PNM’s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability (TTC) & Available Transfer Capability (ATC) Prepared By: Transmission/Distribution Planning and Contracts Department March 1, 2017

PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

  • Upload
    hathien

  • View
    220

  • Download
    1

Embed Size (px)

Citation preview

Page 1: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 1

PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)

Determination and Posting Of Total Transfer Capability (TTC) &

Available Transfer Capability (ATC)

Prepared By:

Transmission/Distribution Planning and Contracts Department

March 1, 2017

Page 2: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 2

Table of Contents

1. Basic TTC, ATC, TRM, and CBM Determination Methodology ______________________ 4

1.1 Transmission Path Diagram _____________________________________________________ 5

_________________________________________________________________________________ 5

1.2 Northern New Mexico Total Transfer Capability (TTC) Summary Table __________________ 6

1.3 Southern New Mexico Total Transfer Capability (TTC) Summary Table __________________ 7

2. Northern New Mexico _____________________________________________________ 8

2.1 FOURCORNE/SJ345 - WNM/ABQ/NEA Path ________________________________________ 8

2.2 WNM/ABQ - FOURCORNE/SJ345 Path ____________________________________________ 9

2.3 STORLK115 - NEA/ABQ Path ___________________________________________________ 10

2.4 NEA - SJ345 Path ____________________________________________________________ 11

2.5 SJ345 – FOURCORNE345 Path __________________________________________________ 12

2.6 SJ345 to SHIPROCK345 Path ___________________________________________________ 14

2.7 SHIPROCK345 – FOURCORNE345 Path ___________________________________________ 16

2.8 FOURCORNE230 – GALLEGOS115 Path ___________________________________________ 18

2.9 SJ345 –MCKINLEY345 Path ____________________________________________________ 20

2.10 MCKINLEY345– SPRINGER345 Path ____________________________________________ 22

2.11 SPRINGER345-CORONADO500 Path ___________________________________________ 24

2.12 SJ345 – GREENLEE345 Path __________________________________________________ 26

2.13 PALOVERDE500 - East (WESTWING500, KYRENE500 & JOJOBA500) Path ______________ 28

2.14 WESTWING500 to PALOVERDE500 Direction ____________________________________ 29

2.15 WESTWING500 – WESTWING230 Path _________________________________________ 30

2.16 KYRENE500 – KYRENE230 Path _______________________________________________ 32

2.17 FOURCORN345 - FOURCORN230 Path __________________________________________ 34

2.18 SJ345 to HOGBACK -Path ____________________________________________________ 36

2.19 REEVES - WNM/ABQ Path ___________________________________________________ 38

2.20 DELTA - WNM/ABQ Path ____________________________________________________ 39

2.21 VEF - ABQ Path ____________________________________________________________ 40

2.22 BW345 – BW230 Path ______________________________________________________ 41

2.23 TAIBAN – BW345 Path ______________________________________________________ 43

2.24 TAIBAN – GUADALUPE Path _________________________________________________ 45

2.25 GUADALUPE-ABQ Path _____________________________________________________ 47

2.26 WILLARD115-ABQ Path _____________________________________________________ 49

Page 3: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 3

2.27 RED MESA115- FOURCORNE Path _____________________________________________ 50

2.28 LALUZ-ABQ Path ___________________________________________________________ 50

3. Southern New Mexico ____________________________________________________ 51

3.1 HIDALGO345 – HIDALGO115 Path _______________________________________________ 51

3.2 LORDSBURG115 – HIDALGO115 Path ____________________________________________ 53

3.3 EDDY230 – AMRAD345 Path ___________________________________________________ 55

3.4 AMRAD115 – ALAMOGORDO 115 Path __________________________________________ 57

3.5 GREENLEE345 – HIDALGO345 Path ______________________________________________ 59

3.6 HIDALGO345 – LUNA345 Path __________________________________________________ 61

3.7 LUNA345 – LUNA115 Path _____________________________________________________ 63

3.8 LUNA115 – MIMBRES115 Path _________________________________________________ 65

3.9 MIMBRES115 – LASCRCS115 Path _______________________________________________ 67

Page 4: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 4

1. Basic TTC, ATC, TRM, and CBM Determination Methodology

PNM’s methodology for determining TTC and ATC values is in the Public Service Company of New Mexico Available Transfer Capability Implementation Document (ATCID). This document is posted on the PNM OASIS site. PNM’s methodology for determining TRM values is in the Public Service Company of New Mexico Transmission Reliability Margin Implementation Document (TRMID). This document is posted on the PNM OASIS site. PNM does not maintain CBM.

