8
This brochure does not contain all informations and any warranty or guarantee of any kind. Also, all informations herein is subject to change without notice. Pumps for Power Plant B 9004 E E Springs of Living Water ISO 9001 DET NORSKE VERITAS MANAGEMENT SYSTEM CERTIFICATE ISO14001 DET NORSKE VERITAS MANAGEMENT SYSTEM CERTIFICATE OHSAS 18001 HEAD OFFICE (04144) 6F, HYOSUNG Bldg., 119 Mapo-daero, Mapo-gu, Seoul, Korea TEL : 82-2-707-7000 CHANGWON PLANT / R&D CENTER (51559) 303 Gongdan-ro, Seongsan-gu, Changwon-si, Gyeongnam, Korea TEL : 82-55-279-7861 GIMHAE PLANT (50969) 158-20 Golden root-ro, Juchon-myeon, Gimhae-si, Gyeongnam, Korea TEL : 82-55-340-4407 www.hsgoodsprings.com DIRECT CONTACT Pumps for Petrochemical, Refinery Plant TEL : +82-2-3279-8221 E-mail : [email protected] Pumps for Power Generation, Desalination Plant TEL : +82-2-3279-8280 E-mail : [email protected]

Pumps for Power Plant

  • Upload
    vunhi

  • View
    254

  • Download
    5

Embed Size (px)

Citation preview

Page 1: Pumps for Power Plant

This brochure does not contain all informations and any warranty or guarantee of any kind.Also, all informations herein is subject to change without notice.

Pumps forPower Plant

B 9004 E E

Springs of Living Water

ISO 9001

DET NORSKE VERITAS

MANAGEMENT SYSTEM

CERTIFICATE

ISO14001

DET NORSKE VERITAS

MANAGEMENT SYSTEM

CERTIFICATE

OHSAS 18001

HEAD OFFICE (04144) 6F, HYOSUNG Bldg., 119 Mapo-daero, Mapo-gu, Seoul, Korea TEL : 82-2-707-7000CHANGWON PLANT / R&D CENTER (51559) 303 Gongdan-ro, Seongsan-gu, Changwon-si, Gyeongnam, Korea TEL : 82-55-279-7861GIMHAE PLANT (50969) 158-20 Golden root-ro, Juchon-myeon, Gimhae-si, Gyeongnam, Korea TEL : 82-55-340-4407

www.hsgoodsprings.com

DIRECT CONTACTPumps for Petrochemical, Refinery Plant TEL : +82-2-3279-8221 E-mail : [email protected]

Pumps for Power Generation, Desalination Plant TEL : +82-2-3279-8280 E-mail : [email protected]

Page 2: Pumps for Power Plant

About HYOSUNGHyosung Power & Industrial Systems PG is a division under Hyosung which consists of

seven performance groups(PGs). In addition to establishing itself as a world-class

manufacturer of electrical equipments, green technology and industrial machineries,

Hyosung is also the largest producer of tire cords and spandex in the global market and

the second largest supplier of ATMs in the USA.

01 Our BusinessBrief Introduction of Hyosung GoodspringsHyosung Goodsprings (HGS) has contributed to the development and economic growth of Korean pumpsand water industries, based on its outstanding technology through continued research & developmentactivities. Hyosung Goodsprings is the largest Korean company specialized in manufacturing pumps andsupplying facilities for water treatments including desalination plants.

By acquiring the KEPIC certificate, which enables to produce safety related pumps for nuclear power plants,Hyosung Goodsprings is currently engaged in conducting a number of national policy tasks, wellrecognized for our superior technologies, which includes nuclear power pumps and the localization ofequipment for desalination plants.

Hyosung Goodsprings is presently producing high quality products for various usages, from pumps forpower plants to those for petrochemicals, building/housing, industrial, desalination plant, andmarine/offshore. Hyosung Goodsprings has outstanding performances in the field of desalination plantsector.

