construed as part of this
Agreement,viz.:
(a) the the Price Schedule submitted by the Bidder;
(b) the Schedule of Requirements;
(c) the Technical Specifications;
(f) the Purchaser's Notification of Award.
3. In consideration of the payments to be made by the Purchaser to the Supplier as hereinafter
mentioned, the Supplier hereby covenants with the Purchaser to provide the goods and
services and to remedy defects therein in conformity in all respects with the provisions of the
Contract.
4. The Purchaser hereby covenants to pay the Supplier in consideration of the provision of the
goods and services and the remedying of defects therein, the Contract Price or such other sum
as may become payable under the provisions of the Contract at the times and in the manner
prescribed by the Contract.
Brief particulars of the goods and services which shall be supplied/provided by the Supplier are
as under:
______________________________________________________________________________
SL. BRIEF QUANTITY TO UNIT Total DELIVERY TERMS
NO. DESCRIPTION- BE SUPPLIED PRICE Price
OF GOODS & ETC.) SERVICES
______________________________________________________________________
TOTAL VALUE:
DELIVERY SCHEDULE:
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in accordance
with their respective laws the day and year first above written.
Signed, Sealed and Delivered by the
said ..................................................... (For the Purchaser)
in the presence of:.......................................
Signed, Sealed and Delivered by the
said ..................................................... (For the Supplier)
in the presence of:.......................................
46
PERFORMA 3. PERFORMANCE BANK GURANTEE FORM
(To be stamped in accordance with Stamp Act if any, of the Country of the Issuing Bank)
To: (Name of Purchaser)
WHEREAS ................................................................... (Name of Supplier)
(hereinafter called "the Supplier") has undertaken , in pursuance of Contract No.................
dated,........... 20... to supply...................... .................................................(Description of
Goods and Services) (hereinafter called "the Contract").
AND WHEREAS it has been stipulated by you in the said Contract that the Supplier shall
furnish you with a Bank Guarantee by a recognized bank for the sum specified therein as
security for compliance with the Supplier's performance obligations in accordance with the
Contract.
AND WHEREAS we have agreed to give the Supplier a Guarantee:
THEREFORE WE hereby affirm that we are Guarantors and responsible to you, on behalf of
the Supplier, up to a total of ................................... ........................................ (Amount of the
Guarantee in Words and Figures) and we undertake to pay you, upon your first written
demand declaring the Supplier to be in default under the Contract and without cavil or
argument, any sum or sums within the limit of ................................ (Amount of Guarantee)
as aforesaid, without your needing to prove or to show grounds or reasons for your demand
or the sum specified therein.
This guarantee is valid until the ........day of...................20......
Signature and Seal of Guarantors
....................................................................
Date....................................................20.....
....................................................................
....................................................................
Address:.......................................................
....................................................................
....................................................................
47
PERFORMA 4. BANK GUARANTEE FOR ADVANCE PAYMENT
(To be stamped in accordance with Stamp Act if any, of the Country of the Issuing
Bank)
To: (name of Purchaser)
(address of Purchaser)
(name of Contract)
Gentlemen:
In accordance with the provisions of the Special Conditions of Contract, which amends
Clause 16 of the General Conditions of Contract to provide for advance payment,
_______________________ (name and address of Supplier) (hereinafter called "the
supplier") shall deposit with the Purchaser a bank guarantee to guarantee his proper and
faithful performance under the said Clause of the Contract in an amount of
(amount of guarantee*(in figures and words).
We, the (bank or financial institution), as instructed by
the Supplier, agree unconditionally and irrevocably to guarantee as primary obligator and not
as Surety merely, the payment to the Purchaser on his first demand without whatsoever right
of objection on our part and without his first claim to the Supplier, in the amount not
exceeding (amount of guarantee*in figures and words).
We further agree that no change or addition to or other modification of the terms of the
Contract to be performed thereunder or of any of the Contract documents which may be
made between the Purchaser and the Supplier, shall in any way release us from any liability
under this guarantee, and we hereby waive notice of any such change, addition or
modification.