Page 5: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 5

1.1 Transmission Path Diagram

WESTWING500

CORONAD500

PALOVERDE500

JOJOBA500

SRP

APS

GREENLEE345

SPRINGER345

TEP

HIDALGO115

MD#1

EDDYCOUNTY

345

ALAMOGORDO115

HOLLYWOOD115

EPE

AMRAD345 EPE

SPS

PNM

Southern New Mexico

GALLEGOS11

5

VAL115

NEA

WNM BW230

WAPA

PNM

Northern New

Mexico NNMI

NEA

ABQ POR/POD

BA 115 WM115 WM345

NEA POR/POD

ETA115

NORTON115 OJO345

FOURCORNE POR/POD

FOURCORNE345 FOURCORNE230

EPE POR/POD

115 KV COMMON BUS

PICHACHO/DONA ANA/LAS CRUCES

WESTWING230

KYRENE230

AMRAD115

T

A

I

B

A

N

G

U

A

D

A

L

U

P

E

B

W

3

4

5

WNM POR/POD

AMB230

YAH-TA-HEY115

REEVES115

LORDSBURG115

MCKINLEY345

SJ345

DELTA

FOURCORNE

KYRENE500

TURQUOISE115

MIMBRES115

HIDALGO345 LUNA345

ABQ

LUNA115

SHIPROCK345

LALUZ VEF

REDMESAA115

R

E

D

M

E

S

A

1

1

5

Page 6: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 6

1.2 Northern New Mexico Total Transfer Capability (TTC) Summary Table

Path

Reference Direction

Reverse Direction

MW MW

FOURCORNE/SJ345 – WNM/ABQ/NEA Variable* NA

WNM/ABQ – FOURCORNE/SJ345 Variable* NA

STORLK115 – NEA/ABQ 33 NA

NEA – SJ345 203 NA

SJ345 – FOURCORNE345 229 299

SJ345 – SHIPROCK345 269 269

SHIPROCK345 – FOURCORNE345 300 300

FOURCORNE230 – GALLEGOS115 100 100

SJ345 – MCKINLEY345 200 150

MCKINLEY345 – SPRINGER345 100 100

SPRINGER345 – CORONADO500 100 100

SJ345 – GREENLEE345 50 50

PALOVERDE500 –EAST (WESTWING500, KYRENE500 & JOJOBA500) 669 NA

WESTWING500 – PALOVERDE500 106 NA

WESTWING500 – WESTWING230 182 182

KYRENE500 – KYRENE230 298 298

FOURCORN345 – FOURCORN230 157 157

SJ345 – HOGBACK 200 200

REEVES – WNM/ABQ 157 NA

DELTA – WNM/ABQ 149 NA

VEF – ABQ 158 NA

BW345 – BW230 Variable* Variable*

TAIBAN – BW345 200 372

TAIBAN – GUADALUPE 572 200

GUADALUPE345 – ABQ 662 201

WILLARD115 – ABQ 137 NA

REDMESA115 – FOURCORNE 102 NA

LALUZ–ABQ 42 NA

*Variable refers to the dynamic nature of this path’s TTC due to seasonal or system configuration parameters including flows held by the Arroyo and Gladstone Phase-Shifting Transformers, the Blackwater AC/DC/AC 200 MW converter flow and generation resources.