Hyosung Goodsprings also known as an import-substituting company thanks to its continuousdevelopment of new technology, is now accelerating to open up local markets as well as foreign markets.Hyosung Goodsprings provides the best solutions that customers can depend and fulfill their needs in theentire process from the receipt of orders to planning, manufacturing, and after-sales services which is allenabled by R&D activities and quality management.

Hyosung Goodsprings will grow up to become a company specialized in producing pumps and waterprocessing and rank along with the world’s top corporations, through continuous innovation and customersatisfaction efforts.

Meaning of ‘Goodsprings’Our corporate name purports to represent “Good & Great Spring”, which symbolizes the origin of all life,wisdom and abundance. It also signifies Hyosung Goodsprings, core value of “positive contribution towardabundance and happiness of humanity” by providing abundant water, the origin of life.

We pledge with our valued customers that we will provide better and more innovative products and services,as well as to leap together in order to become a world class company with global competitiveness.

CONTENTS3 Our Business 4 Pumps for Power Plant 6 Thermal/Combined Cycle Power Plant

8 Nuclear Power Plant 10 R&D 12 Quality Assurance 14 Global Network

Pumps for Power Plant

Page 3: Pumps for Power Plant

02 Pumps for Power Plant- Thermal /Combined Cycle Power Plant- Nuclear Power Plant

This is Youngheung power plant.

Page 4: Pumps for Power Plant

6 I 7 Pumps for Power Plant

Boiler Feedwater PumpFeatureTechnology-intensive pump which enables ultra high-pressure (up to 350bar) and high-temperature liquids (up to 200°C). Applicable for all kinds of power plants.

Capacity As required for any service

Circulating Water PumpFeatureLarge-capacity vertical type pump to which pull-out typestructure can be applied. Duplex stainless steel applicable.

CapacityAs required for any service

Condensate Extraction PumpFeatureVertical barrel casing structure enables to apply in the severe suction condition.

Capacity Up To 5,500m3/h (24,200GPM)

Major Referencesfor Thermal Power Plant

Boiler Feed Water Pump

Delivery Project Site Enduser EPC Item & Specification

~2016 Thermogas Machala CCPP Ecuador Thermogas Machala JSC Machine 6sets (128m3/h, 1,297m, 650kW)

2015 Rabigh II IPP Saudi Arabia SEC SAMSUNG C&T 9sets (380m3/h, 1,649m, 2,050kW)

2015 PP14 Saudi Arabia SEC WorleyParsons(SEC) 24sets (360m3/h, 1,724m, 2,200kW)

2015 PP 13 Saudi Arabia SEC WorleyParsons(SEC) 24sets (360m3/h, 1,724m, 2,200kW)

2015 Bandirma II CCPP Turkey Enerjisa SIEMENS 2sets (553m3/h, 2,156m, 3,700kW)

2015 Khabat TPP Unit # 1&2 Iraq GAMA Power systems POSCO E&C 6sets (334m3/h, 2,250m, 2,600kW)

2014 Prai CCGT PJT Malaysia TNB SAMSUNG C&T 6sets (365m3/h, 2,155m, 2,200kW)

2014 Azito Phase 3 CCPP Cote d'lvoire Azito HYUNDAI E&C 3sets (285m3/h, 1,135m , 1,250kW)

2014 Ain Arnat CCPP Algeria SPE HYUNDAI E&C 6sets (438m3/h, 1,460m, 2,000kW)

2012 Tufanbeyli TPP Turkey Enerjisa KEPCO E&C 9sets (308m3/h, 2,260m, 2,500kW)

2012 UCH II Expansion CCPP Pakistan URS Infrastructured HYUNDAI Eng. 3sets (300m3/h, 1,350m, 1,400kW)& Environment UK Limited