This guarantee shall remain valid and in full effect from the date of the advance
payment received by the Supplier under the contract until _______________ (date).
Yours truly,
Signature and seal :
Name of bank/
financial institution :
Address :
Date :
____________________
* An amount is to be inserted by the bank or financial institution representing the amount of
the Advance Payment.
48
PERFORMA 5. MANUFACTURERS' AUTHORIZATION FORM
(ON THE LETTER HEAD)
No. dated
To
Dear Sir:
IFB No. ___________________
We who are established and reputable
manufacturers of ________________________ (name & descriptions of goods offered)
having factories at (address of factory) do hereby authorize M/s
___________________ (Name and address of Agent) to submit a bid, and sign the contract
with you for the goods manufactured by us against the above IFB.
We hereby extend our full guarantee and warranty as per Clause 15 of the
General Conditions of Contract for the goods and services offered for supply by the above
firm against this IFB.
Yours faithfully,
(Name)
(Name of manufacturers)
Note: This should be signed by a person competent and having the power of attorney to
legally bind the manufacturer. It should be included by the Bidder in its bid.
(The list of items for which this is required should be indicated by Purchaser).
49
PERFORMA 6- PERFORMANCE STATEMENT FORM
PROFORMA FOR PERFORMANCE STATEMENT (for a period of last three years)
Bid no. _____________________________ Date of opening
________________________ Time _____________ hours.
Name of the firm
_________________________________________________________________________
_________
Order
placed by
(full
address
of
purchase
r)
Order
no. and
date
Description
and
quantity of
ordered
equipment
Value
of order
Date of
completion of
delivery
Remarks
indicating
reasons for
late
delivery, if
any
Has the
equipment
been
satisfactorily
functioning?
(attach a
certificate
from the
purchaser/c
onsignee)
As per
contrac
t
Actual
1 2 3 4 5 6 7 8
Signature and seal of the bidder :
___________________________________________
___________________________________________
50
Performa 7. CERTIFICATE FOR ISSUE BY THE PURCHASER
AFTER SUCCESSFUL COMMISSIONING OF EQUIPMENT
[This is to be attached for supply, erection, supervision of erection contacts only]
No. Date :
M/s.
Sub: Certificate of commissioning of equipment
1. This is to certify that the equipment as detailed below has/have been received in
good condition along with all the standard and special accessories) and a set of
spares in accordance with the Contract/Specifications. The same has been
installed and commissioned.
(a) Contract No._________________ dated ______________________
(b) Description of the equipment _______________________________
(c) Plant Nos. _______________________________________________
(d) Quantity ________________________________________________
(e) Bill of Lading ____________________ dated ___________________
(for import contract)
(f) Name of the vessel/transporter _______________________________
(g) R/R No. _____________________ dated ______________________
(h) Name of the consignee _____________________________________
(i) Date of commissioning _____________________
2. Details of accessories/spares not yet supplied and recoveries to be made on
that account:
S.No. Description Amount to be recovered
3. The proving test has been done to our entire satisfaction and operators have
been trained to operate the plant.
4. The supplier has fulfilled his contractual obligations satisfactorily*
or
The supplier has failed to fulfil his contractual obligations with regard to the
51
following :
(a)
(b)
(c)
(d)
5. The amount of recovery on account of non-supply of accessories and spares is
given under Para No. 2.
6. The amount of recovery on account of failure of the supplier to meet his
contractual obligations is as indicated in endorsement of the letter.
Signature _______________________
Name _______________________
Designation with stamp __________________
52
Performa 8 : SERVICE SUPPORT DETAILS
NEAREST SERVICE CENTRE
Pac
k
no.
Destinati
on
Location
List of
models
& types
of Pcs.
Service
d in last
2 years
Pho
ne
no.
Tele
x/Fa
x no.