Page 7: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 7

1.3 Southern New Mexico Total Transfer Capability (TTC) Summary Table

Path

Reference Direction

Reverse Direction

MW MW

HIDALGO345 – HIDALGO115 448 448

LORDSBURG115 – HIDALGO115 80 80

EDDY230 – AMRAD345 67 67

AMRAD115 – ALAMOGORDO115 91 91

GREENLEE345 – HIDALGO345 160 300

HIDALGO345 - LUNA345 214 214

LUNA345 – LUNA115 162 162

LUNA115 – MIMBRES115 200 200

MIMBRES115 – LASCRCS115 133 133

Page 8: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 8

2. Northern New Mexico

2.1 FOURCORNE/SJ345 - WNM/ABQ/NEA Path

Points of Receipt: Four Corners 230 kV Bus

Four Corners 345 kV Bus McKinley 345 kV Bus San Juan 345 kV Bus

Points of Delivery: Ambrosia 230 kV Bus

West Mesa 345 kV Bus Yah-Ta-Hey 115 kV Bus Ojo 345 kV Bus ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus) Jicarilla 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = Variable (1)

Existing Transmission Commitments Native Load Commitment / NLF

Network Customer Commitment to City of Gallup / NITSF

Network Customer Commitment to Kirtland Air Force Base (KAFB ) / NITSF

Network Customer Commitment to Los Alamos County / NITSF

Network Customer Commitment to Tri-State / NITSF

Network Customer Commitment to NTUA / NTISF

Network Customer Commitment to Jicarilla / NTISF

Network Customer Commitment to Kit Carson Electric Cooperative/ NTISF

247 MW Grandfathered Commitment to WAPA / GFF

20 MW Grandfathered Commitment to EPE / GFF

104 MW Point to Point Commitment to EPE / PTPPF

TRM

(1) Variable refers to the dynamic nature of this path’s TTC due to seasonal or system configuration parameters including capacitor, reactors, and generation resources.

Page 9: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 9

2.2 WNM/ABQ - FOURCORNE/SJ345 Path

Points of Receipt: Ambrosia 230 kV Bus West Mesa 345 kV Bus Yah-Ta-Hey 115 kV Bus ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)

Points of Delivery: Four Corners 230 kV Bus Four Corners 345 kV Bus McKinley 345 kV Bus San Juan 345 kV Bus

TTC Determination

The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID).

TTC = Variable (1)

Existing Transmission Commitments

15 MW Point to Point Commitment to Aragonne Wind, LLC /PTPF

25 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF

50 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF

100 MW Point to Point Commitment to High Lonesome Mesa, LLC/ PTPF

75 MW Point to Point Commitment to Grady Wind Energy Center, LLC (2)/ PTPF

130 MW Point to Point Commitment to Broadview Energy KW, LLC (3)/PTPF

42 MW Point to Point Commitment to Broadview Energy JN, LLC (4)/PTPF

125 MW Point to Point Commitment to Broadview Energy JN, LLC (5)/PTPF

(2) The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to January 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC. (3)This commitment becomes effective on May 1, 2017. (4) This commitment becomes effective on May 1, 2017. (5) The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to May 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC.

Page 10: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 10

2.3 STORLK115 - NEA/ABQ Path

STORLK115 to NEA/ABQ Direction Points of Receipt: Storrie Lake 115 kV Bus Points of Delivery: Ojo 345 kV Bus Norton 115 kV Bus

West Mesa 345 kV Bus ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 33 MW

Existing Transmission Commitments None

NEA/ABQ to STORLK115 Direction The path is not rated in this direction.

Page 11: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 11

2.4 NEA - SJ345 Path

NEA - SJ345 Direction Points of Receipt: Ojo 345 kV Bus Norton 115 kV Bus Points of Delivery: San Juan 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 203 MW

Existing Transmission Commitments None

Page 12: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 12

2.5 SJ345 – FOURCORNE345 Path

SJ345 to FOURCORNE345 Direction Points of Receipt: San Juan 345 kV Bus Points of Delivery: Four Corners 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 299 MW

Existing Transmission Commitments

50 MW Grandfathered Commitment to Anaheim / GFF

36 MW Grandfathered Commitment to UAMPS / GFF

Page 13: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 13

FOURCORNE345 to SJ345 Direction Points of Receipt: Four Corners 345 kV Bus Points of Delivery: San Juan 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 299 MW

Existing Transmission Commitments None

Page 14: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 14

2.6 SJ345 to SHIPROCK345 Path

SJ345 to SHIPROCK345 Direction Point of Receipt: San Juan 345 kV Bus Point of Delivery: Shiprock 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 269 MW