2012 SHUWEIHAT S3 IPP UAE SAPCO DAEWOO E&C 6sets (811m3/h, 1,052m, 2,800kW)

2012 NORTE II CCGT POWER PJT Mexico GE SAMSUNG Eng. 4sets (290m3/h, 1,630m, 1,700kW)

2012 Sohar II & Barka III CCPP Oman Al Batinah Power Company GS E&C 6sets (623.6m3/h, 1,588m, 2,800kW)

2011 Marafiq 5&6 CCPP Saudi Arabia Marafiq HANWHA E&C 1sets (584m3/h, 2,200m, 5,000kW)

2010 Shuweihat S2 UAE Ruwais Power Company SAMSUNG C&T 6sets (609m3/h, 1,200m, 2,600kW)

2010 Nhon Trach 2 CCPP Vietnam Petrovietnam SIEMENS 3sets (423.2m3/h, 1,444.5m, 2,200kW)

2009 Severn CCPP UK Public Utilities Board SIEMENS 4sets (278.6m3/h, 1,542.3m, 2,700kW)

2009 Seraya CCPP Singapore Public Utilities Board SIEMENS 4sets (565.2m3/h, 1,610.5m, 3,100kW)

2009 Yoengwol CCPP Korea KOSPO DOOSAN 6sets (184.4m3/h, 1,702m, 1,200kW)

2008 Jebel Ali M project UAE DEWA DOOSAN 4sets (525m3/h, 1,356m, 2,650kW)

2008 Ambatovy CCPP Madagascar Keangnam KEONGNAM 9sets (250m3/h, 1,190m, 1,180kW)

2008 Qatalum CCPP Qatar Qatalum DOOSAN 12sets (505.4m3/h, 1,468m)

2008 Gunsan CCPP Korea KOWEPO S&TC 6sets (184.4m3/h, 1,702m, 1,200kW)

Condensate Extraction Pump

Delivery Project Site Enduser EPC Item & Specification

2015 Rabigh II IPP Saudi Arabia SEC SAMSUNG C&T 6sets (1,080m3/h, 235m, 980kW)

2015 Panda Stonewall USA Panda Energy SIEMENS 3sets (456m3/h, 269m, 480kW)

2015 Khabat TPP Unit # 1&2 Iraq GAMA Power systems POSCO E&C 6sets (470m3/h, 260m, 490kW)

2015 Fast Track 3A PJT Malaysia TNB DAELIM IND. 3sets (1,080m3/h, 130m, 490kW)

2014 Prai CCGT PJT Malaysia TNB SAMSUNG C&T 6sets (370m3/h, 230m, 315kW)

2014 Bandirma II CCPP Turkey Enerjisa SIEMENS 2sets (539m3/h, 272m, 600kW)

2014 Azito Phase 3 CCPP Cote d'lvoire Azito HYUNDAI E&C 2sets (780m3/h, 130m, 400kW)

2014 Eletro Amazonas Maua III Brazil Eletrobras SIEMENS 3sets (390m3/h, 258m, 400kW)

2014 ENARSA Brigadier Lopez Argentina Enarsa SIEMENS 2sets (577m3/h, 243m, 560kW)

2014 ENARSA Ensenada de Barragan Argentina Enarsa SIEMENS 3sets (577m3/h, 243m, 560kW)

2014 Panda Energy Temple II CCPP USA Panda Energy SIEMENS 3sets (456m3/h, 269m, 480kW)

2013 Panda Energy Temple I CCPP USA Panda Energy SIEMENS 3sets (456m3/h, 269m, 480kW)

2013 Panda Sherman I USA Panda Energy SIEMENS 3sets (456m3/h, 269m, 480kW)

2013 SHOAIBA II CCPP Saudi Arabia SEC DAELIM IND. 6sets (412m3/h, 125m, 210kW)

2013 Qurayyah IPP Saudi Arabia SEC SAMSUNG C&T 12sets (1,010m3/h, 330.4m, 1,290kW)

2012 UCH II Expansion CCPP PakistanURS Infrastructured

HYUNDAI Eng. 2sets (655m3/h, 155m, 400kW)& Environment UK Limited

2012 SHUWEIHAT S3 IPP UAE SAPCO DAEWOO E&C 6sets (582m3/h, 275m, 720kW)

2012 New HariPure CCPP Bangladesh EGCB HYUNDAI E&C 2sets (620m3/h, 220m, 550kW)