Status
of
office
workin
g days
and
hours
Numbe
r of
softwar
e
engine
ers
Numbe
r of
hardwa
re
engine
ers
Numb
er of
hardw
are
staff
Value
of Min.
stock
availabl
e at all
times
Signature and Seal of the
Manufacturer/Bidder
53
Performa 9. TECHNICAL DETAIL FORM
S.No. ITEM PARTICULARS
1. SOLAR PHOTOVOLTAIC MODULES
1.1 MANUFACTURER
1.2 SIZE
1.3 TESTING AND QUALIFYING
STANDARDS (Attach Certificates)
1.4 Pnom
1.5 P max
1.6 I mp
1.7 V mp
1.8 CELL EFFICIENCY
1.9 No. of cells in a module
1.10 Warranty offered (Attach Certificate)
2 INVERTERS
2.1 TYPE and Make
2.2 AC Output Voltage
2.3 DC input voltage range
2.4 DC operating voltage
2.5 Continuous rating
2.6 Grid Voltage Tracking range
2.7 Grid Frequency tracking range
2.8 Grid Phase imbalance
2.9 Efficiency
2.10 Operating temperature range
2.11 Power control
2.12 Protection features
2.13 Overload capacity
2.14 Total harmonic distortion
2.15 Islanding protection
2.16 Ingress protection
2.17 Hardware platform
2.18 DC input overload capacity
2.19 Electronic metering accuracy
2.20 Data logger accuracy
Signature of the Bidder ___________________________
Business Address ______________________________
54
.
Performa-11 TURNOVER RECORD FORM
To be certified by Chartered Accountant
Name of Company:-
Annual turnover data for past three years
Sr. No. Year Turnover (Rs. In Lacs) Profit Loss
1 2 3 4 5
1. 2015-16
2. 2016-17
3. 2017-18
4 2018-19 `
Signature with seal of the company
Signature with seal of the Chartered Accountant
55
Performa 12
FORMAT FOR BANK GUARANTEE AGAINST ANNUAL MAINTENANCE
(To be stamped in accordance with Stamp Act if any, of the Country of the Issuing
Bank)
Bank Guarantee No. : ……………………………………. Date:…………………………..
To …………………………………………. (Name of the Purchaser)
Whereas ………………………………….. (Name of the Purchaser) hereinafter called “The
supplier” has undertaken, in pursuance of contract no……………………….. dated ………
20…….. to supply ……………………………………………………. (Description of Goods and
Services) hereinafter called “the contract”.
AND WHEREAS it has been stipulated by you in the said contract that the supplier shall
furnish you with a Bank Guarantee by a recognized Bank for the sum specified therein as
security for compliance with the Supplier’s performance obligations under the contract for
Annual Maintenance and Repairs of the entire system including cost of spares after
warranty period of next five years.
AND WHEREAS we have agreed to give the Supplier a Guarantee
THEREFORE WE hereby affirm that we are Guarantors and responsible to you on behalf of
the Supplier, up to a total of Rs………………………. (Amount of guarantee in words and
figures) being 10 % of the total cost of equipment and we undertake to pay you, upon your
first written demand declaring the Supplier to be in default under the contract and without
cavil or argument, any sum or sums within the limit of Rs…………………………….. (Amount
of guarantee) as aforesaid, without your needing to prove or to show grounds or reasons for
your demand or the sum specified therein.
This guarantee is valid until………………… day of…………….20………
Signature and Seal of Guarantors
……………………….
56
……………………….
Date:…………20…...
Note :
1. SUPPLIER SHOULD ENSURE THAT SEAL AND CODE No. OF THE SIGNATORY
IS PUT BY THE BANKERS, BEFORE SUBMISSION OF THE BANK
GUARANTEES.
57
SECTION VI
6. SCOPE OF MAINTENANCE OF POWER PLANT
58
Scope of maintenance of SPV power plant for a period of 5 years from date of
commissioning
The complete plant after commissioning will be handed over to user agency and
Maintenance work will be seen by the user agency/PEDA as per terms and condition of the
tender document.