Existing Transmission Commitments

43 MW Grandfathered Commitment to City of Farmington / GFF

Page 15: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 15

SHIPROCK345 TO SJ345 Direction Point of Receipt: Shiprock 345 kV Bus Point of Delivery: San Juan 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 269 MW

Existing Transmission Commitments

68 MW Network Customer Commitment to NUA for New Mexico Load / NITSF

Page 16: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 16

2.7 SHIPROCK345 – FOURCORNE345 Path

SHIPROCK345 to FOURCORNE345 Direction Points of Receipt: Shiprock 345 kV Bus Points of Delivery: Four Corners 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 300 MW

Existing Transmission Commitments None

Page 17: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 17

FOURCORNE345 to SHIPROCK345 Direction Points of Receipt: Four Corners 345 kV Bus Points of Delivery: Shiprock 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 300 MW

Existing Transmission Commitments None

Page 18: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 18

2.8 FOURCORNE230 – GALLEGOS115 Path

FOUCORNE230 to GALLEGOS115 Direction Points of Receipt: Four Corners 230 kV Bus Points of Delivery: Gallegos 115 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 100 MW

Existing Transmission Commitments

75 MW Grandfathered Commitment to NAPI / GFF

Page 19: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 19

GALLEGOS115 to FOURCORNE230 Direction Points of Receipt: Gallegos 115 kV Bus Points of Delivery: Four Corners 230 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 100 MW

Existing Transmission Commitments

75 MW Grandfathered Commitment to NAPI / GFF

Page 20: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 20

2.9 SJ345 –MCKINLEY345 Path

SJ345 to MCKINLEY345 Direction Points of Receipt: San Juan 345 kV Bus Points of Delivery: McKinley 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW

Existing Transmission Commitments

162 MW Native Load Commitment at McKinley / NLF

38 MW Network Customer Commitment / NITSF

Page 21: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 21

MCKINLEY345 to SJ345 Direction Points of Receipt: McKinley 345 kV Bus Points of Delivery: San Juan 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 150 MW

Existing Transmission Commitments

94 MW Native Load Commitment for southern New Mexico generation / NLF

Page 22: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 22

2.10 MCKINLEY345– SPRINGER345 Path

MCKINLEY345 to SPRINGER 345 Direction Points of Receipt: McKinley 345 kV Bus Points of Delivery: Springerville 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 100 MW

Existing Transmission Commitments

38 MW Network Customer Commitment / NITSF

Page 23: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 23

SPRINGER345 to MCKINLEY345 Direction Points of Receipt: Springerville 345 kV Bus Points of Delivery: San Juan 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 100 MW

Existing Transmission Commitments

94 MW Native Load Commitment for southern New Mexico generation / NLF

Page 24: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 24

2.11 SPRINGER345-CORONADO500 Path

SPRINGER345-CORONADO500 Direction Points of Receipt: Springerville 345 kV Bus Points of Delivery: Coronado 500 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 100 MW

Existing Transmission Commitments None

Page 25: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 25

CORONADO500- SPRINGER345 Direction Points of Receipt: Coronado 500 kV Bus Points of Delivery: Springerville 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 100 MW

Existing Transmission Commitments None

Page 26: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 26

2.12 SJ345 – GREENLEE345 Path

SJ345 to GREENLEE345 Direction Points of Receipt: San Juan 345 kV Bus Points of Delivery: Greenlee 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 50 MW

Existing Transmission Commitments

50 MW Native Load Commitment / NLF

Page 27: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 27

GREENLEE345 to SJ345 Direction Points of Receipt: Greenlee 345 kV Bus Points of Delivery: San Juan 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 50 MW

Existing Transmission Commitments

50 MW Native Load Commitment for southern New Mexico generation resources / NLF

Page 28: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 28

2.13 PALOVERDE500 - East (WESTWING500, KYRENE500 & JOJOBA500) Path

PALOVERDE500 to WESTWING500, KYRENE500 & JOJOBA500 Direction Points of Receipt: Palo Verde 500 kV Bus Points of Delivery: Westwing 500 kV Bus

Kyrene 500 kV Bus Jojoba 500 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 669 MW