2011 Sohar II & Barka III CCPP Oman Al Batinah Power Company GS E&C 6sets (618m3/h, 248.5m, 630kW)

2009 Shuweihat S2 UAE Ruwais Power Company SAMSUNG C&T 6sets (498m3/h, 208m, 405kW)

2009 Severn CCPP UK Welsh Power SIEMENS 4sets (596.8m3/h, 244.8m, 600kW)

2009 Seraya CCPP Singapore Public Utilities Board SIEMENS 4sets (495.9m3/h, 253m, 581kW)

Circulating Water Pump

Delivery Project Site Enduser EPC Item & Specification

2014 Prai CCGT PJT Malaysia TNB SAMSUNG C&T 3sets (46,050m3/h, 16m, 2,700kW)

2014 PACO Power Plant Panama Minera Panama S.A SK E&C 4sets (13,200m3/h, 35m, 1,770kW)

2013 Takoradi T2 CCPP Ghana TICO KEPCO E&C 2sets (26,000m3/h, 22.3m, 2,100kW)

2013 Qurayyah IPP Saudi Arabia SEC SAMSUNG C&T 12sets (29,600m3/h, 16.63m, 2,250kW)

2013 SHOAIBA II CCPP Saudi Arabia SEC DAELIM IND. 4sets (28,640m3/h, 16.08m, 2,200kW)

2012 HGP #5~8 CCPP Korea Hyundai Green Power HYUNDAI E&C 4sets (19,150m3/h, 22.5m, 1,700kW)

2012 Shuweihat S3 IPP UAE SAPCO DAEWOO E&C 4sets (42,200m3/h, 22.4m, 3,400kW)

2012 Shuweihat S3 IPP UAE SAPCO DAEWOO E&C 2sets (34,500m3/h, 15.6m, 2,000kW)

2011 Sohar II IPP Oman Al Batinah Power Company GS E&C 4sets (14,500m3/h, 23m, 1,250kW)

2011 Barka III IPP Oman Al Batinah Power Company GS E&C 3sets (21,700m3/h, 23m, 1,850kW)

2010 Shuweihat S2 UAE Ruwais Power Company DOOSAN 4sets (27,700m3/h, 27m, 2,600kW)

2010 Bekirli Turkey ICDAS PROKON 4sets (31,500m3/h, 30m, 3,500kW)

2009 Ras Laffan C IWPP Qatar RGPC HYUNDAI E&C 9sets (23,600m3/h, 28m, 2,400kW)

2009 Aravali STPP India NTPC NTPC 2sets (30,000m3/h, 27m, 2,800kW)

2009 Farakka STPP India NTPC NTPC 5sets (44,500m3/h, 7m, 1,100kW)

2004~2009 Boryeong TPP Unit 7,8 Korea KOMIPO KOMIPO 18sets (34,820m3/h, 14.5m, 2,100kW)

2008 Qatalum CCPP Qatar Qatalum DOOSAN 6sets (23,300m3/h, 26m)

Thermal/Combined Cycle Power Plant

CWP Circulating Water Pump

SLP Seawater Lift Pump

BFP Boiler Feedwater Pump

BFBP Boiler Feedwater Booster Pump

CEP Condensate Extraction Pump

CBP Condensate Booster Pump

Pumps for Power Plant

NOTE : For more detailed information on these products, please contact our sales representative.

Page 5: Pumps for Power Plant

8 I 9 Pumps for Power Plant

Safety Injection Pump &Containment Spray PumpFeatureASME Sec, Division - class – component Thermal transient qualification – actual test Dynamic qualification against seismic load Environment qualification against hash zone Fatigue analysis for equipment design life 40 years guarantee

Capacity As required for any service

Circulating Water PumpFeatureLarge-capacity vertical type pump to which pull-out type structure can be applied duplex stainless steel applicable.