Regular maintenance of the SPV Power Plant for a period of 5 years after commissioning
along with supply of Equipment as and when necessary and submission of daily
performance data of the power plant shall come, under the maintenance contract. Complete
maintenance of the plant has to be carried out by the successful bidding company and can
not be sublet to any third party. PEDA shall not bear any extra cost toward the
replacement/repair of faulty equipments during 5 years maintenance period and supplier will
bear the cost.
The maintenance schedule of the SPV power plant during the 5 years contract period shall
be as detailed below :
1. 5 years maintenance period shall begin on the date of actual commissioning of the
power plant. The requisite number of qualified and trained personnel are required to be
deputed round the clock from that very day.
2. The security of the power plant will rest with the suppliers till such time maintenance
of the power plant is not handed over to the purchaser.
3. The deputed personnel shall be qualified and well trained so that they can handle any
type of operation hazard quickly and timely.
4. The deputed personnel shall have to keep daily log sheet for the power plant as per
format to be supplied after commissioning of the power plant.
5. The deputed personnel shall be in a position to check and test all the equipment
regularly, so that, preventive actions, if any, could be taken well in advance to save any
equipment from damage. Any abnormal behavior of any equipment shall be brought to
the notice of PEDA immediately for appropriate action.
6. The deputed personnel shall keep clean the power plant in all time.
7. Normal and preventive maintenance of the power plant such as cleaning of module
surface, tightening of all electrical connections, changing of tilt angle of module
mounting structure, cleaning & greasing of terminals etc.
8. During maintenance period of five years of the power plant, if there is any loss or
damage of any component of the power plant due to miss management/miss handling
or due to any other reasons, what-so-ever, the supplier shall be responsible for
immediate replacement/rectification. The damaged component may be repaired, if it is
understood after examination that after repairing performance of the component shall
not be degraded, otherwise the defective component shall have to be replaced by new
one without any extra cost.
59
9. List of Spare parts & measuring instruments which are to be supplied along with the
systems are given in Annexure 1. These spares are the property of the purchaser and
the contractor will use these spares sparingly with express permission of the purchaser
in case of emergency breakdowns, however, the contractor will have to refill the used
spares within one month of draw down. All the spares inventory of the purchaser has to
be fully refilled with new and unused spares at the time of handing over of the plant
after completion of the 5 years of O&M of the plant by the contractor in case of non-
compliance, the purchaser will refill these spares with new ones at the cost of the
contractor.
10. Maintenance Instructions :
10.1 The successful bidder shall furnish 2 sets of the approved manuals of instructions at
the time of inspection and taking over of the equipment. These manuals shall properly bound
in book form and contain all information, description of equipment, diagram etc., necessary
to enable the customer to operate and maintain the whole scheme.
10.2 Proper maintenance of the plant shall be carried out by the contractor during the
maintenance period of 60 months with 6 monthly/annual review checkup of plant and
equipment in detail with purchaser.
10.3 Properly qualified and trained personnel well versed in O& M of SPV plants and
knowledge of computers with approval from purchaser shall be deployed at site for operation
& maintenance.
10.4 Proper repainting, re coating of exposed surfaces to prevent rusting & replacement of
worn out parts shall be carried out along with the maintenance of the Inverter.
Plant personnel shall be deputed on such basis so that a qualified person with a
minimum qualification of Diploma in Electrical Engineering should be available at
site always during the operation & maintenance period.
Supplier shall depute on engineer of their company for the operation and
maintenance of the plant who shall be fully responsible for the complete O&M
and optimum operation of the plant. The name and contact nos. of this engineer
shall be notified to the purchaser, for the purpose of contact, responsibility and
correspondence with regard to all trouble shooting.
Replacement & repair of damaged parts shall be carried out immediately during
the O&M period so as to ensure at least 95% uptime.