Existing Transmission Commitments

274 MW Native Load Commitment for Palo Verde Generation / NLF 48 MW Native Load Commitment for Palo Verde Generation (6) / NLF

87 MW Native Load Commitment for Palo Verde Generation (7) / NLF

(6) Start date January 1, 2018 (7) Start date January 1, 2018

Page 29: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 29

2.14 WESTWING500 to PALOVERDE500 Direction

WESTWING500 to PALOVERDE500 Direction Points of Receipt: West Wing 500 kV Bus Points of Delivery: Palo Verde 500 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 106 MW

Existing Transmission Commitments None

Page 30: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 30

2.15 WESTWING500 – WESTWING230 Path

WESTWING500 to WESTWING230 Direction Points of Receipt: West Wing 500 kV Bus Points of Delivery: West Wing 230 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 182 MW

Existing Transmission Commitments

134 MW Native Load Commitment for WAPA Deliveries of Palo Verde Generation / NLF 48 MW Native Load Commitment for Palo Verde Generation (8) / NLF

(8 ) Starting 01/01/2016

Page 31: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 31

WESTWING 230 to WESTWING 500 Direction Points of Receipt: West Wing 230 kV Bus Points of Delivery: West Wing 500 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 182 MW

Existing Transmission Commitments None

Page 32: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 32

2.16 KYRENE500 – KYRENE230 Path

KYRENE 500 to KYRENE230 Direction Points of Receipt: Kyrene 500 kV Bus Points of Delivery: Kyrene 230 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 298 MW

Existing Transmission Commitments None

Page 33: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 33

KYRENE230 to KYRENE500 Direction Points of Receipt: Kyrene 230 kV Bus Points of Delivery: Kyrene 500 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 215 MW

Existing Transmission Commitments None

Page 34: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 34

2.17 FOURCORN345 - FOURCORN230 Path

FOURCORN345 to FOURCORN230 Direction Points of Receipt: Four Corners 345 kV Bus Points of Delivery: Four Corners 230 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 157 MW

Existing Transmission Commitments

157 MW Native Load Commitment / NLF

Page 35: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 35

FOURCORN230 to FOURCORN345 Direction Points of Receipt: Four Corners 230 kV Bus Points of Delivery: Four Corners 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 157 MW

Existing Transmission Commitments None

Page 36: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 36

2.18 SJ345 to HOGBACK -Path

SJ345 to HOGBACK Direction Point of Receipt: San Juan 345 kV Bus Point of Delivery: Hogback 230 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW

Existing Transmission Commitments

43 MW Grandfathered Commitment to City of Farmington / GFF

157 MW Point to Point Commitment to the City of Farmington / PTPF

Page 37: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 37

HOGBACK to SJ345 Direction Point of Receipt: Hogback 230 kV Bus Point of Delivery: San Juan 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW

Existing Transmission Commitments

200 MW Point to Point Commitment to the City of Farmington / PTPF

Page 38: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 38

2.19 REEVES - WNM/ABQ Path

REEVES to WNM/ABQ Direction Points of Receipt: Reeves 115 kV Bus Points of Delivery: West Mesa 345 kV Bus ABQ (Albuquerque Area: BA 345 kV, BA 115 kV, West Mesa 115 kV)

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 157 MW

Existing Transmission Commitments

157 Native Load Commitment for Reeves Generation / NLF

WNM/ABQ to REEVES Direction The path is not rated in this direction.

Page 39: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 39

2.20 DELTA - WNM/ABQ Path

DELTA to WNM/ABQ Direction Points of Receipt: Person 115 kV Bus Points of Delivery: West Mesa 345 kV Bus

ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 149 MW

Existing Transmission Commitments

149 MW Native Load Commitment for Delta Generation / NLF

WNM/ABQ to DELTA Direction The path is not rated in this direction.

Page 40: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 40

2.21 VEF - ABQ Path

VEF to ABQ Direction Points of Receipt: VEF (Tome 115 kV Bus) Points of Delivery: ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 158 MW

Existing Transmission Commitments

158 MW Native Load Commitment for VEF Generation / NLF

ABQ-VEF Direction The path is not rated in this direction.