CapacityAs required for any service

Condensate Pump & FeedwaterBooster PumpFeatureTechnology – intensive structure enables to apply in severe suction condition

Capacity As required for any service

Nuclear Power Plant

Pumps for Power Plant

CEP Condensate Extraction Pump

CCP Centrifugal Charging Pump

HPSIP High Pressure Safety Injection Pump

LPSIP Low Pressure Safety Injection Pump

CSP Containment Spray Pump

CVCSP Chemical Volume Control System Pump

ESWP Essential Service Water Pump

SRCP Safety Related Centrifugal Pump

Note : For more detailed information on these products, please contact our sales representative.

Major References for Nuclear Power Plant

Korea

Delivery Project Service Quantity Item & Specification

Boric Acid Makeup Pump 4 4x3 HCN-4/5

Shutdown Cooling Pump 4 12x16x24 VCN

Safety Injection Pump 8 6x11-7stg.-HDBN

Containment Spray Pump 4 12x16x24 VCN

Deisel Fuel Oil Transfer Pump 8 3x2HCN-8.5

Circulating Water Pump 12 VMF2100-1840

Condensate Pump 6 VCP600-575-4Stg.

Feedwater Booster Pump 6 16x24x34L DSJH

Main Feedwater Pump 6 14x14x17B DVSR

Start-Up Feedwater Pump 2 250x200SBRD4M

Boric Acid Makeup Pump 4 4x3 HCN-1

Shutdown Cooling Pump 4 12x16x24 VCN

Safety Injection Pump 4 6x11-7stg.-HDN

Containment Spray Pump 4 12x16x24 VCN

Circulating Water Pump 12 VMF2100-1830

Low Pressure Safety Injection Pump 4 8x14x24 DFSS

High Pressure Safety Injection Pump 4 6x10-1/4-9stg.-HDB

Containment Spray Pump 2 8x14x24 VCN

Boric Acid Makeup Pump 4 3x1 1/2 HCN-1

Deisel Fuel Oil Transfer Pump 8 2 1/2x2 HCN-8 1/2

Containment Cooling Water Pump 8 24x24 HDN-24

Circulating Water Pump 8 VMF1950-1690

Condensate Pump 6 30KxG4VMT

Feedwater Booster Pump 6 16x20x34 LDSJH

Low Pressure Safety Injection Pump 4 8x14x24 DFSS

High Pressure Safety Injection Pump 4 6x10-1/4-9stg.-HDB

Containment Spray Pump 2 8x14x24 VCN

Boric Acid Makeup Pump 4 3x1 1/2 HCN-1

Deisel Fuel Oil Transfer Pump 8 2 1/2x2 HCN-8 1/2

Condensate Pump 6 30KKxH4 VMT

Feedwater Booster Pump 6 10x20x34 LDSJH

Low Pressure Safety Injection Pump 4 8x14x24 DFSS

High Pressure Safety Injection Pump 4 6x10-1/4-9stg.-HDB

Boric Acid Makeup Pump 4 80x40 UCN-25

Holdup Pump 4 80x40 UCN-20

Recent Records

Delivery Project Service Quantity Item & Specification

Safety Injection Pump 16 SBVN150/9

Shutdown Cooling Pump 8 SVSN300-765

Containment Spray Pump 8 12x16x29VCN

Main Feedwater Pump, Turbine Driven 12 FKIH42

Circulation Water Pump 24 VMF2400-2120

Diesel Fuel Oil Transfer Pump 16 HCN 3x2-1

CL Seawater Supply Pump 4 VTM100/3

Circulating Water Screen Wash Pump 6 VTM125/2

2013 ~

2015

Shin-Ul-Chin#1, #2

(1,400MW)

2009~

2011

Shin-Ko-Ri#3, #4

(1,400MW)

2008~

2010

Shin-Wol-Sung#1, #2

(1,000MW)