Plant operation reports in a format prescribed by the purchaser shall be furnished
by the supplier on a weekly and monthly basis.
Plant shall be operated as per the standard IER practices to ensure proper safety
measures.
Proper data logs and records shall be maintained at the plant office with regard to
generation, efficiency, solar radiation, grid conditions and power fed to the grid
which shall be supplied on demand to the purchaser.
The supplier shall ensure replacement of worn out parts and components during
the operation & maintenance period for which purpose the supplier shall carry
and maintain minimum inventory levels of spares at the plant and at its works.
In case of delay in repair & maintenance and non observance of purchasers O&M
schedules, the purchaser shall have the right to impose any penalties including
forfeiture of performance security.
60
Round the clock maintenance (routine, preventive, breakdown and capital
maintenance) of complete plant and equipments including SPV Array,
INVERTER, data logging system shall be carried out by the supplier in
accordance with manufacturer’s instructions, manufacturers procedures, relevant
safety codes, Indian Electricity Act, Indian Electricity Rules, purchaser’s
instructions, prudent utility practices etc.
10.5 Routine, Preventive, Breakdown & Capital Maintenance:
Routine and preventive maintenance shall include such checks and maintenance
activities round the clock on hourly, shift wise, daily, weekly, fortnightly, monthly,
quarterly, half yearly, and yearly basis which are required to be carried out on all the
components of the power plant to minimize breakdowns and to ensure smooth and
trouble free running of the power plant. The supplier shall be responsible to carry out
routine and preventive maintenance and replacement of each and every component /
equipment of the power plant and he shall provide all labour, material, consumables etc.
for routine and preventive maintenance at his own cost.
Breakdown maintenance shall mean the maintenance activity including repairs and
replacement of any component or equipment of the power plant which is not covered by
routine and preventive maintenance and which is required to be carried out as a result
of sudden failure/breakdown of that particular component or equipment while the plant is
running. The supplier shall be responsible to carry out breakdown maintenance of each
and every component of the power plant and he shall provide the required manpower,
materials, consumables, components or equipment etc. for breakdown maintenance at
his own cost irrespective of the reasons of the breakdown/failure.
Capital maintenance shall mean the major overhaul of any component or equipment of
the power plant which is not covered by routine, preventive and breakdown
maintenance which may become necessary on account of excessive wear & tear, aging,
which needs repair/replacement. The capital maintenance of power plant and all civil
structures shall normally be planned to be carried out on an annual basis. For this
purpose a joint inspection by the supplier and purchaser shall be carried out of all the
major components of the power plant, about two months in advance of the annual
maintenance period, in order to ascertain as to which components of the power plant
require capital maintenance. In this regard the decision of the purchaser will be final and
binding. However, if the condition of any plant and component warrants its capital
maintenance at any other time, a joint inspection of the purchaser and supplier shall be
carried out immediately on occurrence of such situation and capital maintenance shall be
carried out by arranging the shutdown of the plant/part of the plant, if required, in
consultation with concerned authorities. The decision of the purchaser shall be final and
binding.
61
Annexure II
List of Min. Spare Parts for each power plant
Sno Item Description Quantity ( nos)
1 SPV Module 0.5% of total numbers of modules
2 Power Conditioning Systems Necessary spares for 5 years of
operation with min. 2 sets of spares
to be kept at plant site. List must be
got approved from the
purchaser/implementing agency.
3 Miscellaneous (cable, fuses/HRC
fuses, screws, soldering material,
wall grips, lugs etc please specify)
Required 5 years of operation
Tools and Measuring instruments
Sno Item Description Quantity ( nos)
1 Digital Multimeter and clamp meter (Fluke /
Motvane)
1 no. each
2 Screw Driver set (Taparia / Eastman) 2 sets
3 Spanner set (Taparia / Eastman) 2 sets
4 Soldering Iron (Philips) 2
Note: Bidders must get the list of spares being supplied approved from the
purchaser before supply.