Page 41: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 41

2.22 BW345 – BW230 Path

TAIBAN to BW230 Direction Points of Receipt: Blackwater 345 kV Bus Points of Delivery: Blackwater 230 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = Variable(9): Minimum of 15 MW, Maximum of 200 MW

Existing Transmission Commitments

11 MW Grandfathered Commitment to Eastern Coop projected load / GFF

9 The Blackwater converter capacity on this path is determined by available short circuit capacity at the Blackwater 345 kV bus. Starting May 1, 2017, this short circuit capacity is shared with the Broadview wind farm and available short circuit capacity is dependent on the Broadview wind generation level.

Page 42: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 42

BW230 to BW345 Direction Points of Receipt: Blackwater 230 kV Bus Points of Delivery: Blackwater 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = Variable(10): Minimum of 15 MW, Maximum of 200 MW

Existing Transmission Commitments - 125 MW Point to Point Commitment to Broadview Energy JN, LLC (11) / PTPF

- 25 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF

- 50 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF

10 The Blackwater converter capacity on this path is determined by available short circuit capacity at the Blackwater 345 kV bus. Starting May 1, 2017, this short circuit capacity is shared with the Broadview wind farm and available short circuit capacity is dependent on the Broadview wind generation level. (11)The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to May 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC.

Page 43: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 43

2.23 TAIBAN – BW345 Path

TAIBAN to BW345 Direction Points of Receipt: Taiban Mesa 345 kV Bus Points of Delivery: Blackwater 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW

Existing Transmission Commitments

11 MW Grandfathered Commitment to Eastern Coop projected load / GFF

Page 44: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 44

BW345 to TAIBAN Direction Points of Receipt: Blackwater 345 kV Bus Points of Delivery: Taiban Mesa 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 372 MW

Existing Transmission Commitments - 125 MW Point to Point Commitment to Broadview Energy JN, LLC (12) / PTPF

- 130 MW Point to Point Commitment to Broadview Energy KW, LLC (13) / PTPF

- 42 MW Point to Point Commitment to Broadview Energy JN, LLC (14)/ PTPF

- 25 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF

- 50 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF

(12) The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to May 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC. (13) This commitment becomes effective on May 1, 2017. (14) This commitment becomes effective on May 1, 2017.

Page 45: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 45

2.24 TAIBAN – GUADALUPE Path

TAIBAN to GUADALUPE Direction Points of Receipt: Taiban Mesa 345 kV Bus Points of Delivery: Guadalupe 345 kV

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 572 MW

Existing Transmission Commitments

- 200 MW Native Load Commitment for Contracted Purchase from FPLE (Taiban Mesa) / NLF - 125 MW Point to Point Commitment to Broadview Energy JN, LLC (15) / PTPF - 42 MW Point to Point Commitment to Broadview Energy JN, LLC (16)/ PTPF - 130 MW Point to Point Commitment to Broadview Energy KW, LLC (17) / PTPF - 25 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF - 50 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF

(15) The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to May 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC. (16) This commitment becomes effective on May 1, 2017. (17) This commitment becomes effective on May 1, 2017.

Page 46: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 46

GUADALUPE to TAIBAN Direction Points of Receipt: Guadalupe 345 kV Bus Points of Delivery: Taiban 345 kV

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW

Existing Transmission Commitments

11 MW Grandfathered Commitment to Eastern Coop projected load / GFF

Page 47: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 47

2.25 GUADALUPE-ABQ Path

GUADALUPE to ABQ Direction Points of Receipt: Guadalupe 345 kV Bus Points of Delivery: West Mesa 345 kV Bus

ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 662 MW

Existing Transmission Commitments

200 MW Native Load Commitment for Contracted Purchase from FPLE (Taiban Mesa) / NLF

75 MW Point to Point Commitment to Grady Wind Energy Center, LLC(18)/PTPF

15 MW Point to Point Commitment to Aragonne Wind, LLC /PTPF

25 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF

50 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF

130 MW Point to Point commitment to Broadview Energy KW, LLC (19) / PTPF

42 MW Point to Point Commitment to Broadview Energy JN, LLC (20)/ PTPF

125 MW Point to Point Commitment to Broadview Energy JN, LLC (21) / PTPF

(18) The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to January 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC. (19) This commitment becomes effective on May 1, 2017. (20) This commitment becomes effective on May 1, 2017. (21) The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to May 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC.