2008~

2010

Shin-Ko-Ri#1, #2

(1,000MW)

2001~

2002

Ul-Chin NPP#5, #6

(1,000MW)

2013~

2017

UAE/Brakah NPP #1~4

Page 6: Pumps for Power Plant

Hydraulic Designs•Various Hydro Data •Basic Shape Design using specially designed programs •Optimal shape design through Experiments

•More hydro design using Impeller 3D design programs •3D Flow simulation performance prediction

03 R&DInspiring innovation, creation and expertiseHyosung R&D Center identifies innovation, creation, and expertise as core values, and concentrates on world class R&D activities in the 21stcentury with a philosophy aspiring after customer satisfaction, quality priority, and performance orientation, Hyosung pursues to be the world’sbest company in the field of Industrial Pump and Desalination, Oil & Gas, and Power Plant (including nuclear).

Impeller design-only program Optimal shape design of Experiments with

Impeller 3D design program

Streamline Vapour Volume Fraction

Structural Integrity Evaluation•Stress analysis, strength evaluation support unit •Dynamic Analysis of Rotor-only program

•Strength test by a fluid flow using FSI (Fluid Structure Interaction) •Structural Vibration, Thermal Stress Analysis

Structural Strength Analysis Shaft Analysis Tool Model Assembly Analysis

Structural Vibration, Thermal Stress Analysis

Sump Model TestDesign of Anti-vortex Device (AVD)To ensure pump safety and customer satisfactions

Pressure distribution

AVD for submerged vortex and removal of vortex

Submergedvortex cavitation

Air-entrance vortex

10 I 11 Pumps for Power Plant

Pump Test CenterHYOSUNG GOODSPRINGS Pump Test Center, one of the largest facilities in the world

Max. Volt. 13,200 V

Max. Power 14,000 kW

Max. Flow 110,000 m3/h

Test Stand 7 ea.

Max. Flow 6,000 m3/h

Max. Press. 400 barG

Max. Temp. 200℃ below

Test Stand 4 ea.

Max. Flow 5,000 m3/h

Test Stand 5 ea.

Feature

Electricity Test Capacity

Large Size Pump Test Stand

High Pressure PumpTest Stand

Petrochemical Pump Test Stand

Capability

Page 7: Pumps for Power Plant

04 Quality AssuranceHyosung strives for excellence. We believe excellence can only be achieved through absolute qualities and values forcustomers. In order to create quality and fine products, we believe that all of the actions of every single employee mustbe focused on the highest level of quality. In order to achieve those levels, we have implemented an assurance policyand programs that make our philosophy into a reality.

Our Quality Assurance Policy is based on the global standard and meets the demands of ISO 9001. As a globally activecompany, we are committed to comprehensive and quality management through three quality systems: qualitymanagement system, customer-focused management system, and concentration on core competencies.The comprehensive quality management system ensures that we completely comply with all compliances and applicablelegislation, codes, and standards along with implementing efficient operation of our management resources in order toeliminate unnecessary wastes.

Our customer-focused management system clarifies and simplifies our first priority which is customer satisfaction. All ofour work is aimed to exceed customer needs and provide exceptional value through quality standards, flexibility, andinnovation.

Finally, we concentrate on our core competencies for strict quality control and continual improvement which providesquality products and cost-saving to our clients via advancement in technical capacity and technological innovation.We implement our policy via the Quality Management Team which manages research laboratories, including theMeasurement Standard Laboratory, the Chemical Analysis Laboratory and the Material Analysis Laboratory to maintain astrict control over quality.