Page 48: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 48

ABQ to GUADALUPE Direction Points of Receipt: West Mesa 345 kV Bus

ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)

Points of Delivery: Guadalupe 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 212 MW

Existing Transmission Commitments

11 MW Commitment to Eastern Coop projected load / GFF

Page 49: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 49

2.26 WILLARD115-ABQ Path

WILLARD115- ABQ Direction Points of Receipt: Willard 115 kV Bus Points of Delivery: West Mesa 345 kV Bus

ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 137 MW

Existing Transmission Commitments

90 MW Point to Point Commitment to High Lonesome Mesa, LLC/ PTPF

10 MW Point to Point Commitment to High Lonesome Mesa, LLC/ PTPF

ABQ-WILLARD115 Direction The path is not rated in this direction.

Page 50: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 50

2.27 RED MESA115- FOURCORNE Path

REDMESA to FOURCORNE Direction Points of Receipt: Red Mesa 115 kV Bus Points of Delivery: Four Corners 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 102 MW

Existing Transmission Commitments None

FOURCORNE to REDMESA Direction The path is not rated in this direction.

2.28 LALUZ-ABQ Path

LALUZ to ABQ Direction Points of Receipt: La Luz 115 kV Bus Points of Delivery: West Mesa 345 kV Bus ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 42 MW

Existing Transmission Commitments None

ABQ to LALUZ Direction The path is not rated in this direction.

Page 51: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 51

3. Southern New Mexico

3.1 HIDALGO345 – HIDALGO115 Path

HIDALGO 345 to HIDALGO 115 Direction Points of Receipt: Hidalgo 345 kV Bus Points of Delivery: Hidalgo 115 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 448 MW

Existing Transmission Commitments

34 MW Native Load Commitment / NLF

96 MW Existing Commitment for Freeport McMoRanLoad / NLF

Page 52: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 52

HIDALGO115 to HIDALGO345 Direction Points of Receipt: Hidalgo 115 kV Bus Points of Delivery: Hidalgo 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 448 MW

Existing Transmission Commitments

50 MW Native Load Commitment for Supplying Native Load From Southern New Mexico Generation Resources / NLF

54 MW Network Customer Commitment to Tri-State for Pyramid Generation / NITSF

60 MW Point to Point Commitment to Tri-State for Pyramid Generation / PTPF

Page 53: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 53

3.2 LORDSBURG115 – HIDALGO115 Path

LORDSBURG115 to HIDALGO115 Direction Points of Receipt: Lordsburg 115 kV Bus Points of Delivery: Hidalgo 115 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 80 MW

Existing Transmission Commitments

80 MW Native Load Commitment/ NLF

Page 54: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 54

HIDALGO115 to LORDSBURG115 Direction Points of Receipt: Hidalgo 115 kV Bus Points of Delivery: Lordsburg 115 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 80 MW

Existing Transmission Commitments

11 MW Native Load Commitment / NLF

Page 55: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 55

3.3 EDDY230 – AMRAD345 Path

EDDY230 to AMRAD345 Direction Points of Receipt: Eddy County 230 kV Bus Points of Delivery: Amrad 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 67 MW

Existing Transmission Commitments None A technical investigation assessment was completed in 2006 on the Eddy County HVDC converter station to identify all components that could impact the reliability of the converter station due to age, condition, availability of spare parts, cost, or obsolesce. Based on this assessment major equipment components have reached the end of their respective useful life. In addition, more recently the converter station has not had a high availability track record which has raised concerns about the ongoing reliability of the station. Based on these facts, PNM will only be posting non-firm transmission service for this path.

Page 56: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 56

AMRAD345 to EDDY230 Direction Points of Receipt: Amrad 345 kV Bus Points of Delivery: Eddy County 230 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 67 MW

Existing Transmission Commitments None A technical investigation assessment was completed in 2006 on the Eddy County HVDC converter station to identify all components that could impact the reliability of the converter station due to age, condition, availability of spare parts, cost, or obsolesce. Based on this assessment major equipment components have reached the end of their respective useful life. In addition, more recently the converter station has not had a high availability track record which has raised concerns about the ongoing reliability of the station. Based on these facts, PNM will only be posting non-firm transmission service for this path.

Page 57: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 57

3.4 AMRAD115 – ALAMOGORDO 115 Path

AMRAD115 to ALAMOGORDO115 Direction Points of Receipt: Amrad 115 kV Points of Delivery: Alamogordo 115 kV

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 91 MW

Existing Transmission Commitments

91 MW Projected Native Load / NLF

Page 58: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 58

ALAMOGORDO115 to AMRAD115 Direction Points of Receipt: Alamogordo 115 kV Points of Delivery: Amrad 115 kV

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 91 MW

Existing Transmission Commitments None

Page 59: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 59

3.5 GREENLEE345 – HIDALGO345 Path

GREENLEE345 to HIDALGO345 Direction Points of Receipt: Greenlee 345 kV Bus Points of Delivery: Hidalgo 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 160 MW

Existing Transmission Commitments

64 MW Native Load Commitment / NLF

96 MW Existing Commitment for Freeport McMoRan Load / NLF

Page 60: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 60

HIDALGO345 to GREENLEE345 Direction Points of Receipt: Hidalgo 345 kV Bus Points of Delivery: Greenlee 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 300 MW

Existing Transmission Commitments

50 MW PNM’s resource commitments supplying native load from southern New Mexico generation resources / NLF

60 MW Point to Point Commitment to Tri-State for Pyramid Generation / PTPF

Page 61: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 61

3.6 HIDALGO345 – LUNA345 Path

HIDALGO345 to LUNA345 Direction Points of Receipt: Hidalgo 345 kV Bus Points of Delivery: Luna 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 214 MW

Existing Transmission Commitments

50 MW Native Load Commitment / NLF

54 MW Network Customer Commitment to Tri-State for Pyramid Generation / NITSF

Page 62: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 62

LUNA345 to HIDALGO345 Direction Points of Receipt: Luna 345 kV Bus Points of Delivery: Hidalgo 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 214 MW

Existing Transmission Commitments

20 MW Native Load Commitment / NLF

Page 63: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 63

3.7 LUNA345 – LUNA115 Path

LUNA345 to LUNA115 Direction Points of Receipt: Luna 345 kV Bus Points of Delivery: Luna 115 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 162 MW

Existing Transmission Commitments

54 MW Network Customer Commitment to Tri-State for Pyramid Generation / NTISF

108 MW Native Load Commitment / NLF

Page 64: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 64

LUNA115 to LUNA345 Direction Points of Receipt: Luna 115 kV Bus Points of Delivery: Luna 345 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 162 MW

Existing Transmission Commitments None

Page 65: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 65

3.8 LUNA115 – MIMBRES115 Path

LUNA115 to MIMBRES115 Direction Points of Receipt: Luna 115 kV Bus Points of Delivery: Mimbres 115 kV Bus Picacho 115 kV Bus Airport 115 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW

Existing Transmission Commitments

70 MW Native Load Commitment / NLF

54 MW Network Customer Commitment to Tri-State for Pyramid Generation / NITSF

Page 66: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 66

MIMBRES115 to LUNA115 Direction Points of Receipt: Mimbres 115 kV Bus Picacho 115 kV Bus Airport 115 kV Bus Points of Delivery: Luna 115 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW

Existing Transmission Commitments None

Page 67: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 67

3.9 MIMBRES115 – LASCRCS115 Path

MIMBRES115 to LASCRUCS115 Direction Points of Receipt: Mimbres 115 kV Bus Points of Delivery: Las Cruces 115 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 133 MW

Existing Transmission Commitments

43 MW Native Load Commitment / NLF

16 MW Network Customer Commitment to Tri-State for Pyramid Generation / NITSF

Page 68: PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)€™s TTC/ATC Determination Document 1 PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transfer Capability

PNM’s TTC/ATC Determination Document 68

LASCRCS115 to MIMBRES115 Direction Points of Receipt: Las Cruces 115 kV Bus Points of Delivery: Mimbres 115 kV Bus

TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 133 MW

Existing Transmission Commitments None