12 I 13 Pumps for Power Plant

ISO 9001 CE MarkKEPICOHSAS 18001ISO 14001

Product Development History

Year Milestones

1962. May ·Established Hanyoung Industrial Corporation

1975. Oct ·Merged into Hyosung Group

1977. Sep ·Completed the Changwon Plant with Korea’s largest test facility

1989. Oct ·Established Hyosung EBARA Co., Ltd.

1990. Oct ·Newly operated pump plant

1995. Jan ·Hyosung Heavy Industries Co., Ltd. Acquired and merged the Pump Business Division

1996. Sep ·Completed Korea’s largest test facility for testing BOILER FEED PUMP for 800MWThermal Power Station and REACTOR FEED PUMP for 1350MW Nuclear Power Station

1997. Aug ·Obtained “Nuclear Reactor Facility Production License” (Pumps & Valves)

1999. Aug ·Supplied pumps for Yeongkwang Nuclear Power (1000MW,NO.5&6) CWP (Korea’s largest capacity)

2003. Nov ·Won a Korea Energy Efficient Product Excellence Award(presented by Korea Management Association)

2006. Apr ·Obtained high-efficiency machinery materials certifications enforced by the Korea Energy Management Corporation

2009. Jul ·Completion ceremony held for the ‘Containerized RO’ project at Incheon Mooui Island /Obtained nuclear power-related ASME ‘N’, ‘NPT’ certifications

2010. Sep ·Hyosung / Ebara Joint Venture Terminated and Changed name to "HYOSUNG GOODSPRINGS"

Dec ·Supplied API610 pump 32 sets (OH2) to Takreer For “Ruwais Refinery Expansion #2 , UAE”

2011. Jan ·Supplied API610 pump 11 sets (BB2, BB3) to GASCO For “SHAH GAS DEVELOPMENT #4, UAE”

Feb ·Defining Corporate Identity & Brand Identity – “Pumps & Water”

Apr ·Supplied API610 pump 32 sets (BB1, OH2) to ARAMCO For “KAPSARC, Saudi Arabia”

Jun ·Awarded for 104 sets of Q class and Non-Q class related pumps For “BARAKAH / UAE Nuclear power plant”

Nov ·Won the Minister’s award from Ministry of Knowledge Economy by developing Safety InjectionPump for nuclear power plant for the first time in Korea

2013. Feb ·Developed the can type diffuser for the first time in Korea

Mar ·Supplied CWP for Shin-Boryeong Units 1 & 2, the largest coal-fired power plant in Korea

Sep ·Supplied BFP, CEP for Taean thermal power plant Units 9 & 10

Oct ·Successful localization of the centrifugal charging pump for the first time in Korea

Nov ·Received order for Bismayah New City Project to NIC, Republic of IRAQ

2014. Apr ·Completion of the World’s Largest Pump Test Center and Opening Ceremony held inHYOSUNG GOODSPRINGS Changwon Plant

2015. Jun ·The opening of HYOSUNG Abu Dhabi branch office

2015. Nov ·Technical Seminar and Improvement Completion Ceremony of BFP for 1000MW

Page 8: Pumps for Power Plant

14 I 15 Pumps for Power Plant

Global Network | Aggressive Expansion of Global Customer Support Structure Major Reference | Hyosung’s Worldwide References

Global NetworkReady to serve our global customer anytime, anywhere

Hyosung, the star company behind Korea’s rapid economic growthover the last five decades, is now leaping forward as the top-rank

global company armed with global excellence and value management.

630 23BranchOffices

SalesNetworks

ServiceNetworks

Sales Network

A/S

Overseas Branch

Domestic Plant

Business NetworksMain Office Seoul, Korea

Manufacturing Plant Changwon & Gimhae, Korea

Branch Office (6) Spain·Italy·UAE·USA·India·Iran

Sales Network (30) USA·Netherlands·Spain·Turkey·Israel·United Kingdom·ItalyUAE·Iran·Saudi Arabia·Kuwait·Jordan·Oman·Egypt·Qatar·Bahrain·IraqThailand·Japan·Indonesia·Singapore·Malaysia·Taiwan·Vietnam·India

A/S Network (23) USA·Mexico·Peru·Puerto Rico·Argentina·Russia·Poland·GermanyTurkey·Italy·Azerbaijan·UAE·Iran·Saudi Arabia·Singapore